A data vectorization method and system for construction management information system

By changing the construction plan data structure into vector data and establishing associations, the problem of inconvenient data processing in the existing system is solved, automatic filling and safety inspection are realized, and the functional scalability and safety of the construction management system are improved.

CN114399260BActive Publication Date: 2024-12-06CRSC RESEARCH & DESIGN INSTITUTE GROUP CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202111450745.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-11-30
Publication Date
2024-12-06
Estimated Expiration
2041-11-30

AI Technical Summary

Technical Problem

The existing business line construction management system has textual content that cannot be effectively formatted in data processing, resulting in poor scalability of the information system, unable to achieve good linkage with the railway comprehensive scheduling system, and the construction plan data is separated, and the lack of vectorized attributes are caused. The plan submission and approval process is cumbersome.

Method used

Change the construction plan data structure from descriptive text to vector data, and establish the connection between construction location, road train requirements, speed limit information, etc. through the station area plan, and form vectorized construction plan data to achieve automatic filling and standardization. Check and conflict check functions.

Benefits of technology

It improves the computer recognition of construction plan data, realizes automatic filling, standardized inspection, error inspection and generation of orders, reduces the labor intensity of plan reviewers, and enhances the safety and card control attributes of the system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114399260B_ABST
    Figure CN114399260B_ABST
Patent Text Reader

Abstract

The present invention provides a data vectorization method and system for a construction management information system, which is applied to railway operating lines, wherein the method comprises the following steps: changing the construction plan data structure from a descriptive text to vector data; establishing associations between the operation items and driving conditions, the construction location and the road vehicle location, the construction location and the speed limit location, and the speed limit template in the construction plan vector data; expressing the vectorized construction location, road train demand, speed limit information, operation content, and impact range through the station interval plan and the associated construction plan vector data. After the present invention vectorizes the construction plan data, it has a higher computer recognition degree, and provides a data basis for realizing a series of functions such as automatic filling, standardization checking, error checking, conflict checking, automatic drawing, automatic generation of dispatch orders, and automatic and accurate generation of operation disclosure.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of rail transportation, and in particular relates to a data vectorization method and system for a construction management information system. Background Art

[0002] An operating line refers to an operating line in the railway transportation system. Line construction refers to the inspection, repair, maintenance, and renovation of related driving equipment and adjacent equipment along the railway. The particularity of operating line construction is that it is necessary to ensure that the daily train operation of the line is not greatly affected, and to complete the construction tasks of the operating line, ensure the health of the line, and ensure the safety of personnel during construction and eliminate safety hazards. Therefore, operating line construction usually requires the submission of construction plans in advance and layer-by-layer review. The content of the construction plan comes from the construction plan finalized during the bidding of the construction project. Therefore, some operating line construction systems on the market currently also incorporate the content of the construction plan for unified management.

[0003] There are many manufacturers of construction management systems for operating lines, and the product functions are relatively mature. The main business modules include construction plan management, monthly construction plan management, weekly maintenance plan management, construction or maintenance daily plan management, registration and cancellation management, and construction statistics. Among them, the monthly construction plan is the outline of the daily construction plan, which is submitted by the construction unit in advance on a monthly basis. The weekly maintenance plan is the outline of the daily maintenance plan, which is submitted by the equipment management unit in advance on a weekly basis. The registration and cancellation record is a record of the actual construction process at the station duty officer (YT46), which requires the construction unit to fill in and sign in person at the duty officer. Construction statistics are mainly used to assess the quality and efficiency of the actual construction and plan of the construction unit. In terms of business, the daily construction plan is inherited from the monthly construction plan, and the monthly construction plan is inherited from the construction plan. In terms of management requirements, the scope of construction should be gradually narrowed and refined when submitting the construction plan. However, the professional content involved in construction is complex. On the one hand, the information system only completes text entry and electronic work approval, which cannot well meet the linkage with other related modules of the railway integrated dispatching system. On the other hand, most of the existing systems are relatively closed, and the data in the three major modules of construction plan, monthly construction plan and daily plan are usually in a separated state. The functions are limited to the submission and approval functions similar to those of OA systems. The key information is not formatted, the scalability is weak, and the expansion function effect is not ideal. Most of the inheritance is manually controlled, and the inheritable information is also relatively limited, which makes it possible for plan submitters to fill in the content at will, and the plan approvers have a heavy workload of inspection and approval.

[0004] The existing construction systems on the market only accurately format time and location, and other content is mostly descriptive text and does not have vectorized properties. Summary of the invention

[0005] In view of the above problems, the present invention provides a data vectorization method and system for a construction management information system, which abstracts the textual construction plan content into specific content vectors and formats the data from the source to facilitate the realization of multiple extended functions.

