Repair method of collapsed tunnel
The method stabilizes collapsed tunnels using crossbeams and drill rods to efficiently reopen and secure the tunnel, addressing safety and cost issues by preventing further blockages and voids.
Patent Information
- Application Number
- CN202210938957.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-08-05
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2042-08-05
AI Technical Summary
Existing tunnel repair methods face challenges in safely and efficiently reopening a tunnel after collapse, leading to increased costs and safety risks due to loose filling materials blocking the tunnel and forming voids.
A method involving the use of crossbeams and drill rods to stabilize the collapsed area, with sequential installation and slag removal operations, followed by concrete sealing to secure the tunnel structure.
Enables quick and safe reopening of the tunnel, reducing costs and construction time while ensuring operator safety by stabilizing the tunnel and preventing further blockages.
Smart Images

Figure CN115306409B_ABST
Abstract
Description
Technical Field
[0001] The present disclosure relates to the field of tunnels, and in particular, to a method for repairing a collapsed tunnel. Background Art
[0002] The backfill mining method is a mining method that fills the goaf with backfill materials. As the mining face advances, backfill materials are continuously fed into the goaf, and mining is carried out on the formed backfill body or under its protection. However, the mined tunnel may be blocked by the collapse of the backfill body due to mining operations such as chute or deformation along the way. When encountering a backfill body collapse, the operators will choose to bypass the collapsed area and reopen the tunnel, or directly clear the collapsed backfill body. If they choose to reopen the tunnel, the vibration generated by the construction operation will make it difficult to ensure the safety of the tunnel. If the length of the bypass tunnel is extended, a lot of costs and construction period will be added. If the backfill body is removed directly, the loose backfill materials in the goaf will continue to fall due to gravity, continue to block the tunnel, and form high sheds and voids in the filled goaf, which is not conducive to low-pressure control and safety management. Summary of the invention
[0003] The purpose of the present invention is to provide a method for repairing a collapsed tunnel to solve the problem in the related art that the tunnel is difficult to repair after collapse.
[0004] In order to achieve the above object, the present disclosure provides a method for repairing a collapsed tunnel, the method comprising:
[0005] Step a, fixing a first crossbeam at a height position corresponding to the tunnel roof in the collapsed area, so that the first crossbeam is perpendicular to the extension direction of the tunnel, and the first crossbeam is provided with a plurality of mounting holes that penetrate through and have axes inclined upward;
[0006] Step b, inserting a drill rod into each of the mounting holes, extending one end of the drill rod into the filling body of the collapsed area, and fixing the other end of the drill rod to the first crossbeam;
[0007] Step c, performing a slag removal operation to remove the filling body below the middle position of the drill rod;
[0008] Repeat steps a to c, wherein a plurality of first crossbeams are arranged in sequence along the extension direction of the tunnel, and each first crossbeam is located directly below the middle position of the drill rod in the previous first crossbeam.
[0009] Optionally, the slag cleaning operation is performed in multiple times. After each slag cleaning operation, a column erected on the tunnel floor is set below the drill rod, and a second beam is fixed on the top of the column. The second beam is set parallel to the first beam and fits the drill rod.
[0010] Optionally, the maximum distance of a single slag cleaning operation is one third of the length of the drill rod, and the maximum total distance of multiple slag cleaning operations is two thirds of the length of the drill rod.
[0011] Optionally, in step b, the drill rod is first driven into a plurality of the mounting holes at intervals, and then the drill rod is driven into the remaining mounting holes.
[0012] Optionally, the inclination angle of the plurality of mounting holes relative to the tunnel roof is 20°-30°, the mounting spacing between two adjacent mounting holes is 0.1m-0.3m, and the aperture of the mounting hole is 0.02m-0.05m.
[0013] Optionally, the length of the drill rod is 1.5m-2.0m.
[0014] Optionally, in step a, a first anchor rod is embedded in the surrounding rock at the edge of the tunnel, and the first crossbeam is fixed on the first anchor rod, wherein the first anchor rod is located at an end position of the first crossbeam.
[0015] Optionally, in step a, a plurality of second anchor rods are embedded in the surrounding rock at the edge of the tunnel, and a support plate is fixed on the plurality of second anchor rods so that the support plate is supported under the first crossbeam.
