A high-efficiency continuous iron removal system and its use method
Through the zinc leaching, oxidation and alkaline leaching system in the efficient continuous iron removal system, combined with the vortex mechanism and the diverter, the problem of solution properties regulation in the prior art during iron removal is solved, and efficient separation of iron slag and resources are achieved. High value recycling improves iron removal efficiency and product quality.
Patent Information
- Application Number
- CN202211002132.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-08-21
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2042-08-21
AI Technical Summary
The existing iron removal technology is difficult to achieve real-time regulation of solution properties in large-scale production, resulting in the difficulty of stably controlling the crystal form of goiterite iron slag, low iron grade, and difficult to achieve high-value recycling and utilization of iron resources.
Adopt efficient continuous iron removal system, including zinc leaching system, oxidation system and alkaline leaching system, oxidation precipitation by passing zinc-containing smoke and oxygen-rich air, and use vortex mechanism and diverter to achieve uniformity of oxidation and gas supply, and quickly generate α-FeOOH precipitation.
The resource utilization of the iron removal process is achieved, the cost is reduced, the iron removal efficiency and product quality is improved, the subsequent filtration process is simplified, and the efficient separation of iron slag and the high-value recovery of resources is ensured.
Smart Images

Figure CN115287450B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of iron removal, and in particular to a high-efficiency continuous iron removal system and a use method thereof. Background Art
[0002] Nonferrous metal ores are usually associated with iron compounds. Hydrometallurgical iron smelting easily causes nonferrous metals to enter the solution together. In order to obtain high-quality metal products, the iron in the solution must first be removed.
[0003] The basic principle of purifying and removing iron from aqueous solution is to precipitate and separate iron ions. The main methods commonly used at present are: ① Iron hydroxide precipitation method, even if the iron in the solution is precipitated as Fe(OH)3 colloid, this method mainly has the problem of difficult solid-liquid separation, especially when the solution contains a high iron content, Fe(OH)3 colloid is easy to block the plate and frame filter press, making the production process difficult to carry out; ② Hematite precipitation method, so that the iron in the solution enters the slag in the form of hematite, invented by Japan's Tonghe Mining Company from 1968 to 1970, and put into production in Japan's Iijima Zinc Smelting Plant in 1972, using the "re-leaching-hematite method" to precipitate iron. At present, Yunnan Yunxi Wenshan Zinc Indium Smelting Co., Ltd. is also building a wet zinc smelting production line based on the hematite precipitation technology route. This method requires expensive titanium materials to manufacture high-pressure equipment and an attached SO2 liquefaction plant, with high investment costs and a separate iron reduction stage; ③ Goethite precipitation method, so that the iron in the solution enters the slag in the form of goethite. It was developed by Vieille Montagne of Belgium from 1965 to 1969 and put into production at the Balen plant in 1971. The goethite method has the advantages of simple process equipment, low iron removal cost, and good filtration performance due to the crystalline iron precipitate. However, a large number of industrial practices have found that the goethite method has prominent problems such as the difficulty in controlling the crystal form of the iron precipitate slag, the low iron content of the iron precipitate slag, and the difficulty in high-value recycling; ④ The potassium ferroaluminate method is based on the presence of ammonium or alkali metal ions. The iron in the solution is generated as potassium ferroaluminate and enters the slag for removal, but it also brings into the solution such as K + 、Na + or NH 4+ And other impurity ions.
