Automatic point-to-point method and point-to-point device for monitoring system of centralized control center of cascade power plant in river basin
Through the automatic point matching method and device, the problem of inconsistent points between the power plant side and the centralized control center side in the monitoring system of the centralized control center of the cascade power plant in the basin is solved, the matching of event messages and data is achieved, the point matching workload is reduced, and the efficiency is improved Accuracy and efficiency, and through automation, regular and timely warnings for point operations are achieved.
Patent Information
- Application Number
- CN202210750833.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-06-29
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2042-06-29
AI Technical Summary
In the monitoring system of the centralized control center of cascade power plants in the river basin, the points on the power plant side and the centralized control center are inconsistent, resulting in mismatches in event messages and data, resulting in delayed fault handling or unplanned outages, and the workload of point matching is large and time-consuming, making it difficult to Accuracy guaranteed.
An automatic point matching method is designed. By extracting the database point tables of the power plant and the centralized control center, converting them into documents, setting the parameters of the automatic point matching system, and comparing them one by one, when inconsistencies are found, prompts are issued and corrections are made to form a point match. The report is stored in the database, and the automatic point-to-point device host is connected to the storage, database module, human-computer interaction device and alarm prompt module to realize automatic point-to-point.
This prevents inconsistencies in event messages or data between the centralized control center side and the power plant side monitoring system, reduces the point-to-point workload, improves the accuracy and efficiency of point-to-point work, and enables automated regular point-to-point operations, timely warnings and alarms.
Smart Images

Figure CN115016419B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of hydropower plant monitoring systems, and in particular relates to an automatic point-to-point method and a point-to-point device for a monitoring system of a centralized control center of a cascade power plant in a river basin. Background Art
[0002] The so-called point of the monitoring system is represented by: a time or a data interface, for example: the successful startup of generator set No. 1 is a point, and the temperature of the transformer winding is also a point. The centralized control center of the cascade power plant is responsible for the control, regulation, and monitoring of the cascade power plants in the basin, and the main work is completed in the monitoring system. The monitoring system of the centralized control center of the cascade power plant in the basin performs start-up and shutdown control, load regulation, and operation monitoring on the cascade power plants, so the points in the monitoring system of the centralized control center of the cascade power plant must be consistent with the points of the monitoring system of the cascade power plant in the basin, otherwise it will cause major accidents. The cascade power plant in the basin generally contains multiple power plants. The centralized control center needs to work with each cascade power plant. A single power plant has thousands of points. The point-to-point work is difficult and time-consuming. The accuracy of the point-to-point is also difficult to reach 100%, and multiple checks are required. At present, there is no set of perfect point-to-point methods or point-to-point systems for the centralized control center monitoring system of the cascade power plant in the basin. Summary of the invention
[0003] In view of the technical problems existing in the background technology, the present invention provides an automatic point-to-point method and a point-to-point device for the monitoring system of the centralized control center of a river basin cascade power plant. The present invention can prevent the inconsistency of event messages or data between the monitoring system on the centralized control center side and the monitoring system on the power plant side, which not only solves the problem of large workload of point-to-point work, but also ensures the accuracy of the point-to-point work.
[0004] In order to solve the above technical problems, the present invention adopts the following technical solutions to achieve:
[0005] An automatic point-to-point method for a monitoring system of a centralized control center of a cascade power plant in a river basin comprises the following steps:
[0006] Step 1, extracting the power plant database point table and the ladder dispatching database point table;
[0007] Step 2: convert the power plant database point table into a power plant database document, the power plant database document includes a serial number and a character, and convert the centralized control center database point table into a centralized control center database document;
[0008] Step 3, determine the premise of the point;
[0009] Prerequisite 1: Maintenance, upgrade or transformation of the monitoring system of the centralized control center of the cascade power plants in the basin;
[0010] Prerequisite 2: Maintenance, upgrade or renovation of the monitoring system of the power plant in the basin;
[0011] Prerequisite 3: The centralized control center of the cascade power plants in the basin will check in with the power plants in the basin regularly;
[0012] Premise 4: After the backup point is used;
[0013] Prerequisite 5: Inspection of newly commissioned monitoring system points;
[0014] Prerequisite 6: Inspection of the meter points of cascade power plants;
[0015] Step 4: Set the automatic point-to-point system parameters in the centralized control center and the power plant operation server;
[0016] Step 5: After any prerequisites in step 3 are met, start point-to-point operation:
[0017] The serial numbers and characters of the power plant database documents and the centralized control center database documents are compared one by one in sequence. If the serial numbers and characters of the power plant database documents and the centralized control center database documents are found to be inconsistent, a prompt will be issued to the point system program, and the inconsistent documents will be displayed; the point program will be terminated;
[0018] Or through the point-to-point program setting, after finding that the power plant database file and the centralized control center database file are inconsistent, continue to perform the point-to-point work of the power plant database file and the centralized control center database file until the point-to-point work of the power plant database file and the centralized control center database file is completed;
[0019] Step 6: The staff checks the inconsistent documents; after correcting the inconsistencies, continue the point-to-point operation, and after the point-to-point operation is completed, check the action status of the point;
[0020] Step 7, generate a point-to-point report and save the report in the database.
