Multifunctional urban tunnel group ventilation system and construction method

By adopting a multi-functional urban tunnel group ventilation system in urban tunnel construction and utilizing an air circulation system formed by multiple air inlets and axial flow fans, the problem of poor air quality in the tunnel is solved, efficient cooling and ventilation is achieved, and construction is simplified. process, reduces costs and noise, and meets the ventilation needs of multi-face tunnels.

CN114922674BActive Publication Date: 2024-10-29CHINA RAILWAY TUNNEL BUREAU GRP CONSTR CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202210288469.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-03-23
Publication Date
2024-10-29
Estimated Expiration
2042-03-23

AI Technical Summary

Technical Problem

The ventilation system in existing urban tunnel construction is ineffective and it is difficult to provide air supply for long-distance multi-face construction, resulting in poor air quality in the tunnel. In addition, traditional methods are costly, noisy, occupy a lot of space, and are difficult to meet cooling and ventilation requirements.

Method used

A multifunctional urban tunnel group ventilation system is adopted, including an air circulation system at the tunnel entrance and inside the tunnel. It utilizes multiple air inlets and an exhaust channel on the surface, combined with the first and second axial flow fans, to form a cooling and noise reduction system with linked circulation inside and outside the tunnel. The dust removal ventilation system solves the problem of poor ventilation effect at the single head and improves the efficiency of tunnel shaft excavation.

Benefits of technology

It realizes the timely supply of fresh air to multiple working surfaces, improves the quality of high-temperature air in the tunnel, reduces construction noise and dust, and meets the cooling and ventilation requirements of long-distance multi-working surface tunnels. It is simple, efficient, low-cost, and conforms to the spirit of green and civilized construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114922674B_ABST
    Figure CN114922674B_ABST
Patent Text Reader

Abstract

The present invention discloses a multifunctional urban tunnel group ventilation system, which includes: a tunnel entrance air circulation system, which includes a factory building, a plurality of first negative pressure fans, a plurality of air compressors, and a plurality of second negative pressure fans; an air circulation system in the tunnel, which includes a plurality of first axial flow fans, a plurality of air inlet holes, and a plurality of second axial flow fans. The present invention can meet the environmental protection requirements of urban dark excavation tunnel construction for noise and dust, and can effectively reduce the construction temperature in the tunnel, timely provide fresh air outside the tunnel for multiple working surfaces of the urban dark excavation tunnel group, meet the requirements of urban tunnel construction for noise and dust control, have no impact on the living and working environment of citizens, implement the spirit of green and civilized construction, and have simple construction, low investment, high efficiency, and good ventilation effect.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of ventilation of municipal dark-excavated tunnel engineering, and more specifically to a multifunctional urban tunnel group ventilation system and a construction method. Background Art

[0002] With the increase of urban population and vehicles, the development and utilization of urban underground space has become a focus. In the construction of urban rail transit, municipal tunnels, dark-digging integrated pipelines, underground civil air defense malls and other projects, excavation blasting smoke, equipment heat dissipation, vehicle exhaust emissions, construction waste transportation dust, concrete hydration reaction heat release, etc., cause a sharp increase in suspended matter in the tunnel and carry heat. The air quality and other working environment conditions in the tunnel are poor. Good cooling and ventilation are conducive to improving the underground working environment, improving construction efficiency, and ensuring the physical and mental health of workers.

[0003] Since urban tunnel construction is mostly carried out in densely populated areas, and vertical shafts or inclined shafts are often used to enter the tunnel main tunnel, construction environmental protection has high requirements for noise and dust, and the commonly used single-head pressure-type ventilation method is difficult to achieve long-distance multi-working surface construction air supply. At present, the method of adding jet fans in the tunnel is mostly used to increase ventilation, but the effect is poor. Most of the dirty air discharged from the tunnel is sucked back in, and only a small part of the fresh air is sent to the construction work surface. The wind is difficult to circulate, the temperature in the tunnel is high, and the air quality is poor. The use of high-power fans, ice or cold air for ventilation has the disadvantages of large investment, high noise, occupied construction space and poor technical feasibility. Vortex winds are often formed in inclined shafts or vertical shafts. Especially in summer, it is difficult to meet the cooling and ventilation requirements of long-distance multi-working surface tunnels, and the cost investment is large and the effect is poor. Summary of the invention

[0004] An object of the present invention is to solve at least the above problems and to provide at least the advantages which will be described hereinafter.

