A composite material micropipe gallery and its drainage method

By arranging brackets and siphon water collection buckets in composite micro-pipe galleries, combined with multi-stage siphon effect and drainage pipe combination, the problem of poor drainage effect of micro-pipe corridors in the existing technology is solved, and low energy consumption and fast drainage are achieved. The effect is to improve safety and engineering efficiency.

CN116005719BActive Publication Date: 2024-10-29CHINA RAILWAY ERYUAN ENGINEERING GROUP CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202310211603.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-03-07
Publication Date
2024-10-29
Estimated Expiration
2043-03-07

AI Technical Summary

Technical Problem

The existing composite micro-pipe gallery has unsatisfactory drainage effects. Especially when it is buried shallowly and is affected by outdoor rainwater, it is prone to water accumulation and leakage, leading to equipment damage and safety hazards.

Method used

A composite micro pipe gallery is designed. Brackets are provided on the inner wall to fix cables and pipes. A siphon water collection bucket and a water distribution pipe are provided in the water collection pit. Through the combination of multi-stage siphon effect and drainage pipes, automatic and rapid drainage is achieved to avoid Additional energy consumption, and the centralized discharge efficiency of water is improved through the circular cross-section and annular bracket.

Benefits of technology

It achieves low-cost, low-energy rapid drainage, effectively prevents equipment damage caused by water accumulation in the pipe gallery, improves safety and engineering efficiency, and reduces operating costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116005719B_ABST
    Figure CN116005719B_ABST
Patent Text Reader

Abstract

The present invention discloses a composite material micro-pipeline gallery and a drainage method thereof. The micro-pipeline gallery comprises a gallery body, a plurality of water collection pits are arranged at the bottom of the gallery body, a water collection tank is arranged in each of the water collection pits, a vertical water distribution pipe is arranged at the bottom of the water collection tank, a siphon water collection bucket is arranged at the upper end of the water distribution pipe, and the lower end of the water distribution pipe is connected and communicated with a drainage system; the drainage system comprises a first drainage pipe, a second drainage pipe and a third drainage pipe connected in sequence, the inlet of the first drainage pipe is communicated with the bottom of the water collection tank, the second drainage pipe comprises a second drainage small pipe, a second drainage middle pipe and a second drainage large pipe arranged in parallel from bottom to top, and the outlet of the third drainage pipe is located in a rainwater inspection well. The present invention quickly discharges the accumulated water in the pipe gallery through the siphon effect, does not require additional energy consumption, has low operating cost, and has a fast drainage speed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of pipe gallery, and in particular to a composite material micro pipe gallery and a drainage method thereof. Background Art

[0002] Micro-pipeline corridors are usually buried under roads, square sidewalks or green belts to centrally arrange pipelines. There are many types and quantities of pipelines in micro-pipeline corridors, usually including communication cables, high-voltage cables and water pipes (recycled water pipes), etc. In addition to the advantages of conventional concrete pipe corridors, micro-pipeline corridors also have significantly lower costs, shallow burial depth, small cross-section, and are very convenient to avoid other pipelines. Maintenance and repair have also been widely recognized, overcoming the significant low-cost economy and practicality of conventional concrete pipe corridors and are increasingly used.

[0003] Conventional reinforced concrete micro-pipeline corridors are severely corroded, with a single section of 2-4m / section, large mass, inconvenient construction and hoisting, serious leakage at the corridor interface, and high comprehensive unit price, so they are subject to certain restrictions. However, due to the poor corrosion resistance and poor anti-leakage ability of reinforced concrete, especially the key nodes of railway-related projects are prone to the settlement of railway bridges or roadbeds in the near future, thus causing safety and quality accidents. At present, micro-pipelines made of composite materials are popular with everyone. Composite materials have high strength, corrosion resistance and long service life, but there are still problems with drainage in micro-pipelines. Micro-pipelines are often laid under sidewalks, squares or green belts, with shallow soil covering, with a burial depth of 1.0~2.0, while the burial depth of outdoor rainwater pipes is generally 3-5m deep, so it is not economical to use dynamic drainage. The accumulated water in the sump in the corridor includes small amounts of water such as rainwater infiltration from the cover plate, groundwater infiltration, rainwater infiltration from the inspection hole, water supply pipe leakage, water supply pipe maintenance and emptying, as well as large amounts of water such as water supply pipe burst accidents and large amounts of water infiltration from outdoor rainwater due to cover plate damage. At present, some patent documents have adopted the siphon principle to improve drainage efficiency, but the overall drainage effect has not reached the ideal effect. Summary of the invention

[0004] The purpose of the present invention is to overcome the above-mentioned deficiencies in the prior art and to provide a composite material micro-pipeline gallery and a drainage method thereof.

