A safe lifting control system for disassembling and assembling device of tunnel boring machine
By adopting a flexible tilt lifting system with 4-cylinder synchronous hydraulic hoisting device and multi-PLC controller in the tunnel boring machine lifting device, the safety hazards and unstable problems in the lifting process in the prior art are solved, and safer and more stable are achieved lifting process.
Patent Information
- Application Number
- CN202211101066.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-09-09
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2042-09-09
AI Technical Summary
The existing tunnel boring machine hoisting device has safety hazards during the lifting process. The rigid dragging method may cause damage to the lifting equipment and the boring machine, and the initial tension is too large, resulting in unstable lifting.
Design a safe lifting control system including lifting module and control module, adopts a 4-cylinder synchronous hydraulic hoisting device and multiple PLC controllers, and realizes flexible tilt lifting through deflection hook, inclination sensor, tension sensor and displacement sensor to share the hoist Initial force is applied, and the lifting status is monitored and adjusted in real time through the wireless communication module.
It improves the safety and stability of the lifting process, reduces the risk of damage to the lifting equipment, and ensures the safety of the operators.
Smart Images

Figure CN115448169B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of tunnel boring machine hoisting, and in particular to a safe hoisting control system for a disassembling and assembling device of a tunnel boring machine. Background Art
[0002] When the disassembly and assembly device of the tunnel boring machine is used to hoist the main machine of the tunnel boring machine, the hoisting process is relatively complicated and unsafe. The existing hoisting equipment is all single hoisting equipment. When hoisting, the main machine of the tunnel boring machine is directly hoisted by the upward pulling force of the hoisting equipment. The traction force required for the equipment is too large. This rigid dragging hoisting method may cause damage to the hoisting equipment and the tunnel boring machine. For example, the publication number CN109205475A, "Tunnel truss-connected beam-type gantry machine assembly and disassembly device and method, improves the stability of equipment hoisting", but this scheme is rigid traction, and a large pull is required to lift the hoisted equipment during operation. For example, the publication number CN207451463U, "A gantry hoisting device for dismantling a hard rock tunnel boring machine in the tunnel", also requires a large traction force from the winch to lift the hoisted equipment. The rigid hoisting method may cause damage to the hoisting equipment and the tunnel boring machine. The tunnel boring machine is extremely heavy and there are safety hazards.
[0003] Therefore, a flexible lifting device is urgently needed to reduce the initial pulling force of the winch during lifting, so as to make the lifting process more stable and safe. Summary of the invention
[0004] In order to solve the problem of potential safety hazards in the lifting process of the existing lifting equipment for the main engine of a tunnel boring machine, the present invention provides a safe lifting control system for the disassembly and assembly device of a tunnel boring machine. A 4-cylinder synchronous hydraulic jacking device is arranged to share the force of the winch at the initial stage, and two beams are kept at a constant height to realize flexible inclined lifting, thereby improving the safety of lifting.
[0005] In order to achieve the above object, the technical solution of the present invention is:
[0006] A safe lifting control system for a disassembling and assembling device of a tunnel boring machine, comprising a lifting module and a control module, wherein the lifting module comprises a crossbeam, two lifting frames, a winch, a steel wire rope and a moving trolley, wherein the winch is fixed to the moving trolley, and the moving trolley is slidably connected to the crossbeam, wherein the lifting frame and the crossbeam are combined to form a gate-shaped structure, wherein there are two lifting modules, and the lifting module further comprises a walking mechanism and a walking track, wherein the walking mechanism is fixed to the lower end of the lifting frame and is slidably connected to the walking track;
[0007] The winch is provided with a deflection hook, the winch is fixed to the wire rope through the deflection hook, the deflection hook is provided with an inclination sensor and a tension sensor, the winch is provided with an eccentric load sensor, and a displacement sensor is provided near the upper ends of the two lifting frames;
[0008] The lifting frame includes a 4-cylinder synchronous hydraulic jacking device, the lower part of which is vertically fixed to the walking mechanism, the upper part of which is vertically fixed to the crossbeam, and the lower end of which is provided with a pressure sensor;
[0009] The control module includes two first PLC controllers, three second PLC controllers and one third PLC controller, the analog input ends of the two first PLC controllers are connected to an inclination sensor, a tension sensor, an eccentric load sensor and a displacement sensor, and the first PLC controller is used to control the winch and the mobile trolley;
[0010] The three second PLC controllers and the third PLC
[0011] The analog input terminals of the controller are all connected to pressure sensors, and the second PLC controller and the third PLC controller are used to control the traveling mechanism and the 4-cylinder synchronous hydraulic jacking device;
[0012] The third PLC controller is also connected to a host computer. A wireless communication module is provided between the first PLC controller, the second PLC controller and the third PLC controller. The first PLC controller, the second PLC controller and the third PLC controller are communicatively connected via the wireless communication module.
