A train power supply system and a train automatic phase-shifting control device

By designing voltage and current detection, train position detection and redundant control systems in the train power supply system, the automatic control and main and backup switching of electronic switch valve groups are realized, and the reliability and cost problems of the train power supply system in the existing technology are solved, and the reliability and cost of the train power supply system is improved. Automatic overphase reliability and reduce costs.

CN114103737BActive Publication Date: 2024-11-05ZHUZHOU CSR TIMES ELECTRIC CO LTD
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202010904951.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-09-01
Publication Date
2024-11-05
Estimated Expiration
2040-09-01

AI Technical Summary

Technical Problem

The existing train power supply system avoids speed loss and arcing caused by short circuits in adjacent power supply intervals. The automatic overphase device of electronic switches on the ground is high cost and has low reliability, making it difficult to effectively ensure the reliability of overphase and increase redundancy. Remaining configuration increases costs.

Method used

Design a control device for automatic excessive phase of trains, including voltage and current detection circuit, train position detection system and redundant control system, realize automatic control of electronic switch valve group through optical signal distribution unit and logic controller, and has a main and backup switching mechanism To improve reliability and reduce the settings of redundant electronic switch valve sets.

Benefits of technology

It improves the reliability of the train's automatic overphase control equipment, while reducing implementation costs, avoiding the redundant setting of redundant electronic switch valve groups, and achieving cost-effective balance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114103737B_ABST
    Figure CN114103737B_ABST
Patent Text Reader

Abstract

The present application discloses a control device for automatic train phase transition, including: a voltage and current detection circuit for detecting the voltage of a primary main circuit and the current of a primary main circuit; a train position detection system for sending a train position signal; a control system for controlling an electronic switch valve group to realize automatic train phase transition according to the train position signal, the voltage of a primary main circuit and the current of a primary main circuit, and having a redundant mechanism for controlling the automatic train phase transition function; an electronic switch valve group. The application of the scheme of the present application can not only improve the reliability of the entire train automatic phase transition control device, but also reduce the implementation cost of the scheme, and facilitate the promotion and application of the scheme. The present application also provides a train power supply system with corresponding technical effects.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of rail transit, and in particular to a train power supply system and a train automatic phase-shifting control device. Background Art

[0002] Electrified railways use single-phase industrial frequency AC power supply. In order to reduce the negative sequence problem caused by the traction load to the power system, phase-changing power supply is usually implemented along the entire electrified railway. This results in different voltage phases in the power supply arms of the traction substation. In order to avoid short circuits between two adjacent power supply sections, necessary electrical phase separation sections are set on the contact network. When the train passes through this section, it cannot obtain electrical energy and can only rush through it by inertia, which will lead to speed loss and arcing when passing through the electrical phase separation device. In addition, for some long slopes, the train may not even be able to completely rely on inertia to rush through the power-free area. At present, the commonly used phase-splitting schemes are automatic phase-splitting by ground electronic switches and phase-splitting by automatic power-off on board. The automatic phase-splitting scheme of ground electronic switches can make the train energized and senseless phase-splitting, and has a long service life, so it has broad prospects.

[0003] The ground electronic switch automatic phase-shifting device is a complex large system, including both the primary system including the thyristor valve group and the phase-shifting control system, i.e., the secondary system. Failure of either the primary system or the secondary system will result in failure of normal phase-shifting. In order to ensure reliability, some current solutions will configure two identical devices, i.e., two primary systems and two secondary systems, which are independent of each other and serve as redundant backups, but such a solution is costly.

[0004] In summary, how to effectively ensure the reliability of the over-phase and reduce the cost is a technical problem that technical personnel in this field urgently need to solve. Summary of the invention

[0005] The purpose of the present invention is to provide a train power supply system and a train automatic phase transition control device, so as to effectively ensure the reliability of phase transition and help reduce costs.

[0006] In order to solve the above technical problems, the present invention provides the following technical solutions:

[0007] A control device for automatic train phase transition, comprising:

[0008] A voltage and current detection circuit for detecting the voltage of a primary main circuit and the current of a primary main circuit;

[0009] A train position detection system for sending a train position signal;

[0010] A control system for controlling the electronic switch valve group to realize automatic train over-phase according to the train position signal, the voltage of the primary main circuit and the current of the primary main circuit, and having a redundant mechanism for controlling the automatic train over-phase function;

[0011] The electronic switch valve group.

