A pre-embedded wall connection node and wall construction method
By using a first connecting piece made of rust-resistance material in the embedded part wall connection node and having a clamping structure design, the problem of rust transmission of embedded part to the steel frame is solved, ensuring the bearing capacity and stability of the wall.
Patent Information
- Application Number
- CN202211630157.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-12-13
- Publication Date
- 2025-05-02
- Estimated Expiration
- 2042-12-13
AI Technical Summary
The existing embedded parts are connected to the steel bar frame through welding. The corrosion of the exposed part of the embedded parts will be transmitted to the welding position with the steel bar frame, resulting in the steel bar frame gradually being rusted, resulting in a serious decrease in the bearing capacity and stability of the wall.
The embedded parts are connected to the wall nodes, including the embedded parts, the first connecting parts and the steel bar frame. The first connecting parts are made of rust-resisting materials, and are equipped with a clamping structure for clamping the embedded parts and the steel bar frame. Through these clamping structures, the embedded parts are connected to the steel bar frame.
It effectively prevents the rust of the embedded parts from being transmitted to the steel bar frame, avoids the rust of the steel bar frame, and ensures the bearing capacity and stability of the wall.
Smart Images

Figure CN115949147B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building engineering, and in particular to a pre-embedded part wall connection node and a wall construction method. Background Art
[0002] During the wall construction process, it is necessary to set up scaffolding on the outer wall. In order to ensure the reliability of the connection between the scaffolding and the wall and avoid safety accidents such as the scaffolding toppling, the scaffolding is often connected to the wall by a pre-embedded wall connection structure. The existing pre-embedded wall connection structure often includes embedded parts made of steel bars or steel pipes. During the wall construction process, before pouring concrete, it is necessary to weld one end of the embedded part to the steel bar frame in the wall according to the design drawing to locate each embedded part and connect it to the steel bar frame. After the wall is poured with concrete, the other end of the embedded part extends out of the wall for connecting the scaffolding. However, after the scaffolding is removed, the exposed part of the embedded part is easily rusted and transmitted to the welding position with the steel bar frame, causing the steel bar frame to gradually rust. The rust of the steel bar frame will cause the bearing capacity and stability of the wall to be seriously reduced. Summary of the invention
[0003] The technical problem to be solved by the present invention is that the existing embedded parts are connected to the steel frame by welding, and the rust on the exposed part of the embedded parts will be transmitted to the welding position with the steel frame, causing the steel frame to be gradually corroded, resulting in a serious decrease in the bearing capacity and stability of the wall.
[0004] In order to solve the above technical problems, the purpose of the present invention is to provide an embedded part wall connection node, including an embedded part, a first connecting part and a steel frame, the first end of the embedded part is located in the steel frame, the second end of the embedded part extends out of the steel frame, the first connecting part is made of rust-resistant material, one end of the first connecting part is provided with a first clamping structure for clamping the first end of the embedded part, and the other end of the first connecting part is provided with a second clamping structure for clamping the steel frame.
[0005] As a preferred solution, the material of the first connecting member is rubber, the first holding structure is a first holding slot arranged at one end of the first connecting member, the second holding structure is a second holding slot arranged at the other end of the first connecting member, and the second holding slot and the first holding slot are arranged at intervals.
[0006] As a preferred solution, the first connecting member is connected to a first binding member and a second binding member, the first binding member is used to bind the first connecting member to the steel frame, and the second binding member is used to bind the first connecting member to the embedded member.
[0007] As a preferred embodiment, a first binding hole and a second binding hole are arranged at intervals in the middle of the first connecting member, the first binding member is a first steel wire inserted into the first binding hole, and the second binding member is a second steel wire inserted into the second binding hole.
[0008] As a preferred solution, the embedded part includes a connecting portion and an anchoring portion embedded in the wall, the anchoring portion is arranged at an angle to the connecting portion, and one end of the connecting portion away from the anchoring portion extends out of the steel frame.
[0009] As a preferred solution, the first clamping structure is clamped on the outer side of one end of the connecting portion located inside the steel frame, and the second clamping structure is clamped on the side of the steel frame close to the connecting portion;
[0010] The embedded wall connection node includes a second connecting member, one end of which is provided with a third clamping structure, and the other end of the second connecting member is provided with a fourth clamping structure, the third clamping structure is clamped on the outside of the anchoring part, and the fourth clamping structure is clamped on the side of the steel frame away from the connecting part.
[0011] As a preferred solution, the second end of the embedded part is provided with an external thread, and the scaffolding is screwed onto the external thread.
