Construction method of climbing frame at bay window
By installing 150mm high K-plates on the beams and using an improved heightening structure, the problem of delayed installation of traditional heightening components was solved, ensuring safe and timely connection of the climbing scaffold and improving construction efficiency.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- YUNNAN KEBAO FORMWORK & SCAFFOLD
- Filing Date
- 2022-11-01
- Publication Date
- 2026-04-10
AI Technical Summary
The installation of traditional extension components is limited by the height of the formwork, which makes it impossible to install the climbing scaffold in a timely manner, affecting construction safety and efficiency.
By designing a 150mm high K-plate and an improved heightening structure, it can be installed on the beam, avoiding waiting for the mullion to be poured and ensuring timely connection of the climbing scaffold wall supports.
This enabled the safe installation of the climbing scaffolding on each existing floor, improved construction efficiency, and ensured the safety and progress of the construction.
Smart Images

Figure CN115653086B_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The present application relates to the field of construction, in particular to a construction method of a bay window. BACKGROUND
[0002] The building bay window usually has two bay window panels, an upper bay window panel and a lower bay window panel. The upper bay window panel and the lower bay window panel are horizontally protruding structures, and the space between the upper bay window panel and the lower bay window panel of the room at the same floor is used for installing the window frame and glass. From the perspective of the room, the vertical wall structure between the upper bay window panel and the roof is usually referred to as a beam, and the vertical wall structure between the lower bay window panel and the floor is usually referred to as a column. During construction, the beam and the upper bay window panel are cast together, the column and the lower bay window panel are cast together, and the beam and the column are cast separately, which needs to be completed in two construction periods. Among them, the beam is cast with the building structure below the floor level, and the column is cast with the building structure above the floor level.
[0003] During casting, formwork needs to be used. At the joint between the upper and lower two floors that need to be cast in sequence, a K plate (also formwork) is usually used. The K plate is used to connect the upper and lower floors, with a part above the floor level and a part below the floor level. The K plate below the floor level is used as formwork. The K plate above the floor level is used for positioning and preventing leakage of the upper layer during casting. In building construction, an aluminum K plate is usually used, and its size is designed with a certain standard, and its height is usually 300 mm.
[0004] When the climbing frame machine position is set at the building bay window, since there is the outwardly protruding bay window panel, a transition piece (commonly known as a heightening piece) needs to be used to connect the attached wall support of the climbing frame machine position and the building main body.
[0005] The traditional heightening piece has a relatively large size, and needs to occupy a large space during installation. It is installed on the beam and column of the upper and lower floors, i.e., a part is installed on the column above the floor level, and a part is installed on the beam below the floor level. Since the beam and the column are cast separately, when the heightening piece needs to be installed, the column has not been cast, and the formwork of the column needs to be fixed by the K plate, and the height of the K plate is 300 mm, which will affect the installation of the heightening piece. The heightening piece needs to be installed after the column is cast and the K plate and the column formwork are removed. Since the heightening piece is installed late, it cannot guarantee that an attached wall support is installed on each built floor, which not only affects the safety of the climbing frame, but also causes the climbing frame to be not lifted in time, thereby affecting the construction efficiency. SUMMARY
[0006] The present application aims to solve the above problems and provides a construction method of a bay window.
[0007] To solve the above problems, the application provides a bay window position climbing frame construction method, which is characterized by comprising the following steps:
[0008] S1, a beam formwork and a 150mm high K plate are arranged at the outer wall position between the upper bay window plate to be poured and the floor level, the top end of the K plate is above the floor level, the bottom end of the K plate is below the floor level, and the beam formwork is arranged between the K plate and the upper bay window plate to be poured;
[0009] S2, the floor level below is poured, and the upper bay window plate and the beam from the upper bay window plate to the roof are poured;
[0010] S3, the K plate is retained without being removed, and the beam formwork and the formwork at the inner wall position of the beam are removed;
[0011] S4, a heightening piece is arranged at the outer wall position of the beam;
[0012] S5, the wall-attached support of the climbing frame is connected with the heightening piece.
[0013] Further, after step S3, the following steps are further included:
[0014] S6, a door frame formwork is arranged at the outer wall position between the K plate and the lower bay window plate;
[0015] S7, the floor level above is poured, and the lower bay window plate and the door frame from the lower bay window plate to the floor level are poured.
