A pre-laid structure of a waterproof coiled material and a method for reverse adhesion construction
By setting up slurry holes, grooves and positioning grooves in the pre-paved structure of the waterproof roll, combined with cement mortar filling and easy-to-tear wire technology, the problems of misalignment and poor bonding in the construction of the waterproof roll are solved, and efficient waterproof construction results are achieved.
Patent Information
- Application Number
- CN202211521982.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-11-30
- Publication Date
- 2025-07-01
- Estimated Expiration
- 2042-11-30
AI Technical Summary
In the construction of traditional waterproof coils, the waterproof layer and structural gaps are easily separated, resulting in water flow and difficulty in repair. The single-sided waterproof coil is easily misaligned, cracked or leaked, and the double-sided adhesive coil is not easy to flatten.
The waterproof coil pre-lay structure is adopted. By setting slurry holes and grooves between the base layer and the auxiliary waterproof layer, filling with cement mortar, fixing the waterproof coil with positioning grooves and positioning strips, and using easy-to-tear wire to retain the isolation layer to avoid construction misalignment and poor bonding.
It improves the constructionability and adhesion effect of waterproof coils, reduces construction difficulty, prevents misalignment and leaks, enhances the adaptability and reliability of the waterproof layer, and simplifies the construction process.
Smart Images

Figure CN115787745B_ABST
Abstract
Description
Technical Field
[0001] This application relates to the technical field of waterproof construction, and particularly relates to a pre-laid structure of waterproof coiled material and an anti-adhesion construction method. Background Art
[0002] At present, the general method for basement waterproof construction is to set a concrete cushion and cement mortar on the plain soil layer, then paste asphalt waterproof coiled material, then set a concrete protective layer, and finally pour a waterproof reinforced concrete floor slab and a building surface layer. Through the double waterproofing of the asphalt waterproof coiled material and the waterproof reinforced concrete floor slab, however, in the traditional construction method, the waterproof coiled material is often pasted or laid empty on the base layer, and the gap between the waterproof layer and the structure body causes the separation of the waterproof layer and the structure. Once the waterproof layer is damaged, water flows around, and it is not easy to find the leakage point, and the repair is very difficult, and even may cause the overall failure of the waterproof layer. Summary of the Invention
[0003] In order to achieve the above object, this application provides a pre-laid structure of waterproof coiled material and an anti-adhesion construction method.
[0004] A pre-laid structure of waterproof coiled material provided by this application adopts the following technical solutions:
[0005] A pre-laid structure of waterproof coiled material includes a base layer, a wall is erected on the base layer, there is an included angle between the base layer and the wall, an auxiliary waterproof layer is provided on the included angle, cement mortar is filled between the auxiliary waterproof layer and the included angle, a grouting hole is provided at the upper part of the auxiliary waterproof layer, a blocking part is provided at the lower end of the auxiliary waterproof layer, a groove matching with the blocking part is provided on the base layer, an additional waterproof layer is attached to the outside of the auxiliary waterproof layer, a waterproof coiled material is attached to the outside of the additional waterproof layer, a first positioning groove is provided on the base layer, a first positioning strip is provided in the first positioning groove, the first positioning strip has a first inner cavity, the first inner cavity has an opening, and the two side walls of the first inner cavity near the opening are concave inward to form a constriction section, and a continuous waterproof coiled material is accommodated inside the first inner cavity.
[0006] By adopting the above technical solutions, an auxiliary waterproof layer is provided between the additional waterproof layer and the internal corner detail. By using the matching structure of the grouting hole on the auxiliary waterproof layer and the groove on the base layer, the filling space of the cement mortar is fixed, so that the filling amount of the cement mortar is easier to control and the construction difficulty is reduced, avoiding the situation that the cement mortar is laid unevenly, the additional waterproof layer is skew, wrinkled or even bulged after being pasted; at the same time, a section of waterproof coiled material is accommodated inside the first inner cavity of the first positioning groove, which has a certain positioning effect on the waterproof coiled material, and can prevent the waterproof coiled material from being deformed, misaligned, wrinkled, etc. caused by workers walking on the waterproof coiled material or dragging building materials during construction. The reserved expansion space enables the waterproof coiled material to have higher adaptability to the expansion or cracking deformation of the building layer. Compared with traditional gluing, the waterproof coiled material can be leveled after being pasted, avoiding wrinkles and bulges. At the same time, the detachable structure makes the waterproof coiled material easier to adjust, improving the constructability.
