A method and device for improving production planning management of a secondary material tracking system of a rolling line

By using manual numbers and transition numbers to replace the production plan numbers in the metallurgical steel rolling production line, the problem of the rolling line's secondary material tracking system being unable to identify materials in the furnace area caused by the delayed release of the MES production management system was solved, and material tracking information was realized accuracy and continuity.

CN114662862BActive Publication Date: 2024-10-18京华日钢(日照)信息技术有限公司
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202210198522.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-03-01
Publication Date
2024-10-18
Estimated Expiration
2042-03-01

AI Technical Summary

Technical Problem

In the metallurgical steel rolling production line, the delay in releasing the production plan from the MES production management system caused the secondary material tracking system of the heating furnace to be unable to match the billet. As a result, the secondary material tracking system of the rolling line was unable to identify the materials in the furnace area, causing the system to terminate tracking.

Method used

When the production plan number is delayed, use manual numbering to replace the production plan number of the billet, and after the current plan number exists, use the production plan number to replace the manual numbering to ensure that the rolling line secondary material tracking system can identify and track the billet. Prevent system outages.

Benefits of technology

By using excessive numbers to replace manual numbers, the accuracy of material tracking information is ensured, and the interruption of the secondary material tracking system of the rolling line caused by the delayed issuance of production plan numbers from the MES production management system is avoided, ensuring the continuity and accuracy of material tracking.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114662862B_ABST
    Figure CN114662862B_ABST
Patent Text Reader

Abstract

The present invention provides a method and device for improving production plan management of a rolling line secondary material tracking system, which belongs to the field of metallurgical automation technology. The method steps are as follows: the heating furnace secondary material tracking system uses the production plan number issued by the MES production management system to track incoming materials, and the rolling line secondary material tracking system uses the production plan number issued by the MES production management system to track the steel billets in the rolling line area; when there is a delay in the production plan number, the heating furnace secondary material tracking system uses manual numbering for incoming materials to track them in the heating furnace; when there is a delay in the production plan number, the rolling line secondary material tracking system uses an overtime number to replace the manual numbering of the steel billets that have been discharged from the furnace to track the steel billets in the rolling line area, and after the current plan number exists, the production plan number is used to replace the manual numbering of the steel billets to track the steel billets in the rolling line area. The present invention uses the overtime plan number to replace the manual numbering in the rolling line area to manage material tracking by the rolling line secondary material tracking system.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of metallurgical automation, and in particular relates to a production plan management improvement method and device for a secondary material tracking system of a rolling line. Background Art

[0002] The MES production management system simultaneously issues the production plan number to the secondary material tracking system of the heating furnace and the rolling line. The billet starts from the loading platform to the furnace roller in front of the furnace. The secondary material tracking system of the heating furnace automatically matches the production plan number issued by the MES production management system to track the billet in front of the furnace, in the furnace and out of the furnace. The rolling line receives the out-of-furnace billet information, checks the production plan number of the out-of-furnace billet, and determines whether it is the current production plan number. If it is not the current production plan number, an error is reported and the tracking of the secondary material tracking system of the rolling line is terminated. Otherwise, material tracking continues.

[0003] However, the delay in the issuance of production plans by the MES production management system frequently occurs in metallurgical steel rolling production lines. In the secondary material tracking system of the rolling line, the delay in the plan number uploaded to the MES production management system by continuous casting, or the failure to discharge the raw materials in time, will cause the MES production management system to delay the issuance of the production plan to the secondary system of the heating furnace and the secondary material tracking system of the rolling line. The billet enters the front loading roller from the loading platform. The secondary material tracking system of the heating furnace cannot match the billet on the front roller because there is no plan number. The operator needs to manually configure the production plan number to track the billet. When the heating furnace is tapping steel, the secondary material tracking system of the rolling line checks the production plan number of the billet. If the production plan number of the billet out of the furnace is in the production plan number issued by the MES production management system, tracking will begin. If the production plan number of the steel tapping is not in the production plan number issued by the MES production management system, the billet cannot be displayed in the secondary material tracking system of the rolling line. Therefore, when the billet production plan number is manually configured when the heating furnace is tapping steel, the secondary material tracking system of the rolling line cannot recognize it, and no material will be displayed in the tapping area, causing the secondary material tracking system of the rolling line to terminate tracking.