[0006] The present invention provides a data vectorization method for a construction management information system, which is applied to a railway operating line and comprises the following steps: changing a construction plan data structure from a descriptive text to vector data; establishing associations between operation items and driving conditions, construction locations and road vehicle locations, construction locations and speed limit locations, and speed limit templates in the construction plan vector data; and expressing vectorized construction locations, road train requirements, speed limit information, operation content, and impact range through a station section plan and the associated construction plan vector data.

[0007] Furthermore, changing the construction plan data structure from descriptive text to vector data includes the following steps:

[0008] The text data of the construction location of the construction plan is defined as a discrete sequence consisting of station, field, section, equipment and its parts information and mileage information;

[0009] Modify the data structure of the planned road train information on the construction day, and change the running information text of the road train information to a sequence consisting of stations, yards, sections, equipment and stops;

[0010] The speed limit information text of the construction plan is defined as a set of three-dimensional vectors consisting of a speed limit position vector, a speed limit time, and a speed limit value;

[0011] Change the text of the daily construction plan work content to a discrete sequence of work items with accompanying workload.

[0012] Furthermore, associating the operation items and driving conditions, the construction location and the road vehicle location, the construction location and the speed limit location, and the speed limit template in the construction plan vector data includes the following steps:

[0013] According to the construction organization process of the construction project, the construction project data and the operation project data are separated into a disassembly relationship;

[0014] Based on the driving conditions affected by the operation project, mark the pairwise correspondence between all operation project data and all driving conditions;

[0015] When the construction plan road train information is initialized, the road train station and operation location are associated with the station and yard in the construction position vector;

[0016] When the construction plan road train information is initialized, the road train operation content is associated with the construction plan operation item vector;

[0017] When the construction plan speed limit information is initialized, the speed limit position vector is associated with the construction position vector;

[0018] When the construction plan speed limit information is initialized, the speed limit template in the driving conditions affected by the operation project is associated with the speed limit time and speed limit value in the construction plan speed limit information vector.

[0019] Furthermore, expressing the vectorized construction position includes the following steps:

[0020] Get each device identifier in the station, field, and device sequence;

[0021] Correspondingly associate each equipment identifier with the equipment graphic on the station area plan at the construction plan editing and review layer;

[0022] According to the sequence of the equipment unique identifier, the equipment sequence is selected through the equipment graphics of the station area plan, and the equipment sequence represents the construction location.

[0023] Furthermore, expressing the vectorized road train demand includes the following steps:

[0024] Get each equipment identifier of the equipment sequence of the station section plan;

[0025] Based on the equipment sequence, the graphics corresponding to the equipment are selected in sequence on the station section plan according to each equipment identifier in the equipment sequence, and the train path is selected through the graphics to express the running path of the construction road train on the station section plan;

[0026] According to the pre-filled information generated by the vectorized construction locations and vectorized work contents in the associated construction plan vector data, the entry of road train requirements is organized in a form.

[0027] Furthermore, expressing the vectored speed limit information includes the following steps:

[0028] Obtain speed limit vector data for construction plans;

[0029] In the speed limit editing position of the construction plan editing and review layer, the speed limit vector data is associated with the station area plan;

[0030] Add information expression symbols on the station map to display the speed limit period and speed limit value.

[0031] Further, expressing the vectorized job content and impact scope includes the following steps:

[0032] Express the work content as checking the work items broken down according to the construction project;

[0033] Obtaining a construction position vector and a speed limit position vector from the construction plan vector data;

[0034] Obtain the impact type and driving conditions of this construction plan based on the operation project;

[0035] The impact types are grouped and attached to the construction location and speed limit location to form an impact range vector sequence.

[0036] Furthermore, the pre-filled information includes the station to be ordered, the operation location, the operation mileage range and the operation content.

[0037] Furthermore, the method further comprises the following steps:

[0038] Express the action instruction data executed by the train dispatching system according to the vectorized construction position;

[0039] Convert the vectorized road train demand into route control start and end command data;

[0040] Associating the vectorized speed limit information with the speed limit representation of the train dispatching system;

[0041] Generate an impact range vector sequence based on the vectorized work content and construction location.

[0042] The present invention also provides a data vectorization system for a construction management information system, which is applied to a railway operating line, and comprises:

[0043] A vector data generation module, used to change the construction plan data structure from descriptive text to vector data;

[0044] The vector data association module is used to establish associations between the operation items in the construction plan vector data and the driving conditions, the construction location and the road vehicle location, the construction location and the speed limit location, and the speed limit template;

[0045] The vector data expression module is used to express the vectorized construction location, road train demand, speed limit information, operation content and impact range through the station section plan and the associated construction plan vector data.

[0046] Furthermore, the vector data generation module is specifically used for:

[0047] The text data of the construction location of the construction plan is defined as a discrete sequence consisting of station, field, section, equipment and its parts information and mileage information;

[0048] Modify the data structure of the planned road train information on the construction day, and change the running information text of the road train information to a sequence consisting of stations, yards, sections, equipment and stops;

[0049] The speed limit information text of the construction plan is defined as a set of three-dimensional vectors consisting of a speed limit position vector, a speed limit time, and a speed limit value;

[0050] Change the text of the daily construction plan work content to a discrete sequence of work items with accompanying workload.

