Experimental device and method for dynamic film formation of slurry under the cutting action of shield cutterhead
By designing a test device containing multiple systems to simulate the dynamic film formation of mud caused by cutterhead cutting during the shield tunneling process, the problem that the existing technology cannot truly simulate the mud film formation during the shield tunneling process is solved, and it provides a solution to the problem. Research on the influence of shield tunneling parameters guides shield construction safety and material optimization.
Patent Information
- Application Number
- CN202210360132.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-04-07
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2042-04-07
AI Technical Summary
The existing shield mud film formation test device cannot truly simulate the dynamic film formation under the cutting action of the cutterhead during the shield tunneling process, and cannot effectively test the penetration and stability of mud in complex formations.
A test device including a soil excavation cabin model, a mud circulation system, data acquisition and control equipment, a seepage pressure sensor, a soil dynamic resistivity monitoring system, a cutting jacking system and a suction and slag extraction system was designed, which can simulate shield tunneling During the excavation process, the cutterhead cutting causes the dynamic film formation process of the mud, and the penetration and film formation rules of the mud under different conditions are studied through data collection and analysis.
This device can truly simulate the dynamic film formation of mud during shield excavation, provide research on the impact of shield excavation parameters (excavation speed, cutterhead speed and mud pressure) on the stability of the excavation surface, and guide shield excavation. Structural construction safety and optimal selection of mud materials.
Smart Images

Figure CN114813481B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of shield machines, and in particular to a test device and method for dynamic film formation of mud under the cutting action of a shield cutter head. Background Art
[0002] In recent years, as underwater tunnels develop towards length, size and depth, the construction process of slurry shield will inevitably pass through various complex strata, especially sand, gravel and pebble strata with strong permeability, low cohesion and poor stability. The slurry pressure on the shield excavation face is difficult to maintain, which can easily cause the shield excavation face to become unstable. The shield slurry film formation is the key to the stability of the excavation face. According to the investigation, the current research on the proportion of shield slurry film materials is mainly based on static film formation tests. Under the cutting action of the cutterhead, the mud film is always in the process of formation-destruction-reformation, which is a dynamic film formation process. The static film formation test results cannot be fully applied to the dynamic film formation of the shield. In addition, the current shield slurry film formation test devices are mostly vertical, while the shield excavation process is a horizontal excavation process. The vertical test device cannot fully and truly simulate the shield excavation process. There is no test device and method in the prior art that effectively considers the dynamic film formation of slurry under the cutting action of the shield cutterhead. Summary of the invention
[0003] The embodiments of the present invention provide a test device and method for dynamic film formation of mud under the cutting action of a shield cutter head, so as to overcome the problem that the existing test devices and methods are not applicable to the dynamic film formation test of shield tunneling mud, which has guiding significance for the safety of shield tunneling construction.
[0004] In order to achieve the above object, the present invention adopts the following technical scheme.
[0005] According to one aspect of the present invention, there is provided a test device for dynamic film formation of mud under the cutting action of a shield cutter head, comprising a soil excavation chamber model device, a mud circulation system, a data acquisition and control device, a seepage pressure sensor, a soil dynamic resistivity monitoring system, a cutting and jacking system, and a stirring and suction slag removal system;
[0006] The mud circulation system can replenish fresh slurry and recycle waste slurry and soil in time, the soil dynamic resistivity monitoring system monitors the changes in sand sample resistivity, the data acquisition control equipment and seepage pressure sensor monitor the changes in pore water pressure of the formation, the stirring and suction slag removal system discharges the slag generated by excavation, and the cutting and jacking system uses two power sources to control the rotation of the cutter head and the jacking of the tool respectively.
[0007] Preferably, the device further comprises: a soil excavation chamber model device, which is made of a super-strong lightweight alloy material and can withstand 2.0 MPa water and soil pressure, and has local high-pressure glass windows for easy observation of test phenomena.
[0008] Preferably, the device also includes: an electrode ring on the side wall of the soil excavation chamber model device, which is used for dynamic resistivity monitoring and is installed on the side wall of the soil excavation chamber model device to perform dynamic cyclic scanning on sand samples within the range and monitor changes in the resistivity of the sand samples.
[0009] Preferably, the device further comprises: a stirring and suction slag removal system, which is located at the bottom of the excavation chamber, and the excavated soil is discharged from the excavation chamber by a stirring and suction pump, thereby reducing the forward resistance of the cutterhead and controlling the purity of the mud.
