A cost assessment method, medium and equipment for power transmission and transformation project considering line loss

By using GIS and optimization algorithms in power transmission and transformation projects, considering the electromagnetic influence of environmentally sensitive areas and high-cost areas, optimizing the route of power transmission and transformation projects solves the problem of inaccurate cost assessment in the existing technology and achieves more accurate evaluation and efficient computing.

CN115760249BActive Publication Date: 2024-10-08STATE GRID NINGXIA ELECTRIC POWER CO LTD ECO TECH RES INST
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202211385815.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-11-07
Publication Date
2024-10-08
Estimated Expiration
2042-11-07

AI Technical Summary

Technical Problem

The electromagnetic impact of lines on the environment is not considered in the route planning of existing power transmission and transformation projects, resulting in inaccurate cost assessment and losing the significance of cost assessment.

Method used

By obtaining the starting point and end point information of the power transmission and transformation project, the environmentally sensitive areas are determined in the GIS geographical information system, the areas with unit cost greater than the threshold are screened out, the field strength information of the obstacles is counted, and the repulsive field cost function and deviation obstacles are constructed The cost function of the object is combined with the A-Star algorithm and the particle swarm optimization algorithm for path planning, and the optimal route is obtained for cost evaluation.

Benefits of technology

In route planning, full consideration is given to avoiding environmentally sensitive areas and high-cost areas, reducing electromagnetic influence, improving the accuracy of cost assessment, avoiding the problem of approaching obstacles first in route planning, and improving calculation efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115760249B_ABST
    Figure CN115760249B_ABST
Patent Text Reader

Abstract

The present invention proposes a method, medium and equipment for evaluating the cost of power transmission and transformation projects considering line loss, and relates to the technical field of power transmission and transformation projects. By obtaining and determining the environmental sensitive area information in the GIS geographic information system based on the starting point information and the end point information; obtaining and filtering out the areas with a unit price greater than a threshold value based on the unit price of the power transmission and transformation project in each area; obtaining obstacle information based on the environmental sensitive area information and the areas with a unit price greater than the threshold value; according to the coordinate position of the obstacle, statistically analyzing the surrounding field strength information; then constructing a repulsive field cost function and a cost function for deviation from obstacles; finally, adding the repulsive field cost function and the cost function for deviation from obstacles to the A‑Star algorithm, and combining with the particle swarm optimization algorithm, performing path planning, and then performing power transmission and transformation project cost evaluation, obtaining an evaluation result, and making the power transmission and transformation project cost evaluation more accurate.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of power transmission and transformation engineering, and in particular to a method, medium and equipment for evaluating the cost of power transmission and transformation engineering taking line loss into consideration. Background Art

[0002] With the development of social economy, the scale of power grid is expanding, and power companies are increasing their investment in power infrastructure and power transformation projects. The investment in power transmission and transformation projects is high and large in scale every year. In order to improve the economic benefits of power transmission and transformation project construction, it is necessary to conduct a reasonable cost assessment of the projects to be built, and provide strong support for investment cost control and cost optimization of each construction unit.

[0003] Since the cost assessment of power transmission and transformation projects is based on planned lines, the existing power transmission and transformation project route planning does not take into account the cost issues caused by the electromagnetic impact of the lines on the environment, resulting in an imbalance between the final cost and the environmental electromagnetic field, which in turn makes the cost assessment of power transmission and transformation projects inaccurate and loses its meaning. Summary of the invention

[0004] The purpose of the present invention is to provide a method, medium and equipment for cost assessment of power transmission and transformation projects taking line losses into consideration, so as to improve the cost problem caused by the failure to take into account the electromagnetic impact of the line on the environment in the route planning of the power transmission and transformation projects in the prior art, resulting in an imbalance between the final cost and the environmental electromagnetic field, making the cost assessment of the power transmission and transformation projects inaccurate.

[0005] In a first aspect, an embodiment of the present application provides a method for evaluating the cost of a power transmission and transformation project taking into account line losses, comprising the following steps:

[0006] Obtain the starting point information and end point information of the power transmission and transformation project;

[0007] According to the starting point information and the end point information, the environmental sensitive area information is determined in the GIS geographic information system;

[0008] Obtain the unit price of power transmission and transformation projects in various regions, and filter out regions where the unit price is greater than a threshold based on the unit price of power transmission and transformation projects;

[0009] Obtaining obstacle information according to the environmentally sensitive area information and the area where the unit price of the construction cost is greater than a threshold;

[0010] According to the coordinate position of the obstacle, statistical field strength information around the path is collected;

[0011] According to the starting point information, the end point information, the obstacle information and the field strength information around the path, the starting point coordinates, the end point coordinates and the obstacle coordinates are marked in the map, and a repulsive field cost function and a cost function for deviation from obstacles are constructed;

[0012] The repulsive field cost function and the obstacle deviation cost function are added to the A-Star algorithm, and combined with the particle swarm optimization algorithm to perform path planning to obtain the optimal route;

[0013] The cost of the power transmission and transformation project is evaluated according to the optimal route to obtain an evaluation result.

