A water conservancy safety monitoring system and method based on big data

Through a water conservancy safety monitoring system based on big data, water flow information can be monitored and analyzed in real time, seepage threats are identified and early warning signals are generated, which solves the problem that existing systems cannot effectively monitor seepage threats, and improves the safety and monitoring efficiency of water conservancy projects.

CN114298549BActive Publication Date: 2024-11-19ANHUI JINHE SOFTWARE CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202111630151.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-12-28
Publication Date
2024-11-19
Estimated Expiration
2041-12-28

AI Technical Summary

Technical Problem

The existing water conservancy safety monitoring system cannot intelligently identify engineering areas with high seepage threats, resulting in the inability to effectively improve the efficiency of water conservancy safety monitoring and increase the risk of accidents.

Method used

Adopt a water conservancy safety monitoring system based on big data, and through monitoring nodes, monitoring centers, security analysis modules, databases and threat assessment modules, water flow information is monitored in real time, deviation coefficients and seepage threat coefficients are calculated, early warning signals are generated, maintenance tasks are assigned, and collection is adjusted. Frequency focuses on monitoring of high-threat areas.

Benefits of technology

Effectively avoid water conservancy engineering accidents, improve the safety of water conservancy engineering, and improve the efficiency of water conservancy safety monitoring by intelligently identifying areas with high seepage threats.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114298549B_ABST
    Figure CN114298549B_ABST
Patent Text Reader

Abstract

The invention discloses a water conservancy safety monitoring system and method based on big data, which relates to the field of water conservancy safety technology, including monitoring nodes, a monitoring center, a safety analysis module and a threat assessment module; the monitoring node is used to monitor the water flow information of seepage at specific locations in various areas of a water conservancy project, and send it to the monitoring center; the monitoring center is used to preprocess the current water flow information, and transmit the preprocessed water flow information to the safety analysis module for safety analysis, determine the safety status of seepage at various locations according to the deviation coefficient, and timely warn and assign corresponding engineering personnel to perform maintenance and reinforcement, so as to improve the safety of the water conservancy project; the threat assessment module is used to analyze the seepage threat coefficient of the seepage maintenance information with timestamps stored in the database, and determine the corresponding information collection instructions according to the seepage threat coefficient, and adjust the collection frequency, so as to focus on monitoring the engineering areas with high seepage threats, and improve the efficiency of water conservancy safety monitoring.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of water conservancy safety technology, and in particular to a water conservancy safety monitoring system and method based on big data. Background Art

[0002] After a dam or water structure blocks water, seepage occurs due to the water level difference, causing part of the water to seep into the dam body and foundation, forming a seepage field in its foundation, leading to soil flow, pipe bursts or landslides. Data show that most water conservancy project accidents (especially dam accidents) are caused by seepage. Therefore, it is very important to monitor the seepage status of water conservancy projects. However, the existing water conservancy safety monitoring system cannot intelligently identify the project areas with high seepage threats for key monitoring and improve the efficiency of water conservancy safety monitoring. To this end, we propose a water conservancy safety monitoring system and method based on big data. Summary of the invention

[0003] The present invention aims to solve at least one of the technical problems existing in the prior art. To this end, the present invention proposes a water conservancy safety monitoring system and method based on big data.

[0004] To achieve the above-mentioned purpose, according to an embodiment of the first aspect of the present invention, a water conservancy safety monitoring system based on big data is proposed, including a monitoring node, a monitoring center, a safety analysis module, a database and a threat assessment module;

[0005] The monitoring nodes are used to monitor the water flow information of the seepage at specific locations in each area of ​​the water conservancy project, and send the monitored current water flow information to the monitoring center;

[0006] The monitoring center is used to pre-process the current water flow information, and transmit the pre-processed water flow information to the safety analysis module for safety analysis, and determine the safety status of seepage at each position according to the deviation coefficient PC; specifically:

[0007] Acquire the water conservancy project area corresponding to the water flow information, and determine the corresponding information collection instruction according to the seepage threat coefficient WX of the water conservancy project area, wherein the information collection instruction includes a collection frequency threshold;

[0008] In response to the corresponding information collection instruction, water flow information is collected; the latest collected water flow information is XLn, and if XLn≥water flow threshold, it is determined that there is a seepage threat and an early warning signal is generated;

[0009] If XLn is less than the water flow threshold, the difference between XLn and the water flow threshold is marked as C1, and the current moment is used as the standard to obtain the four groups of deviation values ​​before the current moment to obtain the difference ratio CX; the deviation coefficient PC of the current water flow information is calculated using the formula PC = (CX×g1) / (C1×g2), where g1 and g2 are coefficient factors; if PC is greater than the deviation threshold, it is determined that there is a seepage threat and an early warning signal is generated;

[0010] The safety analysis module is used to upload the early warning signal to the controller. The controller controls the alarm module to issue an alarm after receiving the early warning signal, and obtains the corresponding regional location to generate a seepage maintenance task and upload it to the monitoring center. After receiving the seepage maintenance task, the monitoring center assigns corresponding engineering personnel to perform maintenance and reinforcement.

[0011] Furthermore, the method for obtaining the deviation value is:

[0012] If XLn is less than the water flow threshold, take the values ​​of the water flow information of XLn and X1 groups before XLn to obtain the interval water flow information group, where X1 is the preset value; calculate the standard deviation μ of the interval water flow information group according to the standard deviation calculation formula; use the formula The deviation value W of the water flow information is calculated; wherein A1 and A2 are preset compensation coefficients; each time a new actual water flow information data is obtained, a new deviation value W is automatically calculated to obtain a deviation value group.

[0013] Furthermore, the calculation method of the difference ratio CX is: obtain the difference between the maximum value and the minimum value in the four groups of deviation values, and divide the difference by the minimum value to obtain the difference ratio CX.

[0014] Furthermore, the database stores a mapping relationship table between seepage threat coefficients and acquisition frequency thresholds, wherein each acquisition frequency threshold corresponds to a preset seepage threat coefficient range.

[0015] Furthermore, after the engineering personnel complete the maintenance, they record the seepage maintenance information and transfer the seepage maintenance information to the database for storage with a timestamp, wherein the seepage maintenance information includes the start time of the maintenance, the end time of the maintenance, the maintenance level and the corresponding project area. The maintenance level is evaluated by the engineering personnel based on the human and material resources invested in the maintenance and reinforcement process.

[0016] Furthermore, the threat assessment module is used to analyze the seepage threat coefficient of the seepage maintenance information with timestamps stored in the database. The specific analysis method is:

[0017] Collect the seepage maintenance information of the same engineering area within the preset time; count the number of maintenance and reinforcement of the corresponding engineering area as G1; mark the maintenance duration of each maintenance as T1, mark the corresponding maintenance level as D1, and use the formula GX=T1×d1+D1×d2 to calculate the maintenance value GX, where d1 and d2 are coefficient factors;

[0018] The number of times GX is greater than the maintenance threshold is counted as P1; when GX is greater than the maintenance threshold, the difference between GX and the maintenance threshold is obtained and summed to obtain the total over-inspection value GZ; the over-inspection coefficient CJ is calculated using the formula CJ=P1×a3+GZ×a4, where a3 and a4 are both proportional factors;

[0019] The buffer time HT is calculated by calculating the time difference between the last maintenance end time and the current system time. The seepage threat coefficient WX of the corresponding project area is calculated using the formula WX=(G1×d3+CJ×d4)×HT, where d3 and d4 are coefficient factors;

[0020] The threat assessment module is used to time-stamp the seepage threat coefficient WX of each engineering area and store it in the storage module.

[0021] Furthermore, the monitoring nodes are ZigBee wireless sensor network nodes with hydroacoustic sensors, which are distributed in arrays in various areas of the water conservancy project; the preprocessing is performed by eliminating obviously erroneous or useless data; and the water flow information includes water flow information.