[0005] Another object of the present invention is to provide a multifunctional urban tunnel group ventilation system, which includes two air circulation systems inside the tunnel and inside the tunnel entrance factory building. It adopts multiple air inlet holes on the ground surface and only sets one exhaust channel for exhaust. It can provide fresh air to the working face in time, and centrally discharge and treat the dirty air in the tunnel, forming a cooling, noise reduction and dust removal ventilation system with linked circulation inside and outside the tunnel; two ventilation construction stages are formed. In the first stage, the first axial flow fan above the open-cut tunnel entrance is used for single-head ventilation. In the second stage, a second axial flow fan is added under the shaft air inlet steel pipe to supply air to multiple working faces, and the air is supplied together with the axial flow fan at the entrance, which solves the problem of poor ventilation effect only from the tunnel entrance or using jet fans in the tunnel for relay ventilation.

[0006] The present invention also provides a multifunctional urban tunnel group ventilation system construction method, which adopts inclined shaft to enter the cave for dark excavation construction, and has high construction and transportation efficiency; the air inlet holes excavated in the structural shaft are used as air inlet channels for tunnel construction in the early stage, and can be used as slag discharge outlets for shaft excavation in the later stage, which can improve the tunnel shaft excavation efficiency.

[0007] In order to achieve these purposes and other advantages according to the present invention, a multifunctional urban tunnel group ventilation system is provided, which comprises:

[0008] The hole air circulation system includes:

[0009] A factory building is located above the open-cut tunnel opening, with an air inlet and a door at one end and an air outlet at the other end;

[0010] A plurality of first negative pressure fans, which are arranged on the air outlet;

[0011] A plurality of air compressors, all of which are located in the factory building and spaced apart on a side of the factory building away from the tunnel;

[0012] Multiple second negative pressure fans, one second negative pressure fan is correspondingly arranged above one air compressor;

[0013] The air circulation system in the tunnel includes:

[0014] A plurality of first axial flow fans are arranged above the open-cut tunnel opening, the air inlet end of any first axial flow fan is arranged opposite to the air inlet, and the air outlet end is connected to the inside of the dark-cut tunnel through a first connecting pipe;

[0015] Multiple air inlet holes, all of which are vertically arranged, with the top of any air inlet hole located on the ground and the bottom extending to the bottom of the tunnel; an air inlet pipe is inserted into each air inlet hole;

[0016] A plurality of second axial flow fans are provided, one second axial flow fan being correspondingly arranged at the bottom of an air inlet pipe, the air inlet end of any second axial flow fan being connected to the bottom of the air inlet pipe, and the air outlet end being connected to the interior of the dark-excavated tunnel through a second connecting pipe.

[0017] Preferably, in the multifunctional urban tunnel group ventilation system, a plurality of retaining piles are vertically provided on both sides of the open-cut tunnel entrance, the tops of the plurality of retaining piles on the same side are connected by a horizontal crown beam, a plurality of cross beams are horizontally provided between the two crown beams, and the first axial flow fan is fixed on the cross beam.

[0018] Preferably, in the multifunctional urban tunnel group ventilation system, any first connecting pipe includes a ventilation steel pipe connected to the air outlet end of the first axial flow fan and a flexible air duct connected to the interior of the dark tunnel; the ventilation steel pipe is sealed and connected to the flexible air duct.

[0019] Preferably, in the multifunctional urban tunnel group ventilation system, any first negative pressure fan / any second negative pressure fan is provided with an automatic spray mechanism.

[0020] Preferably, in the multifunctional urban tunnel group ventilation system, any air inlet pipe is a steel pipe, the top of the air inlet pipe protrudes 1 to 1.5 m above the ground, and the diameter of the air inlet pipe is 1 to 1.5 m; a rainproof cover is provided above any air inlet pipe, and a safety guardrail is provided around the outer circumference of the air inlet pipe at 1.5 to 2 m, and the height of the safety guardrail is 1.2 to 1.5 m.

[0021] Preferably, in the multifunctional urban tunnel group ventilation system, the factory building is assembled with color steel rock wool boards with a thickness greater than 5 cm, a transparent lighting panel is provided on the top of the factory building, and the factory building is 80 m long, 12-13 m wide, and 9-10 m high;

[0022] Two doors are provided on the end face of one end of the factory building, each door is 3.5m wide and 2.5m high; the air inlet is provided above the door, the air inlet is 7m long and 5m high;

[0023] A plurality of rows of exhaust vents are arranged at intervals in the vertical direction on the other end of the factory building, and the distance between any two adjacent rows of exhaust vents is 0.5m; any row of exhaust vents includes a plurality of exhaust vents arranged at intervals, and the distance between any two adjacent exhaust vents is 1.2m.