[0014] Based on the first aspect, in some embodiments of the present invention, the following steps are further included:

[0015] The Floyd algorithm is used to smooth the optimal route and obtain a new optimal path.

[0016] Based on the first aspect, in some embodiments of the present invention, the repulsive field cost function and the obstacle deviation cost function are added to the A-Star algorithm, and combined with the particle swarm optimization algorithm to perform path planning to obtain the optimal route, including the following steps:

[0017] Adding the repulsive field cost function and the obstacle deviation cost function into the A-Star algorithm to obtain an improved A-Star algorithm;

[0018] Parameter information in the repulsive field cost function and the obstacle deviation cost function is extracted, and the parameter information is used as a particle in the particle swarm optimization algorithm. Each particle is input into the improved A-Star algorithm to perform path optimization to obtain the optimal route.

[0019] Based on the first aspect, in some embodiments of the present invention, the repulsive field cost function is:

[0020]

[0021]

[0022]

[0023] Among them, F1(a) represents the repulsive field cost of node a; σ represents the repulsive force scale factor; L(a,m) represents the distance between the current node and the obstacle in the line planning; D represents the obstacle influence range, where D = P0R m ; P0 is the influence coefficient; R m is the radius of the obstacle; L(a,b) is the distance between the current node and the end point.

[0024] Based on the first aspect, in some embodiments of the present invention, the cost function of the deviation from the obstacle is:

[0025]

[0026]

[0027] Where μ is the scale factor of the deviation from the obstacle; L(m,ab) is the distance between the obstacle and the line connecting the current node and the end point; L(a,m,E) is the distance between the current node and the obstacle when the nominal field strength from the current node to the obstacle is higher than the threshold; P1R m represents the influence range of the obstacle; θ represents the angle between the obstacle and the starting point and the end point; E represents the nominal field strength from the current node to the obstacle, P1 is the influence coefficient, R m is the obstacle radius.

[0028] In a second aspect, an embodiment of the present application provides a computer-readable storage medium having a computer program stored thereon, and when the computer program is executed by a processor, the method as described in any one of the above-mentioned first aspects is implemented.

[0029] In a third aspect, an embodiment of the present application provides an electronic device, which includes a computer-readable storage medium as described in the second aspect above.

[0030] The embodiments of the present invention have at least the following advantages or beneficial effects:

[0031] The embodiment of the present invention provides a method, medium and device for evaluating the cost of a power transmission and transformation project considering line loss, which obtains the starting point information and the end point information of the power transmission and transformation project; determines and obtains the environmental sensitive area information in the GIS geographic information system according to the starting point information and the end point information; then obtains the unit price of the power transmission and transformation project in each region, and screens out the region with a unit price greater than a threshold according to the unit price of the power transmission and transformation project; obtains obstacle information according to the environmental sensitive area information and the region with a unit price greater than the threshold; and statistically analyzes the surrounding field strength information according to the coordinate position of the obstacle; then, according to the starting point information, the end point information and the obstacle information, marks the starting point coordinates, the end point coordinates and the obstacle coordinates and the surrounding field strength information in the map, and constructs a repulsive field cost function and a cost function for deviation from obstacles; finally, the repulsive field cost function and the cost function for deviation from obstacles are added to the A-Star algorithm, and combined with the particle swarm optimization algorithm, path planning is performed to obtain the optimal route, and the power transmission and transformation project cost is evaluated according to the optimal route to obtain an evaluation result. In the process of route planning, full consideration is given to avoiding environmentally sensitive areas, areas with unit costs greater than the threshold, and electromagnetic impacts on the surrounding areas, so that the resulting route avoids environmentally sensitive areas, areas with unit costs greater than the threshold, and can reduce electromagnetic impacts on the surrounding areas, so that the evaluation results are based on the planned route that takes into account the impact of line losses, making the cost evaluation of power transmission and transformation projects more accurate. At the same time, the repulsive characteristics of obstacles are applied to the A-Star algorithm, so that the planned path will be affected by obstacles. The algorithm will choose the direction with fewer obstacles on the premise of finding the minimum path cost. At the same time, combined with the particle swarm algorithm, the problem of approaching obstacles first in route planning is avoided, which reduces invalid calculations and improves calculation efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for use in the embodiments are briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without creative work.

[0033] Figure 1 A flow chart of a method for evaluating the cost of a power transmission and transformation project taking line losses into consideration provided by an embodiment of the present invention;

[0034] Figure 2 A structural block diagram of a power transmission and transformation project cost assessment system considering line losses provided by an embodiment of the present invention;

[0035] Figure 3 A relationship diagram of the current node, end point, and obstacle position in the route planning provided by the embodiment of the present invention;

[0036] Figure 4 A structural block diagram of an electronic device provided by an embodiment of the present invention.

[0037] Icons: 110 - starting information acquisition module; 120 - environmentally sensitive area information determination module; 130 - cost exceeding area determination module; 140 - obstacle determination module; 150 - field strength information statistics module; 160 - function construction module; 170 - path planning module; 180 - cost assessment module; 101 - memory; 102 - processor; 103 - communication interface. DETAILED DESCRIPTION

[0038] In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, rather than all the embodiments. The components of the embodiments of the present application described and shown in the drawings here can be arranged and designed in various different configurations.