[0005] In order to achieve the above-mentioned object of the invention, the present invention provides the following technical solutions:

[0006] A composite material micro-pipe gallery, comprising a gallery body, a plurality of brackets are arranged on the inner wall of the gallery body, the plurality of brackets are arranged at intervals in the length direction of the micro-pipe gallery, a cable bracket is arranged on the inner side wall of the gallery body for placing various cables, a pipe is placed on the bottom wall of the gallery body, the pipe is fixed on the bracket, a plurality of water collection pits are arranged at the bottom of the gallery body, each of the water collection pits is provided with a water collection trough, a vertical water distribution pipe is arranged at the bottom of the water collection trough, a plurality of water inlet holes are arranged on the side wall of the water distribution pipe, a siphon water collection bucket is arranged at the upper end of the water distribution pipe, and the lower end of the water distribution pipe is connected to a drainage system;

[0007] The drainage system includes a first drainage pipe, a second drainage pipe and a third drainage pipe which are connected in sequence. The inlet of the first drainage pipe is connected to the bottom of the water collecting tank. The second drainage pipe includes a second small drainage pipe, a second middle drainage pipe and a second large drainage pipe which are arranged in parallel from bottom to top. The diameter of the second middle drainage pipe is larger than the diameter of the second small drainage pipe, the diameter of the second middle drainage pipe is smaller than the diameter of the second large drainage pipe, the highest point of the second middle drainage pipe is not higher than the lowest point of the first drainage pipe, and the highest point of the second large drainage pipe is not higher than the top surface of the siphon water collecting bucket. The outlet of the third drainage pipe is located in the rainwater inspection well.

[0008] The present embodiment provides a composite material micro-pipe gallery, in which equipment such as cables and pipes are arranged, and brackets are arranged on the inner wall of the micro-pipe gallery for fixing the cable brackets and pipes. The accumulated water in the micro-pipe gallery will enter the sump, and a siphon water collecting bucket is arranged in the sump. The siphon water collecting bucket has a very strong anti-vortex function. On the one hand, a siphon effect occurs when the water level line is higher than the siphon water level line of the siphon water collecting bucket. On the other hand, it can well prevent air from being brought into the whole system through the water flow at the entrance of the water collecting bucket, and when the water level in front of the bucket rises to a certain level, a water seal is formed to completely block the entry of air, and the accumulated water enters the water distribution pipe. After entering the water distribution pipe, the water can enter the drainage system connected with the water distribution pipe.

[0009] When there is water leakage in the micro-pipeline gallery and the water is less, the water level in the sump is low, and the accumulated water enters the water distribution pipe through the water inlet hole. The water distribution pipe transports the accumulated water to the first drainage pipe. Under the action of its own weight, the accumulated water flows from the second drainage pipe into the outdoor rainwater inspection well and is finally discharged through the rainwater drainage pipe.

[0010] When there is water leakage in the micro-pipeline gallery or water leakage in the pipe, and there is a lot of water accumulation, the water distribution pipe transports the accumulated water to the first drainage pipe, and the highest point of the second drainage middle pipe is flush with or higher than the lowest point of the first drainage pipe. If the water level of the second drainage middle pipe is higher than the highest point of the second drainage middle pipe, the second drainage middle pipe produces a siphon effect, and the water in the second drainage middle pipe is drained to the rainwater inspection well by siphoning, which further increases the drainage efficiency;