[0010] Preferably, the device also includes: a cutting and jacking system, which is composed of a cutter and a center cutter. The cutter disc is in a cross form and is consistent with the inner diameter of the soil excavation chamber model device. The center cutter is installed at the center of the cutter disc, and the cutters are symmetrically arranged under the four bar shafts of the cutter disc to ensure the balance of the cutter disc during the test. The rotation of the cutter disc and the jacking of the tool are controlled by two power sources respectively.
[0011] Preferably, the seepage pressure sensor is installed on the side wall of the soil excavation chamber model device at a certain interval, and the seepage pressure sensor is saturated with silicone oil before the test.
[0012] According to another aspect of the invention, a test method for dynamic film formation of slurry under the cutting action of a shield cutter head is provided, characterized in that it is applicable to the device described above and comprises the following steps:
[0013] A. Connect and assemble the test device and data acquisition control equipment. Use electric welding to weld the electrode ring joints and resistivity test wires on the soil excavation chamber model device to ensure the stability of the resistivity test value during the test. Install the seepage pressure sensor saturated with silicone oil on the side wall of the soil excavation chamber model device, and use a syringe to inject silicone oil into the gap at the front end of the seepage pressure sensor. Then, stick the filter saturated with silicone oil to the side wall surface of the soil excavation chamber model device at the front end of the seepage pressure sensor to prevent formation particles and mud from entering the seepage pressure sensor during sample preparation and mud infiltration, thereby affecting data acquisition.
[0014] B. Prepare the sample stratum and mud. According to the porosity of the test stratum to be controlled, weigh a certain mass of sand of various particle size ranges in proportion (the sand should be dried before use), mix evenly and fill it into the soil excavation chamber model device. Prepare mud according to a certain proportion of bentonite and tap water, and stir evenly with an electric mixer. Prepare a CMC solution of a certain concentration by water bath method. During the preparation process, control the solution temperature at about 50°C to accelerate the dissolution of CMC powder, pour it into the bentonite mud, stir evenly, and then let it stand for more than 24 hours.
[0015] C. Saturated sample. After preparing the sand sample, use a saturation container to saturate the sample. Make sure that the sample is saturated slowly. When the liquid level is flush with the surface of the sand sample, the sample is considered saturated. The saturation time is approximately 24 hours, which varies depending on the permeability of the sample.
[0016] D. Filling the slurry tank and sealing the soil excavation chamber model device. Before the test begins, ensure that the slurry control valve is in the closed state, and slowly fill the prepared slurry into the slurry tank until the upper cover of the slurry tank is in place. Fix the soil excavation chamber model device on the fixed support of the device, install the cutting tool of the jacking system, and the sealing device.
[0017] E. Set up the pressure control and data acquisition control equipment. Open the pressure regulating valve and set the gas source output pressure. Set the percolation water collection time interval. Open the data acquisition control equipment, set the data collection interval, and record the initial data. Open the dynamic resistivity test software, adjust the resistivity test gear and collection time interval, and start the test.
[0018] F. Start mud infiltration. Open the slurry control valve and the drain valve of the soil excavation chamber model device to fill the soil excavation chamber model device with slurry, and infiltrate the sand sample with pressurized mud. In the mud static permeation film-forming test, when the quality of the percolation water gradually stabilizes (less than 1g of percolation water is discharged per minute), close the drain valve to end the mud infiltration. It should be noted that when the permeability of the formation is large, under the action of pressure, the collected percolation water is basically turbid, or even original mud, and the test is stopped. This indicates that the mud forms a phenomenon similar to mud leakage in the formation and cannot form a film in time. In the mud dynamic penetration film-forming test, after the mud has penetrated for 1 hour, the cutter disc cutting parameters (rotation speed, jacking speed and jacking distance) are set to make the cutter disc rotate at a uniform speed and advance forward to cut the stratum. The agitator and suction head device is turned on to discharge the debris produced by excavation until the tool cutting depth reaches the designed excavation depth. The cutter disc stops excavating. After the quality of the seepage water gradually stabilizes (the amount of seepage water discharged per minute is less than 1g), the drain pipe valve is closed and a set of tests is completed.
[0019] G. Collect sand samples. After the mud static permeability film test is completed, the stratum is excavated and sand samples are collected from 0-2cm, 2-4cm, 4-6cm, 6-8cm and 8-10cm below the stratum surface. The sand samples are placed in a sample box and dried for 24 hours, and then the total mass of the sand sample and the sample box is weighed and recorded. The sand samples are washed several times until the water after washing is clear, and the washed sand samples are dried for 24 hours, and then the total mass of the clean sand samples and the sample box is weighed.