[0013] A 4-cylinder synchronous hydraulic jacking device is set up to adjust the height of the beam. At the same time, a winch is added to realize the flipping and lifting of the tunnel boring machine. Six PLC controllers and inclination sensors, tension sensors, eccentric load sensors, displacement sensors and pressure sensors are set up to monitor the lifting status of the lifting equipment and the tunnel boring machine, so that the lifting speed and force are always in the appropriate range, realizing flexible inclined lifting, thereby improving the safety of lifting.
[0014] Furthermore, the crossbeam is a concave-shaped structure, and rails are arranged on both sides of the crossbeam. The mobile trolley includes a first motor and a vehicle body guide wheel, the vehicle body guide wheel bites the rails, the vehicle body guide wheel is rotationally connected to the first motor, a frequency converter is arranged between the first motor and the first PLC controller, and the first motor is connected to the power supply through the frequency converter to form a loop;
[0015] The winch includes a second motor and a take-up shaft, the second motor is used to drive the take-up shaft to take up and release the wire, the second motor is connected to the first PLC controller through the frequency converter, and the second motor is connected to the power supply through the frequency converter to form a loop.
[0016] Furthermore, the take-up shaft is connected to a suspension rod via a steel wire rope, the eccentric load sensor is arranged in the middle of the suspension rod, and the eccentric load sensor includes a horizontal sensor;
[0017] The lower middle end of the suspension rod is rotatably connected to the deflection hook, and the inclination sensor is used to detect the pitch angle of the deflection hook;
[0018] The pressure sensor is used to detect the tension value of a single deflection hook.
[0019] Two inclination sensors are set to measure the inclination of the two steel ropes with the vertical angle, and the operation of the walking mechanism and the 4-cylinder synchronous hydraulic jacking device is coordinated according to the size of the inclination angle.
[0020] Furthermore, the 4-cylinder synchronous hydraulic jacking device is provided with a base, and the base is arranged between the 4-cylinder synchronous hydraulic jacking device and the walking mechanism. The two 4-cylinder synchronous hydraulic jacking devices are symmetrically arranged at both ends of the base. The 4-cylinder synchronous hydraulic jacking device includes an electric hydraulic valve, and the coil of the electric hydraulic valve is electrically connected to the output end of the second PLC controller or the third PLC controller.
[0021] The tension sensor detects the tension on the wire rope, the pressure sensor monitors the pressure of the 4-cylinder synchronous hydraulic jacking device, the eccentric load sensor detects the vertical angle between the beam and the boom, and the displacement sensor monitors the lifting height. The detection parameters are transmitted to the third PLC through the wireless communication module, which is convenient for the operator to understand the lifting situation in time through the host computer.
[0022] Further, the walking mechanism includes a load-bearing part, a third motor and a driving wheel, the driving wheel is arranged at the lower end of the load-bearing part, the driving wheel is connected by a connecting rod, the connecting rod is connected to the output shaft of the third motor through a synchronous belt, the connecting rod is fixed to the load-bearing part through a bearing, the outer ring surface of the bearing is fixed to the load-bearing part, and the inner ring surface is fixed to the connecting rod;
[0023] A second frequency converter is arranged between the third motor and the PLC controller, and the third motor is connected to the power supply through the second frequency converter to form a loop.