[0051] Furthermore, the vector data association module is specifically used for:

[0052] According to the construction organization process of the construction project, the construction project data and the operation project data are separated into a disassembly relationship;

[0053] Based on the driving conditions affected by the operation project, mark the pairwise correspondence between all operation project data and all driving conditions;

[0054] When the construction plan road train information is initialized, the road train command station, operation location and the station and yard in the construction position vector are associated;

[0055] When the construction plan road train information is initialized, the road train operation content is associated with the construction plan operation item vector;

[0056] When the construction plan speed limit information is initialized, the speed limit position vector is associated with the construction position vector;

[0057] When the construction plan speed limit information is initialized, the speed limit template in the driving conditions affected by the operation project is associated with the speed limit time and speed limit value in the construction plan speed limit information vector.

[0058] Furthermore, the vector data expression module is specifically used for:

[0059] Express the action instruction data executed by the train dispatching system according to the vectorized construction position;

[0060] Convert the vectorized road train demand into route control start and end command data;

[0061] Associating the vectorized speed limit information with the speed limit representation of the train dispatching system;

[0062] Generate an impact range vector sequence based on the vectorized work content and construction location.

[0063] The beneficial effects of the present invention are as follows: after the present invention vectorizes the construction plan data, it has a higher computer recognition degree, and provides a data basis for realizing a series of functions such as automatic filling, standardization checking, error checking, conflict checking, automatic drawing, automatic generation of transfer orders, automatic and accurate generation of operation disclosure, etc. By filtering out the submission of erroneous plans through vectorized construction plan data, the security control attributes of the system are improved, and the labor intensity of plan reviewers is greatly reduced.

[0064] Other features and advantages of the present invention will be described in the following description, and partly become apparent from the description, or understood by practicing the present invention. The purpose and other advantages of the present invention can be realized and obtained by the structures pointed out in the description, claims and drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0065] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the following briefly introduces the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0066] Figure 1 A schematic flow chart of a data vectorization method for a construction management information system according to an embodiment of the present invention is shown;

[0067] Figure 2 A schematic diagram showing the association between a work item, a construction position vector and an automatically generated influence range according to an embodiment of the present invention is shown;

[0068] Figure 3 A schematic diagram showing a device sequence according to an embodiment of the present invention is shown;

[0069] Figure 4 It shows a schematic diagram of construction plan vector data flow according to an embodiment of the present invention;

[0070] Figure 5 A structural schematic diagram of a data vectorization system for a construction management information system according to an embodiment of the present invention is shown. DETAILED DESCRIPTION

[0071] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0072] In the existing business line construction management, the following requirements are placed on the business line construction management information system:

[0073] 1. Requires multi-level planning inheritance and scope control;

[0074] 2. The work content needs to be associated with the driving conditions, and card control is performed to automatically generate the impact range. The existing system construction plan work content is a manually filled descriptive text, which cannot be associated with the driving conditions, and thus cannot realize the function of constraint checking for incorrectly filled driving conditions;

[0075] 3. Detailed conflict check of construction plan is required. The existing system construction plan conflict check can only realize the grouping function of the same station and date plan, and cannot finely check the construction time, section station mileage, impact range, speed limit, power outage range, road vehicle safety range, etc.;

[0076] 4. Standardized templates for work content and workload are needed;

[0077] 5. A standardized template for road vehicle requirements is required;

[0078] 6. Slow down the requirements for standardized templates and automatic filling;

[0079] 7. Vectorized dispatch order templates are needed to accurately generate dispatch orders and run the command;

[0080] 8. The construction workload needs to be summarized and counted based on the real-time registration and cancellation records.

[0081] In view of the above-mentioned requirements of the construction management information system of the operating line, the present invention proposes the concept of construction plan vectorization and specific implementation strategies.

[0082] The embodiment of the present invention extracts the following common vectorizable information based on the existing business line construction management information system: construction plan, monthly construction plan, weekly maintenance plan, and daily construction plan:

[0083] 1. Construction location range;

[0084] 2. Assignment content and workload;

[0085] 3. Demand for road trains;

[0086] 4. Speed ​​limit information.

[0087] The embodiment of the present invention also summarizes the following rules after summarizing a large number of construction plan contents of the railway company:

[0088] 1. All construction plans have corresponding construction projects, and all construction projects are clearly listed in the construction management methods of the railway company;

[0089] 2. Every construction project and engineering project can be broken down into several orderly construction organization processes;

[0090] 3. Each operation item in the construction process has clear and quantifiable workload data when it is designed;

[0091] 4. The large machines and equipment involved in each operation and the driving organization conditions affected can be clearly identified;

[0092] 5. Each operation shall be subject to the specified operation process and the subsequent speed limit conditions shall be determined by the operation method;

[0093] 6. The railway company needs to regularly assess the work progress of the construction units. However, the assessment relies entirely on the outline data reported verbally by the construction units on a regular basis, which is not ideal.