[0024] Preferably, the multifunctional urban tunnel group ventilation system, the retaining piles, the crown beams and the cross beams are all cast with C30 reinforced concrete;

[0025] The diameter of the retaining pile is 1m, the depth of the lower end of the retaining pile into the rock is 3-4m, and the distance between two adjacent retaining piles on the same side is 3m;

[0026] The width of the crown beam is 1m and the height is 1m;

[0027] The width of the beam is 0.6m, the height is 0.7m, and the distance between two adjacent beams is 6m.

[0028] Preferably, in the multifunctional urban tunnel group ventilation system, the distance between the exhaust port and the boundary line between the open and dark excavation of the tunnel is 24 to 26 m.

[0029] The present invention also provides a construction method of a multifunctional urban tunnel group ventilation system, which comprises the following steps:

[0030] Step 1: Build a factory building above the open-cut tunnel entrance, open a door and air inlet at one end of the factory building facing the tunnel entrance, and open an exhaust outlet at the other end;

[0031] Step 2: Install a first negative pressure fan in the exhaust port, arrange an air compressor between the outside of the tunnel excavation contour line behind the tunnel opening and the longitudinal wall of the plant, and install a second negative pressure fan in the longitudinal wall of the plant directly above the air compressor;

[0032] Step 3: Arrange multiple retaining piles on both sides of the tunnel entrance, set a crown beam on the top of the multiple retaining piles on the same side, set multiple cross beams between the two crown beams, and set up a first axial flow fan on the cross beam; connect the air outlet end of the first axial flow fan with the interior of the dark tunnel through a first connecting pipe;

[0033] Step 4: In the tunnel shaft or other structures connected to the tunnel, dig an air inlet hole vertically downward from the ground, insert an air inlet pipe into the air inlet hole, set a second axial flow fan at the bottom of the air inlet pipe, and connect the air outlet end of the second axial flow fan to the interior of the dark tunnel through a second connecting pipe.

[0034] The present invention at least includes the following beneficial effects: the present invention changes the traditional single-head pressure-type ventilation mode of the tunnel, adopts multiple ground air inlets, and changes the single-head long-distance air supply to multiple-head short-distance air supply, which can timely deliver fresh air outside the tunnel to each construction working surface of the tunnel, effectively improving the construction environment of high temperature and poor air quality on the working surface; the tunnel adopts an inclined shaft construction plan with high construction and transportation efficiency, and builds an environmentally friendly sound-proof factory building above the open-cut tunnel entrance. The polluted air in the tunnel is collected and uniformly discharged out of the tunnel through the main construction channel. The first negative pressure fan is installed at the exhaust outlet of the factory building, which can speed up the exhaust speed of the polluted air in the tunnel, meet the requirements of urban tunnel construction for noise and dust control, have no impact on the living and working environment of citizens, implement the spirit of green and civilized construction, and have simple construction, low investment, high efficiency and good ventilation effect.

[0035] Other advantages, objectives and features of the present invention will be embodied in part through the following description, and in part will be understood by those skilled in the art through study and practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0036] Figure 1 It is a structural schematic diagram of a multifunctional urban tunnel group ventilation system described in a technical solution of the present invention;

[0037] Figure 2 It is a structural schematic diagram of a multifunctional urban tunnel group ventilation system described in another technical solution of the present invention;

[0038] Figure 3 The figure is a schematic diagram of the arrangement structure of the exhaust vents at the other end of the plant in another technical solution of the present invention.

[0039] Explanation of the reference numerals in the accompanying drawings: 1-factory building; 2-gate; 3-air inlet; 4-air outlet; 5-first negative pressure fan; 6-air compressor; 7-second negative pressure fan; 8-fresh air inlet flow; 9-hot air flow emitted by the air compressor; 10-dirty hot air flow discharged from the tunnel; 11-guarding piles; 12-crown beam; 13-cross beam; 14 main passage of the dark-cut tunnel; 15-first axial flow fan; 16-ventilation steel pipe; 17-flexible air duct; 18-air inlet; 19-air inlet steel pipe; 20-safety guardrail, 21 second axial flow fan; 22-second connecting pipe; 23-bearing tunnel branch tunnel; 24-break line; 25-contour line of structural shaft excavation; 26-boundary mileage between open and dark excavation of the tunnel entrance. DETAILED DESCRIPTION

[0040] The present invention is further described in detail below in conjunction with the accompanying drawings and embodiments so that those skilled in the art can implement the invention with reference to the description.

[0041] It should be understood that the terms such as “having”, “including” and “comprising” used herein do not exclude the existence or addition of one or more other elements or combinations thereof.

