A symmetrical anti-anchor reinforcement structure and construction method for the first-floor beam of a bottom frame brick-concrete building
By using a square steel column symmetrical anti-anchor structure in the first-floor beams of the bottom-frame brick-concrete building, the problems of traditional reinforcement methods such as large amounts of materials, high costs, and poor results have been solved, and the structural stress safety and cost performance have been improved. , ensuring the bearing capacity and safety of the beam.
Patent Information
- Application Number
- CN202210550002.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-05-20
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2042-05-20
AI Technical Summary
Existing technology: In the reinforcement of first-floor beams of brick-concrete buildings with bottom frames, traditional methods lead to increased material consumption, increased self-weight, high costs, and ineffective effects. They also affect the original structural stress system and are difficult to meet high bearing capacity requirements.
A square steel column symmetrical anti-anchor structure is adopted. By supporting the mid-span of the first floor beam and forming a symmetrical anti-anchor with the foundation, the beam span is reduced, the bending moment and shear force are reduced, and the impact on the stress system of the original structure is avoided. Steel columns, The column top anchoring module and column foot anchoring module are anchored and connected using steel bolts and high-strength bolts to form a non-stressed state to reduce the load.
It effectively reduces the bending moment and shear force of the beam, improves the stress safety of the structure, reduces the dead weight of the reinforcement material, improves the cost performance, and provides reinforcement support when the original beam deflects and deforms, ensuring structural safety without affecting the original Structural integrity.
Smart Images

Figure CN114961318B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building structure reinforcement, and in particular to a symmetrical anti-anchor structure of square steel columns for reinforcing first-floor reinforced concrete beams in a bottom frame brick-concrete building, and in particular to a symmetrical anti-anchor reinforcement structure of first-floor beams in a bottom frame brick-concrete building and a construction method. Background Art
[0002] Structural reinforcement of existing buildings means taking targeted reinforcement measures for the main structural safety problems of existing buildings to ensure the structural safety of the buildings. A large number of cases of reinforcement projects of bottom frame brick-concrete buildings show that the main structural safety problem is that the bearing capacity of the original load-bearing components does not meet the requirements. Bottom frame brick-concrete structures are mostly found in residential buildings, office buildings and other buildings that require street-facing. The shops, restaurants, banks, etc. set up on the first floor are often large-space layouts. The upper floors are masonry load-bearing structures with more vertical and horizontal walls, while the first floor adopts a frame structure due to the large space, forming a bottom frame brick-concrete structure.
[0003] The reinforcement and renovation projects of existing brick-concrete buildings with bottom frames, while meeting the requirements of functional renovation and improvement, are inevitably accompanied by adjustments to the original building layout and other related aspects. The change in the functional layout of the building also brings about an increase in loads. In addition, the increase in the load partial coefficient of the current specification causes the original load-bearing components to fail to meet the bearing capacity verification requirements of the current specification. Therefore, it is particularly important to reinforce the load-bearing components of brick-concrete buildings with bottom frames, especially the beam components of the first-floor bottom frame. At present, the existing reinforced concrete beam reinforcement methods are mainly pasting carbon fiber cloth, pasting steel plates, wrapping steel sections, increasing cross-sections, and planting steel bars. Since the bottom frame structure has high requirements for the bearing capacity of the first-floor beam components, if the above methods are adopted, the increase in the amount of reinforcement materials often leads to an increase in self-weight and weakening of the effective bearing capacity. At the same time, the increase in the amount of reinforcement materials often leads to a high cost. The cost-effectiveness of reinforcing the first-floor beams of the bottom frame is not high and the effect is not obvious.