[0012] An embodiment of a wall construction method, wherein the wall is provided with the above-mentioned embedded wall connection node, comprises the following steps:
[0013] Erect the steel reinforcement frame of the lower wall;
[0014] Positioning the embedded part to the corresponding position of the steel frame, clamping the first clamping structure on the outer side of the first end of the embedded part, and clamping the second clamping structure on the steel frame;
[0015] Casting the lower wall;
[0016] Connect the scaffolding to the second end of the embedded part to construct the steel reinforcement frame of the upper wall.
[0017] As a preferred solution, pouring the lower wall comprises the following steps:
[0018] A template is arranged outside the steel frame, so that a grouting cavity for pouring concrete is formed in the middle of the template; a through hole for the second end of the embedded part to pass through is arranged at a position of the template opposite to the second end of the embedded part;
[0019] Concrete is poured into the grouting cavity.
[0020] As a preferred solution, after the top wall is poured, the scaffolding is removed from the second end of the embedded part from top to bottom, and a keel is connected to the second end of the embedded part, and a wall panel is hung outside the keel.
[0021] Compared with the prior art, the present invention has the following beneficial effects:
[0022] The embedded part wall connection node of the present invention comprises an embedded part, a first connecting part and a steel frame, wherein the first end of the embedded part is located in the steel frame, the second end of the embedded part extends out of the steel frame, the first connecting part is made of rust-resistant material, one end of the first connecting part is provided with a first clamping structure for clamping the first end of the embedded part, and the other end of the first connecting part is provided with a second clamping structure for clamping the steel frame. The first connecting part can not only connect the embedded part to the steel frame to position the embedded part, but also the first connecting part made of rust-resistant material can prevent the rust of the embedded part from being transmitted to the steel frame, thereby avoiding the rust of the steel frame and ensuring the bearing capacity and stability of the wall. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 It is a structural schematic diagram of the embedded part wall connection node of the present invention;
[0024] Figure 2 for Figure 1 Sectional view at A-A in the middle;
[0025] Figure 3 is a cross-sectional view of the second connecting member;
[0026] Figure 4 This is the cross-sectional view of the 3rd section at B-B;
[0027] Figure 5 is a front view of the first connecting member;
[0028] In the figure, 1. embedded part; 11. connecting part; 12. anchoring part; 2. first connecting part; 21. first slot; 22. second slot; 23. first binding hole; 24. second binding hole; 3. steel bar frame; 4. second connecting part; 41. third slot; 42. fourth slot; 43. third binding hole; 44. fourth binding hole. DETAILED DESCRIPTION
[0029] The specific implementation of the present invention is further described in detail below in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.
[0030] In the description of the present invention, it should be understood that the orientation or positional relationship indicated by the terms "upper", "lower", "left", "right", "top", "bottom", etc. is based on the orientation or positional relationship shown in the accompanying drawings, and is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation of the present invention. It should be understood that the terms "first", "second", etc. are used in the present invention to describe various information, but such information should not be limited to these terms, which are only used to distinguish the same type of information from each other. For example, without departing from the scope of the present invention, the "first" information may also be referred to as the "second" information, and similarly, the "second" information may also be referred to as the "first" information.
[0031] like Figures 1 to 5 As shown, a preferred embodiment of an embedded part wall connection node of the present invention comprises an embedded part 1, a first connecting part 2 and a steel frame 3, wherein the first end of the embedded part 1 is located in the steel frame 3, and the second end of the embedded part 1 extends out of the steel frame 3, and the first connecting part 2 is made of rust-resistant material, and one end of the first connecting part 2 is provided with a first clamping structure for clamping the first end of the embedded part 1, and the other end of the first connecting part 2 is provided with a second clamping structure for clamping the steel frame 3. The first connecting part 2 can not only connect the embedded part 1 to the steel frame 3 and position the embedded part 1, but also the first connecting part 2 made of rust-resistant material can prevent the rust of the embedded part from being transmitted to the steel frame 3, thereby avoiding the steel frame 3 from being rusted and ensuring the bearing capacity and stability of the wall.
[0032] The material of the first connector 2 is rubber, the first clamping structure is a first clamping groove 21 arranged at one end of the first connector 2, the second clamping structure is a second clamping groove 22 arranged at the other end of the first connector 2, and the second clamping groove 22 and the first clamping groove 21 are arranged at intervals. The elasticity of rubber is good, so that the first clamping groove 21 can be elastically clamped on the outside of the embedded part 1, and the second clamping groove 22 can be elastically clamped on the outside of a certain steel bar of the steel bar frame 3; in addition, the rubber is integrally made into the first clamping groove 21 and the second clamping groove 22, so that the manufacturing cost of the first connector 2 is low and it is convenient for batch processing; it is conducive to installing a large number of embedded parts on the wall, and the clamping groove installation is convenient for workers to quickly install the connector 2, which greatly speeds up the construction speed and reduces the labor cost.
