Multi-objective planning method and system for integrated energy system with uncertain supply and demand

Through a multi-target planning method for comprehensive energy system oriented towards supply and demand uncertainty, combined with robust parameters and carbon emission measurement indicators, the complexity of uncertainty planning and insufficient carbon emission reduction targets in the existing technology are solved, and the rapid development of the , accurate and optimized configuration, suitable for engineering applications of integrated energy systems.

CN115049250BActive Publication Date: 2024-11-08SHANDONG ELECTRIC POWER ENG CONSULTING INST CORP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210662966.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-06-13
Publication Date
2024-11-08
Estimated Expiration
2042-06-13

AI Technical Summary

Technical Problem

The existing comprehensive energy system planning method is difficult to comprehensively consider the multiple uncertainties on both supply and demand under uncertain conditions, and the consideration of carbon emission reduction targets in the context of carbon neutrality has led to the loss of rationality and optimization of planning and allocation. It is difficult to apply widely in engineering.

Method used

Using a multi-objective planning method for comprehensive energy systems with uncertain supply and demand, it is transformed into a deterministic multi-objective optimization model by obtaining basic data, building alternative equipment energy flow models, introducing robust parameters and carbon emission environmental protection measurement indicators, and using The congestion generation algorithm is used to optimize the solution to obtain the IES optimal planning scheme.

Benefits of technology

On the basis of taking into account both economic and carbon emission reduction goals, the efficiency and accuracy of optimized configuration and capacity planning are improved, the calculation complexity is reduced, and the economic, environmental protection and robustness of the system is adapted to the economic, environmental protection and robustness of the system, and it has good Engineering practicality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115049250B_ABST
    Figure CN115049250B_ABST
Patent Text Reader

Abstract

The present disclosure provides a multi-objective planning method and system for an integrated energy system with supply and demand uncertainties, which belongs to the technical field of integrated energy system optimization planning. The scheme includes: acquiring basic data of a site to be built; constructing an energy flow model of alternative equipment based on pre-determined equivalent characteristic parameters of the operation of alternative equipment; constructing a multi-objective optimization planning model for the integrated energy system based on the energy flow model of the alternative equipment and uncertainty descriptions of multiple stations and multiple users on both the supply and demand sides; converting the multi-objective optimization planning model with uncertainty factors into a deterministic multi-objective optimization model based on equivalent transformation; and optimizing and solving the deterministic multi-objective optimization model based on the basic data using a constraint generation algorithm based on congestion to obtain an IES optimal planning scheme.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present disclosure belongs to the technical field of integrated energy system optimization planning, and in particular, relates to a multi-objective planning method and system for an integrated energy system facing supply and demand uncertainty. Background Art

[0002] The statements in this section merely provide background information related to the present disclosure and do not necessarily constitute prior art.

[0003] Integrated Energy System (IES) is an energy system that unifies the planning and dispatch of various energy sources such as electricity, heat, cooling, and gas to achieve multi-energy complementary and coordinated supply. It has the advantages of high comprehensive energy utilization efficiency, the ability to promote the local consumption of renewable energy, and the ability to meet diverse energy needs. It is an important direction for the future low-carbon transformation of energy. The structure of the integrated energy system is complex and diverse. In the face of different load demands and resource endowments, rational planning of system configuration according to local conditions is an important prerequisite for exerting its advantages, and is also the basis for the efficient operation of the integrated energy system and the realization of investment returns.

[0004] At present, there have been certain studies on the planning and optimization configuration technology of integrated energy systems at home and abroad, but most of them are modeling and planning for energy systems with certain scenarios and specific combinations. The integrated energy system contains a large amount of renewable energy such as wind and light, and is directly oriented to user needs. The uncertainty of renewable energy output and diversified energy demand often leads to the loss of rationality and optimization of planning and configuration schemes under certain scenarios. For the planning of integrated energy systems under uncertain conditions, commonly used optimization modeling methods mainly include stochastic optimization and robust optimization. Stochastic optimization planning methods generally require accurate probability density distribution of known uncertain variables, and the accuracy of optimization results is subject to the degree of fitting of probability density. Robust optimization does not require knowing the probability distribution of uncertain variables, but only needs to determine the range of the uncertainty set. The solution can adapt to the worst scenario and is more widely used in actual solving of uncertainty problems. The inventors found that the current research and application status of robust optimization planning technology for integrated energy systems, the existing methods still have the following problems:

[0005] (1) Existing technologies mainly consider the impact of single uncertain factors such as energy supply or demand response, and fail to comprehensively consider the multiple uncertainties of multiple stations and users on both the supply and demand sides;

[0006] (2) Most existing planning methods only target economic goals. In the context of carbon neutrality, they do not adequately consider carbon emission reduction targets. Multi-stage robust optimization models with multiple optimization objectives are complex to solve, and it is difficult to obtain satisfactory solutions within the specified time in general integrated energy engineering scenarios, making them difficult to be widely used in engineering. Summary of the invention

[0007] In order to solve the above-mentioned problems, the present disclosure provides a multi-objective planning method and system for an integrated energy system with uncertain supply and demand. The scheme effectively simplifies the optimization model and solution process on the basis of taking into account the economic efficiency and carbon emission reduction goals and the robustness of the configuration scheme, thereby realizing rapid optimal configuration and capacity planning of the integrated energy system, and improving the optimization efficiency and the accuracy of the optimization planning.