[0016] Optionally, in step a, the first crossbeam is fully welded to the first anchor rod, and the support plate is fully welded to the second anchor rod;
[0017] In the step b, one end of the drill rod is fully welded to the first beam.
[0018] Optionally, the method further comprises step d: after the slag removal operation in the collapsed area, building a concrete bottom to seal the collapsed area at the height position of the first beam.
[0019] Through the above technical solution, when the filling body of the tunnel collapses, the above-mentioned method for repairing the collapsed tunnel is implemented, the tunnel can be quickly reopened, and the problem of traffic in the collapsed tunnel can be solved safely and efficiently. The operators always work under a solid support body, ensuring the safety of the operators. There is no need to bypass the collapsed area to reopen a tunnel, which saves costs and construction time, improves efficiency, and avoids the construction of reopening the tunnel affecting the safety of the entire tunnel. At the same time, it also avoids the loose filling materials continuing to block the tunnel when the filling body in the collapsed area is directly removed. After the loose filling materials fall, high sheds and voids will be formed in the goaf, which is not conducive to low-pressure control and safety management.
[0020] Other features and advantages of the present disclosure will be described in detail in the following detailed description. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] The accompanying drawings are used to provide a further understanding of the present disclosure and constitute a part of the specification. Together with the following specific embodiments, they are used to explain the present disclosure but do not constitute a limitation of the present disclosure. In the accompanying drawings:
[0022] Figure 1 is a structural schematic diagram of a method for repairing a collapsed tunnel provided by an exemplary embodiment of the present disclosure;
[0023] Figure 2 is along Figure 1 Sectional view taken along line AA;
[0024] Figure 3 yes Figure 1 A magnified view of part I;
[0025] Figure 4 It is a schematic structural diagram after completing step b in the method for repairing a collapsed tunnel provided in an exemplary embodiment of the present disclosure.
[0026] Description of Reference Numerals
[0027] 1-first crossbeam, 11-mounting hole, 12-drill rod, 13-support plate, 2-second crossbeam, 21-column, 3-tunnel, 31-collapsed area, 32-filling body, 33-tunnel roof. DETAILED DESCRIPTION
[0028] The specific implementation of the present disclosure is described in detail below in conjunction with the accompanying drawings. It should be understood that the specific implementation described herein is only used to illustrate and explain the present disclosure, and is not used to limit the present disclosure.
[0029] In the present disclosure, unless otherwise stated, directional words such as "upper, lower, and bottom" generally refer to the directional positions of the relevant components in actual use. Figure 1 The “inside” and “outside” refer to the inside and outside of the corresponding component outline. In addition, when the following description refers to the drawings, unless otherwise indicated, the same numbers in different drawings represent the same or similar elements. The terms “first”, “second”, etc. used in this disclosure are to distinguish one element from another element and have no order or importance.
[0030] The present disclosure provides a method for repairing a collapsed tunnel 3, such as Figures 1 to 4 As shown, it should be noted here that, in the following method steps, the order of the text represents the order of the steps, and the method includes the following steps:
[0031] Step a, fix the first crossbeam 1 at the height position corresponding to the tunnel roof 33 in the collapsed area 31, so that the first crossbeam 1 is perpendicular to the extension direction of the tunnel 3, and the first crossbeam 1 is provided with a plurality of through-going mounting holes 11 with the axis tilted upward. The tunnel roof 33 mentioned here is used to support the rock layer above the tunnel 3, and generally can be constructed of materials such as wood, steel or concrete. If the roof condition is good, no additional support is required, and the roof is the structure such as the mine pillar or rock above. Figure 4 The first cross beam 1 can be arranged at a height position close to the tunnel roof 33 and close to the edge of the collapsed area 31 .
[0032] Step b, driving a drill rod 12 into each mounting hole 11, extending one end of the drill rod 12 into the filling body 32 of the collapsed area 31, and fixing the other end on the first crossbeam 1. In this way, multiple drill rods 12 are fixed obliquely inside the first crossbeam 1 and the filling body 32. When performing step b, a rock drill can be used to drive the drill rod 12, and it is necessary to monitor the changes of the drill rod 12 and the filling body 32 at all times. If it is found that the drill rod 12 is deformed or the filling body 32 keeps falling, the rock drill needs to be stopped in time. One end of the drill rod 12 can be set to a pointed shape, so that it can be easier to drive the filling body 32.
