Construction method of concrete internal support structure combining cast-in-place and prefabrication
By combining cast-in-place and prefabricated technologies in deep foundation pit construction, the areas are divided and prefabricated components and quick-load joints are used to solve the problems of intermittent construction processes and severe weather impacts, and efficient and safe internal support of deep and large foundation pit concrete is achieved. construction.
Patent Information
- Application Number
- CN202211293576.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-10-21
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2042-10-21
AI Technical Summary
The existing internal support construction methods for deep foundation pit concrete have intermittent construction processes, low efficiency, high risk and great impact on bad weather, resulting in insufficient construction progress and safety.
The construction method of concrete internal support structure combining cast-in-place and prefabricated is adopted. By dividing cast-in-place areas and prefabricated areas, prefabricated components are used to shorten the curing time and improve the concrete strength. The assembly efficiency is improved by using quick loading and quick disassembly joints and welding techniques, and reducing the Illegal work and bad weather effects.
It has achieved shortening the construction cycle of deep and large foundation pits, improving safety and quality, reducing idle work, improving on-site civilized construction and resource management efficiency, and reducing the impact of bad weather on construction.
Smart Images

Figure CN115538455B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a construction method for a concrete inner support of a building deep foundation pit, and in particular to a construction method for a concrete inner support structure combining cast-in-place and prefabrication. Background Art
[0002] With the advancement of technology, the increase in building height and underground structures, the application of deep foundation pits and large foundation pits has increased year by year, but their construction process has a great impact on the project progress target. Deep and large foundation pits with an excavation depth of more than 5m are regarded as dangerous and over-scale sub-projects and are subject to key control. Pile support structures with concrete internal supports have been widely used in such projects, and the internal support construction generally adopts cast-in-place technology.
[0003] The overall construction steps of the foundation pit project using this technology are as follows:
[0004] 1. Level the site and construct the pile structure.
[0005] 2. Complete the construction of the crown beam and the first internal support structure in different areas.
[0006] 3. After the first internal support reaches the design strength requirement, excavate the earth to the second internal support.
[0007] 4. Construct waist beam and second support.
[0008] 5. Repeat steps 2, 3, and 4 until the excavation reaches the designed depth.
[0009] 6. Construct the main structure to the lowest internal support structure from bottom to top.
[0010] 7. Replace the support and backfill the lower soil.
[0011] 8. Remove the lowest internal support structure in sections
[0012] 9. Repeat steps 7 and 8 to complete the construction of the underground part of the main structure.
[0013] This process has the following shortcomings: in order to ensure the stability of the foundation pit, the above steps are required to be completed as soon as possible to reduce the exposure time of the foundation pit, and the steps are interspersed with the work procedures and connected very closely; the purpose of dividing the area in step 2 is to facilitate the management and organization of earthwork, internal support and other work, and form a flow construction; in step 3, the design requires that all supporting structures in each area with the same elevation must be maintained to the design required strength, so that the support mechanism can form an overall force system, otherwise it will cause excessive deformation of the supporting structure, leading to safety accidents such as collapse, but the maintenance period will inevitably cause construction process interruptions and on-site idle work; in step 8, it is necessary to set up the lower scaffolding to ensure that the supporting structure in this area is stable, and then use special equipment such as rope saws to cut the concrete structure in sections, or use mechanical demolition, blasting demolition and other methods, which are inefficient, dangerous, and have poor on-site civilized construction. Summary of the invention
[0014] In order to overcome the shortcomings of the prior art, the present invention provides a construction method for a concrete inner support structure that combines cast-in-place and prefabrication. It reduces the impact of open-air operations and bad weather on progress and quality, eliminates the intervals in the maintenance process of the inner support structure, shortens the construction period, improves the safety of foundation pit engineering, shortens the construction period of deep and large foundation pits, and completely solves the problem of idle workers.
