A method of downtime budgeting based on discrete non-rigid production line station cycle time
Through the prediction and shutdown plan based on the work station shutdown model, the problem of predicting work station shutdown in discrete non-rigid production lines is solved, the production efficiency and utilization rate are improved, and the enterprise cost is reduced.
Patent Information
- Application Number
- CN202210647849.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-06-08
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2042-06-08
AI Technical Summary
The existing technology cannot proactively predict and budget for the shutdown of discrete non-rigid production line stations, resulting in product inventory backlog, low station efficiency, low production line efficiency, personnel overtime and increased costs.
Based on the station shutdown model, the timer is used to simulate the operation of the station, predict the timing of shutdown due to material waiting and material blocking, form a shutdown plan, calculate the startup rate of the station and production line, assist managers in adjusting shutdown arrangements, and improve production efficiency and utilization. Rate.
It achieves timely delivery, improves production efficiency and production line utilization, and reduces the overall cost of the enterprise.
Smart Images

Figure CN115062945B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of manufacturing industry, and in particular to a shutdown budgeting method based on discrete non-rigid production line workstation rhythm. Background Art
[0002] In today's era, improving the efficiency of discrete and non-rigid manufacturing stations has become the key to industrial breakthroughs. Most of the current common solutions are to passively detect station downtime, then provide feedback in an automatic or semi-automatic manner, and then form a treatment plan for implementation. There are problems such as passive processing of downtime, inability to predict station downtime and actively arrange subsequent work, which directly leads to the randomness of production task completion, and may also indirectly lead to backlogs of work-in-process inventory, low efficiency of stations or the entire production line, inability to complete production tasks, random overtime of relevant personnel, unclear overall production line operation rate, and high overall manufacturing costs.
[0003] The existing solution is the production line Anton system or equipment management system, which cannot proactively estimate the downtime of workstations on the production line in the future (generally one production shift). The efficiency and delivery status of the workstation or production line can only be calculated in a post-event report, and the arrangement of work during the workstation downtime is also passive, resulting in non-immediate additional costs. Summary of the invention
[0004] The purpose of the present invention is to solve the shortcomings of the current existing technical methods, such as backlog of work-in-process inventory, low efficiency of workstations or the entire production line, inability to complete production tasks, random overtime work of relevant personnel, unclear overall production line operating rate, and high overall manufacturing costs, and to provide a shutdown budget method based on discrete non-rigid production line workstation rhythm. The purpose of the present invention is achieved through the following technical solutions: a shutdown budget method based on discrete non-rigid production line workstation rhythm, based on the workstation shutdown model, predicts the timing of the production line workstation waiting for material or blocking material shutdown, forms a shutdown plan, calculates the workstation operating rate, production line operating rate, and plan fulfillment rate indicators, and assists management personnel to achieve timely delivery, improve production efficiency, improve production line utilization, and reduce the overall cost of the enterprise, including the following steps:
[0005] Step P1: Initialize site information;
[0006] Step P2: Start the timer;
[0007] Step P3: Process the active workstations one by one;
[0008] Step J1: Determine whether the virtual current time is greater than or equal to the off-get off work time. If so, go to P6;
[0009] Step P4: Virtually add the current time to the accumulated timer duration × K;
[0010] Step P5: Wait for the next processing of the timer and return to P3;
[0011] Step P6: stop the timer;
[0012] Step P7: Form a budget report;
[0013] Step J2: Determine whether the budget report meets the requirements, if so, end the method;
[0014] Step P8: Adjust the downtime table and workstation downtime duration parameters, and go to step P1.
[0015] Specifically, the on-site information includes: virtual current time, last acquisition time of the workstation, work-in-progress in the current path, and current shutdown table.
[0016] Specifically, the timer uses the time scaling principle to simulate changes in the work-in-process;
[0017] The virtual current time is specifically the time displayed by the timer.