[0004] In general, the above-mentioned solution iron precipitation methods have their own advantages and disadvantages, and have partially solved the problems of iron separation and solution purification in the hydrometallurgical process. However, there are some technical difficulties in practical application and the utilization of iron resources still needs to be further studied and solved. In particular, the goethite method for iron removal, the research that has been carried out has shown that the goethite method for iron precipitation includes a series of complex physical and chemical reaction processes, including the oxidation of divalent iron ions, the hydrolysis of trivalent iron ions, and neutralization reactions. These chemical reaction processes are affected by factors such as temperature, crystal seeds, stirring speed, degree of catalysis, component concentration, and pH value. The reduction, oxidation, and crystallization of iron in solution involve a series of chemical and physical reactions that are coupled between gas, liquid, and solid, and the reaction mechanism is very complex. Experts and scholars at home and abroad have conducted a lot of research on this, and have achieved a series of research results in the optimization of goethite iron precipitation reaction conditions and the improvement of iron precipitation equipment. The main process conditions for goethite iron precipitation summarized in the current literature are usually pH 3.5, temperature 85°C, Fe in solution 3+ The concentration is less than 1g / L, etc., and the allowable floating range is very narrow, and the parameter control requirements are extremely strict. However, in large-scale production, since the iron precipitation process of goethite is usually composed of multiple continuous iron precipitation reactors in series, there is a large time lag between the inlet and outlet of the reaction solution, and the iron precipitation reactor is large in size, the Fe content at different positions in the solution during the iron precipitation process is very large. 2+ / Fe 3+ Concentration, pH value and temperature are nonlinear and time-varying. According to the existing experience-based control method, it is difficult to achieve real-time control of solution properties. It is very difficult to stably achieve the above-mentioned process parameters for the formation of goethite precipitation, which makes it difficult to stably control the crystal form of goethite precipitated iron slag, resulting in low iron grade of the produced iron slag, making it difficult to realize the resource utilization of iron slag and full-scale high-value recycling. Summary of the invention
[0005] The purpose of the present invention is to solve the shortcomings of the background technology and to propose a high-efficiency continuous iron removal system and a method of using the same.
[0006] To achieve the above purpose, the technical solution adopted by the present invention is: an efficient iron removal system, including a zinc leaching system, an oxidation system and an alkaline leaching system through which the solution passes in sequence,
[0007] in:
[0008] The zinc leaching system leaches the solution by introducing zinc-containing fumes;
[0009] Oxidation is carried out by injecting oxygen-rich air and hydrogen peroxide into the oxidation system.
[0010] Preferably, the zinc leaching system includes a first tank body, a first feed pipe and a first exhaust pipe arranged on the upper surface of the first tank body, a first discharge pipe arranged at the lower end of the first tank body, and a first ventilation pipe arranged on the outer surface of the first tank body near the lower end, and the first discharge pipe delivers the liquid to the oxidation system.
[0011] Preferably, the alkaline leaching system includes a second tank body, a second feed pipe and a second exhaust pipe arranged on the upper surface of the second tank body, a second discharge pipe arranged at the lower end of the second tank body, a second ventilation pipe arranged on the outer surface of the second tank body near the lower end, and an addition pipe arranged on the outer surface of the second tank body near the upper end.
[0012] Preferably, the oxidation system comprises a reactor, a guide tube mechanism fixedly arranged inside the reactor and coaxially arranged, an eddy current mechanism penetrating the inside of the guide tube mechanism, and a flow divider arranged at the lower end of the eddy current mechanism;
[0013] The guide tube mechanism enables the air inside and outside the reactor to communicate with each other, and the vortex mechanism generates a swirling flow from top to bottom on the inner side of the guide tube mechanism.
[0014] Preferably, the reactor comprises a reactor body, a cover body fixedly mounted on the upper end of the reactor body, a liquid inlet pipe arranged on the upper surface of the cover body, a feed pipe and a feed pipe arranged on the side surface of the reactor body, and a maintenance window installed on the outer surface of the reactor body.
[0015] Preferably, the guide cylinder mechanism includes a cylinder fixedly passing through the upper surface of the cover body, a widened cylinder fixedly connected to the lower end of the cylinder, and two air intake bends are fixedly connected to the side surface of the cylinder. The air intake bends extend upward and pass through the upper surface of the cover body.
[0016] Preferably, the vortex mechanism includes a rotating shaft rotatably installed on the inner side of the cylinder through a connecting bearing, an impeller fixedly connected to the lower end of the rotating shaft, a transmission wheel fixedly connected to the upper end of the rotating shaft, and a motor fixedly installed on the upper edge of the reactor, and a transmission belt is commonly provided at the output shaft of the motor and the transmission wheel.
