A wind power generation concrete tower installation construction method

Through the factory prefabricated and centralized assembly combination method, the semi-circular C-type concrete tower pipe sheet is prefabricated in segments, and the overall structure is formed by large lifting machinery and prestressed steel strands, which solves the low installation efficiency and danger of concrete towers. The problem of high performance achieves efficient and stable tower installation and maintenance.

CN115306645BActive Publication Date: 2024-11-01POWER CHINA HENAN ENG CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202211047170.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-08-30
Publication Date
2024-11-01
Estimated Expiration
2042-08-30

AI Technical Summary

Technical Problem

Concrete towers are inefficient and risky during installation and maintenance, making it difficult to meet the needs of the ultra-high tower wind power market.

Method used

Using factory prefabricated and centralized assembly combination methods, the semicircular ring C-type concrete tower pipe sheet is prefabricated in segments. Through the modular design of vertical and horizontal segments, large-scale lifting machinery and prestressed steel strands are used. Form an integral structure to realize section-by-section lifting and sealing joint installation.

Benefits of technology

It improves the installation efficiency of concrete towers, reduces construction risks and maintenance costs, enhances the stability and durability of towers, and is suitable for the ultra-high tower wind power market.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure SMS_1
    Figure SMS_1
  • Figure SMS_2
    Figure SMS_2
Patent Text Reader

Abstract

The present invention discloses a method for installing and constructing a wind power generation concrete tower, which adopts a factory prefabrication and centralized assembly method, including prefabrication of semicircular C-shaped concrete tower segments, centralized assembly of mixed tower segments, installation of accessories in mixed tower segments, on-site transportation of mixed tower segments, hoisting of the first segment of the mixed tower, hoisting of other O-shaped segments of the mixed tower, hoisting of steel transition segments, prestressed construction of the mixed tower, and overall inspection and acceptance. The present invention uses modules to prefabricate into a structural form that is easy to stack, transport, and install, vertically segmented and horizontally segmented, first prefabricated into semicircular C-shaped concrete segments, and assembled into O-shaped mixed tower segments on site, and adopts a segment-by-segment hoisting, staggered installation, and circumferential joint installation method. After the entire concrete tower is installed, it is in a towering truncated cone shape, and is prestressed with the steel transition stage and the permanent foundation platform of the wind turbine to form an integral structure, becoming a stable support tower for the wind turbine, thereby improving the installation quality and safety of the concrete tower.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to an installation method of wind power generation equipment, in particular to an installation construction method of a wind power generation concrete tower, and belongs to the technical field of wind power equipment installation. Background Art

[0002] As high-quality wind source areas gradually decrease, the development of the wind power industry has fully entered the low wind speed area, which requires ultra-high tower technology with better performance. Steel-concrete composite towers with obvious cost advantages and excellent performance have become the preferred choice of the wind power industry. Concrete towers have natural durability (anti-corrosion), can still maintain their performance under extreme conditions, have low maintenance costs, and have lower investment costs than all-steel structure towers, bringing better power generation, especially concrete towers and steel towers. The concrete-steel hybrid towers have gradually increased their share in the ultra-high tower wind power market, and their advantages in wind power generation in plain areas are more prominent.

[0003] Concrete towers are very difficult to build and install due to their high height, and after they are built and installed, it is also very inconvenient to repair and maintain the interior. Therefore, it is an urgent task to conduct innovative research on the installation and construction methods of concrete towers, improve the efficiency of wind turbine concrete tower installation and reduce the danger of construction. Summary of the invention

[0004] The technical problem to be solved by the present invention is to provide a wind power generation concrete tower installation construction method to improve installation efficiency and reduce construction risks.

[0005] The technical solution adopted by the present invention to solve the technical problem is:

[0006] A wind power generation concrete tower installation construction method adopts a factory prefabrication and centralized assembly combination method, and specifically includes the following specific steps:

[0007] A. Prefabricated semicircular C-shaped concrete tower tube segments;

[0008] (1) For ultra-high concrete towers, modules are customized with horizontal segments and vertical slices. Each set of concrete towers has 28 mixed tower pipe sections, with a height of 2.99m to 3.99m, 3.99m at the bottom section, 2.99m at the top section, and gradually increasing in the middle section. The weight of the mixed tower pipe section is 28.75t to 72.68t, with the bottom section being 72.68t. The bottom outer diameter of the bottom mixed tower pipe section is 8620mm, which decreases evenly from bottom to top. The top and bottom outer diameters of the top mixed tower pipe section are both 4300mm.

[0009] (2) Two semi-circular C-shaped segments are prefabricated in each mixed tower pipe section. The two semi-circular C-shaped segments are assembled into an O-shaped mixed tower pipe section, which is equipped with reinforced steel bars and prestressed corrugated pipe channels to meet the external dimension requirements for large-scale highway equipment transportation;

[0010] B. Centralized assembly of mixed tower segments:

[0011] (1) Establish a temporary stacking yard for the assembly of the semi-circular C-shaped segments of the mixed tower, build several assembly platforms, and complete the stacking, assembly, and installation of internal accessories of the concrete tower tube segments; each assembly platform is arranged with 2 groups of 8 concrete piers, the flatness of the concrete piers is 2mm, and the tolerance is +1mm relative to the reference surface. The flatness of the assembly platform is adjusted with 1mm and 2mm thick thin steel plates and rubber pads;

[0012] (2) Two semicircular C-shaped segments are assembled into an O-shaped segment. Before the two semicircular C-shaped segments are assembled, a circular joint template sealing strip is glued to the concrete surface of the joint groove. The diameter of the sealing strip is greater than 20 mm, and the vertical joint of the assembly is 10 to 15 mm.

[0013] (3) The inner and outer gaps of the vertical joints are sealed with sealing strips and epoxy resin glue. Grouting work begins 6 hours after the grouting is completed. To ensure that the position of the semi-circular C-shaped segments remains unchanged during the grouting of the vertical joints and to prevent cracks in the sealing materials, the two semi-circular C-shaped segments are reinforced as a whole. Five fastening devices are used. The upper three are fastening belts tightened by a tensioner, and the lower two are steel wire ropes tightened by a 3t hand winch. The fastening devices are removed 6 hours after grouting.

[0014] (4) The grouting material for the vertical joints of the semi-circular C-type concrete segments is cement-based. The two vertical joints of the O-type segments are grouted at the same time. The grouting flow rate is 10-15L / min. The vertical joint grouting is 4-6 minutes until the grouting material overflows from the top of the segment joint. The vertical joint grouting material is sampled and retained to confirm that the lifting strength is 25mp. More than 4 groups of test blocks are retained each time. The test block size is 40*40*160. The test blocks are taken from the grouting batches of the first and last joints filled on the same day. The lifting can be carried out only 18 hours after the grouting operation is completed or the compressive strength of the grouting test blocks cured under the same conditions exceeds 25MPa.

[0015] C. Installation of accessories in the mixing tower segment:

[0016] The installation of accessories inside the concrete tower segment can be completed before or after assembly. The accessories include platform support, cable clamp bracket, ladder bracket, which are installed according to the embedded screw holes in the precast concrete segment.