[0012] Preferably, the control system comprises:

[0013] The first logic controller is used to determine the master-slave relationship between the first valve group controller and the second valve group controller according to the master-slave setting rule; generate a corresponding first valve group control instruction according to the train position signal, and send it to the first valve group controller and the second valve group controller;

[0014] The second logic controller is used to determine the master-slave relationship between the first valve group controller and the second valve group controller according to the master-slave setting rule; generate a corresponding second valve group control instruction according to the train position signal, and send it to the first valve group controller and the second valve group controller;

[0015] The first valve group controller is used for generating a corresponding optical control signal according to the voltage of the primary main circuit, the current of the primary main circuit, the first valve group control instruction and the second valve group control instruction and sending the corresponding optical control signal to the optical signal distribution unit when the received first valve group control instruction is consistent with the second valve group control instruction and the first valve group controller is the main valve group controller, so as to control the electronic switch valve group through the optical signal distribution unit to realize automatic phase separation of the train;

[0016] The second valve group controller is used for generating a corresponding optical control signal according to the voltage of the primary main circuit, the current of the primary main circuit, the first valve group control instruction and the second valve group control instruction and sending the corresponding optical control signal to the optical signal distribution unit when the received first valve group control instruction is consistent with the second valve group control instruction and the second valve group control instruction is the main valve group controller, so as to control the electronic switch valve group through the optical signal distribution unit to realize automatic phase separation of the train;

[0017] The optical signal distribution unit is respectively connected to the first valve group controller, the second valve group controller and the electronic switch valve group.

[0018] Preferably, the optical signal distribution unit is further used to obtain the state of the electronic switch valve group and send a state feedback signal to the first valve group controller and the second valve group controller;

[0019] The first valve group controller is further used for: when the first valve group controller is the main valve group controller, verifying whether the electronic switch valve group is successfully controlled based on the state feedback signal, and if not, outputting first fault prompt information to the central system;

[0020] The second valve group controller is also used for: when the second valve group controller is the main valve group controller, verifying whether the electronic switch valve group is successfully controlled based on the state feedback signal, and if not, outputting a first fault prompt information to the central system.

[0021] Preferably, the first logic controller determines the master-slave relationship between the first valve group controller and the second valve group controller according to the master-slave setting rule, including:

[0022] After the first logic controller confirms that the primary main circuit is ready, it detects the fault status of the first valve group controller and the second valve group controller;

[0023] When the second valve group controller fails and the first valve group controller is normal, or when both the first valve group controller and the second valve group controller are normal, a first designated instruction is sent to the first valve group controller and the second valve group controller, so that the first valve group controller serves as the main valve group controller and the second valve group controller serves as the standby valve group controller;

[0024] When the first valve group controller fails and the second valve group controller is normal, a second designated instruction is sent to the first valve group controller and the second valve group controller, so that the second valve group controller serves as the main valve group controller and the first valve group controller serves as the standby valve group controller;

[0025] When both the first valve group controller and the second valve group controller fail, second fault prompt information is output to the central system.

[0026] Preferably, the second logic controller determines the master-slave relationship between the first valve group controller and the second valve group controller according to the master-slave setting rule, including:

[0027] After the second logic controller confirms that the primary main circuit is ready, it detects the fault status of the first valve group controller and the second valve group controller;

[0028] When the second valve group controller fails and the first valve group controller is normal, or when both the first valve group controller and the second valve group controller are normal, a first designated instruction is sent to the first valve group controller and the second valve group controller, so that the first valve group controller serves as the main valve group controller and the second valve group controller serves as the standby valve group controller;

[0029] When the first valve group controller fails and the second valve group controller is normal, a second designated instruction is sent to the first valve group controller and the second valve group controller, so that the second valve group controller serves as the main valve group controller and the first valve group controller serves as the standby valve group controller;

[0030] When both the first valve group controller and the second valve group controller fail, second fault prompt information is output to the central system.

[0031] Preferably, the first valve group controller is also used for:

[0032] When the first designated instruction sent by the first logic controller and the first designated instruction sent by the second logic controller are received at the same time and the two are inconsistent, outputting third fault prompt information to the central system;

[0033] When the second designated instruction sent by the first logic controller and the second designated instruction sent by the second logic controller are received at the same time and the two are inconsistent, outputting fourth fault prompt information to the central system;

[0034] The second valve group controller is also used for:

[0035] When the first designated instruction sent by the first logic controller and the first designated instruction sent by the second logic controller are received at the same time and the two are inconsistent, outputting fifth fault prompt information to the central system;

[0036] When the second designated instruction sent by the first logic controller and the second designated instruction sent by the second logic controller are received at the same time and the two are inconsistent, the sixth fault prompt information is output to the central system.

[0037] Preferably, it also includes an instruction execution unit;

[0038] The first logic controller confirms that the primary circuit is ready, including:

[0039] The first logic controller detects whether each switch device of the primary main circuit is in a normal state;

[0040] If not, outputting the seventh fault prompt information to the central system;

[0041] If yes, after receiving the opening and closing command, the command execution unit controls the actions of the various switch devices of the primary main circuit, and after determining that the actions of the various switch devices of the primary main circuit are completed, confirms that the primary main circuit is ready;

[0042] The second logic controller confirms that the primary main circuit is ready, including:

[0043] The second logic controller detects whether each switch device of the primary main circuit is in a normal state;

[0044] If not, outputting an eighth fault prompt message to the central system;

[0045] If yes, after receiving the opening and closing command, the command execution unit controls the actions of the various switch devices of the primary main circuit, and after determining that the actions of the various switch devices of the primary main circuit are completed, it is confirmed that the primary main circuit is ready.