[0017] Preferably, the diverter includes a disk shell arranged below the cylinder body, and a plurality of diverter tubes fixedly embedded in the lower surface of the disk shell, the lower end of the diverter tube is provided with a bottom opening, the outer surface of the diverter tube is provided with a side opening, the side of the disk shell is provided with a plurality of side openings, the upper surface of the disk shell is provided with a hollow opening, the inner edge of the hollow opening is fixedly connected with a plurality of connecting frames, and the end of the connecting frame is fixedly connected to the edge of the impeller.
[0018] A method for using the high-efficiency iron removal system is also proposed, which is carried out using the above system and includes the following steps:
[0019] S1. Pass the original solution into the inner side of the zinc leaching system to leach copper through zinc-containing flue gas;
[0020] S2, passing the treated liquid in S1 into the inner side of the oxidation system, flushing in oxygen-rich air and hydrogen peroxide for oxidation, and oxidizing the ferrous ions;
[0021] S3: Send the treated liquid in S2 to the alkaline leaching system, add alkaline and zinc-containing flue gas for oxidation precipitation to complete the iron removal.
[0022] Compared with the prior art, the present invention has the following beneficial effects:
[0023] 1. This scheme uses industrial tail gas twice to assist in the iron removal process, which is beneficial to environmental protection, reasonable and full use of resources, and adopts an efficient oxidation method to accelerate the oxidation and precipitation of iron, thereby improving industrial processing efficiency.
[0024] 2. In the process of iron removal, industrial tail gas is used to assist iron removal, so as to fully utilize resources and benefit environmental protection. In the final alkaline leaching system, alkaline materials are added and zinc-containing smoke is introduced to achieve oxidation and precipitation. In the later stage, only the generated iron slag and solution need to be separated by filtering equipment, which fully utilizes resources and removes iron thoroughly, conveniently and at low cost.
[0025] 3. The motor drives the transmission wheel to rotate through the transmission belt, and then the rotating shaft rotates, driving the impeller below to form a negative pressure area, sucking the liquid and air downward. At this time, the two air intake elbows inhale a large amount of air or oxygen, and the gas and liquid flow rushes into the inner side of the disk shell, and continues to flow into the diversion pipe, and is discharged through the bottom and side ports. At the same time, the gas and liquid inside the disk shell are also ejected from the side ports to achieve the diversion effect. Compared with the traditional pipeline oxidation method, the air intake range of this mechanism is wider, making the oxidation gas supply more uniform, allowing a large amount of oxygen to enter the mixed solution, and the Fe in the mixed solution 2+ Rapid oxidation to generate α-FeOOH precipitation, it only takes 1-2 hours to remove Fe in the mixed solution 2+ Oxidation precipitation makes the whole oxidation process more uniform and complete. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 This is a schematic diagram of a high-efficiency continuous iron removal system of the present invention;
[0027] Figure 2 This is a structural diagram of an oxidation system in a high-efficiency continuous iron removal system of the present invention;
[0028] Figure 3 It is a cross-sectional view of an oxidation system in a high-efficiency continuous iron removal system of the present invention;
[0029] Figure 4 Another cross-sectional view of an oxidation system in a high-efficiency continuous iron removal system of the present invention;
[0030] Figure 5 The invention relates to a high-efficiency continuous iron removal system. Figure 4 Enlarged view of point A in the middle;
[0031] Figure 6 It is a schematic diagram of a guide cylinder mechanism in a high-efficiency continuous iron removal system of the present invention;
[0032] Figure 7 It is a cross-sectional view of the disk shell of an oxidation system in a high-efficiency continuous iron removal system of the present invention;
[0033] Figure 8 It is a schematic diagram of the disk shell of an oxidation system in a high-efficiency continuous iron removal system of the present invention;
[0034] Fig. 9 This is a schematic diagram from another perspective of the oxidation system disk shell in a high-efficiency continuous iron removal system of the present invention.
