A drainage structure and construction method for structural joints of existing rail transit stations
By setting up a drainage structure of embedded drainage ditches and support units at the structural joints of the rail transit station, the problem of groundwater leakage is solved, ensuring the dry ground of the station, improving the discharge speed and efficiency of the leakage water, and ensuring the safety and beauty of the station .
Patent Information
- Application Number
- CN202210410545.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-04-19
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2042-04-19
AI Technical Summary
In rail transit underground stations, the prior art is difficult to effectively prevent groundwater leakage at structural joints, resulting in slippery ground on the station, affecting the beauty and passenger safety.
Design a structural joint drainage structure including a first drainage ditch and a second drainage ditch. The first drainage ditch is embedded in a concrete cushion layer. The cover plate structure is supported by a support unit. The top and bottom gaps are arranged, and the second drainage ditch is connected with the first The drainage ditches connect to the drainage pipe network, the support unit is I-shaped steel, the cover plate structure is stainless steel edge-covered floor tiles, and angle steel is installed in the right angle groove to support the cover plate.
Water leaks through the discharge structure joint of the first drainage ditch, and the second drainage ditch discharges water to the drainage pipe network, solving the problem of groundwater leakage, ensuring the dry ground of the station, and improving the discharge speed and efficiency of leakage water.
Smart Images

Figure CN114673243B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of subway station construction, and in particular relates to a structural seam drainage structure of an existing rail transit station and a construction method thereof. Background Art
[0002] Structural joints refer to the general term for the intervals of divided concrete structures taken according to structural design requirements or construction needs, that is, the joints between reinforced concrete poured first and later or the gaps between concrete structures. Its types include construction joints, deformation joints, expansion joints, settlement joints, seismic joints, etc.; in addition, the poured concrete structure forms a civil engineering structure layer. In the construction process of underground rail transit stations, structural joints are inevitably set up, and the concrete cushion layer and decoration layer are laid on top of them in sequence as in other locations. Since underground stations are buried deep underground, groundwater can easily leak out of the normal use ground through structural joints. For this reason, waterstops are often buried in structural joints during design and construction to prevent groundwater leakage.
[0003] However, the construction quality of waterstop is very difficult to ensure. Even if the construction quality is good, groundwater will still seep out of the station floor through the waterstop over time. This phenomenon is more likely to occur in underground stations in water-rich areas. After groundwater seeps into the normal ground of the station, it causes slippery weather. At this time, the station has been put into operation, affecting the appearance and normal use of the station. In serious cases, it will affect the safety of passengers. Summary of the invention
[0004] The purpose of the present invention is to provide a drainage structure and construction method for the structural joints of existing rail transit stations, so as to solve the problem that the water stop strips provided in the structural joints in the prior art cannot prevent water from leaking out of the station ground. In order to achieve the above purpose, the present invention solves the problem through the following technical solutions:
[0005] In a first aspect, the present invention provides a drainage structure for a structural seam of an existing rail transit station, comprising:
[0006] A first drainage ditch is embedded in the concrete cushion layer above the structural joint, the bottom of the drainage ditch is connected to the structural joint, the top is covered with a cover structure flush with the ground, two rows of support units are arranged between the top and the bottom along the drainage direction and used to support the cover structure, and gaps are arranged between each row of support units;
[0007] The second drainage ditch has one end connected to the first drainage ditch and the other end connected to the drainage pipe network.
[0008] As a further technical solution, the two rows of support units are arranged on both sides of the structural joint.
[0009] As a further technical solution, a waterproof layer is provided on the exposed surface of the concrete cushion layer facing the first drainage ditch.
[0010] As a further technical solution, the supporting unit is an I-beam, and the lower wing plate of the I-beam is buried in the civil structure layer below the first drainage ditch.
[0011] As a further technical solution, the concrete cushion layers on both sides of the first drainage ditch and the finishing layer thereon form right-angle grooves, and the right-angle grooves are used to support the cover plate structure.
[0012] As a further technical solution, an angle steel adapted to the right-angle groove is provided in the right-angle groove.
[0013] As a further technical solution, the cover plate structure is in free contact with both the support unit and the right-angle groove.