[0008] According to a first aspect of an embodiment of the present disclosure, a multi-objective planning method for an integrated energy system with supply and demand uncertainty is provided, comprising:

[0009] Obtain basic data of the site to be built, wherein the basic data includes the upper and lower limits of the investment capacity of the integrated energy system equipment and unit cost data, and predict the wind and solar power output data under unit capacity and the load demand data of different energy sources of users;

[0010] Based on the predetermined equivalent characteristic parameters of the operation of the alternative equipment, an energy flow model of the alternative equipment is constructed;

[0011] Based on the energy flow model of alternative equipment and the uncertainty description of multiple stations and multiple users on both the supply and demand sides, a multi-objective optimization planning model for the integrated energy system is constructed; wherein, considering the uncertainty of photovoltaic, wind power output and load demand, the uncertainty sets of the energy supply side and the load demand side are constructed by introducing robust parameters; and the carbon emission environmental protection measurement index is introduced into the multi-objective optimization planning model of the integrated energy system;

[0012] Based on equivalent transformation, the multi-objective optimization planning model with uncertain factors is transformed into a deterministic multi-objective optimization model;

[0013] Based on the basic data, the deterministic multi-objective optimization model is optimized and solved by using a congestion-based constraint generation algorithm to obtain the IES optimal planning solution.

[0014] Furthermore, the energy supply side uncertainty set is specifically expressed as follows:

[0015]

[0016]

[0017] Among them, μ i,t and are the actual output and predicted output of the ith photovoltaic, wind power and other uncertain energy access points in period t; Δμ i,t is the maximum deviation between the actual output and the predicted output; i,t is the deviation coefficient; Ω is the set of uncertain energy access points; Γ s ∈[0,|Ω|] is the robust parameter of uncertain energy output.

[0018] Furthermore, the uncertainty set on the load demand side is specifically expressed as follows:

[0019]

[0020]

[0021] in, and are the actual load demand and predicted demand of energy k of the jth energy user in period t, respectively; is the maximum deviation between actual demand and predicted demand; is the deviation coefficient; Ψ is the set of energy users; Γ n ∈[0,|Ψ|] is the robust parameter of uncertain energy demand.

[0022] Furthermore, the multi-objective optimization planning model of the integrated energy system is specifically expressed as follows:

[0023]

[0024] Among them, C total is the annualized total cost of IES, E m is the total annual CO2 emissions, X is the IES planning decision variable (vector, corresponding to the configuration capacity of each alternative equipment), and ξ is the uncertainty deviation coefficient.

[0025] Furthermore, the constraints of the multi-objective optimization planning model of the integrated energy system include energy flow model constraints of each device, system configuration capacity constraints and system operation constraints.

[0026] Furthermore, based on the equivalent transformation, the multi-objective optimization planning model with uncertain factors is transformed into a deterministic multi-objective optimization model, specifically: the energy balance constraint containing uncertain deviation coefficients in the multi-objective optimization model is transformed into an inequality form according to the necessary conditions for energy supply, and the dual cone method is used to perform robust equivalent transformation on it.

[0027] Furthermore, the energy flow model of the alternative equipment is constructed, including a gas turbine model, a waste heat boiler model, a gas boiler model, an electric boiler heating model, an electric refrigerator refrigeration model, an absorption refrigerator refrigeration model, a heat pump model, a photovoltaic power generation model, a wind power generation model, an electric energy storage device model and a hot and cold dual water storage tank model.

[0028] According to a second aspect of an embodiment of the present disclosure, a multi-objective planning system for an integrated energy system with supply and demand uncertainty is provided, comprising:

[0029] A data acquisition unit, which is used to acquire basic data of the site to be built, wherein the basic data includes the upper and lower limits of the investment capacity of the integrated energy system equipment and unit cost data, and predicts the wind and solar power output data under unit capacity and the load demand data of different energy sources of users;

[0030] An alternative equipment energy flow model construction unit, which is used to construct an alternative equipment energy flow model based on pre-determined equivalent characteristic parameters of the alternative equipment operation;

[0031] A multi-objective optimization planning model construction unit is used to construct a multi-objective optimization planning model for an integrated energy system based on an alternative equipment energy flow model and uncertainty descriptions of multiple stations and multiple users on both the supply and demand sides; wherein, taking into account the uncertainty of photovoltaic and wind power output and load demand, an uncertainty set of the energy supply side and the load demand side is constructed by introducing robust parameters; and a carbon emission environmental protection measurement index is introduced into the multi-objective optimization planning model for the integrated energy system;

[0032] A model conversion unit, which is used to convert a multi-objective optimization planning model with uncertain factors into a deterministic multi-objective optimization model based on equivalent transformation;

[0033] The optimization solving unit is used to optimize and solve the deterministic multi-objective optimization model based on the basic data by adopting a constraint generation algorithm based on congestion to obtain the IES optimal planning solution.