[0015] In order to achieve the above object, the present invention adopts the following technical solutions:
[0016] A construction method of a cast-in-place and prefabricated concrete inner support structure comprises the following steps:
[0017] 1) Divide the cast-in-place area and precast area according to the earthwork excavation zoning map and earthwork excavation schedule;
[0018] 2) Decompose the supporting structure in the prefabrication area;
[0019] 3) When excavating earthwork, first complete the excavation of the cast-in-place area, and then complete the excavation of the prefabricated area;
[0020] 4) At the same time as step 3, prefabricated components are manufactured and maintained according to the decomposition plan;
[0021] 5) After the excavation of each cast-in-place area is completed, the construction of the supporting cast-in-place concrete structure in the cast-in-place area is carried out, and the later excavation of the prefabricated area is carried out at the same time;
[0022] 6) While the cast-in-place area is being maintained, the prefabricated area is being assembled:
[0023] 7) According to the excavation sequence, excavate the earthwork to the support bottom elevation in each area of the next layer;
[0024] 8) Carry out steps 3 to 7 until the foundation pit excavation project is completed.
[0025] As a further improvement of the present invention, the division of cast-in-place areas and prefabricated areas in step 1) is carried out according to an earth excavation zoning map, the overall area division is consistent with the earth excavation zoning, and the cast-in-place areas and prefabricated areas are further divided according to the delivery time of earth excavation work in each area. The assembly completion time of the prefabricated area is no later than the concrete of all casting areas is cured to the design strength requirements.
[0026] As a further improvement of the present invention, when the support in the prefabricated area is decomposed in step 2, the installation and removal of each prefabricated component are comprehensively considered, and the maximum weight of a single component is not more than 5t, and the maximum length is not more than the size at the narrowest point of the transportation route, whichever is smaller; in addition, the decomposition location is located at the connection between the beam end and the lattice column as much as possible. When an overly large and long beam is decomposed only at the connection between the beam end and the lattice column and cannot meet the above-mentioned weight and size requirements, an additional decomposition node is added within the middle 1 / 3.
[0027] As a further improvement of the present invention, the temporary road in the production area of step 3 is set up separately to reduce the transportation pressure and congestion of the temporary roads in the site area; the production of prefabricated components and maintenance work are completed in a covered factory building to reduce the impact of adverse weather such as rain and snow; the factory building used for the production of prefabricated components and maintenance work can be combined with the early retaining pile steel cage production plant to reduce the investment in measures.
[0028] As a further improvement of the present invention, the workers supporting the cast-in-place concrete structure construction and the prefabrication plant in the cast-in-place area in step 5 are all reinforcement workers, formwork workers, concrete workers, and laborers. Sufficient workers can maximize the utilization of the working surface of the cast-in-place area without generating idle workers, which is conducive to shortening the construction period of the cast-in-place area.
[0029] After the cast-in-place area was completed, some of the workers in the cast-in-place area were dispatched to the prefabrication plant to produce prefabricated components, and the remaining workers completed the assembly work in the prefabrication area, ensuring that there was no idle work during the maintenance period of the internal support concrete structure.
[0030] As a further improvement of the present invention, the last part of the cast-in-place area in step 5 adopts a method of increasing the concrete strength and adding an early strength agent to shorten the curing time and the construction period.
[0031] As a further improvement of the present invention, during the assembly in step 6, the prefabricated components and the lattice columns are connected by quick-install and quick-disassemble joints, and reinforcing ribs are provided in the upper and lower areas of the lattice columns at the same elevation for rapid installation.
[0032] As a further improvement of the present invention, during the assembly in step 6, a special movable bracket is designed according to the maximum weight and size of a single section to facilitate the alignment of the interface; or a jack, scaffolding, or wooden wedges are used for alignment and correction to improve the assembly efficiency.
[0033] Compared with the existing method, the present invention has the following beneficial effects:
[0034] 1. Compared with the prior art, in terms of organization and management, the present invention provides more working surfaces, adds a prefabrication area in the foundation pit that occupies the site in the foundation pit for a shorter time, relieves the pressure of lack of working surfaces on site, and shortens the construction period. Adding a production plant outside the foundation pit to complete the production of prefabricated components, so that there are more working surfaces for concrete engineering construction, and the deployment of workers on different working surfaces is more convenient, which avoids idle work and facilitates on-site management and balanced resource allocation, thereby improving per capita productivity.