[0018] Specifically, the step P3 further includes the following sub-steps:
[0019] P3_1: Get all active workstations;
[0020] P3_2: Take the unprocessed and most downstream station;
[0021] J3_1: Determine whether the operation time of the workstation exceeds the beat. If not, return to P3_2;
[0022] P3_3: record the completion table and update the last collection time;
[0023] P3_4 / 6: Find the downstream path according to the preset downstream flow strategy, and find the upstream path according to the preset upstream flow strategy;
[0024] P3_5 / 7: Update the number of downstream WIP and upstream WIP of this station;
[0025] J3_2: Determine whether the workstation has stopped;
[0026] P3_8: Add shutdown records;
[0027] J3_3: Determine whether there are any unprocessed workstations. If so, return to step P3_2; if not, end the step.
[0028] Specifically, the cycle time is the time required for the workstation to produce a workpiece.
[0029] Specifically, the sub-step P3_2 is specifically as follows: take the unprocessed and most downstream workstation, where the most downstream workstation refers to the workstation with the longest engineering depth starting from the first workstation of this production line.
[0030] Specifically, the sub-step J3_1 is specifically as follows: whether the operation time of the workstation exceeds the beat, which means that the workstation is in an active state and the operation time exceeds one beat of this workstation. If it exceeds, it means that a workpiece is completed.
[0031] Specifically, the sub-step P3_3 is specifically as follows: recording the completion table and updating the last collection time, which means that when a workstation completes a workpiece, the completion information is recorded and the last recording time is updated once.
[0032] Specifically, the sub-step P3_4 / 6 is as follows: according to the preset flow strategy, find the downstream / upstream path, with the workstation as the core, and there are multiple possible paths upstream and downstream. The workpiece passing through the workstation this time may come from any upstream path, and may also flow into any downstream path. Therefore, an inflow and outflow strategy is needed here. This strategy can be set according to the specific requirements of the factory, such as allocating each path in proportion, allocating according to the earliest or latest time, and allocating according to the job plan.
[0033] Specifically, the sub-step P3_5 / 7 is specifically: updating the number of work-in-progress in the downstream / upstream of this workstation, and based on P3_4 / 6, updating the number of work-in-progress in the upstream and downstream paths.
[0034] Specifically, the sub-step J3_2 of determining whether the workstation is stopped includes the following sub-steps:
[0035] Calculate the sum of theoretical work-in-progress quantities for each downstream path
[0036] Calculate the sum of the actual work-in-progress quantities of each downstream path
[0037] Calculate the sum of theoretical work-in-progress quantities for each upstream path
[0038] Calculate the sum of theoretical work-in-progress quantities for each downstream path
[0039] like It is considered as a work stoppage due to waiting for materials;
[0040] like It is considered as a stoppage due to material blockage;
[0041] Among them, P o1 ,P o2 ,……,P on is the theoretical number of downstream paths in production, p o1 ,p o2 ,……,p on is the actual work-in-progress quantity of each downstream path, P i1 ,P i2 ,……,Pim is the theoretical number of upstream paths in production, P in , p i1 ,p i2 ,……,p im The actual work-in-progress quantity of each upstream path.
[0042] Specifically, K is the difference ratio between the time calculated by the timer and the actual time.
[0043] Specifically, the budget report includes a production line efficiency table, a workstation efficiency table, a plan fulfillment rate, and a workstation shutdown schedule.
[0044] Specifically, the overall utilization rate of the production line and the overall start-up rate of the production line are used as the main indicators to measure the efficiency of the production line; the workstation utilization rate and the workstation start-up rate are used as the main indicators to measure the efficiency of the workstation.
[0045] Beneficial effects of the present invention:
[0046] The present invention obtains a stop plan report by estimating the timing of stopping for material waiting or material blocking at a production line workstation, calculates indicators such as the workstation and production line availability, and the plan fulfillment rate, and gradually adjusts on-site parameters or the stop plan with the participation of management personnel, arranges non-production work, and assists management personnel to achieve the goals of timely delivery, improving production efficiency, increasing production line utilization, and reducing overall enterprise costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0047] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the structures shown in these drawings without paying creative work.