[0016] Further, the top of the K plate is 50mm higher than the floor level.
[0017] Further, the height of one end of the heightening piece arranged with the beam is less than 300mm.
[0018] Further, the heightening piece comprises a first connecting plate, a second connecting plate and a connecting assembly fixedly connected between the first connecting plate and the second connecting plate, the height of the first connecting plate is less than 300mm, the height of the second connecting plate is greater than 300mm, and the lower ends of the first connecting plate and the second connecting plate are flush.
[0019] Further, in step S4, when the heightening piece is arranged at the outer wall position of the beam, the first connecting plate of the heightening piece is fixedly connected with the beam through a wall screw bolt.
[0020] Further, in step S5, when the wall-attached support of the climbing frame is connected with the heightening piece, the second connecting plate of the heightening piece is fixedly connected with the wall-attached support through a bolt.
[0021] Further, a first connecting hole is arranged on the first connecting plate, and a second connecting hole is arranged on the second connecting plate; a reinforcing plate is arranged on the side of the first connecting plate facing the second connecting plate and fixedly connected with the second connecting plate, and the first connecting hole penetrates the reinforcing plate.
[0022] Further, the connecting assembly comprises:
[0023] horizontal connecting rods, which are connected to the lower parts of the first connecting plate and the second connecting plate in parallel and perpendicularly to the first connecting plate and the second connecting plate;
[0024] a first reinforcing plate, one end of which is fixedly connected with the first connecting plate perpendicularly, and one end of which is fixedly connected with the top of the horizontal connecting rod perpendicularly;
[0025] a second reinforcing plate, one end of which is fixedly connected with the second connecting plate perpendicularly, and one end of which is fixedly connected with the top of the horizontal connecting rod perpendicularly;
[0026] inclined connecting rods, which are connected to the upper parts of the first connecting plate and the second connecting plate in parallel and respectively at an angle to the first connecting plate and the second connecting plate.
[0027] The beneficial contribution of the present application is that the above problems are effectively solved. The present application changes the size of the K plate and redesigns the heightening piece, so that the structure and size of the heightening piece are more compact and can be installed on the beam between the K plate and the upper floating window plate, so that the heightening piece can be installed without waiting for the pouring of the vertical column of the floor level of the upper layer to be completed, so that the wall support and the heightening piece can be installed in the first time, so that each built floor covered by the climbing frame can be installed with a wall support through the heightening piece, so that the safety of the climbing frame is ensured, and the construction efficiency is improved. BRIEF DESCRIPTION OF DRAWINGS
[0028] Figure 1 is a schematic view when the floor level of the lower layer has been poured and the floor level of the upper layer has not been poured.
[0029] Figure 2 is a schematic view when the heightening piece is installed.
[0030] Figure 3 is a schematic view of the installation and use of the climbing frame.
[0031] Figure 4 is a schematic view of the structure of the heightening piece.
[0032] The drawings show: the upper floating window plate 10, the beam formwork 20, the K plate 30, the beam 40, the heightening piece 50, the first connecting plate 51, the first connecting hole 511, the second connecting plate 52, the horizontal connecting rod 53, the first reinforcing plate 54, the second reinforcing plate 55, the inclined connecting rod 56, the reinforcing plate 57, the wall support 60, the vertical column 70, the vertical column formwork 80, and the lower floating window plate 90.
Detailed Implementation Methods
[0033] The following embodiments are further explanations and supplements to the present invention and do not constitute any limitation on the present invention.
[0034] like Figures 1-3 As shown, the construction method for the climbing frame at the bay window of the present invention includes the following steps:
[0035] S1. A beam formwork 20 and a 150mm high K plate 30 are erected at the position of the exterior wall between the upper bay window slab 10 to be poured and the floor level. The top of the K plate 30 is above the floor level, and the bottom of the K plate 30 is below the floor level. The beam formwork 20 is located between the K plate 30 and the upper bay window slab 10 to be poured.
[0036] S2. Pour the floor below the floor level, and pour the upper bay window slab 10 and the beam 40 from the upper bay window slab 10 to the roof.
[0037] S3. Keep K plate 30 intact, and remove the beam formwork 20 and the formwork at the inner wall position of beam 40;
[0038] S4. Install the heightening component 50 at the outer wall position of the beam 40;
[0039] S5. Connect the wall-mounted support 60 of the climbing scaffold to the extension piece 50.