[0039] Therefore, the following detailed description of the embodiments of the present application provided in the accompanying drawings is not intended to limit the scope of the present application for which protection is sought, but merely represents selected embodiments of the present application. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in the field without creative work are within the scope of protection of the present application.

[0040] In conjunction with the accompanying drawings, some embodiments of the present application are described in detail below. In the absence of conflict, the following embodiments and features in the embodiments can be combined with each other.

[0041] Please see Figure 1 , Figure 1A flow chart of a cost assessment method for a power transmission and transformation project considering line loss is provided in an embodiment of the present invention. The cost assessment method for a power transmission and transformation project considering line loss is used for cost assessment of a power transmission and transformation project considering line loss for voltages above 220kv. Power transmission and transformation projects above 220kv include substations and transmission lines. Substations have environmental problems of noise pollution; transmission lines have radio and high voltage electricity, which will have a negative impact on people and the environment. For example: the noise generated by transformer equipment is the main noise of substations, and overhead transmission lines will produce corona. When weather conditions are bad, audible noise will be emitted. The high-voltage equipment of the transformer will generate a certain power frequency electromagnetic field. When the equipment is operating normally, the main transformer and one side of the 220kv high-voltage incoming line become the main part of the electromagnetic impact. The power frequency electromagnetic field will cause electromagnetic environmental impact, affecting the lives and health of residents. For example: according to the evaluation standard of the environmental impact of power transmission and transformation, the evaluation standard of the power frequency electric field in residential areas is 4kV / M, and it is required that the power frequency limit of the public radiation throughout the day shall not exceed 0.1mT. Taking the above-mentioned environmental impacts into consideration, when planning the route, we can first establish environmentally sensitive areas and plan the route by avoiding environmentally sensitive areas, thereby reducing the subsequent construction costs for protecting the environment.

[0042] The cost assessment method for power transmission and transformation engineering considering line loss includes the following steps:

[0043] Step S110: Obtain the starting point information and the end point information of the power transmission and transformation project; the starting point information includes the starting point location, the starting point name and other information, and the end point information includes the end point location, the end point name and other information. The above information can be obtained based on the information of the power transmission and transformation project, can be manually input, or can be obtained by importing relevant information from other systems. For example: the power transmission and transformation project A transmits electricity from city A to city B, then the starting point information is city A, and the end point information is city B.

[0044] Step S120: According to the starting point information and the end point information, the environmentally sensitive area information is determined in the GIS geographic information system; the environmentally sensitive area refers to residential areas, nature reserves at all levels, scenic spots and other areas. If passing through these areas, it is necessary to increase the cost of protecting the environment and resettling personnel, which will lead to a high cost of the power transmission and transformation project. Therefore, when planning, the power transmission and transformation project lines need to avoid these areas as much as possible.

[0045] The above-mentioned environmentally sensitive area information includes the size of the environmentally sensitive area. The above-mentioned determination of the environmentally sensitive area information may be to obtain the actual environmentally sensitive area that appears between the starting point and the end point, or to add a buffer zone to the actual environmentally sensitive area according to the evaluation standard of the environmental impact of power transmission and transformation, so as to obtain the environmentally sensitive area information. For example: according to the evaluation standard of the environmental impact of power transmission and transformation, according to the electromagnetic impact range of the transmission line, the evaluation range is determined to be within the 30m strip area on both sides of the line, then according to this standard, a 30m strip buffer zone can be added outside the actual environmentally sensitive area to obtain the environmentally sensitive area information. It is also possible to set different buffer sizes according to experience based on different actual environmentally sensitive areas to obtain the environmentally sensitive area information, for example: if it is a residential area, add a 20m buffer zone, and if it is a scenic spot, add a 10m buffer zone.

[0046] In this embodiment, according to the starting point information and the end point information, the GIS geographic information system can be accessed by using the spatial index technology, and then the corresponding environmentally sensitive area information can be read. The above environmentally sensitive area information can be obtained by means of information on the map, intelligent identification or prediction, and there is no specific limitation. The above intelligent identification or prediction of environmentally sensitive areas can be achieved by using existing technologies, which will not be described in detail here.

[0047] Step S130: Obtain the unit price of the power transmission and transformation project of the crossing path in each region, and select the regions where the unit price is greater than a threshold according to the unit price of the power transmission and transformation project;

[0048] It should be noted that the above-mentioned unit price of power transmission and transformation project construction refers to the unit price of power transmission and transformation project construction on the path of the planned line in the area between the starting point and the end point. The above-mentioned unit price of power transmission and transformation project construction refers to the price per unit distance of power transmission and transformation project construction in the area. Since the labor costs, geographical environment, etc. of each region are different, the unit price of power transmission and transformation project construction in each region is also different.