[0004] Therefore, based on the above situation, a symmetrical anti-anchor steel support structure for the reinforcement of the first-floor beam of the bottom frame brick-concrete building is proposed. This reinforcement form supports and anchors the newly added steel column in the middle of the bottom span of the first-floor beam, and forms a symmetrical anti-anchor with the newly added steel column anchored to the original foundation, thereby reducing the original beam span by half. According to the beam mid-span bending moment calculation formula M = qL 2 / 8, the beam support shear force calculation formula is R=qL / 2, L is the beam span, then the mid-span bending moment is reduced to 1 / 4 of the original bending moment value, and the beam support shear force is reduced to 1 / 4 of the original shear force value. Supporting in the bottom span of the beam and transferring the load to the foundation can significantly reduce the mid-span bending moment and support shear force borne by the original beam, and can also play a significant reinforcement effect. When the original beam does not undergo stress deflection and deformation, the reinforced structure is in a non-stress state. When the original beam undergoes stress deflection and deformation, it plays a reinforcement role of reducing the span and reducing the bearing capacity. It will not affect the original structural force system like the traditional method of adding reinforced concrete support components. This reinforcement form changes the original beam reinforcement idea to adding steel structure symmetrical anti-anchor supports to reduce the beam span, thereby effectively reducing the bearing capacity of the original beam. It also provides a new method for the reinforcement of such components in the future. Summary of the invention
[0005] The purpose of the present invention is to overcome the shortcomings of the prior art and to provide a symmetrical anti-anchor reinforcement structure and construction method for the first-floor beams of a bottom frame brick-concrete building. The reinforcement structure is connected to the original building structure by symmetrical anti-anchor hinge supports rather than by adding new concrete member fixed end connections. This improves the stress safety of the original beam structure while meeting the structural safety reinforcement requirements of the beam member and effectively overcomes the shortcomings of traditional steel-concrete support fixings that affect the stress system of the original structure.
[0006] A symmetrical anti-anchor reinforcement structure for the first-floor beams of a bottom-frame brick-concrete building, comprising a steel column, a column top anchoring module and a column foot anchoring module, wherein the column top anchoring module is anchored on the bottom surface of the original beam of the building, and the bottom of the column top anchoring module is fixedly connected to the steel column; the bottom of the steel column is fixedly connected to the column foot anchoring module, and the column foot anchoring module is anchored on the top surface of the original foundation of the building; the steel column comprises an upper short column, a steel bench and a lower long column which are coaxially arranged from top to bottom, wherein a plurality of steel bolts which are axially guided and supported and radially limited are evenly arranged on the top surfaces of the steel bench and the lower long column; the top surfaces of the steel bolts are pressure-supported on the bottom surfaces of the upper short column and the steel bench.
[0007] Preferably, a plurality of steel bolt guide holes are formed on the top surfaces of the steel bench and the lower long column, and a plurality of limiting holes with diameters larger than the steel bolt guide holes and the steel bolts are formed at the openings of the steel bolt guide holes.
[0008] Preferably, the inner ring of the limiting hole is a radial limiting steel bolt, and the axial end face of the limiting hole is an axial limiting steel bolt.
[0009] Preferably, the top surface of the steel bolt is welded and fixed to the bottom surface of the upper short column or the bottom surface of the steel bench.
[0010] Preferably, the column top anchoring module and the column base anchoring module both include an anchoring steel plate and a reinforcing steel rib plate, wherein a steel column is fixedly arranged on the anchoring steel plate, and a reinforcing steel rib plate for laterally supporting the steel column is fixedly arranged on the anchoring steel plate.
[0011] Preferably, the anchoring steel plate of the column top anchoring module is configured as a rectangular structure arranged along the original beam of the building, and reinforcing steel ribs supporting the steel column are arranged on the two back-facing sides of the anchoring steel plate in the extension direction of the original beam of the building, and the anchoring steel plate is anchored to the bottom surface of the original beam of the building by high-strength fastening bolts; chemical anchoring holes are vertically opened on the bottom surface of the original beam of the building, and the chemical anchoring holes are filled with anchoring glue.
[0012] Preferably, the anchoring steel plate of the column base anchoring module is set as a square structure, and reinforcing steel ribs for supporting steel columns are arranged in the four supporting directions of the anchoring steel plate, and the anchoring steel plate is anchored to the top surface of the original foundation of the building by high-strength fastening bolts with self-expanding bottom bolt feet.