[0046] Preferably, the instruction execution unit is specifically used for:

[0047] When controlling the actions of the various switch devices of the primary main circuit, the actions of the various switch devices of the primary main circuit are controlled based on a hardware interlocking method.

[0048] Preferably, the first logic controller is also used for:

[0049] After receiving the opening and closing instruction, determine whether the opening and closing instruction complies with the preset opening and closing rules, if yes, control the actions of the various switch devices of the primary main circuit through the instruction execution unit, otherwise output the ninth fault prompt information to the central system;

[0050] The second logic controller is also used for:

[0051] After receiving the opening and closing instructions, it is determined whether the opening and closing instructions comply with the preset opening and closing rules. If so, the various switching devices of the primary main circuit are controlled by the instruction execution unit. Otherwise, the tenth fault prompt information is output to the central system.

[0052] A train power supply system comprises the train automatic phase transition control device as described in any one of the above items.

[0053] Applying the technical solution provided in the embodiment of the present invention, considering that in the control equipment of automatic train over-phase, the cost of the electronic switch valve group is higher, while the cost of the control system is lower, and the reliability of the electronic switch valve group is higher, while the reliability of the control system is lower, therefore, the present application only sets up one set of primary system, that is, no redundancy is set for the electronic switch valve group, and the control system is set to be a control system with a redundant mechanism for controlling the function of automatic train over-phase, so that the solution of the present application can not only improve the reliability of the control equipment of the entire train automatic over-phase, but also reduce the implementation cost of the solution, and facilitate the promotion and application of the solution. BRIEF DESCRIPTION OF THE DRAWINGS

[0054] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0055] Figure 1 It is a structural schematic diagram of a control device for automatic train phase transition in the present invention;

[0056] Figure 2 It is a commonly used system topology with ground electronic switches over-phase;

[0057] Figure 3 for Figure 2 A turn-on timing diagram for a specific scenario;

[0058] Figure 4 It is a schematic diagram of the structure of a control device for automatic train phase transition in a specific implementation manner of the present invention. DETAILED DESCRIPTION

[0059] The core of the present invention is to provide a control device for automatic train phase transition, which can not only improve the reliability of the entire train automatic phase transition control device, but also reduce the implementation cost of the solution, and facilitate the promotion and application of the solution.

[0060] In order to enable those skilled in the art to better understand the scheme of the present invention, the present invention is further described in detail below in conjunction with the accompanying drawings and specific implementation methods. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.

[0061] Please refer to Figure 1 , Figure 1 The structure diagram of a control device for automatic train phase transition in the present invention is shown in FIG. 1 , and the control device for automatic train phase transition may include:

[0062] A voltage and current detection circuit 10 for detecting the voltage of a primary main circuit and the current of a primary main circuit;

[0063] A train position detection system 20 for sending a train position signal;

[0064] A control system 30 for controlling the electronic switch valve group 40 to realize automatic train over-phase according to the train position signal, the voltage of the primary main circuit and the current of the primary main circuit, and having a redundant mechanism for controlling the automatic train over-phase function;

[0065] Electronic switch valve group 40.

[0066] Specifically, the train automatic phase-shifting control device of the present application can be applied to a variety of system topologies, such as Figure 2 This is a commonly used ground electronic switch over-phase system topology. For example, when a train runs from power supply arm a to power supply arm b, the conduction timing diagram of phase a valve group and phase b valve group can be found in Figure 3 When the train reaches the J1 position, the a-phase valve group is controlled to be turned on. After reaching the J3 position, it detects that the current of the primary system reaches the zero-crossing state, and immediately turns on the b-phase valve group and closes the a-phase valve group. When the train reaches the J4 position, the b-phase valve group is controlled to be closed, completing the phase separation process. Figure 2 In the implementation manner, the electronic switch valve group 40 is composed of a phase a valve group and a phase b valve group, and the devices used are all thyristors. In other implementation manners, the electronic switch valve group 40 can be composed of other forms as long as it can realize automatic phase transition of the train.

[0067] The voltage and current detection circuit 10 needs to detect the voltage of the primary main circuit and the current of the primary main circuit. The specific device composition of the voltage and current detection circuit 10 and the specific detection position can be set and adjusted according to actual needs, as long as the requirements of this application are met. For example, the voltage and current detection circuit 10 can be composed of one or more current transformers and one or more voltage transformers.

[0068] The train position detection system 20 is used to detect the movement of the train, thereby sending a train position signal to the control system 30, and can usually be detected according to a preset period. It should be noted that the train position signal described in this application needs to carry train position information and travel direction information, and the travel direction includes an upward direction and a downward direction, for example Figure 2 It can be from power supply arm a to power supply arm b, or it can be from power supply arm b to power supply arm a.

[0069] The control system 30 of the present application can control the electronic switch valve group 40 according to the train position signal, the voltage of the primary main circuit and the current of the primary main circuit to realize the automatic phase transition of the train. In addition, the control system 30 of the present application has a redundant mechanism for controlling the automatic phase transition function of the train. For example, the control system 30 can include two independent control units, and after one of them fails, it can switch to the other to ensure the normal operation of the control device for the automatic phase transition of the train.

