A kind of building foundation pit drainage system and drainage structure thereof

By introducing sedimentary chambers, air valves, motor-driven push plates and multi-layer screen plate structures into the building foundation pit drainage system, the problem of slow drainage caused by siltation of the gravel filter layer is solved, and rapid drainage and high efficiency are achieved during heavy rainstorms Water permeability.

CN115075277BActive Publication Date: 2024-11-15GANSU XINGHE ENG CONSULTING CO LTD
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
CN202210970610.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-08-13
Publication Date
2024-11-15
Estimated Expiration
2042-08-13

AI Technical Summary

Technical Problem

In the existing building foundation pit drainage system, the gravel filter layer is prone to siltation, resulting in slow drainage, especially during heavy rainstorms.

Method used

A building foundation pit drainage system was designed. By setting up a deposition chamber, air valve, motor-driven push plate and multi-layer screen plate structure in the water collection well, intermittent ventilation of air valves and motor-driven push plates to pull back into the filter layer The gravel blocks are washed up and down, and the silt sand and gravel are increased, and the permeability of the filter layer is increased. The silt sand and sand are separated through slopes and silt collecting boxes to avoid silt.

Benefits of technology

It effectively avoids siltation of the gravel filter layer, improves drainage rate and water permeability, and ensures rapid and efficient drainage during heavy rainstorms and during large drainage needs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115075277B_ABST
    Figure CN115075277B_ABST
Patent Text Reader

Abstract

A construction pit drainage system and a drainage structure thereof, relating to the technical field of construction pit drainage, wherein the drainage structure comprises a construction pit, wherein water channels are arranged around the bottom of the construction pit, a water collection well is arranged in the water channel, the water collection well comprises a main body, guard plates are arranged at the front and rear of the main body, and the main body and the front and rear guard plates form a sedimentation chamber opening upward on the left and right sides of the water collection well, a sieve plate 1 is arranged in the sedimentation chamber, a filter layer composed of crushed stone is laid above the sieve plate 1, the present invention provides a construction pit drainage system and a drainage structure thereof, wherein an air valve is started to intermittently ventilate the air chamber, thereby causing the volume of the air chamber to change, thereby driving the water in the sedimentation chamber to pulse up and down, thereby driving the crushed stone in the filter layer to sink and float up and down, the up and down pulsation of the water in the sedimentation chamber flushes the silt and gravel clogged in the filter layer of the crushed stone, thereby causing the silt and gravel in the filter layer to be deposited in the sedimentation chamber, thereby avoiding the problem of slow drainage caused by clogging of the filter layer of the crushed stone.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of building foundation pit drainage, and more specifically, to a building foundation pit drainage system and a drainage structure thereof. Background Art

[0002] Today's construction industry is developing very rapidly, among which high-rise buildings are very common. Building construction requires digging construction pits to lay the foundation. During rainfall, the construction pits will accumulate water, affecting the construction progress. At present, it is generally done by digging canals around the foundation pits, placing collection wells in the canals, and using water pumps to drain the water in the construction pits. However, the existing collection wells have insufficient filtering measures, which can easily cause the water pumps to pump out a large amount of mud and sand, damaging their service life.

[0003] The existing Chinese patent with announcement number CN201921947452.5 discloses a water collection well, including a canal and a water collection well. The water collection well is surrounded by water-blocking walls, a crossbeam is provided in the middle of the water-blocking wall, and a boss is provided on the crossbeam for installing a water pump. A water inlet pipe is provided at the lower end of the water pump, and a hemispherical sieve plate is provided on the outer periphery of the water inlet pipe. A drain pipe is provided at the upper end of the water pump, and the drain pipe extends upward and passes through the cover plate. A gravel filter layer is also provided at the bottom of the water collection well, and sieve plates are provided at the openings of the canal and the water collection well. The sieve plate holes of the sieve plate have a large aperture and are used to filter out larger impurities. The drainage in the canal is filtered by the gravel filter layer and the multi-layer sieve plates.