[0013] A construction method for a symmetrical anti-anchor reinforcement structure of a first-floor beam of a bottom frame brick-concrete building comprises the following steps:
[0014] Step 1: First, reserve holes for all positions where high-strength bolts are set at the bottom of the original reinforced concrete beam and the upper part of the original building foundation. The hole diameter should be reserved according to the model and process. When drilling, use a rebar detector to avoid the original beam and foundation steel bars. After drilling, the holes should be cleaned first.
[0015] Step 2: According to the construction sequence of first down and then up, the steel column foot is first anchored to the original foundation. The vertical anchoring structure of the steel column foot includes trapezoidal reinforcement steel ribs, anchor steel plates and high-strength friction-type self-expanding bottom anchor bolts; the trapezoidal reinforcement steel ribs, anchor steel plates and steel columns are all fully welded, and 8 trapezoidal reinforcement steel ribs are set around the top of the steel column foot to form a steel column foot support; after the high-strength friction bolts are anchored in the holes, the self-expanding bottom bolt feet should be locked after the bottom is expanded. After the bolts are installed, an on-site in-situ pull-out test should be carried out to verify whether the anchor connection is firm; after the high-strength friction bolts are anchored in the holes, the steel column foot combined steel components are welded;
[0016] Step 3: The anchor fixing unit on the original beam is a high-strength friction threaded chemical anchor bolt on the top of the column. After the high-strength bolt is anchored in the hole, the chemical anchor glue is used to fill the hole. After the bolt is installed, an on-site in-situ pull-out test should be carried out to verify whether the anchor connection is firm. After the high-strength bolt is anchored in the hole, the steel column top composite steel component is welded;
[0017] Step 4: After completing the installation of the column top anchor module, column foot anchor module, upper short column and lower long column according to steps 1 to 3 above, install the steel bench at the axial interval between the upper short column and the lower long column, and insert the steel bolts into the gaps on the upper surface of the steel bench and the upper surface of the lower long column, and place the steel bolts in the limiting holes. Finally, fix the gap between the top surface of the steel bolt and the upper short column or the bottom surface of the steel bench by full welding.
[0018] The advantages and technical effects of the present invention are:
[0019] 1. The present invention is a new form of square steel column symmetrical anti-anchor structure for reinforcing the first-floor reinforced concrete beam in a bottom frame brick-concrete building. It innovatively applies a support system of square steel columns combined with beams and foundation symmetrical anti-anchors, which can reduce the shear force and bending moment generated by the constant load and live load transmitted to the original beam by the floor slab above the beam span, and can ensure the structural safety of the original beam after reinforcement;
[0020] 2. The column top anchoring module of the present invention is arranged at the column top and anchored to the original steel beam to form a symmetrical anti-anchor with the column foot anchoring module. Since the change of the upper live load will cause the stress of the original beam to change, the steel bench guide hole between the columns is the key to the structure. When the stress of the original beam is small and no deflection occurs, the symmetrical anti-anchor structure has a light weight and is in a standby static state, which does not affect the stress system of the original structure; when the original beam is subjected to a slightly larger stress and deflection occurs, the steel bolts between the columns of the structure can be squeezed and deformed, and the deformation of the steel bolts can provide a 20mm original beam deflection deformation margin. When the original beam is subjected to a larger stress and deflection occurs, the steel bolts are inserted into the remaining 10mm space of the guide hole, so that the upper surface of the lower long column is supported by force on the lower surface of the steel bench, and the upper surface of the steel bench is supported by force on the lower surface of the upper short column. The symmetrical anti-anchor structure support can ensure the stress safety of the beam structure when the deflection of the original beam reaches the warning value. At this time, load reduction measures should be taken to reduce the upper load on the original beam. That is, before the original beam is deformed, the steel bolts are not compressed and the steel columns are not load-bearing. After the original beam is deformed, the steel bolts are deformed and the steel columns are loaded, so that the present invention has the "insurance" function of deformation of the original beam; in the normal state of the steel column not bearing load, the damage to the original building force system can be avoided to the greatest extent, so the upper short column can be as short as possible to reduce the deadweight; in the state of the steel column bearing load, the steel bolts are deformed to reduce the support height of the steel column; after the steel column bearing load state is restored to the non-bearing state, a new disposable "insurance" steel bolt can be replaced according to the deformation of the steel bolt.