[0034] According to a third aspect of an embodiment of the present invention, a computer-readable storage medium is provided, on which a program is stored, and when the program is executed by a processor, the multi-objective planning method for an integrated energy system with supply and demand uncertainties is implemented as described above.

[0035] According to a fourth aspect of an embodiment of the present invention, there is provided an electronic device comprising a memory, a processor, and a program stored in the memory and executable on the processor, wherein when the processor executes the program, the method for multi-objective planning of an integrated energy system with uncertain supply and demand is implemented as described above.

[0036] Compared with the prior art, the beneficial effects of the present invention are:

[0037] (1) The present disclosure provides a multi-objective planning method and system for an integrated energy system with uncertain supply and demand. The scheme effectively simplifies the optimization model and solution process on the basis of taking into account the economic efficiency, carbon emission reduction goals and the robustness of the configuration scheme, thereby realizing rapid optimization configuration and capacity planning of the integrated energy system, and improving the optimization efficiency and the accuracy of the optimization planning.

[0038] (2) The scheme disclosed in the present invention fully considers the uncertainty of wind and solar power output on the supply side and multi-user load on the demand side. It is not necessary to establish a probabilistic model of uncertainty parameters. It is only necessary to set its fluctuation range and adopt robust equivalent conversion to reduce the computational complexity. The robustness of the planning scheme can be adjusted by setting robust parameters to take into account the system's economic and environmental protection indicators and system robustness. The setting of carbon emission targets can provide important guidance for low-carbon planning under the background of carbon neutrality. At the same time, by adopting a constraint generation algorithm based on congestion, an optimal solution within a certain target constraint interval can be obtained in each cycle. Compared with the iterative search of the existing multi-objective and multi-stage optimization algorithm, it not only ensures the target spatial distribution of the optimization solution, but also shortens the model solution calculation time, and has good engineering practicality.

[0039] Advantages of additional aspects of the present disclosure will be given in part in the following description and in part will become apparent from the following description or will be learned through practice of the present disclosure. BRIEF DESCRIPTION OF THE DRAWINGS

[0040] The accompanying drawings constituting a part of the present disclosure are used to provide a further understanding of the present disclosure. The illustrative embodiments of the present disclosure and their descriptions are used to explain the present disclosure and do not constitute an improper limitation on the present disclosure.

[0041] Figure 1 This is a workflow diagram of the multi-objective planning method for an integrated energy system with supply and demand uncertainty described in an embodiment of the present disclosure. DETAILED DESCRIPTION

[0042] The present disclosure is further described below in conjunction with the accompanying drawings and embodiments.

[0043] It should be noted that the following detailed descriptions are exemplary and are intended to provide further explanation of the present disclosure. Unless otherwise specified, all technical and scientific terms used herein have the same meanings as those commonly understood by those skilled in the art to which the present disclosure belongs.

[0044] It should be noted that the terms used herein are only for describing specific embodiments and are not intended to limit the exemplary embodiments according to the present disclosure. As used herein, unless the context clearly indicates otherwise, the singular form is also intended to include the plural form. In addition, it should be understood that when the terms "comprising" and / or "including" are used in this specification, it indicates the presence of features, steps, operations, devices, components and / or combinations thereof.

[0045] In the absence of conflict, the embodiments in the present disclosure and the features in the embodiments may be combined with each other.

[0046] Embodiment 1:

[0047] The purpose of this embodiment is to provide a multi-objective planning method for an integrated energy system with supply and demand uncertainty.

[0048] A multi-objective planning method for an integrated energy system with supply and demand uncertainty, comprising:

[0049] Step 1: Obtain basic data of the site to be built, wherein the basic data includes the upper and lower limits of the investment capacity of the integrated energy system equipment and unit cost data, and predict the wind and solar output data under unit capacity and the load demand data of different energy sources of users;

[0050] Specifically, step 1 includes: obtaining the upper and lower limits of the investment capacity of various types of equipment and unit capacity cost data according to the resource endowment, load demand conditions, construction condition restrictions, etc. of the location where the integrated energy system to be built is located, and predicting the multi-energy load demand curves of cooling, heating, electricity, gas, etc. and the output curves of photovoltaic and wind power per unit capacity of each user in a typical year or typical day;

[0051] Step 2: Based on the predetermined equivalent characteristic parameters of the operation of the alternative equipment, an energy flow model of the alternative equipment is constructed;

[0052] Specifically, step 2 is as follows: according to the efficiency characteristics of various types of IEs equipment in the site to be built, determine the equivalent characteristic parameters of each device (specifically energy conversion efficiency, cooling and heating coefficient, energy storage charging and discharging efficiency and dissipation coefficient, etc.), and establish the energy flow model of each device accordingly. The details are as follows:

[0053] 1) The gas turbine output power expression is as follows:

[0054]

[0055] Where: and are the power output and heat output of the gas turbine during period t respectively; and are the power generation efficiency and heat loss rate of the gas turbine respectively; V GT,t is the natural gas input of the gas turbine during period t; H gas is the lower calorific value of natural gas. The typical model of a gas internal combustion engine is similar to that of a gas turbine, and its power generation and heat output are expressed in terms of t and Alternative representation.