[0048] Figure 1 is a flow chart of the method of the present invention;
[0049] Figure 2 It is a flow chart of step P3 of the present invention. DETAILED DESCRIPTION
[0050] It should be understood that the specific embodiments described herein are only used to explain the present invention, and are not used to limit the present invention.
[0051] In order to have a clearer understanding of the technical features, purposes and beneficial effects of the present invention, the technical solution of the present invention is now described in detail below. Obviously, the implementation cases described are part of the embodiments of the present invention, not all of the embodiments, and cannot be understood as limiting the scope of the implementation of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work belong to the protection scope of the present invention.
[0052] Embodiment 1:
[0053] like Figure 1 As shown in the figure, a shutdown budget method based on discrete non-rigid production line workstation beat is used. Based on the workstation shutdown model, the timing of the production line workstation shutdown due to waiting for materials or blocking is predicted, a shutdown plan is formed, and the workstation start-up rate, production line start-up rate, and plan fulfillment rate indicators are calculated to assist management personnel in achieving timely delivery, improving production efficiency, improving production line utilization, and reducing overall enterprise costs. The method includes the following steps:
[0054] Step P1: Initialize site information;
[0055] Step P2: Start the timer;
[0056] Step P3: Process the active workstations one by one;
[0057] Step J1: Determine whether the virtual current time is greater than or equal to the off-get off work time. If so, go to P6;
[0058] Step P4: Virtually add the current time to the accumulated timer duration × K;
[0059] Step P5: Wait for the next processing of the timer and return to P3;
[0060] Step P6: stop the timer;
[0061] Step P7: Form a budget report;
[0062] Step J2: Determine whether the budget report meets the requirements, if so, end the method;
[0063] Step P8: Adjust the downtime table and workstation downtime duration parameters, and go to step P1.
[0064] Specifically, the on-site information includes: virtual current time, last acquisition time of the workstation, work-in-progress in the current path, and current shutdown table.
[0065] Specifically, the timer uses the time scaling principle to simulate changes in the work-in-process;
[0066] The virtual current time is specifically the time displayed by the timer.
[0067] like Figure 2 As shown, the step P3 also includes the following sub-steps:
[0068] P3_1: Get all active workstations;
[0069] P3_2: Take the unprocessed and most downstream station;
[0070] J3_1: Determine whether the operation time of the workstation exceeds the beat. If not, return to P3_2;
[0071] P3_3: record the completion table and update the last collection time;
[0072] P3_4 / 6: Find the downstream path according to the preset downstream flow strategy, and find the upstream path according to the preset upstream flow strategy;
[0073] P3_5 / 7: Update the number of downstream WIP and upstream WIP of this station;
[0074] J3_2: Determine whether the workstation has stopped;
[0075] P3_8: Add shutdown records;
[0076] J3_3: Determine whether there are any unprocessed workstations. If so, return to step P3_2; if not, end the step.
[0077] Specifically, the cycle time is the time required for the workstation to produce a workpiece.
[0078] Specifically, the sub-step P3_2 is specifically as follows: take the unprocessed and most downstream workstation, where the most downstream workstation refers to the workstation with the longest engineering depth starting from the first workstation of this production line.
[0079] Specifically, the sub-step J3_1 is specifically as follows: whether the operation time of the workstation exceeds the beat, which means that the workstation is in an active state and the operation time exceeds one beat of this workstation. If it exceeds, it means that a workpiece is completed.
[0080] Specifically, the sub-step P3_3 is specifically as follows: recording the completion table and updating the last collection time, which means that when a workstation completes a workpiece, the completion information is recorded and the last recording time is updated once.
[0081] Specifically, the sub-step P3_4 / 6 is as follows: according to the preset flow strategy, find the downstream / upstream path, with the workstation as the core, and there are multiple possible paths upstream and downstream. The workpiece passing through the workstation this time may come from any upstream path, and may also flow into any downstream path. Therefore, an inflow and outflow strategy is needed here. This strategy can be set according to the specific requirements of the factory, such as allocating each path in proportion, allocating according to the earliest or latest time, and allocating according to the job plan.