[0022] Furthermore, a water conservancy safety monitoring method based on big data is applied to a water conservancy safety monitoring system, comprising the following steps:

[0023] Step 1: The monitoring node is used to monitor the water flow information of the seepage at specific locations in each area of ​​the water conservancy project, and send the monitored current water flow information to the monitoring center;

[0024] Step 2: The monitoring center is used to pre-process the current water flow information and transmit the pre-processed water flow information to the safety analysis module for safety analysis, and determine the safety status of seepage at each location based on the deviation coefficient PC of the current water flow information;

[0025] Step 3: If PC is greater than the deviation threshold, it is determined that there is a seepage threat and a warning signal is generated; the controller receives the warning signal to control the alarm module to issue an alarm, and obtains the corresponding regional location to generate a seepage maintenance task and upload it to the monitoring center;

[0026] Step 4: After receiving the seepage maintenance task, the monitoring center assigns the corresponding engineering personnel to carry out maintenance and reinforcement; after the engineering personnel complete the maintenance, they record the seepage maintenance information and transfer the seepage maintenance information to the database with a timestamp for storage;

[0027] Step 5: Use the threat assessment module to analyze the seepage threat coefficient of the seepage maintenance information with timestamps stored in the database, and upload the seepage threat coefficient WX of each project area to the monitoring center for real-time display.

[0028] Compared with the prior art, the present invention has the following beneficial effects:

[0029] 1. The safety analysis module in the present invention is used to perform safety analysis on the monitored water flow information, and the latest collected water flow information is XLn. If XLn≥water flow threshold, it is determined that there is a seepage threat and a warning signal is generated; otherwise, the difference between the water flow information XLn at the current moment and the water flow threshold is marked as C1, and the current moment is used as the standard to obtain the four groups of deviation values ​​before the current moment to obtain the difference ratio CX; the deviation coefficient PC of the current water flow information is calculated using the formula PC=(CX×g1) / (C1×g2), and if PC is greater than the deviation threshold, it is determined that there is a seepage threat and a warning signal is generated; the controller receives the warning signal to control the alarm module to issue an alarm, and obtains the corresponding regional position to generate a seepage maintenance task and upload it to the monitoring center. After receiving the seepage maintenance task, the monitoring center assigns the corresponding engineering personnel to perform maintenance and reinforcement, effectively avoiding water conservancy project accidents and improving the safety of water conservancy projects;

[0030] 2. The threat assessment module described in the present invention is used to analyze the seepage threat coefficient of the seepage maintenance information with timestamps stored in the database, and collect the seepage maintenance information of the same engineering area within a preset time; count the number of maintenance and reinforcement times, over-inspection coefficients and buffer time of the corresponding engineering area, and calculate the seepage threat coefficient WX of the corresponding engineering area; determine the corresponding information collection instructions according to the seepage threat coefficient WX of each water conservancy engineering area, and adjust the collection frequency, so as to focus on monitoring the engineering areas with high seepage threats and improve the efficiency of water conservancy safety monitoring. BRIEF DESCRIPTION OF THE DRAWINGS

[0031] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0032] Figure 1 This is a system block diagram of a water conservancy safety monitoring system based on big data in the present invention.

[0033] Figure 2 It is a schematic diagram of the flow of a water conservancy safety monitoring method based on big data of the present invention. DETAILED DESCRIPTION

[0034] The technical solution of the present invention will be clearly and completely described below in conjunction with the embodiments. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0035] like Figure 1 to Figure 2 As shown, a water conservancy safety monitoring system based on big data includes a monitoring node, a monitoring center, a safety analysis module, a controller, an alarm module, a storage module, a database and a threat assessment module;

[0036] The monitoring nodes are ZigBee wireless sensor network nodes with hydroacoustic sensors, which are distributed in arrays in various areas of the water conservancy project. The monitoring nodes are connected to the monitoring center in a distributed manner through the Internet of Things nodes. The hydroacoustic sensors are all equipped with location identifiers.

