Engineering quantity calculation method, device and electronic equipment

Through the combination and multi-level processing of prefabricated building units, the problem of low engineering quantity calculation efficiency in the existing technology is solved, and efficient and accurate engineering quantity calculation is achieved, which is suitable for international projects of prefabricated buildings.

CN113886924BActive Publication Date: 2024-11-26GLODON CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202111175601.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-10-09
Publication Date
2024-11-26
Estimated Expiration
2041-10-09

AI Technical Summary

Technical Problem

The existing engineering quantity calculation methods are inefficient and difficult to meet the business needs of prefabricated buildings. Especially when dealing with multiple identical building units, it requires repeated calculations, resulting in reduced efficiency.

Method used

By obtaining the prefabricated units and engineering quantity calculation rules of the BIM model, combining the units, determining the prefabricated building model, and calculating the engineering quantity based on the rules, using multi-level combination and standard layer models to improve computing efficiency and accuracy.

Benefits of technology

It improves the efficiency and accuracy of project quantity calculation, reduces repeated calculations for the same unit, supports various engineering quantity calculation services for prefabricated construction international projects, and enhances the convenience of model construction and engineering quantity management.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113886924B_ABST
    Figure CN113886924B_ABST
Patent Text Reader

Abstract

The present invention relates to the field of engineering cost technology, and specifically to a method, device and electronic device for calculating engineering quantity. The method comprises obtaining prefabricated units of a BIM model and engineering quantity calculation rules; combining the prefabricated units to determine a prefabricated building model; and determining the engineering quantity of the prefabricated building model based on the engineering quantity calculation rules. The prefabricated building model is determined by combining the prefabricated units, and then the engineering quantity is calculated. Since the prefabricated units can be repeatedly combined and utilized, the same unit in the prefabricated building model only needs to be constructed once, and the same unit only needs to be calculated once when calculating the engineering quantity, which improves the efficiency of the engineering quantity calculation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of engineering cost, and in particular to an engineering quantity calculation method, device and electronic equipment. Background Art

[0002] With the continuous development of the construction industry, a kind of environmentally friendly, standardized and efficient construction form, prefabricated buildings, has emerged. Prefabricated buildings have little impact on the environment, whether prefabricated in the early stage or assembled on site, and can be reused, so they are more environmentally friendly than traditional construction forms. However, the current method of calculating the amount of engineering has not improved accordingly, making it difficult to meet the business needs of the prefabricated building budget.

[0003] At present, the solution provided by the budgeting market for the prefabricated building system is mainly to establish an accurate prefabricated building BIM model based on precise drawings, and to split the building units based on the prefabricated building model, such as splitting into rooms, walls, doors and windows, etc. Then, the prefabricated engineering quantity and non-prefabricated engineering quantity are calculated based on the split units. However, in this calculation method, if there are multiple identical rooms in the prefabricated building BIM model, they need to be split separately and then the engineering quantity is calculated. This process will lead to low efficiency in engineering quantity calculation. Summary of the invention

[0004] In view of this, an embodiment of the present invention provides a method, device and electronic device for calculating engineering quantities to solve the problem of low efficiency in engineering quantity calculation.

[0005] According to a first aspect, an embodiment of the present invention provides a method for calculating engineering quantities, including:

[0006] Obtain the prefabricated units and quantity calculation rules of the BIM model;

[0007] Combining the prefabricated units to determine a prefabricated building model;

[0008] Based on the engineering quantity calculation rule, the engineering quantity of the prefabricated building model is determined.

[0009] The method for calculating the engineering quantity provided in the embodiment of the present invention determines the prefabricated building model by combining prefabricated units, and then calculates the engineering quantity. Since the prefabricated units can be repeatedly combined and utilized, the same units in the prefabricated building model only need to be constructed once, and the same units only need to be calculated once during the engineering quantity calculation, thereby improving the efficiency of the engineering quantity calculation.

[0010] In combination with the first aspect, in a first implementation of the first aspect, combining the prefabricated units to determine the prefabricated building model includes:

[0011] Acquire assembly information, and combine the assembled units based on the assembly information to determine a model unit;

[0012] The prefabricated building model is determined based on the combination of the model units.

[0013] The engineering quantity calculation method provided in the embodiment of the present invention combines prefabricated units based on assembly information, which can improve the accuracy of the model units obtained after the combination, and then obtain the prefabricated building model by combining the model units, thereby ensuring the reliability of the obtained prefabricated building model.

[0014] In combination with the first implementation manner of the first aspect, in the second implementation manner of the first aspect, the assembly information includes hierarchical structure information, the prefabricated unit includes a plurality of prefabricated component units, the model unit includes a first hierarchical unit, a second hierarchical unit, and a third hierarchical unit, and the prefabricated units are combined based on the assembly information to determine the model unit, including:

[0015] Based on the combination of the first prefabricated component units, the first hierarchical unit is obtained;

[0016] Based on the combination of the first hierarchical unit and the second prefabricated component unit, the second hierarchical unit is obtained;

[0017] Based on the combination of the first hierarchical unit, the second hierarchical unit and the third prefabricated component unit, the third hierarchical unit is obtained.