[0017] D. On-site transportation of mixed tower pipe sections:

[0018] (1) The O-shaped concrete pipe sections assembled in a centralized manner need to be transported from the storage yard to each lifting machine site. In order to improve the installation efficiency, a multi-vehicle flow-type circulation transportation and direct lifting of the vehicle plate at the machine site are adopted. The vehicle model and transportation interval time are determined in advance according to the overall size and weight of the concrete tower section;

[0019] (2) Rubber bottom pads are laid at the location of the mixing tower pipe section to play a shock-absorbing role, prevent the mixing tower pipe section from being bumped, deformed, or overturned during transportation, ensure that the mixing tower pipe section is stable on the vehicle, and protect the bottom from damage; after the mixing tower pipe section is stably dropped onto the vehicle, it is tied and reinforced with nylon flat belts, tying wire ropes, 5t hand winches, and 5t shackles. One end of the hand winch is connected to the nylon flat belt, which is passed over the top of the pipe section, and the other end is connected to the shackle, which is fixed to the vehicle body;

[0020] E. The first section of the mixed tower is hoisted into place:

[0021] The hoisting of the first O-shaped pipe section of the concrete tower is the basis and key to the installation of the wind turbine tower. It is directly hoisted into place by large lifting machinery. Three positioning guide rods are used to ensure that the 40 prestressed holes in the first section of the tower are correctly connected with the reserved corrugated pipes of the foundation. The flatness and centering degree, the through holes of the corrugated pipes are checked. The horizontal joints are filled with fluid grouting materials, and the grouting material test blocks are retained. After the strength of the test blocks reaches the design requirements, the next step of construction is carried out;

[0022] F. Hoisting and placing of other O-shaped pipe sections of the mixing tower:

[0023] (1) The other O-shaped pipe sections and steel transition sections of the mixed tower are hoisted into place and operated continuously. The horizontal seams between each section are coated with epoxy resin glue and hoisted directly upward without waiting for the strength to be reached. However, a maximum of 7 sections of the mixed tower pipe section are allowed to be installed every day. After the hoisting of the first section of the mixed tower M01 is completed, the next section of the mixed tower M02 can be hoisted only after the strength of the grouting material reaches more than 25MPa after 24 hours. When the mixed tower pipe section is hoisted into place every day, the strength of the epoxy resin glue on the horizontal seam of the last section of the mixed tower pipe section of the previous day is pressure tested on the next day. Hoisting can continue after the strength reaches 35MPa. Before hoisting each section of the mixed tower, the ladder and embedded parts must be installed, and the horizontal seam of each section of the mixed tower should be kept at 10-20mm. The thickness of the base slurry, there will be 4 grooves on the top of each section of the concrete tower for leveling the top of each section of the concrete tower, and the horizontal tolerance of the 4 shims is ±0.5mm; starting from the second section M02 concrete tower pipe section, an auxiliary temporary work platform is required. During the hoisting of the concrete tower, 5 temporary work platforms are installed. During the construction process, the arm length is adjusted and the crane is used to move upward along each tower section. The same platform can be used for the installation of concrete tower sections at multiple heights; In addition to the temporary work platform, the tower concrete section is equipped with 5 permanent foundation platforms for wind turbines, which are arranged on the M05 / M10 / M17 / M22 / M28 pipe sections respectively. These platforms are installed together when the concrete tower pipe section is hoisted into place;

[0024] (2) During the hoisting of the concrete tower pipe section, before lifting the next concrete tower pipe section, check whether the sealing strip is placed along the outer circumference of the upper part of the concrete pipe section, whether the positioning guide cone / rod is threadedly connected to the correct pre-buried hanging nails, and the sealing strip of the horizontal joint is arranged along the outer circumference of the upper surface and glued to the pipe section to avoid leakage of horizontal grouting. The sealing strip is installed at the edge to ensure that the grouting width is consistent with the width of the pipe section component. The sealing strip is made of elastic foam plastic and the width of the rectangular cross-section is not more than 10mm; after the pipe section component is hoisted into place, place the positioning guide rod before hoisting the next pipe section component. The size of the positioning guide rod should be consistent with the diameter of the pre-buried corrugated pipe of the pipe segment. The diameters of the pipe sections should be matched. Before the next pipe section is hoisted, the sealing ring should be pasted to the bellows of the bottom of the upper pipe section to protect the bellows from slurry inflow. Before placing the next pipe section, a pad should be placed on the previous pipe section and leveled. At each horizontal joint, the pad should be placed in the corresponding groove of each horizontal joint. The nominal thickness / height of the horizontal joint is 10mm. The pad is made of thin steel plate to adjust the plane level and correct the centering error. The leveling work is measured with a calibrated laser level. The horizontal state of each pad is detected by a level measuring instrument. The flatness requirement is 2mm. For the horizontal reference surface, the leveling allowable deviation is ±1mm.

[0025] (3) Apply epoxy resin to the top surface of the concrete pipe section, and the next concrete tower pipe section is immediately in place. The design value of the width of the horizontal joint is 10 mm, the maximum is not more than 20 mm, and it must not be less than 10 mm. The material for filling the horizontal joint is epoxy resin;

[0026] G. Lifting of the steel transfer section into place:

[0027] When installing the steel transition section, align the flange installation center line, adjust the relatively connected flanges, tighten the fastening connection anchor bolts at each part with an electric tool first, and then use a torque wrench to tighten the anchor bolts one by one to the specified torque value according to the required torque value;

[0028] H. Mixed tower prestressed construction:

[0029] (1) After the O-shaped pipe section and steel transition section of the mixed tower are hoisted in place, post-tensioning prestressing construction is carried out. The anchoring end is located at an elevation of about 110m in the tower, and the tensioning end is located at an elevation of about -2.5m. There are a total of 40 prestressed channels inside the wall of each tower. The inner diameter of the metal corrugated pipe in each channel is 80mm, and there are 8 steel strands with a diameter of 15.2mm. The 40 prestressed channels are divided into 10 groups, with 4 channels in each group.

[0030] (2) Check the holes and seals of the prestressed holes of the permanent foundation platform and the mixed tower pipe section of the wind turbine. Insert a steel wire rope as a guide line, use a traction device to fix the steel strands, and pull the eight steel strands from bottom to top into the tower hole at the same time. Continue to pull until they are dragged to the top of the tower. During the traction process, the steel strands on the ground are placed on the winch pulley to reduce friction;

[0031] (3) Insert the prestressed steel strand bundle into the jack, keep the jack and the steel strand on the same axis, and extend the tensioning cylinder 2 to 4 cm to clamp the prestressed steel strand. During tensioning, the tensioning force line of the jack coincides with the axis of the prestressed steel strand, and the 8 steel strands in each corrugated pipe channel are tensioned at the same time; the anchor bolt tensioning is carried out after the prestressed steel strand is tensioned, and the anchor bolt tensioning control force is 1060 kN;

[0032] (4) After the prestressed steel strands are tensioned, the duct is filled with grouting material to ensure that the prestressed steel is not corroded and is integrated with the concrete tower components. The grouting work should be completed 72 hours after the tensioning is completed. The screw pump grouting machine is used for grouting. Before grouting, the screw pump is tested once. Grouting officially starts when it operates normally and can reach the required pressure. The screw pump pressure is less than 3MPa during grouting to prevent excessive pressure from causing leakage of concrete segments or local blockage. Before grouting, the duct is flushed with pressurized water. Grouting is carried out from the grouting holes at the bottom of the tower and exhaust is exhausted from the exhaust holes at the 98.5m elevation platform. After the prestressed tensioning and grouting meet the design requirements, the excess steel strands are cut with a cutting machine, the area around the concrete port is cleaned, flushed, and roughened, and the steel mesh is tied and the anchor concrete is poured.

