A flood prevention early warning method and system for silt dam
By building a flood control risk assessment system and real-time water level calculation method, the problem of insufficient scientific flood control warning in the existing technology has been solved, and a more efficient and operational flood control warning system has been achieved, ensuring flood control safety.
Patent Information
- Application Number
- CN202211221993.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-10-08
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2042-10-08
AI Technical Summary
The existing technology lacks efficient, accurate and operational systems in flood control warning of silt dams, resulting in waste of resources and flood control warnings that are not scientific enough, making it difficult to deal with extreme rainfall and flood disasters.
Build a flood control risk assessment system for silt dams, including hydrological risks, operation risks and engineering risk indicators, calculate the comprehensive flood control risk score through hierarchical analysis method and weighted normalization method, determine the flood control warning level, and provide real-time water level calculation methods to improve early warning Intelligent and operable.
It improves the clear and intelligent operation steps of flood control warning in silt dams, enhances the operability of the early warning system, and can more accurately assess the flood control risks of silt dams, provide scientific warning references, and ensure flood control safety.
Smart Images

Figure CN115909662B_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of meteorological and geological disaster early warning, relates to flood control safety of silt dams under rainfall conditions, and particularly relates to a flood control early warning method and system for silt dams. Background Art
[0002] As an effective water and soil conservation engineering measure, silt dams are widely distributed in hilly gully areas, playing a very important role in controlling gully erosion, intercepting sediment, storing water and conserving soil, and improving the ecological environment. Especially in the context of frequent extreme weather and increased probability of rainstorms in the region, silt dams play a more obvious role in resisting extreme rainfall and flood disasters, reducing the amount of sediment entering the gully, and ensuring flood control safety.
[0003] At the same time, facing the threat of flood dam breach, in order to ensure the safe operation of the silt dam, the existing technology has given many suggestions for the construction and management of the silt dam. However, since the safety of the silt dam is always relative, insecurity is absolute. Therefore, in addition to taking engineering measures to prevent dam breach disasters, corresponding early warning work should be done as early as possible. After investigation, the existing silt dam management still has problems such as low level of informatization and imperfect early warning mechanism.
[0004] Most of the traditional flood warning methods were established in the 1970s and 1980s, and almost all of them rely on manual measurement of various indicators, which greatly affects the accuracy of flood warning risk assessment. At the same time, due to the complex terrain and different water and soil conditions in various places, it is difficult to form standards and specifications for flood control prediction of silt dams, lack of unified management, and cause waste of resources.
[0005] The latest flood warning methods have initially established a flood warning response mechanism, but there are still some shortcomings, mainly because they only use machine measurements instead of manual measurements, and input the statistical warning system information into the computer for calculation. However, there is still a lack of systematic and scientific analysis, making it difficult to establish an efficient, accurate and highly operable flood warning system. Summary of the invention
[0006] In order to overcome the above-mentioned shortcomings of the prior art, the purpose of the present invention is to provide a method and system for flood prevention and early warning of a silt dam, so as to further improve the intelligence level and operability of flood prevention and early warning of a silt dam.
[0007] In order to achieve the above object, the technical solution adopted by the present invention is:
[0008] A flood prevention early warning method for a silt dam comprises the following steps:
[0009] Step 1: Select hydrological risk, operational risk and engineering risk to construct a flood control risk assessment system for silt dams; the hydrological risk indicators include the distance from the water surface to the dam top C1 and the presence or absence of a spillway C2; the operational risk indicators include the remaining sedimentation years C3, the remaining sedimentation storage capacity C4 and the presence or absence of a flood control plan C5; the engineering risk indicators include the foundation anti-seepage quality C6, the dam body anti-seepage quality C7, the filling quality C8, the dam shoulder leakage C9 and the dam body and anti-seepage body leakage C 10 ;
[0010] Step 2, obtaining the real-time water level of the silt dam to obtain the indicator C1;
[0011] Step 3, determine the influencing factors of each type of the indicators and divide the flood warning levels; the influencing factors are the impact of the indicators on the flood control risk of the silt dam; the influencing factors are weighted and normalized to obtain a comprehensive flood control risk score; and the flood warning level is determined.