[0024] Furthermore, the wireless communication module includes a MOXA Client wireless remote kit, and the host computer includes a wireless remote controller and a PC.
[0025] Through the above technical solution, the beneficial effects of the present invention are:
[0026] 1. The present invention sets two lifting modules which are respectively connected to the lifting points at the upper and lower ends of the tunnel boring machine. Four 4-cylinder synchronous hydraulic lifting devices are arranged on both sides of the tunnel boring machine. Two of them are first raised to tighten the wire rope, and then the winch also works. One side of the tunnel boring machine is lifted and the other side touches the ground. The wire rope at the other end is in a relaxed state. During this process, the walking mechanism provides displacement for the 4-cylinder synchronous hydraulic lifting device to ensure that the wire rope can be vertically stressed during the lifting process. The tunnel boring machine is tilted and lifted until the wire ropes of the two lifting modules are in a taut state, indicating that the tunnel boring machine is lifted. The stability and safety of the lifting process are improved.
[0027] 2. The present invention is equipped with 6 PLC controllers and inclination sensors, tension sensors, eccentric load sensors, displacement sensors and pressure sensors to monitor the lifting process, thereby improving operational safety and providing data reference for construction workers. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Figure 1 This is one of the structural schematic diagrams of a safe lifting control system for a disassembly and assembly device of a tunnel boring machine according to the present invention;
[0029] Figure 2 This is the second structural schematic diagram of a safe lifting control system for a disassembly and assembly device of a tunnel boring machine according to the present invention;
[0030] Figure 3 This is one of the electrical schematic diagrams of a safe lifting control system for a disassembly and assembly device of a tunnel boring machine according to the present invention;
[0031] Figure 4 This is the second electrical schematic diagram of a safe lifting control system for a disassembly and assembly device of a tunnel boring machine according to the present invention;
[0032] Figure 5 It is one of the lifting construction drawings of a safe lifting control system for a disassembly and assembly device of a tunnel boring machine according to the present invention;
[0033] Figure 6 This is the second lifting construction drawing of a safe lifting control system for a disassembly and assembly device of a tunnel boring machine according to the present invention;
[0034] Figure 7 This is the third lifting construction drawing of a safe lifting control system for a disassembly and assembly device of a tunnel boring machine according to the present invention;
[0035] Figure 8 This is the fourth lifting construction drawing of a safe lifting control system for a disassembly and assembly device of a tunnel boring machine according to the present invention;
[0036] Fig. 9 The present invention discloses a communication wiring diagram of a safe lifting control system for a disassembly and assembly device of a tunnel boring machine.