[0037] In this embodiment, the hydroacoustic sensor is a sensor for receiving and detecting sound waves propagating in water, generally composed of a voltage sensor and related electronic circuits, enclosed in a waterproof and airtight container, and can be placed in the seepage water flow; the hydroacoustic sensor drifts in the seepage flow, and transmits the seepage water flow information to the monitoring center via the Internet of Things node; the hydroacoustic sensor uses a detection series 28kHz hydroacoustic sensor, that is, a horizontal non-directional cylindrical hydroacoustic sensor;

[0038] In this embodiment, a wireless sensor network is used to monitor the seepage in real time in a large-scale water conservancy project, which saves the need to lay a large number of wires, saves costs, and reduces construction difficulty; and the monitoring nodes of the wireless sensor network have a simple structure, small size, and low cost, and do not require personnel to regularly patrol and check the seepage, saving a lot of manpower costs;

[0039] The monitoring node is used to monitor the water flow information of the seepage at specific locations in each area of ​​the water conservancy project, and send the monitored current water flow information to the monitoring center; the monitoring center is used to pre-process the current water flow information, and transmit the pre-processed water flow information to the safety analysis module for safety analysis to determine the safety status of the seepage at each location; the pre-processing is performed by eliminating obviously erroneous or useless data; the water flow information includes water flow information;

[0040] The specific analysis steps of the security analysis module are as follows:

[0041] The water conservancy project area corresponding to the water flow information is obtained, and the corresponding information collection instruction is determined according to the seepage threat coefficient of the water conservancy project area, and the information collection instruction includes a collection frequency threshold; specifically: a database stores a mapping relationship table between the seepage threat coefficient and the collection frequency threshold, wherein each collection frequency threshold corresponds to a preset seepage threat coefficient range; wherein the larger the seepage threat coefficient, the higher the collection frequency threshold;

[0042] In response to the corresponding information collection instruction, water flow information is collected; the latest collected water flow information is XLn, and if XLn≥water flow threshold, it is determined that there is a seepage threat and an early warning signal is generated;

[0043] If XLn is less than the water flow threshold, the values ​​of the water flow information of XLn and X1 groups before XLn are taken to obtain the interval water flow information group, where X1 is a preset value; the standard deviation μ of the interval water flow information group is calculated according to the standard deviation calculation formula;

[0044] According to the standard deviation μ and the interval water flow information group, the deviation value W of the water flow information is obtained. The specific calculation method is:

[0045] When n≤X1, the value of X1 is automatically reset to make X1=n-1;

[0046] When n>X1, using the formula The deviation value W of the water flow information is calculated; wherein A1 and A2 are preset compensation coefficients; each time a new actual water flow information data is obtained, a new deviation value W is automatically calculated to obtain a deviation value group;

[0047] The difference between the water flow information XLn at the current moment and the water flow threshold is marked as C1, where C1 takes a positive value; taking the current moment as the standard, obtaining the four groups of deviation values ​​before the current moment, calculating the difference between the maximum value and the minimum value of the four groups of deviation values, and dividing the difference by the minimum value to obtain the difference ratio CX;

[0048] The deviation coefficient PC of the current water flow information is calculated using the formula PC = (CX × g1) / (C1 × g2), where g1 and g2 are coefficient factors;

[0049] Compare the deviation coefficient PC with the deviation threshold. If PC is greater than the deviation threshold, it is determined that there is a seepage threat and a warning signal is generated.

[0050] The safety analysis module is used to upload the early warning signal to the controller. After receiving the early warning signal, the controller controls the alarm module to issue an alarm, obtains the corresponding regional location, generates a seepage maintenance task and uploads it to the monitoring center. After receiving the seepage maintenance task, the monitoring center assigns the corresponding engineering personnel to carry out maintenance and reinforcement.