[0012] The present invention also provides a flood prevention early warning system for a silt dam, comprising:
[0013] Index input unit, the indicators include the distance from the water surface to the dam top C1, the presence or absence of spillway C2, the remaining sedimentation years C3, the remaining sedimentation storage capacity C4, the presence or absence of flood control plan C5, the foundation anti-seepage quality C6, the dam body anti-seepage quality C7, the filling quality C8, the dam shoulder leakage C9 and the dam body and anti-seepage body leakage C 10 ;
[0014] The processing unit obtains the real-time water level of the silt dam to obtain the index C1; determines the influencing factors of various indicators and divides the flood prevention warning level; the influencing factors are the influence of the indicators on the flood prevention risk of the silt dam; obtains the comprehensive flood prevention risk score by weighting and normalizing the influencing factors; and determines the flood prevention warning level;
[0015] The early warning unit outputs different early warning signals according to the flood prevention early warning level.
[0016] Compared with the existing methods, the beneficial effect of the present invention is that the operating steps of the flood prevention warning of the silt dam are clarified and its intelligence is improved; in addition, the present invention provides a simplified method for measuring the real-time water level of the silt dam under rainfall conditions, which effectively improves the operability of the flood prevention warning of the silt dam. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is a schematic diagram of the process of the present invention.
[0018] Figure 2 It is a schematic diagram of the flood control risk assessment system of the silt dam of the present invention.
[0019] Figure 3It is a schematic diagram of the flow chart for calculating the outflow volume of a silt dam with a spillway. DETAILED DESCRIPTION
[0020] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail by specific embodiments in conjunction with the accompanying drawings. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.
[0021] As mentioned above, there is no efficient, accurate and highly operable flood warning system in the current technology. To this end, the present invention provides a flood warning method for a silt dam. First, based on the typical characteristics of the silt dam, the analytic hierarchy process is applied to select the main hydrological risks, operational risks and engineering risks, and a flood risk evaluation index system for the warning model is constructed. Then, a simplified calculation method for the real-time water level of the silt dam is obtained based on rainfall data and silt dam engineering parameters, which is used to evaluate the hydrological risk of the silt dam. Finally, based on the evaluation of the hydrological risk, operational risk and engineering risk of the silt dam, the flood warning level of the silt dam is obtained, which provides a realistic reference for ensuring the safety of the basin where the silt dam is located.
[0022] like Figure 1 As shown, the present invention specifically includes the following steps:
[0023] Step 1: Based on the characteristics of the silt dam in the region, taking into account the hydrological risk, operation risk and engineering risk, a flood control risk assessment system for silt dams that meets actual needs is constructed ( Figure 1 The part within the dotted box).
[0024] The flood control risk assessment system of the silt dam of the present invention is constructed by analyzing the key factors affecting the flood control risk of the silt dam and applying the hierarchical analysis method. Specifically, the indicators of hydrological risk include the distance from the water surface to the dam top C1 and the presence or absence of a spillway C2. The indicators of operational risk include the remaining sedimentation years C3, the remaining sedimentation storage capacity C4, and the presence or absence of a flood control plan C5. The indicators of engineering risk include the foundation anti-seepage quality C6, the dam body anti-seepage quality C7, the filling quality C8, the dam shoulder leakage C9, and the dam body and anti-seepage body leakage C 10 .
[0025] Among them, C1 is obtained by measurement, and rainfall information is obtained and calculated using a computer. The rainfall information is automatically collected by a hydrological station and transmitted to the computer, which will be described in detail in step 2.
[0026] Whether there is a spillway C2, the remaining sedimentation years C3, the remaining sedimentation storage capacity C4, and whether there is a flood control plan C5 can be obtained through the silt dam project information; C6~C 10It can be obtained by computer or expert scoring, and collected and maintained by using the silt dam information management system. The present invention sets the value of whether there is a spillway C2 and whether there is a flood control plan C5 as 0 or 9, 0 represents no, 9 represents yes; the other indicators are in the range of 0 to 9; the larger the value of each indicator, the more unfavorable the indicator is to flood control safety.
[0027] like Figure 2 As shown, the flood control risk assessment system of the silt dam constructed by the present invention is divided into three layers:
[0028] Target layer: Flood control risk of silt dam, which is the overall goal of this invention.