[0021] 3. The present invention is a new structural reinforcement form of square steel column symmetrical anti-anchor for reinforcing the first-floor reinforced concrete beam in a bottom frame brick-concrete building, which overcomes many shortcomings of the method of reinforcing the first-floor beam in a bottom frame brick-concrete building, abandons the adverse effect of adding concrete components to implement reinforcement that affects the change of the original structural force system, better improves the force stability of the original beam components, and does not affect the integrity of the original structure. The square steel column symmetrical anti-anchor structure is economical, easy to implement, and safe and reliable. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 It is a three-dimensional structural diagram of the support posture of the present invention;
[0023] Figure 2 for Figure 1 Side view of
[0024] Figure 3 for Figure 2 Sectional view of section AA;
[0025] Figure 4 for Figure 2 Enlarged cross-sectional view of the middle BB section;
[0026] Figure 5 for Figure 3 A partial enlarged view of point C in the middle;
[0027] Figure 6 It is a schematic diagram of the connection structure of the column top anchoring module and the column foot anchoring module of the present invention;
[0028] In the figure: 1-original beam of the building; 2-column top anchoring module; 3-upper short column; 4-steel bench; 5-lower long column; 6-column foot anchoring module; 7-original foundation of the building; 8-steel bolt; 9-limiting hole; 10-steel bolt guide hole; 11-chemical anchoring grouting hole; 12-anchoring steel plate; 13-high-strength fastening bolt; 14-reinforced steel rib plate; 15-self-expanding bottom bolt foot. DETAILED DESCRIPTION
[0029] In order to further understand the content, features and effects of the present invention, the following embodiments are given as examples and described in detail with reference to the accompanying drawings. It should be noted that the embodiments are illustrative, not restrictive, and the protection scope of the present invention cannot be limited thereby.
[0030] A symmetrical anti-anchor reinforcement structure for the first-floor beams of a bottom-frame brick-concrete building, comprising a steel column, a column top anchoring module 2 and a column foot anchoring module 6, wherein the column top anchoring module is anchored on the bottom surface of an original beam 1 of the building, and the bottom of the column top anchoring module is fixedly connected to the steel column; the bottom of the steel column is fixedly connected to the column foot anchoring module, and the column foot anchoring module is anchored on the top surface of an original foundation 7 of the building; the steel column comprises an upper short column 3, a steel bench 4 and a lower long column 5 which are coaxially arranged from top to bottom, wherein a plurality of steel bolts 8 which are axially guided and supported and radially limited are evenly arranged on the top surfaces of the steel bench and the lower long column; the top surfaces of the steel bolts are pressure-supported on the bottom surfaces of the upper short column and the steel bench.
[0031] Preferably, a plurality of steel bolt guide holes 10 are evenly distributed on the top surfaces of the steel bench and the lower long column, and a plurality of limiting holes 9 with diameters larger than the steel bolt guide holes and the steel bolts are formed at the openings of the steel bolt guide holes.
[0032] Preferably, the inner ring of the limiting hole is a radial limiting steel bolt, and the axial end face of the limiting hole is an axial limiting steel bolt.
[0033] Preferably, the top surface of the steel bolt is welded and fixed to the bottom surface of the upper short column or the bottom surface of the steel bench.
[0034] Preferably, the column top anchoring module and the column foot anchoring module both include an anchoring steel plate 12 and a reinforcing steel rib plate 14, wherein a steel column is fixed on the anchoring steel plate, and a reinforcing steel rib plate for supporting the steel column laterally is fixed on the anchoring steel plate.
