Construction method of assembling secondary lining formwork in highway tunnel using trolley

By using a hand chain hoist lifting system to assemble the formwork trolley inside the tunnel during highway tunnel construction, the problem of being unable to assemble outside the tunnel due to terrain and geological conditions was solved, achieving economical and environmentally friendly construction results and reducing disturbance to the rock mass. and construction intersection areas.

CN115288746BActive Publication Date: 2024-10-15GANSU ROAD & BRIDGE CONSTR GROUP +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202211084140.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-09-06
Publication Date
2024-10-15
Estimated Expiration
2042-09-06

AI Technical Summary

Technical Problem

In the construction of highway tunnels, poor terrain and geological conditions make it impossible to assemble formwork trolleys outside the tunnel, resulting in increased costs and environmental damage. In addition, traditional assembly methods cause greater disturbance to the rock mass, making it difficult to achieve the construction requirement of zero-excavation tunnels.

Method used

The method of assembling the formwork trolley in the hole of the secondary lining of the highway tunnel is adopted. Cement mortar anchors are installed during the tunnel anchor shot blasting support, and the hand chain hoist lifting system is used to assemble the formwork trolley in the hole to ensure that the construction site is flat. and reasonable hoisting of formwork to reduce disturbance to the rock mass.

Benefits of technology

It realizes the trolley assembly in the tunnel, reduces the disturbance to the rock mass, reduces the construction cost, protects the ecological environment, and conforms to the concept of zero excavation, reduces the construction cross area, and reduces the impact on bridge construction. Influence.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115288746B_ABST
    Figure CN115288746B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of trolley assembly construction of secondary lining formwork for highway tunnels, and in particular to a trolley assembly construction method for secondary lining formwork for highway tunnels. The core is to solve the engineering problem that the trolley cannot assemble outside the tunnel due to force majeure factors such as terrain conditions. The present invention uses the fact that the secondary lining has not yet been constructed after the initial support of the tunnel, providing construction space for the trolley assembly; the lifting system composed of anchor rods and hand winches is used to solve the problem that the crane cannot be constructed in a limited space in traditional assembly; the present invention does not need to consume resources to fill the assembly area, reduces post-construction recovery, implements the concept of zero excavation into the tunnel, and greatly protects the ecological environment; the present invention reduces the construction intersection area for the zero-connection section between the bridge and the tunnel and the bridge section, reducing the impact on the bridge construction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of highway tunnel secondary lining formwork trolley assembly construction, and in particular to a highway tunnel secondary lining formwork trolley in-tunnel assembly construction method, the core of which is to solve the engineering problem of being unable to assemble outside the tunnel due to force majeure factors such as terrain conditions. Background Art

[0002] During tunnel construction, the surrounding rock of the tunnel entrance is generally broken and the geological conditions are poor. The principle of minimizing the disturbance to the rock mass should be followed to improve the stability of the rock mass and the side and back slopes of the tunnel entrance. The "Technical Specifications for Highway Tunnel Construction" and "Construction Drawing Design" both set requirements for the location of the tunnel entrance, emphasizing "entering the tunnel early and exiting the tunnel late", and advocating zero excavation of the tunnel entrance. In the past construction of bridges and tunnels, the practice of pulling earthwork or using tunnel slag to fill and widen the trolley assembly site increased costs, damaged the environment, and disturbed the rock mass of the tunnel entrance.

[0003] Gansu Road and Bridge actively implemented the green construction concept during the construction of the KLTJ1 section of the S44 Kanglue Expressway. Through in-depth exploration and research on the assembly of trolleys, the construction of highways and environmental protection were closely combined in a scientific construction method. Through summary and comparison, a construction method for the assembly of trolleys in the secondary lining formwork of highway tunnels was formed. Summary of the invention

[0004] The purpose of the present invention is to address the deficiencies in the prior art and provide a construction method for assembling the secondary lining formwork trolley in a highway tunnel, which is used for the assembly construction of the secondary lining formwork trolley in a highway tunnel, and is particularly suitable for the assembly construction of the secondary lining formwork trolley in a tunnel where a bridge and a tunnel are connected at zero and a tunnel is wrapped around a bridge, and has the best economic and social benefits.