[0004] This is the deficiency of the prior art. Therefore, in view of the above-mentioned defects in the prior art, it is very necessary to provide an improved method and device for production planning management of a rolling line secondary material tracking system. Summary of the invention

[0005] In view of the defect in the prior art that when the billet production plan number is manually configured when the heating furnace is tapping steel, the secondary material tracking system of the rolling line cannot recognize it, and there will be no material display in the tapping area, causing the secondary material tracking system of the rolling line to terminate tracking, the present invention provides a production plan management improvement method and device for the secondary material tracking system of the rolling line to solve the above technical problems.

[0006] In a first aspect, the present invention provides a method for improving production planning management of a rolling line secondary material tracking system, comprising the following steps:

[0007] S1. The secondary material tracking system of the heating furnace uses the production plan number issued by the MES production management system to track the incoming materials, and the secondary material tracking system of the rolling line uses the production plan number issued by the MES production management system to track the billets in the rolling line area;

[0008] S2. When there is a delay in the production plan number, the heating furnace secondary material tracking system uses manual numbering for incoming materials to track them in the heating furnace;

[0009] S3. When there is a delay in the production plan number, the secondary material tracking system of the rolling line uses the transition number to replace the manual number of the billet coming out of the furnace to track the billet in the rolling line area, and after the current plan number exists, the production plan number is used to replace the manual number of the billet to track the billet in the rolling line area.

[0010] Furthermore, the specific steps of step S1 are as follows:

[0011] S11. The MES production management system issues the production plan number to the heating furnace secondary material tracking system;

[0012] S12. The MES production management system issues the production plan number to the secondary material tracking system of the rolling line;

[0013] S13. When incoming materials enter the furnace, the secondary material tracking system of the heating furnace uses the production plan number to track the materials in the heating furnace;

[0014] S14. After the billet is discharged from the furnace, it enters the steel-out roller table in the rolling line area. The secondary material tracking system of the rolling line uses the production plan number to track the billet in the rolling line area;

[0015] S15. When the heating furnace needs to activate the old production plan number due to production needs, the MES production management system will notify the heating furnace secondary material tracking system and the rolling line secondary material tracking system of the old production plan number for synchronous use. The production plan number is used for the heating furnace secondary material tracking system and the rolling line secondary material tracking system to track materials. When the heating furnace needs to activate the old production plan number due to production needs, the production plan numbers of the two tracking systems should be consistent.

[0016] Furthermore, the specific steps of step S2 are as follows:

[0017] S21. When there is a delay in the production plan number, the heating furnace secondary material tracking system assigns a manual number to the incoming material;

[0018] S22. When incoming materials enter the furnace, the secondary material tracking system of the heating furnace tracks the materials in the heating furnace according to the manual numbering. When there is a delay in the production plan number, the manual numbering is used to track the materials in the heating furnace to ensure that the production in the heating furnace will not be interrupted due to the delay in the production plan number.

[0019] Furthermore, the specific steps of step S22 are as follows:

[0020] S221. When incoming materials enter the furnace, the secondary material tracking system of the heating furnace obtains the manual numbering of the incoming materials in sequence;

[0021] S222. The secondary material tracking system of the heating furnace obtains the number of corresponding incoming materials, the corresponding steel type and specifications, and reports the number of corresponding incoming materials, the corresponding steel type and specifications to the MES production management system in chronological order;

[0022] S223. The MES production management system issues the production plan and the corresponding production plan number according to the reported number of incoming materials, corresponding steel types and specifications. Because manual numbering is used when the production plan number is delayed, the number of incoming materials, corresponding steel types and specifications produced in real time in the heating furnace need to be notified to the MES production management system so that the entire production plan can match the real-time production when the production plan number is issued.