[0033] Step c, performing a slag removal operation to remove the filling body 32 below the middle position of the drill rod 12. The middle position of the drill rod 12 represents other positions except the two ends of the drill rod 12. One end of the drill rod 12 is fixed on the first crossbeam 1, and the other end after the slag removal operation is still embedded in the filling body 32 and is in a fixed state. During the slag removal operation, the filling body 32 below the middle position of the drill rod 12 will not completely expose the drill rod 12 driven into the filling body 32. Even if there is no filling body 32 support below the middle position of the drill rod 12, the filling body 32 and the drill rod 12 above it will not fall. The slag removal operation also reduces the filling material in the collapsed area 31 by a distance along the length direction of the tunnel 3.
[0034] For the convenience of explanation, the end of the drill rod 12 fixed to the first beam 1 is defined as the front end of the drill rod 12, and the end of the drill rod 12 embedded in the filling body 32 and in a fixed state after the slag cleaning operation is defined as the end of the drill rod 12.
[0035] Repeat steps a to c, wherein the plurality of first beams 1 are arranged in sequence according to the extension direction of the tunnel 3, and each first beam 1 is located directly below the middle position of the drill rod 12 in the previous first beam 1. After repeating steps a and b, the next first beam 1 and the drill rod 12 fixed to the next first beam 1 can support the end of the drill rod 12 in the previous first beam 1, preventing the drill rod 12 in the previous first beam 1 and the filling material above from falling when step c is repeated. Repeat steps a to c until the filling material in the collapsed area 31 is cleaned up.
[0036] When the filling body 32 of the tunnel 3 collapses, the filling body 32 causes the tunnel roof 33 to collapse, and the filling body 32 enters the tunnel 3. Through the above technical solution, the above-mentioned method for repairing the collapsed tunnel 3 is implemented, so that the tunnel 3 can be quickly reopened, and the traffic problem of the collapsed tunnel 3 can be solved safely and efficiently. The operators always work under a solid support body, ensuring the safety of the operators. There is no need to bypass the collapsed area 31 to reopen a tunnel 3, which saves costs and construction time, improves efficiency, and avoids the construction of reopening the tunnel 3 affecting the safety of the entire tunnel 3. At the same time, it also avoids the loose filling material continuing to block the tunnel 3 when the filling body 32 is directly removed. After the loose filling material falls, high sheds and voids will be formed in the goaf, which is not conducive to ground pressure control and safety management.
[0037] Further, the slag removal operation can be carried out in multiple times. After each slag removal operation, a column 21 standing on the bottom plate of the tunnel 3 is set below the drill rod 12, and a second crossbeam 2 is fixed on the top of the column 21. The second crossbeam 2 is arranged parallel to the first crossbeam 1 and fits the drill rod 12. After the slag removal operation, the weight of the upper filling body 32 is supported by the drill rod 12. The drill rod 12 may be bent or fall off directly. The second crossbeam 2 can ensure the strength and service life of the drill rod 12, and play a supporting and protective role for the drill rod 12. At the same time, the second crossbeam 2 can also hinder the filling, further preventing the filling from falling from the gap between the drill rods 12. The material of the second crossbeam 2 and the column 21 can be selected from wood, for example, a pine beam with a diameter of not less than 0.2m can be selected. Pine wood has high strength and corrosion resistance, and pine wood has certain toughness and elasticity, which is suitable for fitting the drill rod 12. In addition to wood, the second crossbeam 2 can also be made of any material with suitable strength, such as steel, which is not specifically limited in the present disclosure, as long as the support conditions for the drill rod 12 can be met.
[0038] Since the filling material contains a lot of impurities such as dust, a spray device can be set in tunnel 3 during slag cleaning operations to spray water mist into the slag cleaning area. The water mist can wrap the dust caused by the slag cleaning operation and fall down. At the same time, when the filling material becomes moist, the generation of dust will be reduced, ensuring that the operators will not inhale too much dust during the slag cleaning operation.