[0018] The engineering quantity calculation method provided in the embodiment of the present invention can fully support various engineering quantity calculation businesses of international prefabricated building projects by combining prefabricated units in a multi-level manner, thereby providing convenience for model construction and engineering quantity management.

[0019] In combination with the first implementation manner of the first aspect, in a third implementation manner of the first aspect, determining the prefabricated building model based on the combination of the model units includes:

[0020] Based on the combination of the model units, a standard layer model is formed;

[0021] The prefabricated building model is determined based on the standard floor model.

[0022] The method for calculating the engineering quantity provided by the embodiment of the present invention utilizes the standard layer model to construct the prefabricated building model, thereby improving the construction efficiency of the prefabricated building model.

[0023] In combination with the first aspect, in a fourth implementation of the first aspect, determining the engineering quantity of the prefabricated building model based on the engineering quantity calculation rule includes:

[0024] Obtaining the category of the engineering quantity to be calculated, where the engineering quantity category includes civil engineering or decoration;

[0025] Based on the engineering quantity calculation rule, determining a target engineering quantity calculation rule corresponding to the engineering quantity category;

[0026] Based on the target engineering quantity calculation rule, the engineering quantity corresponding to the engineering quantity category in the prefabricated building model is determined.

[0027] The method for calculating the engineering quantity provided in the embodiment of the present invention pre-sets calculation methods for multiple engineering quantity categories in the engineering quantity calculation rules, including civil engineering and decoration. Therefore, the method also provides calculation of the engineering quantity of the decoration part, thereby improving the integrity of the engineering quantity calculation of the prefabricated building model.

[0028] In combination with the fourth implementation of the first aspect, in the fifth implementation of the first aspect, the prefabricated building model includes a plurality of hierarchical structures, and determining the engineering quantity of the prefabricated building model based on the engineering quantity calculation rule further includes:

[0029] Counting the number of each hierarchical structure in the prefabricated building model;

[0030] Based on the engineering quantity calculation rule, the engineering quantity corresponding to each of the hierarchical structures is determined.

[0031] The method for calculating the engineering quantity provided by the embodiment of the present invention performs statistical calculations on the engineering quantity according to different levels, thereby realizing refined management of the engineering quantity.

[0032] In combination with the first aspect, in a sixth implementation of the first aspect, the obtaining of the assembled unit of the BIM model includes:

[0033] Acquire an initial prefabricated unit, where the initial prefabricated unit is obtained by importing a model unit or identifying a model drawing;

[0034] Adjustments to the initial prefabricated unit are obtained to determine the prefabricated unit.

[0035] The method for calculating the engineering quantity provided in the embodiment of the present invention can ensure the accuracy of the obtained prefabricated units by adjusting the initial prefabricated units on the one hand, and can reduce the accuracy requirements for the initial prefabricated units on the other hand.

[0036] In combination with the first aspect, in a seventh implementation of the first aspect, obtaining a construction quantity calculation rule includes:

[0037] Obtain calculation rule library;

[0038] Based on the region corresponding to the prefabricated building model, determining a corresponding calculation rule in the calculation rule library;

[0039] The adjustment to the calculation rule is obtained to determine the engineering quantity calculation rule.

[0040] The engineering quantity calculation method provided in the embodiment of the present invention integrates the calculation rules of multiple countries and regions in the calculation rule library, and can provide calculation rules of corresponding regions for prefabricated building models, thereby ensuring the reliability of the calculation results, and also providing adjustments to the calculation rules so that the calculation results can be customized.

[0041] According to the second aspect, an embodiment of the present invention further provides an engineering quantity calculation device, comprising:

[0042] An acquisition module is used to obtain the assembly units and engineering quantity calculation rules of the BIM model;

[0043] A combination module, used to combine the prefabricated units to determine a prefabricated building model;

[0044] The engineering quantity calculation module is used to determine the engineering quantity of the prefabricated building model based on the engineering quantity calculation rule.

[0045] The engineering quantity calculation device provided in the embodiment of the present invention determines the prefabricated building model by combining prefabricated units, and then calculates the engineering quantity. Since the prefabricated units can be repeatedly combined and utilized, the same units in the prefabricated building model only need to be constructed once, and the same units only need to be calculated once during the engineering quantity calculation, thereby improving the efficiency of the engineering quantity calculation.

[0046] According to the third aspect, an embodiment of the present invention provides an electronic device, comprising: a memory and a processor, the memory and the processor being communicatively connected to each other, the memory storing computer instructions, and the processor executing the engineering quantity calculation method described in the first aspect or any one of the embodiments of the first aspect by executing the computer instructions.