[0023] Furthermore, the specific steps of step S3 are as follows:

[0024] S31. When the production plan number is delayed and the heating furnace discharge signal is received, the rolling line secondary material tracking system determines whether the current production plan number is received;

[0025] If yes, go to step S32;

[0026] If not, proceed to step S33;

[0027] S32. The secondary material tracking system of the rolling line uses the production plan number to replace the manual number of the billet to track the material, and then proceeds to step S34;

[0028] S33. The secondary material tracking system of the rolling line uses the transition number to replace the manual number of the billet out of the furnace for material tracking;

[0029] S34. The secondary material tracking system of the rolling line tracks the steel billet to the cooling bed, and judges whether there is a delay in the production plan number according to whether the steel billet at the cooling bed has the current production plan number, and when there is a production plan delay, judges whether to replace the transition plan number with the production plan number according to whether there is a production plan number that can be matched. When the secondary material tracking system of the rolling line tracks the steel billet in the rolling line area, it is necessary to judge the current production plan number. If the current production plan number appears, the manual number will be replaced with the production plan number in time, and the steel billet entering the rolling line area will use the production plan number without another number. If there is no production plan number, it means that there is still a delay, and the manual number will be replaced with the transition plan number to ensure that the secondary material tracking system of the rolling line can identify it; at the same time, the steel billet leaving the cooling bed is judged, and when the current production plan number exists at the cooling bed, it is judged to see if there is still a delay.

[0030] Furthermore, the specific steps of step S34 are as follows:

[0031] S341. The secondary material tracking system of the rolling line tracks the steel billet to the cooling bed and determines whether the steel billet at the cooling bed adopts the current production plan number or the transition plan number;

[0032] When the steel billet at the cooling bed adopts the current production plan number, proceed to step S342;

[0033] When the billet at the cooling bed adopts the transition plan number, go to step S343;

[0034] S342. The secondary material tracking system of the rolling line determines that there is no delay in the production plan number, and sends a rolling completion signal to the MES production management system, and ends;

[0035] S343. The secondary material tracking system of the rolling line determines that there is a delay in the production plan number, and determines whether there is a matching production plan number at the cooling bed;

[0036] If yes, go to step S344;

[0037] If not, proceed to step S345;

[0038] S344. The secondary material tracking system of the rolling line uses the production plan number to replace the transition plan number in batches in the order of small and large, and notifies the secondary material tracking system of the heating furnace that the corresponding replacement production plan number has been released, and returns to step S341;

[0039] S345. The secondary material tracking system of the rolling line accumulates and stores the over-plan number, and returns to step S341. When the cooling bed is the current production plan number, it means that the production plan number has replaced the over-plan number and the production is completed; and when the cooling bed is the over-plan number, it is necessary to further determine whether there is a production plan number that can be replaced. If there is a batch replacement, if there is no over-plan number stored, continue to wait for the production plan number to be issued.

[0040] In a second aspect, the present invention provides a production planning management improvement device for a rolling line secondary material tracking system, comprising:

[0041] The production plan number issuing module is used for the heating furnace secondary material tracking system to track incoming materials using the production plan number issued by the MES production management system, and the rolling line secondary material tracking system to track the steel billets in the rolling line area using the production plan number issued by the MES production management system;

[0042] The manual numbering module for heating furnaces is used to track incoming materials in the heating furnace using manual numbers in the secondary material tracking system of the heating furnace when there is a delay in the production plan number;

[0043] The module for using transition numbers in the rolling area is used when there is a delay in the production plan number. The secondary material tracking system of the rolling line uses the transition number to replace the manual number of the billet coming out of the furnace to track the billets in the rolling area, and after the current plan number exists, the production plan number is used to replace the manual number of the billet to track the billets in the rolling area.

[0044] Furthermore, the production plan number issuing module includes:

[0045] The first issuing unit of the production plan number is used by the MES production management system to issue the production plan number to the secondary material tracking system of the heating furnace;

[0046] The second issuing unit of production plan number is used for the MES production management system to issue the production plan number to the secondary material tracking system of the rolling line;

[0047] The heating furnace incoming material tracking unit is used to enter the furnace. The heating furnace secondary material tracking system uses the production plan number to track the materials in the heating furnace.

[0048] The billet tracking unit in the rolling area is used for the billets to enter the steel-out roller table in the rolling area after they come out of the furnace. The secondary material tracking system of the rolling line uses the production plan number to track the billets in the rolling area.