[0029] Middle layer: The key factors affecting the flood control risk of the silt dam are decomposed by category. The present invention decomposes them into hydrological risk, operational risk and engineering risk; hydrological risk refers to the risk brought by factors related to the storage and drainage of the silt dam; operational risk refers to the risk related to the management and operation of the silt dam. Engineering risk refers to the risk related to the quality of the silt dam project.
[0030] Indicator layer: The key factors affecting the flood control risk of the silt dam are classified according to the above categories to form the key indicators of risk assessment. 10 The specific evaluation method is shown in Table 1:
[0031] Table 1 Evaluation methods of key indicators of flood control risk of silt dams
[0032] index Evaluation Method Value range Normalization <![CDATA[Distance C1 from the water surface or sediment surface to the dam crest]]> Calculation 0~9 Distance × 10 / Dam height <![CDATA[Presence or absence of spillway C2]]> Project Information 0 or 9 0 - with spillway, 9 - without spillway <![CDATA[Remaining siltation years C3]]> Project Information 0~9 Remaining life × 10 / design life <![CDATA[Remaining sediment storage capacity C4]]> Project Information 0~9 Remaining storage capacity × 10 / designed storage capacity <![CDATA[Availability of flood control plan C5]]> Project Information 0 or 9 0-with a plan, 9-without a plan <![CDATA[Basic anti-seepage quality C6]]> Expert Rating 0~9 <![CDATA[Seepage prevention quality of dam body C7]]> Expert Rating 0~9 <![CDATA[Filling quality C8]]> Expert Rating 0~9 <![CDATA[Seepage at Dam Shoulder C9]]> Expert Rating 0~9 <![CDATA[Leakage of dam body and impervious body C 10 > Expert Rating 0~9
[0033] Step 2: Obtain the real-time water level of the silt dam to obtain indicator C1.
[0034] In the flood risk assessment system constructed in step 1, the most important influencing factor is the change in the water level of the silt dam under rainfall conditions. Based on the existing research results, the present invention simplifies the method for measuring the real-time water level of the silt dam. The details are as follows:
[0035] Step 2.1: Calculation of inflow volume
[0036] The flood volume entering the reservoir refers to the total amount of sediment and precipitation generated in the basin controlled by the silt dam under rainfall conditions and flowing into the silt dam, thus causing the water level change in the silt dam reservoir; usually, it is necessary to consult the regional hydrological manual before calculation to obtain the initial loss value of rainfall I0. Only when the rainfall is higher than I0 will it affect the water level of the silt dam. The calculation process of the flood volume entering the reservoir is as follows:
[0037] (1) Calculation of inflow: Inflow consists of basin flow and direct rainfall. Direct rainfall refers to the rainfall directly received by the reservoir surface, which can generally be ignored. Basin flow W wIt refers to the flow rate around the reservoir area and is calculated using the following formula:
[0038]
[0039] Area controlled by silt dam A c It can be obtained through the parameters of the silt dam project. Generally speaking, the net rainfall process can be deduced from the known rainstorm process based on the initial loss and post-loss parameters. However, due to the complexity of the calculation process and the outdated data in the regional hydrological manual, the present invention simplifies the calculation of net rainfall as follows:
[0040] R n =P×β
[0041] Where: R n is the net rainfall (mm), A c is the controlled area of the silt dam (m 2 ), P is the rainfall in the basin (mm), β is the runoff coefficient, and the empirical value is given by experts according to the different types of basins and check dams.
[0042] (2) Calculation of the amount of sand entering the reservoir: When heavy rain occurs, a large amount of eroded sediment enters the silt dam along with rainfall and runoff. The amount of sand entering the reservoir is the eroded sediment that enters the silt dam along with rainfall and runoff. The usual practice is to use the Revised Universal Soil Loss Equation (RUSLE) to calculate the amount of sand entering the reservoir. The RUSLE model (The Revised Universal Soil Loss Equation) was revised and established by the United States Department of Agriculture in 1997 based on the Universal Soil Loss Equation (USLE) and formally implemented. It is a revised model with a wider range of applications. The RUSLE model can make the calculation of the amount of sand entering the reservoir more accurate. Therefore, the amount of sand entering the reservoir W s The calculation formula is as follows:
[0043]
[0044]
[0045] In the formula: In the formula: is the average soil erosion modulus in the watershed controlled by the silt dam (t / hm 2 ), γ is the dry volume of loess (t / m 2 ); R is the erosivity of rainfall ((MJ·mm) / (hm 2 h)), It is the product of the other five factors in the RUSLE model except R, that is:
[0046]
[0047] Where: K is the soil erodibility factor ((t·hm 2 ·h) / (hm 2 ·MJ·mm)), L is the slope length factor, S is the slope factor, C is the vegetation coverage and management factor, and P is the soil and water conservation measures factor.