[0004] With respect to the related technologies proposed above, the gravel filter layer is easily clogged by the accumulation of silt, sand and the like in the drainage after being used for a period of time, which leads to a decrease in drainage efficiency. During heavy rains, it is easy to cause untimely drainage, and the drainage rate cannot be accelerated by adjusting the collection well. Therefore, in view of this situation, it is urgent to propose a construction foundation pit drainage system and its drainage structure to overcome the shortcomings in current practical applications. Summary of the invention

[0005] The present invention aims to solve the problems that the existing construction foundation pit drainage structure has a gravel filter layer arranged in a water collection well, which is prone to siltation and leads to slow drainage, and the water collection well cannot be adjusted to speed up the drainage rate during heavy rain.

[0006] The purpose and effect of a building foundation pit drainage system and a drainage structure thereof of the present invention are achieved by the following specific technical means: a building foundation pit drainage structure, including a building foundation pit, a water channel is arranged around the bottom of the building foundation pit, a water collection well is arranged in the water channel, a water pump is arranged outside the building foundation pit, the water pump is fixedly connected to the water collection well through a pumping pipe, and the water pump is also provided with a drainage pipe for discharging water, the water collection well includes a main body, guard plates are arranged at the front and rear of the main body, and the main body and the front and rear guard plates form a sedimentation chamber with an opening upward on the left and right sides of the water collection well, a sieve plate 1 is arranged in the sedimentation chamber, a filter layer composed of crushed stone is laid above the sieve plate 1, a sieve plate 2 is fixedly connected in the main body close to the middle direction of the water collection well, the pumping pipe runs through the main body and extends between the two sieve plates 2, a driving mechanism is also arranged in the main body, push plates are fixedly connected to the left and right sides of the driving mechanism through push rods, the front and rear ends of the push plates are connected to the guard plates, and the lower end of the push plates is connected to the sieve plate 1, an air valve is fixedly connected to the upper side of the main body, a plurality of air chambers are arranged in the sedimentation chamber, and the air valve is connected to the air chamber through a ventilation pipe.

[0007] Furthermore, the driving mechanism includes a motor, which is fixedly installed in the main body. The motor is a double-headed motor, and coaxial driving wheels are fixedly connected to the output shafts on both sides of the motor. Rotatable screws are provided at the front and back of the main body, a push rod that is slidably connected to the main body, and a slider that is slidably connected to the inner wall of the main body. A driven wheel that meshes with the driving wheel is also fixedly connected to the screw, and the screw is connected through the slider. One side of the push rod is fixed to the push plate, and the other side is fixed to the slider. The front and rear push rods move in opposite directions.

[0008] Furthermore, a slope one is provided on one side of the sedimentation chamber close to the second screen plate, and the silt is deposited downward along the slope one on the other side of the sedimentation chamber away from the second screen plate.

[0009] Furthermore, two silt clearing channels are fixedly connected to the front end of the guard plate, and a vertically slidable silt collecting box is provided at the bottom of the silt clearing channel. The bottom of slope 1 of the sedimentation chamber is connected to slope 2 inclined forward and downward, and the guard plate is provided with a silt discharge port connected to the silt collecting box at the bottom end of slope 2.

[0010] Furthermore, sieve plate 1 includes a fixed sieve plate and a movable sieve plate. Fixed sieve plates are fixedly connected to the outer sides of the left and right sides of the deposition chamber, and a plurality of movable sieve plates are hingedly connected to one end of the fixed sieve plate suspended in the inner side. Rollers are provided under the movable sieve plate, and the free ends of the other sides of the plurality of movable sieve plates are hingedly connected to the connecting block. A slide rail is provided on the push plate, and the connecting block is slidably connected to the slide rail. During the movement of the push plate toward the outside, the rollers are sequentially embedded in the slide rail and slidably connected.

[0011] Furthermore, a horizontal bending portion is provided at the lower end of the push plate, and a slide rail is arranged on the surface of the push plate and the bending portion, and the lower end of the slide rail is connected to the bending portion by being arranged in an arc shape. A fixed pulley is provided at the top of the push plate, and a horizontal pulley line is provided on the main body, which is folded vertically downward through the fixed pulley and fixed to the connecting block. A plurality of limit blocks that limit sliding and resetting with the roller bracket are provided on the guard plate, and a pressing block is fixed to the lower end of the limit block. During the movement of the push plate, the front end of the bending portion touches the pressing block, and the limit block is pressed to separate from the roller bracket, and at the same time, the roller begins to be embedded and slidably connected in the slide rail.