[0051] The present invention conducts progressive analysis on the collected water flow information, determines the corresponding information collection instructions according to the seepage threat coefficient of the water conservancy project area, and adjusts the collection frequency, so as to focus on monitoring the project area with high seepage threat, timely warn, effectively avoid water conservancy project accidents, and improve the safety of water conservancy projects;

[0052] After the maintenance is completed, the engineers record the seepage maintenance information and transfer it to the database with a timestamp for storage. The seepage maintenance information includes the start time of the maintenance, the end time of the maintenance, the maintenance level and the corresponding engineering area. The maintenance level is evaluated by the engineers according to the human and material resources invested in the maintenance and reinforcement process. The more human and material resources invested, the higher the maintenance level.

[0053] The threat assessment module is used to analyze the seepage threat coefficient of the seepage maintenance information with timestamps stored in the database. The specific analysis method is as follows:

[0054] Collect the seepage maintenance information of the same engineering area within the preset time; count the number of maintenance and reinforcement of the corresponding engineering area as G1; mark the maintenance duration of each maintenance as T1, mark the corresponding maintenance level as D1, and use the formula GX=T1×d1+D1×d2 to calculate the maintenance value GX, where d1 and d2 are coefficient factors;

[0055] Compare the maintenance value GX with the maintenance threshold, and count the number of times GX is greater than the maintenance threshold as P1; when GX is greater than the maintenance threshold, obtain the difference between GX and the maintenance threshold and sum them to get the total over-inspection value GZ; use the formula CJ=P1×a3+GZ×a4 to calculate the over-inspection coefficient CJ, where a3 and a4 are both proportional factors;

[0056] The buffer time HT is calculated by calculating the time difference between the last maintenance end time and the current system time. The maintenance reinforcement times, over-inspection coefficient and buffer time are normalized and their values ​​are taken. The seepage threat coefficient WX of the corresponding project area is calculated using the formula WX=(G1×d3+CJ×d4)×HT, where d3 and d4 are coefficient factors.

[0057] The threat assessment module is used to time-stamp the seepage threat coefficient WX of each engineering area and store it in the storage module.

[0058] A water conservancy safety monitoring method based on big data, applied to the above-mentioned water conservancy safety monitoring system, comprises the following steps:

[0059] Step 1: The monitoring node is used to monitor the water flow information of the seepage at specific locations in each area of ​​the water conservancy project, and send the monitored current water flow information to the monitoring center;

[0060] Step 2: The monitoring center is used to pre-process the current water flow information and transmit the pre-processed water flow information to the safety analysis module for safety analysis, and determine the safety status of seepage at each location based on the deviation coefficient PC of the current water flow information;

[0061] Step 3: If PC is greater than the deviation threshold, it is determined that there is a seepage threat and a warning signal is generated; the controller receives the warning signal and controls the alarm module to issue an alarm, and obtains the corresponding regional location to generate a seepage maintenance task and upload it to the monitoring center;

[0062] Step 4: After receiving the seepage maintenance task, the monitoring center assigns the corresponding engineering personnel to carry out maintenance and reinforcement. After the maintenance is completed, the engineering personnel record the seepage maintenance information and transfer the seepage maintenance information to the database with a timestamp for storage;

[0063] Step 5: Use the threat assessment module to analyze the seepage threat coefficient of the seepage maintenance information with timestamps stored in the database, and upload the seepage threat coefficient WX of each project area to the monitoring center for real-time display.

[0064] The above formulas are all calculated by removing dimensions and taking numerical values. The formula is a formula that is closest to the actual situation obtained by collecting a large amount of data and performing software simulation. The preset parameters and preset thresholds in the formula are set by technical personnel in this field according to actual conditions or obtained by simulating a large amount of data.