[0033] In other embodiments of the present invention, the first connector 2 may adopt a split structure, such as the first clamping structure and the second clamping structure are both made of steel, and the first clamping structure and the second clamping structure are connected by a rust-resistant connecting structure, and the connecting structure is made of rust-resistant materials such as plastic or rubber; or one of the first clamping structure and the second clamping structure may be made of rust-resistant material. In other embodiments of the present invention, the first clamping structure and the second clamping structure may be clamps.
[0034] Furthermore, in order to improve the connection between the first connecting member 2 and the embedded member 1, the first connecting member 2 is connected to a first binding member, which is used to bind the first connecting member 2 to the steel frame 3, and the first connecting member 2 is connected to a second binding member, which is used to bind the first connecting member 2 to the embedded member 1.
[0035] Specifically, a first lashing hole 23 and a second lashing hole 24 are arranged at intervals in the middle of the first connecting member 2. The first lashing member is a first steel wire inserted in the first lashing hole 23, and the second lashing member is a second steel wire inserted in the second lashing hole 24. The first lashing hole 23 and the second lashing hole 24 are arranged at intervals to avoid rust conduction caused by contact between the first steel wire and the second steel wire.
[0036] In this embodiment, the embedded part 1 includes a connecting part 11 and an anchoring part 12 embedded in the wall, the anchoring part 12 is arranged at an angle with the connecting part 11, and one end of the connecting part 11 away from the anchoring part 12 extends out of the steel frame 3. The provision of the anchoring part 12 improves the connection strength between the embedded part and the wall.
[0037] Furthermore, the first clamping structure is clamped on the outer side of one end of the connecting portion 11 located in the steel frame 3, and the second clamping structure is clamped on the side of the steel frame 3 close to the connecting portion 11; the embedded wall node includes a second connecting member 4, one end of the second connecting member 4 is provided with a third clamping structure, and the other end of the second connecting member 4 is provided with a fourth clamping structure, the third clamping structure is clamped on the outer side of the anchoring portion 12, and the fourth clamping structure is clamped on the side of the steel frame 3 away from the connecting portion 11.
[0038] Specifically, Figures 3 to 5 As shown, in this embodiment, in the first connecting member 2, the first slot 21 and the second slot 22 are both arc-shaped, and the axis of the first slot 21 and the axis of the second slot 22 are arranged vertically, so that the connecting part 11 is connected to the vertical steel bars of the steel frame; the anchoring part 12 is arranged vertically to the connecting part 11, and in the second connecting member 4, the third slot 43 and the fourth slot 44 are both arc-shaped, and the axis of the third slot 43 and the axis of the fourth slot 44 are arranged in parallel, so that the anchoring part 12 is connected to the horizontal ribs of the steel frame 3; in order to ensure the connection strength of the anchor 1, a plurality of second connecting members 4 can be provided, and the plurality of second connecting members 4 are arranged at intervals along the axial direction of the anchoring part 12.
[0039] In this embodiment, the second end of the embedded part 1 is provided with an external thread, and the lower end of the scaffolding is provided with a fastening structure, which is screwed to the second end of the embedded part 1; specifically, the fastening structure includes a nut and a fixing plate fixed under the scaffolding, the fixing plate is provided with a fastening hole, the second end of the embedded part 1 is passed through the fastening hole, the nut is screwed to the second end of the embedded part 1 and presses the fixing plate against the outside of the wall.
[0040] A wall construction method, in which the above-mentioned embedded wall connection node is provided, comprises the following steps:
[0041] Erecting the steel reinforcement frame 3 of the lower wall;
[0042] Position the embedded part 1 to the corresponding position of the steel frame 3, clamp the first clamping structure on the outer side of the first end of the embedded part 1, and clamp the second clamping structure on the steel frame 3;
[0043] Casting of lower wall;
[0044] Connect the scaffolding to the second end of the embedded part 1 to construct the steel bar frame of the upper wall.
[0045] The pouring of the lower wall comprises the following steps:
[0046] A template is arranged outside the steel frame 3 so that a grouting cavity for pouring concrete is formed in the middle of the template; a through hole for the second end of the embedded part 1 to pass through is arranged at a position opposite to the second end of the embedded part 1;
[0047] Pour concrete into the grouting cavity.
[0048] In this embodiment, after the top wall is poured, the scaffold is removed from the second end of the embedded part 1 from top to bottom, and the keel is connected to the second end of the embedded part 1, and the wallboard is hung outside the keel. Therefore, the embedded part of this embodiment can not only connect the scaffold during the construction of the wall body, but also can be used to connect the keel after the wall body is built to achieve the connection of the wallboard.