[0007] Preferably, the upper surface of the waterproof coiled material is provided with an upper adhesive surface, the upper adhesive surface is provided with a separation layer, and a first easy tear line is provided at a position of the separation layer close to the first positioning groove.
[0008] By adopting the above technical solution, an upper adhesive surface is arranged on the upper surface of the waterproof coiled material, so that the waterproof coiled material is integrated with the upper cast-in-place concrete surface, avoiding the hidden danger of water seepage in the middle. At the same time, due to the arrangement of the first easy tear line, the separation layer can be reserved during construction and then torn off according to the construction situation. Compared with directly tearing off the separation layer and sprinkling cement powder in the traditional construction, there is no influence of cement powder, and the bonding effect between the waterproof coiled material and the concrete surface is better.
[0009] Preferably, the upper surface of the separation layer is provided with anti-slip convex lines.
[0010] By adopting the above technical solution, when the separation layer is reserved, the friction between the construction personnel and the surface of the separation layer is increased, enhancing the construction safety.
[0011] Preferably, a connecting block is arranged on the upper adhesive surface of the upper part of the waterproof coiled material that abuts against the wall, one end of a pull rope is connected to the connecting block, and the other end of the pull rope is connected to the wall or a bracket.
[0012] By adopting the above technical solution, the vertical waterproof coiled material is fixed to prevent the waterproof coiled material from sagging.
[0013] Preferably, the separation layer is divided into an anti-adhesive layer and a puncture-resistant layer, and the puncture-resistant layer can adopt a high-density polyethylene geomembrane.
[0014] By adopting the above technical solution, the anti-adhesive layer is composed of an adhesive film and a bottom layer, and the puncture-resistant layer is adhesively bonded to the upper surface of the bottom layer. The puncture-resistant layer can reduce the damage to the waterproof coiled material that is easily caused due to the lack of a protective layer during construction.
[0015] Preferably, the waterproof coiled material at least includes a first waterproof coiled material sheet and a second waterproof coiled material sheet. An overlapping lapping portion is arranged between the first waterproof coiled material sheet and the second waterproof coiled material sheet. A second positioning groove is arranged in the base layer below the lapping portion, a second positioning strip is arranged in the second positioning groove, the second positioning strip is provided with a second inner cavity, and the space of the second inner cavity is larger than that of the first inner cavity.
[0016] By adopting the above technical solution, adjacent waterproof coiled material sheets are fixed by the second positioning strip, strengthening the lapping part of the waterproof coiled material and the overall waterproof effect.
[0017] Preferably, the auxiliary waterproof layer is annular.
[0018] By adopting the above technical solution, the annular auxiliary waterproof layer can be directly sleeved on the pile head for waterproofing the pile head internal corner.
[0019] Preferably, a third positioning groove is provided between two adjacent first positioning grooves.
[0020] By adopting the above technical solution, the cooperation of the first positioning groove and the third positioning groove strengthens the positioning of the waterproof coiled material.
[0021] Preferably, the first positioning strip is a magnetic metal strip.
[0022] By adopting the above technical solution, the magnetic metal strip cooperates with the magnet, which can be used to determine the position of the positioning groove, facilitating the subsequent pressing of the waterproof coiled material into the positioning strip.
[0023] A reverse sticking construction method for a pre-laid structure of a waterproof coiled material includes the following steps:
[0024] Base surface cleaning: Remove the attachments on the base surface, adopt the empty-laying method, and do not level the base; and dig grooves and first positioning grooves at the corresponding positions according to the BIM simulation results.
[0025] Prepare cement slurry: Weigh cement and water in a weight ratio of 2:1, then add 5% - 8% of the water-retaining agent based on the amount of cement, and stir with a mixer for more than 5 minutes to obtain the cement slurry.