[0033] I. Overall inspection and acceptance:

[0034] (1) When all pipe sections and steel transition sections of the concrete tower are installed and prestressed construction is completed, the tower is inspected and accepted twice to check whether the concentricity deviation, inclination, grounding system resistance, and horizontal joints meet the design requirements; the tower concentricity deviation, that is, the deviation distance between the center of the tower base and the top center of the steel transition stage in the plan view must be less than 200mm, and the eccentricity or inclination of the tower must be less than 1.667mm / m; in order to correct the tower concentricity deviation or eccentricity, the concentricity shall be measured in at least 8 stages during the hoisting of the tower pipe sections, and the deviation shall be corrected in time during the installation process; during the installation process, if the tower inclination exceeds 1mm / m, correction measures shall be taken, but inclination correction adjustment is not allowed during the installation of the top concrete tower section and steel transition stage;

[0035] (2) Acceptance of the continuity and final resistance of the tower grounding system, using two pairs of different points, two pipe sockets on the steel transfer stage and two opposite pipe sockets on the foundation. In both cases, the total measured grounding resistance must be less than 4Ω; if the actual value is greater than this limit, it is necessary to check whether all grounding devices are correctly fixed and connected in the tower concrete pipe section area.

[0036] In step H, during the production and installation of prestressed steel strands, mechanical cutting shall be adopted, and heating, welding or arc cutting shall not be allowed; during the steel strand bundle threading, plastic bending of the steel strands shall be prevented, and the bending radius during bending shall be greater than 600mm, and there shall be no twisting of the entire bundle or twisting of a single strand; during prestressing, a multi-point symmetrical equal-load uniform force tensioning method shall be adopted to control the relative deviation between the measured value and the calculated value of the elongation of the prestressed steel strand under tensioning to be no more than 6%; during the construction of prestressed duct grouting, the slurry temperature shall be between 5℃ and 35℃, and the ambient temperature shall not be lower than 5℃ during the grouting process and within 48 hours. During grouting, the slurry shall be injected from the lowest point of the prestressed duct, and the slurry in the duct shall be full and dense.

[0037] The present invention utilizes modules to prefabricate into a structure that is easy to stack, transport and install. It is divided into vertical slices and horizontal sections. Semicircular C-shaped concrete segments are prefabricated first, and then assembled into circular (O-shaped) mixed tower segments on site. The installation method of segment-by-segment hoisting, staggered installation and circumferential splicing is adopted. After installation, the entire concrete tower is in the shape of a tall truncated cone, and is formed into an integral structure with the steel transfer stage and the permanent foundation platform of the wind turbine through prestressing, becoming a stable supporting tower for the wind turbine.

[0038] The present invention prefabricates the mixed tower pipe segments and centrally assembles the mixed tower pipe sections on site, simplifies the appearance and structure of the mixed tower components, and facilitates long-distance transportation and on-site hoisting. During assembly, the vertical joints are sealed with adhesive strips and epoxy resin glue as vertical joint templates, and cement-based grouting materials are added into the gaps to ensure the quality of centralized assembly and improve assembly efficiency.

[0039] The O-shaped pipe section of the mixing tower of the present invention is transported by circulating water and installed by lifting on a vehicle plate, which reasonably matches the on-site transportation vehicles and the progress of large-scale machinery lifting, improves the utilization rate of vehicles and machinery, and can shorten the installation period of the mixing tower. The horizontal joints between the mixing tower pipe sections are sealed by the slurry method using epoxy resin glue, which greatly shortens the solidification and hardening time and has high technical and economic benefits.

[0040] The fixation of the concrete tower, the fan pedestal foundation and the steel transition section of the present invention is a cohesive prestressed system structure. Prestressed steel strands are bundled and tensioned and anchored, and the channel is grouted through the reserved prestressed channels, so that all concrete tower pipe sections, steel transition sections and the permanent foundation platform of the fan form an integral rigid support tower, thereby improving the quality, process and safety of the tower.

[0041] The wind power generation concrete tower installation construction method of the present invention is suitable for the installation construction of wind power generator towers with rigid towers or steel-concrete combined towers in land areas and with wind turbines having a height of more than 100 meters.

[0042] Compared with similar engineering methods, the present invention has a meticulous and rigorous construction plan and perfect measures. It significantly reduces the use of tower steel, increases the stability of the wind turbine tower, and adopts a rigid mixed tower steel frame, which has good durability and low maintenance cost.

[0043] The prefabricated wind power concrete tower of the present invention is multifunctional and customizable, can overcome structural limitations, reduce large size to small size, and can be designed into a form that is easy to stack, transport and install using prefabricated unit modules. It is particularly easy to transport over long distances by road, and is also beneficial for transportation within wind farms and installation of mixed towers, which can reduce the impact of large equipment transportation on society.

[0044] The excellent concrete tower prefabrication and installation technology provides better ultra-high tower technology for wind power generation, improving the power generation and operation stability of wind turbines.

[0045] The process flow includes institutionalized centralized on-site assembly, lifting into place by the mortar method, and full-process measurement and control. At the same time, prestressed tendons and tensioning are carried out on the wind turbine foundation, mixed tower pipe section, and steel transfer stage to form a stable and solid overall wind turbine tower, laying the foundation for the construction of high-quality projects.

[0046] The concrete tower tube segments are prefabricated in factories and assembled in a centralized manner to reduce pollutant emissions caused by the production of mixed towers. The establishment of a centralized assembly site can meet the requirements of all wind turbine mixed towers in the project. Compared with the individual assembly of wind turbines, it reduces the construction of hoisting platforms and temporary land acquisition, and reduces the impact on natural resources.

[0047] The first phase of the Tianmen project constructed 10 concrete towers for wind turbines, shortening the overall construction period by 20 days and reducing labor costs to: 12 people * 20 days * 0.04 yuan / day = 96,000 yuan; saving one auxiliary lifting machine, reducing machinery costs by 116,000 yuan; saving costs for assembly platform construction, temporary land acquisition, etc. (10 units * 65,000 yuan - 183,000 yuan) = 467,000 yuan. This phase of the project saved a total of 679,000 yuan.

[0048] In the second phase of the Tianmen project, the overall construction period of concrete tower installation was shortened by 18 days, and the labor cost was reduced to: 14 people * 18 days * 0.04 yuan / day = 100,800 yuan; one large lifting machine was saved, reducing the machinery fee by 280,000 yuan; the cost of assembly platform construction, temporary land acquisition, etc. was saved (10 units * 65,000 yuan) = 650,000 yuan. This project saved a total of 1,030,800 yuan.

[0049] The first phase of the CGN Tianmen 33MW distributed wind power project is the first hybrid tower wind turbine project in Hubei Province using prestressed concrete towers. It is located in Mawan Town, Tianmen City. The project scale is 10×3.3MW wind turbines. Construction started on August 20, 2021 and was completed on December 30, 2021.

[0050] The tower of this project adopts a combined structure of concrete tower and steel tower. The height of the mixed tower is 110m, with a total of 28 sections weighing about 1,340 tons. The height of the mixed tower pipe section is between 3.99m (bottom section) and 2.99m (top section). The weight of the mixed tower pipe section is between 72.68t (bottom section) and 28.75t. The outer diameter of the bottom of the M01 section (first section) is 8620mm, and the outer diameter of the top of the M27 section is 4300mm, which decreases evenly from bottom to top. The outer diameter of the top and bottom of the M28 tower is 4300mm. The length of the steel transition section is 1.2m and the weight is 8.478t. The bottom of the wind turbine concrete tower is connected to the concrete foundation with anchor plates and prestressed cables, and the top of the mixed tower is connected to the steel transition stage through prestressed cable anchors. Under the premise of ensuring quality and quantity, the first phase of the project's concrete tower was built by discussing the entire tower assembly and installation method. It adopted construction methods such as centralized assembly and flow-type circulation transportation, vehicle plate hoisting into place, and slurry sealing. The installation period of the 10 wind turbine concrete towers was shortened by 20 days, achieving good economic benefits.