[0048] Since the loess dry capacity γ and the five factors in the above formula are inherent properties of the watershed controlled by the silt dam, the present invention simplifies the calculation of the amount of sediment entering the reservoir as follows:
[0049] W s =A c Rθ
[0050] Where: R is the erosivity of rainfall ((MJ·mm) / (hm 2 h)), θ is the newly defined sediment yield factor after comprehensive consideration of the above factors, which can be calculated based on experience or directly set as a fixed value.
[0051] Step 2.2: Calculation of outflow volume
[0052] According to the different types of silt dams, the discharge facilities of silt dams mainly include horizontal pipes, vertical shafts and spillways. The discharge volume of horizontal pipes and vertical shafts is small and can be ignored. For silt dams with spillways, the trial calculation method can be used to obtain the outflow volume W at the end of the rainfall period. out ;refer to Figure 3 The calculation process is as follows:
[0053] (1) Obtain the initial silt dam storage capacity W during the rainfall period t , and assuming that the water level Z′ at the end of the rainfall period t+1 ;
[0054] (2) The water level-reservoir capacity curve is derived from W t Get the real-time water level Z of the silt dam t ;
[0055] (3) Obtain the leakage flow Q by checking the leakage flow relationship diagram t and Q t+1 , and calculate the average leakage flow The calculation formula is:
[0056] (4) Calculate the flood discharge during the rainfall period Δt. The calculation formula is:
[0057] (5) The flood volume W entering the reservoir during the rainfall period is obtained through step 2.1 Δt_in , calculate the storage capacity of the silt dam at the end of the rainfall period W t+1 , the calculation formula is W t+1 =W Δt_in -W Δt_out;
[0058] (6) Obtain the water level Z through the water level-reservoir capacity curve t+1 ;.
[0059] (7) Compare Z t+1 and Z′ t+1 If the two are equal, then accept the assumption and end the process early, and let the outflow volume at the end of the rainfall period be W out =W Δt_out ; If the two are different, repeat steps (1)-(6).
[0060] Step 2.3: Calculation of real-time water level of the check dam under given rainfall conditions
[0061] Calculate the real-time storage capacity of the silt dam and combine it with the water level-storage capacity curve data to obtain the real-time water level Z of the silt dam. t .
[0062] Among them, the calculation formula of the real-time storage capacity W of the silt dam is as follows:
[0063] W=W old +W in -W out
[0064] Where: W old is the original storage capacity of the silt dam, W in is the inflow volume, which is obtained by the following formula:
[0065] W in =W w +W s
[0066] Therefore, the formula for calculating the real-time storage capacity of the silt dam is simplified to:
[0067] W=W old +W w +W s -W out
[0068] The water level-reservoir capacity curve data is shown in Table 2 below.
[0069] Table 2 Example of data table of water level-storage capacity curve of silt dam
[0070] Water level (m) Water level (m) ~ Area (km2) Water level (m) ~ reservoir capacity V (10,000 m3) 0.00 0.0000 0.000 1.00 0.7000 0.350 3.50 3.1000 5.100 6.00 7.2000 17.975 8.50 10.8000 40.475 11.00 16.10 74.100
[0071] The present invention can also monitor the water level in real time through hardware sensors, and predict the water level at the next moment through a neural network, thereby achieving early warning.
[0072] Step 3, determine the influencing factors of various indicators and divide the flood warning levels; the influencing factor is the impact of the indicator on the flood risk of the silt dam; the influencing factor is weighted and normalized to obtain a comprehensive flood risk score; determine the flood warning level.
[0073] The present invention provides examples of influencing factors of various risk indicators and obtains warning level classification standards that are instructive for practical work through calculations.
[0074] Specifically, the method for determining the influencing factors of various indicators and dividing the flood warning levels is as follows:
[0075] Step 3.1: Through expert scoring, the influencing factors of each indicator on the flood control risk of the silt dam are obtained, as shown in Table 3.