[0026] Prepare waterproof coating: Use polymer emulsion and cement as the main raw materials, and add additives to make a water-based building waterproof coating.
[0027] Snap the reference line: According to the paving direction of the waterproof coiled material, snap the control line of the waterproof coiled material on the base, and lay the waterproof coiled material from low to high along the water flow direction.
[0028] Detail treatment: Set additional waterproof layers at the detailed positions of the internal and external corners, post-cast strips, and pile heads; before construction, first apply an oily base treatment agent, and then lay the additional waterproof layer after it dries; dig grooves on the base near the corner parts of the internal and external corners and lay the auxiliary waterproof layer and inject cement mortar to form an arc angle with a minimum radius of 50 mm, and the side lengths of the additional waterproof layers on both sides of the internal and external corners are both ≥ 250 mm; apply the waterproof coating twice to the pile head, including the side and the range of 150 - 200 mm around the pile head, to form a coating with a thickness of at least 1 mm; dig grooves on the base on the side of the pile head and paste a circular auxiliary waterproof layer and a 1.5-mm-thick additional waterproof layer, with a width of 150 - 200 mm from the outer edge of the pile.
[0029] Coiled material paving: When paving the vertical coiled material, use a connecting block and a pull rope to connect and fix the upper part of the coiled material to the wall or the set bracket on the upper adhesive surface of the coiled material close to the wall; use a soft rubber plate or roller to scrape and press from the middle to the other side of the coiled material lap direction to discharge the air, so that the coiled material is fully adhered to the base surface; when lapping and paving the next coiled material, lift the release paper at the lap part of the coiled material located at the lower layer, align the upper coiled material with the lap control line and paste it flat on the lower coiled material, scrape and press to discharge the air, and fully adhere.
[0030] When laying flat coiled materials, after placing the first positioning strip in the first positioning groove, first cut the coiled materials to be laid, and lay the single-sided reaction adhesive waterproof coiled material with the adhesive side facing up on the base surface; then use a rolling equipment to press the waterproof coiled material above the first positioning groove into the first positioning groove and heat-press a first easy-to-tear line near the first positioning groove; after tying the steel bars, gradually peel off the release paper of the coiled material at the corresponding part.
[0031] Lap sealing: Tear off the release film at the lap of the upper and lower coiled materials, scrape and apply neat cement slurry at the lap edge and lap them together, directly seal the end with neat cement slurry, the lap widths of the long side and the short side are both not less than 100 mm, and finally level and seal with neat cement slurry.
[0032] By adopting the above technical solutions, the reaction adhesive polymer waterproof coiled material is used, the non-bonding surface is laid empty on the foundation cushion layer, the bonding surface faces upward and is combined with the cast-in-place concrete surface as a whole, and there is no hidden danger of water channeling in the middle; even if the coiled material is locally damaged, the water will be limited within a very small range, greatly improving the reliability of the waterproof layer. At the same time, with the setting of the auxiliary waterproof layer and the positioning groove, the construction is more convenient, the position of the waterproof coiled material after pre-laying is more fixed, and it is not easy to be misaligned to generate leakage joints, ensuring the waterproof construction quality.
[0033] In summary, the present application includes at least one of the following beneficial technical effects:
[0034] 1. The structure of the present invention that the waterproof coiled material is accommodated in the positioning groove solves the problems that the single-sided adhesive waterproof coiled material is easy to move and be misaligned during the reverse laying due to construction, resulting in rupture or leakage joints, and there is no problem that the double-sided adhesive waterproof coiled material is not easy to be leveled after laying.
[0035] 2. The setting of the easy-to-tear line in the present invention makes the release layer easier to tear off, realizes that the release layer is retained instead of spreading cement powder, and improves the bonding effect between the waterproof coiled material and the cast-in-place concrete layer.
[0036] 3. By setting the structure of the auxiliary waterproof layer in the present invention, the construction difficulty of making a fillet at the internal angle is reduced, and the quality of the detail treatment at the internal angle is improved.