[0056] 2) The waste heat boiler model expression is as follows:

[0057]

[0058] In the formula, Q WB,t and are the heat output of the waste heat boiler and the input flue gas heat during period t respectively; η WBIt is the heat recovery conversion efficiency of waste heat boiler.

[0059] 3) The gas boiler model expression is as follows:

[0060] Q GB,t =η GB ·V GB,t ·H gas (3)

[0061] In the formula, Q GB,t is the heat output of the gas boiler during period t; η GB is the conversion efficiency of the gas boiler; V GB,t is the natural gas input to the gas boiler during period t.

[0062] 4) The heating expression of electric boiler is as follows:

[0063] Q EB,t =η EB ·P EB,t (4)

[0064] In the formula, Q EB,t is the output heat of the electric boiler during period t; η EB is the conversion efficiency of electric boiler; P EB,t is the input power of the electric boiler during period t.

[0065] 5) The refrigeration expression of the electric refrigerator is:

[0066] Q EC,t =γ EC ·P EC,t (5)

[0067] In the formula, Q EC,t is the cooling capacity of the electric refrigerator during period t; EC is the coefficient of performance (COP) of the electric refrigerator; P EC,t is the input power of the electric refrigerator during period t.

[0068] 6) The refrigeration expression of absorption refrigeration machine is:

[0069]

[0070] In the formula, Q AC,t is the cooling capacity of the absorption refrigerator during period t; AC is the coefficient of performance (COP) of the absorption chiller; is the input thermal power of the absorption refrigerator during period t.

[0071] 7) Heat pumps are divided into air source heat pumps, water source heat pumps and ground source heat pumps according to the type of heat source. Generally speaking, heat pumps can achieve two operating conditions: heating and cooling. Its mathematical model is

[0072]

[0073] In the formula, and are the heating and cooling capacities of the heat pump during period t respectively; and are the heating coefficient and cooling coefficient of the heat pump respectively; and are the input electrical power of the heat pump during period t respectively. and It is a 0-1 variable, indicating the operating condition of the heat pump in period t. The heat pump can only work in one condition, heating or cooling, in the same period. When is 1, the heat pump is in heating condition, and when When it is 1, the heat pump is in cooling condition; is a very large constant.

[0074] 8) Photovoltaic and wind power are connected as distributed power sources, and their power generation output can be expressed as

[0075] P PV,t =X PV ·μ PV,t (8)

[0076] P WT,t =X WT ·μ WT,t (9)

[0077] Where P PV,t and P WT,t are the output of photovoltaic power and wind power in period t respectively; X PV and X WT are the configuration capacities of photovoltaic and wind power respectively; μ PV,t and μ WT,t are the output values ​​of photovoltaic and wind power of unit capacity in period t respectively.

[0078] 9) As an energy storage device, the charging and discharging process of the battery is expressed as

[0079]

[0080] In the formula, is the battery charge at the end of period t; and are the charging and discharging power of the battery during period t; e is the dissipation coefficient of the battery; and The charging and discharging efficiency of the battery respectively.

[0081] 10) The water storage tank can be used to store cold or heat alone, or it can be used to store both cold and hot water. The model of the cold and hot dual water storage tank is as follows:

[0082]

[0083] In the formula, and are the cold storage capacity and heat storage capacity of the water storage tank at the end of period t respectively; and They are the cooling power and cooling release power of the water storage tank respectively; and are the heat storage and heat release power of the water storage tank respectively; δ c and δ h are the dissipation coefficients of the water storage tank in the cold storage or heat storage mode, respectively; and are the cold storage and cooling release efficiencies of the water storage tank respectively; and are the heat storage and heat release efficiencies of the water storage tank, respectively; and is a 0-1 variable, indicating that the water storage tank is operating in the cold storage or heat storage mode during the period t. is a very large constant.

[0084] Step 3: Based on the energy flow model of the candidate equipment and the uncertainty description of multiple stations and multiple users on both the supply and demand sides, a multi-objective optimization planning model for the integrated energy system is constructed; wherein, considering the uncertainty of photovoltaic and wind power output and load demand, the uncertainty sets of the energy supply side and the load demand side are constructed by introducing robust parameters; and the carbon emission environmental protection measurement index is introduced into the multi-objective optimization planning model of the integrated energy system;

[0085] Wherein, the step 3 is specifically as follows:

[0086] Combined with the description of uncertainty on both the supply and demand sides, a multi-objective robust optimization planning model for the integrated energy system is constructed.

[0087] (1) Considering the uncertainty of photovoltaic and wind power output and load demand, robust parameters are introduced to construct the uncertainty set of energy supply and demand. The uncertainty set on the energy supply side is described as follows:

[0088]

[0089]

[0090] In the formula, μ i,t and are the actual output and predicted output of the ith photovoltaic, wind power and other uncertain energy access points in period t; Δμ i,t is the maximum deviation between the actual output and the predicted output;i,t is the deviation coefficient; Ω is the set of uncertain energy access points; Γ s ∈[0,|Ω|] is the robust parameter of uncertain energy output, which characterizes the spatial clustering effect of uncertain energy output in practical problems, that is, the deviation coefficients of various uncertain energy outputs cannot reach the boundary at the same time in the same period.