[0012] Furthermore, the space limited by the limit block is larger than the volume of the roller bracket, and the roller bracket can move freely within the space limited by the limit block.

[0013] The present invention also provides a construction foundation pit drainage system, comprising any one of the above-mentioned construction foundation pit drainage structures. Beneficial Effects

[0014] 1. The present invention provides a construction foundation pit drainage system and a drainage structure thereof, which intermittently ventilates the air chamber by starting the air valve, thereby causing the volume of the air chamber to change, thereby driving the water in the deposition chamber to pulse up and down, thereby driving the gravel in the filter layer to sink and float up and down, and the up and down pulsation of the water in the deposition chamber flushes the silt and gravel clogged in the gravel filter layer, thereby causing the silt and gravel in it to be deposited in the deposition chamber, thereby avoiding the problem of slow drainage caused by clogging of the gravel filter layer.

[0015] 2. The present invention provides a construction foundation pit drainage system and a drainage structure thereof. When a large amount of drainage is required, the push plate is driven to retreat by a motor, thereby increasing the water flow area of ​​the screen plate, and at the same time, the air valve is started to intermittently ventilate the air chamber, thereby driving the water in the sedimentation chamber to pulse up and down, thereby driving the gravel in the filter layer to sink and float up and down, so that the gravel on the screen plate can be better spread on it when the push plate retreats inward. At the same time, the water in the sedimentation chamber rises and falls and pulsates to flush and clean the silt and gravel blocked in the gravel filter layer, thereby making the filter layer more permeable, thereby making the drainage rate of the water collection well faster.

[0016] 3. The present invention provides a construction foundation pit drainage system and a drainage structure thereof, which arranges the sieve plate as a fixed sieve plate and a movable sieve plate, so that the push plate rotates and folds the movable sieve plate to be vertical when it is pushed outward, so that the crushed stones on the vertical movable sieve plate are squeezed and overturned onto another horizontal movable sieve plate, thereby avoiding the problem that the push plate is easily stuck due to the crushed stones when it is directly contacted and pushed by the sieve plate. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a schematic diagram of the overall structure of the present invention.

[0018] Figure 2 For the present invention Figure 1 A magnified schematic diagram of center A.

[0019] Figure 3 It is a schematic diagram of the main cross-section of the water collection well of the present invention.

[0020] Figure 4 It is a top cross-sectional schematic diagram of the driving mechanism of the present invention.

[0021] Figure 5 It is a schematic diagram of the partial cross-sectional structure of the water collection well of the present invention.

[0022] Figure 6 It is a front view and cross-sectional schematic diagram of the fixed sieve plate and the movable sieve plate of the present invention.

[0023] Figure 7 It is a structural schematic diagram of the fixed sieve plate and the movable sieve plate of the present invention.

[0024] Figure 8 For the present invention Figure 7 A magnified schematic diagram of point B in the middle.

[0025] Fig. 9 It is a schematic diagram of the workflow of the present invention.

[0026] Figure 1-9 In: 1-building pit, 2-water pump, 3-water pipe, 4-drainage pipe, 5-water channel, 6-main body, 7-push plate, 701-bending part, 702-slide rail, 8-drainage channel, 9-filter layer, 10-air valve, 11-ventilation pipe, 12-driving mechanism, 121-motor, 122-driving wheel, 123-driven wheel, 124-screw, 125-sliding block, 126-push rod, 13-guard plate, 14-air chamber, 15-sieve plate one, 151-fixed sieve plate, 152-movable sieve plate, 153-roller, 154-connecting block, 16-sedimentation chamber, 17-sieve plate two, 18-slope one, 19-slope two, 20-drainage port, 21-sludge collecting box, 22-fixed pulley, 23-pulley line, 24-limiting block, 25-pressing block. DETAILED DESCRIPTION

[0027] The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.