[0014] As a further technical solution, the cover plate structure is a stainless steel-edged floor tile.
[0015] As a further technical solution, a pipe is buried in the second drainage ditch, and the leaked water from the first drainage ditch is drained to the drainage network through the pipe.
[0016] In a second aspect, the present invention provides a construction method for the drainage structure of the existing railway station structure joint as described in the first aspect, comprising the following steps:
[0017] The original decoration layer and concrete cushion layer of a set width above the structural joint where water leakage occurs are chiseled off to expose both sides of the concrete cushion layer and the civil structure layer; a support unit is arranged on the civil structure layer to support the cover structure to form a first drainage ditch; a second drainage ditch is opened at the end of the first drainage ditch to drain the leaking water of the first drainage ditch to the drainage network through the second drainage ditch.
[0018] The beneficial effects of the present invention are as follows:
[0019] (1) The present invention sets a first drainage ditch in the original decoration layer and the concrete cushion layer above the structural joint. The water leaking through the structural joint can be discharged through the first drainage ditch to prevent excessive water accumulation in the structural joint from leaking out of the station floor. The leaked water is discharged to the drainage network through the second drainage ditch to be completely discharged from the station.
[0020] (2) The present invention arranges two rows of support units in the first drainage ditch, and each row includes a plurality of support units for supporting the cover plate structure. Meanwhile, there are gaps between the support units in each row to facilitate the flow of leaked water. When the amount of leaked water is small, continuous support units are used to divide the first drainage ditch into three chambers. Each chamber works independently to discharge the leaked water. When the amount of leakage is large, it is difficult to ensure that the leaked water flows out in time. By using support units with gaps, the three chambers are interconnected, which can increase the speed of discharging the leaked water. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] The accompanying drawings constituting a part of the present invention are used to provide a further understanding of the present invention. The illustrative embodiments of the present invention and their description are used to explain the present invention and do not constitute a limitation of the present invention. It should also be understood that these drawings are shown for simplicity and clarity and are not necessarily drawn to scale. The present invention will now be described and explained with additional features and details through the use of the accompanying drawings, in which:
[0022] Figure 1 A schematic top view of a drainage structure in an embodiment of the present invention is shown;
[0023] Figure 2 A schematic cross-sectional view of a drainage structure in an embodiment of the present invention is shown.
[0024] In the figure: 1. structural joint; 2. waterproof layer; 3. angle steel; 4. first drainage ditch; 5. I-beam; 51. upper wing plate; 52. web plate; 53. lower wing plate; 6. second drainage ditch; 7. decoration layer; 8. concrete cushion layer; 9. civil structure layer; 10. cover plate structure; 11. structural water-facing surface; 12. waterstop. DETAILED DESCRIPTION
[0025] The technical solutions in typical embodiments of the present invention will be described clearly and completely below in conjunction with the accompanying drawings in the embodiments of the present invention.
[0026] Example 1
[0027] like Figure 1 and Figure 2 As shown, this embodiment provides a drainage structure for a structural seam of an existing rail transit station, including:
[0028] A first drainage ditch 4 is embedded in a concrete cushion layer 8 above the structural joint 1, the bottom of the drainage ditch is connected to the structural joint 1, and the top is covered with a cover structure 10 flush with the ground, and two rows of support units are arranged between the top and the bottom along the drainage direction and used to support the cover structure 10, and gaps are arranged between each row of support units;
[0029] One end of the second drainage ditch 6 is connected to the first drainage ditch 4, and the other end is connected to the drainage network.
[0030] The structural joint 1 of this embodiment is set in the civil structure layer 9, which is obtained by pouring concrete into a steel cage, and the structural joint is set during pouring. A concrete cushion layer 8 and a decoration layer 7 are set on the upper part of the civil structure layer 9. Usually, the decoration layer 7 is a floor tile, and the concrete cushion layer 8 is set to fix and stabilize the floor tile. Groundwater flows to the structural joint 1 through the structural water-facing surface 11 at the bottom of the civil structure layer 9, and then the water leaks upward through the water stop 12.