[0047] According to the fourth aspect, an embodiment of the present invention provides a computer-readable storage medium, wherein the computer-readable storage medium stores computer instructions, and the computer instructions are used to enable the computer to execute the engineering quantity calculation method described in the first aspect or any one of the embodiments of the first aspect. BRIEF DESCRIPTION OF THE DRAWINGS

[0048] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0049] Figure 1 is a flow chart of a method for calculating engineering quantities according to an embodiment of the present invention;

[0050] Figure 2 is a flow chart of a method for calculating engineering quantities according to an embodiment of the present invention;

[0051] Figure 3 is a flow chart of a method for calculating engineering quantities according to an embodiment of the present invention;

[0052] Figure 4 is a structural block diagram of an engineering quantity calculation device according to an embodiment of the present invention;

[0053] Figure 5 It is a schematic diagram of the hardware structure of an electronic device provided by an embodiment of the present invention. DETAILED DESCRIPTION

[0054] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present invention.

[0055] The method for calculating the engineering quantity provided in the embodiment of the present invention calculates the engineering quantity of the prefabricated building model by using the corresponding calculation rules in the quantity calculation software. Among them, the category of the engineering quantity to be calculated can be set according to actual needs, and can include the engineering quantity of civil engineering, decoration or prefabricated components, etc. In the quantity calculation software, it is first necessary to determine the corresponding prefabricated building model, and then calculate the engineering quantity based on the prefabricated building model. For the prefabricated building model, in the embodiment of the present invention, the prefabricated unit is first constructed, and then the prefabricated building model is determined by the combination of the prefabricated units. For example, a building is composed of 4 groups of blocks, each of which has 3 red small blocks. In the embodiment of the present invention, the prefabricated unit, i.e., 3 red small blocks, is directly established first, and then the building model is built by this prefabricated unit. Due to the reuse of the prefabricated unit, when calculating the engineering quantity of the prefabricated building model, only one calculation is required for the same part, and then the corresponding engineering quantity can be determined by combining the number of the same parts, thereby improving the efficiency of the engineering quantity calculation.

[0056] According to an embodiment of the present invention, an embodiment of a method for calculating engineering quantities is provided. It should be noted that the steps shown in the flowchart of the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and although a logical order is shown in the flowchart, in some cases, the steps shown or described can be executed in an order different from that shown here.

[0057] In this embodiment, a method for calculating engineering quantities is provided, which can be used for electronic devices such as computers, mobile phones, tablet computers, etc. Figure 1 is a flow chart of a method for calculating engineering quantities according to an embodiment of the present invention. Figure 1 As shown, the process includes the following steps:

[0058] S11, obtaining the prefabricated units and engineering quantity calculation rules of the BIM model.

[0059] The prefabricated unit of the BIM model can be obtained by importing a pre-established model into an electronic device. For example, if a prefabricated unit model is constructed in the modeling software, the prefabricated unit model can be imported into the quantity calculation software running on the electronic device, and the corresponding conversion can be performed to obtain the prefabricated unit; it can also be constructed by importing PDF drawings or DWG drawings and identifying the boundaries of the PDF drawings to construct the prefabricated unit model; it can also be constructed in the quantity calculation software. Furthermore, after importing the model or drawing, if the automatically generated prefabricated unit model does not meet the calculation conditions of the quantity calculation software, an interactive interface can be provided so that the user can manually adjust it to finally determine the prefabricated unit.

[0060] The assembled units may be prefabricated components, such as doors, windows, walls, etc., or non-prefabricated components, such as concrete components connecting doors and windows, etc. The components may be configured according to actual needs, and are not limited here.

[0061] The quantity calculation rules are built into the quantity calculation software. The quantity calculation software has a built-in quantity calculation rule library, which contains quantity calculation rules for multiple countries and regions. When performing quantity calculation, you can configure it as needed. The quantity calculation rules described here refer to the prefabricated building model to be calculated.

[0062] S12, combining the prefabricated units to determine the prefabricated building model.

[0063] After the electronic device obtains the prefabricated units, it combines them according to the requirements. For example, room A requires a combination of prefabricated units 1-3, room B requires a combination of prefabricated units 2-4, and room C requires a combination of prefabricated units 4-7, then the corresponding prefabricated units are used to combine to form the corresponding rooms.

[0064] Furthermore, after the rooms are combined, the floors are obtained by combining the rooms with the prefabricated units, and the prefabricated building model is obtained by combining the prefabricated units, the rooms, and the floors. Therefore, the prefabricated building model is obtained based on the combination of the prefabricated units.

[0065] This step will be described in detail below.

[0066] S13, determining the engineering quantity of the prefabricated building model based on the engineering quantity calculation rules.

[0067] Due to the processing of S12, in the process of forming the prefabricated building model, the number of each model unit involved in the prefabricated building model and the type of each model unit have been determined. Among them, the type of model unit can be a component, a room, a floor, etc. The type of model unit can be divided according to actual needs. For example, it can be divided by floor, or by room, or by level, etc.