[0094] Based on the above rules of vectorizable information and construction plan content, a data vectorization method for railway operating line construction management information system is proposed.

[0095] See also Figure 1 , Figure 1 A schematic flow chart of a data vectorization method for a construction management information system according to an embodiment of the present invention is shown.

[0096] A data vectorization method for a construction management information system is applied to a railway operating line, comprising the following steps: changing a construction plan data structure from a descriptive text to vector data; establishing associations between operation items and driving conditions, construction locations and road vehicle locations, construction locations and speed limit locations, and speed limit templates in the construction plan vector data; and expressing vectorized construction locations, road train requirements, speed limit information, operation content, and impact range through a station section plan and the associated construction plan vector data.

[0097] The embodiment of the present invention abstracts the textual construction plan content into specific content vectors, formats the data from the source, and facilitates the realization of multiple extended functions. After the construction plan is vectorized, the computer recognition is higher and the scalability is stronger.

[0098] The embodiment of the present invention quantifies all contents such as construction projects, operation contents and indicators, and the impact on relevant driving organization conditions into the basic data of the railway operating line construction management information system, thereby achieving effective linkage.

[0099] Specifically, changing the construction plan data structure from descriptive text to vector data includes the following steps:

[0100] S11. Define the text data of the construction location of the construction plan as a discrete sequence consisting of station, field, section, equipment and its various parts information and mileage information.

[0101] In this step, stations, yards, sections, and equipment are considered as location points, each of which has additional location information and mileage values.

[0102] S12. Modify the data structure of the road train information planned for the construction day, and define the running information text of the road train as a sequence consisting of stations, yards, sections, equipment and stops.

[0103] S13. Define the speed limit information text of the construction plan as a set of three-dimensional vectors consisting of a speed limit position vector, a speed limit time, and a speed limit value.

[0104] Specifically, the speed limit vector data mainly includes the speed limit position, speed limit time and speed limit value. The speed limit position vector has the same vectorized form as the construction position vector, and the speed limit time includes two types of vector values: train sequence and time period.

[0105] It should be noted that the speed limit time and speed limit value can be calculated based on the construction time and technical specifications, or can be filled in by the user himself.

[0106] The main purpose of vectorizing the speed limit information in this embodiment is to separate the location, time, and value from the text data, so as to realize the logical association and automatic calculation of these values ​​and facilitate the expansion of other automated operations.

[0107] S14. Change the text of the daily construction plan work content into a discrete sequence of work items with incidental workload.

[0108] Specifically, establishing associations between the operation items and driving conditions, the construction locations and road vehicle locations, the construction locations and speed limit locations, and the speed limit templates in the construction plan vector data includes the following steps:

[0109] S21. According to the construction organization process of the construction project, a disassembly relationship is established between the construction project data and the operation project data.

[0110] It should be noted that all construction plans have corresponding construction projects, and all construction projects are clearly listed in the railway company's construction management regulations. Construction projects can be broken down into several orderly construction organization processes, and the work projects can be clarified through the construction organization processes.

[0111] S22. Based on the driving conditions affected by the operation items, mark the pairwise correspondence between all operation item data and all impact types and driving conditions.

[0112] See also Figure 2 , Figure 2 A schematic diagram showing the association between a work item, a construction position vector and an automatically generated impact range according to an embodiment of the present invention is shown.

[0113] S23. When the construction plan road train information is initialized, the road train command station, the operation site and the station and yard in the construction position vector are associated with each other.

[0114] S24. When the construction plan road train information is initialized, the road train operation content is associated with the construction plan operation item vector.

[0115] S25. When the construction plan speed limit information is initialized, the speed limit position vector is associated with the construction position vector.

[0116] S26. When the construction plan speed limit information is initialized, the speed limit template in the driving conditions affected by the operation project is associated with the speed limit time and speed limit value in the construction plan speed limit information vector.

[0117] It should be noted that there is a clear correspondence between what operations are carried out at the construction site, the scope of impact and changes in driving conditions, which are usually described in long paragraphs in regulatory documents such as operating specifications and management methods.

[0118] The embodiment of the present invention designs a correlation structure of specifications, abstracts these relationships in the specifications and management methods specified by the user, and combines the intention expressed by the user management department, enters them into the correlation structure after confirmation, and is used for automatic judgment by the railway operating line construction management information system.

[0119] In the embodiment of the present invention, both the railway freight integrated dispatching command and management system and the train dispatching command system are provided with station area plan views with consistent visual effects.