[0031] In this embodiment, a first drainage ditch 4 is arranged in the concrete cushion layer 8 above the structural joint 1. Water leaking through the structural joint 1 can be discharged through the first drainage ditch to prevent excessive water accumulation in the structural joint 1 from leaking out of the station floor. The leaked water can be discharged to the drainage network through the second drainage ditch and completely discharged from the station.
[0032] After the construction of the first drainage ditch 4 is completed, the cover structure 10 is covered to serve as a decoration layer to close the first drainage ditch 4. In this embodiment, the cover structure 10 is a stainless steel-edged floor tile, which is consistent with the floor tile structure of the decoration layer 7. It has no adverse effect on the normal operation and use of the existing station, has no impact on the original structural joints, and can reduce the impact on the existing station ground decoration layer.
[0033] Two rows of support units are arranged in the first drainage ditch 4, and each row includes a plurality of support units for supporting the cover structure 10. At the same time, there are gaps between the support units in each row to facilitate the flow of leaked water. When the amount of leaked water is small, continuous support units are used to divide the first drainage ditch 4 into three chambers. Each chamber works independently to discharge the leaked water. When the amount of leakage is large, it is difficult to ensure that the leaked water flows out in time. By using support units with gaps, the three chambers are interconnected, which can increase the speed of leaked water discharge.
[0034] The two rows of support units are arranged on both sides of the structural joint 1, which can evenly support the cover structure 10, and are conducive to the uniform flow of leakage water. If they are all arranged on the same side of the structural joint, the cover structure 10 will be unevenly stressed and it will be unfavorable for the flow of leakage water.
[0035] In this embodiment, the support unit is an I-beam 5, and the lower wing plate 53 of the I-beam 5 is buried in the civil engineering structure layer 9 below the first drainage ditch 4. The I-beam 5 is cut into sections, each section is a support unit, and the I-beam 5 includes an upper wing plate 51, a web plate 52 and a lower wing plate 53. Since the wing plate has a large force-bearing area, it is conducive to uniformly supporting the cover plate structure, and the narrow web plate is conducive to the flow of leaking water, and will not cause excessive obstruction to the leaking water.
[0036] In order to achieve stable support of the I-beam 5 , the lower wing plate 53 thereof is buried in the civil engineering structure layer 9 . Meanwhile, the lower wing plate does not hinder water leakage, and the only structure that can hinder water leakage is the web 52 .
[0037] The concrete cushion layers 8 on both sides of the first drainage ditch 4 and the finishing layer 7 above them form a right-angle groove, such as Figure 2 During the chiseling construction, the width of the concrete cushion layer 8 is smaller than the width of the finishing layer 7, so that a right-angle groove can be formed, which can be used to support the cover plate structure 10.
[0038] The surface of the right-angle groove formed by chiseling is not smooth, and the cover plate structure 10 placed on it may not necessarily play a supporting role. For this reason, an angle steel 3 adapted to it is provided in the right-angle groove, and the angle steel 3 is fixed to the right-angle groove by expansion bolts or other technical means. Since the surface of the angle steel 3 is smooth, it can ensure that it can provide good support for the cover plate structure 10. It is not difficult to understand that the upper surface of the upper wing plate 51 and the surface of the angle steel are at the same level.
[0039] Some structural joints are deformation joints, and the spacing may change. The cover plate structure 10 is in free contact with the support unit and the right-angle groove, and can change with the change of the joint to prevent the first drainage ditch 4 from being damaged.
[0040] like Figure 2 As shown, a waterproof layer 2 is provided on the exposed surface of the concrete cushion layer 8 facing the first drainage ditch 4 . The waterproof layer 2 can be realized by coating a waterproof coating to prevent water in the first drainage ditch 4 from leaking into the decoration layer 7 .
[0041] A pipe is buried in the second drainage ditch 6, and the leaked water of the first drainage ditch 4 is drained to the drainage network through the pipe. The structure of the second drainage ditch 6 is not as complicated as that of the first drainage ditch, and the pipe can be buried by chiseling a small part of the ground. In some other embodiments, existing drainage ditches can also be used, but not all of them can be used, and they should be used according to the site conditions.