[0040] In step S1, the K-plate 30 is used to support the formwork 80 and the beam formwork 20. It can be installed between the building walls to be poured in two separate sections using known methods. The K-plate 30 is made of aluminum and has a height of 150mm. During installation, the top of the K-plate 30 is 50mm above the floor level, and the bottom 100mm of the K-plate 30 is below the floor level.
[0041] The dimensions of beam 40 vary depending on the building unit. Based on the height of beam 40 and the height of K-slab 30, the required number and dimensions of beam formwork 20 can be calculated. The dimensions of the beam formwork 20 are not limited and can be selected according to actual needs. The installation of the beam formwork 20 can refer to known techniques, and it is located between K-slab 30 and the upper bay window slab 10 to be poured.
[0042] To complete the pouring of the next floor at the next floor level, the required formwork is not only the K-slab 30 and beam formwork 20, but also the formwork at the interior wall position and other positions. The installation and dismantling of these formworks are no different from the existing process, and the present invention does not limit them.
[0043] When the formwork of the floor level of the next floor is set up, the pouring of the floor level of the next floor can be performed, so as to pour the upper balcony plate 10 and the beam 40 from the upper balcony plate 10 to the roof.
[0044] In step S2, the pouring method can refer to the known technology, and the embodiment does not limit it.
[0045] When the floor level of the next floor is poured, the formwork can be removed. When the formwork is removed, the K plate 30 is not removed, and the formwork at other positions can be removed, including but not limited to the beam formwork 20 and the corresponding formwork at the inner wall position of the beam 40.
[0046] When the beam formwork 20 and the formwork at the inner wall position of the beam 40 are removed, the through-wall bolt can be installed on the beam 40 to fix the heightening piece 50.
[0047] The heightening piece 50 is redesigned in the application, so that the height dimension is improved and can be installed on the beam 40. In the application, the height of the end of the heightening piece 50 installed on the beam 40 is less than 300 mm.
[0048] In addition, the height dimension of the K plate 30 is reduced, so that the wall between the K plate 30 and the upper balcony plate 10 is sufficient to install the heightening piece 50. Therefore, when the heightening piece 50 is installed, whether the vertical column 70 of the floor level of the next floor is poured or not, the heightening piece 50 can be installed after the pouring of the beam 40 is completed, so that the climbing frame can be connected to the wall without waiting for the pouring of the vertical column 70 to complete the second construction period, and the construction efficiency is improved.
[0049] As shown in Figure 4 The heightening piece 50 includes a first connecting plate 51, a second connecting plate 52 and a connecting assembly. The first connecting plate 51 and the second connecting plate 52 are parallel and spaced apart, and the connecting assembly is fixedly connected between the first connecting plate 51 and the second connecting plate 52.
[0050] The first connecting hole 511 is arranged on the first connecting plate 51 and is used for connecting with the beam 40. The second connecting hole is arranged on the second connecting plate 52 and is used for connecting with the wall-attached support 60. The first connecting hole 511 and the second connecting hole can be through holes or threaded holes, which can be arranged according to the needs.
[0051] The size and shape of the first connecting hole 511 and the second connecting hole can be arranged according to the needs. In the embodiment, the first connecting hole 511 and the second connecting hole are long strip-shaped runway holes, which are beneficial to facilitate the installation error.
[0052] The first connecting hole 511 and the second connecting hole can be set according to the requirement. In the embodiment, one first connecting hole 511 is arranged on the first connecting plate 51, and one second connecting hole is arranged on the second connecting plate 52.
[0053] The height of the first connecting plate 51 is less than the height of the second connecting plate 52. The height of the first connecting plate 51 is less than 300 mm and greater than 150 mm. The height of the second connecting plate 52 is less than 550 mm and greater than 300 mm. In the embodiment, the height of the first connecting plate 51 is 260 mm, and the height of the second connecting plate 52 is 420 mm.
[0054] The shape of the first connecting plate 51 and the second connecting plate 52 can be set according to the requirement. In the embodiment, the first connecting plate 51 and the second connecting plate 52 are rectangular steel plates.
[0055] The bottom ends of the first connecting plate 51 and the second connecting plate 52 are flush, and thus the top end of the second connecting plate 52 is higher than the top of the first connecting plate 51.
