A bridge alignment control method for steel-concrete composite beam construction
By combining the bridge design coordinates, cumulative construction deformation values and pre-camber of the finished bridge to form a prefabricated line, and setting up the bracket structure on site and calculating the bracket top elevation, the problem of line shape control of the steel-concrete composite beam bridge was solved, and precise control and construction were achieved. Satisfaction of needs.
Patent Information
- Application Number
- CN202111419155.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-11-26
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2041-11-26
AI Technical Summary
The existing technology makes it difficult to effectively control the bridge alignment during factory prefabrication and on-site installation of steel-concrete composite beams, resulting in construction difficulties.
The prefabricated alignment is formed by combining the bridge design coordinates, cumulative construction deformation values and the pre-camber of the completed bridge. The support structure is set up on site to assist construction and the top elevation of the support is calculated to control the final bridge alignment.
It achieves precise control of the bridge alignment of steel-concrete composite beams, with the error controlled within 2mm, meeting construction needs.
Smart Images

Figure CN114169050B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of bridge engineering construction, and proposes a control method for the final bridge line shape of a simply supported steel-concrete composite beam during factory prefabrication and on-site installation. Background Art
[0002] At present, with the continuous development of bridge engineering construction, in the context of the unstoppable development of prefabrication and assembly technology, steel structure beams are gradually replacing reinforced concrete structure beams. With its advantages of lightweight and standardized construction, it plays a vital role in important bridge node positions, such as curved ramps and large-span bridge spans. Steel structure beams and conventional reinforced concrete beams have the same difficulty in controlling the line shape of the completed bridge. At present, the control method for the line shape of the completed bridge of steel structures such as steel-concrete composite beams during factory prefabrication and on-site installation is not perfect. Therefore, it is necessary to comprehensively consider various factors and then produce a line shape control method to meet construction needs. Summary of the invention
[0003] The purpose of the present invention is to design a bridge line shape control method for steel-concrete composite beam construction, so as to solve the problem of difficult bridge line shape control during the steel-concrete composite beam construction process.
[0004] The present invention solves the above technical problems through the following technical solutions:
[0005] The present invention provides a bridge line control method for steel-concrete composite beam construction, which is characterized in that it comprises the following steps:
[0006] Step 1: Factory prefabrication control: Taking the design coordinates of the bridge as the benchmark, taking into account the cumulative deformation value of the construction and the pre-camber of the completed bridge, the two are combined to form a prefabrication line type, that is, prefabrication line type = design coordinates + cumulative deformation value of construction + pre-camber of the completed bridge, and prefabrication is completed;
[0007] Step 2: On-site installation control: Since the construction of steel-concrete composite beams needs to be carried out in sections, the support structure is set to assist the construction. During the construction period, the factor affecting the line shape is the top elevation of the support;
[0008] The top elevation of the bracket is calculated according to the following formula:
[0009] The top elevation of the support = the designed bottom elevation + the pre-camber of the completed bridge + the correction value;
[0010] By controlling the design top elevation of the support, after the segmented structure welding is completed and the support is removed, the final bridge line shape can meet the construction design requirements.
[0011] Preferably, in step 1, the design coordinates are: the bottom elevation of the steel beam in the steel-concrete composite beam calculated according to the vertical curve of the road;
[0012] Cumulative deformation value of construction: includes the structural deformation value caused by self-weight and other loads during the construction stage, which is used to offset during the construction process;
[0013] Pre-camber of completed bridge: The pre-camber value obtained by calculation that will be gradually offset within 3 to 10 years after the bridge is completed, given by the design.
[0014] Preferably, in step 2, the bottom elevation is designed as follows: the elevation of the bottom support point of the steel beam calculated according to the vertical curve of the road;
[0015] Pre-camber of completed bridge: the pre-camber value gradually offset within 3 to 10 years after the completion of the bridge, obtained by calculation and given by the design;
[0016] Correction value: factory processing arch value + on-site support compression deformation value + foundation settlement value;
[0017] Among them, the factory processing arch value is the displacement of the center position of the bridge span after loading according to the deadweight load;
[0018] On-site support compression deformation value: The deformation value of the support under the load of the steel beam is calculated through modeling;
[0019] Foundation settlement value: the deformation value of the foundation under the load of the support and steel beam is obtained through modeling.
[0020] On the basis of being in accordance with the common sense in the art, the above-mentioned preferred conditions can be arbitrarily combined to obtain the preferred embodiments of the present invention.
[0021] The positive and progressive effects of the present invention are:
[0022] The present invention can accurately control the final bridge line shape of the steel-concrete composite beam through factory prefabrication control and on-site installation control, thereby meeting the construction requirements. Through the analysis of the prefabricated line shape and the top elevation of the bracket setting, the influencing factors such as pre-camber, bracket, foundation, etc. are explained in turn to form a calculation formula, and then a control method is formed, which can ultimately ensure that the error of the bridge line shape is controlled within 2mm. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 The present invention is a flowchart of a bridge alignment control method for steel-concrete composite beam construction according to a preferred embodiment of the present invention. DETAILED DESCRIPTION
[0024] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.