[0070] Furthermore, in a specific embodiment of the present invention, considering that the control system 30 is composed of two independent control units, although redundancy can be achieved, if a train happens to be automatically switching phases when a failure occurs, there will be a safety hazard during the time period of primary and standby switching.

[0071] Therefore, in a specific embodiment of the present invention, the control system 30 includes:

[0072] The first logic controller 31 is used to determine the master-slave relationship between the first valve group controller 33 and the second valve group controller 34 according to the master-slave setting rule; generate the corresponding first valve group control instruction according to the train position signal, and send it to the first valve group controller 33 and the second valve group controller 34;

[0073] The second logic controller 32 is used to determine the master-slave relationship between the first valve group controller 33 and the second valve group controller 34 according to the master-slave setting rule; generate the corresponding second valve group control instruction according to the train position signal, and send it to the first valve group controller 33 and the second valve group controller 34;

[0074] The first valve group controller 33 is used for generating a corresponding optical control signal according to the voltage of the primary main circuit, the current of the primary main circuit, the first valve group control instruction and the second valve group control instruction when the received first valve group control instruction is consistent with the second valve group control instruction and the first valve group controller 33 is a main valve group controller, and sending the optical control signal to the optical signal distribution unit 35, so as to control the electronic switch valve group 40 through the optical signal distribution unit 35 to realize automatic phase separation of the train;

[0075] The second valve group controller 34 is used for generating a corresponding optical control signal according to the voltage of the primary main circuit, the current of the primary main circuit, the first valve group control instruction and the second valve group control instruction and sending the optical control signal to the optical signal distribution unit 35 when the received first valve group control instruction is consistent with the second valve group control instruction and the second valve group control instruction is the main valve group controller, so as to control the electronic switch valve group 40 through the optical signal distribution unit 35 to realize automatic phase separation of the train;

[0076] The optical signal distribution unit 35 is connected to the first valve group controller 33, the second valve group controller 34 and the electronic switch valve group 40 respectively.

[0077] See also Figure 4 In this implementation, both the first logic controller 31 and the second logic controller 32 receive the train position signal, that is, both the first logic controller 31 and the second logic controller 32 are set to work. The first logic controller 31 can generate the corresponding first valve group control instruction according to the train position signal, and send it to the first valve group controller 33 and the second valve group controller 34 at the same time. For example, for Figure 2In the implementation mode, when the train runs from power supply arm a to power supply arm b and reaches the J1 position, the information carried in the first valve group control instruction should be to turn on the a-phase valve group. If the train reaches the J3 position, the information carried in the first valve group control instruction should be to turn on the b-phase valve group and close the a-phase valve group.

[0078] Similarly, the second logic controller 32 can generate a corresponding second valve group control instruction according to the train position signal. And it can be understood that if the first logic controller 31 and the second logic controller 32 are both operating normally, the contents of the first valve group control instruction and the second valve group control instruction should be the same, that is, the two are consistent.

[0079] It should also be noted that when the first logic controller 31 or the second logic controller 32 fails, the logic controller after the failure usually does not output erroneous data. Therefore, after any one of the first logic controller 31 and the second logic controller 32 fails, it will not affect the automatic phase transition of the train. Therefore, this application sets both the first logic controller 31 and the second logic controller 32 to a working state.

[0080] The first valve group controller 33 can determine whether the received first valve group control instruction is consistent with the second valve group control instruction. If they are consistent, it means that the first logic controller 31 and the second logic controller 32 are operating normally. Of course, if the two are inconsistent, a prompt message can be output to the central system. However, generally speaking, there will be no inconsistency, because generally speaking, if a valve group controller fails, the faulty valve group controller will usually not output a signal.

[0081] When the first valve group controller 33 is the main valve group controller, the first valve group controller 33 can generate a corresponding optical control signal according to the voltage of the primary main circuit, the current of the primary main circuit, the first valve group control instruction and the second valve group control instruction and send it to the optical signal distribution unit 35, so as to control the electronic switch valve group 40 through the optical signal distribution unit 35 to realize the automatic phase transition of the train. For example, in the above example, the information carried in the first valve group control instruction is to make the a-phase valve group conductive, then according to the voltage of the primary main circuit and the current of the primary main circuit, the moment when the current of the primary main circuit reaches the zero-crossing state is determined, and the corresponding optical control signal can be generated and sent to the optical signal distribution unit 35, and the information carried in the optical control signal is to make the a-phase valve group conductive. After the optical control signal is sent to the optical signal distribution unit 35, the electronic switch valve group 40 can be controlled by the optical signal distribution unit 35, specifically, the a-phase valve group is controlled to be conductive at this time.

[0082] Similarly, the second valve group controller 34 can also determine whether the received first valve group control instruction is consistent with the second valve group control instruction. If they are consistent, it can be explained that the first logic controller 31 and the second logic controller 32 are operating normally.