[0049] In this embodiment, the process of screening out areas where the unit price of the cost is greater than the threshold value can be to pre-set a threshold value, compare the unit price of the power transmission and transformation project in each area with the threshold value, and screen out areas where the unit price of the cost is greater than the threshold value. The above threshold value can be set according to experience or project cost requirements. The screened areas where the unit price of the cost is greater than the threshold value may cause the cost of the power transmission and transformation project to exceed the standard in the later stage. In order to avoid the cost exceeding the standard as much as possible, when designing the line, it is necessary to avoid these areas as much as possible, so that the path planning is as balanced as possible between avoidance and cost.

[0050] Step S140: Obtain obstacle information based on the environmentally sensitive area information and the area where the unit price of the construction cost is greater than the threshold value; in order to avoid excessively high costs for power transmission and transformation projects, environmentally sensitive areas and areas where the unit price of the construction cost is greater than the threshold value should be avoided as much as possible when designing the line. In this embodiment, in order to facilitate the later line planning, environmentally sensitive areas and areas where the unit price of the construction cost is greater than the threshold value can be regarded as obstacles. According to the environmentally sensitive area information and the area where the unit price of the construction cost is greater than the threshold value, the obstacle information in these areas can be obtained. The above obstacle information includes information such as the location, size, and shape of the obstacle. Furthermore, in each area, a specific building, intersection, or street can also be identified as an obstacle and brought into the path planning of the embodiment of the present invention.

[0051] Step S150: According to the coordinate position of the obstacle, which can be a GPS coordinate point or an area composed of multiple coordinate points, the field strength information around the coordinate point or the composed area is counted; in order to make the planned path reduce the electromagnetic impact on the surroundings, especially the impact on the human body, when planning, areas that are sensitive to electromagnetic impacts (such as living areas, airports, radio / mobile base stations, etc.) can be marked and used as obstacles. The above-mentioned surrounding field strength information can be the nominal field strength, and the mirror method can be used to estimate the nominal field strength at each sensitive area point. The calculation of the nominal field strength is described in detail below and will not be repeated here.

[0052] Step S160: marking the starting point coordinates, the ending point coordinates and the obstacle coordinates in the map according to the starting point information, the ending point information and the obstacle information and the field strength information of the surrounding areas, and constructing a repulsive field cost function and a cost function for deviation from obstacles;

[0053] In this embodiment, the map may be further marked according to the starting point information, the end point information and the obstacle information, and may be marked in different colors or highlighted for distinction, which is not limited in this embodiment. A coordinate system is constructed in the map, and the above-mentioned marking includes center coordinate marking, shape marking, etc., and the above-mentioned obstacle coordinates include center point coordinates, shape coordinates, etc. The coordinates can be used to quickly determine the location of the starting point, end point and obstacle of the path planning.

[0054] The purpose of constructing the repulsive field cost function is to avoid dense obstacles during route planning, and it can be constructed based on the idea of ​​an artificial force field algorithm. Figure 3 , Figure 3 The relationship diagram of the current node, end point, and obstacle position in the route planning provided by the embodiment of the present invention. If the coordinates of the starting point A are (x a ,y a ), the coordinates of the end point B are (x b ,y b), the coordinates of obstacle M are (x m ,y m ), the constructed repulsive field cost function is:

[0055]

[0056]

[0057]

[0058] Among them, F1(a) represents the repulsive field cost of node a, and node a refers to the point that forms the path during the path planning process; σ represents the repulsive scale factor. According to the idea of ​​the artificial force field algorithm, obstacles have a repulsive effect on the points on the path. It can be set according to the actual situation, generally set in the range of 0.1-2. The repulsive scale factor affects the cost of the repulsive field. The gap between the cost of the A-Star algorithm and the repulsive force can be reduced by adjusting the size of the repulsive scale factor; L(a,m) represents the distance between the node and the obstacle at the current location of the route planning; D represents the obstacle influence range, where D = P0R m ; P0 is the influence coefficient; R m is the radius of the obstacle; L(a,b) is the distance between the current node and the end point.

[0059] In the calculation process, due to the characteristics of heuristic search, the path will always search towards the target point first, and then search to both sides after encountering obstacles. In other words, the path will prioritize approaching obstacles, which will lead to more redundant points on the path, which is not conducive to fast path planning. Constructing a cost function for deviation from obstacles can improve the problem of preferentially approaching obstacles. The cost function for deviation from obstacles constructed above is:

[0060]

[0061]

[0062] Among them, μ is the obstacle deviation scale factor, which can be set according to the actual situation. The value range is generally between 0.1 and 2. The larger the value, the greater the proportion of the cost function F2(a) in the cost value of the A-Star algorithm, which will make the path deviate more from the obstacle between the starting point and the end point; L(m, ab) is the distance between the obstacle and the line connecting the current node and the end point; L(a, m, E) is the distance between the current node and the obstacle when the nominal field strength from the current node to the obstacle is higher than the threshold; P1R m represents the influence range of obstacles on path planning; θ represents the angle between the obstacle and the starting point, and the starting point and the end point; E represents the nominal field strength between the current node and the obstacle, P1 is the influence coefficient, and R mis the obstacle radius.