[0076] Table 3 Examples of influencing factors of flood risk assessment indicators for silt dams
[0077]
[0078]
[0079] Step 3.2: Obtain each indicator C through measurement, engineering information and expert scoring i The value of C i Normalized to a value between 0 and 9, and then calculated according to the impact factor W given in Table 3 i , weighted calculation of the flood control risk score A of the silt dam is:
[0080]
[0081] Step 3.2: According to the interval of the flood control risk score of the silt dam, the flood control warning level of the silt dam is divided into 4 levels, which means no need to deal with, dam break alarm, make preparations for evacuation, and need to evacuate immediately; the corresponding flood control risk scores are 0, 1-4, 4-7, and 7-9. As shown in Table 4 below.
[0082] Table 4 Classification of flood warning levels for silt dams
[0083] Flood risk score Risk Level Warning level Countermeasures 0 4 normal No treatment required 1-4 3 blue Dam breach alarm 4-7 2 yellow Prepare for the transfer 7-9 1 red Need to transfer immediately
[0084] The overall execution process of the method of the present invention is described below through a specific example.
[0085] The implementation object of this embodiment is the Chadianliang No. 1 backbone dam located in Bojianghai Town, Dongsheng District, Ordos City, Inner Mongolia. It was built in 2007, with a dam height of 11m and a total storage capacity of 53.9m 3 , siltation storage capacity 24.61m 3 , dam control area 3.02m 2 , consists of two major parts: the dam body and the water release project.
[0086] First, we need to collect the data corresponding to the silt dam. Figure 2 The data of other indicators except C1 in the risk assessment system shown in the figure, among which C2~C5 can be obtained directly, C6~C 10 Obtained through expert scoring (Table 5).
[0087] Secondly, the real-time water level of the silt dam is calculated under given rainfall conditions to obtain the score of the evaluation index C1. This embodiment calculates the real-time water level of the silt dam based on given rainfall process data, the initial loss value of rainfall (I0=2) obtained by consulting the regional hydrological manual, and the runoff coefficient (β=1.15) and sediment production factor (θ=0.005) given by experience. The rainfall process and the water level changes and C1 index score data calculated using this method are shown in Table 7.
[0088] Table 5 Expert scoring table used in this embodiment
[0089] index Expert 1 Expert 2 Expert 3 score Foundation anti-seepage quality C6 9 1 7 6 Dam body anti-seepage quality C7 4 7 6 8 Filling quality C8 6 4 6 6 Dam abutment leakage C9 5 9 8 8 Leakage of dam body and anti-seepage body C10 2 9 5 5
[0090] Table 6 Rainfall process data used in this embodiment
[0091]
[0092]
[0093]
[0094] Table 7 Calculation results of this embodiment
[0095]
[0096] Finally, the score of each indicator is combined, and the weighted sum is used to calculate the flood control risk score of the silt dam, and the corresponding warning level is given according to the score range in reference to Table 4. The final calculation results are shown in Table 7. The comprehensive score is 3.99, which is located in the blue warning area. The response measures are: issue a dam break alarm.
[0097] Through this example, it can be seen that the method provided by the present invention simplifies the method for measuring the real-time water level of the silt dam under rainfall conditions on the basis of constructing a more scientific flood control risk assessment system, and can effectively improve the operability of flood control warning of the silt dam.
[0098] In order to match the above-mentioned silt dam flood prevention early warning method, the present invention also provides a silt dam flood prevention early warning system, which includes: an indicator input unit, a processing unit and an early warning unit.
[0099] The index input unit is used to input the aforementioned indexes C2 to C 10, which can be a computer input device or a handheld input device, connected to the processing unit by wire or wireless means. 10 It can be directly input or programmed to access the silt dam project information system, from which C2~C5 can be directly extracted, and access the silt dam information management system to directly extract C6~C 10 .
[0100] Indicators C2~C 10 Input the processing unit, and the indicator C1 needs to be obtained in the processing unit based on the calculated real-time water level of the silt dam. In the processing unit, determine the influencing factors of various indicators and divide the flood warning levels. The influencing factors can be obtained through big data training, or assigned by experts, and can be further updated iteratively based on the comparison between the obtained flood warning level and the actual flood risk. The influencing factors are weighted and normalized to obtain a comprehensive flood risk score; determine the flood warning level. The processing unit can be a local computer or a cloud server, which should be set with certain management permissions.