[0065] Working principle of the present invention:

[0066] A water conservancy safety monitoring system and method based on big data, when working, the monitoring node is used to monitor the water flow information of the seepage at the specific location of each area of ​​the water conservancy project; the monitoring center is used to preprocess the current water flow information, and transmit the preprocessed water flow information to the safety analysis module for safety analysis, and mark the difference between the water flow information XLn at the current moment and the water flow threshold as C1; take the current moment as the standard, obtain the four groups of deviation values ​​before the current moment, and obtain the difference ratio CX; use the formula PC=(CX×g1) / (C1×g2) to calculate the deviation coefficient PC of the current water flow information, if PC is greater than the deviation threshold, it is determined that there is a seepage threat, and generate an early warning signal; the controller receives the early warning signal to control the alarm module to issue an alarm, and obtains the corresponding regional location to generate a seepage maintenance task and upload it to the monitoring center, after receiving the seepage maintenance task, the monitoring center assigns the corresponding engineering personnel to perform maintenance and reinforcement;

[0067] After the engineering personnel complete the maintenance, the seepage maintenance information is recorded and the seepage maintenance information is timestamped and transmitted to the database for storage; the threat assessment module is used to analyze the seepage threat coefficient of the seepage maintenance information with timestamps stored in the database, and collect the seepage maintenance information of the same engineering area within the preset time; the number of maintenance and reinforcement times, over-inspection coefficient and buffer time of the corresponding engineering area are counted, and the seepage threat coefficient WX of the corresponding engineering area is calculated, and the seepage threat coefficient WX of each engineering area is timestamped and stored in the storage module, so as to intelligently identify the engineering areas with high seepage threats for key monitoring and improve the efficiency of water conservancy safety monitoring.

[0068] In the description of this specification, the description with reference to the terms "one embodiment", "example", "specific example", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.

[0069] The preferred embodiments of the present invention disclosed above are only used to help explain the present invention. The preferred embodiments do not describe all the details in detail, nor do they limit the invention to only specific implementation methods. Obviously, many modifications and changes can be made according to the content of this specification. This specification selects and specifically describes these embodiments in order to better explain the principles and practical applications of the present invention, so that those skilled in the art can understand and use the present invention well. The present invention is limited only by the claims and their full scope and equivalents.