[0011] When there is water leakage in the micro-pipeline corridor or the pipes are leaking, and there is a lot of water accumulation, the water level in the sump is higher than the siphon water level line of the siphon water collecting bucket, and the accumulated water enters the water distribution pipe through the siphon water collecting bucket. Under the siphon effect at the siphon water collecting bucket, the accumulated water in the sump will be quickly discharged into the drainage system. At this time, the highest point of the second drainage pipe is flush with or lower than the top surface of the siphon water collecting bucket. If the water level of the second drainage pipe is higher than the highest point of the second drainage pipe, the second drainage pipe will produce a siphon effect, and the water in the second drainage pipe will be drained to the rainwater inspection well by siphoning. The double siphon effect further increases the drainage efficiency, and quickly drains a large amount of water from the sump. The above drainage process is all automatic drainage, does not require additional energy consumption, has low operating costs, and has a fast drainage speed. In addition, in the present invention, the second drainage middle pipe and the second drainage large pipe can drain water by siphoning. When the water level in the rainwater inspection well is higher than the siphon water level line at the siphon collecting bucket, the water inlet and drainage direction of the second drainage pipe can be opposite to each other to prevent backflow into the pipe gallery, thereby eliminating the need to set a check valve device at the third drainage pipe.

[0012] As a preferred solution of the present invention, the pipe gallery structure has a thickness of 15 to 50 mm.

[0013] As a preferred solution of the present invention, the cross section of the gallery is circular, and the bracket arranged in the gallery is a ring bracket. The circular gallery is in line with the height and aesthetics of the human body, with a smaller head and a wider body. The smaller space inside the micro-gallery creates a great amount of maintenance space. At the same time, the circular gallery can further ensure that the water in the micro-gallery is concentrated in the sump for discharge, preventing water accumulation in the gallery.

[0014] As a preferred solution of the present invention, the cable support is fixedly mounted on the annular support, and the pipeline is fixed to the support via a pipe clamp.

[0015] As a more preferred solution of the present invention, the cables include power cables and communication cables, and the pipes include grey water pipes, water supply pipes, drainage pipes, etc.

[0016] As a preferred solution of the present invention, a pedestrian grille is provided at the bottom of the corridor, and the pedestrian grille is a frame structure.

[0017] As a preferred solution of the present invention, a fire extinguisher is also provided in the micro-pipeline gallery. The fire extinguisher is arranged at intervals on the top of the gallery body along the length direction of the micro-pipeline gallery and is used for extinguishing fire when a fire occurs in the gallery.

[0018] As a preferred solution of the present invention, the pipeline is connected to the sump through a pipeline drain pipe, which is used to provide the required water in the sump or empty or drain the pipeline. Furthermore, a hydroelectric power generation component is arranged on the pipeline drain pipe, and the hydroelectric power generation component is arranged at a lower part of the pipeline drain pipe. The hydroelectric power generation component has a lighting function and a sound monitoring function. The lighting function can provide lighting for the staff during maintenance, which greatly improves safety. The sound monitoring function can automatically turn off the lighting function when the staff leaves.

[0019] As a preferred solution of the present invention, the second small drainage pipe is an inclined curved pipe with an angle of 100-135°, the second middle drainage pipe and the second large drainage pipe are arc-shaped pipes, and the second middle drainage pipe is located on the inner side of the second large drainage pipe.

[0020] As a preferred solution of the present invention, the third drain pipe is fixed to the side wall of the rainwater inspection well by a fixing bracket.

[0021] As a preferred solution of the present invention, the third drain pipe outlet is configured as a duckbill valve outlet to prevent water in the rainwater inspection well from flowing back to the micro-pipeline gallery, serving as an anti-backflow system.

[0022] As a preferred solution of the present invention, a lighting system is provided in the micro-tunnel, and the lighting system includes a lighting device, a light guide device, and a projection light device. The lighting device is provided on the ground, and is used to sense the sun and gather the sunlight, and after coupling, enter the light guide device. The light guide device includes an optical fiber, and the optical fiber connects the lighting device and the projection light device. In addition, the projection light device is a lighting lamp, and the optical fiber connects the lighting lamp, and the sunlight introduced from the outside drives the lighting lamp to work and provide lighting; the projection light device is arranged on the inner top wall at intervals along the tunnel, and the sunlight is used for lighting in the tunnel, which can save electricity during daytime maintenance.