[0091] The uncertainty set on the load demand side is described as follows:

[0092]

[0093]

[0094] In the formula, and are the actual load demand and predicted demand of energy k of the jth energy user in period t, respectively; is the maximum deviation between actual demand and predicted demand; is the deviation coefficient; Ψ is the set of energy users; Γ n ∈[0,|Ψ|] is a robust parameter for uncertain energy demand. By adjusting Γ s and Γ n The robustness of the planning system can be changed.

[0095] (2) The constraints of the robust optimization planning model of the integrated energy system include not only the energy flow model constraints of each device, but also the system configuration capacity constraints and operation constraints. The system operation constraints mainly include energy balance constraints, equipment operation constraints, interaction constraints with the power grid, and system network constraints.

[0096] 1) Configure capacity constraints

[0097]

[0098] Where, X i is the investment capacity of equipment i; is the maximum construction capacity limit of equipment i; I = {GT, GE, WB, GB, EB, EC, AC, HP, PV, WT, ES, WS}, is the equipment type set.

[0099] 2) Energy balance constraints

[0100] Energy balance constraints include electricity balance, heat balance, cold balance and gas balance constraints, that is, the sum of the input and production of each energy is equal to the sum of the output and consumption.

[0101] Electrical balance:

[0102]

[0103] Thermal balance:

[0104]

[0105] Cold balance:

[0106] Gas balance:

[0107] In the formula, and are the amount of electricity purchased and sold from the power grid by the system during period t; V in,t is the gas purchase volume in period t, and are the load forecast demand and maximum fluctuation deviation of gas for the jth energy user in period t, respectively.

[0108] 3) Equipment operation constraints

[0109] Equipment operation constraints include equipment output constraints and energy storage capacity constraints, where equipment output constraints are:

[0110]

[0111]

[0112]

[0113]

[0114] In the formula, is the minimum operating load factor of equipment i; σ hc It is the conversion factor of rated capacity of heat pump for hot and cold working conditions.

[0115] The operating constraints of the energy storage device are as follows:

[0116]

[0117]

[0118] In the formula, and are the lower limit proportional coefficients of the energy-release capacity of the battery and the water tank respectively; and They are the battery charge and discharge limit multiples respectively; and They are respectively the storage and discharge limit multiples in the cold storage mode of the water storage tank; and They are respectively the storage and discharge limit multiples in the water tank heat storage mode; and Assign capacity X to the water storage tanks WSThe corresponding rated cooling and heating capacity can be obtained by the following formula:

[0119]

[0120] In the formula, Δt c and Δt h are the design temperature differences of the cold storage and heat storage modes of the water storage tank, respectively, in °C; and The unit is kWh, X WS The unit is m 3 .

[0121] In addition, for periodic energy storage applications, the energy at the beginning and end of the storage and discharge cycle must be equal:

[0122]

[0123] 4) Interaction constraints with the power grid

[0124]

[0125] In the formula, It is the upper limit of the power interaction with the upper-level power grid tie line.

[0126] 5) System network constraints

[0127] IES configuration needs to consider factors such as process system flow and energy cascade utilization to meet the requirements of input and output energy types and quality parameters of various equipment. Constraints related to process flow principles, for example, waste heat boilers use gas turbines to exhaust smoke, and absorption chillers use gas internal combustion engines, waste heat boilers or gas boilers to output heat. The network constraints are as follows:

[0128]

[0129] (3) IES planning is a typical multi-objective optimization problem. Especially in the current context of carbon peak and carbon neutrality, IES planning needs to at least take into account both economic and environmental goals. The economic objective function is expressed as:

[0130] minC total =C inv +C op +C ma

[0131] In the formula, C total is the annualized total cost of IES; C inv is the annualized cost of equipment investment; C op and C ma are the annual operation and maintenance costs of IES respectively.

[0132] The calculation formula for the annualized cost of equipment investment is:

[0133]

[0134] In the formula, r is the annual interest rate; n is the system design life; p i The cost of investing in unit capacity for equipment i.

[0135] The calculation formula for system operation and maintenance cost is:

[0136]

[0137]

[0138] Where D is the set of typical days in a typical year; N d is the number of days corresponding to a typical day d in a typical year; and are the unit prices for purchasing and selling electricity from the power grid respectively; is the unit price of gas purchase; is the maintenance cost corresponding to the unit output of equipment i; Q i,t is the output of device i in period t.

[0139] In the context of carbon neutrality, the total annual CO2 emissions are used as the environmental performance indicator of IES planning, and the environmental performance objective function is expressed as:

[0140]

[0141] In the formula, E m is the total annual CO2 emission; α and β are the pollutant emission coefficients corresponding to grid electricity and gas, respectively.

[0142] In summary, the robust optimization planning objective of the integrated energy system can be expressed as:

[0143]

[0144] Step 4: Based on equivalent transformation, the multi-objective optimization planning model with uncertain factors is transformed into a deterministic multi-objective optimization model;

[0145] Wherein, the step 4 is specifically as follows:

[0146] Perform robust equivalence transformation on the robust optimization model established in step 3 and convert it into a deterministic optimization model.