[0120] It should be noted that the operating line construction management information system is a subsystem of the railway freight comprehensive dispatching command and management system. The construction plan editing and review layer is set in the operating line construction management information system.

[0121] Specifically, expressing the vectorized construction location includes the following steps:

[0122] S31. Obtain each device identifier in the station, field, and device sequence.

[0123] S32. Correspondingly associate each equipment identifier with the equipment graphic on the station area plan of the construction plan editing and review layer.

[0124] During the specific implementation, a station section plan visualization module is added to the construction plan editing and review layer, that is, the operating line construction management information system. The station section plan visualization module can be used to edit and view the station section plan.

[0125] The design of the station section plane visual module fits the operating interface of the train terminal and the train switching console. What you see is what you get, making the expression of the construction planning layer and the construction execution layer consistent.

[0126] S33. According to the sequence of the equipment unique identifier, the equipment sequence is selected through the equipment graphics of the station area plan, and the equipment sequence represents the construction location.

[0127] See also Figure 3 , Figure 3 A schematic diagram of a device sequence according to an embodiment of the present invention is shown.

[0128] For example, select the equipment sequence of the turnout on the station section plan, click the identifiers 12, 6, 4, and 2 in sequence on the station section plan, and obtain the equipment sequence of 12→6→4→2, which is the equipment sequence of the turnout.

[0129] The construction location is indicated by the equipment sequence on the station section plan. When reviewing the plan, the image can be opened to check whether any equipment has been missed and whether there are any potential safety hazards based on the train operation in non-construction areas.

[0130] During the specific implementation, the business line construction management information system incorporates the mileage information of the equipment data of the three professions of engineering, electrical and power supply into the system, so as to accurately locate the work site of the construction unit based on the mileage information of the equipment data and the vectorized construction position. When submitting the plan, the business line construction management information system will compare the work site of the construction unit it has located with the construction location filled in by the construction unit, effectively filtering out the submission of erroneous plans, improving the system's security control attributes, and reducing the labor intensity of plan reviewers.

[0131] It should be noted that the mainline equipment has corresponding mileage values. If the mileage range filled in by the user according to his own cognition is not enough to cover all the equipment, it means that the original cognition is wrong. Time period error is also a kind of planning error, which generally refers to the plan that should be constructed within the skylight period, but is not reported within the skylight period.

[0132] The wrong plan here refers to the contradictions in the filling of the construction location itself, which can reflect that the person filling in the construction plan has wrong construction data or neglects the understanding of the plan content.

[0133] Specifically, expressing the vectorized road train demand includes the following steps:

[0134] S41. Obtain each device identifier of the equipment sequence of the station area plan.

[0135] S42. Based on the equipment sequence, graphics corresponding to the equipment are selected in sequence on the station section plan according to each equipment identifier in the equipment sequence, and the train path is selected through the graphics to express the operation path of the construction road train on the station section plan.

[0136] It should be noted that the operation of road vehicles mainly describes where the road vehicles or locomotives designated by the construction unit need to start from, where they need to stop, where they need to work, and where they need to return to. These information points coincide with the train operation diagram and the train routes and shunting routes that need to be opened.

[0137] S43. Organize the entry of road train demand in a form according to the pre-filled information generated by the vectorized construction location and vectorized operation content in the associated construction plan vector data.

[0138] Specifically, the pre-filled information includes the station to be ordered, the operation location, the operation mileage range and the operation content.

[0139] In the specific implementation, the operating line construction management information system uses a form to input the road train demand. The operating line construction management information system automatically completes the input according to the vectorized construction location and vectorized operation content, which simplifies the input work. It should be noted that the input work needs to be repeated manually when the construction location and operation content are not vectorized. At the same time, the vectorized road vehicle demand provides the conditions for the road train self-laying function of the train dispatching system.

[0140] Specifically, expressing vectored speed limit information includes the following steps:

[0141] S51. Obtain speed limit vector data of the construction plan.

[0142] S52. At the speed limit editing location in the construction plan editing and review layer, associate the speed limit vector data with the station area plan.

[0143] S53. Add information expression symbols on the station map to display the speed limit period and speed limit value.

[0144] It should be noted that the speed limit template contains the correspondence between the operation content and the speed limit stage and speed limit value.

[0145] For example, after the construction of two types of operations, namely, replacement of sleepers in sections and replacement of base bed filling, the line needs to be operated at a speed limit. Therefore, in this data structure, speed limit tags need to be added for the two types of operations, namely, replacement of sleepers in sections and replacement of base bed filling. Furthermore, the speed limit content depends on the different tamping operation methods, so the user can maintain multiple speed limit templates of different operation methods and bind them to these two operation projects as an optional content of driving conditions.

[0146] During specific implementation, the actual speed limit start and end times and speed limit value are calculated based on the operation time in the construction plan, the operation project vector, and the currently selected speed limit template.