[0023] The present invention also provides a drainage method for a composite material micro-pipe gallery, wherein the water in the gallery body enters the sump and then enters the sump;

[0024] When the water level in the water collection tank is lower than the top surface of the siphon water collection bucket, water enters the water distribution pipe, and the water distribution pipe transports the water to the first drainage pipe. If the water level in the second drainage middle pipe is lower than the highest point of the second drainage middle pipe, the water flows from the second drainage small pipe to the third drainage pipe under the action of its own weight and is discharged; if the water level in the second drainage middle pipe is higher than the highest point of the second drainage middle pipe, the water flows from the second drainage middle pipe to the third drainage pipe under the siphon effect and is discharged;

[0025] When the water level in the sump is lower than the top surface of the siphon hopper, the water is discharged into the first drain pipe under the siphon effect. If the water level in the second drain pipe is higher than the highest point of the second drain pipe, the water flows from the second drain pipe into the third drain pipe under the siphon effect and is discharged.

[0026] Compared with the prior art, the present invention has the following beneficial effects:

[0027] 1. The micro-pipe gallery of the present invention is provided with a bracket on the inner wall for fixing the cable bracket and the pipe. The accumulated water in the micro-pipe gallery will enter the sump. A siphon water collecting bucket is provided in the sump. When the accumulated water is less, the accumulated water enters the water distribution pipe through the water inlet hole. The water distribution pipe transports the accumulated water to the first drainage pipe. The accumulated water flows from the second drainage pipe into the outdoor rainwater inspection well under the action of its own weight. The water is automatically discharged by the gravity of the water body without consuming additional energy. When the accumulated water is more, the water distribution pipe transports the accumulated water to the first drainage pipe. If the water level of the second drainage middle pipe is higher than the highest point of the second drainage middle pipe, the second drainage middle pipe generates a siphon effect, and the water in the second drainage middle pipe is drained by siphoning. To the rainwater inspection well, the drainage efficiency is further increased, and the siphon effect is used to drain water, the drainage speed is fast, and no extra energy is consumed; when there is a lot of accumulated water, the water level in the sump is higher than the siphon water level line of the siphon water collecting bucket, and the accumulated water enters the water distribution pipe through the siphon water collecting bucket. Under the siphon effect at the siphon water collecting bucket, the accumulated water in the sump will be quickly discharged into the drainage system. At this time, if the water level of the second drainage pipe is higher than the highest point of the second drainage pipe, the second drainage pipe will produce a siphon effect, and the water in the second drainage pipe will be drained to the rainwater inspection well by siphoning. Through the double siphon effect, the drainage efficiency is further increased, and a large amount of water in the sump is quickly discharged. The above drainage process is all automatic drainage, does not require additional energy consumption, has low operating costs, and has a fast drainage speed, and can effectively prevent the equipment in the micro-pipeline from being soaked in accumulated water and damaged.

[0028] 2. In the drainage system of the micro-pipeline gallery of the present invention, the second drainage middle pipe and the second drainage large pipe can drain water by siphoning. When the water level in the rainwater inspection well is higher than the siphon water level line at the siphon collecting bucket, the water inlet and drainage directions of the second drainage pipe can be opposite to each other to prevent backflow into the pipe gallery, thereby eliminating the need to set a check valve device at the third drainage pipe.

[0029] 3. The cross-section of the micro-pipeline corridor of the present invention is circular. It is made of fiber material and unsaturated polyester resin through a special process. It replaces the original traditional reinforced concrete pipe corridor. It has the advantages of long service life, quick installation, good anti-leakage performance, etc. It can realize factory-style assembly production, speed up the progress of project installation, improve the completion efficiency of product engineering, have a low comprehensive cost, and embody the significant characteristics of green, low-carbon, energy-saving and environmental protection. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] Figure 1 is a cross-sectional view of the composite material micro-pipeline gallery in Example 1;

[0031] Figure 2 It is a partial cross-sectional view of the composite material micro-pipeline gallery;

[0032] Figure 3 It is a partial cross-sectional view of the composite material micro-pipeline gallery;

[0033] Figure 4 is a cross-sectional view of the composite material micro-pipeline gallery in Example 2;

[0034] Markings in the figure: 1-corridor, 11-annular channel steel, 21-bracket, 22-power cable, 23-communication cable, 31-water supply pipe, 32-drainage pipe, 33-pipe clamp, 34-pedestrian grating plate, 35-pipeline drainage pipe, 36-hydropower generation component, 41-sump, 42-sump, 43-water distribution pipe, 44-siphon water collecting bucket, 51-first drainage pipe, 52-second small drainage pipe, 53-second middle drainage pipe, 54-second large drainage pipe, 55-third drainage pipe, 56-duckbill valve outlet, 57-fixed bracket, 6-rainwater inspection well, 71-lighting device, 72-projection light device. DETAILED DESCRIPTION

[0035] The present invention is further described in detail below in conjunction with test examples and specific implementation methods. However, this should not be understood as the scope of the above subject matter of the present invention being limited to the following embodiments, and all technologies realized based on the content of the present invention belong to the scope of the present invention.