[0020] H. Analyze test data. Process the pore water pressure, soil resistivity and percolation water flow collected during the test and analyze the sampling results after the test.
[0021] I. In order to explore the effects of tool cutting frequency, tool cutting depth and mud pressure on mud penetration and film formation in sandy soil formations, the cutter head speed, excavation speed and mud pressure were changed, the mud materials and proportions were changed, the BF steps were repeated, and the test data were recorded and sorted out until the end of the test to determine the optimal mud material proportion.
[0022] Preferably, the method further comprises:
[0023] The power source is used to automatically control the rotation of the cutter head and the advancement of the cutter 7, and the speed and displacement control is used to achieve the effect of the cutter on the penetration and film formation of the mud in the sandy soil layer;
[0024] The monitoring system connected to the seepage pressure sensor on the side wall of the soil excavation chamber model device records in real time the changes in the pore water pressure of the sandy soil layer during the mud penetration film forming and tool cutting sandy soil layer test processes.
[0025] Preferably, the method further comprises:
[0026] The soil dynamic resistivity monitoring system connected to the electrode ring on the side wall of the soil excavation chamber model device records the changes in the resistivity of the sandy soil layer during the mud penetration film forming test in real time.
[0027] Preferably, the method further comprises:
[0028] The water collecting bucket is placed on a balance connected to a seepage pressure sensor to record in real time the changes in the amount of filtered water during the mud penetration film formation and tool cutting sandy strata tests.
[0029] It can be seen from the technical solution provided by the above-mentioned embodiments of the present invention that the device of the present invention can more realistically simulate the disturbance effect of the shield cutter on the excavation face and the mud penetration and film-forming process during the excavation of the slurry shield, further study the influence of the slurry shield excavation parameters (excavation speed, cutter head rotation speed and mud pressure) on the dynamic film-forming law and characteristics of the mud on the excavation face, and propose the requirements for the selection and configuration of mud materials during the dynamic excavation period of the slurry shield. The present invention has guiding significance for the safety of shield excavation. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the accompanying drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the accompanying drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other accompanying drawings can be obtained based on these accompanying drawings without paying creative work.
[0031] Figure 1 A schematic diagram of the structure of a test device for dynamic film formation of slurry under the cutting action of a shield cutter head provided in an embodiment of the present invention;
[0032] Figure 2 A three-dimensional diagram and a side view of a cutting disc and a tool provided in an embodiment of the present invention.
[0033] The numbers in the figure represent:
[0034] 1-power source; 2-agitation and suction head, 3-pressure gauge, 4-sealing cover of soil excavation chamber model device, 5-slurry control valve, 6-slurry inlet pipe, 7-cutting tool, 8-fixing bolt, 9-soil excavation chamber model device, 10-electrode ring, 11-seepage pressure sensor; 12-pressure regulating valve, 13-slurry storage tank, 14-gas generating device; 15-drain valve, 16-drain pipe, 17-water collecting bucket, 18-balance; 19-device fixing support; 20-data acquisition and control equipment, 21-computer. DETAILED DESCRIPTION
[0035] The embodiments of the present invention are described in detail below, examples of which are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present invention, and cannot be interpreted as limiting the present invention.
[0036] It will be understood by those skilled in the art that, unless expressly stated, the singular forms "one", "said", and "the" used herein may also include plural forms. It should be further understood that the term "comprising" used in the specification of the present invention refers to the presence of the features, integers, steps, operations, elements and / or components, but does not exclude the presence or addition of one or more other features, integers, steps, operations, elements, components and / or groups thereof. It should be understood that when we refer to an element as being "connected" or "coupled" to another element, it may be directly connected or coupled to the other element, or there may be intermediate elements. In addition, the "connection" or "coupling" used herein may include wireless connection or coupling. The term "and / or" used herein includes any unit and all combinations of one or more associated listed items.
[0037] It will be understood by those skilled in the art that, unless otherwise defined, all terms (including technical and scientific terms) used herein have the same meaning as those generally understood by those skilled in the art in the art to which the present invention belongs. It should also be understood that terms such as those defined in common dictionaries should be understood to have meanings consistent with the meanings in the context of the prior art, and will not be interpreted with idealized or overly formal meanings unless defined as herein.