[0147] Specifically, expressing the content and impact range of vectorized operations includes the following steps:

[0148] S61, expressing the work content as checking the work items disassembled from the construction project;

[0149] S62, obtaining a construction position vector and a speed limit position vector in the construction plan vector data;

[0150] S63. Obtain the impact type and driving conditions of this construction plan according to the operation project;

[0151] S64. Group the impact types and attach them to the construction location and the speed limit location respectively to form an impact range vector sequence.

[0152] Furthermore, the data vectorization method for the construction management information system also includes the following steps:

[0153] S71. Express the action instruction data executed by the train dispatching system according to the vectorized construction position.

[0154] Specifically, the action instruction data includes electronic information packages of device action instructions and description scripts of execution time and sequence, which can be transmitted between computers through common network protocols.

[0155] It should be noted that the vectorized construction position is the basis of the action instruction, and the object part of the action instruction statement includes the elements in the vectorized construction position.

[0156] The action instructions are for tracks or non-turnout sections, turnouts and signals, specifically:

[0157] Track or non-branch section action instructions include blocking instructions and unlocking instructions;

[0158] The turnout action instructions include single-operation positioning instructions, single-operation reverse position instructions, single-locking instructions, single-release instructions, single-sealing instructions, and unlocking instructions;

[0159] Traffic signal action instructions include blocking instructions and unlocking instructions.

[0160] In the specific implementation, a script language for data information exchange is defined to convert the action instructions executed by the train control console or train service terminal during construction according to the vectorized construction position.

[0161] An action instruction calculation module is added to the construction plan background to calculate the instruction data that should be executed when construction starts; an interface is added between the construction plan background and the train dispatching system to transmit the action instruction data corresponding to the plan to the train dispatching system, so that the train dispatching system has the conditions to realize automated operation.

[0162] S72. Convert the vectorized road train demand into route control start and end command data.

[0163] During specific implementation, the train path is converted into route control start and end instruction data through the action instruction calculation module of the construction plan background, and the route control start and end instruction data are transmitted to the train dispatching system through the interface between the construction plan background and the train dispatching system, so that the train dispatching system has the conditions to realize automated operation.

[0164] S73. Associate the vectorized speed limit information with the temporary speed limit indication of the train dispatching system.

[0165] During the specific implementation, a speed limit template management module is added to the operating line construction management information system. After the user selects the corresponding template, the speed limit template can be selected according to the operation time, operation content, and the currently selected speed limit template. The speed limit template includes the correspondence between the operation content and the speed limit stage and speed limit value. The operating line construction management information system calculates the actual speed limit start and end times and speed limit values ​​to be filled in based on the vectorized speed limit information and the selected speed limit template.

[0166] S74. Generate an impact range vector sequence based on the vectorized work content and construction location, and display it on the train terminal station yard representation diagram through the interface between the construction plan background and the train dispatching system.

[0167] During specific implementation, the operating line construction management information system automatically determines the impact scope of this construction plan based on the vectorized work content and vectorized construction location.

[0168] The specific types of impacts and driving conditions of the construction plan include station blockades, section blockades, section double-track blockades, line vacancy, speed limits during construction, speed limits after construction, speed limit templates, whether to cut off power, whether to disable signal closure, etc.

[0169] Automatic judgment is achieved based on the correspondence between the work items and the impact types and driving conditions data. After the judgment is completed, a label is generated to mark the impact type of the construction plan and the driving conditions, and the corresponding position vector is attached to form an impact range vector sequence.

[0170] When a plan is submitted and approved, the system compares the scope of influence filled in by the user with the scope of influence automatically generated by the system, and issues prompts or blocks.

[0171] See also Figure 4 , Figure 4 A schematic diagram of construction plan vector data flow according to an embodiment of the present invention is shown.

[0172] Based on the above method, the flow process of construction plan vector data is explained below: the construction plan submitter edits and submits the construction plan on the operating line construction management information system, and expresses the construction vector information through the station section plane visual module. The construction vector information passes through the action instruction calculation module of the construction plan background, and the action instruction calculation module processes the construction plan vector data; an interface is added between the construction plan background and the train dispatching system, and the processed construction plan vector data is transmitted to the train dispatching system through the TDCS\CTC interface device. The duty officer can batch confirm the execution or batch cancel the operation through the station map of the train dispatching system, and synchronize the construction plan execution status to the railway freight comprehensive dispatching command and management system.

[0173] Vectorized construction plan data has a higher computer recognition degree, and provides a data basis for realizing a series of functions such as automatic filling, standardization check, error check, conflict check, automatic drawing, automatic generation of transfer orders, automatic and accurate generation of operation disclosure, etc. By filtering out the submission of erroneous plans through vectorized construction plan data, the security control attributes of the system are improved, and the labor intensity of plan reviewers is greatly reduced.