[0042] In the description of the present invention, the terms "lateral", "longitudinal", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside" and "outside" etc. to indicate directions or positional relationships are based on the directions or positional relationships shown in the accompanying drawings and are only for the convenience of describing the present invention and simplifying the description. They do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore should not be understood as a limitation on the present invention.

[0043] like Figures 1 to 3 As shown, the present invention provides a multifunctional urban tunnel group ventilation system, which comprises:

[0044] The hole air circulation system includes:

[0045] A factory building is located above the open-cut tunnel opening, with an air inlet and a door at one end and an air outlet at the other end;

[0046] A plurality of first negative pressure fans are arranged on the exhaust port; the number and fan power of the first negative pressure fans can be determined through specific design calculations according to the scale of tunnel construction;

[0047] A plurality of air compressors, all of which are located in the factory building and spaced apart on a side of the factory building away from the tunnel;

[0048] The air compressor room is set in the exhaust area, located outside the tunnel excavation contour line behind the tunnel entrance and between the longitudinal wall of the plant;

[0049] Multiple second negative pressure fans, one second negative pressure fan is set above each air compressor; second negative pressure fans are set at the longitudinal wall position above the air compressor, one for each air compressor, and 1 to 1.5 meters higher than the air compressor;

[0050] The air circulation system in the tunnel includes:

[0051] A plurality of first axial flow fans are arranged above the open-cut tunnel opening, the air inlet end of any first axial flow fan is arranged opposite to the air inlet, and the air outlet end is connected to the inside of the dark-cut tunnel through a first connecting pipe;

[0052] There are multiple air inlets, all of which are set vertically. The top of any air inlet is located on the ground, and the bottom extends to the bottom of the tunnel. An air inlet pipe is inserted into an air inlet. According to the number of on-site working surfaces and the plane layout of the underground tunnel, 1 to 2 air inlet pipes are preferably provided at each location. The air inlet can be located in the vertical shaft of the building, the vertical shaft of the wind pavilion, or a separate air inlet can be set according to construction needs, so as to timely transport fresh air outside the tunnel to each working surface and improve the working environment of the working surface in the tunnel. The air inlet is used as an air inlet channel for tunnel construction in the early stage, and as a slag discharge port for shaft excavation in the later stage, which can improve the efficiency of tunnel shaft excavation. In order to ensure the safety of the later shaft excavation construction, the distance between the wall of the air inlet and the wall of the structural shaft is 0.5 to 1.5 meters. The air inlet is excavated by a rotary drilling rig or other methods, with a hole diameter of 1.0 to 1.5 meters. A steel pipe with a wall thickness of 4 to 6 mm is installed in the hole as an air inlet pipe. The steel pipe is used to support and reinforce the strata around the hole wall and used as an air inlet duct.

[0053] A plurality of second axial flow fans are provided, one second axial flow fan being correspondingly arranged at the bottom of an air inlet pipe, the air inlet end of any second axial flow fan being connected to the bottom of the air inlet pipe, and the air outlet end being connected to the interior of the dark-excavated tunnel through a second connecting pipe.

[0054] In the above technical scheme, the tunnel ventilation system provided by the present invention includes two air circulation systems inside and outside the tunnel. An environmentally friendly sound-insulating and noise-reducing colored steel rock wool board factory building is built above the open-cut tunnel entrance. Air inlets and exhaust outlets are arranged at the front and rear ends of the factory building. The second negative pressure fan in the factory building cooperates with the first negative pressure fan at the rear end of the factory building to realize air circulation; a plurality of air inlets are arranged on the ground, one is arranged at the open-cut entrance in the factory building, and the rest are arranged at suitable locations such as safe entrances and exits connected to the tunnel or wind pavilion shafts. Fresh air outside the tunnel is supplied to the tunnel working face through the first axial flow fan, the second axial flow fan, the first connecting pipe, and the second connecting pipe. The present invention can accelerate the exhaust speed of polluted air in the tunnel by arranging internal and external double circulation, meets the requirements of urban tunnel construction for noise and dust control, has no impact on the living and working environment of citizens, implements the spirit of green and civilized construction, is simple in construction, requires less investment, has high efficiency, and has good ventilation effect.

[0055] Tunnel entrance air circulation system: an environmentally friendly sound-insulated and noise-reducing colored steel rock wool board factory building is built above the open-cut tunnel entrance. Air inlets and exhaust outlets are respectively arranged on the front and rear end walls of the factory building. Multiple first negative pressure fans are arranged at the exhaust outlets. Multiple second negative pressure fans are arranged above multiple air compressors arranged inside the factory building. Multiple first negative pressure fans and multiple second negative pressure fans create a wind pressure difference at both ends of the factory building, speed up the air flow circulation speed in the factory building, allow fresh air to quickly enter the factory building, and promptly discharge the polluted air in the tunnel to prevent the polluted air from being sucked into the tunnel for the second time.