[0082] Specifically, the sub-step P3_5 / 7 is specifically: updating the number of work-in-progress in the downstream / upstream of this workstation, and based on P3_4 / 6, updating the number of work-in-progress in the upstream and downstream paths.
[0083] Specifically, the sub-step J3_2 of determining whether the workstation is stopped includes the following sub-steps:
[0084] Calculate the sum of theoretical work-in-progress quantities for each downstream path
[0085] Calculate the sum of the actual work-in-progress quantities of each downstream path
[0086] Calculate the sum of theoretical work-in-progress quantities for each upstream path
[0087] Calculate the sum of theoretical work-in-progress quantities for each downstream path
[0088] like It is considered as a work stoppage due to waiting for materials;
[0089] like It is considered as a stoppage due to material blockage;
[0090] Among them, P o1 ,P o2 ,……,P on is the theoretical number of downstream paths in production, p o1 ,p o2 ,……,p on is the actual work-in-progress quantity of each downstream path, P i1 ,P i2 ,……,P im is the theoretical number of upstream paths in production, P in , p i1 ,p i2 ,……,p im The actual work-in-progress quantity of each upstream path.
[0091] Specifically, K is the difference ratio between the time calculated by the timer and the actual time.
[0092] Specifically, the budget report includes a production line efficiency table, a workstation efficiency table, a plan fulfillment rate, and a workstation shutdown schedule.
[0093] Specifically, the overall utilization rate of the production line and the overall start-up rate of the production line are used as the main indicators to measure the efficiency of the production line; the workstation utilization rate and the workstation start-up rate are used as the main indicators to measure the efficiency of the workstation.
[0094] The above shows and describes the basic principles, main features and advantages of the present invention. It should be understood by those skilled in the art that the present invention is not limited by the above embodiments, and the above embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, which fall within the scope of the present invention to be protected. The scope of the present invention to be protected is defined by the attached claims and their equivalents.
[0095] It should be noted that, for the above-mentioned various method embodiments, for the sake of simplicity of description, they are all expressed as a series of action combinations, but those skilled in the art should be aware that this application is not limited by the order of the actions described, because according to this application, some steps can be performed in other orders or simultaneously. Secondly, those skilled in the art should also be aware that the embodiments described in the specification are all preferred embodiments, and the actions and units involved are not necessarily required by this application.
[0096] In the above embodiments, the description of each embodiment has its own emphasis. For parts that are not described in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.
[0097] Those skilled in the art can understand that all or part of the processes in the above-mentioned embodiments can be implemented by instructing related hardware through a computer program, and the program can be stored in a computer-readable storage medium, and when the program is executed, it can include the processes of the embodiments of the above-mentioned methods. The storage medium can be a disk, an optical disk, a ROM, a RAM, etc.
[0098] The above disclosure is only the preferred embodiment of the present invention, which certainly cannot be used to limit the scope of the present invention. Therefore, equivalent changes made according to the claims of the present invention are still within the scope of the present invention.