[0051] The second phase of the 33MW distributed wind power project of CGN Hubei Tianmen Branch is located in Xiaoban Town, Tianmen City. The project scale is 10×3.3MW wind turbines. It continues to use prestressed concrete tower and tower structure. Construction started on October 25, 2021 and was completed on March 5, 2022.

[0052] The height of the concrete tower of this project is 110m, and 28 concrete tower pipe sections are hoisted and stacked to form an integral supporting tower structure. The concrete tower uses semicircular C-shaped pipe segments prefabricated at the production base, which are assembled and combined into O-shaped concrete tower pipe sections on site. The bottom of the wind turbine concrete tower is connected to the concrete foundation with anchor pads and prestressed cables, and the top of the concrete tower is connected to the steel transition stage through prestressed cable anchors. The prestressed steel strands are bundled and anchored, and the channel is filled with channel grouting material, so that all the O-shaped pipe sections of the concrete tower, the steel transition section and the wind turbine foundation are connected as a whole, which effectively meets the tower requirements of large wind turbines in plain areas and has good economic benefits for this project. DETAILED DESCRIPTION

[0053] The present invention will be further explained and illustrated below in conjunction with specific embodiments:

[0054] A wind power generation concrete tower installation construction method adopts a factory prefabrication and centralized assembly combination method, and specifically includes the following specific steps:

[0055] A. Construction preparation:

[0056] (1) According to the specific conditions of the wind farm site, a temporary stacking yard for the assembly of mixed tower C-type segments is established, and several assembly platforms are built. Each assembly platform is arranged with 2 groups of 8 concrete piers. The length and placement of the concrete piers can be used for the assembly of multiple different segments; the assembly yard and the machine position hoisting operation point are equipped with corresponding large-scale hoisting machinery, grouting equipment, material cutting tools, and testing tools;

[0057] (2) Equipment and materials: concrete mixed tower semi-circular C-shaped pipe segments, grouting materials, epoxy resin glue, steel strands, etc. The concrete mixed tower semi-circular C-shaped pipe segments are prefabricated and supplied by the mixed tower production base. They are equipped with reinforced steel bars and prestressed corrugated pipe channels to meet the external dimensions requirements for large-scale highway equipment transportation. They are transported to the temporary assembly site on site and assembled into O-shaped mixed tower pipe segments;

[0058] (3) Each set of concrete tower has 28 mixed tower pipe sections, the height of the mixed tower pipe section is 3.99m (bottom section) to 2.99m (top section), the weight of the mixed tower pipe section is between 72.68t (bottom section) and 28.75t, the outer diameter of the bottom of the first mixed tower pipe section is 8620mm, and it decreases evenly from bottom to top. The top and bottom outer diameters of the top mixed tower pipe section are both 4300mm;

[0059] (4) Grouting materials, epoxy resin glue, steel strands, anchors and other equipment materials shall be inspected in batches on site in accordance with the regulations and specifications and the requirements of the tower concrete manufacturer; during the construction process, grouting materials and epoxy resin glue shall be tested under the same conditions during the installation process according to the requirements of the tower concrete manufacturer, and the test blocks shall be sent to a third-party testing agency for testing to ensure compliance with the requirements;

[0060] B. Centralized assembly of mixed tower segments:

[0061] (1) Select a site with convenient transportation and suitable distance to build a temporary stacking site for concrete tower assembly, complete the stacking, assembly and installation of internal accessories of the concrete tower tube sections; the flatness of the assembled pier is 2mm, that is, the tolerance is +1mm relative to the reference surface. The flatness of the assembly platform is adjusted with 1mm and 2mm thick thin steel plates and rubber pads, and the height difference of the 8 pedestals is checked and measured to be within the required range;

[0062] (2) The unloading and assembly of the segments are handled by a crawler crane arranged in the middle of the site, equipped with a special lifting ring and a hand winch. When placing the segments on the assembly table, the center line of the O-shaped segments must be determined in advance and placed on the center line;

[0063] (3) The vertical joint reinforcement is the first step in the assembly of two semi-circular C-type segments. The threaded straight steel bars are made of the same matching material as the embedded parts during the prefabrication of the concrete C-type segment components. A certain torque of 80-120 N·m should be applied during the installation of the straight steel bars. Before the two semi-circular C-type segments are spliced, a sealing strip (circular joint template) is glued to the concrete surface of the joint groove, and only on one side of each joint. The sealing strip has a certain deformation capacity and its diameter should be greater than 20 mm (10-15 mm for the vertical joint of the assembly). After the C-type segments are initially assembled in place, the inner and outer diameters are checked. When checking the diameter of the O-type segments, cross-measurements should be made. At least two sets of data are required for the top and bottom to ensure that the assembled segments meet the design specifications.

[0064] (4) After the initial splicing is completed and passed the inspection, grouting preparation is carried out. The inner and outer gaps of the vertical joints are sealed with sealing strips and epoxy resin glue. The epoxy resin should have good adhesion (with concrete) and high initial strength. The epoxy resin glue should be applied evenly to ensure the overall aesthetics and firmness. The grouting operation starts 6 hours after the application is completed. In order to ensure that the position of the C-type segment remains unchanged during the grouting of the vertical joints and prevent cracks in the sealing material, the two assembled C-type segments are reinforced as a whole. At least 5 fastening devices are used. The upper 3 are fastening belts tightened by a tensioner, and the lower 2 are steel wire ropes tightened by a 3t hand winch. The fastening devices can be removed 6 hours after grouting.

[0065] (5) The grouting material for the vertical joints of the C-type concrete segment is cement-based. The two vertical joints of the O-type segment are grouted at the same time. The grouting material mix ratio is strictly implemented as required. The grouting is carried out slowly with a flow rate of 10-15L / min. The vertical joint grouting is 4-6 minutes until the grouting material overflows from the top of the segment joint. The vertical joint grouting material is sampled and retained to confirm the strength (the lifting strength is 25mp). At least 4 groups (40*40*160) of test blocks are retained each time. The test blocks are taken from the grouting batches of the first and last joints filled on the same day. The lifting can be carried out only 18 hours after the grouting operation is completed or the compressive strength of the grouting test blocks cured under the same conditions exceeds 25MPa;

[0066] C. Installation of mixing tower accessories:

[0067] The installation of accessories inside the concrete tower can be completed before or after assembly, and it should not affect the quality of the concrete tower assembly; the accessories include: platform support, cable clamp bracket, ladder bracket, etc., which are installed according to the embedded screw holes in the precast concrete segments;

[0068] D. On-site transportation of mixed tower pipe sections:

[0069] (1) The concrete O-type pipe sections assembled in the assembly yard need to be transported from the storage yard to each lifting machine site. In order to improve the installation efficiency, a multi-vehicle flow-type circulation transportation and direct lifting of the vehicle plate at the machine site are adopted. The vehicle transportation interval is determined in advance according to the installation time of each section of the mixed tower, and reasonable scheduling is carried out to reduce the waiting time of vehicles and large machinery and improve the operation efficiency. When transporting within the wind farm, according to the size and weight of the mixed tower section, the transportation road meets the requirements of flatness, road width, road net width, road net height, etc.;

[0070] (2) To prevent the mixing tower pipe section from being bumped, deformed or overturned during transportation, a rubber bottom pad is laid at the designated position at the bottom of the pipe section to play a shock-absorbing role, ensure that the mixing tower pipe section is stable on the vehicle, and protect the bottom from damage; after the mixing tower pipe section is stably dropped onto the vehicle, it is tied and reinforced, generally using nylon flat belt, tying wire rope, 5t hand winch and 5t shackle. One end of the hand winch is connected to the nylon flat belt, which is passed around the top of the pipe section, and the other end is connected to the shackle, which is fixed to the vehicle body. The tying should avoid the weak and vulnerable parts of the pipe section and the finished surface, and soft fabric padding should be used to prevent damage to the mixing tower section.