[0021] Preferably, in step 6, the staff modifies the inconsistent parts and then performs action verification: if it is a switch signal, check whether the actions are consistent in the "0" and "1" states respectively; if it is an analog signal, give a specific analog signal value to check whether the actions are consistent.
[0022] Preferably, in steps 1-5, when there are multiple hydropower stations, the power plant database point table is extracted for each hydropower station respectively, and converted into multiple power plant database documents respectively, and each power plant database document is numbered; when compared with the database document of the centralized control center, each power plant database document is compared with the database document of the centralized control center in turn.
[0023] Preferably, when the power plant or the centralized control center modifies the point table, automatic point alignment is required. At this time, the staff needs to communicate and contact. After confirming that the point table has been modified, the staff of the centralized control center or the staff of the power plant can choose to start automatic point alignment. The automatic point alignment process is the process of automatic point alignment between a single power plant and the centralized control center.
[0024] Preferably, the point-to-point report includes time, content, staff, and point-to-point records.
[0025] Preferably, it includes a monitoring system automatic point-to-point device host, the monitoring system automatic point-to-point device host is respectively connected to the storage of multiple power plant points, and the monitoring system automatic point-to-point device host is connected to the storage of the centralized control center point; the monitoring system automatic point-to-point device host is respectively connected to the database module, the human-computer interaction device, the log storage module and the alarm prompt module;
[0026] The storage device at the power plant point is used to take out and store the point meter of the hydropower plant monitoring system;
[0027] The storage device at the central control center is used to take out and store the point table of the monitoring system of the central control center;
[0028] The host of the automatic point-to-point device of the monitoring system is used for automatic point-to-point of the monitoring system and displays the point-to-point results;
[0029] The database module is used to store the situation of each point and the point table of the passed points;
[0030] The human-computer interaction device is used to display the point-to-point results and perform point-to-point settings;
[0031] The log storage module is used to record the information of each point-to-point;
[0032] The alarm prompt module is used to issue early warnings and alarms when point inconsistencies or errors occur, prompting staff to handle them in a timely manner.
[0033] This patent can achieve the following beneficial effects:
[0034] 1. When the monitoring system on the centralized control center side is inconsistent with the monitoring system on the power plant side, the event message or abnormal operation data on the power plant side will be inconsistent with the event message or data of the monitoring system on the centralized control center side, resulting in the staff being unable to timely and accurately judge the impact of the event message or abnormal data, and thus unable to quickly handle the fault, ultimately leading to the expansion of the fault or unplanned shutdown events. The present invention can prevent the event message or data of the monitoring system on the centralized control center side from being inconsistent with the monitoring system on the power plant side.
[0035] 2. The present invention solves the problem of large workload of regular work. According to the requirements of safe and stable operation, it is necessary to regularly perform regular work of point-to-point. This work is large in workload, takes a long time, and is prone to errors. The process of regular point-to-point work is that the staff on both sides check the point number, check the content of the point, and then check the status change of the point. After automatic point-to-point, not only the problem of large workload of point-to-point is solved, but also the accuracy of point-to-point work can be guaranteed.