[0068] The electronic device can calculate the engineering quantity of a single model unit using the corresponding engineering quantity calculation rules, and then combine the number of corresponding model units to finally determine the corresponding engineering quantity. In the process of engineering quantity calculation, not only the civil engineering quantity can be calculated, but also the decoration engineering quantity, prefabricated component engineering quantity and non-prefabricated component engineering quantity, etc. can be calculated. The specific settings can be made according to actual needs.

[0069] This step will be described in detail below.

[0070] The method for calculating the engineering quantity provided in this embodiment determines the prefabricated building model by combining prefabricated units, and then calculates the engineering quantity. Since the prefabricated units can be repeatedly combined and utilized, the same units in the prefabricated building model only need to be constructed once, and the same units only need to be calculated once during the engineering quantity calculation, thereby improving the efficiency of the engineering quantity calculation.

[0071] In this embodiment, a method for calculating engineering quantities is provided, which can be used for electronic devices such as computers, mobile phones, tablet computers, etc. Figure 2 is a flow chart of a method for calculating engineering quantities according to an embodiment of the present invention. Figure 2 As shown, the process includes the following steps:

[0072] S21, obtaining the prefabricated units and engineering quantity calculation rules of the BIM model.

[0073] In this embodiment, the electronic device can obtain the prefabricated units of the BIM model in a variety of ways. Specifically, different methods can be adopted according to the specific circumstances of the corresponding construction project, or a combination of multiple methods can be used to construct it. For example, for the quantity calculation work, the upstream construction practitioners can provide prefabricated and assembled building projects with BIM models that meet the engineering quantity calculation standards, and can directly import the prefabricated units constructed by other building platforms (for example, RVT / IFC format files); for high-quality and highly readable CAD drawings, the corresponding drawing information can be directly identified to automatically establish prefabricated units; for PDF drawings or other drawings with low quality of building information display, an interactive interface is provided to allow users to manually construct prefabricated units.

[0074] For example, the prefabricated units of the BIM model can be obtained in the following three ways:

[0075] (1) Import the initial prefabricated building unit of the BIM model provided by upstream business personnel, and convert this model into a calculable engineering quantity model in the quantity calculation software. If the initial prefabricated building unit (including the spatial position, size, basic properties and other building information that are strongly related to the quantity calculation of each part of the building model) meets the engineering quantity calculation requirements, there is no need to adjust it; if the actual building model provided does not meet the construction project quantity calculation accuracy requirements, manually adjust the various building information of the initial prefabricated unit (including all the above building information that is strongly related to the quantity calculation) through the interactive interface provided, and finally reach the quality standard that can be used as the subsequent BIM model engineering quantity calculation. This method supports the import of building models from multiple modeling platforms and supports model files in the international general building engineering data exchange standard format.

[0076] (2) Automatically generate the initial prefabricated building units of the BIM model based on the architectural drawings of the prefabricated building project. By reading the original information and model facets of models such as Revit and IFC, the information is converted into a model and information database that can be recognized by the quantity calculation software. For example, the components in the converted architectural drawings include conventional main building components, other configuration building components, and various building component tables, decoration tables, etc.

[0077] (3) If the original BIM model or building drawings that meet the standards and can be intelligently converted into the quantity calculation model cannot be obtained during the engineering quantity calculation stage of the prefabricated building project, the prefabricated building unit can also be manually constructed. Alternatively, when manual construction is used as a supplement to the above two modeling approaches, that is, when the building model constructed by other modeling platforms does not meet the quantity calculation standards, the missing building information can be manually supplemented; or when the quantity calculation model converted from the drawings encounters engineering design changes, the quantity calculation model can also be manually edited to quickly respond to various actual engineering situations.

[0078] In some optional implementations of this embodiment, obtaining the assembled unit of the BIM model includes:

[0079] (1) Obtaining an initial prefabricated unit, wherein the initial prefabricated unit is obtained by importing a model unit or identifying a model drawing.

[0080] (2) Obtain adjustments to the initial prefabricated unit and determine the prefabricated unit.

[0081] The electronic device provides an interactive interface and automatically or manually confirms whether the initial prefabricated unit needs to be adjusted. If adjustment is required, the user adjusts the initial prefabricated unit on the interactive interface and ultimately determines the prefabricated unit that can meet the calculation requirements of the quantity calculation software.

[0082] By adjusting the initial prefabricated unit, on the one hand, the accuracy of the obtained prefabricated unit can be guaranteed, and on the other hand, the accuracy requirement for the initial prefabricated unit can be reduced.

[0083] Wherein, the obtaining of engineering quantity calculation rules includes:

[0084] (1) Obtain the calculation rule library.

[0085] (2) Based on the region corresponding to the prefabricated building model, a corresponding calculation rule is determined in a calculation rule library.

[0086] (3) Obtain adjustments to the calculation rules and determine the engineering quantity calculation rules.

[0087] To calculate various engineering quantities based on the prefabricated building model, it is necessary to set the corresponding engineering project calculation settings, obtain the original engineering quantity calculation method of each sub-component (including the main body and decoration components) of the prefabricated building model, the deduction principle of the overlapping part (including the main body and template area, etc.), and other special business engineering quantities (including super-high template area, etc.) Calculation method. In this embodiment, by determining the corresponding calculation rules in the calculation rule library for the region corresponding to the prefabricated building model, and then adaptively adjusting the calculation rules according to actual needs, the engineering quantity calculation rules are finally determined.