Claims
1. A shutdown budget method based on discrete non-rigid production line station beat, based on the station shutdown model, predicts the timing of the production line station shutdown due to material waiting or material blocking, and forms a shutdown plan. The station shutdown model includes the following steps: Step P1: Initialize site information; Step P2: Start the timer; Step P3: Process the active workstations one by one; Step J1: Determine whether the virtual current time is greater than or equal to the off-get off work time. If so, go to P6; Step P4: Virtually set the current time to be the accumulated timer duration × K; Step P5: Wait for the next processing of the timer and return to P3; Step P6: stop the timer; Step P7: Calculate the workstation operation rate, production line operation rate, and plan fulfillment rate indicators to form a budget report; Step J2: Determine whether the budget report meets the requirements, if so, end the method; Step P8: Adjust the downtime table and the downtime duration parameters of the workstation, and go to step P1; The on-site information includes: virtual current time, last acquisition time of the workstation, work-in-progress in the current path, and current shutdown table; The timer uses the time scaling principle to simulate WIP changes; The step P3 also includes the following sub-steps: P3_1: Obtain all active workstations; P3_2: Take the unprocessed and most downstream station; J3_1: Determine whether the operation time of the workstation exceeds the beat. If not, return to P3_2; P3_3: record the completion table and update the last collection time; P3_4 / 6: Find the downstream path according to the preset downstream flow strategy, and find the upstream path according to the preset upstream flow strategy; P3_5 / 7: Update the number of downstream WIP and upstream WIP of this station; J3_2: Determine whether the workstation has stopped; P3_8: Add shutdown records; J3_3: Determine whether there are any unprocessed workstations. If yes, return to step P3_2; if no, end the step; The sub-step J3_2 determines whether the workstation has stopped, including the following sub-steps: calculating the sum of the theoretical work-in-progress quantities of each downstream path Calculate the sum of the actual work-in-progress quantities of each downstream path Calculate the sum of theoretical work-in-progress quantities for each upstream path Calculate the sum of the actual work-in-progress quantities of each upstream path like It is deemed that a work stoppage has occurred due to waiting for materials; like It is considered as a stoppage due to material blockage; Among them, Po1, Po2, ..., Pon are the theoretical in-production quantities of each downstream path, po1, po2, ..., pon are the actual in-production quantities of each downstream path, Pi1, Pi2, ..., Pim are the theoretical in-production quantities of each upstream path, pi1, pi2, ..., pim are the actual in-production quantities of each upstream path; K is the difference between the timer time and the actual time. The budget report includes a production line efficiency table, a workstation efficiency table, a plan fulfillment rate and a workstation shutdown schedule.
2. According to claim 1, a shutdown budget method based on discrete non-rigid production line station beat is characterized in that: The cycle time is specifically the time required for the workstation to produce one workpiece.
3. According to claim 1, a shutdown budget method based on discrete non-rigid production line station beat is characterized in that: The sub-step P3_2 is specifically as follows: taking the unprocessed and most downstream workstation, where the most downstream workstation refers to the workstation with the longest engineering depth starting from the first workstation of this production line.
4. According to claim 1, a shutdown budget method based on discrete non-rigid production line station beat is characterized in that: The sub-step J3_1 is specifically as follows: whether the operation time of the workstation exceeds the beat, which means that the workstation is in an active state and the operation time exceeds one beat of this workstation. If it exceeds, it means that one workpiece is completed.
5. The method for downtime budgeting based on discrete non-rigid production line station beat according to claim 1 is characterized in that: The sub-step P3_3 is specifically as follows: recording the completion table and updating the last collection time, which means that when a workstation completes a workpiece, the completion information is recorded and the last recording time is updated.
6. The shutdown budget method based on discrete non-rigid production line station beat according to claim 1 is characterized in that: The sub-step P3_4 / 6 is specifically as follows: according to the preset flow strategy, find the downstream / upstream path, with the workstation as the core, and there are multiple possible paths upstream and downstream. The workpiece passing through the workstation this time may come from any upstream path, and may also flow into any downstream path. Therefore, an inflow and outflow strategy is needed here. This strategy is set according to the specific requirements of the factory. The specific requirements of the factory include: proportional allocation of each path, allocation according to the earliest or latest time, and allocation according to the job plan.
7. The method for downtime budgeting based on discrete non-rigid production line station beat according to claim 1 is characterized in that: The sub-step P3_5 / 7 is specifically as follows: updating the number of work-in-progress in the downstream / upstream of this workstation, and based on P3_4 / 6, updating the number of work-in-progress in the upstream and downstream paths.
8. The method for downtime budgeting based on discrete non-rigid production line station beat according to claim 1 is characterized in that: The overall utilization rate of the production line and the overall start-up rate of the production line are used as the main indicators to measure the efficiency of the production line; the utilization rate of the workstation and the start-up rate of the workstation are used as the main indicators to measure the efficiency of the workstation.