[0063] Among them, P1R m ,θ lim All of them are F2(a) restriction conditions. When the nominal field strength from the current node to the obstacle is higher than the threshold, the distance between the current node and the obstacle is P1R m In θ lim Obstacles within the angle range will take effect. After adding the cost function, each obstacle within the range will have an impact on the node. The greater the nominal field strength from the current node to the obstacle, the greater the impact of the obstacle. When planning the route, it deviates in advance, so it is preferred to search towards the side that deviates from the obstacle, avoiding the problem of approaching the obstacle first, and reducing invalid calculations. The calculation of the nominal field strength will be described in detail below, so I will not go into details here.

[0064] Step S170: Add the repulsive field cost function and the obstacle deviation cost function to the A-Star algorithm, and combine with the particle swarm optimization algorithm to perform path planning to obtain the optimal route. Specifically, the following steps are included:

[0065] First, the repulsive field cost function and the cost function of the deviation obstacle are added to the A-Star algorithm to obtain an improved A-Star algorithm; in this embodiment, the repulsive field cost function and the cost function of the deviation obstacle are added to the original A-Star algorithm to obtain an improved A-Star algorithm. The A-Star algorithm is the most effective direct search method for solving the shortest path in a static road network, and is also an effective algorithm for solving many search problems. The above-mentioned A-Star algorithm belongs to the prior art and will not be repeated here.

[0066] Then, the parameter information in the repulsive field cost function and the obstacle deviation cost function is extracted, and the parameter information is used as a particle in the particle swarm optimization algorithm. Each particle is input into the improved A-Star algorithm to perform path optimization to obtain the optimal route.

[0067] In this embodiment, there are four parameters that need to be optimized in the above-mentioned improved A-Star algorithm, namely, the parameter information in the cost function of the repulsive field and the cost function of the deviation from the obstacle. The above-mentioned parameter information includes σ, P0, μ, and P1. Combined with the particle swarm algorithm, the four parameters constitute a particle, and then each particle is input into the improved A-Star algorithm, and the optimization target of the planned path is calculated and saved, so as to evaluate the paths planned by all particles and select the current optimal particle. Then the particle is updated to move toward the optimal target, that is, the particle is moved toward the target with the optimal path planned by the particle, and the global optimal solution is found after multiple cycles, that is, the parameters corresponding to the optimal path of the improved A-Star algorithm. In the calculation process, the optimal solution needs to be selected based on the evaluation of the quality of the path. In order to ensure that the path is as short as possible and avoid obstacles better, the path length and the amount of calculation can be used as optimization targets. Therefore, the set optimization objective functions are:

[0068] Path Length: Where n is the number of path points, (x i ,y i ) is the path coordinate of point i, L ab is the path length, and the path points here refer to the various nodes in the process of path planning.

[0069] Calculation amount: the number of nodes traversed during the path planning process. Finally, the path length and the calculation amount are weighted and summed to obtain the total objective function value, and the minimum total objective function value is selected as the optimal objective function value.

[0070] The above-mentioned particle swarm algorithm is combined with the A-Star algorithm to obtain different paths through the movement of particles, and then obtain the optimal path, which specifically includes the following steps:

[0071] First, initialize the number of iterations, the number of independent variables, the number of particles, the individual learning factor, the social learning factor, the inertia factor, the particle wandering range, the particle initial position and the initial velocity. Among them, the independent variables of the particles include σ, P0, μ, and P1, and their corresponding ranges and particle wandering ranges are: σ range: 0.1-2; P0 range: 1-12; μ range: 0.1-2, P1 range: 1-4.

[0072] Then define the fitness function, bring each particle into the A-Star algorithm, plan the path, calculate the evaluation values ​​of the path, including path length, calculation amount, etc., and normalize the evaluation values ​​corresponding to all particles, and then use the weighted average method to calculate the fitness;

[0073] Then find the historical best fitness and corresponding position of individuals and groups;

[0074] Finally, the particle speed and particle position are updated, and the particles that are out of range are resampled near the historical best position of the group until the number of iterations or the optimal constraint condition is reached, and the particle swarm algorithm is exited. In order to reduce the electromagnetic impact on the surroundings, especially on the human body, the areas sensitive to electromagnetic impact (such as living areas, airports, radio / mobile base stations, etc.) can be marked and used as obstacles during planning. In the process of calculating the optimal path of the improved A-Star algorithm, in order to ensure that the path is as short as possible and avoid obstacles, the path length and the minimum field strength of each sensitive area point can also be used as the optimization target.

[0075] The optimization objective function set includes path length and field strength, wherein the expression of path length is the same as the expression of path length function used when path length and calculation amount are used as optimization objectives, and will not be repeated here. The field strength can be a nominal field strength, and the nominal field strength at each sensitive area point can be estimated by the mirror method. The above nominal field strength is:

[0076]

[0077]

[0078] Among them, x t ,y t is the coordinate of the wire t; s is the number of wires; R t and R' t are the distances from the wire t and its mirror image to the points in each sensitive area, E x and E y are the components of the electric field along the x-axis and y-axis, ε0 is the dielectric constant of air, Q t is the equivalent charge on the unit wire of wire t.

[0079] Finally, the path length and field strength are weightedly summed to obtain the total objective function value, and the minimum value of the total objective function value is selected as the optimal objective function value.