[0039] The distance of a single slag removal operation can be at most one-third of the length of the drill rod 12, and the total distance of multiple slag removal operations can be at most two-thirds of the length of the drill rod 12. The distance of a single slag removal operation can be changed according to actual conditions. When the volume of the filling body 32 is small and easy to fall or when the material quality of the filling body 32 is heavy, the distance of the slag removal operation can be shortened, and the number of second beams 2 is increased to ensure the strength of the drill rod 12. During the slag removal operation, it is also necessary to pay attention to the state of the drill rod 12 at all times. When the drill rod 12 is deformed by force, it is necessary to stop the slag removal operation in time and install the second beam 2. At the same time, the total distance of the slag removal operation can be at most two-thirds of the length of the drill rod 12, ensuring that the end of the drill rod 12 has enough length to ensure the use strength and support effect of the drill rod 12 after the slag removal operation. Among them, the distance of the slag removal operation refers to the length of the drill rod 12 itself.
[0040] In the method for repairing the collapsed tunnel 3 disclosed in the present invention, in step b, the drill rod 12 may be driven into the multiple installation holes 11 at intervals (i.e., a drill rod 12 may be driven into every other installation hole 11), and then the drill rod 12 may be driven into the remaining installation holes 11. The common tunnel 3 filling material is gravel, and the drill rod 12 is driven into the filling material. The drill rod 12 may affect the gap between the filling bodies 32 during the driving process. Driving the drill rod 12 into the installation holes 11 at intervals can ensure that all the drill rods 12 can be driven into the filling bodies 32, and avoid the gap between the filling bodies 32 becoming smaller due to the injected drill rod 12 squeezing the filling bodies 32, thereby affecting the subsequent installation of the drill rod 12.
[0041] The inclination angle of the plurality of mounting holes 11 relative to the tunnel roof 33 may be 20°-30°, so that the drill rod 12 can better play the role of supporting the filling body 32. If the inclination angle of the mounting hole 11 is too large, the height position of the end of the drill rod 12 from the tunnel roof 33 will be too large, and the filling body 32 will fall from the gap between the end of the drill rod 12 and the front end of the drill rod 12 on the next first beam 1 in the vertical direction. If the inclination angle of the mounting hole 11 is too small, the drill rod 12 on the next first beam 1 will be too close to the distance from the end of the drill rod 12 in the vertical direction when it is driven into the filling body 32, and the drill rod 12 will become loose during the driving process.
[0042] The installation spacing between two adjacent installation holes 11 can be 0.1m-0.3m, ensuring that the filling body 32 will not fall between the two drill rods 12. The aperture of the installation hole 11 can be 0.02m-0.05m, and the aperture of the installation hole 11 limits the diameter of the drill rod 12, ensuring that the drill rod 12 can be driven into the gap between the filling bodies 32.
[0043] The length of the drill rod 12 can be 1.5m-2.0m. Thus, in combination with the above description of the slag removal operation, the maximum length of a single slag removal operation can be controlled between 0.5m and 0.6m, ensuring the use strength and support effect of the drill rod 12 after the slag removal operation.
[0044] In step a, a first anchor rod can be embedded in the surrounding rock at the edge of the tunnel 3, and the first beam 1 can be fixed on the first anchor rod, wherein the first anchor rod is located at the end of the first beam 1. Further, in step a, multiple second anchor rods are embedded in the surrounding rock at the edge of the tunnel 3, and a support plate 13 is fixed on the multiple second anchor rods, so that the support plate 13 is supported under the first beam 1. The distance that the first anchor rod and the second anchor rod are embedded in the surrounding rock can be 0.8m. If the first beam 1 is subjected to a large force, a longer first anchor rod and a longer second anchor rod can be adaptively selected. The longer the distance that the first anchor rod and the second anchor rod are embedded in the surrounding rock, the better the fixing effect and the supporting effect on the first beam 1. The support plate 13 further prevents possible deformation of the first beam 1 and improves the service life of the first beam 1.
[0045] In step a, the first crossbeam 1 can be fully welded to the first anchor rod, and the support plate 13 can be fully welded to the second anchor rod; in step b, one end of the drill rod 12 can be fully welded to the first crossbeam 1. Full welding can weld all the contacting places of the two workpieces to be welded, ensure the connection strength required at the connection of the two workpieces, and increase the service life.