[0049] In summary, the embedded part wall connection node of the present invention includes an embedded part 1, a first connecting part 2 and a steel frame 3, wherein the first end of the embedded part 1 is located in the steel frame 3, the second end of the embedded part 1 extends out of the steel frame 3, the first connecting part 2 is made of rust-resistant material, one end of the first connecting part 2 is provided with a first clamping structure for clamping the first end of the embedded part 1, and the other end of the first connecting part 2 is provided with a second clamping structure for clamping the steel frame 3. The first connecting part 2 can not only connect the embedded part 1 to the steel frame 3 and position the embedded part 1, but also the first connecting part 2 made of rust-resistant material can prevent the rust of the embedded part from being transmitted to the steel frame 3, thereby avoiding the steel frame 3 from being rusted and ensuring the bearing capacity and stability of the wall.
[0050] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and substitutions can be made without departing from the technical principles of the present invention. These improvements and substitutions should also be regarded as the scope of protection of the present invention.
Claims
1. A pre-embedded wall connection node, characterized in that: The invention comprises an embedded part (1), a first connecting part (2) and a steel frame (3), wherein the first end of the embedded part (1) is located in the steel frame (3), the second end of the embedded part (1) extends out of the steel frame (3), the first connecting part (2) is made of rust-resistant material, one end of the first connecting part (2) is provided with a first clamping structure for clamping the first end of the embedded part (1), and the other end of the first connecting part (2) is provided with a second clamping structure for clamping the steel frame (3); the material of the first connecting part (2) is rubber, the first clamping structure is a first clamping groove (21) arranged at one end of the first connecting part (2), the second clamping structure is a second clamping groove (22) arranged at the other end of the first connecting part (2), and the second clamping groove (22) and the first clamping groove (21) are arranged at intervals; The first connecting member (2) is connected to a first tying member and a second tying member, the first tying member is used to tie the first connecting member (2) to the steel bar frame (3), and the second tying member is used to tie the first connecting member (2) to the embedded member (1); A first tying hole (23) and a second tying hole (24) are arranged at intervals in the middle of the first connecting member (2); the first tying member is a first steel wire inserted into the first tying hole, and the second tying member is a second steel wire inserted into the second tying hole; The second end of the embedded part (1) is also used to connect the keel after the scaffolding is removed, and the keel is used to hang the wall panel.
2. The embedded wall connection node according to claim 1, characterized in that: The embedded part (1) comprises a connecting portion (11) and an anchoring portion (12) embedded in the wall, the anchoring portion (12) and the connecting portion (11) are arranged at an angle, and one end of the connecting portion (11) away from the anchoring portion (12) extends out of the steel bar frame (3).
3. The embedded wall connection node according to claim 2, characterized in that: The first clamping structure is clamped on the outer side of one end of the connecting portion (11) located inside the steel frame (3), and the second clamping structure is clamped on a side of the steel frame (3) close to the connecting portion (11); The embedded part wall connection node comprises a second connecting part (4), one end of the second connecting part (4) is provided with a third clamping structure, the other end of the second connecting part (4) is provided with a fourth clamping structure, the third clamping structure is clamped on the outside of the anchoring part (12), and the fourth clamping structure is clamped on the side of the reinforcement frame (3) away from the connecting part (11).
4. The embedded wall connection node according to any one of claims 1 to 3, characterized in that: The second end of the embedded part (1) is provided with an external thread, and the scaffolding is screwed onto the external thread.
5. A wall construction method, characterized in that: The wall is provided with the embedded wall connection node according to any one of claims 1 to 4, comprising the following steps: Erecting a steel reinforcement frame (3) for the lower wall; Positioning the embedded component (1) at a corresponding position of the steel frame (3), clamping the first clamping structure on the outer side of the first end of the embedded component (1), and clamping the second clamping structure on the steel frame (3); Casting the lower wall; The scaffolding is connected to the second end of the embedded part (1) to construct the steel reinforcement frame of the upper wall.
6. The wall construction method according to claim 5, characterized in that: Casting the lower wall comprises the following steps: A template is arranged outside the steel frame (3) so that a grouting cavity for pouring concrete is formed in the middle of the template; a through hole is provided at a position of the template opposite to the second end of the embedded part (1) for the second end of the embedded part (1) to pass through; Concrete is poured into the grouting cavity.
7. The wall construction method according to claim 5, characterized in that: After the top wall is poured, the scaffolding is removed from the second end of the embedded part (1) from top to bottom, and a keel is connected to the second end of the embedded part (1), and a wall panel is hung on the outside of the keel.
Citation Information
Patent Citations
Multifunctional split bolt and application thereof
CN103061505A
Building engineering wall body rebars formwork support spare
CN208668965U
Scaffold embedded assembly type wall connecting device
CN212336695U