[0005] In order to achieve the above object, the present invention provides the following technical solutions:

[0006] The highway tunnel secondary lining formwork trolley in-hole assembly construction method is characterized by comprising the following steps:

[0007] Step 1: Construction Preparation

[0008] When using anchor spraying support in tunnels, install a cement mortar anchor rod on the arch crown and the arch waists on both sides of the same section. The mortar anchor rod should undergo a pull-out force (F) test before the formwork is installed.

[0009] F ≥ G × K

[0010] Where: K: safety factor, recommended value is 2; G: weight of single template (kN);

[0011] The assembly of the trolley should start after the invert casting length is greater than 18m, and the flatness of the top surface of the invert should be less than or equal to 5mm to ensure that the construction site is flat;

[0012] Step 2: Laying the track

[0013] Lay the track according to the track gauge requirements. The track is required to be straight, without obvious triangular pits, without misalignment at the joints, with a front-to-back and left-to-right height difference of less than 5mm. The center line should coincide with the tunnel center line as much as possible, with an error of less than 15mm. The track sleeper spacing is generally ≤0.5m and is secured with spikes. The rails are of P43 specification;

[0014] Step 3: Install the walking wheel frame assembly

[0015] Use a loader or excavator to place the driving wheel frame and the driven wheel frame on the paved track, and make temporary supports. According to the center line of the bottom longitudinal beam, adjust the distance between the front and rear wheel frames, and use the principle of equal diagonals to adjust the correct position of the wheel frames, and level and fix them;

[0016] Step 4: Install the bottom longitudinal beam

[0017] Lift the bottom longitudinal beam onto the already arranged wheel frame, and use bolts to add temporary support, check whether the diagonal line has changed, if it is within the correct value, you can install the portal frame;

[0018] Step 5: Install the gantry

[0019] First, assemble the single-piece assembly of the portal frame on the ground; then hoist it piece by piece to the relative position of the bottom longitudinal beam and temporarily fix it with bolts; then install the lock beam and the scissor brace set in each space; use the plumb bob or eye observation to adjust and align; and tighten the bolts of each part in time to form a complete skeleton;

[0020] Step 6: Install the lifting cylinder and other components;

[0021] Step 7: Install the hanging beam, hanging beam column and platform beam

[0022] After all the gantries are installed, the excavator cooperates with the workers to install the hanging beams, columns and platform beams using hand hoists. The hanging beams and columns in the outer row are not installed for the time being;

[0023] Step 8: Top mold installation

[0024] (1) Trial lifting

[0025] After installing the hand chain hoist on the mortar anchor rod of the arch steel frame, a trial hoist should be carried out to determine whether the traction force of the hand chain hoist and the tension and length of the wire rope can meet the requirements and whether the template hoisting point is reasonable. During the trial hoisting, pedestrians and vehicles are prohibited from passing within a radius of 4m from the hoisting point.

[0026] The safety factor of the steel wire rope used in the template should be no less than 6. A lifting ring should be welded on the template. The lifting ring should use HPB300 steel bars. The diameter of the steel bars should be determined through calculation. Under the standard value of the template's deadweight, the tensile stress of the lifting ring should not be greater than 65MPa.

[0027]

[0028] Where: G: weight of a single formwork, N; [σ]: allowable tensile stress of the lifting ring, 65 MPa; n: number of lifting ring sections, 4 for 2 lifting rings; A: cross-sectional area of ​​the lifting ring steel bar used, mm 2 ;

[0029] (2) Top mold installation

[0030] ① Use an excavator to move the top mold to the trolley gantry at the bottom of the hoist;

[0031] ② Remove the wire rope from the excavator hook and connect it to the hand hoists installed at lifting points 1 and 2. Lift the template by mainly vertical lifting at lifting point 1 and supplemented by horizontal lifting at lifting point 2;

[0032] ③Translate the secondary lining trolley to the bottom of the template, use a hoist to slowly lower the template to contact the hanging beam column, and then fix it with bolts. To ensure the accurate positioning of the trolley, you can use a plumb line or infrared measurement to set the position;

[0033] ④When installing the top mold, start from the middle and extend to both ends. This can reduce the cumulative error. After installing the first top mold in the middle, check that the position is correct, and then install other top molds until the top mold installation task is completed;

[0034] Step 9: Install side formwork

[0035] First, place the side formwork on the tunnel side wall at the predetermined position in advance, then return the trolley to its position, hang a hand chain hoist on the stand, use the hand chain hoist to lift the side formwork to the installation position, use the jack and crowbar to make fine adjustments, insert and tighten the bolts, install the lead screw and cylinder, then move the hand chain hoist to the stand at the next formwork to install the next formwork. Pay attention to the left-right symmetry of the installation sequence to prevent biased deformation;

[0036] Step 10: Install hydraulic and electrical systems and ancillary facilities;

[0037] Step 11: Check and tighten all bolts, conduct a no-load test run, and check whether the electrical and hydraulic systems are working properly.