[0025] like Figure 1 As shown, this embodiment provides a bridge line control method for steel-concrete composite beam construction, which includes the following steps:
[0026] Step 1: Factory prefabrication control: mainly control the prefabrication line type.
[0027] Taking the design coordinates of the bridge as the benchmark, and considering the cumulative deformation value of the construction and the pre-arch of the completed bridge, the two are combined to form a prefabricated line type, that is, prefabricated line type = design coordinates + cumulative deformation value of the construction + pre-arch of the completed bridge, and the prefabrication is completed.
[0028] Among them, the design coordinates are: the bottom elevation of the steel beam in the steel-concrete composite beam calculated based on the vertical curve of the road.
[0029] Cumulative construction deformation value: includes the structural deformation value caused by self-weight and other loads during the construction phase, which is used to offset during the construction process.
[0030] Pre-camber of completed bridge: The pre-camber value obtained by calculation that will be gradually offset within 3 to 10 years after the bridge is completed, given by the design.
[0031] Step 2: On-site installation control: mainly control the top elevation of the bracket.
[0032] Since the construction of steel-concrete composite beams needs to be carried out in sections, the support structure is set to assist the construction. The factor affecting the line shape during construction is the top elevation of the support. The top elevation of the support is calculated according to the following formula:
[0033] The top elevation of the support = the designed bottom elevation + the pre-camber of the completed bridge + the correction value;
[0034] By controlling the design top elevation of the support, after the segmented structure welding is completed and the support is removed, the final bridge line shape can meet the construction design requirements.
[0035] Among them, the design bottom elevation: the elevation at the bottom support point of the steel beam calculated based on the vertical curve of the road.
[0036] Pre-camber of completed bridge: The pre-camber value obtained by calculation that will be gradually offset within 3 to 10 years after the bridge is completed, given by the design.
[0037] Correction value: factory processing arch value + on-site support compression deformation value + foundation settlement value.
[0038] Among them, the factory processed arch value is generally the displacement of the center position of the bridge span after loading with self-weight load.
[0039] On-site support compression deformation value: The deformation value of the support under the action of steel beam load is calculated through modeling.
[0040] Foundation settlement value: the deformation value of the foundation under the load of the support and steel beam is obtained through modeling.
[0041] The advantage of the present invention is that it can accurately control the final bridge line shape of the steel-concrete composite beam through factory prefabrication control and on-site installation control, thereby meeting the construction requirements. Through the analysis of the prefabricated line shape and the top elevation of the bracket setting, the influencing factors such as pre-camber, bracket, foundation, etc. are explained in turn to form a calculation formula, and then a control method is formed to ensure the bridge line shape.
[0042] Although the specific embodiments of the present invention are described above, those skilled in the art should understand that these are only examples, and the protection scope of the present invention is defined by the appended claims. Those skilled in the art may make various changes or modifications to these embodiments without departing from the principles and essence of the present invention, but these changes and modifications all fall within the protection scope of the present invention.
Claims
1. A bridge line control method for steel-concrete composite beam construction, characterized in that: It includes the following steps: Step 1: Factory prefabrication control: Taking the design coordinates of the bridge as the benchmark, taking into account the cumulative deformation value of the construction and the pre-camber of the completed bridge, the two are combined to form a prefabrication line type, that is, prefabrication line type = design coordinates + cumulative deformation value of construction + pre-camber of the completed bridge, and prefabrication is completed; Step 2: On-site installation control: Since the construction of steel-concrete composite beams needs to be carried out in sections, the support structure is set to assist the construction. During the construction period, the factor affecting the line shape is the top elevation of the support; The top elevation of the bracket is calculated according to the following formula: The top elevation of the support = the designed bottom elevation + the pre-camber of the completed bridge + the correction value; By controlling the top elevation of the support design, after the segmented structure is welded and the support is removed, the final bridge line shape can meet the construction design requirements; In step 1, design coordinates: the bottom elevation of the steel beam in the steel-concrete composite beam calculated according to the vertical curve of the road; Cumulative deformation value of construction: includes the structural deformation value caused by self-weight and other loads during the construction stage, which is used to offset during the construction process; Pre-camber of completed bridge: the pre-camber value gradually offset within 3 to 10 years after the completion of the bridge, obtained by calculation and given by the design; In step 2, the bottom elevation is designed: the elevation of the bottom support point of the steel beam calculated according to the vertical curve of the road; Pre-camber of completed bridge: the pre-camber value gradually offset within 3 to 10 years after the completion of the bridge, obtained by calculation and given by the design; Correction value: factory processing arch value + on-site support compression deformation value + foundation settlement value; Among them, the factory processing arch value is the displacement of the center position of the bridge span after loading according to the deadweight load; On-site support compression deformation value: The deformation value of the support under the load of the steel beam is calculated through modeling; Foundation settlement value: the deformation value of the foundation under the load of the support and steel beam is obtained through modeling.
Citation Information
Patent Citations
Three-dimensional numerical control method for bridge section precasting technology
CN101942805A
Continuous beam short line matching prefabricated cantilever assembly linear control method
CN110904846A
Cited By
Pre-cambering construction method for long-span steel reinforced concrete beam based on multi-point curve fitting
CN123027954A