[0028] As attached Figure 1-9As shown, a construction foundation pit drainage structure includes a construction foundation pit 1, a water channel 5 is dug around the bottom of the construction foundation pit 1, a water collection well is arranged in the water channel 5, a water pump 2 is arranged outside the construction foundation pit 1, the water pump 2 is fixedly connected to the water collection well through a pumping pipe 3, and a drainage pipe 4 for discharging water is also arranged on the water pump 2, and the drainage pipe 4 can be extended into drainage facilities such as ditches to drain the water, and the water collection well includes a main body 6, and guard plates 13 are arranged at the front and rear of the main body 6, and the main body 6 and the front and rear guard plates 13 form a sedimentation chamber 16 with an opening upward on the left and right sides of the water collection well, and the upper opening of the sedimentation chamber 16 can be flush with the bottom of the water channel 5, and a sieve plate 15 is arranged in the sedimentation chamber 16. The sieve plate 15 is a coarse sieve plate, which can be arranged near the middle of the sedimentation chamber 16. A filter layer 9 composed of crushed stones is laid above the sieve plate 15. The volume of the crushed stones is larger than the mesh on the filter layer 9, that is, the crushed stones cannot pass through the sieve plate 15 to the sedimentation chamber 16. The sedimentation chamber 16 is close to the main body 6 in the middle direction of the water collection well. The sieve plate 17 is a fine sieve plate that filters mud and sand. The pumping pipe 3 runs through the main body 6 and extends between the two sieve plates 17. A driving mechanism 12 is also arranged in the main body 6. The left and right sides of the driving mechanism 12 are fixedly connected with push plates 7 through push rods 126. The front and rear ends of the push plates 7 are connected to the guard plate 13. The push plate 7 is connected to each other, and the lower end of the push plate 7 is connected to the sieve plate 15, that is, the side of the push plate 7 is also connected to the filter layer 9. The upper side of the main body 6 is fixedly connected with a wind valve 10. A plurality of air chambers 14 are arranged in the sedimentation chamber 16. The wind valve 10 is connected to the air chamber 14 through a ventilation pipe 11. The air chamber 14 and the wind valve 10 are both existing device structures. The crushed stones in the filter layer 9 are driven to change by driving the push plate 7, thereby changing the thickness of the filter layer 9. During normal drainage, the push plate 7 is pushed outward to drive the filter layer 9 to become thicker, thereby making the filtering effect better. When a large amount of drainage is required, the filter layer 9 becomes an obstacle to rapid drainage. By driving the push plate 7 inward, the filter layer 9 is greatly improved. The push plate 7 moves back, thereby causing the filter layer 9 to become thinner, and at the same time the water flow area becomes larger. Air is intermittently introduced through the air valve 10, thereby causing the volume of the air chamber 14 to change, thereby causing the water in the sedimentation chamber 16 to rise and fall and pulsate, thereby causing the gravel in the filter layer 9 to rise and fall, so that the gravel on the sieve plate 15 can be better spread on it when the push plate 7 moves back inward. At the same time, the ups and downs and pulsations of the water in the sedimentation chamber 16 can flush the silt and gravel clogged in the gravel filter layer 9, thereby causing the silt and gravel in it to be deposited in the sedimentation chamber 16, thereby avoiding the problem of slow drainage caused by clogging of the gravel filter layer 9.

[0029] Among them, as attached Figure 3-4As shown, as a specific structure and implementation of the driving mechanism 12, the driving mechanism 12 includes a motor 121, the motor 121 is fixedly installed in the main body 6, the motor 121 is a double-headed motor, and the output shafts on both sides of the motor 121 are fixedly connected with coaxial driving wheels 122, and the main body 6 is provided with rotatable screws 124 at the front and rear, that is, the two screws 124 are rotatably connected in the main body 6, and the main body also runs through the front and rear of the main body. Connected with two push rods 126 and two sliders 125 slidably connected to the front and rear inner walls of the main body 6, the screw 124 is also fixedly connected to the There is a driven wheel 123 meshing with the driving wheel 122, and the screw 124 penetrates and meshes with the slider 125, that is, when the screw 124 rotates, the slider 125 is driven to slide on the main body 6. One side of the push rod 126 is fixed to the push plate 7, and the other side is fixed to the slider 125. The driving wheel 122 is driven to rotate by the rotation of the motor 121, which in turn drives the driven wheel 123 to rotate, and then drives the slider 125 to slide on the main body 6, and then drives the push rod 126 to move, and then drives the two push plates 7 to move. The front and rear push rods 126 move in opposite directions.