[0037] The numbers in the accompanying drawings are: 1 is a cross beam, 2 is a lifting frame, 3 is a winch, 4 is a wire rope, 5 is a walking track, 6 is a deflection hook, 7 is an inclination sensor, 8 is a tension sensor, 9 is an eccentric load sensor, 10 is a displacement sensor, 11 is a 4-cylinder synchronous hydraulic jacking device, 12 is a pressure sensor, 13 is a first PLC sensor, 14 is a second PLC sensor, 15 is a third PLC sensor, 16 is a wireless communication module, 17 is a host computer, 18 is a first motor, 19 is a vehicle body guide wheel, 20 is a second motor, 21 is a take-up shaft, 22 is a boom, 23 is a base, 24 is an electric hydraulic valve, 25 is a load-bearing part, 26 is a third motor, and 27 is a driving wheel. DETAILED DESCRIPTION
[0038] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments:
[0039] Example 1
[0040] like Figure 1 to Figure 4 As shown in Figure 9, a safe lifting control system for disassembling and assembling device of a tunnel boring machine includes a lifting module and a control module, wherein the lifting module includes a cross beam 1, two lifting frames 2, a winch 3, a wire rope 4 and a moving trolley, wherein the winch 3 is fixed to the moving trolley, and the moving trolley is slidably connected to the cross beam 1, and the lifting frame 2 and the cross beam 1 are combined to form a gate-shaped structure, wherein the number of the lifting modules is two, and the lifting module also includes a walking mechanism and a walking track 5, wherein the walking mechanism is fixed to the lower end of the lifting frame 2 and is slidably connected to the walking track 5;
[0041] The hoist 3 is provided with a deflection hook 6, and the hoist 3 is fixed to the wire rope 4 through the deflection hook 6. The deflection hook 6 is provided with a tilt sensor 7 and a tension sensor 8. The hoist 3 is provided with an eccentric load sensor 9, and a displacement sensor 10 is provided near the upper ends of the two lifting frames 2;
[0042] The lifting frame 2 includes a 4-cylinder synchronous hydraulic jacking device 11, the lower part of which is vertically fixed to the walking mechanism, the upper part of which is vertically fixed to the crossbeam 1, and the lower end of which is provided with a pressure sensor 12;
[0043] The control module includes two first PLC controllers 13, three second PLC controllers 14 and one third PLC controller 15. The analog input ends of the two first PLC controllers 13 are connected to the inclination sensor 7, the tension sensor 8, the eccentric load sensor 9 and the displacement sensor 10. The first PLC controller 13 is used to control the winch 3 and the moving trolley.
[0044] The analog input terminals of the three second PLC controllers 14 and the third PLC controller 15 are all connected to the pressure sensor 12, and the second PLC controller 14 and the third PLC controller 15 are used to control the walking mechanism and the 4-cylinder synchronous hydraulic jacking device 11;
[0045] The third PLC controller 15 is also connected to a host computer 17 . A wireless communication module 16 is provided between the first PLC controller 13 , the second PLC controller 14 and the third PLC controller 15 . The first PLC controller 13 , the second PLC controller 14 and the third PLC controller 15 are communicatively connected via the wireless communication module 16 .
[0046] Preferably, the crossbeam 1 is a concave structure, and rails are provided on both sides of the crossbeam 1. The mobile trolley includes a first motor 18 and a vehicle body guide wheel 19. The vehicle body guide wheel 19 bites the rails, and the vehicle body guide wheel 19 is rotatably connected to the first motor 18. A frequency converter is provided between the first motor 18 and the first PLC controller 13, and the first motor 18 is connected to the power supply through the frequency converter to form a loop;
[0047] The winch 3 includes a second motor 20 and a take-up shaft 21. The second motor 20 is used to drive the take-up shaft 21 to take up and release the wire. The second motor 20 is connected to the first PLC controller 13 through the inverter. The second motor 20 is connected to the power supply through the inverter to form a loop.
[0048] Preferably, the take-up shaft 21 is connected to the suspension rod 22 via a steel wire rope, the eccentric load sensor 9 is arranged in the middle of the suspension rod 22, and the eccentric load sensor 9 includes a horizontal sensor;
[0049] The lower middle end of the suspension rod 22 is rotatably connected to the deflection hook 6, and the inclination sensor 7 is used to detect the pitch angle of the deflection hook 6;
[0050] The pressure sensor 12 is used to detect the tension value of a single deflection hook 6 .
[0051] Preferably, the 4-cylinder synchronous hydraulic jacking device 11 is provided with a base 23, and the base 23 is arranged between the 4-cylinder synchronous hydraulic jacking device 11 and the walking mechanism. The two 4-cylinder synchronous hydraulic jacking devices 11 are symmetrically arranged at both ends of the base 23. The 4-cylinder synchronous hydraulic jacking device 11 includes an electric hydraulic valve 24, and the coil of the electric hydraulic valve 24 is electrically connected to the output end of the second PLC controller 14 or the third PLC controller 15.