[0071] E. The first section of the mixed tower is hoisted into place:

[0072] (1) The hoisting of the first section of the concrete tower is the basis and key to the installation of the wind turbine tower. Before hoisting the first pipe section of the tower, confirm that the preparation work for the wind turbine foundation has been completed and meets the hoisting requirements. The control points for the handover of the wind turbine foundation are the accuracy of the size and position of the embedded corrugated pipe, embedded shim, etc., the flatness of the foundation surface, etc.;

[0073] (2) Unload the O-shaped pipe section of the mixed tower. Use a mixed tower crane and a special lifting device to directly lift the mixed tower pipe section into place, reducing temporary storage and secondary lifting in the middle. If temporary stacking is used at the machine site, try to unload it as close to the foundation as possible. Pay attention to anti-collision measures when lifting the mixed tower pipe section to protect the pipe section from damage during the lifting process. The first section of the O-shaped pipe section of the mixed tower is directly lifted into place using large lifting machinery. Generally, three positioning guide rods are used to ensure that the 40 prestressed holes of the first section of the mixed tower are correctly connected with the reserved corrugated pipe of the foundation. Check the flatness and centering, the through hole of the corrugated pipe, and the horizontal joints are filled with fluid grouting material. Take the grouting material test block. The test block strength reaches the design requirements of the mixed tower (about 24 hours) before the next step of construction can be carried out;

[0074] F. Hoisting and placing of other O-shaped pipe sections of the mixing tower:

[0075] (1) The other O-shaped pipe sections of the mixed tower are hoisted into place in a continuous operation. The horizontal seams between each section are coated with epoxy resin glue and hoisted directly upward without waiting for the strength to be reached. However, a maximum of 7 sections of the mixed tower section are allowed to be installed every day. After the hoisting of the first section of the mixed tower M01 is completed, it is necessary to wait for 24 hours for the grouting material strength to reach more than 25MPa before the hoisting of the next section of the mixed tower M02 can be carried out. Every day when the mixed tower section is hoisted into place, the strength of the epoxy resin glue of the horizontal seam of the last section of the mixed tower section of the previous day must be pressure tested on the next day. Only when the strength reaches 35MPa can the hoisting be continued. Before hoisting each section of the mixed tower, the ladder and embedded parts must be installed. The horizontal seam of each section of the mixed tower should maintain a slurry thickness of 10-20mm. There will be 4 grooves on the top of each section of the mixed tower for leveling the top of each section of the mixed tower. The level of the 4 shims The allowable error is ±0.5mm; starting from the second section M02 mixed tower pipe section, an auxiliary temporary work platform is required. During the hoisting of the concrete tower, 5 work platforms are temporarily installed. During the construction process, the arm length is adjusted and the crane can be moved upward along each tower section. The same platform can be used for the installation of mixed tower sections at multiple heights. Proper adjustment of the arm length is crucial to the platform load and personnel safety. To support the temporary platform, the concrete pipe segment must be equipped with embedded angle supports where the platform arm is located; after the temporary platform is installed and before bearing load, it must be inspected and load tested, and can only be used after acceptance; in addition to the temporary work platform, the tower concrete section has 5 permanent platforms, which are arranged in the M05 / M10 / M17 / M22 / M28 pipe sections respectively. These platforms are installed together when the concrete tower pipe section is hoisted into place;

[0076] (2) During the hoisting of the concrete tower pipe section, before hoisting the next concrete tower pipe section, it is necessary to check whether the sealing strip is placed along the outer circumference of the upper part of the concrete pipe section and whether the positioning guide cone / rod is threadedly connected to the correct pre-buried hanging nails; the sealing strip of the horizontal joint can be installed before the hoisting of the concrete tower pipe section, or it can be installed at high altitude after it is in place. The sealing strip is arranged along the outer circumference of the upper surface and glued to the pipe section to avoid leakage of the horizontal surface mortar. The sealing strip is installed at the edge to ensure that the mortar width is consistent with the width of the pipe section component; the sealing strip is made of elastic foam plastic (it is strictly forbidden to use any wood, steel or other rigid materials), and the width of the rectangular cross-section is not more than 10mm. After the pipe section component is hoisted in place, before hoisting the next pipe section component, the positioning guide cone / rod is placed. It is generally made of plastic (such as polyvinyl chloride, high-density polyethylene), steel or other strong and durable materials. The size of the positioning guide rod is based on the diameter of the pre-buried corrugated pipe of the pipe segment; Before the next pipe segment is hoisted, the sealing ring is pasted to the bellows of the bottom of the upper pipe segment to protect the bellows from slurry inflow; before placing the next pipe segment on the tower, a pad must be placed on the previous pipe segment and leveled. At each horizontal joint, the pad is placed in the corresponding groove or pad contour mark of each horizontal joint. The plane size of the groove depends on the specific component (the heavier the component, the larger the groove size). The pad contour is the area marked by the marker pen on the top surface of the pipe segment. The nominal thickness / height of the horizontal joint is 10mm. The pad is made of thin steel plate to adjust the plane level and correct the centering error. The leveling work is measured with a calibrated laser level. The horizontal state of each pad is detected by a level measuring instrument; in order to evaluate the actual level error of each horizontal joint, the level surface of the upper surface of the component is detected before placing the pad. The flatness requirement is 2mm, that is, for the horizontal reference surface, the leveling allowable deviation is ±1mm;

[0077] (3) Hoisting and grouting of concrete tower pipe sections: First, apply epoxy resin to the top surface of the concrete pipe section (already in place), and then the next concrete tower pipe section should be put in place immediately; to ensure that the horizontal joints are filled densely, check whether the thickness of the grouting layer meets the requirements (generally 10-20mm), there are no gaps / voids (especially around the corrugated pipe and pads), and the top surface of each pad is clean (no grouting and debris); if the concrete pipe section is hoisted to about 50cm above the tower, When placing, the staff should enter the temporary working platform and ensure that the pipe section component is correctly positioned in the air, check the position of the internal accessories (especially the ladder) and the positioning guide cone / rod (the corresponding groove of the raised module should be assembled), and use ropes and other tools to rotate the mixing tower pipe section around its vertical axis to correctly position the pipe section; then slowly lower the raised pipe section and use the positioning guide cone / rod to guide it to the correct final position; when the pipe section component has been placed, carefully check the gap, especially in the area near the corrugated pipe. If any looseness is found, use a trowel to remove excess material from the joint surface and refill the gap to make the joint surface smooth and uniform; visually check the misalignment of the top component relative to the bottom component. The vertical surface is continuous and uniform, and only slight protrusions (about 5mm) are allowed. The width of the horizontal seam is designed to be 10mm. The maximum shall not exceed 20mm, and shall not be less than 10mm; before the horizontal joint is slurried, first ensure that the pad is correctly leveled (it shall not be moved after leveling), and the auxiliary components (i.e. sealing strips and guide cones) have been installed. The material for filling the horizontal joint is epoxy resin. The tightness of the pipe segment slurry is the focus of construction. The time interval between stirring the slurry and placing the next pipe segment on the top is less than 25 minutes. In order to achieve uniform and correct slurry, the requirements of the material instructions shall be met when stirring the slurry, and attention shall be paid to the ingredients, water, ambient temperature, material temperature, tools and mixing time of the constituent materials; after the slurry is properly stirred, it shall be immediately applied to the top of the surface of the concrete pipe segment in place with a trowel. The slurry should be slightly excessive, about 5-10mm higher than the pad, but not covering the pad, so that the concrete tower pipe segment ready to be in place can directly contact the surface of the steel pad, and the grouting can overflow inward to ensure that the entire horizontal joint is filled;