[0030] Among them, as attached Figure 5 As shown, a slope 18 is provided on one side of the sedimentation chamber 16 close to the sieve plate 17. The slope 18 is inclined downward in the outward direction. The silt accumulates downward along the slope 18 on the other side of the sedimentation chamber 16 away from the sieve plate 17. By setting the slope 18, the silt is moved away from the sieve plate 17 along its inclined surface, thereby reducing the filtering burden of the sieve plate 17.

[0031] Among them, as attached Figure 2 With attached Figure 5 As shown, two silt clearing channels 8 are fixedly connected to the front end of the guard plate 13, and a vertically slidable silt collecting box 21 is provided at the bottom of the silt clearing channel 8. The silt collecting box 21 is vertically slidably connected in the silt clearing channel 8 and can be separated from the silt clearing channel 8 for easy removal. The bottom of the slope 18 of the sedimentation chamber 16 is connected to a slope 2 19 inclined forward and downward, and the guard plate 13 is provided with a silt discharge port 20 connected to the silt collecting box 21 at the bottom end of the slope 2 19. The silt is deposited on the slope 2 19 through the action of the slope 18, and then passes through the silt discharge port 20 through the slope 2 19 and enters the silt collecting box 21. Part of the silt can be easily removed through the silt collecting box 21 to prevent silt accumulation in the sedimentation box 16.

[0032] Among them, as attached Figure 6-8As shown, as a further improved structure and implementation method of the sieve plate 15, the sieve plate 15 includes a fixed sieve plate 151 and a movable sieve plate 152. The fixed sieve plates 151 are fixedly connected to the outer sides of the left and right sides of the sedimentation chamber 16. The fixed sieve plates 151 are connected to the inner wall of the main body 6 on the outer side and the other side is suspended. A plurality of movable sieve plates 152 are hinged to one end of the fixed sieve plate 151 on the inner side. The movable sieve plates 152 are hinged to each other in pairs, and the movable sieve plates 152 are still connected to the other movable sieve plates 152 when rotating. 2 is connected to each other to prevent the broken stones from passing through. A roller 153 is provided under the movable screen plate 152, and the free ends of the other sides of the movable screen plates 152 are hinged on the connecting block 154. The front and rear ends of the fixed screen plate 151 and the movable screen plate 152 are connected to the inner walls of the front and rear guard plates 13. A slide rail 702 is provided on the push plate 7. The connecting block 154 is slidably connected to the slide rail 702, and the connecting block 154 can be connected to the surface of the push plate 7. When the push plate 7 moves outward, the rollers 153 are sequentially embedded and slidably connected in the slide rail 702.

[0033] Among them, as attached Figure 6-8 As shown, the specific structure and implementation method of the roller 153 embedded in the slide rail 702 is that a horizontal bending portion 701 is provided at the lower end of the push plate 7, the slide rail 702 is arranged on the surface of the push plate 7 and the bending portion 701, and the lower end of the slide rail 702 is connected to the bending portion 701 by being arranged in an arc shape, a fixed pulley 22 is fixedly connected to the top of the push plate 7, a horizontal pulley line 23 is provided on the main body 6, and is folded vertically downward through the fixed pulley 22 and fixed to the connecting block 154, wherein the pulley line 23 can be fixed to the main body 6 by a spring to obtain a certain preload force, and a plurality of limit blocks 24 are provided on the guard plate 13 for limiting sliding and resetting with the roller 153 bracket. The limit block 24 can be embedded and slidably connected in the guard plate 13, and the resetting function can be realized by a resetting spring, and a pressing block 25 is fixedly connected to the lower end of the limit block 24. During the movement of the push plate 7, the front end of the bending portion 701 touches the pressing block 25, and the bending portion 701 is connected to the guard plate 1 3, and then the pressing block 25 is pressed into the guard plate 13, the limiting block 24 is pressed to separate from the roller 153 bracket, and at the same time, the roller 153 begins to be embedded in the sliding connection in the slide rail 702, and moves through the push plate 7, thereby driving the pulley line 23 to pull the connecting block 154 upward, thereby pulling the movable screen plate 152 upward, and at the same time, the front end of the bending portion 701 presses the pressing block 25 down, thereby making the limiting block 24 separate from the roller 153 bracket, and then one end of the movable screen plate 152 is released to become a free end, and the other side is hinged on the other movable screen plate 152, and rotates with it as the axis, and the roller 153 slides along the slide rail 702, thereby changing the movable screen plate 152 from horizontal to vertical, thereby turning the crushed stone filter layer 9 on the movable screen plate 152 over onto the other movable screen plate 152, thereby avoiding the situation that the push plate 7 is directly contacted and pushed by the screen plate 15, and the crushed stone makes the push plate 7 easy to get stuck.