[0038] Compared with the prior art, the present invention has the following beneficial effects:

[0039] 1. The present invention utilizes the fact that after the initial support of the tunnel, the secondary lining has not yet been constructed, thus providing construction space for the assembly of the trolley.

[0040] 2. The present invention utilizes a lifting system composed of anchor rods and hand hoists, which solves the problem that the crane cannot be used for construction in a limited space in traditional assembly.

[0041] 3. This method does not require the consumption of resources to fill the assembly area, reduces post-construction restoration, implements the concept of zero excavation, and greatly protects the ecological environment.

[0042] 4. The present invention reduces the construction intersection area for the zero-connection section between bridge and tunnel and the section where the tunnel covers the bridge, thereby reducing the impact on the bridge construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0043] Figure 1 The top mold installation diagram of the present invention is shown in FIG. Figure 1 ;

[0044] Figure 2 The top mold installation diagram of the present invention is shown in FIG. Figure 2 ;

[0045] Figure 3 The top mold installation diagram of the present invention is shown in FIG. Figure 3 ;

[0046] Figure 4 It is a construction process flow chart of the present invention. DETAILED DESCRIPTION

[0047] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.

[0048] Example 1

[0049] like Figure 4 As shown, the highway tunnel secondary lining formwork trolley in-hole assembly construction method is characterized by comprising the following steps:

[0050] Step 1: Construction Preparation

[0051] When using anchor spraying support in tunnels, install a cement mortar anchor rod on the arch crown and the arch waists on both sides of the same section. The mortar anchor rod should undergo a pull-out force (F) test before the formwork is installed.

[0052] F ≥ G × K

[0053] Where: K: safety factor, recommended value is 2; G: weight of single template (kN);

[0054] The assembly of the trolley should start after the invert casting length is greater than 18m, and the flatness of the top surface of the invert should be less than or equal to 5mm to ensure that the construction site is flat;

[0055] Step 2: Laying the track

[0056] Lay the track according to the track gauge requirements. The track is required to be straight, without obvious triangular pits, without misalignment at the joints, with a front-to-back and left-to-right height difference of less than 5mm. The center line should coincide with the tunnel center line as much as possible, with an error of less than 15mm. The track sleeper spacing is generally ≤0.5m and is secured with spikes. The rails are of P43 specification;

[0057] Step 3: Install the walking wheel frame assembly

[0058] Use a loader or excavator to place the driving wheel frame and the driven wheel frame on the paved track, and make temporary supports. According to the center line of the bottom longitudinal beam, adjust the distance between the front and rear wheel frames, and use the principle of equal diagonals to adjust the correct position of the wheel frames, and level and fix them;

[0059] Step 4: Install the bottom longitudinal beam

[0060] Lift the bottom longitudinal beam onto the already arranged wheel frame, and use bolts to add temporary support, check whether the diagonal line has changed, if it is within the correct value, you can install the portal frame;

[0061] Step 5: Install the gantry

[0062] First, assemble the single-piece assembly of the portal frame on the ground; then hoist it piece by piece to the relative position of the bottom longitudinal beam and temporarily fix it with bolts; then install the lock beam and the scissor brace set in each space; use the plumb bob or eye observation to adjust and align; and tighten the bolts of each part in time to form a complete skeleton;

[0063] Step 6: Install the lifting cylinder and other components;

[0064] Step 7: Install the hanging beam, hanging beam column and platform beam

[0065] After all the gantries are installed, the excavator cooperates with the workers to install the hanging beams, columns and platform beams using hand hoists. The hanging beams and columns in the outer row are not installed for the time being;

[0066] Step 8: Top mold installation

[0067] (3) Trial lifting

[0068] After installing the hand chain hoist on the mortar anchor rod of the arch steel frame, a trial hoist should be carried out to determine whether the traction force of the hand chain hoist and the tension and length of the wire rope can meet the requirements and whether the template hoisting point is reasonable. During the trial hoisting, pedestrians and vehicles are prohibited from passing within a radius of 4m from the hoisting point.