[0078] G. Lifting of the steel transfer section into place:

[0079] When installing the steel transition section, align the flange installation center line, adjust the relatively connected flanges, tighten the fastening anchor bolts at each part with an electric tool, and then use a torque wrench to tighten the anchor bolts one by one to the specified torque value according to the required torque value. Perform a 100% inspection on the anchor bolts. After each inspection, mark the anchor bolt with a marker pen, and mark to the edge of the flange plane;

[0080] H. Tower pre-tensioning stress construction:

[0081] (1) After the O-shaped pipe section and the steel transition section of the mixed tower are hoisted in place, the post-tensioning prestressing construction is immediately carried out, including steel strand threading, prestressing tensioning, anchor sealing, prestressing channel grouting, etc. The anchoring end is located at an elevation of about 110m in the tower, and the tensioning end is located at an elevation of about -2.5m (inside the foundation cavity). There are a total of 40 prestressed channels inside the wall of each tower. The inner diameter of the metal corrugated pipe in each channel is 80mm, and there are 8 steel strands with a diameter of 15.2mm. The 40 prestressed channels are divided into 10 groups, with 4 channels in each group;

[0082] (2) Check the prestressed holes of the foundation and M01-M28 mixed tower sections for through-holes and sealing. Insert a steel wire rope as a guide line and use a traction device to fix the steel strands. The steel wire rope pulls the eight steel strands from bottom to top into the tower tube holes at the same time. Continue pulling until they are dragged to the top of the tower. During the pulling process, the steel strands on the ground are placed on the winch pulley to reduce friction.

[0083] (3) Insert the prestressed steel strand bundle into the jack and align it with the anchor plate ring, keeping the jack and the steel strand on the same axis; extend the tensioning cylinder by 2-4 cm to clamp the prestressed steel strand; prestressing can only be carried out when the concrete tower and horizontal joint mortar reach the design strength. During tensioning, strictly follow the design value and operating specifications. During tensioning, the tensioning force line of the jack coincides with the axis of the prestressed steel strand; tensioning procedure: 0→initial stress→2 times initial stress→σcon (hold load for 2-5 minutes for anchoring), tensioning to initial stress When the stress reaches the design value, the line is drawn to mark the measured elongation value, and the single-end jack is used to lift and lower the pressure, draw the line, measure the elongation, insert the pad and other work at the same time; when the stress reaches the design value, and the error between the actual elongation value and the theoretical elongation value is within the design range (not more than 6%), the original record of on-site tensioning is made, and the 8 steel strands in each corrugated pipe channel are tensioned at the same time; the steel strands in the channels on both sides of the tower are tensioned at the same time or alternately to ensure the uniformity of the tower's stress. The anchor bolt tensioning is carried out after the prestressed steel strand is tensioned. The anchor bolt tensioning control force is 1060kN, and over-tensioning is strictly prohibited;

[0084] (4) After the prestressed steel strands are tensioned, the grouting material is filled into the hole to ensure that the prestressed steel is not corroded and is integrated with the concrete tower components. The grouting work should be completed 72 hours after the tensioning is completed. The screw pump grouting machine is used for grouting. Before grouting, the screw pump is tested once. When it operates normally and can reach the required pressure, the grouting is officially started. During grouting, the screw pump pressure is less than 3MPa to prevent excessive pressure from causing leakage of concrete segments or local blockage of holes. Before grouting, the hole is flushed with pressurized water. Grouting is carried out from the grouting hole at the bottom of the tower. Exhaust air from the exhaust hole at the 8.5m elevation platform; when the exhaust hole at the top of the tower member discharges air-water-thin slurry-thick slurry, plug it with a wooden plug and increase the pressure of the grouting machine slightly. When the pressure reaches the appropriate level and stabilizes for 2 minutes, pull out the nozzle from the grouting hole and plug it with a wooden plug immediately; when the prestressing and grouting meet the design requirements, cut the excess steel strands with a cutting machine, clean and rinse the area around the concrete port, and chisel it. According to the design requirements, set the steel mesh and pour the anchor concrete. The anchor concrete meets the construction design and construction specifications;

[0085] I. Overall inspection and acceptance:

[0086] (1) After all pipe sections and steel transition sections of the concrete tower are installed and prestressed construction is completed, the tower must be inspected and accepted twice. The inspection items include: concentricity deviation, inclination, grounding system resistance, horizontal joints, etc. The tower concentricity deviation, that is, the deviation distance between the center of the tower base and the top center of the steel transition stage in the plan view is less than 200mm, and the eccentricity or inclination of the tower is less than 1.667mm / m. In order to correct the tower concentricity deviation or eccentricity, the concentricity should be measured in at least 8 stages during the hoisting of the tower pipe section. Generally, the tower centering verification is carried out once a day during the installation, and the deviation is corrected in time during the installation process. During the installation process, if the tower inclination exceeds 1mm / m, corrective measures must be taken immediately, but the inclination correction adjustment is not allowed during the installation of the top concrete tower section and the steel transition stage.

[0087] (2) The continuity and final resistance of the tower grounding system are the main control items for tower acceptance; the measured resistance verification should be carried out twice, using two different pairs of points, namely the two pipe seats of the steel transfer stage and the two opposite pipe seats on the foundation. In both cases, the total measured grounding resistance should be less than 4Ω. If the actual value is greater than this limit, check whether all grounding devices are properly fixed and connected in the tower concrete pipe section area.

[0088] In the present invention, the flatness of the assembled pier is 2mm, that is, the tolerance is +1mm relative to the reference surface. When the vertical joint width is ≤50mm, the vertical joint grouting adopts the pressure grouting process, and the slurry is injected from the bottom grouting pipe until the slurry emerges from the top of the vertical joint and the slurry is stably discharged. The vertical joint grouting operation of the same combined pipe segment is carried out synchronously, and the grouting speed and temperature are monitored in real time to ensure that the grouting pressure of all vertical joints is balanced.

[0089] In the present invention, before the concrete tower tube section is hoisted into place, it is confirmed that the strength of the foundation concrete meets the design requirements, and the flatness of the foundation top surface, the horizontality of the shim, the center of the foundation, and the position of the prestressed channel are re-measured; the coaxiality of each section of the mixed tower tube segment is measured, and the center of the foundation or the first section is used as a reference point for the subsequent inspection of the tower center offset, and its error should meet the design requirements; when each section of the mixed tower tube segment is hoisted into place, it is leveled, and the horizontality error meets the design requirements; the horizontal seam sealing adhesive material uses epoxy resin glue, the construction and hoisting are carried out simultaneously, and the gap of the horizontal joint meets the design requirements; before each section of the mixed tower tube segment is hoisted and put into place, the patency of the prestressed channel of the mixed tower tube section must be checked.