[0036] 3. The automatic point-to-point device does not require manual operation, so point-to-point work can be performed regularly, that is, a point-to-point cycle is set, and the automatic point-to-point device performs automatic point-to-point. When there is an inconsistency in the point table, an early warning or alarm is issued to prompt the staff to deal with it in time. BRIEF DESCRIPTION OF THE DRAWINGS
[0037] The present invention will be further described below in conjunction with the accompanying drawings and embodiments:
[0038] Figure 1 is a flow chart of the method of the present invention;
[0039] Figure 2 This is a module connection diagram of the present invention. DETAILED DESCRIPTION
[0040] The preferred solution is Figure 1 to Figure 2 As shown, an automatic point-to-point method for a monitoring system of a centralized control center of a cascade power plant in a river basin is provided, and the steps are as follows:
[0041] Step 1, extracting the point table of the power plant database and the point table of the centralized control center database;
[0042] The alarm messages or analog parameters of the monitoring system of the hydropower station are stored in the monitoring system in the form of points. The table storing these points is called a point table. When a point in the point table is activated with the corresponding point of the power plant (the point of the switch quantity is activated), the alarm message corresponding to the point in the corresponding centralized control center monitoring system will also be displayed due to the action of the point. Therefore, if the monitoring system wants to operate accurately, the point table of the power plant must be completely consistent with the point table of the centralized control center monitoring system. The content of the point table mainly includes the point number (number), the point number of all points is different, the text description of the point, the action of the point (mainly the state of the point is 1 or 0, the action when it is in state 1, and the action when it is in state 0). There are also some spare points in the point table for adding alarm message signals or analog signals.
[0043] Step 2: convert the power plant database point table into a power plant database document, the power plant database document includes serial numbers and characters, and convert the centralized control center database point table into a centralized control center database document; the document includes an Excel table or a Word text;
[0044] Step 3, determine the premise of the point;
[0045] Prerequisite 1: Maintenance, upgrading or transformation of the monitoring system of the centralized control center of the cascade power plants in the basin;
[0046] The monitoring system of the centralized control center of the cascade power plant in the basin will be regularly maintained and upgraded, or after a certain number of years of use, the monitoring system needs to be transformed, that is, a new monitoring system is used. Regardless of maintenance, upgrading, or transformation, after completing the corresponding work, it is necessary to conduct point matching to ensure the consistency of the points on the centralized control center side of the cascade power plant in the basin and the power plant side of the basin.
[0047] Prerequisite 2: Maintenance, upgrading or transformation of monitoring systems of cascade power plants;
[0048] The monitoring system of the cascade power plant in the basin will be regularly maintained and upgraded, or after a certain number of years of use, the monitoring system needs to be transformed, that is, a new monitoring system is used. Regardless of maintenance, upgrading, or transformation, after completing the corresponding work, it is necessary to conduct point matching to ensure the consistency of the points on the centralized control center side of the cascade power plant in the basin and the cascade power plant side.
[0049] Prerequisite 3: The centralized control center of the cascade power plants in the basin will check in with the cascade power plants regularly;
[0050] In order to ensure the safe and stable operation of the centralized control center and the monitoring system of the cascade power plants in the basin, it is necessary to conduct regular point-to-point work on the point meters on both sides.
[0051] Premise 4: After the backup point is used;
[0052] In order to ensure the scalability of the monitoring system, multiple spare points are often reserved in the point table. Regardless of whether the spare points of the monitoring system of the centralized control center of the cascade power plant in the basin are used, or the spare points of the point table of the cascade power plant monitoring system are used, point matching work is required to ensure the consistency of the point tables on both sides.
[0053] Prerequisite 5: Inspection of newly commissioned monitoring system points;
[0054] After the monitoring system is redeveloped, it is necessary to check the points before it is put into production to ensure the correctness of the point table during the later trial operation. After the trial operation is completed, the point check work is carried out again to ensure the correctness and completeness of the point table, so as to ensure the normal operation of the later monitoring system.
[0055] Prerequisite 6: Inspection of the meter points of cascade power plants;
[0056] The monitoring system controls and monitors the power generation equipment of the cascade power plants. The automatic point-to-point system monitors and inspects the point meters of the cascade power plants. It performs automatic point-to-point checking regularly and issues alarms in time if any abnormality is found in the point meters of the cascade power plants, prompting the staff and the staff of the cascade power plants to check and handle the situation.
[0057] Step 4: Set the automatic point-to-point system parameters in the centralized control center and the power plant operation server;
[0058] Step 5: After any prerequisites in step 3 are met, start point-to-point operation:
[0059] The serial numbers and characters of the power plant database files and the centralized control center database files are compared one by one in turn. If the serial numbers and characters of the power plant database files and the centralized control center database files are found to be inconsistent, the point-to-point system program will issue a prompt and display the inconsistent files; the point-to-point program will be terminated; the point-to-point program can also be set to continue the point-to-point work of the power plant database files and the centralized control center database files after the inconsistency is found between the power plant database files and the centralized control center database files until the point-to-point work of the power plant database files and the centralized control center database files is completed;
[0060] Step 6: The staff checks the inconsistent documents; after correcting the inconsistencies, continue the point-to-point operation; after the power plant database document and the centralized control center database document are aligned, the action status of the point is checked;
[0061] Step 7, generate a point-to-point report and save the report in the database.