[0088] Specifically, the determination of the engineering quantity calculation rules can be divided into the following steps:

[0089] 1) According to the country or region where the prefabricated building project is located, select the calculation rules for the corresponding region.

[0090] 2) After selecting the calculation rule, the calculation rule is further set. For example, the quantity calculation method can be set in depth for each building sub-component. The building sub-components include main supporting components, other functional components, and decorative components. Optionally, in addition to including super-high components, template calculation methods, etc., the calculation rules can also adjust the calculation settings that may be required for the quantity calculation, etc.

[0091] 3) Based on the selected calculation rules combined with the prefabricated building model, various engineering quantities that meet national standards can be directly obtained. If the actual on-site construction or factory prefabrication of each sub-component requires adjustment to the standard calculation rules due to special business environments or equipment, the calculation settings of the calculation rules can be modified according to actual conditions. For example, the calculation settings for all civil engineering quantities of main components such as columns, walls, beams, and slabs, as well as the calculation settings for decoration quantities of decorative components such as cavity surfaces, floors, and ceilings, etc., after modifying the calculation settings according to project requirements, the various engineering quantities of prefabricated buildings will be calculated according to the adjusted engineering quantity calculation rules.

[0092] The calculation rules of multiple countries and regions are integrated in the calculation rule library, which can provide calculation rules for the corresponding region for the prefabricated building model, ensuring the reliability of the calculation results, and also providing adjustments to the calculation rules so that the calculation results can be customized.

[0093] S22, combining the prefabricated units to determine the prefabricated building model.

[0094] Specifically, the above S22 includes:

[0095] S221, obtaining assembly information, and combining the prefabricated units based on the assembly information to determine the model unit.

[0096] The assembly information may be a prefabricated building drawing, for example, a prefabricated unit type detail drawing, a unit type detail drawing (which may be represented as an X-Room detail drawing in the drawing). The prefabricated units are combined based on the assembly information to obtain a model unit. The type of the model unit may be set according to actual needs and is not limited here.

[0097] In some optional implementations of this embodiment, the assembly information includes hierarchical structure information, the prefabricated unit includes a plurality of prefabricated component units, and the model unit includes a first hierarchical unit, a second hierarchical unit, and a third hierarchical unit. Based on this, the above S221 may include the following steps:

[0098] (1) Based on the combination of the first prefabricated component units, a first-level unit is obtained.

[0099] The combination method corresponding to the first-level units is based on the assembly information, that is, which first prefabricated component units are combined. The first-level units can be one or more, and can be set according to actual needs. However, for multiple identical first-level units, they only need to be constructed once.

[0100] The specific combination method can be realized by the user through the interactive interface, or it can be obtained by the electronic device through analysis of the assembly information. For example, the division of each hierarchical unit and the required prefabricated units have been acquired by the electronic device in advance. For example, the first hierarchical unit A requires the combination of the first prefabricated components 1-3, so the electronic device first extracts the first prefabricated components 1-3, and then uses the position information of each first prefabricated component in the first hierarchical unit to combine them, thereby obtaining the first hierarchical unit.

[0101] (2) Based on the combination of the first-level unit and the second prefabricated component unit, a second-level unit is obtained.

[0102] (3) Based on the combination of the first-level unit, the second-level unit and the third prefabricated component unit, a third-level unit is obtained.

[0103] The combination method corresponding to the second-level units and the third-level units is similar to the combination method of the first-level units, and can be processed based on the assembly information.

[0104] As a specific example, the first level unit is a precast component, the second level unit is a precast module (PPVC), and the third level unit is a unit type (Unit). For example, a precast component can be an assembled unit, a precast module is an assembled unit to be basically decorated, and a precast module, a threshold component, and any other building components and decoration components can be further combined into a unit type.

[0105] Specifically, electronic equipment is formed into prefabricated components based on the combination of prefabricated units. The combination of prefabricated components involved in the actual construction project will not have any impact on the overall quantity calculation results of the project. However, establishing an assembly model at this level can be beneficial to the subsequent engineering quantity classification and building information management, and the reuse combination of assembly building units can improve the modeling efficiency and the efficiency of engineering quantity calculation.

[0106] Further, according to the provided assembly information, the threshold module can be combined. Generally, the threshold module is a single room prefabricated in the project, such as a bedroom or kitchen bathroom with basic decoration (including ceiling, floor, wall and skirting). During the actual on-site assembly, there may be other components cast on site in the adjacent prefabricated modules. By combining prefabricated components, cast-in-place components, decoration components and other building configuration components, it is suitable for the calculation of the engineering quantity of prefabricated assembled buildings. Optionally, the prefabricated module can not only include components prefabricated in the actual project, but also include a combination of on-site construction building components, which can be set according to actual needs. Although the combination of on-site construction building components can be included in the prefabricated module, it is essentially cast on site, not prefabricated. When the prefabricated engineering quantity is calculated later, this part of the on-site cast engineering quantity can be excluded by distinguishing. Further, according to the detailed description of the prefabricated module or prefabricated components and other components in the unit type detailed drawing of the prefabricated assembled building drawing, the unit type corresponding to the construction project is constructed.