[0069] The safety factor of the steel wire rope used in the template should be no less than 6. A lifting ring should be welded on the template. The lifting ring should use HPB300 steel bars. The diameter of the steel bars should be determined through calculation. Under the standard value of the template's deadweight, the tensile stress of the lifting ring should not be greater than 65MPa.

[0070]

[0071] Where: G: weight of a single formwork, N; [σ]: allowable tensile stress of the lifting ring, 65 MPa; n: number of lifting ring sections, 4 for 2 lifting rings; A: cross-sectional area of ​​the lifting ring steel bar used, mm 2 ;

[0072] (4) Top mold installation

[0073] ① Use an excavator to move the top mold to the trolley gantry at the bottom of the hoist; Figure 1 As shown;

[0074] ② Remove the wire rope from the excavator hook and connect it to the hand hoists set at lifting points 1 and 2. Lift the template by vertical lifting at lifting point 1 as the main method and horizontal lifting at lifting point 2 as the auxiliary method. Figure 2 As shown;

[0075] ③ Move the secondary lining trolley horizontally to the bottom of the template, use the hoist to slowly lower the template and make contact with the hanging beam column, then fix it with bolts. To ensure the accurate positioning of the trolley, you can use a plumb line or infrared measurement to set the position; Figure 3 As shown;

[0076] ④When installing the top mold, start from the middle and extend to both ends. This can reduce the cumulative error. After installing the first top mold in the middle, check that the position is correct, and then install other top molds until the top mold installation task is completed;

[0077] Step 9: Install side formwork

[0078] First, place the side formwork on the tunnel side wall at the predetermined position in advance, then return the trolley to its position, hang a hand chain hoist on the stand, use the hand chain hoist to lift the side formwork to the installation position, use the jack and crowbar to make fine adjustments, insert and tighten the bolts, install the lead screw and cylinder, then move the hand chain hoist to the stand at the next formwork, and install the next formwork. Pay attention to the left-right symmetry of the installation sequence to prevent biased deformation;

[0079] Step 10: Install hydraulic and electrical systems and ancillary facilities;

[0080] Step 11: Check and tighten all bolts, conduct a no-load test run, and check whether the electrical and hydraulic systems are working properly.

[0081] Example 2

[0082] Project name: S44 Kangxian to Lueyang Expressway Wangguan to Baihegou Section Project

[0083] Project location: Kang County, Longnan City, Gansu Province

[0084] Project Overview: The entrance and exit of the Huaqiao Tunnel of the TJ1 section of Kanglue Expressway are arranged according to the principle of "entering the tunnel early and exiting the tunnel late", and the "zero excavation" tunnel entry design concept is implemented to minimize the excavation height of the tunnel entrance and the back slope to ensure the stability of the original rock and soil. This project is located in the mountainous area of ​​​​Nanjing, and the tunnel entry conditions are relatively poor. In order to protect the local ecological environment, the design is based on the principle of minimizing the damage to the natural ecological environment of the tunnel entrance due to tunnel excavation. In the selection of the location and form of the tunnel portal, the terrain, engineering geology, hydrogeology, natural environment, construction site and other factors of the tunnel portal are fully considered to reasonably determine the location and structural type of the tunnel portal. The tunnel adopts a sleeve arch scheme to assist in entering the tunnel to reduce excavation; through the advanced pipe shed and advanced pre-grouting of the tunnel entrance and shallow buried section, the comprehensive formulation of the tunnel entrance section construction plan, the strengthening of surface settlement and displacement observation, and the reasonable layout of the tunnel entrance drainage facilities and other measures to ensure the stability of the tunnel entrance structure and construction safety.

[0085] Construction start and completion dates: March 1, 2021 to August 31, 2023.

[0086] Project cost: 1,105,685,000 yuan.