[0090] Performance requirements of epoxy resin adhesive for horizontal joints of mixed towers

[0091]

[0092] In the present invention, during the manufacture and installation of the prestressed steel strands, heating, welding or arc cutting are prohibited, and mechanical cutting is adopted; during the steel strands being threaded through the bundle, plastic bending of the steel strands is prevented, the bending radius during bending is greater than 600mm, and there is no twisting of the entire bundle or twisting of a single strand; during prestressing, the compressive strength of the concrete meets the design requirements; during tensioning, a multi-point symmetrical equal-load uniform force tensioning method is adopted, and the relative deviation between the measured value and the calculated value of the elongation of the prestressed steel strands under tensioning is controlled to be no more than 6%.

[0093] In the present invention, the performance indicators of the prestressed channel cement-based grouting material meet the requirements of the technical standards. During the prestressed channel grouting construction, the slurry temperature is preferably between 5°C and 35°C. During the grouting process and within 48 hours, the ambient temperature is not lower than 5°C. During grouting, the slurry is injected from the lowest point of the prestressed channel, and the slurry in the channel is full and dense.

[0094] Performance requirements of cement-based grouting materials for prestressed ducts in mixed towers

[0095]

[0096] In the present invention, after the hoisting of the first section M01 of the mixed tower is completed, it is necessary to wait for 24 hours and the strength of the grouting material reaches more than 25MPa before the next hoisting work can be carried out; the horizontal seams between the mixed tower pipe sections are covered with epoxy resin glue, and they can be directly hoisted without waiting for the strength, but a maximum of 7 sections can be hoisted per day, and the compressive strength test of the epoxy resin glue strength of the horizontal seams of the last section of the tower tube on the previous day must be carried out on the next day, and the hoisting can continue only when the strength reaches 35MPa.