[0036] Example 1

[0037] A composite material micro-pipe gallery, comprising a gallery body 1, a plurality of brackets are arranged on the inner wall of the gallery body 1, and the plurality of brackets are arranged at intervals in the length direction of the micro-pipe gallery, a cable bracket is arranged on the inner side wall of the gallery body 1 for placing various cables, a pipe is placed on the inner bottom wall of the gallery body 1, and the pipe is fixed on the bracket, a plurality of water collection pits 41 are arranged at the bottom of the gallery body 1, a water collection trough 42 is arranged in each of the water collection pits 41, a vertical water distribution pipe 43 is arranged at the bottom of the water collection trough 42, a plurality of water inlet holes are arranged on the side wall of the water distribution pipe 43, and a siphon water collection bucket 44 is arranged at the upper end of the water distribution pipe 43, and the lower end of the water distribution pipe 43 is connected to a drainage system;

[0038] The drainage system includes a first drainage pipe 51, a second drainage pipe and a third drainage pipe 55 which are connected in sequence. The inlet of the first drainage pipe 51 is connected to the bottom of the water collecting tank 42. The second drainage pipe includes a second drainage small pipe 52, a second drainage middle pipe 53 and a second drainage large pipe 54 which are arranged in parallel from bottom to top. The diameter of the second drainage middle pipe 53 is larger than the diameter of the second drainage small pipe 52, the diameter of the second drainage middle pipe 53 is smaller than the diameter of the second drainage large pipe 54, the highest point of the second drainage middle pipe 53 is not higher than the lowest point of the first drainage pipe 51, and the highest point of the second drainage large pipe 54 is not higher than the top surface of the siphon water collecting bucket 44; the outlet of the third drainage pipe 55 is located in the rainwater inspection well.

[0039] It should be noted that the top surface of the sump 41 is lower than the bottom surface of the gallery 1 or is flush with the bottom surface of the gallery 1. This arrangement ensures that the water in the micro-pipe gallery is concentrated in the sump 41, which is conducive to the discharge of accumulated water. Specifically, in this embodiment, the top surface of the sump 41 is flush with the bottom surface of the inner cavity of the micro-pipe gallery. The water distribution pipe 43 is used to discharge the accumulated water in the sump 42 into the drainage system. The accumulated water in the sump 42 enters the water distribution pipe 43 in two ways, one is to enter the water distribution pipe 43 through the water inlet hole on the side wall of the water distribution pipe 43, and the other is to enter the water distribution pipe 43 through the siphon water collection bucket 44. In addition, the first drainage pipe 51 is connected to the sump 42 through an elbow. The first drainage pipe 51 is inclined. Specifically, the angle between the first drainage pipe 51 and the horizontal plane is 1 to 10 degrees to improve drainage efficiency. The outdoor rainwater inspection well 6 is part of the existing drainage system, which is used to drain the water in the pipe gallery to the outside of the pipe gallery, mainly into the rainwater inspection well 6, and then discharged centrally through the outdoor rainwater drainage pipe. The siphon water collecting bucket 44 is a conventional siphon rainwater bucket, which is purchased commercially.

[0040] This embodiment provides a micro-pipeline corridor for passing under a railway, such as Figure 1-3 As shown in the figure, the micro-pipeline corridor is laid under the sidewalk or green belt, with a shallow burial depth, which reduces investment and avoids conflicts with drainage pipe branches. The thickness of the pipe corridor structure is 15~50mm, and the specific thickness is selected and adjusted according to the actual situation of the project.