[0052] Preferably, the walking mechanism includes a load-bearing part 25, a third motor 26 and a driving wheel 27, the driving wheel 27 is arranged at the lower end of the load-bearing part 25, the driving wheel 27 is connected by a connecting rod, the connecting rod is connected to the output shaft of the third motor 26 through a synchronous belt, the connecting rod is fixed to the load-bearing part 25 through a bearing, the outer ring surface of the bearing is fixed to the load-bearing part 25, and the inner ring surface is fixed to the connecting rod;
[0053] A second frequency converter is provided between the third motor 26 and the PLC controller, and the third motor 26 is connected to a power source via the second frequency converter to form a loop.
[0054] Preferably, the wireless communication module 16 includes a MOXA Client wireless remote kit, and the host computer 17 includes a wireless remote controller and a PC.
[0055] Combining the above embodiments and the attached Figures 5 to 8 Explain the hoisting process of the tunnel boring machine:
[0056] During operation, the hoisting device is first moved to the position of the tunnel boring machine through the walking track 5 by the walking mechanism to check the state of the hoisting equipment. In the initial state, the 4-cylinder synchronous hydraulic jacking device 11 is in a retracted state. In this embodiment, two hoisting modules are set up, and in order to facilitate the distinction between the two hoisting modules, they are divided into a first hoisting module and a second hoisting module.
[0057] The first step is Figure 5 As shown, the two deflection hooks 6 of the first lifting module are fixedly connected to one end of the wire rope 4, and the other end of the deflection hook 6 is connected to the two lifting points on the lower left of the main drive of the tunnel boring machine through another section of the wire rope 4, and the two deflection hooks 6 of the second lifting module are connected to the two lifting points on the upper left of the main drive of the tunnel boring machine through the wire rope 4. At this time, the deflection hook 6 on the hoist 3 of the first lifting module is located lower than the deflection hook 6 on the hoist 3 of the second lifting module, and the wire rope 4 hanging on the second lifting module is in a relaxed state.
[0058] The second step is Figure 6 As shown, the main machine of the tunnel boring machine begins to flip, the 4-cylinder synchronous hydraulic jacking device 11 of the first lifting module is lifted, thereby driving the deflection hook 6 to rise, so that the wire rope 4 is straightened and stressed, and the walking mechanism will also move to the right through the walking track 5, and one side of the tunnel boring machine is lifted, lifted and flipped. The walking mechanism of the second lifting module moves to the right synchronously, and the 4-cylinder synchronous hydraulic jacking device 11 is lifted until it reaches a certain height, ensuring that the winch 3 of the first lifting module 4 will not cause the tunnel boring machine to hit the crossbeam 1 of the second lifting module when lifting in the next step. At this time, the wire rope 4 of the winch 3 of the second lifting module is still in a relaxed state.
[0059] The third step is Figure 7As shown, the winch 3 of the first lifting module 4 moves, driving the deflection hook 6 to rise to the highest point, one side of the tunnel boring machine is continuously lifted, and the flip angle increases. The winch 3 of the second lifting module moves at the same time, and moves to an appropriate height according to the difference of the wire rope 4 (the wire rope 4 of the second lifting module is connected to the two lifting points on the upper left of the tunnel boring machine, and at this time, there is still a height difference with the wire rope 4 of the first lifting module). Then, the 4-cylinder synchronous hydraulic jacking device 11 of the first lifting module and the second lifting module continues to maintain synchronous lifting, and the two winches 3 continue to move to the right through the moving trolley, and the height is flush. Since the distance between the lifting points is equal to the minimum distance between the two deflection hooks 6, there is no need for the two winches 3 to have a spacing. At this time, the wire rope 4 connected to the winch 3 of the first lifting module is always under force, and the wire rope 4 connected to the winch 3 of the second lifting module is still not under force.
[0060] Step 4 Figure 8 As shown, when the tunnel boring machine is flipped to vertical, the height of the deflection hook 6 is fine-tuned, the wire rope 4 of the second lifting module is vertically stressed, and the two sets of mobile trolleys move synchronously to lift the tunnel boring machine to the designated workstation, completing the lifting operation.