[0038] To facilitate understanding of the embodiments of the present invention, several specific embodiments will be further explained below with reference to the accompanying drawings, and each embodiment does not constitute a limitation on the embodiments of the present invention.
[0039] Figure 1 A schematic diagram of the structure of a test device for dynamic film formation of slurry under the cutting action of a shield cutter head provided in an embodiment of the present invention, Figure 2 A three-dimensional diagram and a side view of a cutting disc and a tool provided in an embodiment of the present invention. The above-mentioned device includes a soil excavation chamber model device 9, a sealing cover 4 fixed to the soil excavation chamber model device by bolts 8, a seepage pressure sensor 11 installed on the side wall of the soil excavation chamber model device, an electrode ring 10, a stirring suction head 2, a barometer 3 installed on the sealing cover of the soil excavation chamber model device, a power source 1 fixed to the device fixed support 19, a slurry control valve 5 connected to the slurry inlet hole, a slurry inlet pipe 6, a slurry storage tank 13, a pressure regulating valve 12 installed on the top of the slurry storage tank, a gas generating device 14 connected to the pressure regulating valve, a drainage valve 15 fixed to the soil excavation chamber model device, a drainage pipe 16 connected to the drainage valve, a water collecting bucket 17, a balance 18, a data acquisition control device 20 connected to the seepage pressure sensor and the balance, a computer 21 connected to the data acquisition control device, and a cutting tool 7 rotatably connected to the power source and placed in the soil excavation chamber model device, wherein the cutting tool 7 is driven by the power source 1 to advance forward.
[0040] Specifically, the power source 1 is composed of two stepper motors, which can automatically control the rotation of the cutter head and the thrust of the cutter 7, thereby realizing the influence of the cutting tool 7 on the slurry penetration and film formation in the sandy soil layer through speed and displacement control.
[0041] Specifically, the monitoring system connected to the seepage pressure sensor 11 records the changes of the pore water pressure of the sandy soil layer during the test in real time.
[0042] Specifically, the soil dynamic resistivity monitoring system connected to the electrode ring 10 records the change of the resistivity of the sand layer during the test in real time.
[0043] Specifically, the slurry control valve 5 controls the inflow and outflow of slurry.
[0044] Specifically, the pressure regulating valve 12 controls the mud pressure in the soil excavation chamber model device.
[0045] Specifically, the drainage valve 15 controls the water injection rate to prevent the formation from being disturbed and controls the time when the percolation water is measured.
[0046] Specifically, the water collecting bucket 17 is placed on a balance 18 connected to a seepage pressure sensor to record in real time the change in the amount of water filtered from the sandy soil layer during the test.
[0047] Specifically, the seepage pressure sensor 11 is installed on the side wall of the soil excavation chamber model device at a certain interval.
[0048] Specifically, the seepage pressure sensor 11 should be saturated with silicone oil before the test to achieve the purpose of excluding air.
[0049] Specifically, the seepage pressure sensor 11 is pasted with geotextile at the opening of the side wall of the soil excavation chamber model device to prevent sand and mud particles from entering the interior and affecting its measurement accuracy.
[0050] Specifically, the electrode ring 10 is a copper wire arranged at the groove of the side wall of the soil excavation chamber model device.
[0051] Specifically, the electrode ring 10 performs dynamic cycle scanning on the sand sample within the range to perform real-time monitoring.
[0052] Figure 2 The three-dimensional diagram and side view of a cutting disc and a tool provided by an embodiment of the present invention are shown in FIG. Specifically, the cutter disc in the cutting tool 7 is in the form of a cross, and its diameter is consistent with the inner diameter of the soil excavation chamber model device.
[0053] Specifically, the cutting tool 7 is equipped with a cutter and a center knife (18 cutters and 1 center knife) under the cutter disc. The center knife is installed at the center of the cutter disc, and the cutters are symmetrically arranged under the four bar shafts of the cutter disc to ensure the balance of the cutter disc during the test.
[0054] Furthermore, the test materials required for the test are mainly composed of two parts: mud material and formation material. All of the above materials need to be prepared before the test. The mud material is mainly composed of bentonite, water and sodium carboxymethyl cellulose (CMC) solution. The formation material for the mud permeation film test can be standard sand. In order to control the particle size and gradation of the formation, the standard sand is screened to obtain a variety of sands with different particle size ranges, which are combined in a certain proportion to prepare the formation material for the test.