[0041] like Figure 1 As shown, the cross section of the gallery 1 is circular. The circular gallery is in line with the height and aesthetics of the human body, with a smaller head and a wider body. The smaller space inside the micro gallery creates a great amount of maintenance space. At the same time, the circular gallery can further ensure that the water in the micro gallery is concentrated in the sump 41 for discharge to prevent water accumulation in the gallery. In this embodiment, the gallery 1 is supported by a fiber-reinforced polymer matrix, specifically basalt fiber polyester resin, which has the advantages of energy saving and environmental protection. The ring stiffness is 10KN / m2 The pressure level is PN6, and the socket joint is connected. Specifically, the corridor 1 is a three-layer composite material structure consisting of a fiber protective layer, a basalt fiber base layer and a resin protective layer, which is lighter and less difficult to construct. At the same time, a sealing ring can be set at the interface of the corridor 1 segment to improve the anti-seepage and water leakage effect.

[0042] An annular channel steel 1 is arranged on the inner wall of the micro-pipeline gallery, and the bracket is an annular bracket. Specifically, the bracket is a channel steel. When designed, the bracket is a circular ring with an adjustable inner diameter length. The outer circle forms a secondary lining, forming an integral body. The bracket can effectively support the external composite material and prevent the fiber-reinforced pipe gallery of the composite material from being pulled. The bracket is a circular ring with an adjustable inner diameter length, so that the outer diameter of the circular ring can be adjusted to be firmly fixed at the inner circle of the fiber-wound integrated pipe gallery, and the installation spacing of the circular ring in the integrated pipe gallery and the circumferential positioning can be adjusted arbitrarily.

[0043] The cable bracket is fixedly installed on the annular bracket, and the mounting holes for the transverse cable bracket are processed on the annular bracket. The number and spacing of the transverse cable brackets can be flexibly arranged according to the needs. The pipeline is fixed to the bracket through a pipe clamp 33. Further, the cables include power cables 22 and communication cables 23. The cable bracket adopts hot magnesium zinc anti-corrosion treatment, and the installation spacing of the cable bracket is 1.5m. The pipeline includes a recycled water pipe, a water supply pipe 31, a drainage pipe, etc. Figure 2 As shown, in this embodiment, the pipeline includes a recycled water pipe and a water supply pipe 31, the left side is the recycled water pipe, which is ≤DN300, and the right side is the water supply pipe 31, which is ≤DN300.

[0044] A pedestrian grille plate 34 is arranged at the bottom of the corridor body 1. The pedestrian grille plate 34 is a frame structure fixed on the bracket. At the same time, drainage holes are arranged on the pedestrian grille plate 34, taking into account both pedestrian and drainage functions.

[0045] In some embodiments, a fire extinguisher is also provided in the micro-pipeline gallery, and the fire extinguisher is arranged at intervals on the top of the micro-pipeline gallery along the length direction of the micro-pipeline gallery. Figure 1 It is not shown in the figure. The fire extinguisher is fixed to the bracket with an expansion screw with a hook. The load-bearing structure should meet a static load of not less than 5 times the weight of the device. The nozzle is downward in the plumb direction and is used to extinguish fire when a fire occurs in the pipe gallery. The fire extinguisher is a dry powder fire extinguisher.

[0046] like Figure 2As shown, the pipeline is connected to the sump 41 through a pipeline drain pipe 35, which is used to provide the required water in the sump 41 or empty or drain the pipeline. Furthermore, a hydroelectric component 36 is provided on the pipeline drain pipe 35, and the hydroelectric component 36 is arranged at a lower position of the pipeline drain pipe 35. The hydroelectric component 36 has a lighting function and a sound monitoring function. The lighting function can provide lighting for the staff to inspect and repair, which greatly improves safety. The sound monitoring function can automatically turn off the lighting function when the staff leaves. The hydroelectric component 36 can be purchased in a commercially available manner. The sump 42 is a truncated cone, with the large end facing up and the small end facing down. Holes are provided on the inner wall of the sump 42 to filter and prevent large particles of stone and sand from entering the sump 42. In some embodiments, the sump 42 is made of a composite material structure. A siphon water collecting bucket 44 is arranged in the sump 42 and is fixedly connected to the sump 42. Specifically, the water distribution pipe 43 is a composite drainage and drainage pipe.