[0056] The horizontal height of the first connecting hole 511 is lower than the horizontal height of the second connecting hole.
[0057] The connecting assembly comprises a horizontal connecting rod 53, a first reinforcing plate 54, a second reinforcing plate 55, and an inclined connecting rod 56.
[0058] The horizontal connecting rod 53 is horizontally connected to the lower parts of the first connecting plate 51 and the second connecting plate 52. The horizontal connecting rod 53 is provided with multiple rods, which are perpendicular to the first connecting plate 51 and the second connecting plate 52 and are respectively fixedly connected to the first connecting plate 51 and the second connecting plate 52. In the embodiment, two horizontal connecting rods 53 are arranged between the first connecting plate 51 and the second connecting plate 52, which are parallel and spaced. In order to strengthen the structural strength, the horizontal connecting rod 53 is selected as a U-shaped steel, both ends of which are welded to the first connecting plate 51 and the second connecting plate 52, and the opening of the U-shaped steel faces two sides, so that the two wing plates of the U-shaped steel are in a horizontal state.
[0059] The first reinforcing plate 54 is fixedly connected between the first connecting plate 51 and the horizontal connecting rod 53. One end of the first reinforcing plate 54 is fixedly connected to the first connecting plate 51 perpendicularly, and the other end is fixedly connected to the wing plate of the horizontal connecting rod 53 perpendicularly. In the embodiment, the first reinforcing plate 54 is selected as a triangular steel plate, which is welded to the first connecting plate 51 and the horizontal connecting rod 53.
[0060] The second reinforcing plate 55 is fixedly connected between the second connecting plate 52 and the horizontal connecting rod 53. One end of the second reinforcing plate 55 is fixedly connected with the second connecting plate 52 perpendicularly, and the other end is fixedly connected with the wing plate of the horizontal connecting rod 53 perpendicularly. In the embodiment, the second reinforcing plate 55 is a triangular steel plate, which is welded with the second connecting plate 52 and the horizontal connecting rod 53.
[0061] The oblique connecting rod 56 is connected to the upper parts of the first connecting plate 51 and the second connecting plate 52, and is inclined at a certain angle with the first connecting plate 51 and the second connecting plate 52 respectively. The oblique connecting rod 56 is provided with a plurality of oblique connecting rods 56, which are inclined to the first connecting plate 51 and the second connecting plate 52 and are fixedly connected with the first connecting plate 51 and the second connecting plate 52 respectively. In the embodiment, one oblique connecting rod 56 is provided between the first connecting plate 51 and the second connecting plate 52, and is parallel and spaced. The oblique connecting rod 56 is an L-shaped steel plate, and the two ends thereof are welded with the first connecting plate 51 and the second connecting plate 52.
[0062] Further, the first connecting plate 51 is provided with a reinforcing plate 57 fixedly connected thereto on the side facing the second connecting plate 52. The reinforcing plate 57 is attached to and fixedly connected with the first connecting plate 51. The first connecting hole 511 penetrates the reinforcing plate 57, thereby facilitating installation and improving the strength of the connection. In the embodiment, the reinforcing plate 57 is a U-shaped steel plate.
[0063] In step S4, when the heightening piece 50 is installed at the outer wall position of the beam 40, the heightening piece 50 is fixed on the beam 40 by means of the through-wall bolt. Specifically, the through-wall bolt penetrates the first connecting hole 511 of the first connecting plate 51 and is fixed with the beam 40.
[0064] In step S5, when the wall-attached support 60 of the climbing frame is connected with the heightening piece 50, the wall-attached support 60 and the second connecting plate 52 of the heightening piece 50 are fixedly connected by means of the bolt. Specifically, the wall-attached support 60 is fixed at the second connecting hole by means of the bolt.
[0065] Further, after step S3, the following steps are further included:
[0066] S6, a vertical column formwork 80 is erected at the outer wall position between the K plate 30 and the lower casement 90;
[0067] S7, the floor level of the upper layer is poured, and the vertical column 70 of the lower casement 90 and the lower casement 90 to the floor level is poured.
[0068] In S6, the erection of the vertical column formwork 80 can refer to the known technology, and the embodiment is not limited thereto.