[0034] Among them, as attached Figure 8 As shown, the space limited by the limit block 24 is larger than the volume of the roller 153 bracket, and the roller 153 bracket can move freely in the space limited by the limit block 24, that is, when the movable screen plates 152 are all turned into a horizontal state, the fulcrum of the movable screen plates 152 can shake in a small range, and then the movable screen plates 152 shake under the action of the ups and downs of the water pulse to better flatten the gravel filter layer 9.

[0035] The present invention also provides a construction foundation pit drainage system, comprising any one of the above-mentioned construction foundation pit drainage structures.

[0036] During normal drainage, the push plate 7 is pushed outward, thereby driving the pulley line 23 to pull the connecting block 154 upward, thereby pulling the movable screen plate 152 upward, and at the same time, the front end of the bending portion 701 presses the pressing block 25 down, thereby causing the limit block 24 to be separated from the roller 153 bracket, and then one end of the movable screen plate 152 is released to become a free end, and the other side is hinged on another movable screen plate 152, which rotates with it as the axis, and the roller 153 slides along the slide rail 702, thereby moving the movable screen plate 15 2 changes from horizontal to vertical, thereby turning the crushed stone filter layer 9 on the movable screen plate 152 over onto another movable screen plate 152, pushing the push plate 7 outward to reduce the water flow area of ​​the screen plate 15, and at the same time increase the thickness of the crushed stone filter layer 9, the water flows into the water collection well through the water channel 5, and enters the sedimentation chamber 16 through the filter layer 9 and the screen plate 15, and then the sand and gravel are filtered through the fine filtration of the screen plate 2 17, and the water pump 2 is started to pump the water between the two screen plates 17 in the main body 6 through the pumping pipe 3. , thereby completing the drainage operation. When a large amount of water is required, the push plate 7 is driven to retreat by the motor 121, thereby increasing the water flow area of ​​the sieve plate 15, and at the same time starting the air valve 10 to intermittently ventilate the air chamber 14, thereby causing the volume of the air chamber 14 to change, thereby driving the water in the sedimentation chamber 16 to pulse up and down, thereby driving the gravel in the filter layer 9 to sink and float up and down, so that the gravel on the sieve plate 15 is better spread on it when the push plate 7 retreats inward, and at the same time The up and down pulsation of water in the accumulation chamber 16 flushes the silt and gravel blocked in the gravel filter layer 9, so that the silt and gravel therein are deposited in the sedimentation chamber 16, thereby avoiding the problem of slow drainage caused by clogging of the gravel filter layer 9. The silt in the sedimentation chamber 16 is deposited on the slope 2 19 through the slope 18, and then passes through the silt discharge port 20 through the slope 2 19 into the silt collecting box 21. Part of the silt can be easily removed through the silt collecting box 21 to prevent silt accumulation in the sedimentation box 16.

Claims

1. A construction foundation pit drainage structure, comprising a construction foundation pit (1), wherein a water channel (5) is arranged around the bottom of the construction foundation pit (1), a water collection well is arranged in the water channel (5), a water pump (2) is arranged outside the construction foundation pit (1), the water pump (2) is fixedly connected to the water collection well through a pumping pipe (3), and a drainage pipe (4) for discharging water is also arranged on the water pump (2), characterized in that: The water collection well comprises a main body (6), the main body (6) is provided with guard plates (13) at the front and rear, and the main body (6) and the front and rear guard plates (13) form a sedimentation chamber (16) opening upward on both sides of the water collection well, a sieve plate (15) is provided in the sedimentation chamber (16), a filter layer (9) composed of crushed stone is laid above the sieve plate (15), a sieve plate (2) (17) is fixedly connected to the main body (6) in the middle direction of the water collection well, and the water pumping pipe (3) penetrates the main body (6) and extends to both sides. A driving mechanism (12) is further provided in the main body (6) between the second sieve plate (17). Push plates (7) are fixedly connected to the left and right sides of the driving mechanism (12) via push rods (126). The front and rear ends of the push plates (7) are connected to the guard plate (13), and the lower end of the push plates (7) is connected to the first sieve plate (15). An air valve (10) is fixedly connected to the upper side of the main body (6). A plurality of air chambers (14) are provided in the deposition chamber (16). The air valve (10) is connected to the air chamber (14) via a ventilation pipe (11).