[0061] Since the lifting device of the tunnel boring machine is too large and complex to control, its control module is controlled by 6 PLC controllers. The first PLC controller 13, the second PLC controller 14 and the third PLC controller 15 all use Siemens S7-1500 controllers.
[0062] The first PLC controller 13 is used to control the movement of the mobile trolley, and the release and reeling of the winch 3, and receives the displacement detection parameters of the winch, the tension parameters of the wire rope 4, the eccentric load parameters of the boom 22 and the vertical inclination parameters of the wire rope 4;
[0063] The second PLC controller 14 and the third PLC controller 15 are used to control the lifting and resetting of the 4-cylinder synchronous hydraulic jacking device 11 and the movement of the walking mechanism, and receive the pressure value of the 4-cylinder synchronous hydraulic jacking device 11;
[0064] In addition, the third PLC controller 15 is connected to the host computer 17 to facilitate workers to perform data monitoring and lifting control.
[0065] In order to further ensure the safety of the lifting operation, during the lifting process, a parameter threshold is set. If the data collected by the sensor exceeds the set threshold, the host computer 17 will actively alarm and indicate the fault.
[0066] The PLC controller controls the lifting module through sensor detection parameters:
[0067] During lifting, the inclination sensor 7 of the first lifting module detects the inclination angle between the two steel ropes 4 on the winch 3 of the first lifting module and the downward vertical plane, and the second PLC controller 14 or the third PLC controller 15 adjusts the motor speed of the third motor 26 and the valve opening of the electric hydraulic valve 24 connected to the 4-cylinder synchronous hydraulic jacking device 11 according to the size of the inclination angle, thereby realizing the speed regulation of the third motor 26 and the lifting speed control of the 4-cylinder synchronous hydraulic jacking device 11.
[0068] When the inclination angle gradually increases to the left, the second PLC controller 14 or the third PLC controller 15 adjusts the third motor 26 to speed up the rotation, and the lifting speed of the 4-cylinder synchronous hydraulic jacking device 11 remains unchanged. When the speed of the third motor 26 reaches the maximum value, if the inclination angle to the left is not significantly reduced, the lifting speed of the 4-cylinder synchronous hydraulic jacking device 11 is reduced.
[0069] When the inclination angle gradually increases to the right, the second PLC controller 14 or the third PLC controller 15 controls the third motor 26 to reduce the rotation speed, and the lifting speed of the 4-cylinder synchronous hydraulic jacking device 11 remains unchanged.
[0070] The inclination angle is reduced to ensure that the wire rope 4 can be vertically stressed during the lifting process, thereby further improving the safety of the lifting operation.
[0071] The embodiments described above are only preferred embodiments of the present invention and are not intended to limit the scope of implementation of the present invention. Therefore, any equivalent changes or modifications made according to the structures, features and principles described in the patent scope of the present invention should be included in the scope of the patent application of the present invention.