[0083] It should be noted that the light control signal is sent to the light signal distribution unit 35 by the main valve group controller in the first valve group controller 33 and the second valve group controller 34. When the second valve group controller 34 is the main valve group controller, the second valve group controller 34 can generate a corresponding light control signal according to the voltage of the primary main circuit, the current of the primary main circuit, the first valve group control instruction and the second valve group control instruction, and send it to the light signal distribution unit 35.

[0084] That is to say, the optical signal distribution unit 35 will only receive the optical control signal sent by the first valve group controller 33 or the second valve group controller 34 at a time. This is because the valve group controller is different from the logic controller. When the first valve group controller 33 or the second valve group controller 34 fails, the failed valve group controller is likely to output erroneous data. Therefore, this application only allows the main valve group controller to send an optical control signal to the optical signal distribution unit 35. Of course, the main valve group controller needs to be determined to be not faulty before it can be used as the main valve group controller. The specific main and standby setting rules can be set according to actual needs.

[0085] For example, in a specific embodiment of the present invention, the first logic controller 31 determines the master-slave relationship between the first valve group controller 33 and the second valve group controller 34 according to the master-slave setting rule, which may specifically include:

[0086] After the first logic controller 31 confirms that the primary main circuit is ready, it detects the fault status of the first valve group controller 33 and the second valve group controller 34;

[0087] When the second valve group controller 34 fails and the first valve group controller 33 is normal, or when both the first valve group controller 33 and the second valve group controller 34 are normal, a first designated instruction is sent to the first valve group controller 33 and the second valve group controller 34, so that the first valve group controller 33 serves as the main valve group controller and the second valve group controller 34 serves as the standby valve group controller;

[0088] When the first valve group controller 33 fails and the second valve group controller 34 is normal, a second designated instruction is sent to the first valve group controller 33 and the second valve group controller 34, so that the second valve group controller 34 acts as the main valve group controller and the first valve group controller 33 acts as the standby valve group controller;

[0089] When both the first valve group controller 33 and the second valve group controller 34 fail, second failure prompt information is output to the central system.

[0090] In this implementation, the first logic controller 31 can determine the fault status of the first valve group controller 33 and the second valve group controller 34 through the status feedback of the first valve group controller 33 and the second valve group controller 34. When both are normal or only the second valve group controller 34 fails, the first valve group controller 33 is used as the main valve group controller and the second valve group controller 34 is used as the standby valve group controller. When only the first valve group controller 33 fails, the second valve group controller 34 is used as the main valve group controller and the first valve group controller 33 is used as the standby valve group controller. Of course, if both the first valve group controller 33 and the second valve group controller 34 fail, the second fault prompt information can be output to the central system to prompt relevant personnel to deal with the situation in a timely manner.

[0091] Correspondingly, the second logic controller 32 also needs to be able to determine the master-slave relationship between the first valve group controller 33 and the second valve group controller 34 according to the master-slave setting rule, which may specifically include:

[0092] After the second logic controller 32 confirms that the primary main circuit is ready, it detects the fault status of the first valve group controller 33 and the second valve group controller 34;

[0093] When the second valve group controller 34 fails and the first valve group controller 33 is normal, or when both the first valve group controller 33 and the second valve group controller 34 are normal, a first designated instruction is sent to the first valve group controller 33 and the second valve group controller 34, so that the first valve group controller 33 serves as the main valve group controller and the second valve group controller 34 serves as the standby valve group controller;

[0094] When the first valve group controller 33 fails and the second valve group controller 34 is normal, a second designated instruction is sent to the first valve group controller 33 and the second valve group controller 34, so that the second valve group controller 34 acts as the main valve group controller and the first valve group controller 33 acts as the standby valve group controller;

[0095] When both the first valve group controller 33 and the second valve group controller 34 fail, second failure prompt information is output to the central system.

[0096] This implementation can be cross-referenced with the above description of the first logic controller 31, and will not be repeated here. It can be seen that when any one of the first valve group controller 33 and the second valve group controller 34 is normal, the normal valve group controller can be used as the main valve group controller to ensure the implementation of the present application, and the first logic controller 31 and the second logic controller 32 can determine the master-slave relationship between the first valve group controller 33 and the second valve group controller 34 according to the master-slave setting rules, that is, when any one of the first logic controller 31 and the second logic controller 32 fails, it can still ensure the implementation of the present application and realize the automatic phase separation of the train.

[0097] In addition, in addition to obtaining status feedback from the first valve group controller 33 and the second valve group controller 34, the first logic controller 31 can also receive feedback from the first valve group controller 33 and the second valve group controller 34 on the active and standby status, that is, determine whether the first valve group controller 33 and the second valve group controller 34 have completed the active and standby settings as required. Similarly, the second logic controller 32 can also receive feedback from the first valve group controller 33 and the second valve group controller 34 on the active and standby status.

[0098] also, Figure 4 In the implementation manner, the first logic controller 31 and the second logic controller 32 can also communicate with each other to check and exchange information as needed.