[0042] Example 2
[0043] This embodiment provides a construction method of the existing rail transit station structural joint drainage structure as described in Embodiment 1, comprising the following steps:
[0044] Chisel away the original decoration layer 7 and concrete cushion layer 8 of a set width above the structural joint 1 where water leakage occurs, exposing both sides of the concrete cushion layer 8 and the civil structure layer 9. The width of the decoration layer 7 chiseled away is selected to be 400-600mm, and the width of the concrete cushion layer 8 is smaller than the width of the decoration layer 7 chiseled away, about 20-50mm smaller, to form a right-angle groove, and a supporting unit is arranged on the civil structure layer 9 to support the cover structure 10 to form a first drainage ditch 4; a second drainage ditch 6 is opened at the end of the first drainage ditch 4, a pipe is buried in the second drainage ditch 6, and then it is re-covered to discharge the leaking water of the first drainage ditch 4 to the drainage network through the second drainage ditch 6.
[0045] Although the present invention has been disclosed as above in the form of a preferred embodiment, it is not intended to limit the present invention. Any person skilled in the art may make possible changes and modifications to the technical solution of the present invention by using the methods and technical contents disclosed above without departing from the spirit and scope of the present invention. Therefore, any simple modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solution of the present invention shall fall within the protection scope of the technical solution of the present invention.
Claims
1. A construction method for drainage structure of existing rail transit station structure joints, characterized in that: A drainage structure for the structural seams of existing rail transit stations is adopted, including: A first drainage ditch is embedded in the concrete cushion layer above the structural joint, the bottom of the drainage ditch is connected to the structural joint, the top is covered with a cover structure flush with the ground, and two rows of support units are arranged between the top and the bottom along the drainage direction and used to support the cover structure, the two rows of support units are arranged on both sides of the structural joint, each row of support units includes a plurality of support units, and gaps are arranged between the support units in each row; When the leakage is small, a continuous support unit is used, which divides the first drainage ditch into three chambers, each of which works independently; when the leakage is large, it is difficult to ensure that the leakage water flows out in time, and a support unit with gaps is used, and the three chambers are interconnected, which can increase the speed of leakage water discharge; the second drainage ditch, one end of which is connected to the first drainage ditch, and the other end is connected to the drainage network; A waterproof layer is provided on the exposed surface of the concrete cushion layer facing the first drainage ditch; The support unit is an I-beam, and the lower wing plate of the I-beam is buried in the civil structure layer below the first drainage ditch; the I-beam is cut into sections, each section is a support unit, and the I-beam includes an upper wing plate, a web plate and a lower wing plate. Since the wing plate has a large force-bearing area, it is conducive to uniformly supporting the cover plate structure, and the narrow web plate is conducive to the flow of leaking water, and will not cause excessive obstruction to the leaking water; The method comprises the following steps: Chisel away the original decoration layer and concrete cushion layer with a set width above the structural joint where water seepage occurs, exposing both sides of the concrete cushion layer and the civil engineering structure layer; Select continuous support units or gap support units according to the amount of water leakage; arrange support units on the civil structure layer to support the cover plate structure to form a first drainage ditch; A second drainage ditch is opened at the end of the first drainage ditch, and the leaked water of the first drainage ditch is drained to the drainage network through the second drainage ditch.
2. The construction method of the drainage structure of the existing rail transit station structure joint according to claim 1, characterized in that: The concrete cushion layers on both sides of the first drainage ditch and the finishing layer thereon form right-angle grooves, and the right-angle grooves are used to support the cover plate structure.
3. A construction method for a drainage structure of a structural seam of an existing rail transit station as claimed in claim 2, characterized in that: An angle steel adapted to the right-angle groove is arranged in the right-angle groove.
4. The construction method of the drainage structure of the existing rail transit station structure according to claim 2, characterized in that: The cover plate structure is in free contact with both the support unit and the right-angle groove.
5. The construction method of the drainage structure of the existing rail transit station structure joint according to claim 1, characterized in that: The cover plate structure is a stainless steel edged floor tile.
6. The construction method of the drainage structure of the existing railway station structure joint according to claim 1, characterized in that: A pipe is buried in the second drainage ditch, and the leaked water from the first drainage ditch is drained to the drainage network through the pipe.