[0049] The old production plan number restart unit is used when the heating furnace needs to activate the old production plan number due to production needs. The MES production management system notifies the heating furnace secondary material tracking system and the rolling line secondary material tracking system of the old production plan number for synchronous use.

[0050] Furthermore, the manual numbering module for the heating furnace includes:

[0051] The manual numbering configuration unit is used for the heating furnace secondary material tracking system to configure manual numbers for incoming materials when there is a delay in the production plan number;

[0052] The manual numbering tracking unit is used for incoming materials into the furnace. The secondary material tracking system of the heating furnace tracks the materials in the heating furnace according to the manual numbering.

[0053] Furthermore, the rolling line area transition number use module includes:

[0054] The current production plan number receiving and judging unit is used for judging whether the current production plan number is received by the rolling line secondary material tracking system when a delay in the production plan number occurs and a heating furnace discharge signal is received;

[0055] The production plan number replaces the manual number tracking unit, which is used for the rolling line secondary material tracking system to use the production plan number to replace the manual number of the billet out of the furnace for material tracking when receiving the current production plan number;

[0056] The tracking unit for replacing the manual number with the transition plan number is used when the current production plan number is not received. The secondary material tracking system of the rolling line uses the transition number to replace the manual number of the billet out of the furnace for material tracking.

[0057] The production plan delay and production plan number pairing judgment unit at the cooling bed is used for the secondary material tracking system of the rolling line to track the steel billet to the cooling bed, and judge whether there is a production plan number delay according to whether the steel billet at the cooling bed has a current production plan number, and when there is a production plan delay, judge whether to replace the transition plan number with the production plan number according to whether there is a production plan number that can be matched.

[0058] The beneficial effects of the present invention are:

[0059] The improved method and device for production plan management of a secondary material tracking system of a rolling line provided by the present invention improve the management of the production plan number of the secondary material tracking system of the rolling line, specify an excessive plan number in the rolling line area to replace the manual numbering of the heating furnace for material tracking, and when the MES production management system delays the issuance of the production plan number, the excessive plan number is used to replace the manual numbering in a one-to-one correspondence, the actual tracking information is retained, and the plan information is replaced, thereby ensuring the accuracy of the material tracking information, and the secondary material tracking system of the rolling line will not be interrupted due to the delayed issuance of the production plan number of the MES production management system.

[0060] In addition, the invention has a reliable design principle, a simple structure and a very broad application prospect.

[0061] It can be seen that compared with the prior art, the present invention has outstanding substantive features and significant progress, and the beneficial effects of its implementation are also obvious. BRIEF DESCRIPTION OF THE DRAWINGS

[0062] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.

[0063] Figure 1 It is a flow chart of Example 1 of the improved method for production planning management of the secondary material tracking system of a rolling line of the present invention.

[0064] Figure 2 This is a schematic diagram of the process of Example 2 of the improved method for production planning management of the secondary material tracking system of the rolling line of the present invention.

[0065] Figure 3 It is a flow chart of step S43 of the improved method for production planning management of the secondary material tracking system of the rolling line of the present invention.

[0066] Figure 4 It is a schematic diagram of the production plan management improvement device of the rolling line secondary material tracking system of the present invention.

[0067] In the figure, 1-production plan number issuing module; 1.1-production plan number first issuing unit; 1.2-production plan number second issuing unit; 1.3-heating furnace incoming material tracking unit; 1.4-rolling line area billet tracking unit; 1.5-old production plan number restart unit; 2-heating furnace manual number allocation module; 2.1-manual number allocation configuration unit; 2.2-manual number allocation tracking unit; 3-rolling line area transition number usage module; 3.1-current production plan number receiving judgment unit; 3.2-production plan number replacement manual number allocation tracking unit; 3.3-transition plan number replacement manual number allocation tracking unit; 3.4-production plan delay at cooling bed and production plan number pairing judgment unit. DETAILED DESCRIPTION

[0068] In order to enable those skilled in the art to better understand the technical solutions in the present invention, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.