[0035] Preferably, the anchoring steel plate of the column top anchoring module is configured as a rectangular structure arranged along the original beam of the building, and the two back-facing side surfaces of the anchoring steel plate facing the extension direction of the original beam of the building are fixedly connected to reinforcing steel ribs, and the anchoring steel plate is anchored to the bottom surface of the original beam of the building by high-strength fastening bolts 13; a chemical anchoring hole 11 is vertically opened on the bottom surface of the original beam of the building, and the chemical anchoring hole is filled with anchoring glue.
[0036] Preferably, the anchoring steel plate of the column base anchoring module is set to a square structure, and reinforcing steel ribs supporting the steel column are fixed on the four supporting directions of the anchoring steel plate, and the anchoring steel plate is anchored on the top surface of the original foundation of the building by high-strength fastening bolts with self-expanding bottom bolt feet 15.
[0037] In order to more clearly describe the specific implementation mode of the present invention, an embodiment is provided below:
[0038] The present invention discloses a symmetrical anti-anchor reinforcement structure for the first-floor beams of a bottom frame brick-concrete building, wherein the cross-section of the steel column is square, the square steel column is perpendicular to the bottom surface of the original beam and the upper surface of the original foundation, the square steel column is connected to the original foundation by bottom-enlarged bolt anchoring, and is connected to the original beam by threaded high-strength bolt anchoring. A steel bench and an upper short column are arranged at the 1 / 3 floor height of the square steel column, the steel bench and the upper short column are used as welded supports for connecting two columns, and the square steel column combined steel member is used as a mid-span hinged support and is symmetrically anchored to the original structure.
[0039] Moreover, reserved holes should be drilled at all locations where high-strength bolts are to be installed at the bottom of the original reinforced concrete beam and the upper part of the foundation. The hole diameter should be reserved according to the model and process. When drilling, a rebar detector should be used to avoid the original beam and foundation steel bars. After drilling, the holes should be cleaned first.
[0040] Moreover, the square steel column foot should be anchored to the original foundation in the order of first down and then up. The vertical anchoring structure of the square steel column 1 foot includes trapezoidal reinforcement steel ribs, square steel plates for the column foot anchors, and high-strength friction-type self-expanding bottom anchor bolts. The trapezoidal reinforcement steel ribs, the square steel plates for the column foot anchors, and the square steel columns are all fully welded, and 8 trapezoidal reinforcement steel ribs are set around the top of the square steel column foot to form the square steel column foot support. The anchor fixing unit under the original foundation is the high-strength friction-type self-expanding bottom anchor bolt for the column foot, which includes a high-strength friction-type bolt, an anchor steel plate pad, a high-strength fastening screw, and a self-expanding bottom bolt foot. The high-strength friction-type bolt hole is located at the upper part of the original foundation around the column foot. After the high-strength friction-type bolt is anchored in the hole, the self-expanding bottom bolt foot should be locked after the bottom is expanded. After the bolt is installed, an on-site in-situ pull-out test should be carried out to verify whether it is firmly anchored. After the high-strength friction-type bolt is anchored in the hole, the square steel column foot combined steel component welding is carried out.
[0041] Moreover, after the square steel column foot is anchored to the original foundation, the square steel column top is anchored to the original beam. The vertical anchoring structure of the square steel column top includes a rectangular steel plate anchored at the top of the column, a trapezoidal reinforcement steel rib plate, and a high-strength threaded chemical anchor bolt; the trapezoidal reinforcement steel rib plate is used for column top support, and the rectangular steel plate anchored at the top of the column and the square steel column are fully welded, and 4 trapezoidal reinforcement steel rib plates are set on both sides of the square steel column top to form a square steel column top support. The anchor fixing unit on the original beam is a high-strength friction high-strength threaded chemical anchor bolt at the top of the column, which includes a high-strength bolt, an anchor steel plate pad, a high-strength fastening screw, a chemical anchor hole and an anchor glue. After the high-strength bolt is anchored into the hole, the chemical anchor glue is used to fill the hole. After the bolt is installed, an on-site in-situ pull-out test should be carried out to verify whether it is firmly anchored. After the high-strength bolt is anchored into the hole, the square steel column top composite steel component is welded.