[0035] 2. Compared with the prior art, in terms of construction period control, the present invention makes full use of the working surface in the foundation pit, which is conducive to concentrating resources to complete the construction of the cast-in-place area in the early stage; and to concentrate resources to complete the assembly construction of the prefabricated area in the later stage, so that both processes shorten the absolute construction period, shorten the total construction period, and the concrete engineering of the whole process has no idle workers. At the same time, the foundation pit exposure time is shortened and the safety is improved.
[0036] 3. Compared with the prior art, the present invention adds an off-site production plant. When a covered factory building is used, it is less affected by bad weather and the quality is easier to ensure.
[0037] 4. Compared with the prior art, the present invention shortens the time of dismantling the prefabricated area and improves the civilized construction and safety on site.
[0038] The demolition of the prefabricated area is faster than that of the cast-in-place area because welding, bolt connection, steel bar connection and prestressed connection technology can be used, which is more efficient than cutting concrete beams with special equipment such as rope saws, and the construction environment is better. At the same time, it can relieve the pressure of temporary roads and equipment transportation on site in the later stage of demolition. BRIEF DESCRIPTION OF THE DRAWINGS
[0039] Figure 1 It is a schematic diagram of a deep and large foundation pit using a concrete inner support pile support structure of the present invention;
[0040] Figure 2 It is a schematic diagram of earthwork excavation zoning of the present invention;
[0041] Figure 3 This is a construction schedule diagram of the internal support of the fully cast-in-place structure of the present invention;
[0042] Figure 4 It is a progress plan diagram of the construction method of the concrete inner support structure combining cast-in-situ and prefabrication of the present invention;
[0043] Figure 5 It is the layout diagram of the cast-in-place area and the prefabricated area of the present invention;
[0044] Figure 6 It is a schematic diagram of support decomposition in the prefabricated area of the present invention;
[0045] Figure 7It is a schematic diagram of the connection between the beam section and the lattice column of the present invention;
[0046] Figure 8 It is a schematic diagram of beam segment connection of the present invention.
[0047] In the figure: 1-pile enclosure structure 2-concrete internal support structure 3-concrete beam 4-lattice column 41-lattice column support plate 42-connecting internal support 5-prefabricated beam section 51-embedded hook 61-steel structure pad 62 connecting steel bar 63-concrete sealant DETAILED DESCRIPTION
[0048] The following embodiments of the present invention are described in further detail in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.
[0049] In the description of the present invention, unless otherwise specified, "plurality" means two or more than two; the orientations or positional relationships indicated by the terms "upper", "lower", "left", "right", "inner", "outer", "front end", "rear end", "head", "tail", etc. are based on the orientations or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", "third", etc. are only used for descriptive purposes and cannot be understood as indicating or implying relative importance.
[0050] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "connected" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0051] A construction method of a cast-in-place and prefabricated concrete inner support structure comprises the following steps:
[0052] 1) Divide the cast-in-place area and prefabricated area according to the earthwork excavation zoning map and earthwork excavation schedule.
[0053] The division of cast-in-place area and precast area is carried out according to the earthwork excavation zoning map. The overall area division is consistent with the earthwork excavation zoning. The cast-in-place area and precast area are further divided according to the delivery time of earthwork excavation work in each area. The assembly completion time of the precast area shall not be later than the concrete curing of all the cast-in-place areas to the required strength of the design. The advantage of this is that it has the least impact on the construction deployment of earthwork excavation work and is easier to manage the construction of each area.
[0054] 2) Decompose the supporting structure within the prefabrication area.
[0055] When decomposing the supports in the prefabricated area, the installation and removal of each prefabricated component shall be comprehensively considered. The maximum weight of a single component shall not exceed 5t, and the maximum length shall not exceed the size at the narrowest point of the transportation route, whichever is smaller. In addition, the decomposition location shall be located at the connection between the beam end and the lattice column as much as possible. If an overly large and long beam is only decomposed at the connection between the beam end and the lattice column and cannot meet the above weight and size requirements, an additional decomposition node shall be added in the middle 1 / 3.
[0056] 3) When excavating earth, complete the excavation of the cast-in-place area first, and then complete the excavation of the prefabricated area.