[0080] Step S180: Evaluate the power transmission and transformation project cost according to the optimal route to obtain an evaluation result. In this embodiment, the optimal route is used as the planning path, and then the project cost is calculated based on the planning path. Finally, the obtained project cost is compared with the preset project cost threshold to obtain a comparison result. The above-mentioned project cost threshold can be estimated by technical personnel with reference to the settlement value of historical power transmission and transformation projects of the same type, similar or same economic indicators. The comparison result includes exceeding the threshold, being lower than the threshold, etc. According to the comparison result, an evaluation result can be obtained. The above-mentioned calculation of the project cost can be obtained by using the existing cost software in the prior art.

[0081] In the above implementation process, the starting point information and the end point information of the power transmission and transformation project are obtained; according to the starting point information and the end point information, the environmental sensitive area information is determined in the GIS geographic information system; then the unit price of the power transmission and transformation project in each area is obtained, and the area with the unit price greater than the threshold is screened out according to the unit price of the power transmission and transformation project; according to the environmental sensitive area information and the area with the unit price greater than the threshold, the obstacle information is obtained; according to the coordinate position of the obstacle, the surrounding field strength information is counted; then according to the starting point information, the end point information and the obstacle information and the surrounding field strength information, the starting point coordinates, the end point coordinates and the obstacle coordinates are marked in the map, and the repulsion field cost function and the cost function of deviation from the obstacle are constructed; finally, the repulsion field cost function and the cost function of deviation from the obstacle are added to the A-Star algorithm, and combined with the particle swarm optimization algorithm, path planning is performed to obtain the optimal route; the power transmission and transformation project cost is evaluated according to the optimal route to obtain the evaluation result. In the process of route planning, full consideration is given to avoiding environmentally sensitive areas, areas with unit costs greater than the threshold, and electromagnetic impacts on the surrounding areas, so that the resulting route avoids environmentally sensitive areas, areas with unit costs greater than the threshold, and can reduce electromagnetic impacts on the surrounding areas, so that the evaluation results are based on the planned route that takes into account the impact of line losses, making the cost evaluation of power transmission and transformation projects more accurate. At the same time, the repulsive characteristics of obstacles are applied to the A-Star algorithm, so that the planned path will be affected by obstacles. The algorithm will choose the direction with fewer obstacles on the premise of finding the minimum path cost. At the same time, combined with the particle swarm algorithm, the problem of approaching obstacles first in route planning is avoided, which reduces invalid calculations and improves calculation efficiency.

[0082] In order to make the obtained path smoother, a smoothing process may be performed, which specifically includes the following steps: using the Floyd algorithm to perform path smoothing on the optimal line to obtain a new optimal path.

[0083] The above-mentioned Floyd algorithm is one of the effective methods to solve the shortest path problem. It has the characteristics of dynamic programming. When smoothing, the algorithm can be used to find the turning points of the path and complete the path points between the turning points. If the path turning points are straight lines and there are no obstacles, the turning points can be determined by judging whether there are obstacles between the two path points. At the same time, it is necessary to judge whether there are obstacles in the area formed by the smoothed path and the optimal line, so as to obtain a new optimal path. The use of the Floyd algorithm can greatly improve the smoothness of the path, and without changing the obstacle avoidance function and the direction of the path, the path length is reduced, which can further reduce the cost of the power transmission and transformation project. There may be multiple turning points on the optimal line. In order to smooth the path, the Floyd algorithm is used to smooth the path, including the following steps:

[0084] First, initialize the total number of optimizations and the number of forward path optimizations; then initialize the path starting point as the starting point of the current optimal route and the end point as the current end point; then check whether there are obstacles on the line connecting the current starting point and the current end point. If there are obstacles, take the end point on the original path as the current end point and recheck whether there are obstacles; if there are no obstacles, generate and save the path from the current starting point to the end point, move the current end point back one point according to the original path, and check again whether there are obstacles on the line connecting the starting point to the end point. If there are no obstacles, generate and save the path from the current starting point to the end point, and exit when there are obstacles; construct the saved path into a new path. If the current end point is the end point of the original path, complete the path optimization, otherwise take the current end point as the current starting point and the original end point as the current end point, and recheck whether there are obstacles. Finally, determine whether the total number of optimizations has been reached. If so, complete the path optimization. If not, further determine whether the forward optimization times have been reached. If not, continue to optimize. If so, invert the path to form a new path, reset the forward optimization times, and continue to optimize.