[0056] Air circulation system in the tunnel: multiple first axial flow fans are arranged above the open-cut tunnel opening, and external fresh air is sent into the tunnel through the first connecting pipe. Preferably, the first connecting pipe is arranged along the slope of the tunnel vault; multiple air inlets are arranged vertically downward from the ground to the inside of the tunnel, and second axial flow fans are arranged at the bottom of the air inlets. External fresh air is sent to multiple working surfaces of the tunnel's dark-cut branch tunnels through the air inlet pipes and the second connecting pipes, and the polluted air generated by each working surface of the tunnel is discharged to the open-cut tunnel opening in the factory building through the main tunnel channel, and then discharged to the outside of the factory building by the tunnel opening air circulation system.

[0057] In another technical solution, in the multifunctional urban tunnel group ventilation system, a plurality of retaining piles are vertically arranged on both sides of the open-cut tunnel entrance, the tops of the plurality of retaining piles on the same side are connected by a horizontal crown beam, a plurality of cross beams are horizontally arranged between the two crown beams, and the first axial flow fan is fixed on the cross beam.

[0058] By setting up retaining piles, crown beams and cross beams at the open-cut opening of the tunnel, a mounting position is provided for the first axial flow fan. The air inlet end of the first axial flow fan is arranged opposite to the air inlet on the front end of the plant. The fresh air outside the plant passes through the air inlet and the air inlet end of the first axial flow fan in sequence. Under the action of the first axial flow fan, the fresh air is sent into the tunnel through the first connecting pipe. The first axial flow fan is installed above the two cross beams farthest from the tunnel opening, and the air outlet end of the first axial flow fan is more than 10m away from the boundary section between the open and dark excavation of the tunnel.

[0059] In another technical solution, in the multifunctional urban tunnel group ventilation system, any first connecting pipe includes a ventilation steel pipe connected to the air outlet of the first axial flow fan and a flexible air duct connected to the inside of the dark tunnel; the ventilation steel pipe is sealed and connected to the flexible air duct. A curved over-ventilation steel pipe is installed at the air outlet of the first axial flow fan, and the ventilation steel pipe is connected to the tunnel hole 1 to 3 meters away; the end of the ventilation steel pipe is connected to the flexible air duct, and the flexible air duct is about 30 to 40 meters away from the tunnel excavation working surface.

[0060] In another technical solution, in the multifunctional urban tunnel group ventilation system, any first negative pressure fan / any second negative pressure fan is provided with an automatic spray mechanism. The automatic spray mechanism is provided on the negative pressure fan to spray at the same time as exhausting air, so as to achieve the effect of dust removal and air purification.

[0061] In another technical solution, in the multifunctional urban tunnel group ventilation system, any air inlet pipe is a steel pipe, the top of the air inlet pipe protrudes 1 to 1.5 meters above the ground, and the diameter of the air inlet pipe is 1 to 1.5 meters; a rainproof cover is provided above any air inlet pipe, and a safety guardrail is provided around the outer periphery of the air inlet pipe at 1.5 to 2 meters, and the height of the safety guardrail is 1.2 to 1.5 meters. The rainproof cover is provided to prevent rainwater and other impurities from entering the air inlet pipe, causing fan failure or safety accidents, and the safety guardrail is provided on the periphery to prevent construction personnel from accidentally touching the air inlet pipe and the rainproof cover, thereby ensuring construction safety.

[0062] In another technical solution, the multifunctional urban tunnel group ventilation system, the plant is assembled with color steel rock wool panels with a thickness greater than 5 cm, a transparent lighting panel is provided on the top of the plant, and the plant is 80 m long, 12-13 m wide, and 9-10 m high;

[0063] Two doors are provided on the end face of one end of the factory building, each door is 3.5m wide and 2.5m high; the air inlet is provided above the door, the air inlet is 7m long and 5m high;

[0064] A plurality of rows of exhaust vents are arranged at intervals in the vertical direction on the other end of the factory building, and the distance between any two adjacent rows of exhaust vents is 0.5m; any row of exhaust vents includes a plurality of exhaust vents arranged at intervals, and the distance between any two adjacent exhaust vents is 1.2m.