[0042] Moreover, after the square steel column top and column foot are anchored, the square steel column and the top and bottom plates of the steel bench welded support are fully welded. The steel bench welded support should be located 1 / 3 of the height above the top surface of the foundation, and the upper short beam should be welded 1 / 3 of the height below the bottom surface of the original beam. The appropriate square steel column section should be selected based on the original beam width and the bearing capacity verification results. The steel plate area of the top and bottom plates of the steel bench welded support should be the same as the square steel column section area.
[0043] The present invention is a symmetrical anti-anchor reinforcement structure for the first-floor beams of a bottom frame brick-concrete building. All steel components are made of Q235B hot-rolled ordinary steel. Before welding, the connection contact surfaces are cleaned of floating rust with a wire brush. E43 type welding rods are used. The weld quality of the butt weld is not less than level 2. If there is no special marking, the welding parts are all fully welded. All bolts are 10.9 grade high-strength bolts.
[0044] In addition, the present invention preferably installs alarms on the top and bottom plates of the steel bench respectively. When the original beam is subjected to a large force and produces deflection, all the steel bolts enter the steel bolt guide holes to make the top plate fit with the bottom plate. At this time, the positive and negative poles are connected to the alarm to remind that the deflection of the original beam has reached the warning value. The symmetrical anti-anchor structure support can ensure the safety of the beam structure. At this time, load reduction measures should be taken to reduce the upper load on the original beam. After the load is reduced, the original beam deflects back, and the deformed steel bolts return to the steel bolt guide holes. After the new steel bolts are replaced, the structure continues to play the role of warning the dangerous force value of the original beam and reinforcing support protection.
[0045] In addition, the present invention is preferably applicable to the long-term reinforcement of a first floor of a frame structure building, and can also be applied to temporary support when increasing the upper vertical load during building decoration or renovation and expansion.
[0046] Finally, all the parts not described in the present invention adopt mature products and mature technical means in the prior art.
[0047] It should be understood that those skilled in the art can make improvements or changes based on the above description, and all these improvements and changes should fall within the scope of protection of the appended claims of the present invention.
Claims
1. A symmetrical anti-anchor reinforcement composite structure for the first floor beam of a bottom frame brick-concrete building, characterized by: It comprises a steel column, a column top anchoring module and a column foot anchoring module, wherein the column top anchoring module is anchored on the bottom surface of the original beam of the building, and the bottom of the column top anchoring module is fixedly connected to the steel column; the bottom of the steel column is fixedly connected to the column foot anchoring module, and the column foot anchoring module is anchored on the top surface of the original foundation of the building; the steel column comprises an upper short column, a steel bench and a lower long column which are coaxially arranged from top to bottom, wherein a plurality of steel bolts which are axially guided and supported and radially limited are evenly arranged on the top surfaces of the steel bench and the lower long column; the top surfaces of the steel bolts are supported by top pressure on the bottom surfaces of the upper short column and the steel bench; The top surfaces of the steel bench and the lower long column are provided with a plurality of steel bolt guide holes, and the openings of the steel bolt guide holes are provided with a plurality of limit holes with diameters larger than the steel bolt guide holes and the steel bolts; The inner ring of the limiting hole is provided with a radial limiting steel bolt, and the axial end face of the limiting hole is provided with an axial limiting steel bolt; The top surface of the steel bolt is welded and fixed to the bottom surface of the upper short column or the bottom surface of the steel bench; When the original beam does not produce deflection, the symmetrical anti-anchor reinforcement composite structure is in a standby static state and does not affect the original structural force system; when the original beam is subjected to force and produces deflection, the steel bolts are squeezed and deformed to provide the original beam deflection deformation margin, and when the original beam is subjected to force and produces deflection, the steel bolts are inserted into the steel bolt guide holes, so that the upper surface of the lower long column is supported by force on the lower surface of the steel bench, and the upper surface of the steel bench is supported by force on the lower surface of the upper short column.