[0047] The height of the top of the siphon water collecting bucket 44 is the siphon drainage water level line. When the water level in the water collecting tank 42 is higher than this water level, the drainage system is siphon pressure drainage. When the water level in the water collecting tank 42 is lower than this water level, it is gravity drainage.

[0048] like Figure 3 As shown, the second drainage small pipe 52 is an inclined curved pipe with an angle of 100-135°, the second drainage middle pipe 53 and the second drainage large pipe 54 are arc-shaped pipes, and the second drainage middle pipe 53 is located inside the second drainage large pipe 54. The third drainage pipe 55 is fixed to the side wall of the rainwater inspection well by a fixing bracket 57.

[0049] Furthermore, the outlet of the third drainage pipe 55 is set as a duckbill valve outlet 56 to prevent the water in the rainwater inspection well 6 from flowing back to the micro-pipe gallery, serving as an anti-backflow system. The outlet of the third drainage pipe 55 is set as low as possible to facilitate the rapid discharge of the siphon effect water flow of the drainage system, and at the same time, the outlet of the third drainage pipe 55 meets the requirement of being higher than the top elevation of the rainwater inspection well 6.

[0050] In some embodiments, a comprehensive monitoring system and a marking system are installed inside the tunnel. The micro tunnel does not contain fire separations (partitions), ventilation facilities, or lighting facilities. For wiring and maintenance, an inspection hole is set up every 50 meters.

[0051] Example 2

[0052] This embodiment is similar to Embodiment 1, except that a lighting system is provided in the micro-tube gallery of this embodiment. Figure 4As shown, the lighting system includes a lighting device 71, a light guide device, and a projection light device 72. The lighting device 71 is set on the ground. The lighting device 71 includes a sensor, a microcomputer, a driver, a micromotor, a transmission system, a lens group array, etc. The sensor senses the sun's position, and the microcomputer sends instructions to drive the lens group to accurately track the sun, focusing the sunlight more than 10,000 times, and coupling it into the optical fiber of the light guide device. The lighting device 71 automatically wakes up, tracks, and resets every day without any human intervention. The light guide device includes a light guide optical fiber, which connects the lighting device 71 and the projection light device 72, and transmits the light in the lighting device 71 to the projection light device 72. The projection light device 72 in this embodiment is a lighting lamp, which is arranged on the top wall of the corridor at intervals along the corridor.

[0053] Example 3

[0054] This embodiment provides a drainage method for the micro-pipeline gallery of embodiment 1, wherein the water in the gallery body 1 enters the sump 41 and then enters the sump 42;

[0055] When the water level in the water collection tank 42 is lower than the top surface of the siphon water collection bucket 44, water enters the water distribution pipe 43, and the water distribution pipe 43 transports the water to the first drainage pipe 51. If the water level in the second drainage middle pipe 53 is lower than the highest point of the second drainage middle pipe 53, the water flows from the second drainage small pipe 52 to the third drainage pipe 55 for discharge under the action of its own weight; if the water level in the second drainage middle pipe 53 is higher than the highest point of the second drainage middle pipe 53, the water flows from the second drainage middle pipe 53 to the third drainage pipe 55 for discharge under the siphon effect;

[0056] When the water level in the water collecting tank 42 is lower than the top surface of the siphon collecting bucket 44, the water is discharged into the first drain pipe 51 under the action of the siphon effect. If the water level in the second drain pipe 54 is higher than the highest point of the second drain pipe 54, the water flows from the second drain pipe 54 to the third drain pipe 55 under the siphon effect.