[0147] The energy balance constraint containing the uncertain deviation coefficient ξ in the robust optimization model is converted into an inequality form according to the necessary conditions for energy supply, and the dual cone method is used to perform robust equivalence transformation to obtain:

[0148]

[0149]

[0150]

[0151]

[0152] In the formula, ω i,t , are all dual variables. The sufficiency of the original constrained energy balance can be ensured by the optimization process of the planning objectives, or in the scheduling optimization process during the system operation phase. Therefore, the IES robust planning problem considering the uncertainty of supply and demand is transformed into a deterministic multi-objective optimization problem.

[0153] Step 5: Based on the basic data, the deterministic multi-objective optimization model is optimized and solved using a congestion-based constraint generation algorithm to obtain the IES optimal planning solution.

[0154] Wherein, the step 5 is specifically as follows:

[0155] The constraint generation algorithm based on congestion is used to solve the deterministic multi-objective optimization model obtained in step 4, and the IES optimal robust planning scheme set is obtained for decision makers to make comparative decisions based on their target preferences.

[0156] The steps of the constraint generation algorithm based on congestion are as follows:

[0157] 1) The multi-objective optimization model obtained in step 4 is transformed into two single-objective optimization sub-problems SP1 and SP2 according to the objective decomposition, where M1 and M2 are constraint parameters.

[0158]

[0159]

[0160] 2) Parameter initialization. Given the number of solutions N, let M1 = +∞, M2 = +∞;

[0161] 3) Solve SP1 to get the target value o1, set M2 = o1, solve SP2, and get the optimal solution and the target value o2, And the corresponding target value {o1,o2} is included in the Pareto solution set; let M2 = +∞, solve SP2, get the target value o2, let M1 = o2, solve SP1, get the optimal solution and the target value o1, And the corresponding target values ​​{o1,o2} are included in the Pareto solution set.

[0162] 4) Randomly select an optimization target, sort the Pareto solutions according to the target value, and calculate the crowding distance d between two adjacent solutions i , select the two solutions corresponding to the maximum crowding distance

[0163]

[0164] In the formula, is the target value of the kth target corresponding to the ith solution; and are the maximum and minimum values ​​of the kth objective value in the Pareto solution set; K is the number of objectives in the optimization problem.

[0165] 5) If the target selected in step 4) is target 1, then let Solve SP2 and get the target value o 2,n , let M1 = o 2,n , solve SP1 and get the optimal solution and target value o 1,n Otherwise, let Solve SP1 and get the target value o 1,n , let M2 = o 1,n , solve SP2 and get the optimal solution and target value o 2,n .Will And the corresponding target value {o 1,n ,o 2,n} is included in the Pareto solution set;

[0166] 6) If the number of Pareto solutions ≥ N, output the Pareto solution and the algorithm terminates; otherwise, return to step 4).

[0167] Embodiment 2:

[0168] The purpose of this embodiment is to provide a multi-objective planning system for an integrated energy system with supply and demand uncertainty.

[0169] A multi-objective planning system for an integrated energy system with supply and demand uncertainty, comprising:

[0170] A data acquisition unit, which is used to acquire basic data of the site to be built, wherein the basic data includes the upper and lower limits of the investment capacity of the integrated energy system equipment and unit cost data, and predicts the wind and solar power output data under unit capacity and the load demand data of different energy sources of users;

[0171] An alternative equipment energy flow model construction unit, which is used to construct an alternative equipment energy flow model based on pre-determined equivalent characteristic parameters of the alternative equipment operation;

[0172] A multi-objective optimization planning model construction unit is used to construct a multi-objective optimization planning model for an integrated energy system based on an alternative equipment energy flow model and uncertainty descriptions of multiple stations and multiple users on both the supply and demand sides; wherein, taking into account the uncertainty of photovoltaic and wind power output and load demand, an uncertainty set of the energy supply side and the load demand side is constructed by introducing robust parameters; and a carbon emission environmental protection measurement index is introduced into the multi-objective optimization planning model for the integrated energy system;

[0173] A model conversion unit, which is used to convert a multi-objective optimization planning model with uncertain factors into a deterministic multi-objective optimization model based on equivalent transformation;

[0174] The optimization solving unit is used to optimize and solve the deterministic multi-objective optimization model based on the basic data by adopting a constraint generation algorithm based on congestion to obtain the IES optimal planning solution.

[0175] Furthermore, the system described in this embodiment corresponds to the multi-objective optimization planning method described in Embodiment 1, and its technical details have been described in detail in Embodiment 1, so they will not be repeated here.

[0176] In further embodiments, there is also provided:

[0177] An electronic device includes a memory and a processor, and computer instructions stored in the memory and executed on the processor, wherein when the computer instructions are executed by the processor, the method described in Embodiment 1 is performed. For the sake of brevity, no further description is given here.

[0178] It should be understood that in this embodiment, the processor may be a central processing unit CPU, and the processor may also be other general-purpose processors, digital signal processors DSP, application-specific integrated circuits ASIC, off-the-shelf programmable gate arrays FPGA or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. The general-purpose processor may be a microprocessor or the processor may also be any conventional processor, etc.