[0065] Color steel rock wool board has certain sound insulation and noise reduction performance, and has good environmental protection and flame retardant properties. A tunnel entrance and exit gate is set at the front end of the factory building, an air inlet is set above the gate, and multiple exhaust vents are arranged in rows at the rear end.

[0066] In another technical solution, the multifunctional urban tunnel group ventilation system, the retaining piles, the crown beams, and the cross beams are all cast with C30 reinforced concrete;

[0067] The diameter of the retaining pile is 1m, the depth of the lower end of the retaining pile into the rock is 3-4m, and the distance between two adjacent retaining piles on the same side is 3m;

[0068] The width of the crown beam is 1m and the height is 1m;

[0069] The width of the beam is 0.6m, the height is 0.7m, and the distance between two adjacent beams is 6m.

[0070] In the above technical solution, the structural dimensions of the retaining piles, cap beams and cross beams need to be designed according to the actual surrounding rock geological conditions of the construction site.

[0071] In another technical solution, the multifunctional urban tunnel group ventilation system has an air outlet and a distance of 24 to 26 meters from the boundary line between the open and dark tunnels, which accounts for about 1 / 3 of the entire plant length.

[0072] The present invention also provides a construction method of a multifunctional urban tunnel group ventilation system, which comprises the following steps:

[0073] Step 1: Build a factory building above the open-cut tunnel entrance, open a door and air inlet at one end of the factory building facing the tunnel entrance, and open an exhaust outlet at the other end;

[0074] Step 2: Install a first negative pressure fan in the exhaust port, arrange an air compressor between the outside of the tunnel excavation contour line behind the tunnel opening and the longitudinal wall of the plant, and install a second negative pressure fan in the longitudinal wall of the plant directly above the air compressor;

[0075] Step 3: Arrange multiple retaining piles on both sides of the tunnel entrance, set a crown beam on the top of the multiple retaining piles on the same side, set multiple cross beams between the two crown beams, and set up a first axial flow fan on the cross beam; connect the air outlet end of the first axial flow fan with the interior of the dark tunnel through a first connecting pipe;

[0076] Step 4: In the tunnel shaft or other structures connected to the tunnel, dig an air inlet vertically downward from the ground, insert an air inlet pipe into the air inlet, set a second axial flow fan at the bottom of the air inlet pipe, and connect the outlet of the second axial flow fan to the inside of the dark-cut tunnel through the second connecting pipe. As the tunnel excavation length increases and the number of working faces increases, if only single-head ventilation is carried out from the open-cut tunnel entrance, the air quality and construction environment in the tunnel will continue to deteriorate, and a second ventilation stage system needs to be added. The construction content includes: constructing an air inlet at a suitable position of the structure; installing an air inlet pipe in the air inlet; setting up safety guardrails around the air inlet where the air inlet pipe extends out of the ground; connecting and installing a second axial flow fan at the bottom of the air inlet pipe, installing a second connecting pipe (flexible air duct) at the outlet of the second axial flow fan, and excavating a dark-cut branch tunnel. The second connecting pipe extends forward with the excavation working face, and is about 30 to 40 meters away from the tunnel excavation working face.

[0077] The construction method and sequence of the ventilation system of the present invention are as follows: determine the position of the open-cut tunnel entrance by measuring and locating → arrange the plant plan according to the position of the tunnel entrance, determine the positions of ancillary rooms such as the air compressor and the duty room → build the plant and install the first negative pressure fan and the second negative pressure fan → carry out open-cut construction of the tunnel entrance and dark-cut construction of the entrance section → erect the first axial flow fan and connect the first connecting pipe → continue tunnel excavation and support construction → timely excavate ventilation air inlets (when the tunnel construction distance is long, the working surfaces are many, and the ventilation effect is poor, timely excavate ventilation air inlets) → install the air inlet pipe in the air inlet → install the second axial flow fan below the air inlet pipe → connect the second axial flow fan to the second connecting pipe → connect the second connecting pipe to the working surface of each branch tunnel.

[0078] The multifunctional urban tunnel group ventilation system construction method provided by the present invention adopts inclined shaft to enter the cave for dark excavation construction, and the construction and transportation efficiency is high; the air inlet hole excavated in the structural shaft is used as an air inlet channel for tunnel construction in the early stage, and can be used as a slag discharge port for shaft excavation in the later stage, which can improve the tunnel shaft excavation efficiency and reduce the construction cost.

[0079] by Figures 1 to 3 Take this as an example to further explain:

[0080] A gate 2 and an air inlet 3 are arranged at one end of the plant 1, and an exhaust vent 4 is arranged at the other end. A first negative pressure fan 5 is installed in the exhaust vent. An air compressor 6 is arranged longitudinally at intervals on the side of the plant (between the open-cut tunnel entrance and the rear end of the tunnel) away from the tunnel, and a second negative pressure fan 7 is arranged above the air compressor.