[0062] Furthermore, in step 6, the staff will check the actions of the inconsistencies: if it is a switch signal, check whether the actions are consistent in the "0" and "1" states respectively; if it is an analog signal, give a specific analog signal value to check whether the actions are consistent.
[0063] Furthermore, in steps 1-5, when a single hydropower station is aligned with the centralized control center, the power plant is first selected for alignment with the centralized control center. After selection, automatic alignment begins. The staff does not need to operate and can monitor the alignment work or not. After the alignment work is completed, there will be a detailed alignment report.
[0064] The process of automatic point alignment: After the power plant is selected to be aligned with the centralized control center, the alignment system automatically calls out the point table of the power plant (the point table is updated in real time. After the power plant completes the work, the point table will be automatically updated to the latest point table), and then extracts the point table corresponding to the power plant from the database of the centralized control center monitoring system to start automatic point alignment. The first point alignment is the consistency between the point number (serial number) and the character (or text) description. Compare the two point tables to see whether all the point numbers and the corresponding text descriptions are completely consistent. If not, the automatic point alignment system will display all the inconsistencies to the staff in the form of a document report, and the automatic point alignment process will stop and issue a prompt. The staff will check. If they are completely consistent, the point alignment work will continue to check after the action of the point, that is, the same point in the power plant and the centralized control center, whether the action consequences when the flag bit is 1 are consistent with the action consequences when the flag bit is 0. For the analog point, a number (analog quantity) is given to compare the two points. Regardless of whether they are consistent, after the completion of the point alignment content, a document report will be formed to show the comparison of the content. If there is an inconsistency, the inconsistent content will be listed in detail. After the point-to-point check is completed, a detailed point-to-point report will be generated, including the point-to-point check time, content, staff, point-to-point details, etc. The point-to-point report will be saved in the database.
[0065] When there are multiple hydropower stations, the database point table is extracted for each hydropower station and converted into multiple power plant database documents respectively, and each power plant database document is numbered; when compared with the database document of the centralized control center, each power plant database document is compared with the database document of the centralized control center in turn.
[0066] When multiple power plants perform monitoring system maintenance or point table modifications, generally, some units may be maintained and upgraded during the overhaul period, and the corresponding point tables may also be modified accordingly. In this case, multiple power plants are required to perform point-to-point work with the centralized control center. When multiple power plants and stations are performing point-to-point work with the centralized control center, they need to queue up for point-to-point work. The system will automatically form a point-to-point order, and the point-to-point order can also be manually intervened. However, automatic point-to-point work is fully automated, and the point-to-point work time is short. There is no need to intervene in the point-to-point order. After the point-to-point work is completed, the corresponding point-to-point report is generated according to the plant station. When multiple power plants are performing point-to-point work with the centralized control center, except for the point-to-point order, the point-to-point process between each power plant and the centralized control center is the same.
[0067] Furthermore, when the power plant or the centralized control center modifies the point table, automatic point matching is required. At this time, the staff needs to communicate and contact. After confirming that the point table has been modified, the staff of the centralized control center or the power plant staff can choose to start automatic point matching. The automatic point matching process is the process of automatic point matching between a single power plant and the centralized control center.
[0068] After automatic alignment, if the point tables on both sides are completely consistent, no further operation is required. The automatic alignment process is the same as the alignment process between a single power plant and the centralized control center. After the alignment is completed, a detailed alignment report will also be generated.
[0069] Furthermore, to ensure the normal operation of the monitoring system of the centralized control center, the point meter of the cascade power plant and the centralized control center needs to be consistent. To prevent one party from changing the point meter due to work needs or other work affecting the point meter, the point meter needs to be monitored and automatically checked to ensure the consistency of the point meter. The staff can set a regular check-in time. When the time arrives, the system automatically checks the point and generates a check-in report. When there is an inconsistency in the point meter, an alarm is issued in the monitoring system to prompt the staff to deal with it in time.