[0101] The early warning unit is connected to the processing unit and outputs different early warning signals according to the flood warning level.
[0102] For example, the early warning unit includes a local early warning unit and a distributed early warning unit. The local early warning unit is directly connected to the processing unit by wire and can be set in the control room. The distributed early warning unit is connected to the processing unit by wire or wireless means and is set in an inhabited area within the influence range of the silt dam so as to provide an early warning signal in the first time.
[0103] In order to calculate the index C1, the present invention also includes a number of sensors distributed within the scope of the silt dam, which are used to collect:
[0104] Net rainfall R n , the basin's rainfall amount P.
[0105] Although the present invention has been described through preferred embodiments, the present invention is not limited to the embodiments described herein but includes various changes and modifications that may be made without departing from the scope of the present invention.
Claims
1. A flood prevention early warning method for a silt dam, characterized in that: The steps include: Step 1: Select hydrological risk, operational risk and engineering risk to construct a flood control risk assessment system for silt dams; the hydrological risk indicators include the distance from the water surface to the dam top C1 and the presence or absence of a spillway C2; the operational risk indicators include the remaining sedimentation years C3, the remaining sedimentation storage capacity C4 and the presence or absence of a flood control plan C5; the engineering risk indicators include the foundation anti-seepage quality C6, the dam body anti-seepage quality C7, the filling quality C8, the dam shoulder leakage C9 and the dam body and anti-seepage body leakage C 10 ; The presence or absence of spillway C2, remaining sedimentation years C3, remaining sedimentation storage capacity C4 and presence or absence of flood control plan C5 are obtained through the silt dam project information; the project risk indicators include foundation anti-seepage quality C6, dam body anti-seepage quality C7, filling quality C8, dam shoulder leakage C9 and dam body and anti-seepage body leakage C 10 , collected through the silt dam information management system; the values of whether there is a spillway C2 and whether there is a flood control plan C5 are 0 or 9, 0 represents no, 9 represents yes; the other indicators are in the range of 0 to 9; the larger the value of each indicator, the more unfavorable the indicator is to flood control safety; Step 2, obtaining the real-time water level of the silt dam to obtain the indicator C1; the method for obtaining the real-time water level of the silt dam includes: Step 2.1: Calculation of inflow volume The flood volume in the reservoir refers to the total amount of sediment and precipitation generated in the basin controlled by the silt dam under rainfall conditions and flowing into the silt dam, thereby causing the water level change in the silt dam reservoir; the calculation process of the flood volume in the reservoir is as follows: (1) Calculation of inflow: Inflow consists of basin flow and direct rainfall. Direct rainfall refers to the rainfall directly received by the reservoir surface, which is negligible. Basin flow W w It refers to the flow rate around the reservoir area and is calculated using the following formula: R n =P×β Where: R n is the net rainfall (mm), A c is the controlled area of the silt dam (m 2 ), P is the rainfall in the basin (mm), β is the runoff coefficient; (2) Calculation of inflow sediment: The inflow sediment is the eroded sediment that enters the silt dam along with rainfall and runoff. The inflow sediment is W s The calculation formula is as follows: W s =A c Rθ Where: R is the erosivity of rainfall ((MJ·mm) / (hm 2 h), θ is the sediment yield factor, which is calculated based on experience or directly set to a fixed value; Thus, the flood volume W in the rainfall period Δt is obtained. Δt_in =W w +W s ; Step 2.2: Calculation of outflow volume The discharge facilities of the silt dam mainly include horizontal pipes, vertical shafts and spillways. The discharge volume of horizontal pipes and vertical shafts is small and can be ignored. For the silt dam with spillways, the trial calculation method is used to obtain the outflow volume W at the end of the rainfall period. out The calculation process is as follows: (1) Obtain the initial silt dam storage capacity W during the rainfall period t , and assuming that the water level Z′ at the end of the rainfall period t+1 ; (2) The water level-reservoir capacity curve is derived from W t Get the real-time water level Z of the silt dam t ; (3) Obtain the leakage flow Q by checking the leakage flow relationship diagram t and Q t+1 , and calculate the average leakage flow The calculation formula is: (4) Calculate the flood discharge during the rainfall