[0081] The invention relates to a construction tunnel, comprising a main tunnel passage 14 and a plurality of branch tunnels 23; a retaining pile 11, a crown beam 12 and a cross beam 13 are constructed at an open tunnel opening, a first axial flow fan 15 is arranged on the cross beam, and an air outlet of the first axial flow fan passes through a ventilation steel pipe 16 and a flexible air duct 17 (the first axial flow fan 15 is arranged on the tunnel opening support cross beam, mainly considering that the fan can be fully utilized in the tunnel opening foundation pit retaining support structure to install the fan, solving the problem of the first axial flow fan erection, and the design is reasonable and the operability is strong.); Figure 1 The middle tunnel opening open-ditch and dark-cut boundary mileage 26 is the tunnel open-ditch and dark-cut boundary line. The left side of the tunnel opening open-ditch and dark-cut boundary mileage 26 is the tunnel dark-cut opening, and the right side is the tunnel open-ditch opening.

[0082] A plurality of air inlet holes 18 are dug vertically downward from the ground within the structural shaft excavation contour line 25, an air inlet pipe 19 is arranged in the air inlet hole, a safety guardrail 20 is arranged around the air inlet hole on the ground, and a rainproof roof cover is set up on the top; a second axial flow fan 21 is arranged at the bottom of the air inlet pipe 19, the air inlet end of the second axial flow fan 21 is connected with the air inlet pipe 19, and the air outlet end is connected with the working surface of each dark tunnel branch hole 23 through the second connecting pipe 22, so as to transport the fresh air on the ground to the working surface of the dark tunnel branch hole through the second connecting pipe 19;

[0083] Fresh air outside the factory (such as Figure 1 The fresh air inlet flow 8 shown in the figure enters the factory from the air inlet, and the air in the factory is exhausted by multiple first negative pressure fans 5 at the exhaust port and multiple second negative pressure fans 7 in the factory, so that a pressure difference is generated at the front and back ends of the factory, thereby accelerating the air circulation speed in the factory. Figure 1 As shown, the hot air flow 9 emitted by the air compressor and the polluted hot air flow 10 discharged from the tunnel will also be discharged to the outside of the factory through the exhaust port; under the action of the second axial flow fan 21, fresh air is transported to each working surface of the branch tunnel 23 of the dark tunnel through the air inlet pipe and the second connecting pipe 22. At the same time, each working surface in the dark tunnel squeezes the polluted air in the tunnel into the factory building at the entrance of the tunnel under the fresh air transported by the first axial flow fan 15 and the second axial flow fan 21. Due to the negative pressure in the factory building, the polluted air is promptly exhausted to the outside of the factory building by the negative pressure fan at the exhaust port of the factory building. The two air circulation paths of the present invention can quickly exhaust the polluted air in the tunnel and transport fresh air to the inside of the tunnel, thereby ensuring construction safety and efficiency; at the same time, the automatic spraying mechanism arranged on the first negative pressure fan and the second negative pressure fan can spray the air in the factory building to remove dust and then discharge it to the outside of the factory building, thereby achieving the effect of purifying the air.

[0084] The number of devices and processing scales described here are used to simplify the description of the present invention. Applications, modifications and variations of the present invention will be obvious to those skilled in the art.

[0085] Although the embodiments of the present invention have been disclosed as above, they are not limited to the applications listed in the specification and the implementation modes, and they can be fully applied to various fields suitable for the present invention. For those familiar with the art, additional modifications can be easily implemented. Therefore, without departing from the general concept defined by the claims and the scope of equivalents, the present invention is not limited to the specific details and the illustrations shown and described herein.