Claims

1. A wind power generation concrete tower installation construction method, which adopts a factory prefabrication and centralized assembly combination method, characterized in that: The specific steps include: A. Prefabricated semicircular C-shaped concrete tower tube segments; (1) For ultra-high concrete towers, modules are customized with horizontal segments and vertical slices. Each set of concrete towers has 28 mixed tower pipe sections, with a height of 2.99m to 3.99m, 3.99m at the bottom section, 2.99m at the top section, and gradually increasing in the middle section. The weight of the mixed tower pipe section is 28.75t to 72.68t, with the bottom section being 72.68t. The bottom outer diameter of the bottom mixed tower pipe section is 8620mm, which decreases evenly from bottom to top. The top and bottom outer diameters of the top mixed tower pipe section are both 4300mm. (2) Two semi-circular C-shaped segments are prefabricated in each mixed tower pipe section, and the two semi-circular C-shaped segments are assembled into an O-shaped mixed tower pipe section, which is equipped with reinforced steel bars and prestressed corrugated pipe channels; B. Centralized assembly of mixed tower segments: (1) Establish a temporary stacking yard for the assembly of the semi-circular C-shaped segments of the mixed tower, build several assembly platforms, and complete the stacking, assembly, and installation of internal accessories of the concrete tower tube segments; each assembly platform is arranged with 2 groups of 8 concrete piers, the flatness of the concrete piers is 2mm, and the tolerance is +1mm relative to the reference surface. The flatness of the assembly platform is adjusted with 1mm and 2mm thick thin steel plates and rubber pads; (2) Two semicircular C-shaped segments are assembled into an O-shaped segment. Before the two semicircular C-shaped segments are assembled, a circular joint template sealing strip is glued to the concrete surface of the joint groove. The diameter of the sealing strip is greater than 20 mm, and the vertical joint of the assembly is 10 to 15 mm. (3) The inner and outer gaps of the vertical joints are sealed with sealing strips and epoxy resin glue. Grouting work begins 6 hours after the grouting is completed. To ensure that the position of the semi-circular C-shaped segments remains unchanged during the grouting of the vertical joints and to prevent cracks in the sealing materials, the two semi-circular C-shaped segments are reinforced as a whole. Five fastening devices are used. The upper three are fastening belts tightened by a tensioner, and the lower two are steel wire ropes tightened by a 3t hand winch. The fastening devices are removed 6 hours after grouting. (4) The grouting material for the vertical joints of the semi-circular C-type concrete segments is cement-based. The two vertical joints of the O-type segments are grouted simultaneously. The grouting flow rate is 10-15 L / min. The vertical joint grouting is 4-6 minutes, until the grouting material overflows from the top of the segment joint. The vertical joint grouting material is sampled and retained to confirm that the lifting strength is 25 MPa. More than 4 groups of test blocks are retained each time. The test block size is 40mm*40mm*160mm. The test blocks are taken from the grouting batches of the first and last joints filled on the same day. The lifting can only be carried out 18 hours after the grouting operation is completed or when the compressive strength of the grouting test blocks cured under the same conditions exceeds 25 MPa. C. Installation of accessories in the mixing tower segment: The installation of accessories inside the concrete tower segment can be completed before or after assembly. The accessories include platform support, cable clamp bracket, ladder bracket, which are installed according to the embedded screw holes in the precast concrete segment. D. On-site transportation of mixed tower pipe sections: (1) The O-shaped concrete pipe sections assembled in a centralized manner need to be transported from the storage yard to each lifting machine site. In order to improve the installation efficiency, a multi-vehicle flow-type circulation transportation and direct lifting of the vehicle plate at the machine site are adopted. The vehicle model and transportation interval time are determined in advance according to the overall size and weight of the concrete tower section; (2) Rubber bottom pads are laid at the location of the mixing tower pipe section to play a shock-absorbing role, prevent the mixing tower pipe section from being bumped, deformed, or overturned during transportation, ensure that the mixing tower pipe section is stable on the vehicle, and protect the bottom from damage; after the mixing tower pipe section is stably dropped onto the vehicle, it is tied and reinforced with nylon flat belts, tying wire ropes, 5t hand winches, and 5t shackles. One end of the hand winch is connected to the nylon flat belt, which is passed over the top of the pipe section, and the other end is connected to the shackle, which is fixed to the vehicle body; E. The first section of the mixed tower is hoisted into place: The hoisting of the first O-shaped pipe section of the concrete tower is the basis and key to the installation of the fan tower. It is directly hoisted into place by large lifting machinery. Three positioning guide rods are used to ensure that the 40 prestressed holes of the first section of the tower are correctly connected with the reserved corrugated pipes of the foundation. The flatness and centering degree, the through holes of the corrugated pipes, the horizontal joints are filled with fluid grouting materials, and the grouting material test blocks are retained; F. Hoisting and placing of other O-shaped pipe sections of the mixing tower: (1) The other O-shaped pipe sections and steel transition sections of the mixed tower are hoisted into place and operated continuously. Epoxy resin glue is applied to the horizontal joints between each section. However, a maximum of 7 sections of mixed tower sections are allowed to be installed every day. After the hoisting of the first section of the mixed tower M01 is completed, the next section of the mixed tower M02 can be hoisted only after the strength of the grouting material reaches more than 25MPa after 24 hours. When the mixed tower sections are hoisted into place every day, the strength of the epoxy resin glue on the horizontal joints of the last section of the mixed tower section of the previous day is pressure tested on the next day. Hoisting can continue after the strength reaches 35MPa. Before hoisting each section of the mixed tower, the ladder and embedded parts must be installed. The horizontal joints of each section of the mixed tower should maintain a grouting thickness of 10-20mm. There will be 4 grooves on the top of the mixed tower for leveling each section of the mixed tower. The horizontal tolerance of the 4 shims is ±0.5mm. Starting from the second section M02 mixed tower pipe section, an auxiliary temporary work platform is required. During the hoisting of the concrete tower, 5 temporary work platforms are installed. During the construction process, the arm length is adjusted and the crane is used to move upward along each tower section. The same platform can be used for the installation of mixed tower sections at multiple heights. In addition to the temporary work platform, the tower concrete section is equipped with 5 permanent foundation platforms for wind turbines, which are arranged on the M05 / M10 / M17 / M22 / M28 pipe sections respectively. These platforms are installed together when the concrete tower pipe section is hoisted into place. (2) During the hoisting of the concrete tower pipe section, before lifting the next concrete tower pipe section, check whether the sealing strip is placed along the outer circumference of the upper part of the concrete pipe section, whether the positioning guide cone / rod is threadedly connected to the correct pre-buried hanging nails, and the sealing strip of the horizontal joint is arranged along the outer circumference of the upper surface and glued to the pipe section to avoid leakage of horizontal grouting. The sealing strip is installed at the edge to ensure that the grouting width is consistent with the width of the pipe section component. The sealing strip is made of elastic foam plastic and the width of the rectangular cross-section is not more than 10mm; after the pipe section component is hoisted into place, place the positioning guide rod before hoisting the next pipe section component. The size of the positioning guide rod should be consistent with the diameter of the pre-buried corrugated pipe of the pipe segment. The diameters of the pipe sections should be matched. Before the next pipe section is hoisted, the sealing ring should be pasted to the bellows of the bottom of the upper pipe section to protect the bellows from slurry inflow. Before placing the next pipe section, a pad should be placed on the previous pipe section and leveled. At each horizontal joint, the pad should be placed in the corresponding groove of each horizontal joint. The nominal thickness / height of the horizontal joint is 10mm. The pad is made of thin steel plate to adjust the plane level and correct the centering error. The leveling work is measured with a calibrated laser level. The horizontal state of each pad is detected by a level measuring instrument. The flatness requirement is 2mm. For the horizontal reference surface, the leveling allowable deviation is ±1mm. (3) Apply epoxy resin to the top surface of the concrete pipe section, and the next concrete tower pipe section is immediately in place. The design value of the width of the horizontal joint is 10 mm, the maximum is not more than 20 mm, and it must not be less than 10 mm. The material for filling the horizontal joint is epoxy resin; G. Lifting of the steel transfer section into place: When installing the steel transition section, align the flange installation center line, adjust the relatively connected flanges, tighten the fastening connection anchor bolts at each part with an electric tool first, and then use a torque wrench to tighten the anchor bolts one by one to the specified torque value according to the required torque value; H. Mixed tower prestressed construction: (1) After the O-shaped pipe section and steel transition section of the mixed tower are hoisted in place, post-tensioning prestressing construction is carried out. The anchoring end is located at the 110m elevation of the tower, and the tensioning end is located at the -2.5m elevation. There are a total of 40 prestressed channels inside the wall of each tower. The inner diameter of the metal corrugated pipe in each channel is 80mm, and there are 8 steel strands with a diameter of 15.2mm. The 40 prestressed channels are divided into 10 groups, with 4 channels in each group. (2) Check the holes and seals of the prestressed holes of the permanent foundation platform and the mixed tower pipe section of the wind turbine. Insert a steel wire rope as a guide line, use a traction device to fix the steel strands, and pull the eight steel strands from bottom to top into the tower hole at the same time. Continue to pull until they are dragged to the top of the tower. During the traction process, the steel strands on the ground are placed on the winch pulley to reduce friction; (3) Insert the prestressed steel strand bundle into the jack, keep the jack and the steel strand on the same axis, and extend the tensioning cylinder 2 to 4 cm to clamp the prestressed steel strand. During tensioning, the tensioning force line of the jack coincides with the axis of the prestressed steel strand, and the 8 steel strands in each corrugated pipe channel are tensioned at the same time; the anchor bolt tensioning is carried out after the prestressed steel strand is tensioned, and the anchor bolt tensioning control force is 1060 kN; (4) After the prestressed steel strands are tensioned, the duct is filled with grouting material to ensure that the prestressed steel is not corroded and is integrated with the concrete tower components. The grouting work should be completed 72 hours after the tensioning is completed. The screw pump grouting machine is used for grouting. Before grouting, the screw pump is tested once. Grouting officially starts when it operates normally and can reach the required pressure. The screw pump pressure is less than 3MPa during grouting to prevent excessive pressure from causing leakage of concrete segments or local blockage. Before grouting, the duct is flushed with pressurized water. Grouting is carried out from the grouting holes at the bottom of the tower and exhaust is exhausted from the exhaust holes at the 98.5m elevation platform. After the prestressed tensioning and grouting meet the design requirements, the excess steel strands are cut with a cutting machine, the area around the concrete port is cleaned, flushed, and roughened, and the steel mesh is tied and the anchor concrete is poured. I. Overall inspection and acceptance: (1) When all pipe sections and steel transition sections of the concrete tower are installed and prestressed construction is completed, the tower is inspected and accepted twice to check whether the concentricity deviation, inclination, grounding system resistance, and horizontal joints meet the design requirements; the tower concentricity deviation, that is, the deviation distance between the center of the tower base and the top center of the steel transition stage in the plan view must be less than 200mm, and the eccentricity or inclination of the tower must be less than 1.667mm / m; in order to correct the tower concentricity deviation or eccentricity, the concentricity shall be measured in at least 8 stages during the hoisting of the tower pipe sections, and the deviation shall be corrected in time during the installation process; during the installation process, if the tower inclination exceeds 1mm / m, correction measures shall be taken, but inclination correction adjustment is not allowed during the installation of the top concrete tower section and steel transition stage; (2) Acceptance of the continuity and final resistance of the tower grounding system, using two pairs of different points, two pipe sockets on the steel transfer stage and two opposite pipe sockets on the foundation. In both cases, the total measured grounding resistance must be less than 4Ω; if the actual value is greater than this limit, it is necessary to check whether all grounding devices are correctly fixed and connected in the tower concrete pipe section area.

2. The wind power generation concrete tower installation construction method according to claim 1 is characterized in that: In step H, during the production and installation of prestressed steel strands, mechanical cutting shall be adopted, and heating, welding or arc cutting shall not be allowed; during the steel strand bundle threading, plastic bending of the steel strands shall be prevented, and the bending radius during bending shall be greater than 600mm, and there shall be no twisting of the entire bundle or twisting of a single strand; during prestressing, a multi-point symmetrical equal-load uniform force tensioning method shall be adopted to control the relative deviation between the measured value and the calculated value of the elongation of the prestressed steel strand under tensioning to be no more than 6%; during the construction of prestressed duct grouting, the slurry temperature shall be between 5℃ and 35℃, and the ambient temperature shall not be lower than 5℃ during the grouting process and within 48 hours. During grouting, the slurry shall be injected from the lowest point of the prestressed duct, and the slurry in the duct shall be full and dense.

Citation Information

Patent Citations

  • Construction method applied to split installation of offshore wind power generators

    CN107218179A

  • Grouting-free dry-type prestressed bolt splicing segmentation prefabricated assembly type mixed tower

    CN112096573A

  • Prestress hollow interlayer concrete filled steel tube lattice type mixing tower and production and installation method thereof

    CN112177857A