period Δt. The calculation formula is: (5) The flood volume W entering the reservoir during the rainfall period is obtained through step 2.1 Δt_in , calculate the storage capacity of the silt dam at the end of the rainfall period W t+1 , the calculation formula is W t+1 =W Δt_in -W Δt_out ; (6) Obtain the water level Z through the water level-reservoir capacity curve t+1 ; (7) Compare Z t+1 and Z′ t+1 If the two are equal, then accept the assumption and end the process early, and let the outflow volume at the end of the rainfall period be W out =W Δt_out ; If the two are different, repeat steps (1)-(6); Step 2.3: Calculation of real-time water level of the check dam under given rainfall conditions Calculate the real-time storage capacity W of the silt dam, and combine it with the water level-storage capacity curve data to obtain the real-time water level Z of the silt dam t , the calculation formula of the real-time storage capacity W of the silt dam is as follows: W=W old +W w +W s -IN out Where: W old is the original storage capacity of the silt dam; Step 3, determining the influencing factors of each type of the indicators and classifying the flood warning levels; the influencing factors are the influence of the indicators on the flood control risk of the silt dam; the influencing factors are weighted and normalized to obtain a comprehensive flood control risk score; and the flood warning level is determined; The methods for determining the influencing factors of various indicators and dividing the flood warning levels are as follows: Step 3.1: Obtain the influencing factors of each indicator on the flood control risk of the silt dam through expert scoring; Step 3.2: Set the value of each indicator C i Normalized to a value between 0 and 9, and then calculated according to the impact factor W i , weighted calculation of the flood control risk score A of the silt dam is: Step 3.2: According to the range of flood risk scores of the silt dam, the flood warning level of the silt dam is divided into 4 levels, which respectively mean no need for treatment, dam break alarm, preparation for evacuation, and need for immediate evacuation; the corresponding flood risk scores are 0, 1-4, 4-7, and 7-9.
2. A flood prevention early warning system for a silt dam, characterized in that: include: Index input unit, the indicators include the distance from the water surface to the dam top C1, the presence or absence of spillway C2, the remaining sedimentation years C3, the remaining sedimentation storage capacity C4, the presence or absence of flood control plan C5, the foundation anti-seepage quality C6, the dam body anti-seepage quality C7, the filling quality C8, the dam shoulder leakage C9 and the dam body and anti-seepage body leakage C 10 ; The presence or absence of spillway C2, remaining sedimentation years C3, remaining sedimentation storage capacity C4 and presence or absence of flood control plan C5 are obtained through the silt dam engineering information; the indicators of engineering risk include foundation anti-seepage quality C6, dam body anti-seepage quality C7, filling quality C8, dam shoulder leakage C9 and dam body and anti-seepage body leakage C 10 , collected through the silt dam information management system; the values of whether there is a spillway C2 and whether there is a flood control plan C5 are 0 or 9, 0 represents no, 9 represents yes; the other indicators are in the range of 0 to 9; the larger the value of each indicator, the more unfavorable the indicator is to flood control safety; The processing unit obtains the real-time water level of the silt dam to obtain the index C1; determines the influencing factors of various indicators and divides the flood prevention warning levels; the influencing factors are the influence of the indicators on the flood prevention risk of the silt dam; Obtain a comprehensive flood risk score by weighting and normalizing the influencing factors; Determine flood warning levels; The method for obtaining the real-time water level of the silt dam comprises: Step 2.1: Calculation of inflow volume The flood volume in the reservoir refers to the total amount of sediment and precipitation generated in the basin controlled by the silt dam under rainfall conditions and flowing into the silt dam, thereby causing the water level change in the silt dam reservoir; the calculation process of the flood volume in the reservoir is as follows: (1) Calculation of inflow: Inflow consists of basin flow and direct rainfall. Direct rainfall refers to the rainfall directly received by the reservoir surface, which is negligible. Basin flow W w It refers to the flow rate around the reservoir area and is calculated using the following formula: R n =P×β Where: R n is the net rainfall (mm), A c is the controlled area of the silt dam (m 2 ), P is the rainfall in the basin (mm), β is the runoff coefficient; (2) Calculation of inflow sediment: The inflow sediment is the eroded sediment that enters the silt dam along with rainfall and runoff. The inflow