[0179] The memory may include a read-only memory and a random access memory, and provide instructions and data to the processor. A portion of the memory may also include a non-volatile random access memory. For example, the memory may also store information about the device type.

[0180] A computer-readable storage medium is used to store computer instructions. When the computer instructions are executed by a processor, the method described in embodiment 1 is completed.

[0181] The method in the first embodiment can be directly embodied as a hardware processor, or a combination of hardware and software modules in the processor. The software module can be located in a mature storage medium in the field such as a random access memory, a flash memory, a read-only memory, a programmable read-only memory, or an electrically erasable programmable memory, a register, etc. The storage medium is located in the memory, and the processor reads the information in the memory and completes the steps of the above method in combination with its hardware. To avoid repetition, it will not be described in detail here.

[0182] Those skilled in the art will appreciate that the units, i.e., algorithm steps, of the various examples described in the present embodiment can be implemented in electronic hardware or in a combination of computer software and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of this disclosure.

[0183] The above-mentioned embodiment provides a multi-objective planning method and system for an integrated energy system with supply and demand uncertainty, which can be implemented and has broad application prospects.

[0184] The above description is only a preferred embodiment of the present disclosure and is not intended to limit the present disclosure. For those skilled in the art, the present disclosure may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present disclosure shall be included in the protection scope of the present disclosure.

Claims

1. A multi-objective planning method for an integrated energy system with supply and demand uncertainty, characterized in that: include: Obtain basic data of the site to be built, wherein the basic data includes the upper and lower limits of the investment capacity of the integrated energy system equipment and unit cost data, and predict the wind and solar power output data under unit capacity and the load demand data of different energy sources of users; Based on the predetermined equivalent characteristic parameters of the operation of the alternative equipment, an energy flow model of the alternative equipment is constructed; Based on the energy flow model of alternative equipment and the uncertainty description of multiple stations and multiple users on both the supply and demand sides, a multi-objective optimization planning model for the integrated energy system is constructed; wherein, considering the uncertainty of photovoltaic, wind power output and load demand, the uncertainty sets of the energy supply side and the load demand side are constructed by introducing robust parameters; and the carbon emission environmental protection measurement index is introduced into the multi-objective optimization planning model of the integrated energy system; The uncertainty set on the energy supply side is specifically expressed as follows: In the formula, μ i,t and are the actual output and predicted output of the ith photovoltaic, wind power and other uncertain energy access points in period t; Δμ i,t is the maximum deviation between the actual output and the predicted output; i,t is the deviation coefficient; Ω is the set of uncertain energy access points; Γ s ∈[0,|Ω|] is the robust parameter of uncertain energy output; Based on the equivalence transformation, a multi-objective optimization planning model with uncertain factors is transformed into a deterministic multi-objective optimization model; specifically, the energy balance constraint containing the uncertain deviation coefficient in the multi-objective optimization model is transformed into an inequality form according to the necessary conditions for energy supply, and a dual cone method is used to perform robust equivalence transformation on it; Based on the basic data, the deterministic multi-objective optimization model is optimized and solved by using a congestion-based constraint generation algorithm to obtain an IES optimal planning solution; The steps of the congestion-based constraint generation algorithm are as follows: 1) transforming the deterministic multi-objective optimization model into two single-objective optimization sub-problems SP1 and SP2 according to the objective decomposition, where M1 and M2 are constraint parameters; SP1: SP2: 2) Parameter initialization, given the number of solutions N, let M1 = +∞, M2 = +∞; 3) Solve SP1 to get the target value o1, set M2 = o1, solve SP2, and get the optimal solution and the target value o2, And the corresponding target value {o1,o2} is included in the Pareto solution set; let M2 = +∞, solve SP2, get the target value o2, let M1 = o2, solve SP1, get the optimal solution and the target value o1, And the corresponding target values ​​{o1,o2} are included in the Pareto solution set; 4) Randomly select an optimization target, sort the Pareto solutions according to the target value, and calculate the crowding distance d between two adjacent solutions i , select the two solutions corresponding to the maximum crowding distance In the formula, is the target value of the kth target corresponding to the ith solution; and are the maximum and minimum values ​​of the kth objective value in the Pareto solution set, respectively; K is the number of objectives in the optimization problem; 5) If the target selected in step 4) is target 1, then let Solve SP2 and get the target value o 2,n , let M1 = o 2,n , solve SP1 and get the optimal solution and target value o 1,n Otherwise, let Solve SP1 and get the target value o 1,n , let M2 = o 1,n , solve SP2 and get the optimal solution and target value o 2,n ;Will And the corresponding target value {o 1,n ,o 2,n } is included in the Pareto solution set; 6) If the number of Pareto solutions ≥ N, output the Pareto solution and the algorithm terminates; otherwise, return to step 4).

2. A multi-objective planning method for an integrated energy system with supply and demand uncertainty as claimed in claim 1, characterized in that: The uncertainty set on the load demand side is specifically expressed as follows: in, and are the actual load demand and predicted demand of energy k of the jth energy user in period t, respectively; is the maximum deviation between actual demand and predicted demand; is the deviation coefficient; Ψ is the set of energy users; Γ n ∈[0,|Ψ|] is the robust parameter of uncertain energy demand.