[0035] 1. Zinc leaching system; 11. First tank body; 12. First feed pipe; 13. First ventilation pipe; 14. First exhaust pipe; 15. First discharge pipe; 2. Oxidation system; 21. Reactor; 211. Reactor body; 212. Cover body; 213. Liquid inlet pipe; 214. Feeding pipe; 215. Feeding pipe; 216. Maintenance window; 22. Guide cylinder mechanism; 221. Cylinder body; 222. Widening cylinder;
[0036] 223, intake elbow; 23, vortex mechanism; 231, rotating shaft; 232, connecting bearing;
[0037] 233. Drive wheel; 234. Drive belt; 235. Motor; 236. Impeller; 24. Diverter; 241. Disc shell; 242. Hollow opening; 243. Connecting frame; 244. Diverter pipe; 245. Bottom opening; 246. Side opening; 247. Edge opening; 3. Alkaline leaching system; 31. Second tank body; 32. Second feed pipe; 33. Second ventilation pipe; 34. Second exhaust pipe; 35. Addition pipe; 36. Second discharge pipe. DETAILED DESCRIPTION
[0038] The following description is used to disclose the present invention so that those skilled in the art can implement the present invention. The preferred embodiments described below are only examples, and those skilled in the art may think of other obvious variations.
[0039] like Figure 1-Figure 9 The high-efficiency iron removal system shown in the figure comprises a zinc leaching system 1, an oxidation system 2 and an alkaline leaching system 3 through which the solution passes in sequence, wherein:
[0040] The zinc leaching system 1 leaches the solution by introducing zinc-containing smoke;
[0041] Oxidation is carried out in the oxidation system 2 by injecting oxygen-enriched air and hydrogen peroxide.
[0042] The zinc leaching system 1 includes a first tank body 11, a first feed pipe 12 and a first exhaust pipe 14 arranged on the upper surface of the first tank body 11, a first discharge pipe 15 arranged at the lower end of the first tank body 11, and a first ventilation pipe 13 arranged on the outer surface of the first tank body 11 near the lower end. The first discharge pipe 15 sends the liquid to the oxidation system 2, the first ventilation pipe 13 is used to allow the flue gas to enter and discharge it through the first exhaust pipe 14, the first feed pipe 12 is used to allow the original liquid to enter, and the first discharge pipe 15 discharges the treated liquid.
[0043] The alkaline leaching system 3 includes a second tank body 31, a second feed pipe 32 and a second exhaust pipe 34 arranged on the upper surface of the second tank body 31, a second discharge pipe 36 arranged at the lower end of the second tank body 31, a second ventilation pipe 33 arranged on the outer surface of the second tank body 31 near the lower end, and an addition pipe 35 arranged on the outer surface of the second tank body 31 near the upper end. The second feed pipe 32 is used to introduce a mixed liquid, the second ventilation pipe 33 is used to pass flue gas, the addition pipe 35 is used to add an alkaline solution, the second exhaust pipe 34 is used to discharge gas, and the second discharge pipe 36 is used to discharge the treated liquid and iron precipitate.
[0044] The oxidation system 2 includes a reactor 21, a guide tube mechanism 22 fixedly arranged on the inner side of the reactor 21 and coaxially, a vortex mechanism 23 is arranged through the inner side of the guide tube mechanism 22, and a diverter 24 is arranged at the lower end of the vortex mechanism 23; the guide tube mechanism 22 allows the air inside and outside the reactor 21 to communicate, and the vortex mechanism 23 generates a swirling flow from top to bottom on the inner side of the guide tube mechanism 22.
[0045] The reaction kettle 21 includes a kettle body 211, a cover body 212 fixedly installed on the upper end of the kettle body 211, a liquid inlet pipe 213 arranged on the upper surface of the cover body 212, and a lower pipe 214 and a upper pipe 215 arranged on the side surface of the kettle body 211. The upper pipe 215 can be used to introduce hydrogen peroxide during the oxidation process to promote the oxidation process, and the lower pipe 214 can be used to discharge materials. A maintenance window 216 is installed on the outer surface of the kettle body 211 to facilitate the user to clean and maintain the inside after opening it later.