[0069] Embodiment 1:

[0070] like Figure 1 As shown, the present invention provides a method for improving production planning management of a rolling line secondary material tracking system, comprising the following steps:

[0071] S1. The secondary material tracking system of the heating furnace uses the production plan number issued by the MES production management system to track the incoming materials, and the secondary material tracking system of the rolling line uses the production plan number issued by the MES production management system to track the billets in the rolling line area;

[0072] S2. When there is a delay in the production plan number, the heating furnace secondary material tracking system uses manual numbering for incoming materials to track them in the heating furnace;

[0073] S3. When there is a delay in the production plan number, the secondary material tracking system of the rolling line uses the transition number to replace the manual number of the billet coming out of the furnace to track the billet in the rolling line area, and after the current plan number exists, the production plan number is used to replace the manual number of the billet to track the billet in the rolling line area.

[0074] Embodiment 2:

[0075] like Figure 2 As shown, the present invention provides a method for improving production planning management of a rolling line secondary material tracking system, comprising the following steps:

[0076] S1. The secondary material tracking system of the heating furnace uses the production plan number issued by the MES production management system to track the incoming materials, and the secondary material tracking system of the rolling line uses the production plan number issued by the MES production management system to track the billets in the rolling line area; the specific steps are as follows:

[0077] S11. The MES production management system issues the production plan number to the heating furnace secondary material tracking system;

[0078] S12. The MES production management system issues the production plan number to the secondary material tracking system of the rolling line;

[0079] S13. When incoming materials enter the furnace, the secondary material tracking system of the heating furnace uses the production plan number to track the materials in the heating furnace;

[0080] S14. After the billet is discharged from the furnace, it enters the steel-out roller table in the rolling line area. The secondary material tracking system of the rolling line uses the production plan number to track the billet in the rolling line area;

[0081] S15. When the heating furnace needs to use the old production plan number due to production needs, the MES production management system notifies the heating furnace secondary material tracking system and the rolling line secondary material tracking system of the old production plan number for simultaneous use;

[0082] S2. When there is a delay in the production plan number, the secondary material tracking system of the heating furnace uses manual numbering for incoming materials to track them in the heating furnace; the specific steps are as follows:

[0083] S21. When there is a delay in the production plan number, the heating furnace secondary material tracking system assigns a manual number to the incoming material;

[0084] S22. When incoming materials enter the furnace, the secondary material tracking system of the heating furnace tracks the materials in the heating furnace according to the manual numbering; the specific steps are as follows:

[0085] S221. When incoming materials enter the furnace, the secondary material tracking system of the heating furnace obtains the manual numbering of the incoming materials in sequence;

[0086] S222. The secondary material tracking system of the heating furnace obtains the number of corresponding incoming materials, the corresponding steel type and specifications, and reports the number of corresponding incoming materials, the corresponding steel type and specifications to the MES production management system in chronological order;

[0087] S223. MES production management system issues production plan and corresponding production plan number according to the number of incoming materials, corresponding steel type and specification reported;

[0088] S3. When the production plan number is delayed, the secondary material tracking system of the rolling line uses the transition number to replace the manual number of the billet out of the furnace to track the billet in the rolling line area, and after the current plan number exists, the production plan number is used to replace the manual number of the billet to track the billet in the rolling line area; the specific steps are as follows:

[0089] S31. When the production plan number is delayed and the heating furnace discharge signal is received, the rolling line secondary material tracking system determines whether the current production plan number is received;

[0090] If yes, go to step S32;

[0091] If not, proceed to step S33;

[0092] S32. The secondary material tracking system of the rolling line uses the production plan number to replace the manual number of the billet to track the material, and then proceeds to step S34;

[0093] S33. The secondary material tracking system of the rolling line uses the transition number to replace the manual number of the billet out of the furnace for material tracking;

[0094] S34. The secondary material tracking system of the rolling line tracks the steel billet to the cooling bed, and determines whether there is a production plan number delay according to whether the steel billet at the cooling bed has a current production plan number, and when there is a production plan delay, determines whether to replace the transition plan number with the production plan number according to whether there is a production plan number that can be matched; if Figure 3 As shown, the specific steps are as follows:

[0095] S341. The secondary material tracking system of the rolling line tracks the steel billet to the cooling bed and determines whether the steel billet at the cooling bed adopts the current production plan number or the transition plan number;

[0096] When the steel billet at the cooling bed adopts the current production plan number, proceed to step S342;

[0097] When the billet at the cooling bed adopts the transition plan number, go to step S343;

[0098] S342. The secondary material tracking system of the rolling line determines that there is no delay in the production plan number, and sends a rolling completion signal to the MES production management system, and ends;

[0099] S343. The secondary material tracking system of the rolling line determines that there is a delay in the production plan number, and determines whether there is a matching production plan number at the cooling bed;

[0100] If yes, go to step S344;

[0101] If not, proceed to step S345;

[0102] S344. The secondary material tracking system of the rolling line uses the production plan number to replace the transition plan number in batches in the order of small and large, and notifies the secondary material tracking system of the heating furnace that the corresponding replacement production plan number has been released, and returns to step S341;

[0103] S345. The rolling line secondary material tracking system accumulates and stores the excessive plan number and returns to step S341.

[0104] Embodiment 3:

[0105] like Figure 4 As shown, the present invention provides a production plan management improvement device for a rolling line secondary material tracking system, comprising:

[0106] The production plan number issuing module 1 is used for the heating furnace secondary material tracking system to track the incoming materials using the production plan number issued by the MES production management system, and the rolling line secondary material tracking system to track the steel billets in the rolling line area using the production plan number issued by the MES production management system; the production plan number issuing module 1 includes:

[0107] The first issuing unit 1.1 of the production plan number is used by the MES production management system to issue the production plan number to the secondary material tracking system of the heating furnace;

[0108] The second production plan number issuing unit 1.2 is used for the MES production management system to issue the production plan number to the rolling line secondary material tracking system;

[0109] Heating furnace incoming material tracking unit 1.3 is used for incoming materials entering the furnace. The heating furnace secondary material tracking system uses the production plan number to track the materials in the heating furnace;

[0110] The billet tracking unit 1.4 in the rolling area is used for the billet to enter the steel-out roller table in the rolling area after it comes out of the furnace. The secondary material tracking system of the rolling area uses the production plan number to track the billet in the rolling area;

[0111] The old production plan number restart unit 1.5 is used when the heating furnace needs to use the old production plan number due to production needs. The MES production management system notifies the heating furnace secondary material tracking system and the rolling line secondary material tracking system of the old production plan number for synchronous use;

[0112] The manual numbering module 2 for the heating furnace is used for tracking the incoming materials in the heating furnace by using the manual numbering system when the production plan number is delayed. The manual numbering module 2 for the heating furnace includes:

[0113] Manual number allocation unit 2.1 is used for the heating furnace secondary material tracking system to allocate manual numbers for incoming materials when there is a delay in the production plan number;

[0114] Manual numbering tracking unit 2.2 is used for incoming materials into the furnace. The secondary material tracking system of the heating furnace tracks the materials in the heating furnace according to the manual numbering;

[0115] The rolling line area transition number using module 3 is used for when there is a delay in the production plan number, the rolling line secondary material tracking system uses the transition number to replace the artificial number of the billet out of the furnace to track the billet in the rolling line area, and after the current plan number exists, the production plan number is used to replace the artificial number of the billet to track the billet in the rolling line area; the rolling line area transition number using module 3 includes:

[0116] The current production plan number receiving judgment unit 3.1 is used for judging whether the current production plan number is received by the rolling line secondary material tracking system when a delay in the production plan number occurs and a heating furnace discharge signal is received;

[0117] The production plan number replaces the manual number tracking unit 3.2, which is used for the rolling line secondary material tracking system to use the production plan number to replace the manual number of the billet out of the furnace for material tracking when receiving the current production plan number;

[0118] The transition plan number replaces the manual number tracking unit 3.3, which is used for the rolling line secondary material tracking system to use the transition number to replace the manual number of the billet out of the furnace for material tracking when the current production plan number is not received;

[0119] The production plan delay and production plan number pairing judgment unit 3.4 at the cooling bed is used for the secondary material tracking system of the rolling line to track the steel billet to the cooling bed, and judge whether there is a production plan number delay according to whether the steel billet at the cooling bed has a current production plan number, and when there is a production plan delay, judge whether to replace the transition plan number with the production plan number according to whether there is a production plan number that can be paired.