2. The symmetrical anti-anchor reinforcement composite structure of the first floor beam of a bottom frame brick-concrete building according to claim 1 is characterized by: The column top anchoring module and the column foot anchoring module both include an anchoring steel plate and a reinforcing steel rib plate, wherein a steel column is fixed on the anchoring steel plate, and a reinforcing steel rib plate for supporting the steel column laterally is fixed on the anchoring steel plate.
3. The symmetrical reverse anchor reinforcement composite structure of the first floor beam of a bottom frame brick-concrete building according to claim 2 is characterized by: The anchoring steel plate of the column top anchoring module is configured as a rectangular structure arranged along the original beam of the building. The two back-facing side surfaces of the anchoring steel plate facing the extension direction of the original beam of the building are fixedly connected to reinforcing steel ribs, and the anchoring steel plate is anchored to the bottom surface of the original beam of the building by high-strength fastening bolts; a chemical anchoring hole is vertically opened on the bottom surface of the original beam of the building, and the chemical anchoring hole is filled with anchoring glue.
4. The symmetrical reverse anchor reinforcement composite structure of the first floor beam of a bottom frame brick-concrete building according to claim 2 is characterized by: The anchoring steel plate of the column base anchoring module is set as a square structure. Reinforced steel ribs supporting the steel column are fixed in four supporting directions of the anchoring steel plate, and the anchoring steel plate is anchored on the top surface of the original foundation of the building by high-strength fastening bolts with self-expanding bottom bolt feet.
5. A construction method for the symmetrical anti-anchor reinforcement structure of the first floor beam of a bottom frame brick-concrete building as claimed in claim 1, characterized in that: The following steps are involved: Step 1: First, reserve holes for all positions where high-strength bolts are set at the bottom of the original reinforced concrete beam and the upper part of the original building foundation. The hole diameter should be reserved according to the model and process. When drilling, use a rebar detector to avoid the original beam and foundation steel bars. After drilling, the holes should be cleaned first; Step 2: According to the construction sequence of first down and then up, the steel column foot is first anchored to the original foundation. The vertical anchoring structure of the steel column foot includes trapezoidal reinforcement steel ribs, anchor steel plates and high-strength friction-type self-expanding bottom anchor bolts; the trapezoidal reinforcement steel ribs, anchor steel plates and steel columns are all fully welded, and 8 trapezoidal reinforcement steel ribs are set around the top of the steel column foot to form a steel column foot support; after the high-strength friction bolts are anchored in the holes, the self-expanding bottom bolt feet should be locked after the bottom is expanded. After the bolts are installed, an on-site in-situ pull-out test should be carried out to verify whether the anchor connection is firm; after the high-strength friction bolts are anchored in the holes, the steel column foot combined steel components are welded; Step 3: The anchor fixing unit on the original beam is a high-strength friction high-strength threaded chemical anchor bolt on the top of the column. After the high-strength bolt is anchored in the hole, the chemical anchor glue is used to fill the hole. After the bolt is installed, an on-site in-situ pull-out test should be carried out to verify whether the anchor connection is firm; after the high-strength bolt is anchored in the hole, the steel column top composite steel component is welded; Step 4: After completing the installation of the column top anchor module, column foot anchor module, upper short column and lower long column according to steps 1 to 3 above, install the steel bench at the axial interval between the upper short column and the lower long column, and insert the steel bolts into the gaps on the upper surface of the steel bench and the upper surface of the lower long column, and place the steel bolts in the limiting holes. Finally, fix the gap between the top surface of the steel bolt and the upper short column or the bottom surface of the steel bench by full welding.