[0070] Preferably, the automatic point-to-point device of the hydropower plant monitoring system automatic point-to-point method comprises a monitoring system automatic point-to-point device host, the monitoring system automatic point-to-point device host is respectively connected to the storages of multiple power plant points, and the monitoring system automatic point-to-point device host is connected to the storage of the centralized control center point; the monitoring system automatic point-to-point device host is respectively connected to the database module, the human-computer interaction device, the log storage module and the alarm prompt module;
[0071] The storage device at the power plant point is used to take out and store the point meter of the hydropower plant monitoring system;
[0072] The storage device at the central control center is used to take out and store the point table of the monitoring system of the central control center;
[0073] The host of the automatic point-to-point device of the monitoring system is used for automatic point-to-point of the monitoring system and displays the point-to-point results;
[0074] The database module is used to store the situation of each point and the point table of the passed points;
[0075] The human-computer interaction device is used to display the point-to-point results and perform point-to-point settings;
[0076] The log storage module is used to record the information of each point-to-point;
[0077] The alarm prompt module is used to issue early warnings and alarms when point inconsistencies or errors occur, prompting staff to handle them in a timely manner.
[0078] The above embodiments are only preferred technical solutions of the present invention and should not be regarded as limiting the present invention. The protection scope of the present invention shall be the technical solutions recorded in the claims, including equivalent replacement solutions of the technical features in the technical solutions recorded in the claims. That is, equivalent replacement improvements within this scope are also within the protection scope of the present invention.
Claims
1. An automatic point-to-point method for the monitoring system of the centralized control center of cascade power plants in a river basin, Features The following steps are involved: Step 1, extracting the point table of the power plant database and the point table of the centralized control center database; Step 2: convert the power plant database point table into a power plant database document, the power plant database document includes a serial number and a character, and convert the centralized control center database point table into a centralized control center database document; Step 3, determine the premise of the point; Prerequisite 1: Maintenance, upgrading or transformation of the monitoring system of the centralized control center of the cascade power plants in the basin; Prerequisite 2: Maintenance, upgrading or renovation of monitoring systems of power plants in the basin; Prerequisite 3: The centralized control center of the cascade power plants in the basin will check in with the power plants in the basin regularly; Premise 4: After the backup point is used; Prerequisite 5: Inspection of newly commissioned monitoring system points; Prerequisite 6: Inspection of the meter points of cascade power plants; Step 4: Set the automatic point-to-point system parameters in the centralized control center and the power plant operation server; Step 5: After any prerequisites in step 3 are met, start point-to-point operations: The serial numbers and characters of the power plant database documents and the centralized control center database documents are compared one by one in sequence. If the serial numbers and characters of the power plant database documents and the centralized control center database documents are found to be inconsistent, a prompt will be issued to the point system program, and the inconsistent documents will be displayed; the point program will be terminated; Or through the point-to-point program setting, after finding that the power plant database file and the centralized control center database file are inconsistent, continue to perform the point-to-point work of the power plant database file and the centralized control center database file until the point-to-point work of the power plant database file and the centralized control center database file is completed; Step 6: The staff checks the inconsistent documents; after correcting the inconsistencies, they continue to perform point-to-point operations, and after point-to-point operations are completed, they check the action status of the points; Step 7, generate a point-to-point report and save the report in the database.
2. According to claim 1, the automatic point-to-point method for the monitoring system of the centralized control center of the river basin cascade power plant, Features: In step 6, the staff will modify the inconsistencies and then check the actions: if it is a switch signal, check whether the actions are consistent in the "0" and "1" states respectively; if it is an analog signal, give a specific analog signal value to check whether the actions are consistent.
3. The automatic point-to-point method for the monitoring system of the centralized control center of the cascade power plant in the basin according to claim 1, Features: In steps 1-5, when there are multiple hydropower stations, the power plant database point table is extracted for each hydropower station, and converted into multiple power plant database documents, and each power plant database document is numbered; when compared with the centralized control center database document, each power plant database document is compared with the centralized control center database document in turn.
4. The automatic point-to-point method for the monitoring system of the centralized control center of the cascade power plant in the basin according to claim 1, Features: When the power plant or the centralized control center modifies the point list, automatic point matching is required. At this time, the staff needs to communicate and contact each other. After confirming that the point list has been modified, the staff of the centralized control center or the power plant staff will choose to start automatic point matching. The automatic point matching process is the process of automatic point matching between a single power plant and the centralized control center.
5. According to claim 1, the automatic point-to-point method for the monitoring system of the centralized control center of the river basin cascade power plant, Features: The point-to-point report includes time, content, staff, and point-to-point records.