[0174] The embodiment of the present invention quantifies all the contents such as construction projects, operation projects, impact types and driving conditions into the basic data of the system, realizing effective linkage. After the proposal is submitted, it has been determined what work will be done in the later stage, how many windows need to be allocated in the conventional indicators, what resources are needed, what impact will it have on driving organization, etc. The submission of subsequent plans is the disassembly of the content of the proposal and the allocation and adjustment of time, etc., which achieves precise control over the standardization of the plan;

[0175] For the actual reported plan, each work content has a completion amount, which must be reported within a limited time after the registration and cancellation are completed. The reported workload can be summarized into the total workload of the construction plan. This meets the needs of project managers to grasp the progress of the project.

[0176] The corresponding construction items of the bidding can guide the construction unit to select which work items need to be completed when submitting. The determined work items can control the construction unit to not mistakenly submit non-existent driving conditions or omit necessary driving conditions (driving conditions play a strict safety guidance role, which is also a key task for construction plan reviewers when checking plans), and can also enable the system to automatically fill in the necessary speed limit content after construction. The standardization of speed limit content creates conditions for the accurate generation of running reveal commands.

[0177] See also Figure 5 , Figure 5 A structural schematic diagram of a data vectorization system for a construction management information system according to an embodiment of the present invention is shown.

[0178] The embodiment of the present invention further provides a data vectorization system for a construction management information system, which is applied to a railway operating line, and includes:

[0179] A vector data generation module, used to change the construction plan data structure from descriptive text to vector data;

[0180] Vector data association module, used to establish association between operation items and driving conditions, construction locations and road vehicle locations, construction locations and speed limit locations, and speed limit templates in the construction plan vector data;

[0181] The vector data expression module is used to express the vectorized construction location, road train demand, speed limit information, operation content and impact range through the station section plan and the associated construction plan vector data.

[0182] Furthermore, the vector data generation module is specifically used to: define the text data of the construction location of the construction plan as a discrete sequence consisting of stations, yards, sections, equipment and their various parts information, and mileage information; modify the data structure of the road train information planned for the construction day, and change the running information text of the road train information to a sequence consisting of stations, yards, sections, equipment and stopping points; define the speed limit information text of the construction plan as a set of three-dimensional vectors consisting of a speed limit position vector, a speed limit time and a speed limit value; and change the work content of the construction day plan from a descriptive text to a discrete sequence of work items with incidental workload.

[0183] Furthermore, the vector data association module is specifically used to: establish a disassembly relationship between the construction project data and the operation project data according to the construction organization process of the construction project; based on the driving conditions affected by the operation project, mark the pairwise correspondence between all operation project data and all impact types and driving conditions; when the construction plan road train information is initialized, the road train command station and operation location are associated with the station and field in the construction position vector; when the construction plan road train information is initialized, the road train operation content is associated with the construction plan operation project vector; when the construction plan speed limit information is initialized, the speed limit position vector is associated with the construction position vector; when the construction plan speed limit information is initialized, the speed limit template in the driving conditions affected by the operation project is associated with the speed limit time and speed limit value in the construction plan speed limit information vector.

[0184] Furthermore, the vector data expression module is specifically used to: express the action instruction data executed by the train dispatching system according to the vectorized construction location; convert the vectorized road train demand into the route control starting and ending instruction data; associate the vectorized speed limit information with the speed limit representation of the train dispatching system; generate an impact range vector sequence according to the vectorized work content and construction location.

[0185] Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent substitutions for some of the technical features therein; and these modifications or substitutions do not make the essence of the corresponding technical solutions deviate from the spirit and scope of the technical solutions of the embodiments of the present invention.

Claims

1. A data vectorization method for construction management information system, applied to railway operating lines, characterized in that: The following steps are involved: Changing the construction plan data structure from descriptive text to vector data includes the following steps: defining the text data of the construction location of the construction plan as a discrete sequence consisting of station, yard, section, equipment and its various parts information, and mileage information; modifying the data structure of the road train information of the construction day plan, changing the running information text of the road train information to a sequence consisting of station, yard, section, equipment and stop points; defining the speed limit information text of the construction plan as a set of three-dimensional vectors consisting of speed limit position vector, speed limit time and speed limit value; changing the work content text of the construction day plan to a discrete work item sequence of incidental workload; Establishing associations between the operation items and driving conditions, the construction location and the road vehicle location, the construction location and the speed limit location, and the speed limit template in the construction plan vector data includes the following steps: establishing a disassembly relationship between the construction project data and the operation project data according to the construction organization process of the construction project; marking the pairwise correspondence between all operation project data and all driving conditions based on the driving conditions affected by the operation project; when the construction plan road train information is initialized, the road train command station and the operation location are correspondingly associated with the station and yard in the construction position vector; when the construction plan road train information is initialized, the road train operation content is correspondingly associated with the construction plan operation item vector; when the construction plan speed limit information is initialized, the speed limit position vector is correspondingly associated with the construction position vector; when the construction plan speed limit information is initialized, the speed limit template in the driving conditions affected by the operation project is correspondingly associated with the speed limit time and speed limit value in the construction plan speed limit information vector; The vectorized construction location, road train demand, speed limit information, operation content and impact range are expressed through the station section plan and the associated construction plan vector data.