[0069] Before pouring the floor level on one side, the required formwork, not limited to the vertical column formwork 80, can be set up according to known technology, and the present embodiment does not limit it.
[0070] In the above steps, S1, S2, S3, S4, and S5 are sequential steps, and S6 and S7 are sequential steps. There is no sequence between S4, S5 and S6, S7, which can be arranged according to the actual situation. As a preferred, S4 and S5 are constructed in advance, and S6 and S7 are constructed in the rear. In this way, the wall-attached support 60 of the climbing frame can be connected with the heightening piece 50 in the fastest time, so as to ensure that each built floor covered by the climbing frame can be installed with a wall-attached support 60, thereby ensuring the safety of the climbing frame and ensuring the timeliness of the climbing frame. In some embodiments, S4 and S5 can be constructed simultaneously with S6 and S7.
[0071] Although the present application is disclosed through the above embodiments, the scope of the present application is not limited thereto, and each component above can be replaced by similar or equivalent elements known to those skilled in the art without departing from the concept of the present application.
Claims
1. A method of constructing a climbing frame at a bay window, characterized by, It comprises the following steps: S1, supporting a beam formwork (20) and a K plate (30) with a height of 150 mm at the outer wall position between the upper floating window plate (10) to be poured and the floor level, the top end of the K plate (30) is above the floor level and is 50 mm higher than the floor level, the bottom end of the K plate (30) is below the floor level, and the beam formwork (20) is located between the K plate (30) and the upper floating window plate (10) to be poured; S2, pouring the next floor below the floor level, pouring out the upper floating window plate (10) and the beam (40) from the upper floating window plate (10) to the roof; S3, retaining the K plate (30) without removing, removing the beam formwork (20) and the formwork at the inner wall position of the beam (40); S4, installing a heightening piece (50) on the outer wall position of the beam (40), the height of one end of the heightening piece (50) installed with the beam (40) is less than 300 mm; the heightening piece (50) comprises a first connecting plate (51), a second connecting plate (52) and a connecting assembly fixedly connected between the first connecting plate (51) and the second connecting plate (52), the height of the first connecting plate (51) is less than 300 mm, the height of the second connecting plate (52) is greater than 300 mm, and the lower ends of the first connecting plate (51) and the second connecting plate (52) are flush; S5, connecting the wall attachment support (60) of the climbing frame with the heightening piece (50).
2. The method of claim 1, wherein, After step S3, it further comprises: S6, supporting a door frame formwork (80) at the outer wall position from above the K plate (30) to the lower floating window plate (90); S7, pouring the next floor above the floor level, pouring out the lower floating window plate (90) and the door frame (70) from the lower floating window plate (90) to the floor level.
3. The method of claim 1, wherein, In step S4, when installing the heightening piece (50) on the outer wall position of the beam (40), the first connecting plate (51) of the heightening piece (50) is fixedly connected with the beam (40) through a wall bolt.
4. The method of claim 1, wherein, In step S5, when connecting the wall attachment support (60) of the climbing frame with the heightening piece (50), the second connecting plate (52) of the heightening piece (50) is fixedly connected with the wall attachment support (60) through a bolt.
5. The method of claim 1, wherein, A first connecting hole (511) is arranged on the first connecting plate (51), and a second connecting hole is arranged on the second connecting plate (52); a reinforcing plate (57) is fixedly connected to one side of the first connecting plate (51) facing the second connecting plate (52), and the first connecting hole (511) penetrates through the reinforcing plate (57).
6. The method of claim 1, wherein, The connecting assembly comprises: horizontal connecting rods (53) connected to the lower parts of the first connecting plate (51) and the second connecting plate (52) in parallel and vertically with the first connecting plate (51) and the second connecting plate (52); a first reinforcing plate (54) fixedly connected vertically at one end with the first connecting plate (51) and at one end with the top of the horizontal connecting rod (53); a second reinforcing plate (55) fixedly connected vertically at one end with the second connecting plate (52) and at one end with the top of the horizontal connecting rod (53); Oblique connecting rods (56) are connected to upper portions of the first and second connecting plates (51, 52) in parallel and at an angle with respect to the first and second connecting plates (51, 52), respectively.
Citation Information
Patent Citations
Climb frame and building structure is connected increases device
CN208534006U
Aluminum alloy K plate for bay window construction climbing frame support
CN211666235U