[0120] Although the present invention has been described in detail by referring to the accompanying drawings and in combination with the preferred embodiments, the present invention is not limited thereto. Without departing from the spirit and essence of the present invention, a person of ordinary skill in the art may make various equivalent modifications or substitutions to the embodiments of the present invention, and these modifications or substitutions shall be within the scope of the present invention. Any person of ordinary skill in the art may easily think of changes or substitutions within the technical scope disclosed by the present invention, and these shall be within the scope of protection of the present invention. Therefore, the scope of protection of the present invention shall be subject to the scope of protection of the claims.

Claims

1. A method for improving production planning management of a rolling line secondary material tracking system, characterized in that: The steps include: S1. The secondary material tracking system of the heating furnace uses the production plan number issued by the MES production management system to track the incoming materials, and the secondary material tracking system of the rolling line uses the production plan number issued by the MES production management system to track the billets in the rolling line area; S2. When there is a delay in the production plan number, the heating furnace secondary material tracking system uses manual numbering for incoming materials to track them in the heating furnace; S3. When there is a delay in the production plan number, the secondary material tracking system of the rolling line uses the transition number to replace the manual number of the billet out of the furnace to track the billet in the rolling line area, and after the current plan number exists, the production plan number is used to replace the manual number of the billet to track the billet in the rolling line area; The specific steps of step S1 are as follows: S11. The MES production management system issues the production plan number to the heating furnace secondary material tracking system; S12. The MES production management system issues the production plan number to the secondary material tracking system of the rolling line; S13. When incoming materials enter the furnace, the secondary material tracking system of the heating furnace uses the production plan number to track the materials in the heating furnace; S14. After the billet is discharged from the furnace, it enters the steel-out roller table in the rolling line area. The secondary material tracking system of the rolling line uses the production plan number to track the billet in the rolling line area; S15. When the heating furnace needs to use the old production plan number due to production needs, the MES production management system notifies the heating furnace secondary material tracking system and the rolling line secondary material tracking system of the old production plan number for simultaneous use; The specific steps of step S2 are as follows: S21. When there is a delay in the production plan number, the heating furnace secondary material tracking system assigns a manual number to the incoming material; S22. When incoming materials enter the furnace, the secondary material tracking system of the heating furnace tracks the materials in the heating furnace according to the manual numbering; The specific steps of step S22 are as follows: S221. When incoming materials enter the furnace, the secondary material tracking system of the heating furnace obtains the manual numbering of the incoming materials in sequence; S222. The secondary material tracking system of the heating furnace obtains the number of corresponding incoming materials, the corresponding steel type and specifications, and reports the number of corresponding incoming materials, the corresponding steel type and specifications to the MES production management system in chronological order; S223. MES production management system issues production plan and corresponding production plan number according to the number of incoming materials, corresponding steel type and specification reported; The specific steps of step S3 are as follows: S31. When the production plan number is delayed and the heating furnace discharge signal is received, the rolling line secondary material tracking system determines whether the current production plan number is received; If yes, go to step S32; If not, proceed to step S33; S32. The secondary material tracking system of the rolling line uses the production plan number to replace the manual number of the billet to track the material, and then proceeds to step S34; S33. The secondary material tracking system of the rolling line uses the transition number to replace the manual number of the billet out of the furnace for material tracking; S34. The secondary material tracking system of the rolling line tracks the steel billet to the cooling bed, and determines whether there is a production plan number delay based on whether the steel billet at the cooling bed has a current production plan number. When there is a production plan delay, it determines whether to replace the transition plan number with the production plan number based on whether there is a production plan number that can be matched.