[0046] The above method may also include step d: after the slag removal operation in the collapsed area 31, a concrete bottom is established at the height position of the first beam 1 to block the collapsed area 31. In this way, the gaps at the top of the tunnel 3 passing through the collapsed area 31 are filled with concrete, and the drill rod 12, the first beam 1 and the second beam 2 are further fixed. When working in the tunnel 3, vibration may occur. The concrete bottom can avoid the misalignment between the drill rod 12, the first beam 1 and the second beam 2 due to vibration, thereby improving the safety and stability of repairing the tunnel 3. At the same time, there is no gap at the top of the tunnel 3, which prevents the small-volume filling body 32 from falling and reduces the generation of dust.
[0047] The preferred embodiments of the present disclosure are described in detail above in conjunction with the accompanying drawings; however, the present disclosure is not limited to the specific details in the above embodiments. Within the technical concept of the present disclosure, a variety of simple modifications can be made to the technical solution of the present disclosure, and these simple modifications all fall within the protection scope of the present disclosure.
[0048] It should also be noted that the various specific technical features described in the above specific embodiments can be combined in any suitable manner without contradiction. In order to avoid unnecessary repetition, the present disclosure will not further describe various possible combinations.
[0049] In addition, various embodiments of the present disclosure may be arbitrarily combined, and as long as they do not violate the concept of the present disclosure, they should also be regarded as the contents disclosed by the present disclosure.
Claims
1. A method for repairing a collapsed tunnel. It is characterized in that The method comprises: Step a, fixing a first crossbeam at a height position corresponding to the tunnel roof in the collapsed area, so that the first crossbeam is perpendicular to the extension direction of the tunnel, and the first crossbeam is provided with a plurality of mounting holes that penetrate through and have axes inclined upward; Step b, inserting a drill rod into each of the mounting holes, extending one end of the drill rod into the filling body of the collapsed area, and fixing the other end of the drill rod to the first crossbeam; Step c, performing a slag removal operation to remove the filling body below the middle position of the drill rod; Repeating steps a to c, wherein the plurality of first crossbeams are arranged in sequence along the extension direction of the tunnel, and each first crossbeam is located directly below the middle position of the drill rod in the previous first crossbeam; The slag cleaning operation is performed in multiple times. After each slag cleaning operation, a column standing on the bottom plate of the tunnel is arranged below the drill rod, and a second crossbeam is fixed on the top of the column. The second crossbeam is arranged parallel to the first crossbeam and fits the drill rod. The maximum distance of a single slag cleaning operation is one third of the length of the drill rod, and the maximum total distance of multiple slag cleaning operations is two thirds of the length of the drill rod.
2. The method for repairing a collapsed tunnel according to claim 1, It is characterized in that In the step b, the drill rods are first driven into the plurality of mounting holes at intervals, and then the drill rods are driven into the remaining mounting holes.
3. The method for repairing a collapsed tunnel according to claim 1, It is characterized in that The inclination angle of the plurality of mounting holes relative to the tunnel roof is 20°-30°, the mounting spacing between two adjacent mounting holes is 0.1m-0.3m, and the aperture of the mounting holes is 0.02m-0.05m.
4. The method for repairing a collapsed tunnel according to claim 1, It is characterized in that The length of the drill rod is 1.5m-2.0m.
5. The method for repairing a collapsed tunnel according to claim 1, It is characterized in that In the step a, a first anchor rod is embedded in the surrounding rock at the edge of the tunnel, and the first crossbeam is fixed on the first anchor rod, wherein the first anchor rod is located at the end position of the first crossbeam.
6. The method for repairing a collapsed tunnel according to claim 5, It is characterized in that In step a, a plurality of second anchor rods are embedded in the surrounding rock at the edge of the tunnel, and a support plate is fixed on the plurality of second anchor rods so that the support plate is supported under the first crossbeam.
7. The method for repairing a collapsed tunnel according to claim 6, It is characterized in that In step a, the first crossbeam is fully welded to the first anchor rod, and the support plate is fully welded to the second anchor rod; In the step b, one end of the drill rod is fully welded to the first beam.
8. The method for repairing a collapsed tunnel according to claim 1, It is characterized in that The method further comprises step d: after the slag removal operation in the collapsed area, a concrete bottom is established at the height position of the first crossbeam to seal the collapsed area.