[0057] When excavating earthwork, the excavation of the cast-in-place area is completed first, and then the excavation of the prefabricated area is completed. Because the demand for temporary roads and working surfaces on site during the construction of the concrete structure in the prefabricated area is small, more excavation equipment can be arranged according to the conditions of the temporary roads, shortening the absolute construction period of earthwork in each area, which is conducive to shortening the total construction period and facilitating civilized construction on site.
[0058] Preferably, temporary roads in the production area can be set up separately to reduce the transportation pressure and congestion of temporary roads in the site, which is conducive to completing step 3 faster.
[0059] Preferably, the production and maintenance of prefabricated components can be completed in a covered workshop to reduce the impact of adverse weather such as rain and snow.
[0060] Preferably, the factory building used for manufacturing prefabricated components and maintenance work can be combined with the early retaining pile reinforcement cage manufacturing plant to reduce the investment in measures costs.
[0061] 4) At the same time as step 3, prefabricated components are manufactured and maintained according to the decomposition plan.
[0062] The production and maintenance of prefabricated components can be carried out outside the foundation pit boundary, without occupying the foundation pit earth excavation work surface, and the start time is no longer limited by the completion time of the earthwork in this area, so it can be carried out simultaneously with step 3; because prefabrication is carried out outside the foundation pit boundary, more concrete engineering construction work surfaces are created, and the working environment is no longer close to the earth excavation work, which reduces safety hazards, facilitates quality control, and improves work efficiency; the concrete engineering construction work surface of the prefabrication plant can accommodate the remaining workers when the construction conditions are not met in the early cast-in-place area to avoid idle work.
[0063] 5) After the excavation of each cast-in-place area is completed, the construction of the supporting cast-in-place concrete structure in the cast-in-place area will be carried out, and the subsequent excavation of the prefabricated area will be carried out at the same time.
[0064] The construction of the supporting cast-in-place concrete structure in the cast-in-place area is carried out, and the later excavation of the prefabrication area is carried out at the same time. The workers who support the cast-in-place concrete structure construction in the cast-in-place area and the workers in the prefabrication plant are all steel workers, formwork workers, concrete workers, and labor workers. There are sufficient workers to maximize the utilization of the working surface of the cast-in-place area without idle workers, which is conducive to shortening the construction period of the cast-in-place area. After the cast-in-place area is completed, some of the workers in the cast-in-place area can be dispatched to the prefabrication plant to make prefabricated components, and the remaining workers complete the assembly work in the prefabrication area, so that there is no idle work during the maintenance period of the internal supporting concrete structure.
[0065] Preferably, the last part of the cast-in-place area can be cured by increasing the concrete strength, adding early strength agents, etc., thereby shortening the construction period.
[0066] 6) While the cast-in-place area is being maintained, the prefabricated area is being assembled.
[0067] While the cast-in-place area is being maintained, the prefabricated area is being assembled. Because the prefabricated components have been maintained in the factory, they can be assembled on site using forming machines such as car cranes, forklifts, and other special machines. The time required is much less than the time required for cast-in-place and maintenance, thus significantly shortening the construction period. The connection between the prefabricated components and the lattice columns is achieved using a variety of quick connection methods such as welding, steel bar connection, bolt connection, snap-on, and prestressed connection.
[0068] Preferably, during assembly, the connection between the prefabricated components and the lattice columns can also be quickly installed by means of quick-install and quick-disassemble joints, and reinforcing ribs are provided in the upper and lower areas of the lattice columns at the same elevation.
[0069] Preferably, during assembly, a movable special bracket can be designed according to the maximum weight and size of a single section to facilitate the alignment of the interface, or conventional methods such as jacks, scaffolding, wooden wedges, etc. can be used for alignment and correction to improve assembly efficiency.
[0070] 7) According to the excavation sequence, excavate the earthwork to the support bottom elevation in each area of the next layer;
[0071] 8) Carry out steps 3 to 7 until the foundation pit excavation project is completed.
[0072] The demolition of the prefabricated area of the present invention is faster than that of the cast-in-place area, because welding, bolt connection, steel bar connection, and prestressed connection technology can be used, which is more efficient than cutting concrete beams with special equipment such as rope saws, and the construction environment is better. At the same time, it relieves the pressure of temporary roads and equipment transportation on site in the later demolition stage.