[0055] Furthermore, the mud penetration film forming test is carried out using the above-mentioned self-designed mud penetration film forming device. The mud penetrates into the sand sample under a specific pressure and gradually forms a mud film on the surface of the sample. During the test, the pore water pressure, percolation water flow rate, and soil resistance of the sand sample are monitored and data collected in real time until the end of the test.
[0056] Furthermore, the test on dynamic film formation of mud under the cutting action of shield cutter disc is aimed at exploring the influence of tool cutting frequency, tool cutting depth and mud pressure on the penetration and film formation of mud in sandy strata. By changing the three factors of cutter disc rotation speed, excavation speed and mud pressure, different test conditions are designed, and multiple groups of dynamic film formation tests on mud under the cutting action of shield cutter disc are carried out.
[0057] Furthermore, the test of dynamic film formation of mud under the cutting action of the shield cutter head is to set the cutter head rotation speed and excavation speed after the mud penetration is stable, so that the cutter head rotates at a uniform speed and pushes forward to cut the stratum until the tool cutting depth reaches the designed excavation depth, that is, the seepage water valve is closed to end this group of tests.
[0058] like Figure 1 As shown, the power source 1 automatically controls the rotation of the cutter head and the advancement of the cutter 7, thereby realizing the influence of the cutting tool 7 on the mud penetration film formation in the sandy soil layer through speed and displacement control. The monitoring system connected to the seepage pressure sensor 11 on the side wall of the soil excavation chamber model device records in real time the changes in the pore water pressure of the sandy soil layer during the mud penetration film formation and the tool cutting sandy soil layer test process. The soil dynamic resistivity monitoring system connected to the electrode ring 10 on the side wall of the soil excavation chamber model device records in real time the changes in the resistivity of the sandy soil layer during the mud penetration film formation test process. The water collection bucket 17 is placed on a balance 18 connected to the seepage pressure sensor, which records in real time the changes in the amount of filtered water during the mud penetration film formation and the tool cutting sandy soil layer test process.
[0059] Furthermore, the test device can conduct the following research during the mud penetration film test: ① The test device studies the penetration distance of the same mud in different sandy soil layers, so as to further study the relationship between the particle size characteristics of the formation and the mud penetration loss; ② Whether the mud pressure can be quickly and effectively converted into effective stress of the soil and act on the excavation surface or the soil within a certain range in front of the excavation surface is the key to the slurry shield to maintain the stability of the excavation surface. The test device can study the distribution of the effective conversion rate of mud pressure along the depth direction of the soil excavation chamber model device under different mud penetration times; ③ The test device can study the change of the formation permeability coefficient with the mud penetration time through the data recorded by the pore water pressure gauge; ④ After the test is completed, the soil at different depths of the formation is sampled, and the dried sand-mud mixture is photographed and weighed. The test device can study the distribution of the proportion of mud particle retention in the formation; ⑤ The test device can study the resistivity characteristics of mud penetration soil, and the soil resistivity and mud concentration calibration test is adopted to analyze the soil resistivity under different mud concentrations.
[0060] Furthermore, the test device can conduct the following research during the test process of dynamic film formation of mud under the cutting action of the shield cutter: ① The test device can study the relationship between the amount of infiltration water and the tool cutting time under different mud pressure conditions; ② The test device can respectively study the relationship between the tool cutting time and the effective conversion rate of mud pressure under different cutter head rotation speeds, different excavation speeds and different mud pressures; ③ The test device can study the relationship between the proportion of surface mud film formation time in the tool cutting interval time and the number of tool cutting times and the relationship between the ratio of the mud secondary penetration film forming time to the mud penetration film forming time in the clean sandy soil layer and the tool cutting time interval; ④ The test device can study the relationship between the amount of mud particle deposition on the soil surface and the tool cutting time; ⑤ The test device can study the relationship between the amount of infiltration water and the tool cutting time; ⑥ The test device can study the relationship between the effective conversion rate of mud pressure and the tool cutting interval time.
[0061] Based on the above-mentioned test device for dynamic film formation of slurry under the cutting action of shield cutter head, the embodiment of the present invention further provides a new test method for dynamic film formation of slurry under the cutting action of shield cutter head, comprising the following steps:
[0062] A. Connect and assemble the test device and data acquisition control equipment. Use electric welding to weld the electrode ring joints and resistivity test wires on the soil excavation chamber model device to ensure the stability of the resistivity test value during the test. Install the seepage pressure sensor saturated with silicone oil on the side wall of the soil excavation chamber model device, and use a syringe to inject silicone oil into the gap at the front end of the seepage pressure sensor. Then, stick the filter saturated with silicone oil to the side wall surface of the soil excavation chamber model device at the front end of the seepage pressure sensor to prevent formation particles and mud from entering the seepage pressure sensor during sample preparation and mud infiltration, thereby affecting data acquisition.