sediment is W s The calculation formula is as follows: W s =A c Rθ Where: R is the erosivity of rainfall ((MJ·mm) / (hm 2 h), θ is the sediment yield factor, which is calculated based on experience or directly set to a fixed value; Thus, the flood volume W in the rainfall period Δt is obtained. Δt_in =W w +W s ; Step 2.2: Calculation of outflow volume The discharge facilities of the silt dam mainly include horizontal pipes, vertical shafts and spillways. The discharge volume of horizontal pipes and vertical shafts is small and can be ignored. For the silt dam with spillways, the trial calculation method is used to obtain the outflow volume W at the end of the rainfall period. out The calculation process is as follows: (1) Obtain the initial silt dam storage capacity W during the rainfall period t , and assuming that the water level Z′ at the end of the rainfall period t+1 ; (2) The water level-reservoir capacity curve is derived from W t Get the real-time water level Z of the silt dam t ; (3) Obtain the leakage flow Q by checking the leakage flow relationship diagram t and Q t+1 , and calculate the average leakage flow The calculation formula is: (4) Calculate the flood discharge during the rainfall period Δt. The calculation formula is: (5) The flood volume W entering the reservoir during the rainfall period is obtained through step 2.1 Δt_in , calculate the storage capacity of the silt dam at the end of the rainfall period W t+1 , the calculation formula is W t+1 =W Δt_in -W Δt_out ; (6) Obtain the water level Z through the water level-reservoir capacity curve t+1 ; (7) Compare Z t+1 and Z′ t+1 If the two are equal, then accept the assumption and end the process early, and let the outflow volume at the end of the rainfall period be W out =W Δt_out ; If the two are different, repeat steps (1)-(6); Step 2.3: Calculation of real-time water level of the check dam under given rainfall conditions Calculate the real-time storage capacity W of the silt dam, and combine it with the water level-storage capacity curve data to obtain the real-time water level Z of the silt dam t , the calculation formula of the real-time storage capacity W of the silt dam is as follows: W=W old +W w +W s -IN out Where: W old is the original storage capacity of the silt dam; The methods for determining the influencing factors of various indicators and dividing the flood warning levels are as follows: Step 3.1: Obtain the influencing factors of each indicator on the flood control risk of the silt dam through expert scoring; Step 3.2: Set the value of each indicator C i Normalized to a value between 0 and 9, and then calculated according to the impact factor W i , weighted calculation of the flood control risk score A of the silt dam is: Step 3.2: According to the interval of the flood control risk score of the silt dam, the flood control warning level of the silt dam is divided into 4 levels, which means no need to deal with, dam break alarm, make preparations for evacuation, and need to evacuate immediately; the corresponding flood control risk scores are 0, 1-4, 4-7, and 7-9; The early warning unit outputs different early warning signals according to the flood prevention early warning level.
3. The flood prevention early warning system for silt dam according to claim 2 is characterized in that: The index input unit is a computer input device or a handheld input device, C2~C 10 The indicators are directly input, or C2~C5 are extracted from the silt dam engineering information system, and C6~C8 are extracted from the silt dam information management system. 10 The index input unit is connected to the processing unit, and the indexes C2 to C 10 Input processing unit; the influencing factors of the various indicators are iteratively updated according to the comparison between the obtained flood warning level and the actual flood risk.
4. The flood prevention early warning system for silt dam according to claim 2 is characterized in that: It also includes several sensors distributed within the silt dam, which are used to collect: Net rainfall R n , the basin's rainfall amount P.
5. The flood prevention early warning system for silt dam according to claim 2 is characterized in that: The processing unit is a local computer, and the early warning unit includes a local early warning unit and a distributed early warning unit. The local early warning unit is directly connected to the processing unit by wire and is set in the control room. The distributed early warning unit is connected to the processing unit by wire or wireless means and is set in an inhabited area within the influence range of the silt dam.
Citation Information
Patent Citations
Three-in-one small reservoir or silt dam flood season early warning method
CN108681848A
Dam bursting flood analysis system of dam system
CN110219277A
Tailing pond dam break risk estimation and emergency response method and device and electronic equipment
CN113705127A
Mountain torrent disaster early warning index checking and rechecking method and system
CN114023049A