[0073] [Example]
[0074] like Figures 1 to 8 As shown, a construction method of a concrete inner support structure combining cast-in-place and prefabrication specifically includes the following steps:
[0075] Figure 1 This is a schematic diagram of a deep foundation pit project. The foundation pit is 120m wide, 240m long and 35m deep. The supporting structure adopts a pile retaining structure with concrete inner support. Specifically, it includes a pile retaining structure 1, a concrete inner support structure 2, a concrete beam 3 and a lattice column 4.
[0076] Figure 2 This is a schematic diagram of the on-site earthwork excavation division. According to the pit bottom elevation, engineering quantity, and soil conditions, the earthwork excavation is divided into A1 area, B1 area, C1 area, D1 area, E area, and F area.
[0077] Figure 3 This is a construction method schedule diagram for the concrete internal support structure that combines cast-in-place and prefabrication. Figure 4 The construction method schedule for the concrete internal support structure combining cast-in-place and precast is provided, and the original earthwork schedule has not been modified.
[0078] Step 1: Divide the cast-in-place area and precast area according to the original earthwork excavation zoning diagram and earthwork excavation schedule.
[0079] like Figure 2 As shown, the order of completion of earthwork excavation is A1, B1, C1, D1, E, and F. Internal support must be carried out after the earthwork in the same area is completed and the working surface is available.
[0080] like Figure 3 As shown in the figure, when the fully cast-in-place technology of internal support is adopted, the common measures such as increasing the concrete strength grade and adding early strength agent are adopted for the support in the F area that is finally completed. However, the construction period is still as long as 92 days to complete the construction of the single-layer internal support structure and meet the conditions for downward excavation.
[0081] like Figure 4 As shown, when the technology of the present invention is used to divide the cast-in-place area and the prefabricated area, the prefabrication of some internal supports reduces the occupation of temporary roads on site. According to the calculation of road use efficiency, the absolute construction period of earth excavation in some areas is shortened. In the embodiment, the absolute construction period of earth excavation in the three areas of D1, E, and F is adjusted to 15 days. Then, the F area, E area, and D1 area completed later are changed to prefabricated areas in chronological order until the total construction period is shortened to within expectations. The embodiment project has no other external construction period constraints, so it is chosen to shorten the construction period to the same day when the earth excavation of the F area is completed, and the support construction in all areas of the entire layer is completed. And it wins a free time difference for the concrete maintenance of the cast-in-place area that is finally completed. In the embodiment, area C1 can have a 14-day maintenance period by taking measures.
[0082] The divided cast-in-place area and precast area are as follows Figure 5 As shown, A1, B1, and C1 are cast-in-place areas, and D1, E, and F are prefabricated areas.
[0083] Step 2: Decompose the support structure within the precast area.
[0084] Figure 6 It is a schematic diagram of the support decomposition within the precast area. As Figure 6 shown, according to the design drawings, follow the rule that the maximum weight of a single component is not greater than 5t, and the maximum length is not greater than the size of the narrowest part of the transportation route. Take the smaller value of the two.
[0085] In addition, the decomposition part should be located as close as possible to the connection between the beam end and the lattice column. When the decomposition at only the connection between the beam end and the lattice column for a beam that is too large or too long cannot meet the above weight and size requirements, add 1 decomposition point within the middle 1 / 3 range. By referring to the drawings, in the embodiment, the beam cross-sections are 0.9m×1m respectively, and the narrowest part of the transportation route during demolition is 2.5m, which is located at the entrance of the foundation pit material hoisting equipment.
[0086] Maximum length design:
[0087] For a beam with a weight of 5t and a cross-section of 0.9m×1m, the length is: 5 / (0.9×1×2.1) = 2.645m
[0088] The narrowest part of the transportation route during demolition is 2.5m.
[0089] Take the smaller value: the length of the longest beam segment is 2.5m.
[0090] For a beam with a length less than 2.5m, directly select to set the decomposition node at the connection between the beam end and the lattice column.
[0091] For a beam with a length greater than 2.5m, in addition to setting a decomposition node at the connection between the beam end and the lattice column, add 1 decomposition point within the middle 1 / 3 range.
[0092] As Figure 6 shown, the "□" symbol in the precast area in the figure is the decomposition node.