[0085] Based on the same inventive concept, the present invention also proposes a power transmission and transformation project cost evaluation system taking line loss into consideration, which can implement all the method steps in the embodiment. Figure 2 , Figure 2 A structural block diagram of a power transmission and transformation project cost assessment system considering line loss provided by an embodiment of the present invention, the power transmission and transformation project cost assessment system considering line loss includes:

[0086] The starting information acquisition module 110 is used to obtain the starting point information and the end point information of the power transmission and transformation project;

[0087] An environmentally sensitive area information determination module 120, configured to determine the environmentally sensitive area information in a GIS geographic information system according to the starting point information and the end point information;

[0088] The cost exceeding area determination module 130 is used to obtain the unit price of the power transmission and transformation project in each area, and screen out the areas where the unit price is greater than the threshold according to the unit price of the power transmission and transformation project;

[0089] The obstacle determination module 140 is used to obtain obstacle information according to the environmentally sensitive area information and the area where the unit price of the construction cost is greater than a threshold;

[0090] A field strength information statistics module 150, used to count the field strength information around the path according to the coordinate position of the obstacle;

[0091] A function construction module 160, for marking the starting point coordinates, the ending point coordinates and the obstacle coordinates in the map according to the starting point information, the ending point information and the obstacle information and the field strength information around the path, and constructing a repulsive field cost function and a cost function for deviation from obstacles;

[0092] The path planning module 170 is used to add the repulsive field cost function and the obstacle deviation cost function into the A-Star algorithm, and combine the particle swarm optimization algorithm to perform path planning to obtain the optimal route.

[0093] The cost assessment module 180 is used to perform a cost assessment on the power transmission and transformation project according to the optimal route to obtain an assessment result.

[0094] In the above implementation process, the starting point information and the end point information of the power transmission and transformation project are obtained through the starting information acquisition module 110; the environmental sensitive area information determination module 120 determines the environmental sensitive area information in the GIS geographic information system according to the starting point information and the end point information; the cost exceeding area determination module 130 obtains the unit price of the power transmission and transformation project in each area, and screens out the area with the unit price greater than the threshold according to the unit price of the power transmission and transformation project; the obstacle determination module 140 obtains the obstacle information according to the environmental sensitive area information and the area with the unit price greater than the threshold; the field strength information statistics module 150 obtains the obstacle information according to the obstacle The coordinate position of the object is calculated, and the field strength information of the surrounding area is counted; the function construction module 160 marks the starting point coordinates, the end point coordinates and the obstacle coordinates in the map according to the starting point information, the end point information and the obstacle information and the field strength information of the surrounding area, and constructs the repulsive field cost function and the cost function of deviation from the obstacle; the path planning module 170 adds the repulsive field cost function and the cost function of deviation from the obstacle to the A-Star algorithm, and combines the particle swarm optimization algorithm to perform path planning to obtain the optimal route, and the cost evaluation module 180 performs the cost evaluation of the power transmission and transformation project according to the optimal route to obtain the evaluation result. In the process of route planning, full consideration is given to avoiding environmentally sensitive areas, areas with a unit price greater than a threshold, and electromagnetic influence on the surrounding area, so that the route obtained avoids environmentally sensitive areas, areas with a unit price greater than a threshold, and can reduce electromagnetic influence on the surrounding area, so that the evaluation result is based on the planned route considering the influence of line loss, making the cost evaluation of the power transmission and transformation project more accurate. At the same time, the repulsive characteristics of obstacles are applied to the A-Star algorithm, so that the planned path will be affected by obstacles. The algorithm will choose the direction with fewer obstacles while finding the lowest path cost. At the same time, combined with the particle swarm algorithm, it avoids the problem of approaching obstacles first in route planning, reduces invalid calculations, and improves calculation efficiency.

[0095] See also Figure 4 , Figure 4 A schematic structural block diagram of an electronic device provided in an embodiment of the present application. The electronic device includes a memory 101, a processor 102 and a communication interface 103, and the memory 101, the processor 102 and the communication interface 103 are electrically connected to each other directly or indirectly to realize data transmission or interaction. For example, these elements can be electrically connected to each other through one or more communication buses or signal lines. The memory 101 can be used to store software programs and modules, such as program instructions / modules corresponding to a power transmission and transformation project cost assessment system considering line losses provided in an embodiment of the present application. The processor 102 executes various functional applications and data processing by executing software programs and modules stored in the memory 101. The communication interface 103 can be used to communicate signaling or data with other node devices.

[0096] Among them, the memory 101 can be, but is not limited to, a random access memory (RAM), a read only memory (ROM), a programmable read-only memory (PROM), an erasable programmable read-only memory (EPROM), an electrically erasable read-only memory (EEPROM), etc.

[0097] The processor 102 may be an integrated circuit chip with signal processing capability. The processor 102 may be a general-purpose processor, including a central processing unit (CPU), a network processor (NP), etc.; it may also be a digital signal processor (DSP), an application specific integrated circuit (ASIC), a field programmable gate array (FPGA), or other programmable logic devices, discrete gate or transistor logic devices, or discrete hardware components.

[0098] Understandably, Figure 4 The structure shown is for illustration only. The electronic device may also include Figure 4 More or fewer components as shown, or with Figure 4 Different configurations are shown. Figure 4Each component shown in the figure can be implemented by hardware, software or a combination thereof.