Claims

1. A water conservancy safety monitoring system based on big data, characterized in that: Includes monitoring nodes, monitoring center, security analysis module, controller, database and threat assessment module; The monitoring nodes are used to monitor the water flow information of the seepage at specific locations in each area of ​​the water conservancy project, and send the monitored current water flow information to the monitoring center; The threat assessment module is used to analyze the seepage threat coefficient WX of the seepage maintenance information with timestamps stored in the database. The specific analysis method is as follows: Collect the seepage maintenance information of the same engineering area within the preset time; count the number of maintenance and reinforcement of the corresponding engineering area as G1; mark the maintenance duration of each maintenance as T1, mark the corresponding maintenance level as D1, and use the formula GX=T1×d1+D1×d2 to calculate the maintenance value GX, where d1 and d2 are coefficient factors; count the number of times GX is greater than the maintenance threshold as P1; When GX is greater than the maintenance threshold, the difference between GX and the maintenance threshold is obtained and summed to obtain the total over-inspection value GZ; the over-inspection coefficient CJ is calculated using the formula CJ=P1×a3+GZ×a4, where a3 and a4 are both proportional factors; The buffer time HT is calculated by calculating the time difference between the end time of the most recent maintenance and the current time of the system. The seepage threat coefficient WX of the corresponding project area is calculated using the formula WX=(G1×d3+CJ×d4)×HT, where d3 and d4 are coefficient factors; The threat assessment module is used to time-stamp the seepage threat coefficient WX of each engineering area and store it in the storage module; The monitoring center is used to pre-process the current water flow information, and transmit the pre-processed water flow information to the safety analysis module for safety analysis, and determine the safety status of seepage at each position according to the deviation coefficient PC; Specifically: The water conservancy project area corresponding to the water flow information is obtained, and the corresponding information collection instructions are determined according to the seepage threat coefficient WX of the water conservancy project area, specifically: The database stores a mapping relationship table between seepage threat coefficient and acquisition frequency threshold, wherein each acquisition frequency threshold corresponds to a preset seepage threat coefficient range; the information acquisition instruction includes the acquisition frequency threshold; In response to a corresponding information collection instruction, collecting water flow information; Let the latest collected water flow information be XLn. If XLn ≥ water flow threshold, it is determined that there is a seepage threat and an early warning signal is generated. If XLn is less than the water flow threshold, the difference between XLn and the water flow threshold is marked as C1, and the current moment is used as the standard to obtain the four groups of deviation values ​​before the current moment; the method for obtaining the deviation value is: If XLn is less than the water flow threshold, take the values ​​of the water flow information of XLn and X1 groups before XLn to obtain the interval water flow information group, where X1 is the preset value; calculate the standard deviation µ of the interval water flow information group according to the standard deviation calculation formula; use the formula The deviation value W of the water flow information is calculated; wherein A1 and A2 are preset compensation coefficients; Every time a new actual water flow information data is obtained, a new deviation value W is automatically calculated to obtain a deviation value group; the difference between the maximum value and the minimum value in the four groups of deviation values ​​is calculated, and the difference is divided by the minimum value to obtain a difference ratio CX; The deviation coefficient PC of the current water flow information is calculated using the formula PC=(CX×g1) / (C1×g2), where g1 and g2 are coefficient factors; if PC is greater than the deviation threshold, it is determined that there is a seepage threat and an early warning signal is generated; The safety analysis module is used to upload the early warning signal to the controller. The controller controls the alarm module to issue an alarm after receiving the early warning signal, and obtains the corresponding regional location to generate a seepage maintenance task and upload it to the monitoring center. After receiving the seepage maintenance task, the monitoring center assigns corresponding engineering personnel to perform maintenance and reinforcement.

2. A water conservancy safety monitoring system based on big data according to claim 1, characterized in that: After the engineering personnel complete the maintenance, the seepage maintenance information is recorded and the seepage maintenance information is timestamped and transmitted to the database for storage. The seepage maintenance information includes the start time of the maintenance, the end time of the maintenance, the maintenance level and the corresponding project area. The maintenance level is evaluated by the engineering personnel based on the human and material resources invested in the maintenance and reinforcement process.

3. The water conservancy safety monitoring system based on big data according to claim 1 is characterized in that: The monitoring nodes are ZigBee wireless sensor network nodes with hydroacoustic sensors, which are distributed in arrays in various areas of the water conservancy project; the preprocessing is performed by eliminating obviously erroneous or useless data; and the water flow information includes water flow information.

4. A water conservancy safety monitoring method based on big data, applied to a water conservancy safety monitoring system based on big data as described in any one of claims 1 to 3, characterized in that: The steps include: Step 1: The monitoring node is used to monitor the water flow information of the seepage at specific locations in each area of ​​the water conservancy project, and send the monitored current water flow information to the monitoring center; Step 2: The monitoring center is used to pre-process the current water flow information and transmit the pre-processed water flow information to the safety analysis module for safety analysis, and determine the safety status of seepage at each location based on the deviation coefficient PC of the current water flow information; Step 3: If PC is greater than the deviation threshold, it is determined that there is a seepage threat and a warning signal is generated; the controller receives the warning signal to control the alarm module to issue an alarm, and obtains the corresponding regional location to generate a seepage maintenance task and upload it to the monitoring center; Step 4: After receiving the seepage maintenance task, the monitoring center assigns the corresponding engineering personnel to carry out maintenance and reinforcement; after the engineering personnel complete the maintenance, they record the seepage maintenance information and transfer the seepage maintenance information to the database with a timestamp for storage; Step 5: Use the threat assessment module to analyze the seepage threat coefficient of the seepage maintenance information with timestamps stored in the database, and upload the seepage threat coefficient WX of each project area to the monitoring center for real-time display.