[0063] B. Prepare the sample stratum and mud. According to the porosity of the test stratum to be controlled, weigh a certain mass of sand of various particle size ranges in proportion (the sand should be dried before use), mix evenly and fill it into the soil excavation chamber model device. Prepare mud according to a certain proportion of bentonite and tap water, and stir evenly with an electric mixer. Prepare a CMC solution of a certain concentration by water bath method. During the preparation process, control the solution temperature at about 50°C to accelerate the dissolution of CMC powder, pour it into the bentonite mud, stir evenly, and then let it stand for more than 24 hours.
[0064] C. Saturated sample. After preparing the sand sample, use a saturation container to saturate the sample. Make sure that the sample is saturated slowly. When the liquid level is flush with the surface of the sand sample, the sample is considered saturated. The saturation time is approximately 24 hours, which varies depending on the permeability of the sample.
[0065] D. Filling the slurry tank and sealing the soil excavation chamber model device. Before the test begins, ensure that the slurry control valve is in the closed state, and slowly fill the prepared slurry into the slurry tank until the upper cover of the slurry tank is in place. Fix the soil excavation chamber model device on the fixed support of the device, install the cutting tool of the jacking system, and the sealing device.
[0066] E. Set up the pressure control and data acquisition control equipment. Open the pressure regulating valve and set the gas source output pressure to 50kPa. Set the percolation water collection time interval to 0.5s. Open the data acquisition control equipment, set the data collection interval to 0.2s, and record the initial data. Open the dynamic resistivity test software, adjust the resistivity test gear to 1kΩ, the collection time interval to 0.2s, and start the test.
[0067] F. Start mud infiltration. Open the slurry control valve and the drain valve of the soil excavation chamber model device to fill the soil excavation chamber model device with slurry, and infiltrate the sand sample with pressurized mud. In the mud static permeation film-forming test, when the quality of the percolation water gradually stabilizes (less than 1g of percolation water is discharged per minute), close the drain valve to end the mud infiltration. It should be noted that when the permeability of the formation is large, under the action of pressure, the collected percolation water is basically turbid, or even original mud, and the test is stopped. This indicates that the mud forms a phenomenon similar to mud leakage in the formation and cannot form a film in time. In the mud dynamic penetration film-forming test, after the mud has penetrated for 1 hour, the cutter disc cutting parameters (rotation speed, jacking speed and jacking distance) are set to make the cutter disc rotate at a uniform speed and advance forward to cut the stratum. The agitator and suction head device is turned on to discharge the debris produced by excavation until the tool cutting depth reaches the designed excavation depth. The cutter disc stops excavating. After the quality of the seepage water gradually stabilizes (the amount of seepage water discharged per minute is less than 1g), the drain pipe valve is closed and a set of tests is completed.
[0068] G. Collect sand samples. After the mud static permeability film test is completed, the stratum is excavated and sand samples are collected from 0-2cm, 2-4cm, 4-6cm, 6-8cm and 8-10cm below the stratum surface. The sand samples are placed in a sample box and dried for 24 hours, and then the total mass of the sand sample and the sample box is weighed and recorded. The sand samples are washed several times until the water after washing is clear, and the washed sand samples are dried for 24 hours, and then the total mass of the clean sand samples and the sample box is weighed.
[0069] H. Analyze test data. Process the pore water pressure, soil resistivity and percolation water flow collected during the test and analyze the sampling results after the test.
[0070] I. In order to explore the influence of tool cutting frequency, tool cutting depth and mud pressure on mud penetration and film formation in sandy soil strata, the cutter head speed, excavation speed and mud pressure were changed. The cutter head speed was set to 0.5, 1.0 and 2.0 (r / min), the excavation speed was set to 10, 15 and 20 (mm / min), and the mud pressure was set to 50, 70 and 90 (kPa). The BG steps were repeated, and the test data were recorded and organized until the end of the test.