[0093] Step 3: During the earth excavation, first complete the earth excavation in the cast-in-place area, and then complete the excavation in the precast area.
[0094] During the earth excavation of the embodiment project, according to the progress plan as Figure 4 shown, the excavation work in areas A1, B1, C1, D1, E, and F was completed in sequence. The cast-in-place construction of the concrete internal support was carried out by area.
[0095] Step 4: Simultaneously with Step 3, fabricate precast components according to the decomposition plan and cure them.
[0096] Before the A1, B1, and C1 areas were equipped with work surfaces, concrete workers participated in the production of precast components in the production plant. As the number of workers in the production plant increased with the increase in the work surface of the foundation pit concrete project, they were gradually transferred to the A1, B1, and C1 areas for construction work, ensuring the absolute construction period of the cast-in-place area.
[0097] Step 5: After the excavation of each cast-in-place area is completed, the construction of the supporting cast-in-place concrete structure in the cast-in-place area will be carried out, and the later excavation of the prefabricated area will be carried out at the same time.
[0098] After the excavation of the A1, B1 and C1 areas was completed, concrete workers were dispatched to the various cast-in-place areas to carry out cast-in-place construction of the internal support concrete structure. Some workers were dispatched by the manufacturer. The staffing ensured the absolute construction period of each cast-in-place area.
[0099] Step 6: While the cast-in-place area is being cured, assemble the prefabricated area.
[0100] The three areas of cast-in-place area maintenance, prefabrication area assembly, and prefabrication production in the manufacturing plant are all equipped with work surfaces to meet the number of people for assembly. In addition, concrete workers in the cast-in-place area are dispatched to the manufacturing plant to produce prefabricated structures. When assembling, welding, steel bar connection, bolt connection, snap-on connection, prestressed connection and other forms can be used.
[0101] Figure 7 This is a schematic diagram of the connection between the beam segment and the lattice column. Figure 8 is a schematic diagram of beam segment connection, such as Figure 7 , Figure 8 As shown, the embodiment project uses a snap-on connection method at the beam end and lattice column node in combination with the surrounding material supply on site, and uses a steel bar connection joint at the decomposition node between beam sections.
[0102] like Figure 7 As shown, when the prefabricated beam segment 5 is prefabricated, a pre-embedded hook 51 made of a steel plate is arranged at the end, a lattice column support plate 41 and a hook are arranged at the connection between the lattice column 4 and the prefabricated beam segment 5, and a connecting inner support 42 is arranged inside the lattice column 4. During installation, the prefabricated beam segment 5 is dropped from top to bottom into the lattice column support plate 41 and the hook on the lattice column 4, and a steel structure pad 61 is placed to squeeze the gap between the prefabricated beam segment 5 and the lattice column 4 tightly.
[0103] like Figure 8 As shown, the beam section connection is composed of a precast beam section 5, connecting steel bars 62, and concrete sealant 63. The connecting steel bars 62 are reserved at intervals on both sides. When overlapping with the original steel bars in the precast beam section 5, the original longitudinal steel bars can also be directly used on one side.
[0104] First, the precast beam segment 5 is aligned so that the connecting steel bar 62 is aligned with the reserved hole of the precast beam segment 5 on the other side, and the exposed length of the connecting steel bar 62 + 100 to 200 operation width is reserved at the interface; the exposed part of the connecting steel bar 62 is coated with anchor glue, and the contact section of the precast beam segments 5 on both sides is coated with concrete sealant 63, and the precast beam segments 5 on both sides are pushed tightly to complete the connection of the precast beam segments 5. After the precast beam segment 5 connection inspection is passed, the precast beam and the lattice column 4 are quickly assembled.
[0105] Step 7: According to the excavation sequence, excavate the earth to the support bottom elevation in each area of the next layer.
[0106] Step 8: Repeat steps 3 to 7 until the foundation pit excavation is completed.