3. A multi-objective planning method for an integrated energy system with supply and demand uncertainty as claimed in claim 1, characterized in that: The multi-objective optimization planning model of the integrated energy system is specifically expressed as follows: Among them, C total is the annualized total cost of IES, E m is the total annual CO2 emissions, X is the IES planning decision variable, corresponding to the configuration capacity of each alternative equipment, and ξ is the uncertainty deviation coefficient.

4. A multi-objective planning method for an integrated energy system with supply and demand uncertainty as claimed in claim 1, characterized in that: The constraints of the multi-objective optimization planning model of the comprehensive energy system include energy flow model constraints of each device, system configuration capacity constraints and system operation constraints.

5. The multi-objective planning method for an integrated energy system with supply and demand uncertainty as claimed in claim 1, characterized in that: The energy flow model of the alternative equipment is constructed, including a gas turbine model, a waste heat boiler model, a gas boiler model, an electric boiler heating model, an electric refrigerator refrigeration model, an absorption refrigerator refrigeration model, a heat pump model, a photovoltaic power generation model, a wind power generation model, an electric energy storage device model and a cold and hot dual water storage tank model.

6. A multi-objective planning system for an integrated energy system with supply and demand uncertainty, characterized in that: include: A data acquisition unit, which is used to acquire basic data of the site to be built, wherein the basic data includes the upper and lower limits of the investment capacity of the integrated energy system equipment and unit cost data, and predicts the wind and solar power output data under unit capacity and the load demand data of different energy sources of users; An alternative equipment energy flow model construction unit, which is used to construct an alternative equipment energy flow model based on pre-determined equivalent characteristic parameters of the alternative equipment operation; A multi-objective optimization planning model construction unit is used to construct a multi-objective optimization planning model for an integrated energy system based on an alternative equipment energy flow model and uncertainty descriptions of multiple stations and multiple users on both the supply and demand sides; wherein, taking into account the uncertainty of photovoltaic and wind power output and load demand, an uncertainty set of the energy supply side and the load demand side is constructed by introducing robust parameters; and a carbon emission environmental protection measurement index is introduced into the multi-objective optimization planning model for the integrated energy system; The uncertainty set on the energy supply side is specifically expressed as follows: In the formula, μ i,t and are the actual output and predicted output of the ith photovoltaic, wind power and other uncertain energy access points in period t; Δμ i,t is the maximum deviation between the actual output and the predicted output; i,t is the deviation coefficient; Ω is the set of uncertain energy access points; Γ s ∈[0,|Ω|] is the robust parameter of uncertain energy output; A model conversion unit is used to convert a multi-objective optimization planning model with uncertain factors into a deterministic multi-objective optimization model based on equivalent transformation; specifically: converting the energy balance constraint containing uncertain deviation coefficients in the multi-objective optimization model into an inequality form according to the necessary conditions for energy supply, and performing robust equivalent transformation on it using a dual cone method; An optimization solving unit, which is used to optimize and solve the deterministic multi-objective optimization model based on the basic data by using a constraint generation algorithm based on congestion to obtain an IES optimal planning solution; The steps of the congestion-based constraint generation algorithm are as follows: 1) transforming the deterministic multi-objective optimization model into two single-objective optimization sub-problems SP1 and SP2 according to the objective decomposition, where M1 and M2 are constraint parameters; SP1: SP2: 2) Parameter initialization, given the number of solutions N, let M1 = +∞, M2 = +∞; 3) Solve SP1 to get the target value o1, set M2 = o1, solve SP2, and get the optimal solution and the target value o2, And the corresponding target value {o1,o2} is included in the Pareto solution set; let M2 = +∞, solve SP2, get the target value o2, let M1 = o2, solve SP1, get the optimal solution and the target value o1, And the corresponding target values ​​{o1,o2} are included in the Pareto solution set; 4) Randomly select an optimization target, sort the Pareto solutions according to the target value, and calculate the crowding distance d between two adjacent solutions i , select the two solutions corresponding to the maximum crowding distance In the formula, is the target value of the kth target corresponding to the ith solution; and are the maximum and minimum values ​​of the kth objective value in the Pareto solution set, respectively; K is the number of objectives in the optimization problem; 5) If the target selected in step 4) is target 1, then let Solve SP2 and get the target value o 2,n , let M1 = o 2,n , solve SP1 and get the optimal solution and target value o 1,n Otherwise, let Solve SP1 and get the target value o 1,n , let M2 = o 1,n , solve SP2 and get the optimal solution and target value o 2,n ;Will And the corresponding target value {o 1,n ,o 2,n } is included in the Pareto solution set; 6) If the number of Pareto solutions ≥ N, output the Pareto solution and the algorithm terminates; otherwise, return to step 4).

7. A computer-readable storage medium having a program stored thereon, characterized in that: When the program is executed by a processor, it implements a multi-objective planning method for an integrated energy system with supply and demand uncertainty as described in any one of claims 1 to 5.

8. An electronic device comprising a memory, a processor, and a program stored in the memory and executable on the processor, characterized in that: When the processor executes the program, it implements a multi-objective planning method for an integrated energy system with uncertain supply and demand as described in any one of claims 1-5.