2. A construction foundation pit drainage structure according to claim 1, characterized in that: The driving mechanism (12) comprises a motor (121), the motor (121) being fixedly mounted in the main body (6), the motor (121) being a double-headed motor, and coaxial driving wheels (122) being fixedly connected to the output shafts on both sides of the motor (121), the main body (6) being provided with rotatable screw rods (124) at the front and rear, a push rod (126) penetrating and slidably connected to the main body (6), and a slider (125) slidably connected to the inner wall of the main body (6), the screw rod (124) being further fixedly connected to a driven wheel (123) meshing with the driving wheel (122), and the screw rod (124) being connected through the slider (125), one side of the push rod (126) being fixedly connected to the push plate (7), and the other side being fixedly connected to the slider (125), and the front and rear push rods (126) moving in opposite directions.

3. A construction foundation pit drainage structure according to claim 1, characterized in that: The sedimentation chamber (16) is provided with a slope one (18) on one side close to the second sieve plate (17), and the silt is deposited downward along the slope one (18) on the other side of the sedimentation chamber (16) away from the second sieve plate (17).

4. A construction foundation pit drainage structure according to claim 3, characterized in that: The front end of the guard plate (13) is fixedly connected to two silt removal channels (8), the bottom of the silt removal channels (8) is provided with a vertically slidable silt collection box (21), the bottom of the slope 1 (18) of the sedimentation chamber (16) is connected to a slope 2 (19) inclined forward and downward, and the guard plate (13) is provided with a silt discharge port (20) connected to the silt collection box (21) at the bottom end of the slope 2 (19).

5. A construction foundation pit drainage structure according to claim 1, characterized in that: The sieve plate 1 (15) comprises a fixed sieve plate (151) and a movable sieve plate (152); the fixed sieve plates (151) are fixedly connected to the outer sides of the left and right sides of the deposition chamber (16); a plurality of movable sieve plates (152) are hingedly connected to one end of the fixed sieve plate (151) suspended in the inner side; a roller (153) is provided below the movable sieve plate (152); and the free ends of the other sides of the plurality of movable sieve plates (152) are hingedly connected to a connecting block (154); a slide rail (702) is provided on the push plate (7); the connecting block (154) is slidably connected to the slide rail (702); and when the push plate (7) moves toward the outer side, the rollers (153) are sequentially embedded and slidably connected in the slide rail (702).

6. A construction foundation pit drainage structure according to claim 5, characterized in that: The push plate (7) has a horizontal bending portion (701) at its lower end, the slide rail (702) is arranged on the push plate (7) and the surface of the bending portion (701), and the lower end of the slide rail (702) is connected to the bending portion (701) by being arranged in an arc shape, a fixed pulley (22) is arranged at the top of the push plate (7), and a horizontal pulley line (23) is provided on the main body (6) and is folded vertically downward through the fixed pulley (22) to be fixedly connected to the connecting block (154). The guard plate (13) is provided with a plurality of limit blocks (24) that are limited in position, slide and reset with the roller (153) bracket, and a pressing block (25) is fixedly connected to the lower end of the limit block (24). During the movement of the push plate (7), the front end of the bent portion (701) contacts the pressing block (25), and the limit block (24) is pressed to separate from the roller (153) bracket, and at the same time, the roller (153) begins to be embedded and slidably connected in the slide rail (702).

7. A construction foundation pit drainage structure according to claim 6, characterized in that: The space limited by the limit block (24) is larger than the volume of the roller (153) bracket, and the roller (153) bracket can move freely within the space limited by the limit block (24).

Citation Information

Patent Citations

  • Recyclable building foundation pit drainage structure

    CN212001201U

  • High-efficiency washing method and device for filter adopting expansive filler

    CN101985375A

  • Foundation pit supporting structure and construction method thereof

    CN108005085A

  • Pavement drainage device for municipal road

    CN108149542A

  • Suspension rapid filtration device

    CN113893608A