2. The method for improving production planning management of a rolling line secondary material tracking system according to claim 1, characterized in that: The specific steps of step S34 are as follows: S341. The secondary material tracking system of the rolling line tracks the steel billet to the cooling bed and determines whether the steel billet at the cooling bed adopts the current production plan number or the transition plan number; When the steel billet at the cooling bed adopts the current production plan number, proceed to step S342; When the billet at the cooling bed adopts the transition plan number, go to step S343; S342. The secondary material tracking system of the rolling line determines that there is no delay in the production plan number, and sends a rolling completion signal to the MES production management system, and ends; S343. The secondary material tracking system of the rolling line determines that there is a delay in the production plan number, and determines whether there is a matching production plan number at the cooling bed; If yes, go to step S344; If not, proceed to step S345; S344. The secondary material tracking system of the rolling line uses the production plan number to replace the transition plan number in batches in ascending order, and notifies the secondary material tracking system of the heating furnace that the corresponding replacement production plan number has been released, and returns to step S341; S345. The rolling line secondary material tracking system accumulates and stores the excessive plan number and returns to step S341.

3. A production planning management improvement device for a rolling line secondary material tracking system, characterized in that: include: The production plan number issuing module (1) is used for the heating furnace secondary material tracking system to track incoming materials using the production plan number issued by the MES production management system, and the rolling line secondary material tracking system to track the steel billets in the rolling line area using the production plan number issued by the MES production management system; The heating furnace manual numbering module (2) is used for the heating furnace secondary material tracking system to use manual numbering for incoming materials to track them in the heating furnace when there is a delay in the production plan number; The rolling line area transition number using module (3) is used for when there is a delay in the production plan number, the rolling line secondary material tracking system uses the transition number to replace the manual number of the billet discharged from the furnace to track the billet in the rolling line area, and after the current plan number exists, uses the production plan number to replace the manual number of the billet to track the billet in the rolling line area; The production plan number issuing module (1) includes: The first issuing unit of the production plan number (1.1) is used by the MES production management system to issue the production plan number to the secondary material tracking system of the heating furnace; The second production plan number issuing unit (1.2) is used by the MES production management system to issue the production plan number to the rolling line secondary material tracking system; The heating furnace incoming material tracking unit (1.3) is used for incoming materials entering the furnace. The heating furnace secondary material tracking system uses the production plan number to track the materials in the heating furnace; The billet tracking unit (1.4) in the rolling area is used for the billets to enter the steel-out roller table in the rolling area after they are discharged from the furnace. The secondary material tracking system of the rolling area uses the production plan number to track the billets in the rolling area. The old production plan number restart unit (1.5) is used when the heating furnace needs to use the old production plan number for production. The MES production management system notifies the heating furnace secondary material tracking system and the rolling line secondary material tracking system of the old production plan number for synchronous use; The manual numbering module (2) for the heating furnace includes: The manual numbering configuration unit (2.1) is used for the heating furnace secondary material tracking system to configure manual numbers for incoming materials when there is a delay in the production plan number; Manual numbering tracking unit (2.2) is used for incoming materials into the furnace. The secondary material tracking system of the heating furnace tracks the materials in the heating furnace according to the manual numbering; The module (3) for using the transition number in the rolling line area includes: The current production plan number receiving judgment unit (3.1) is used for judging whether the current production plan number has been received by the rolling line secondary material tracking system when a delay in the production plan number occurs and a heating furnace discharge signal is received; The production plan number replaces the manual number tracking unit (3.2), which is used for the rolling line secondary material tracking system to use the production plan number to replace the manual number of the billet out of the furnace for material tracking when receiving the current production plan number; The tracking unit (3.3) for replacing the manual number with the transition plan number is used when the current production plan number is not received. The secondary material tracking system of the rolling line uses the transition number to replace the manual number of the billet out of the furnace for material tracking. The production plan delay and production plan number pairing judgment unit (3.4) at the cooling bed is used for the rolling line secondary material tracking system to track the steel billet to the cooling bed, and judge whether there is a production plan number delay according to whether the steel billet at the cooling bed has a current production plan number, and when there is a production plan delay, judge whether to replace the transition plan number with the production plan number according to whether there is a production plan number that can be paired.

Citation Information

Patent Citations

  • Monitoring method used for information management of materials in steel rolling mill

    CN102393722A

  • CSP continuous casting and continuous rolling temporary steel coil number automatic matching method and system

    CN109877158A