[0107] Compared with the prior art, in terms of organization and management, the present invention provides more working surfaces, adds a prefabrication area in the foundation pit that occupies the site in the foundation pit for a shorter time, alleviates the pressure of lack of working surfaces on site, and shortens the construction period. The addition of a manufacturing plant outside the foundation pit to complete the production of prefabricated components makes the concrete engineering construction work surface more, and the deployment of workers on different working surfaces is more convenient, which avoids idle work and facilitates on-site management and balanced resource allocation, thereby improving per capita productivity. Compared with the prior art, in terms of construction period control, the present invention realizes the full use of the working surface in the foundation pit, which is conducive to the concentration of resources to complete the construction of the cast-in-place area in the early stage; and in the later stage, it is conducive to the concentration of resources to complete the assembly construction of the prefabricated area, so that both processes shorten the absolute construction period, shorten the total construction period, and the concrete engineering of the whole process has no idle work. At the same time, the exposure time of the foundation pit is shortened and safety is improved. Compared with the prior art, the present invention adds an off-site manufacturing plant, which is less affected by bad weather when a covered factory is used, and the quality is easier to guarantee. Compared with the prior art, the present invention shortens the dismantling operation time of the prefabricated area and improves the civilized construction and safety on site.
[0108] The demolition of the prefabricated area of the present invention is faster than that of the cast-in-place area, because welding, bolt connection, steel bar connection, and prestressed connection technology can be used, which is more efficient than cutting concrete beams with special equipment such as rope saws, and the construction environment is better. At the same time, it relieves the pressure of temporary roads and equipment transportation on site in the later stage of demolition.
[0109] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A construction method for a concrete inner support structure combining cast-in-place and prefabrication, characterized in that: The specific steps include: 1) Divide the cast-in-place area and precast area according to the earthwork excavation zoning map and earthwork excavation schedule; The division of cast-in-place area and precast area is carried out according to the earthwork excavation zoning map. The overall area division is consistent with the earthwork excavation zoning. The cast-in-place area and precast area are further divided according to the delivery time of earthwork excavation work in each area. The assembly completion time of the precast area shall not be later than the concrete curing of all the casting areas to the design strength requirements; 2) Decompose the supporting structure in the prefabrication area; When decomposing the supports in the prefabricated area, the installation and removal of each prefabricated component shall be comprehensively considered. The maximum weight of a single component shall not exceed 5t, and the maximum length shall not exceed the size at the narrowest point of the transportation route, whichever is smaller. In addition, the decomposition location is located at the connection between the beam end and the lattice column. Beams that are too large and too long are only decomposed at the connection between the beam end and the lattice column. If the above weight and size requirements cannot be met, an additional decomposition node shall be added within the middle 1 / 3 range. 3) When excavating earthwork, first complete the excavation of the cast-in-place area, and then complete the excavation of the prefabricated area; 4) At the same time as step 3, prefabricated components are manufactured and maintained according to the decomposition plan; 5) After the excavation of each cast-in-place area is completed, the construction of the supporting cast-in-place concrete structure in the cast-in-place area will be carried out, and the later excavation of the prefabricated area will be carried out at the same time; The workers supporting the cast-in-place concrete structure construction and the prefabrication plant in the cast-in-place area are all reinforcement workers, formwork workers, concrete workers, and laborers. After the cast-in-place area is completed, some of the workers in the cast-in-place area are dispatched to the prefabrication plant to make prefabricated components, and the remaining workers complete the assembly work in the prefabrication area. 6) While the cast-in-place area is being maintained, the prefabricated area is being assembled: The connection between the prefabricated components and the lattice columns is carried out by using quick-install and quick-disassemble joints, and reinforcing ribs are provided in the upper and lower areas of the lattice columns at the same elevation; When the prefabricated beam segment is prefabricated, a pre-buried hook made of a steel plate is set at the end, a lattice column support plate and a hook are set at the connection between the lattice column and the prefabricated beam segment, and a connecting inner support is set inside the lattice column; when installing, the prefabricated beam segment is dropped from top to bottom into the lattice column support plate and the hook on the lattice column, and a steel structure pad is placed to squeeze the gap between the prefabricated beam segment and the lattice column tightly; The beam section connection is composed of precast beam sections, connecting steel bars, and concrete sealant. The connecting steel bars are reserved at intervals on both sides. When overlapping with the original steel bars in the precast beam section, the original longitudinal steel bars are directly used on one side. 7) According to the excavation sequence, excavate the earth to the support bottom elevation in each area of the next layer; 8) Carry out steps 3 to 7 until the foundation pit excavation work is completed.