Claims
1. A safe lifting control system for a disassembly and assembly device of a tunnel boring machine, comprising a lifting module and a control module, wherein the lifting module comprises a crossbeam (1), two lifting frames (2), a winch (3), a steel wire rope (4) and a moving trolley, wherein the winch (3) is fixed to the moving trolley, and the moving trolley is slidably connected to the crossbeam (1), wherein the lifting frame (2) and the crossbeam (1) are combined to form a gate-shaped structure, and wherein: The number of the lifting modules is two, and the lifting modules further include a walking mechanism and a walking track (5), wherein the walking mechanism is fixed to the lower end of the lifting frame (2) and is slidably connected to the walking track (5); The hoist (3) is provided with a deflection hook (6), the hoist (3) is fixed to the wire rope (4) via the deflection hook (6), the deflection hook (6) is provided with an inclination sensor (7) and a tension sensor (8), the hoist (3) is provided with an eccentric load sensor (9), and a displacement sensor (10) is provided near the upper ends of the two lifting frames (2); The lifting frame (2) comprises a 4-cylinder synchronous hydraulic lifting device (11), the lower part of the 4-cylinder synchronous hydraulic lifting device (11) is vertically fixed to the walking mechanism, the upper part of the 4-cylinder synchronous hydraulic lifting device (11) is vertically fixed to the crossbeam (1), and the lower end of the 4-cylinder synchronous hydraulic lifting device (11) is provided with a pressure sensor (12); The control module comprises two first PLC controllers (13), three second PLC controllers (14) and one third PLC controller (15); the analog input ends of the two first PLC controllers (13) are connected to the inclination sensor (7), the tension sensor (8), the eccentric load sensor (9) and the displacement sensor (10); the first PLC controller (13) is used to control the winch (3) and the moving trolley; The analog input ends of the three second PLC controllers (14) and the third PLC controller (15) are all connected to a pressure sensor (12), and the second PLC controller (14) and the third PLC controller (15) are used to control the walking mechanism and the 4-cylinder synchronous hydraulic jacking device (11); The third PLC controller (15) is also connected to a host computer (17); a wireless communication module (16) is provided between the first PLC controller (13), the second PLC controller (14) and the third PLC controller (15); the first PLC controller (13), the second PLC controller (14) and the third PLC controller (15) are communicatively connected via the wireless communication module (16); The crossbeam (1) is a concave-shaped structure, and rails are arranged on both sides of the crossbeam (1). The mobile trolley comprises a first motor (18) and a vehicle body guide wheel (19), the vehicle body guide wheel (19) bites the rails tightly, and the vehicle body guide wheel (19) is rotationally connected to the first motor (18). A frequency converter is arranged between the first motor (18) and the first PLC controller (13), and the first motor (18) is connected to a power supply through the frequency converter to form a loop; The hoist (3) comprises a second motor (20) and a wire take-up shaft (21), the second motor (20) being used to drive the wire take-up shaft (21) to perform wire take-up and wire release actions, the second motor (20) being connected to the first PLC controller (13) via the frequency converter, and the second motor (20) being connected to a power source via the frequency converter to form a loop; The take-up shaft (21) is connected to a suspension rod (22) via a steel wire rope (4); the eccentric load sensor (9) is arranged in the middle of the suspension rod (22); the eccentric load sensor (9) comprises a horizontal sensor; The lower middle end of the suspension rod (22) is rotatably connected to the deflection hook (6), and the inclination sensor (7) is used to detect the pitch angle of the deflection hook (6); The pressure sensor (12) is used to detect the tension value of a single deflection hook (6); The 4-cylinder synchronous hydraulic lifting device (11) is provided with a base (23), the base (23) is arranged between the 4-cylinder synchronous hydraulic lifting device (11) and the walking mechanism, two 4-cylinder synchronous hydraulic lifting devices (11) are symmetrically arranged at both ends of the base (23), the 4-cylinder synchronous hydraulic lifting device (11) includes an electric hydraulic valve (24), and the coil of the electric hydraulic valve (24) is electrically connected to the output end of the second PLC controller (14) or the third PLC controller (15); The walking mechanism comprises a load-bearing part (25), a third motor (26) and a driving wheel (27), wherein the driving wheel (27) is arranged at the lower end of the load-bearing part (25), the driving wheel (27) is connected via a connecting rod, the connecting rod is drivingly connected to the output shaft of the third motor (26) via a synchronous belt, the connecting rod is fixed to the load-bearing part (25) via a bearing, the outer annular surface of the bearing is fixed to the load-bearing part (25), and the inner annular surface is fixed to the connecting rod; A second frequency converter is provided between the third motor (26) and the PLC controller, and the third motor (26) is connected to a power supply via the second frequency converter to form a loop.
2. A safe lifting control system for disassembling and assembling equipment of a tunnel boring machine according to claim 1, characterized in that: The wireless communication module (16) includes a MOXA Client wireless remote control kit, and the host computer (17) includes a wireless remote control and a PC.