[0057] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A composite material micro-pipeline gallery, comprising a gallery body (1), characterized in that: A plurality of brackets are arranged on the inner wall of the corridor (1), and the plurality of brackets are arranged at intervals in the length direction of the micro-pipe corridor. A cable bracket is arranged on the inner side wall of the corridor (1) for placing various cables. A pipe is placed on the inner bottom wall of the corridor (1), and the pipe is fixed on the bracket. A plurality of water collection pits (41) are arranged at the inner bottom of the corridor (1), and a water collection trough (42) is arranged in each of the water collection pits (41). A vertical water distribution pipe (43) is arranged at the bottom of the water collection trough (42). A plurality of water inlet holes are arranged on the side wall of the water distribution pipe (43), and a siphon water collection bucket (44) is arranged at the upper end of the water distribution pipe (43). The lower end of the water distribution pipe (43) is connected to a drainage system. The drainage system comprises a first drainage pipe (51), a second drainage pipe and a third drainage pipe (55) which are connected in sequence. The inlet of the first drainage pipe (51) is communicated with the bottom of the water collecting tank (42). The second drainage pipe comprises a second drainage small pipe (52), a second drainage middle pipe (53) and a second drainage large pipe (54) which are connected in parallel and arranged from bottom to top. The diameter of the second drainage middle pipe (53) is larger than the diameter of the second drainage small pipe (52), and the diameter of the second drainage middle pipe (53) is smaller than the diameter of the second drainage large pipe (54). The diameter of the second drainage middle pipe (53) is not higher than the lowest point of the first drainage pipe (51), and the highest point of the second drainage large pipe (54) is not higher than the top surface of the siphon collecting bucket (44); the outlet of the third drainage pipe (55) is located in the rainwater inspection well; the second drainage small pipe (52) is an inclined curved pipe with an angle of 100-135°, the second drainage middle pipe (53) and the second drainage large pipe (54) are arc-shaped pipes, and the second drainage middle pipe (53) is located on the inner side of the second drainage large pipe (54).

2. The composite material micro-pipeline gallery according to claim 1, characterized in that: The cross section of the gallery body (1) is circular, and the bracket arranged in the gallery body (1) is an annular bracket.

3. The composite material micro-pipeline gallery according to claim 1, characterized in that: A pedestrian grille plate (34) is arranged at the bottom of the gallery body (1), and the pedestrian grille plate (34) is a frame structure.

4. The composite material micro-pipeline gallery according to claim 1, characterized in that: The pipeline is connected to the sump (41) via a pipeline drain pipe (35).

5. The composite material micro-pipeline gallery according to claim 4, characterized in that: A hydroelectric power generation component (36) is arranged on the pipeline drainage pipe (35). The hydroelectric power generation component (36) is arranged at a lower position of the pipeline drainage pipe (35). The hydroelectric power generation component (36) has a lighting function and a sound monitoring function.

6. The composite material micro-pipeline gallery according to claim 1, characterized in that: The third drainage pipe (55) is fixed to the side wall of the rainwater inspection well via a fixing bracket (57).

7. The composite material micro-pipeline gallery according to claim 1, characterized in that: The outlet of the third drainage pipe (55) is configured as a duckbill valve outlet (56) to prevent water in the rainwater inspection well (6) from flowing back into the micro-pipe gallery, serving as an anti-backflow system.

8. The composite material micro-pipeline gallery according to claim 1, characterized in that: The micro-pipeline corridor is provided with a lighting system, the lighting system comprising a lighting device (71), a light guiding device, and a projection light device (72). The lighting device (71) is provided on the ground and is used to sense the sun and gather sunlight, which enters the light guiding device after coupling. The projection light device (72) is provided on the inner top wall at intervals along the pipe corridor.

9. The drainage method of a composite material micro-pipeline gallery according to any one of claims 1 to 8, wherein the water in the gallery body (1) enters the sump (41) and then enters the sump (42); When the water level in the water collecting tank (42) is lower than the top surface of the siphon water collecting bucket (44), water enters the water distribution pipe (43), and the water distribution pipe (43) transports the water to the first drainage pipe (51). If the water level in the second drainage middle pipe (53) is lower than the highest point of the second drainage middle pipe (53), the water flows from the second drainage small pipe (52) into the third drainage pipe (55) under the action of its own weight and is discharged; if the water level in the second drainage middle pipe (53) is higher than the highest point of the second drainage middle pipe (53), the water flows from the second drainage middle pipe (53) into the third drainage pipe (55) under the siphon effect and is discharged; When the water level in the water collecting trough (42) is higher than the top surface of the siphon water collecting bucket (44), the water is discharged into the first drainage pipe (51) under the action of the siphon effect. If the water level in the second drainage pipe (54) is higher than the highest point of the second drainage pipe (54), the water flows from the second drainage pipe (54) into the third drainage pipe (55) under the siphon effect and is discharged.

Citation Information

Patent Citations

  • Weak permeation soil layer slope underground water disaster treatment method

    CN114575359A

  • Automatic drain in order

    CN207277484U

  • Miniature pipe gallery drainage system

    CN212104426U