[0037] The construction method of the present invention has low potential safety hazards; the construction process is simplified, and the integrity of the waterproof layer and the concrete layer is high; the waterproof coiled material is convenient to adjust after laying, has extremely strong applicability, and the waterproof effect is more excellent, and it can be used for all waterproof constructions adopting the structure of the laid waterproof layer. BRIEF DESCRIPTION OF THE DRAWINGS
[0038] Figure 1 is a schematic structural diagram of the present invention.
[0039] Figure 2 is a schematic combined structural diagram of the present invention.
[0040] Figure 3 It is a schematic diagram of the auxiliary waterproof layer structure of the present invention.
[0041] Figure 4 It is a schematic diagram of the first positioning strip structure of the present invention.
[0042] Figure 5 It is a schematic diagram of the second positioning strip structure of the present invention.
[0043] Figure 6 It is a schematic diagram of the flat paving structure of the present invention.
[0044] Figure 7 It is a schematic diagram of the rolling equipment structure adopted by the present invention.
[0045] Explanation of reference numerals: 1, base layer; 11, groove; 12, first positioning groove; 13, first positioning strip; 131, first inner cavity; 132, opening; 133, constriction section; 14, second positioning strip; 141, second inner cavity; 15, third positioning groove; 2, wall; 3, auxiliary waterproof layer; 31, grouting hole; 32, blocking part; 4, cement mortar; 5, additional waterproof layer; 6, waterproof coiled material; 7, isolation layer; 71, first easy-to-tear line; 72, anti-slip convex pattern; 8, connecting block; 9, pull rope; 10, rolling equipment; 101, thin pressing wheel; 102, hot pressing roller cutter. Specific embodiments
[0046] The following will Figure 1-7 make a further detailed description of the present application in conjunction with the attached
[0047] Referring to Figure 1-2 , an embodiment of the present application discloses a pre-laying structure of a waterproof coiled material, including a base layer 1, a wall 2 is erected on the base layer 1, an included angle is provided between the base layer 1 and the wall 2, and an auxiliary waterproof layer 3 is provided on the included angle. When the wall 2 is a pile head, the auxiliary waterproof layer 3 is annular. Referring to Figure 3 . It is directly sleeved on the outer peripheral side of the pile head. Cement mortar 4 is filled between the auxiliary waterproof layer 3 and the included angle. A grouting hole 31 is provided at the upper part of the auxiliary waterproof layer 3, and a blocking part 32 is provided at the lower end of the auxiliary waterproof layer 3. The blocking part 32 is formed by overlapping and laminating multiple layers of the auxiliary waterproof layer 3. The base layer 1 is provided with a groove 11 that cooperates with the blocking part 32. An additional waterproof layer 5 is attached to the outside of the auxiliary waterproof layer 3, and a waterproof coiled material 6 is attached to the outside of the additional waterproof layer 5. The base layer 1 is provided with a first positioning groove 12, and a third positioning groove 15 is provided between two adjacent first positioning grooves 12. A first positioning strip 13 is provided in the first positioning groove 12, and the first positioning strip 13 is a magnetic metal strip. The first positioning strip 13 is provided with a first inner cavity 131, the first inner cavity 131 is provided with an opening 132, and both side walls of the first inner cavity 131 near the opening 132 are recessed inward to form a constriction section 133. A continuous section of the waterproof coiled material 6 is accommodated inside the first inner cavity 131.