[0071] In summary, the device of the embodiment of the present invention can study the dynamic permeation-film formation law of mud in sandy soil strata; in addition, the device can fully consider the influence of shield cutter cutting on the mud support pressure mechanism of the excavation face, and then analyze the stable limit support pressure of the excavation face and the excavation face stability control problem during the slurry shield tunneling period. Based on the test device involved in the present invention, a relatively complete test method for the dynamic film formation of mud under the action of shield cutter cutting is provided, which provides a new idea for studying the influence of shield cutter cutting on the mud support pressure mechanism of the excavation face.
[0072] The device of the embodiment of the present invention can more realistically simulate the disturbance effect of the shield cutter on the excavation face and the mud penetration film-forming process during the excavation of the slurry shield. It can further analyze the influence of the slurry shield excavation parameters (excavation speed, cutter head rotation speed and mud pressure) on the film-forming law and characteristics of the excavation face. Finally, a comprehensive analysis can be made on the stable limit support pressure of the excavation face and the excavation face stability control problem during the slurry shield excavation period.
[0073] Those skilled in the art can understand that the accompanying drawings are only schematic diagrams of an embodiment, and the modules or processes in the accompanying drawings are not necessarily required to implement the present invention.
[0074] Each embodiment in this specification is described in a progressive manner, and the same or similar parts between the embodiments can be referred to each other, and each embodiment focuses on the differences from other embodiments. In particular, for the device or system embodiment, since it is basically similar to the method embodiment, the description is relatively simple, and the relevant parts can be referred to the partial description of the method embodiment. The device and system embodiments described above are merely schematic, wherein the units described as separate components may or may not be physically separated, and the components displayed as units may or may not be physical units, that is, they may be located in one place, or they may be distributed on multiple network units. Some or all of the modules may be selected according to actual needs to achieve the purpose of the scheme of this embodiment. Ordinary technicians in this field can understand and implement it without paying creative labor.
[0075] The above is only a preferred specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that can be easily thought of by a person skilled in the art within the technical scope disclosed by the present invention should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.
Claims
1. A test method for dynamic film formation of slurry under the cutting action of shield cutter head, characterized in that: The following steps are involved: A. Connect and assemble the test device and data acquisition control equipment, weld the electrode ring joint and resistivity test line on the soil excavation chamber model device by electric welding, install the seepage pressure sensor saturated with silicone oil on the side wall of the soil excavation chamber model device, and inject silicone oil into the gap in front of the seepage pressure sensor with a syringe, and then stick the filter saturated with silicone oil on the side wall surface of the soil excavation chamber model device in front of the seepage pressure sensor; B. Prepare the sample stratum and mud. According to the porosity of the test stratum to be controlled, weigh a certain mass of sand and soil of various particle size ranges in proportion, mix them evenly and fill them into the soil excavation chamber model device. Prepare mud according to a certain proportion of bentonite and tap water, and stir them evenly with an electric stirrer. Prepare a certain concentration of CMC solution by water bath method. During the preparation process, control the solution temperature at 50°C to accelerate the dissolution of CMC powder, pour it into the bentonite mud, stir it evenly, and then let it stand for expansion for more than 24 hours; C. Saturated sample: after preparing the sand sample, use a saturated container to saturate the sample; D. Fill the slurry storage tank and seal the soil excavation chamber model device, slowly fill the prepared slurry into the slurry storage tank until the upper cover plate of the slurry storage tank is located, fix the soil excavation chamber model device, and install the cutting tool of the cutting jacking system; E. Set up the pressure control and data acquisition control equipment, open the pressure regulating valve, set the gas source output pressure, set the percolation water collection time interval, open the data acquisition control equipment, set the data collection interval, and record the initial data, open the dynamic resistivity test software, adjust the resistivity test gear and collection time interval, and start the test; F. Start mud infiltration, open the slurry control valve and the drain valve of the soil excavation chamber model device, so that the slurry fills the soil excavation chamber model device, and the pressurized mud infiltrates into the sand sample. In the mud static infiltration film test, when the quality of the percolation water is stable, close the drain valve to end the mud infiltration; in the mud dynamic infiltration film test, after the mud infiltrates for 1 hour, set the cutterhead cutting parameters to make the cutterhead rotate at a uniform speed and excavate forward to cut the stratum, open the stirring and suction head device, discharge the debris generated by excavation, until the cutting depth of the tool reaches the designed excavation depth, the cutterhead stops excavation, and after the quality of the percolation water gradually stabilizes, close the drain valve, and a set of tests ends; G. Collect sand samples. After the mud static permeability film test is completed, the stratum is excavated and sand samples are collected from 0-2cm, 2-4cm, 4-6cm, 6-8cm and 8-10cm below the stratum surface. The sand samples are placed in a sample box and dried for 24 hours. The total mass of the sand sample and the sample box is then weighed and recorded. The sand sample is washed several times until the water after washing is clear. The washed sand sample is dried for 24 hours, and the total mass of the clean sand sample and the sample box is then weighed. H. Analyze test data, process the pore water pressure, soil resistivity and percolation water flow collected during the test, and analyze the sampling results after the test; I. In order to explore the effects of tool cutting frequency, tool cutting depth and mud pressure on mud penetration and film formation in sandy soil formations, the cutter head speed, excavation speed and mud pressure were changed, the mud materials and proportions were changed, the BF steps were repeated, and the test data were recorded and sorted out until the end of the test to determine the optimal mud material proportion.