[0107] By combining prefabricated units in a multi-level manner, we can fully support various engineering quantity calculation businesses for international prefabricated building projects, and provide convenience for model construction and engineering quantity management.

[0108] S222, determining the prefabricated building model based on the combination of model units.

[0109] The electronic device uses the combination of various model units to finally obtain the assembled building model. For example, the various model units are combined to form various floors, and finally the floors are assembled to obtain the assembled building model; in the case of standard floors, the standard floors are first formed by combining various model units, and then the assembled building model is formed by using the standard floors.

[0110] After the model unit is created, the model unit is repeatedly used to construct a complete prefabricated building model. The prefabricated building model can be formed by arranging the unit type, prefabricated modules and prefabricated components to the corresponding spatial positions according to the architectural drawings.

[0111] In some optional implementations of this embodiment, the above S222 may include:

[0112] (1) Based on the combination of model units, a standard layer model is formed.

[0113] (2) Determine the prefabricated building model based on the standard floor model.

[0114] For prefabricated building projects with standard floors, a single-story building is formed by combining model units; the single-story model is then set as a standard floor to quickly build a prefabricated building model. Using the standard floor model to build a prefabricated building model improves the construction efficiency of the prefabricated building model.

[0115] S23, determining the engineering quantity of the prefabricated building model based on the engineering quantity calculation rules.

[0116] For details, please see Figure 1 S13 of the illustrated embodiment will not be described in detail here.

[0117] The engineering quantity calculation method provided in this embodiment combines prefabricated units based on assembly information, which can improve the accuracy of the model units obtained after the combination, and then obtain the prefabricated building model by combining the model units, thereby ensuring the reliability of the obtained prefabricated building model.

[0118] In this embodiment, a method for calculating engineering quantities is provided, which can be used for electronic devices such as computers, mobile phones, tablet computers, etc. Figure 3 is a flow chart of a method for calculating engineering quantities according to an embodiment of the present invention. Figure 3 As shown, the process includes the following steps:

[0119] S31, obtaining the prefabricated units and engineering quantity calculation rules of the BIM model.

[0120] For details, please see Figure 2 S21 of the illustrated embodiment will not be described in detail here.

[0121] S32, combining the prefabricated units to determine the prefabricated building model.

[0122] For details, please see Figure 2 S22 of the illustrated embodiment will not be described in detail here.

[0123] S33, determining the engineering quantity of the prefabricated building model based on the engineering quantity calculation rule.

[0124] After the electronic device determines the prefabricated building model and the engineering quantity calculation rules, it can automatically calculate and statistically classify and manage the engineering quantity of the prefabricated building model. Since the corresponding calculation rules have been set according to the basic information of the construction project in the above steps, and the quantity calculation settings and deduction principles are adjusted as needed according to the actual factory prefabrication, on-site construction and other specific conditions, various engineering quantities that meet the prefabricated building model can be obtained.

[0125] Specifically, the above S33 includes:

[0126] S331, obtaining the category of the engineering quantity to be calculated.

[0127] Among them, the engineering quantity categories include civil engineering or decoration.

[0128] Specifically, it includes the amount of civil engineering related works, the amount of decoration and renovation works, and the statistical quantities of each hierarchical structure, etc. The protection scope of this embodiment is not limited thereto, and can be specifically configured accordingly according to actual needs.

[0129] S332, based on the engineering quantity calculation rule, determine the target engineering quantity calculation rule corresponding to the engineering quantity category.

[0130] The engineering quantity calculation rules determined above include calculation rules for multiple engineering quantity categories. Therefore, it is necessary to determine the corresponding target engineering quantity calculation rules from the engineering quantity calculation rules according to each engineering quantity category.

[0131] S333: Determine the engineering quantity corresponding to the engineering quantity category in the prefabricated building model based on the target engineering quantity calculation rule.

[0132] Specifically, the engineering quantities related to civil engineering include cast-in-place concrete volume, prefabricated component quantity, standard formwork area or length quantity, cast-in-place surface quantity, etc. Depending on the calculation rules set, the formwork quantity may be given by area or by length, or the quantity of the super-high part and the quantity of the segment may be given according to the principle of automatic calculation.

[0133] Regarding the same-city quantity of the decoration part, it includes the quantity of decoration components combined in the prefabricated modules or unit types and other on-site cast-in-place decoration quantities not included in the model units of the prefabricated building model.

[0134] In some optional implementations of this embodiment, the prefabricated building model includes multiple hierarchical structures, and the above S333 may include:

[0135] (1) Count the number of structures at each level in the prefabricated building model.