[0048] The upper surface of the waterproof coiled material 6 is provided with an upper adhesive surface, and an isolation layer 7 is provided on the upper adhesive surface. The isolation layer 7 is divided into an anti-sticking layer and a puncture-resistant layer. The upper surface of the isolation layer 7 is provided with anti-slip ridges 72. The upper adhesive surface of the waterproof coiled material 6 that abuts against the wall 2 is provided with a connecting block 8. The connecting block 8 is adhered to the upper adhesive surface, and the connecting block 8 can be made of a rubber block or a plastic block. One end of a pull rope 9 is connected to the connecting block 8, and the other end of the pull rope 9 is connected to the wall 2 or a bracket. The waterproof coiled material 6 at least includes a first waterproof coiled material sheet 6 and a second waterproof coiled material sheet 6. An overlapping lapping portion is provided between the first waterproof coiled material sheet 6 and the second waterproof coiled material sheet 6. The base layer 1 below the lapping portion is provided with a second positioning groove. In this embodiment, the second positioning groove has the same structure as the first positioning groove 12. The difference is that a second positioning strip 14 is provided in the second positioning groove. The second positioning strip 14 is provided with a second inner cavity 141, and the space of the second inner cavity 141 is larger than that of the first inner cavity 131. See Figure 4-6 。
[0049] An anti-adhesive construction method for the pre-laid structure of the waterproof coiled material in the present invention includes the following steps:
[0050] Base surface cleaning: Remove the attachments on the surface of the base layer 1, adopt the empty-laying method, and do not level the base layer 1; and dig grooves 11 and first positioning grooves 12 at corresponding positions according to the BIM simulation results;
[0051] Prepare cement slurry: Weigh cement and water in a weight ratio of 2:1. Pour water into the mixing bucket according to the ratio, then put the cement into the water, soak for 15 - 20 minutes and fully soak it, and then pour out the excess water on the bucket surface; then add 5% - 8% of the water-retaining agent based on the amount of cement used, and stir with a mixer for more than 5 minutes to obtain the cement slurry;
[0052] Prepare waterproof coating: The waterproof coating is prepared with polymer emulsion and cement as the main raw materials, and additives are added to make a two-component water-based building waterproof coating of liquid material and powder material;
[0053] Snap reference lines: According to the construction site conditions, make reasonable positioning, determine the paving direction of the waterproof coiled material 6, snap the control lines of the waterproof coiled material 6 on the base layer 1, and pave the waterproof coiled material 6 from low to high along the flowing water direction to prevent misalignment and skew when paving the waterproof coiled material 6;
[0054] Detail treatment: Set additional waterproof layers 5 at the details of the internal and external corners, post-cast strips, and pile heads. The additional waterproof layers 5 are cut and made according to the drawings and use double-sided reaction-adhesive waterproof coiled materials 6; Before construction, first apply an oily base layer treatment agent, and then lay the additional waterproof layers 5 after drying, so that the additional waterproof layers 5 are fully adhered to the base layer 1, and for the stress concentration parts, empty-lay according to the specifications;
[0055] Among them, the detailed treatment steps for internal and external corners include applying neat cement slurry on the base layer 1 before paving. Grooves 11 are dug on the base layer 1 near the corner parts of the internal and external corners, and auxiliary waterproof layers 3 are paved and cement mortar 4 is injected to form an arc angle with a minimum radius of 50 mm. The side lengths of the additional waterproof layers 5 on both sides of the internal and external corners are both ≥ 250 mm;
[0056] The detailed treatment steps for the post-cast strip include adding an additional waterproof layer 5 at the post-cast strip, and the width of the additional waterproof layer 5 extends at least 300 mm beyond both sides of the post-cast strip;
[0057] The detailed treatment steps for the pile head include cleaning the mortar, soil and sundries on the pile head, applying the waterproof coating twice on the pile head including the side of the pile head and the range of 150 - 200 mm around the pile head to form a coating with a thickness of at least 1 mm; digging grooves 11 on the base layer 1 on the side of the pile head and pasting a circular auxiliary waterproof layer 3 and an additional waterproof layer 5 with a thickness of 1.5 mm, with a width of 150 - 200 mm from the outer edge of the pile;
[0058] Vertical coiled material paving: Apply neat cement slurry on the side walls of the bearing platform, elevator shaft and sump, and then pave the double-sided reaction adhesive waterproof coiled material 6; Horizontal coiled material paving: On the bottom of the bearing platform, elevator shaft, sump and the bottom surface of the floor slab cushion, without applying neat cement slurry, after placing the first positioning strip 13 in the first positioning groove 12, directly lay the single-sided reaction adhesive waterproof coiled material 6 with the sticky side facing up on the base surface in a floating manner;