2. The data vectorization method for construction management information system according to claim 1 is characterized in that: Expressing the vectorized construction location includes the following steps: Get each device identifier in the station, field, and device sequence; Correspondingly associate each equipment identifier with the equipment graphic on the station area plan at the construction plan editing and review layer; According to the sequence of the equipment unique identifier, the equipment sequence is selected through the equipment graphics of the station area plan, and the equipment sequence represents the construction location.

3. The data vectorization method for construction management information system according to claim 1, characterized in that: The expression of vectorized road train demand consists of the following steps: Get each equipment identifier of the equipment sequence of the station section plan; Based on the equipment sequence, the graphics corresponding to the equipment are selected in sequence on the station section plan according to each equipment identifier in the equipment sequence, and the train path is selected through the graphics to express the running path of the construction road train on the station section plan; According to the pre-filled information generated by the vectorized construction locations and vectorized work contents in the associated construction plan vector data, the entry of road train requirements is organized in a form.

4. The data vectorization method for construction management information system according to claim 1, characterized in that: Expressing vectored speed limit information includes the following steps: Obtain speed limit vector data for construction plans; In the speed limit editing position of the construction plan editing and review layer, the speed limit vector data is associated with the station area plan; Add information expression symbols on the station map to display the speed limit period and speed limit value.

5. The data vectorization method for construction management information system according to claim 1, characterized in that: Expressing the content and scope of vectorization operations includes the following steps: Express the work content as checking the work items broken down according to the construction project; Obtaining a construction position vector and a speed limit position vector from the construction plan vector data; Obtain the impact type and driving conditions of this construction plan based on the operation project; The impact types are grouped and attached to the construction location and speed limit location to form an impact range vector sequence.

6. The data vectorization method for construction management information system according to claim 1, characterized in that: The pre-filled information includes the required station, operation location, operation mileage range and operation content.

7. The data vectorization method for construction management information system according to any one of claims 1 to 6, characterized in that: The following steps are also included: Express the action instruction data executed by the train dispatching system according to the vectorized construction position; Convert vectorized road train demand into route control start and end command data; Associating the vectorized speed limit information with the speed limit representation of the train dispatching system; Generate an impact range vector sequence based on the vectorized work content and construction location.

8. A data vectorization system for construction management information system, applied to railway operating lines, characterized in that: include: The vector data generation module is used to change the construction plan data structure from descriptive text to vector data, including the following steps: defining the text data of the construction location of the construction plan as a discrete sequence consisting of station, yard, section, equipment and its various parts information, and mileage information; modifying the data structure of the road train information of the construction day plan, changing the running information text of the road train information to a sequence consisting of station, yard, section, equipment and stop point; defining the speed limit information text of the construction plan as a set of three-dimensional vectors consisting of speed limit position vector, speed limit time and speed limit value; changing the construction day plan operation content text to a discrete sequence of operation items with incidental workload; The vector data association module is used to establish associations between the operation items and driving conditions, the construction location and the road vehicle location, the construction location and the speed limit location, and the speed limit template in the construction plan vector data, including the following steps: according to the construction organization process of the construction project, the construction project data and the operation project data are established in a disassembly relationship; based on the driving conditions affected by the operation project, the pairwise correspondence between all operation project data and all driving conditions is marked; when the construction plan road train information is initialized, the road train command station, the operation location and the station and yard in the construction position vector are established; when the construction plan road train information is initialized, the road train operation content is established with the construction plan operation item vector; when the construction plan speed limit information is initialized, the speed limit position vector is established with the construction position vector; when the construction plan speed limit information is initialized, the speed limit template in the driving conditions affected by the operation project is established with the speed limit time and speed limit value in the construction plan speed limit information vector; The vector data expression module is used to express the vectorized construction location, road train demand, speed limit information, operation content and impact range through the station section plan and the associated construction plan vector data.

9. The data vectorization system for construction management information system according to claim 8, characterized in that: The vector data expression module is specifically used for: Express the action instruction data executed by the train dispatching system according to the vectorized construction position; Convert vectorized road train demand into route control start and end command data; Associating the vectorized speed limit information with the speed limit representation of the train dispatching system; Generate an impact range vector sequence based on the vectorized work content and construction location.

Citation Information

Patent Citations

  • System and method for managing railway bridge construction progress based on 3DGIS (Three-dimensional Geographic Information System) and engineering three-dimensional model

    CN106339490A

  • Data organization and management method and system for three-dimensional digital park

    CN107153723A

  • New line railway engineering transport train construction electronic protection method

    CN112896239A