[0099] In a specific embodiment of the present invention, the optical signal distribution unit 35 is also used to obtain the state of the electronic switch valve group 40 and send a state feedback signal to the first valve group controller 33 and the second valve group controller 34;

[0100] The first valve group controller 33 is further used to: when the first valve group controller 33 is the main valve group controller, verify whether the electronic switch valve group 40 is successfully controlled based on the state feedback signal, and if not, output the first fault prompt information to the central system;

[0101] The second valve group controller 34 is also used for: when the second valve group controller 34 is the main valve group controller, verifying whether the electronic switch valve group 40 is successfully controlled based on the state feedback signal, and if not, outputting the first fault prompt information to the central system.

[0102] In this embodiment, a means for verifying whether the control of the electronic switch valve group 40 is successfully completed is provided for the first valve group controller 33 and the second valve group controller 34. Specifically, after the optical signal distribution unit 35 obtains the state of the electronic switch valve group 40, it will send a state feedback signal to both the first valve group controller 33 and the second valve group controller 34. When the first valve group controller 33 is the main valve group controller, it can verify whether the electronic switch valve group 40 is successfully controlled based on the state feedback signal. If not, it can output the first fault prompt information to the central system to remind the staff to pay attention to the situation in time.

[0103] Similarly, when the second valve group controller 34 is the main valve group controller, it can verify whether the electronic switch valve group 40 is successfully controlled based on the status feedback signal. If not, it can output the first fault prompt information to the central system to remind the staff to pay attention to the situation in time.

[0104] In a specific embodiment of the present invention, the first valve group controller 33 is also used for:

[0105] When the first designated instruction sent by the first logic controller 31 and the first designated instruction sent by the second logic controller 32 are received at the same time and the two are inconsistent, outputting third fault prompt information to the central system;

[0106] When the second designated instruction sent by the first logic controller 31 and the second designated instruction sent by the second logic controller 32 are received at the same time and the two are inconsistent, outputting fourth fault prompt information to the central system;

[0107] The second valve group controller 34 is also used for:

[0108] When the first designated instruction sent by the first logic controller 31 and the first designated instruction sent by the second logic controller 32 are received at the same time and the two are inconsistent, outputting fifth fault prompt information to the central system;

[0109] When the second designated instruction sent by the first logic controller 31 and the second designated instruction sent by the second logic controller 32 are received at the same time and the two are inconsistent, the sixth fault prompt information is output to the central system.

[0110] Considering that generally speaking, the first designated instruction sent by the first logic controller 31 and the first designated instruction sent by the second logic controller 32 should be instructions with the same content, because once one of the logic controllers fails, the logic controller will not send out erroneous data. However, in this embodiment, in order to avoid unexpected situations, the first valve group controller 33 further compares the received first designated instruction sent by the first logic controller 31 and the first designated instruction sent by the second logic controller 32 to determine whether the two are consistent. If they are inconsistent, the third fault prompt information can be output to the central system.

[0111] Similarly, the second valve group controller 34 will further compare the second designated instruction sent by the first logic controller 31 and the second designated instruction sent by the second logic controller 32 to determine whether the two are consistent. If they are inconsistent, the fourth fault prompt information can be output to the central system;

[0112] The operation of the second valve group controller 34 may refer to the first valve group controller 33 , and will not be repeated here.

[0113] In a specific embodiment of the present invention, it also includes an instruction execution unit;

[0114] The first logic controller 31 confirms that the primary main circuit is ready, including:

[0115] The first logic controller 31 detects whether each switch device of the primary main circuit is in a normal state;

[0116] If not, outputting the seventh fault prompt information to the central system;

[0117] If yes, after receiving the opening and closing command, the command execution unit controls the actions of the various switch devices of the primary main circuit, and after determining that the actions of the various switch devices of the primary main circuit are completed, confirms that the primary main circuit is ready;

[0118] The second logic controller 32 confirms that the primary main circuit is ready, including:

[0119] The second logic controller 32 detects whether each switch device of the primary main circuit is in a normal state;

[0120] If not, outputting an eighth fault prompt message to the central system;

[0121] If yes, after receiving the opening and closing command, the instruction execution unit controls the actions of the various switching devices of the primary main circuit, and after determining that the actions of the various switching devices of the primary main circuit are completed, it is confirmed that the primary main circuit is ready.

[0122] In this implementation, both the first logic controller 31 and the second logic controller 32 can determine whether the primary main circuit is ready based on the instruction execution unit.

[0123] Taking the first logic controller 31 as an example, the second logic controller 32 is the same. The first logic controller 31 detects whether the various switching devices of the primary main circuit are in normal status, and the specific detection items can be set and adjusted according to actual needs. If at least one switching device is abnormal, the seventh fault prompt information can be output to the central system. If they are all normal, the operation of each switching device of the primary main circuit can be controlled by the instruction execution unit after receiving the opening and closing instructions. Usually, the opening and closing instructions sent by the central system can be received through the communication unit. By obtaining feedback from each switching device of the primary main circuit, it can be determined whether each switching device of the primary main circuit has completed the operation. After the operation is completed, it can be confirmed that the primary main circuit is ready.