2. The method according to claim 1, characterized in that: The method further comprises: The power source consists of two stepper motors, which automatically control the rotation of the cutter head and the thrust of the cutter. The speed and displacement control is used to control the effect of the cutting tool on the penetration and film formation of mud in the sandy soil layer. The monitoring system connected to the seepage pressure sensor on the side wall of the soil excavation chamber model device records in real time the changes in the pore water pressure of the sandy soil layer during the mud penetration film forming and tool cutting sandy soil layer test processes.
3. The method according to claim 2, characterized in that The method further comprises: The soil dynamic resistivity monitoring system connected to the electrode ring on the side wall of the soil excavation chamber model device records the changes in the resistivity of the sandy soil layer during the mud penetration film forming test in real time.
4. The method according to claim 3, characterized in that The method further comprises: The water collecting bucket is placed on a balance connected to a seepage pressure sensor to record in real time the changes in the amount of filtered water during the mud penetration film formation and tool cutting sandy strata tests.
5. A test device for dynamic film formation of slurry under the cutting action of shield cutter head, characterized in that: An experimental method for dynamic film formation of slurry under the cutting action of a shield cutter head as described in any one of claims 1 to 4, wherein the device comprises a soil excavation chamber model device, a slurry circulation system, a data acquisition and control device, a seepage pressure sensor, a soil dynamic resistivity monitoring system, a cutting and jacking system, and a stirring and suction slag removal system; A sand sample is placed in the soil excavation chamber model device, the mud circulation system replenishes fresh slurry to the soil excavation chamber model device and recovers waste slurry and soil, the soil dynamic resistivity monitoring system is used to monitor the change of the resistivity of the sand sample in the soil excavation chamber model device, the data acquisition control equipment and the seepage pressure sensor monitor the change of the pore water pressure of the formation, the cutting and jacking system is a toothed tool, which uses two power sources to control the rotation of the cutter head and the jacking of the tool respectively, so as to cut the mud in the soil excavation chamber model device, and the agitation and suction slag discharge system discharges the slag generated by excavation.
6. The device according to claim 5, characterized in that The soil excavation chamber model device is made of super-strong lightweight alloy material, can withstand 2.0MPa water and soil pressure, and is partially provided with ribbed high-pressure glass windows.
7. The device according to claim 5, characterized in that The soil dynamic resistivity monitoring system installs an electrode ring on the side wall of the soil excavation chamber model device, performs dynamic cyclic scanning on the sand and soil samples within the range, and monitors the change of the mud infiltration distance.
8. The device according to claim 5, characterized in that The stirring and suction slag discharge system is located at the bottom of the excavation chamber, and the excavated soil is discharged from the excavation chamber by a stirring and suction pump.
9. The device according to claim 5, characterized in that The cutting and jacking system consists of a 20° blade angle tooth cutter and a 50° blade angle center cutter. The cutter disc adopts a cross shape, which is consistent with the inner diameter of the soil excavation chamber model device. The 50° blade angle center cutter is installed at the center of the cutter disc, and the 20° blade angle tooth cutters are symmetrically arranged under the four strip shafts of the cutter disc. Two power sources control the rotation of the cutter disc and the jacking of the tool respectively.
10. The device according to claim 5, characterized in that The seepage pressure sensor is installed on the side wall of the soil excavation chamber model device at a certain interval, and the seepage pressure sensor needs to be saturated with silicone oil before the test.
Citation Information
Patent Citations
Test apparatus for obtaining stratum filling distribution and film forming characteristic of shield slurry particles
CN106248533A
Complex formation underwater slurry shield mud film formation simulation device and simulation method
CN110031369A
Slurry permeation column resistance measuring device, test device and test method
CN114235644A