[0046] The guide cylinder mechanism 22 includes a cylinder 221 fixedly passing through the upper surface of the cover body 212, and a widened cylinder 222 fixedly connected to the lower end of the cylinder 221. Two air intake elbows 223 are fixedly connected to the side surface of the cylinder 221. The air intake elbows 223 extend upward and pass through the upper surface of the cover body 212 to inhale gas, and can also be connected to an oxygen supply pipeline.
[0047] The vortex mechanism 23 includes a rotating shaft 231 rotatably mounted on the inner side of the cylinder 221 through a connecting bearing 232, an impeller 236 fixedly connected to the lower end of the rotating shaft 231, a transmission wheel 233 fixedly connected to the upper end of the rotating shaft 231, and a motor 235 fixedly mounted on the upper edge of the reactor 21. A transmission belt 234 is provided on the output shaft of the motor 235 and the transmission wheel 233 to provide power for the rotation of the rotating shaft 231.
[0048] The diverter 24 includes a disk shell 241 arranged below the cylinder 221, and a plurality of diverter tubes 244 fixedly embedded in the lower surface of the disk shell 241. The lower end of the diverter tube 244 is provided with a bottom opening 245, the outer surface of the diverter tube 244 is provided with a side opening 246, the side of the disk shell 241 is provided with a plurality of side openings 247, the upper surface of the disk shell 241 is provided with a hollow opening 242, the inner edge of the hollow opening 242 is fixedly connected with a plurality of connecting frames 243, the end of the connecting frame 243 is fixedly connected to the edge of the impeller 236, which can play a role of diversion and promote the full mixing of liquid and gas.
[0049] In the process of iron removal, industrial tail gas is used for auxiliary iron removal, so as to achieve the effect of full utilization of resources and be beneficial to environmental protection. In the final alkaline leaching system 3, alkaline material is added and zinc-containing smoke is introduced at the same time to achieve the purpose of oxidation and precipitation. In the later stage, only the generated iron slag and solution need to be separated by filtering equipment, so as to make full use of resources and remove iron thoroughly, conveniently and at low cost. The motor 235 drives the transmission wheel 233 to rotate through the transmission belt 234, thereby rotating the rotating shaft 231, driving the impeller 236 below to form a negative pressure area, and sucking the liquid and air downward. At this time, the two air intake elbows 223 inhale a large amount of air or oxygen, and the gas-liquid flow rushes into the inner side of the disk shell 241, and continues to flow into the diversion pipe 244, and is discharged through the bottom port 245 and the side port 246. At the same time, the gas and liquid inside the disk shell 241 are also ejected from the side port 247 to achieve the diversion effect. Compared with the traditional pipeline oxidation method, the air intake range of this mechanism is wider, making the oxidation gas supply more uniform, so that a large amount of oxygen enters the mixed solution, and the Fe in the mixed solution 2+ Rapid oxidation to generate α-FeOOH precipitation, it only takes 1-2 hours to remove Fe in the mixed solution 2+ Oxidation precipitation makes the whole oxidation process more uniform and complete.
[0050] A method for using a high-efficiency iron removal system, using the above system, comprises the following steps:
[0051] S1, passing the original solution into the inner side of the zinc leaching system 1, and leaching copper through the zinc-containing flue gas;
[0052] S2, passing the treated liquid in S1 into the inner side of the oxidation system 2, flushing in oxygen-enriched air and hydrogen peroxide for oxidation, oxidizing the ferrous ions;
[0053] S3, sending the treated liquid in S2 to the alkaline leaching system 3, adding alkaline and zinc-containing materials for oxidation precipitation to complete iron removal.
[0054] This solution utilizes industrial tail gas twice to assist in the iron removal process, which is beneficial to environmental protection, reasonable and full use of resources, and adopts an efficient oxidation method to accelerate the oxidation and precipitation of iron, thereby improving industrial processing efficiency.
[0055] The above shows and describes the basic principles, main features and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited to the above embodiments. The above embodiments and descriptions only describe the principles of the present invention. The present invention may be subject to various changes and improvements without departing from the spirit and scope of the present invention. These changes and improvements fall within the scope of the present invention. The scope of protection claimed by the present invention is defined by the attached claims and their equivalents.