[0059] Rolling and exhausting air: After the vertical coiled material paving is completed, use a connecting block 8 and a pull rope 9 to connect and fix the upper part of the coiled material to the wall 2 or the set bracket on the upper sticky surface of the coiled material close to the wall 2; Use a soft rubber plate or roller to scrape and exhaust air from the middle to the other side of the coiled material lap direction, so that the coiled material is fully adhered to the base surface; When lapping and paving the next coiled material, lift the release paper at the lap part of the coiled material located at the lower layer, align the upper coiled material with the lap control line and paste it flat on the lower coiled material, scrape and exhaust air to make it fully adhered; When paving the horizontal coiled material, first cut the coiled material to be paved well, lay it on the base surface with the bottom release paper facing up in a reverse manner, and then use the rolling equipment 10 to press the waterproof coiled material 6 above the first positioning groove 12 into the first positioning groove 12 and thermally press the first easy tear line 71 near the first positioning groove 12. Refer to Figure 7 As shown, the rolling equipment is provided with a thin pressing wheel 101, and a hot pressing roller cutter 102 for manufacturing the easy tear line is arranged on one side of the thin pressing wheel 101; After tying the steel bars, gradually peel off the release paper of the corresponding part of the coiled material; When peeling, the peeled release paper should preferably form an acute angle of 45 - 60 degrees with the bonding surface to prevent the release paper from being pulled off, and try to keep it in a natural relaxed state, but without wrinkles;
[0060] Lap sealing edge: Tear off the release film at the lap joint of the upper and lower coils, apply neat cement slurry to the lap edge and lap them together, directly seal the end with neat cement slurry, the lap width of both the long side and the short side is not less than 100 mm, and finally level and seal it with neat cement slurry.
[0061] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereby. Therefore, all equivalent changes made according to the structure, shape, and principle of the present application shall be covered within the protection scope of the present application.
Claims
1. A pre-laid structure of a waterproof coiled material, characterized in that: It includes a base layer (1), on which a wall (2) stands upright. There is an included angle between the base layer (1) and the wall (2), and an auxiliary waterproof layer (3) is provided at the included angle. Cement mortar (4) is filled between the auxiliary waterproof layer (3) and the included angle. An inlet hole (31) is provided at the upper part of the auxiliary waterproof layer (3), and a blocking part (32) is provided at the lower end of the auxiliary waterproof layer (3). The base layer (1) is provided with a groove (11) that cooperates with the blocking part (32). An additional waterproof layer (5) is attached to the outer side of the auxiliary waterproof layer (3), and a waterproof coiled material (6) is attached to the outer side of the additional waterproof layer (5). The base layer (1) is provided with a first positioning groove (12), and a first positioning strip (13) is provided in the first positioning groove (12). The first positioning strip (13) is provided with a first inner cavity (131), and the first inner cavity (131) is provided with an opening (132). The two side walls of the first inner cavity (131) near the opening (132) are recessed inward to form a constriction section (133). A continuous section of the waterproof coiled material (6) is accommodated inside the first inner cavity (131).
2. The pre-laid structure of the waterproof coiled material according to claim 1, wherein: The upper surface of the waterproof coiled material (6) is provided with an upper adhesive surface, and an isolation layer (7) is provided on the upper adhesive surface. A first easy-to-tear line (71) is provided on the isolation layer (7) near the first positioning groove (12).
3. The pre-laid structure of the waterproof coiled material according to claim 2, characterized in that: The upper surface of the isolation layer (7) is provided with anti-slip ridges (72).
4. The pre-laid structure of the waterproof coiled material according to claim 2, wherein: A connecting block (8) is provided on the upper adhesive surface of the waterproof coiled material (6) that abuts against the wall (2) at the upper part. One end of the connecting block (8) is connected to one end of a pull rope (9), and the other end of the pull rope (9) is connected to the wall (2) or a bracket.
5. The pre-laid structure of the waterproof coiled material according to claim 2, characterized in that: The isolation layer (7) is divided into an anti-adhesive layer and a puncture-resistant layer.
6. The pre-laid structure of the waterproof coiled material according to claim 1, characterized in that: The waterproof coiled material (6) at least includes a first waterproof coiled material sheet and a second waterproof coiled material sheet. There is an overlapping lapping part between the first waterproof coiled material sheet and the second waterproof coiled material sheet. A second positioning groove is provided on the base layer (1) below the lapping part, and a second positioning strip (14) is provided in the second positioning groove. The second positioning strip (14) is provided with a second inner cavity (141), and the space of the second inner cavity (141) is larger than that of the first inner cavity (131).