[0136] (2) Based on the engineering quantity calculation rules, determine the engineering quantity corresponding to each hierarchical structure.

[0137] Specifically, after obtaining the above-mentioned engineering quantities, the electronic device can count the quantities corresponding to each hierarchical structure, and thereby obtain the engineering quantities of each level of the prefabricated component, prefabricated module or unit type. Optionally, a viewing interface for the statistical quantities of each hierarchical structure is also provided to finely manage the engineering quantities of each sub-item of the assembly construction project. The engineering quantities are statistically calculated according to different levels, thereby realizing the fine management of the engineering quantities.

[0138] Further optionally, the electronic device also extracts various calculated engineering quantities into required engineering quantity materials, including engineering quantity lists and reports, etc. According to the actual situation of the stage or region of the engineering project, the corresponding engineering quantities are extracted to meet different business backgrounds.

[0139] The method for calculating the quantity of work provided in this embodiment pre-sets calculation methods for a variety of quantity categories in the quantity calculation rules, including civil engineering and decoration. Therefore, the method also provides calculation of the quantity of the decoration part, thereby improving the integrity of the quantity calculation of the prefabricated building model.

[0140] The method for calculating the engineering quantity provided by the embodiment of the present invention supports multiple ways of constructing prefabricated building models, especially manual and flexible adjustment based on PDF drawings. There is also a built-in rule library of standard construction engineering quantity calculation methods for multiple countries and regions, which can be freely set. Furthermore, the engineering quantity of the decoration components of the prefabricated and non-prefabricated parts in the prefabricated building model can also be calculated. By dividing the prefabricated building model through a hierarchical structure, the number of model units at each level and the corresponding engineering quantity can be obtained.

[0141] In the present embodiment, a device for calculating engineering quantity is also provided, and the device is used to implement the above-mentioned embodiment and preferred implementation mode, and the descriptions which have been made are omitted. As used below, the term "module" can implement a combination of software and / or hardware of a predetermined function. Although the device described in the following embodiments is preferably implemented in software, the implementation of hardware, or a combination of software and hardware is also possible and conceived.

[0142] This embodiment provides a device for calculating engineering quantities, such as Figure 4 As shown, including:

[0143] An acquisition module 41 is used to acquire the assembly units and engineering quantity calculation rules of the BIM model;

[0144] A combination module 42, used to combine the prefabricated units to determine a prefabricated building model;

[0145] The engineering quantity calculation module 43 is used to determine the engineering quantity of the prefabricated building model based on the engineering quantity calculation rule.

[0146] The engineering quantity calculation device provided in this embodiment determines the prefabricated building model by combining prefabricated units, and then calculates the engineering quantity. Since the prefabricated units can be repeatedly combined and utilized, the same units in the prefabricated building model only need to be constructed once, and the same units only need to be calculated once during the engineering quantity calculation, thereby improving the efficiency of the engineering quantity calculation.

[0147] The engineering quantity calculation device in this embodiment is presented in the form of a functional unit, where the unit refers to an ASIC circuit, a processor and memory that executes one or more software or fixed programs, and / or other devices that can provide the above functions.

[0148] The further functional description of each of the above modules is the same as that of the above corresponding embodiments and will not be repeated here.

[0149] The embodiment of the present invention also provides an electronic device having the above Figure 4 The engineering quantity calculation device shown.

[0150] See also Figure 5 , Figure 5 is a schematic diagram of the structure of an electronic device provided by an optional embodiment of the present invention, such as Figure 5 As shown, the electronic device may include: at least one processor 51, such as a CPU (Central Processing Unit), at least one communication interface 53, a memory 54, and at least one communication bus 52. The communication bus 52 is used to realize the connection and communication between these components. The communication interface 53 may include a display screen (Display) and a keyboard (Keyboard), and the optional communication interface 53 may also include a standard wired interface and a wireless interface. The memory 54 may be a high-speed RAM memory (Random Access Memory) or a non-volatile memory (non-volatile memory), such as at least one disk storage. The memory 54 may optionally be at least one storage device located away from the aforementioned processor 51. The processor 51 may be combined with Figure 4 In the described device, the memory 54 stores an application program, and the processor 51 calls the program code stored in the memory 54 to execute any of the above method steps.

[0151] The communication bus 52 may be a peripheral component interconnect (PCI) bus or an extended industry standard architecture (EISA) bus. The communication bus 52 may be divided into an address bus, a data bus, a control bus, etc. For ease of representation, Figure 5 Only one thick line is used in the diagram, but this does not mean that there is only one bus or only one type of bus.

[0152] Among them, the memory 54 may include a volatile memory (English: volatile memory), such as a random access memory (English: random-access memory, abbreviated: RAM); the memory may also include a non-volatile memory (English: non-volatile memory), such as a flash memory (English: flash memory), a hard disk drive (English: hard disk drive, abbreviated: HDD) or a solid-state drive (English: solid-state drive, abbreviated: SSD); the memory 54 may also include a combination of the above types of memory.