Claims

1. Multifunctional urban tunnel ventilation system, It is characterized in that include: The hole air circulation system includes: A factory building is located above the open-cut tunnel opening, with an air inlet and a door at one end and an air outlet at the other end; A plurality of first negative pressure fans, which are arranged on the air outlet; A plurality of air compressors, all of which are located in the factory building and spaced apart on a side of the factory building away from the tunnel; Multiple second negative pressure fans, one second negative pressure fan is correspondingly arranged above one air compressor; The air circulation system in the tunnel includes: A plurality of first axial flow fans are arranged above the open-cut tunnel opening, the air inlet end of any first axial flow fan is arranged opposite to the air inlet, and the air outlet end is connected to the inside of the dark-cut tunnel through a first connecting pipe; Multiple air inlet holes, all of which are vertically arranged, with the top of any air inlet hole located on the ground and the bottom extending to the bottom of the tunnel; an air inlet pipe is inserted into each air inlet hole; A plurality of second axial flow fans, one second axial flow fan is correspondingly arranged at the bottom of an air inlet pipe, the air inlet end of any second axial flow fan is connected to the bottom of the air inlet pipe, and the air outlet end is connected to the interior of the dark tunnel through a second connecting pipe; A plurality of retaining piles are vertically arranged on both sides of the open-cut tunnel opening, the tops of the plurality of retaining piles on the same side are connected by a horizontal crown beam, a plurality of cross beams are horizontally arranged between the two crown beams, and the first axial flow fan is fixed on the cross beam; Any first connecting pipe includes a ventilation steel pipe connected to the air outlet end of the first axial flow fan and a flexible air duct connected to the inside of the dark tunnel; the ventilation steel pipe is connected to the flexible air duct in a sealed manner.

2. The multifunctional urban tunnel group ventilation system according to claim 1, It is characterized in that Any first negative pressure fan / any second negative pressure fan is provided with an automatic spray mechanism.

3. The multifunctional urban tunnel group ventilation system according to claim 1, It is characterized in that Any air inlet pipe is a steel pipe, the top of the air inlet pipe protrudes 1 to 1.5m above the ground, and the diameter of the air inlet pipe is 1 to 1.5m; a rainproof cover is provided above any air inlet pipe, and a safety guardrail is provided around the outer circumference of the air inlet pipe at 1.5 to 2m, and the height of the safety guardrail is 1.2 to 1.5m.

4. The multifunctional urban tunnel group ventilation system according to claim 1, It is characterized in that The factory building is assembled with color steel rock wool boards with a thickness greater than 5 cm. A transparent lighting panel is provided on the top of the factory building. The factory building is 80 m long, 12 to 13 m wide, and 9 to 10 m high. Two doors are provided on the end face of one end of the factory building, each door is 3.5m wide and 2.5m high; the air inlet is provided above the door, the air inlet is 7m long and 5m high; A plurality of rows of exhaust vents are arranged at intervals in the vertical direction on the other end of the factory building, and the distance between any two adjacent rows of exhaust vents is 0.5m; any row of exhaust vents includes a plurality of exhaust vents arranged at intervals, and the distance between any two adjacent exhaust vents is 1.2m.

5. The multifunctional urban tunnel group ventilation system according to claim 1, It is characterized in that The retaining piles, crown beams and cross beams are all cast with C 30 reinforced concrete; The diameter of the retaining pile is 1m, the depth of the lower end of the retaining pile into the rock is 3-4m, and the distance between two adjacent retaining piles on the same side is 3m; The width of the crown beam is 1m and the height is 1m; the width of the cross beam is 0.6m and the height is 0.7m, and the distance between two adjacent cross beams is 6m.

6. The multifunctional urban tunnel group ventilation system according to claim 1, It is characterized in that The distance between the exhaust vent and the boundary line between the open and concealed excavation of the tunnel is 24 to 26 meters.

7. Construction method of multifunctional urban tunnel ventilation system, It is characterized in that The multifunctional urban tunnel group ventilation system according to any one of claims 1 to 6 comprises the following steps: Step 1: Build a factory building above the open-cut tunnel entrance, open a door and air inlet at one end of the factory building facing the tunnel entrance, and open an exhaust outlet at the other end; Step 2: Install a first negative pressure fan in the exhaust port, arrange an air compressor between the outside of the tunnel excavation contour line behind the tunnel opening and the longitudinal wall of the plant, and install a second negative pressure fan in the longitudinal wall of the plant directly above the air compressor; Step 3: Arrange multiple retaining piles on both sides of the tunnel entrance, set a crown beam on the top of the multiple retaining piles on the same side, set multiple cross beams between the two crown beams, and set up a first axial flow fan on the cross beam; connect the air outlet end of the first axial flow fan with the interior of the dark tunnel through a first connecting pipe; Step 4: In the tunnel shaft or other structures connected to the tunnel, dig an air inlet hole vertically downward from the ground, insert an air inlet pipe into the air inlet hole, set a second axial flow fan at the bottom of the air inlet pipe, and connect the air outlet end of the second axial flow fan to the interior of the dark tunnel through a second connecting pipe.

Citation Information

Patent Citations

  • Ventilation heating system for tunnels in high-altitude and cold regions as well as ventilation heating construction method

    CN105134278A

  • Subway station ventilation and air conditioning environmental-control system

    CN106152349A

  • Ventilation system in city tunnel

    CN207278289U