[0087] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. Highway tunnel secondary lining formwork trolley in-hole assembly construction method, characterized by: The steps include: Step 1: Construction Preparation When using anchor spraying support in tunnels, a cement mortar anchor rod is installed on the arch crown and the arch waists on both sides of the same section. The mortar anchor rod is subjected to a pull-out force F test before the formwork is installed. F ≥ G × K Where: K: safety factor, value is 2; G: weight of single template, kN; The assembly of the trolley starts after the invert casting length is greater than 18m, and the flatness of the top surface of the invert is less than or equal to 5mm to ensure that the construction site is flat; Step 2: Laying the track Lay the track according to the track gauge requirements. The track should be straight, without obvious triangular pits, without misalignment at the joints, with a front-to-back and left-to-right height difference of less than 5mm. The center line should coincide with the tunnel center line as much as possible, with an error of less than 15mm. The spacing between track sleepers should be ≤0.5m and fastened with spikes. The rails should be of P43 specification. Step 3: Install the walking wheel frame assembly Use a loader or excavator to place the driving wheel frame and the driven wheel frame on the paved track, and make temporary supports. According to the center line of the bottom longitudinal beam, adjust the distance between the front and rear wheel frames, and use the principle of equal diagonals to adjust the correct position of the wheel frames, and level and fix them; Step 4: Install the bottom longitudinal beam Lift the bottom longitudinal beam onto the already placed wheel frame, and use bolts to add temporary support, check whether the diagonal line has changed, and if it is within the correct value, install the portal frame; Step 5: Install the gantry First, assemble the single-piece assembly of the portal frame on the ground; then hoist it piece by piece to the relative position of the bottom longitudinal beam and temporarily fix it with bolts; then install the lock beam and the scissor brace set in each space; use the plumb bob or eye observation to adjust and align; and tighten the bolts of each part in time to form a complete skeleton; Step 6: Install the lifting cylinder; Step 7: Install the hanging beam, hanging beam column and platform beam After all the gantries are installed, the excavator cooperates with the workers to install the hanging beams, columns and platform beams using hand hoists. The hanging beams and columns in the outer row are not installed for the time being; Step 8: Top mold installation (1) Trial lifting After installing the hand chain hoist on the mortar anchor rod of the arch steel arch frame, conduct a trial hoist to determine whether the traction force of the hand chain hoist and the tension and length of the wire rope can meet the requirements, and whether the template lifting point is reasonable. During the trial hoist, pedestrians and vehicles are prohibited from passing within a radius of 4m from the lifting point; The safety factor of the steel wire rope used in the template is not less than 6. The lifting ring is welded on the template. The lifting ring uses HPB300 steel bars. The diameter of the steel bars is determined by calculation. Under the standard value of the template's deadweight, the tensile stress σ of the lifting ring is not greater than 65MPa. Where: G: weight of a single template, N; [σ]: allowable tensile stress of the lifting ring, 65MPa; n: number of lifting ring sections, 4 for 2 lifting rings; A: cross-sectional area of ​​the lifting ring steel bar used, mm 2 ; (2) Top mold installation ① Use an excavator to move the top mold to the trolley gantry at the bottom of the hoist; ② Remove the wire rope from the excavator hook and connect it to the hand hoists installed at lifting points 1 and 2. Lift the template by mainly vertical lifting at lifting point 1 and supplemented by horizontal lifting at lifting point 2; ③Translate the secondary lining trolley to the bottom of the template, use a hoist to slowly lower the template to contact the hanging beam column, and then fix it with bolts. To ensure the accurate positioning of the trolley, use a plumb line or infrared measurement to set the position; ④When installing the top mold, start from the middle and extend to both ends. Install the first top mold in the middle. After checking that the position is correct, install other top molds until the top mold installation task is completed; Step 9: Install side formwork First, place the side formwork on the tunnel side wall at the predetermined position in advance, then return the trolley to its position, hang a hand chain hoist on the stand, use the hand chain hoist to lift the side formwork to the installation position, use the jack and crowbar to make fine adjustments, insert and tighten the bolts, install the lead screw and cylinder, then move the hand chain hoist to the stand at the next formwork, and install the next formwork. Pay attention to the left-right symmetry of the installation sequence to prevent biased deformation; Step 10: Install hydraulic and electrical systems and ancillary facilities; Step 11: Check and tighten all bolts, conduct a no-load test run, and check whether the electrical and hydraulic systems are working properly.