[0153] The processor 51 may be a central processing unit (CPU), a network processor (NP), or a combination of a CPU and a NP.

[0154] The processor 51 may further include a hardware chip. The hardware chip may be an application-specific integrated circuit (ASIC), a programmable logic device (PLD), or a combination thereof. The PLD may be a complex programmable logic device (CPLD), a field-programmable gate array (FPGA), a generic array logic (GAL), or any combination thereof.

[0155] Optionally, the memory 54 is also used to store program instructions. The processor 51 can call the program instructions to implement the present application Figures 1 to 3 The method for calculating the engineering quantities shown in any embodiment.

[0156] The embodiment of the present invention further provides a non-transitory computer storage medium, wherein the computer storage medium stores computer executable instructions, and the computer executable instructions can execute the engineering quantity calculation method in any of the above method embodiments. The storage medium can be a disk, an optical disk, a read-only memory (ROM), a random access memory (RAM), a flash memory, a hard disk (HDD) or a solid-state drive (SSD), etc.; the storage medium can also include a combination of the above types of memory.

[0157] Although the embodiments of the present invention have been described in conjunction with the accompanying drawings, those skilled in the art may make various modifications and variations without departing from the spirit and scope of the present invention, and such modifications and variations are all within the scope defined by the appended claims.

Claims

1. A method for calculating engineering quantities, characterized in that: include: Obtain the prefabricated units and quantity calculation rules of the BIM model; Combining the prefabricated units to determine a prefabricated building model; Determining the engineering quantity of the prefabricated building model based on the engineering quantity calculation rule; The prefabricated building model includes multiple hierarchical structures, and determining the engineering quantity of the prefabricated building model based on the engineering quantity calculation rule includes: Counting the number of each hierarchical structure in the prefabricated building model; Based on the engineering quantity calculation rule, the engineering quantity corresponding to each of the hierarchical structures is determined.

2. The method according to claim 1, characterized in that The step of combining the prefabricated units to determine the prefabricated building model includes: Acquire assembly information, and combine the assembled units based on the assembly information to determine a model unit; The prefabricated building model is determined based on the combination of the model units.

3. The method according to claim 2, characterized in that The assembly information includes hierarchical structure information, the prefabricated unit includes a plurality of prefabricated component units, the model unit includes a first hierarchical unit, a second hierarchical unit, and a third hierarchical unit, and combining the prefabricated units based on the assembly information to determine the model unit includes: Based on the combination of the first prefabricated component units, the first hierarchical unit is obtained; Based on the combination of the first hierarchical unit and the second prefabricated component unit, the second hierarchical unit is obtained; Based on the combination of the first hierarchical unit, the second hierarchical unit and the third prefabricated component unit, the third hierarchical unit is obtained.

4. The method according to claim 2, characterized in that: The step of determining the prefabricated building model based on the combination of the model units includes: Based on the combination of the model units, a standard layer model is formed; The prefabricated building model is determined based on the standard floor model.

5. The method according to claim 1, characterized in that The determining the engineering quantity of the prefabricated building model based on the engineering quantity calculation rule includes: Obtaining the category of the engineering quantity to be calculated, where the engineering quantity category includes civil engineering or decoration; Based on the engineering quantity calculation rule, determining a target engineering quantity calculation rule corresponding to the engineering quantity category; Based on the target engineering quantity calculation rule, the engineering quantity corresponding to the engineering quantity category in the prefabricated building model is determined.

6. The method according to claim 1, characterized in that The method of obtaining the assembled unit of the BIM model includes: Acquire an initial prefabricated unit, where the initial prefabricated unit is obtained by importing a model unit or identifying a model drawing; Adjustments to the initial prefabricated unit are obtained to determine the prefabricated unit.

7. The method according to claim 1, characterized in that Obtain quantity calculation rules, including: Obtain calculation rule library; Based on the region corresponding to the prefabricated building model, determining a corresponding calculation rule in the calculation rule library; The adjustment to the calculation rule is obtained to determine the engineering quantity calculation rule.

8. A device for calculating engineering quantities, characterized in that: include: An acquisition module is used to obtain the assembly units and engineering quantity calculation rules of the BIM model; A combination module, used to combine the prefabricated units to determine a prefabricated building model; A project quantity calculation module, used to determine the project quantity of the prefabricated building model based on the project quantity calculation rule; The prefabricated building model includes multiple hierarchical structures, and determining the engineering quantity of the prefabricated building model based on the engineering quantity calculation rule includes: Counting the number of each hierarchical structure in the prefabricated building model; Based on the engineering quantity calculation rule, the engineering quantity corresponding to each of the hierarchical structures is determined.

9. An electronic device, characterized in that: include: A memory and a processor, wherein the memory and the processor are communicatively connected to each other, the memory stores computer instructions, and the processor executes the engineering quantity calculation method according to any one of claims 1 to 7 by executing the computer instructions.

10. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores computer instructions, and the computer instructions are used to enable a computer to execute the engineering quantity calculation method according to any one of claims 1 to 7.