Claims
1. A high efficiency iron removal system, characterized by: The invention comprises a zinc leaching system (1), an oxidation system (2) and an alkaline leaching system (3) through which a solution passes in sequence, wherein: The zinc leaching system (1) leaches the solution by introducing zinc-containing smoke; In the oxidation system (2), oxygen-enriched air and hydrogen peroxide are injected for oxidation; The oxidation system (2) comprises a reaction kettle (21), a guide tube mechanism (22) fixedly arranged inside the reaction kettle (21) and coaxially arranged, an eddy current mechanism (23) penetrating the inside of the guide tube mechanism (22), and a flow divider (24) arranged at the lower end of the eddy current mechanism (23); The guide tube mechanism (22) enables air inside and outside the reaction kettle (21) to communicate with each other, and the vortex mechanism (23) generates a vortex flow from top to bottom on the inner side of the guide tube mechanism (22); The reaction kettle (21) comprises a kettle body (211), a cover body (212) fixedly mounted on the upper end of the kettle body (211), a liquid inlet pipe (213) arranged on the upper surface of the cover body (212), a feed pipe (214) and a feed pipe (215) arranged on the side surface of the kettle body (211), and a maintenance window (216) mounted on the outer surface of the kettle body (211); The guide tube mechanism (22) comprises a tube body (221) fixedly penetrating the upper surface of the cover body (212), and a widened tube (222) fixedly connected to the lower end of the tube body (221); two air intake bends (223) are fixedly connected to the side surface of the tube body (221); the air intake bends (223) extend upward and pass through the upper surface of the cover body (212); The vortex mechanism (23) comprises a rotating shaft (231) rotatably mounted on the inner side of the cylinder (221) via a connecting bearing (232), an impeller (236) fixedly connected to the lower end of the rotating shaft (231), a transmission wheel (233) fixedly connected to the upper end of the rotating shaft (231), and a motor (235) fixedly mounted on the upper edge of the reaction kettle (21), wherein a transmission belt (234) is sleeved on the output shaft of the motor (235) and the transmission wheel (233); The flow divider (24) comprises a disk shell (241) arranged below the cylinder (221), and a plurality of flow divider pipes (244) fixedly embedded in the lower surface of the disk shell (241); a bottom opening (245) is provided at the lower end of the flow divider pipe (244); a side opening (246) is provided on the outer surface of the flow divider pipe (244); a plurality of side openings (247) are provided on the side of the disk shell (241); a hollow opening (242) is provided on the upper surface of the disk shell (241); a plurality of connecting frames (243) are fixedly connected to the inner edge of the hollow opening (242); and the end of the connecting frame (243) is fixedly connected to the edge of the impeller (236).
2. A high efficiency iron removal system according to claim 1, characterized in that: The zinc leaching system (1) comprises a first tank body (11), a first feed pipe (12) and a first exhaust pipe (14) arranged on the upper surface of the first tank body (11), a first discharge pipe (15) arranged at the lower end of the first tank body (11), and a first ventilation pipe (13) arranged on the outer surface of the first tank body (11) near the lower end, wherein the first discharge pipe (15) delivers liquid to the oxidation system (2).
3. A high-efficiency iron removal system according to claim 1, characterized in that: The alkaline leaching system (3) comprises a second tank body (31), a second feed pipe (32) and a second exhaust pipe (34) arranged on the upper surface of the second tank body (31), a second discharge pipe (36) arranged at the lower end of the second tank body (31), a second ventilation pipe (33) arranged on the outer surface of the second tank body (31) near the lower end, and an addition pipe (35) arranged on the outer surface of the second tank body (31) near the upper end.
4. A method for using a high-efficiency iron removal system, characterized in that: The method of claim 1 comprises the following steps: S1, passing the original solution into the inner side of the zinc leaching system (1), and leaching copper through the zinc-containing flue gas; S2, passing the treated liquid in S1 into the inner side of the oxidation system (2), injecting oxygen-rich air and hydrogen peroxide to oxidize the ferrous ions; S3, sending the treated liquid in S2 to the alkaline leaching system (3), adding alkaline and zinc-containing flue gas for oxidation precipitation to complete iron removal.