[0124] When the action of each switch device of the primary main circuit is controlled by the instruction execution unit, in order to avoid misoperation, the action of each switch device of the primary main circuit can be controlled based on hardware interlocking. That is, in a specific embodiment of the present invention, the instruction execution unit can be specifically used to: when controlling the action of each switch device of the primary main circuit, the action of each switch device of the primary main circuit can be controlled based on hardware interlocking. Specifically, it can include five-prevention interlocking and safety-oriented interlocking.

[0125] In a specific embodiment of the present invention, the first logic controller 31 is further used for:

[0126] After receiving the opening and closing instructions, it is determined whether the opening and closing instructions comply with the preset opening and closing rules. If yes, the various switch devices of the primary main circuit are controlled to act through the instruction execution unit. Otherwise, the ninth fault prompt information is output to the central system.

[0127] The second logic controller 32 is also used for:

[0128] After receiving the opening and closing instructions, it is determined whether the opening and closing instructions comply with the preset opening and closing rules. If so, the various switching devices of the primary main circuit are controlled by the instruction execution unit, otherwise the tenth fault prompt information is output to the central system.

[0129] In this implementation, in order to further avoid misoperation, in addition to hardware interlocking, the first logic controller 31 is also required to determine whether the opening and closing instructions meet the preset opening and closing rules after receiving the opening and closing instructions. If so, the instruction execution unit is used to control the actions of the various switch devices of the primary main circuit. The second logic controller 32 is similar.

[0130] Applying the technical solution provided in the embodiment of the present invention, considering that in the control equipment of automatic train over-phase, the cost of the electronic switch valve group is higher, while the cost of the control system is lower, and the reliability of the electronic switch valve group is higher, while the reliability of the control system is lower, therefore, the present application only sets up one set of primary system, that is, no redundancy is set for the electronic switch valve group, and the control system is set to be a control system with a redundant mechanism for controlling the function of automatic train over-phase, so that the solution of the present application can not only improve the reliability of the control equipment of the entire train automatic over-phase, but also reduce the implementation cost of the solution, and facilitate the promotion and application of the solution.

[0131] Corresponding to the above method embodiments, an embodiment of the present invention further provides a train power supply system, including the train automatic phase transition control device in any of the above embodiments, which can be referenced in correspondence with the above.

[0132] It should also be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the presence of other identical elements in the process, method, article or device including the elements.

[0133] Professionals may further realize that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, computer software or a combination of the two. In order to clearly illustrate the interchangeability of hardware and software, the composition and steps of each example have been generally described in the above description according to the function. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of the present invention. Specific examples are used herein to illustrate the principles and implementation methods of the present invention, and the description of the above embodiments is only used to help understand the technical solution and its core idea of ​​the present invention. It should be pointed out that for ordinary technicians in the technical field, without departing from the principle of the present invention, the present invention can also be improved and modified in a number of ways, and these improvements and modifications also fall within the scope of protection of the claims of the present invention.

Claims

1. A control device for automatic train phase transition, characterized in that: include: A voltage and current detection circuit for detecting the voltage of a primary main circuit and the current of a primary main circuit; A train position detection system for sending a train position signal; A control system for controlling the electronic switch valve group to realize automatic train over-phase according to the train position signal, the voltage of the primary main circuit and the current of the primary main circuit, and having a redundant mechanism for controlling the automatic train over-phase function; The electronic switch valve group; The control system comprises: The first logic controller is used to determine the master-slave relationship between the first valve group controller and the second valve group controller according to the master-slave setting rule; generate a corresponding first valve group control instruction according to the train position signal, and send it to the first valve group controller and the second valve group controller; The second logic controller is used to determine the master-slave relationship between the first valve group controller and the second valve group controller according to the master-slave setting rule; generate a corresponding second valve group control instruction according to the train position signal, and send it to the first valve group controller and the second valve group controller; The first valve group controller is used for generating a corresponding optical control signal according to the voltage of the primary main circuit, the current of the primary main circuit, the first valve group control instruction and the second valve group control instruction and sending the corresponding optical control signal to the optical signal distribution unit when the received first valve group control instruction is consistent with the second valve group control instruction and the first valve group controller is the main valve group controller, so as to control the electronic switch valve group through the optical signal distribution unit to realize automatic phase separation of the train; The second valve group controller is used for generating a corresponding optical control signal according to the voltage of the primary main circuit, the current of the primary main circuit, the first valve group control instruction and the second valve group control instruction and sending the corresponding optical control signal to the optical signal distribution unit when the received first valve group control instruction is consistent with the second valve group control instruction and the second valve group control instruction is the main valve group controller, so as to control the electronic switch valve group through the optical signal distribution unit to realize automatic phase separation of the train; The optical signal distribution unit is respectively connected to the first valve group controller, the second valve group controller and the electronic switch valve group.

2. The train automatic phase-by-phase control device according to claim 1, characterized in that: The optical signal distribution unit is also used to obtain the state of the electronic switch valve group and send a state feedback signal to the first valve group controller and the second valve group controller; The first valve group controller is further used for: when the first valve group controller is the main valve group controller, verifying whether the electronic switch valve group is successfully controlled based on the state feedback signal, and if not, outputting first fault prompt information to the central system; The second valve group controller is also used for: when the second valve group controller is the main valve group controller, verifying whether the electronic switch valve group is successfully controlled based on the state feedback signal, and if not, outputting a first fault prompt information to the central system.