[0099] In the embodiments provided in the present application, it should be understood that the disclosed devices and methods can also be implemented in other ways. The device embodiments described above are merely schematic. For example, the flowcharts and block diagrams in the accompanying drawings show the possible architecture, functions and operations of the devices, methods and computer program products according to the multiple embodiments of the present application. In this regard, each box in the flowchart or block diagram can represent a module, a program segment or a part of a code, and the module, a program segment or a part of a code contains one or more executable instructions for implementing the specified logical function. It should also be noted that in some alternative implementations, the functions marked in the box can also occur in a different order from the order marked in the accompanying drawings. For example, two consecutive boxes can actually be executed substantially in parallel, and they can sometimes be executed in the opposite order, depending on the functions involved. It should also be noted that each box in the block diagram and / or the flowchart, and the combination of boxes in the block diagram and / or the flowchart can be implemented with a dedicated hardware-based system that performs a specified function or action, or can be implemented with a combination of dedicated hardware and computer instructions.

[0100] In addition, the functional modules in the various embodiments of the present application may be integrated together to form an independent part, or each module may exist separately, or two or more modules may be integrated to form an independent part.

[0101] If the functions are implemented in the form of software function modules and sold or used as independent products, they can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present application can be essentially or partly embodied in the form of a software product that contributes to the prior art. The computer software product is stored in a storage medium, including several instructions to enable a computer device (which can be a personal computer, a server, or a network device, etc.) to perform all or part of the steps of the methods described in each embodiment of the present application. The aforementioned storage medium includes: various media that can store program codes, such as a USB flash drive, a mobile hard disk, a read-only memory (ROM), a random access memory (RAM), a magnetic disk or an optical disk.

[0102] The above description is only the preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.

[0103] It will be apparent to those skilled in the art that the present application is not limited to the details of the exemplary embodiments described above, and that the present application can be implemented in other specific forms without departing from the spirit or essential features of the present application. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the present application is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims be included in the present application. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.

Claims

1. A method for evaluating the cost of power transmission and transformation projects taking line losses into consideration, characterized in that: The following steps are involved: Obtain the starting point information and end point information of the power transmission and transformation project; According to the starting point information and the end point information, the environmental sensitive area information is determined in the GIS geographic information system; Obtain the unit price of power transmission and transformation projects in various regions, and filter out regions where the unit price is greater than a threshold based on the unit price of power transmission and transformation projects; Obtaining obstacle information according to the environmentally sensitive area information and the area where the unit price of the construction cost is greater than a threshold; According to the coordinate position of the obstacle, statistical field strength information around the path is collected; According to the starting point information, the end point information, the obstacle information and the field strength information around the path, the starting point coordinates, the end point coordinates and the obstacle coordinates are marked in the map, and a repulsive field cost function and a cost function for deviation from obstacles are constructed; wherein the repulsive field cost function is: Among them, F1(a) represents the repulsive field cost of node a; σ represents the repulsive force scale factor; L(a,m) represents the distance between the current node and the obstacle in the line planning; D represents the obstacle influence range, where D = P0R m ; P0 is the influence coefficient; R m is the radius of the obstacle; L(a,b) is the distance between the current node and the end point; The cost function of the deviation from the obstacle is: Where μ is the scale factor of the deviation from the obstacle; L(m,ab) is the distance between the obstacle and the line connecting the current node and the end point; L(a,m,E) is the distance between the current node and the obstacle when the nominal field strength from the current node to the obstacle is higher than the threshold; P1R m represents the influence range of the obstacle; θ represents the angle between the obstacle and the starting point and the end point; E represents the nominal field strength from the current node to the obstacle, P1 is the influence coefficient, R m is the obstacle radius; (x a ,y a ) is the starting point coordinate, (x b ,y b ) is the end point coordinate, (x m ,y m ) are the obstacle coordinates; The repulsive field cost function and the obstacle deviation cost function are added to the A-Star algorithm, and combined with the particle swarm optimization algorithm to perform path planning to obtain the optimal route; The cost of the power transmission and transformation project is evaluated according to the optimal route to obtain an evaluation result.

2. The method for evaluating the cost of power transmission and transformation projects considering line loss according to claim 1 is characterized in that: The following steps are also included: The Floyd algorithm is used to smooth the optimal route and obtain a new optimal path.

3. The method for evaluating the cost of power transmission and transformation projects considering line loss according to claim 1, characterized in that: The repulsive field cost function and the obstacle deviation cost function are added to the A-Star algorithm, and combined with the particle swarm optimization algorithm to perform path planning to obtain the optimal route, including the following steps: Adding the repulsive field cost function and the obstacle deviation cost function into the A-Star algorithm to obtain an improved A-Star algorithm; Parameter information in the repulsive field cost function and the obstacle deviation cost function is extracted, and the parameter information is used as a particle in the particle swarm optimization algorithm. Each particle is input into the improved A-Star algorithm to perform path optimization to obtain the optimal route.

4. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the method according to any one of claims 1 to 3 is implemented.

5. An electronic device, characterized in that: include: A processor is provided for reading the computer readable storage medium as claimed in claim 4.

Citation Information

Patent Citations

  • Transmission and transformation project construction cost assessment method and device

    CN103440370A

  • Power transmission line state evaluation method and device, computer device and memory medium

    CN108471114A

  • A*algorithm-based path planning method

    CN109443364A

  • Unmanned ship path planning method based on potential field parameter optimization

    CN112099501A

  • Global dynamic smooth path planning method based on optimized A-STAR algorithm

    CN114166235A