7. The pre-laid structure of the waterproof coiled material according to claim 1, characterized in that: The auxiliary waterproof layer (3) is annular.
8. The pre-laid structure of the waterproof coiled material according to claim 1, characterized in that: A third positioning groove (15) is provided between two adjacent first positioning grooves (12).
9. The pre-laid structure of the waterproof coiled material according to claim 8, wherein: The first positioning strip (13) is a magnetic metal strip.
10. The anti - sticking construction method of the waterproof coiled material pre - laying structure according to any one of claims 1 - 9, characterized in that, It includes the following steps: Base surface cleaning: Remove the attachments on the surface of the base layer (1), adopt the empty-laying method, and do not level the base layer (1); and dig the groove (11) and the first positioning groove (12) at the corresponding positions according to the BIM simulation results; Prepare cement slurry: Weigh cement and water in a weight ratio of 2:1, then add 5% - 8% of the water retention agent based on the amount of cement, and stir with a mixer for more than 5 minutes to obtain the cement slurry; Prepare waterproof coating: Use polymer emulsion and cement as the main raw materials, and add additives to make a water-based building waterproof coating; Snap the reference line: According to the paving direction of the waterproof coiled material (6), snap the control line of the waterproof coiled material (6) on the base layer (1), and pave the waterproof coiled material (6) from low to high following the water flow direction; Detail treatment: An additional waterproof layer (5) is provided at the positions of internal and external corners, post-cast strips, and pile heads; before construction, an oily base layer (1) treatment agent is applied first, and after drying, the additional waterproof layer (5) is laid; a groove (11) is dug on the base layer (1) near the corner part of the internal and external corners, and an auxiliary waterproof layer (3) is laid and cement mortar (4) is injected and plastered into an arc angle with a minimum radius of 50 mm. The side lengths of the additional waterproof layer (5) on both sides of the internal and external corners are both ≥ 250 mm; the pile head, including the side and the area within 150 - 200 mm around the pile head, is coated with waterproof coating twice to form a coating with a thickness of at least 1 mm; a groove (11) is dug on the base layer (1) on the side of the pile head, and a circular auxiliary waterproof layer (3) and a 1.5-mm-thick additional waterproof layer (5) are pasted, with a width of 150 - 200 mm from the outer edge of the pile. Roll laying: The vertical roll is laid, and on the upper adhesive surface of the roll against the wall (2) at the upper part of the roll, a connecting block (8) and a pull rope (9) are used to connect and fix the upper part of the roll to the wall (2) or the set bracket; a soft rubber plate or roller is used to scrape and press from the middle to the other side in the direction of the roll overlap to discharge air, so that the roll is fully adhered to the base surface; when overlapping and laying the next roll, the release paper at the overlapping part of the roll located at the lower layer is lifted, and the upper roll is aligned with the overlapping control line and smoothly pasted on the lower roll, and then scraped and pressed to discharge air and fully adhered; when laying the flat roll, after placing the first positioning strip (13) in the first positioning groove (12), the roll to be laid is cut first, and the single-sided reaction adhesive waterproof roll (6) is laid on the base surface with the adhesive side facing up; then, a rolling device is used to press the waterproof roll (6) above the first positioning groove (12) into the first positioning groove (12), and a first easy-tear line (71) is hot-pressed near the first positioning groove (12); after tying the steel bars, the release paper of the corresponding part of the roll is gradually peeled off. Overlap sealing: The release film at the overlap of the upper and lower rolls is torn off, the overlap edge is scraped and coated with neat cement slurry and overlapped together, and the end is directly sealed with neat cement slurry. The lap widths of the long and short sides are both not less than 100 mm, and finally, it is plastered and sealed with neat cement slurry.
Citation Information
Patent Citations
Station main body and accessory structure top plate joint heat preservation waterproof structure and construction method
CN110528593A
Underground waterproof structure
CN210117738U