3. The train automatic phase-by-phase control device according to claim 1, characterized in that: The first logic controller determines the master-slave relationship between the first valve group controller and the second valve group controller according to the master-slave setting rule, including: After the first logic controller confirms that the primary main circuit is ready, it detects the fault status of the first valve group controller and the second valve group controller; When the second valve group controller fails and the first valve group controller is normal, or when both the first valve group controller and the second valve group controller are normal, a first designated instruction is sent to the first valve group controller and the second valve group controller, so that the first valve group controller serves as the main valve group controller and the second valve group controller serves as the standby valve group controller; When the first valve group controller fails and the second valve group controller is normal, a second designated instruction is sent to the first valve group controller and the second valve group controller, so that the second valve group controller serves as the main valve group controller and the first valve group controller serves as the standby valve group controller; When both the first valve group controller and the second valve group controller fail, second fault prompt information is output to the central system.

4. The train automatic phase-by-phase control device according to claim 3, characterized in that: The second logic controller determines the master-slave relationship between the first valve group controller and the second valve group controller according to the master-slave setting rule, including: After the second logic controller confirms that the primary main circuit is ready, it detects the fault status of the first valve group controller and the second valve group controller; When the second valve group controller fails and the first valve group controller is normal, or when both the first valve group controller and the second valve group controller are normal, a first designated instruction is sent to the first valve group controller and the second valve group controller, so that the first valve group controller serves as the main valve group controller and the second valve group controller serves as the standby valve group controller; When the first valve group controller fails and the second valve group controller is normal, a second designated instruction is sent to the first valve group controller and the second valve group controller, so that the second valve group controller serves as the main valve group controller and the first valve group controller serves as the standby valve group controller; When both the first valve group controller and the second valve group controller fail, second fault prompt information is output to the central system.

5. The train automatic phase-by-phase control device according to claim 4, characterized in that: The first valve group controller is also used for: When the first designated instruction sent by the first logic controller and the first designated instruction sent by the second logic controller are received at the same time and the two are inconsistent, outputting third fault prompt information to the central system; When the second designated instruction sent by the first logic controller and the second designated instruction sent by the second logic controller are received at the same time and the two are inconsistent, outputting fourth fault prompt information to the central system; The second valve group controller is also used for: When the first designated instruction sent by the first logic controller and the first designated instruction sent by the second logic controller are received at the same time and the two are inconsistent, outputting fifth fault prompt information to the central system; When the second designated instruction sent by the first logic controller and the second designated instruction sent by the second logic controller are received at the same time and the two are inconsistent, the sixth fault prompt information is output to the central system.

6. The train automatic phase-by-phase control device according to claim 4, characterized in that: Also includes an instruction execution unit; The first logic controller confirms that the primary circuit is ready, including: The first logic controller detects whether each switch device of the primary main circuit is in a normal state; If not, outputting the seventh fault prompt information to the central system; If yes, after receiving the opening and closing command, the command execution unit controls the actions of the various switch devices of the primary main circuit, and after determining that the actions of the various switch devices of the primary main circuit are completed, confirms that the primary main circuit is ready; The second logic controller confirms that the primary main circuit is ready, including: The second logic controller detects whether each switch device of the primary main circuit is in a normal state; If not, outputting an eighth fault prompt message to the central system; If yes, after receiving the opening and closing command, the command execution unit controls the actions of the various switch devices of the primary main circuit, and after determining that the actions of the various switch devices of the primary main circuit are completed, it is confirmed that the primary main circuit is ready.

7. The train automatic phase-by-phase control device according to claim 6, characterized in that: The instruction execution unit is specifically used for: When controlling the actions of the various switch devices of the primary main circuit, the actions of the various switch devices of the primary main circuit are controlled based on a hardware interlocking method.

8. The train automatic phase-by-phase control device according to claim 6, characterized in that: The first logic controller is also used for: After receiving the opening and closing instruction, determine whether the opening and closing instruction complies with the preset opening and closing rules, if yes, control the actions of the various switch devices of the primary main circuit through the instruction execution unit, otherwise output the ninth fault prompt information to the central system; The second logic controller is also used for: After receiving the opening and closing instructions, it is determined whether the opening and closing instructions comply with the preset opening and closing rules. If so, the various switching devices of the primary main circuit are controlled by the instruction execution unit. Otherwise, the tenth fault prompt information is output to the central system.

9. A train power supply system, characterized in that: It comprises the control device for automatic train phase transition as claimed in any one of claims 1 to 8.

Citation Information

Patent Citations

  • Electronic ground automatic neutral section passing device

    CN105799553A

  • Ground automatic no-power section passing device for zoning station and control method thereof

    CN109835213A

  • Ground automatic neutral section passing device with redundancy function and control method

    CN110091757A

  • Switching state detecting circuit, over phase splitting device, detecting method and control method

    CN110095712A

  • Redundancy control system

    CN110095975A