Publication Date
2024-11-08
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing artificial turf cannot be drained in time during heavy rain, which is prone to water accumulation, and poor material performance leads to fading, desilencing, breaking and other problems, and is prone to static hazards, affecting the safety of activities.

Method used

Using a structure including plain soil layer, drainage layer, concrete layer, buffer layer and quartz sand layer, by setting up U-shaped grooves on the surface of the buffer layer and filling ceramics with concrete layer, improving water flow permeability and drainage efficiency, and in artificial Use modified materials and reasonable raw materials to improve the color fixation, anti-silver and anti-breaking properties of the lawn.

Benefits of technology

It achieves rapid drainage, extends service life, reduces static electricity generation, improves the quality and safety of artificial turf, and significantly improves drainage efficiency and service life.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118910969A_ABST
    Figure CN118910969A_ABST
Patent Text Reader

Abstract

The invention discloses an anti-ponding gate court artificial turf and a construction method, and relates to the technical field of artificial turfs.The anti-ponding gate court artificial turf comprises a plain soil layer, a drainage layer, a concrete layer, a buffer layer and a quartz sand layer, the drainage layer is laid on the upper surface of the plain soil layer, and first geotechnical cloth is laid on the upper surface of the drainage layer; a gravel layer is laid on the upper surface of the first geotechnical cloth, a concrete layer is arranged on the upper surface of the gravel layer, a buffer layer is laid on the upper surface of the concrete layer, and when rainwater is large, accumulated water on the ground can permeate into a groove in the surface of the top of the buffer layer through the surface of the lawn; the grooves are formed in the surface of the buffer layer, so that the circulation of accumulated water in the buffer layer is improved, the downward permeation speed of the accumulated water on the ground is increased, the accumulated water can quickly penetrate through the buffer layer and then enter the concrete layer, and compared with a traditional artificial turf, the drainage efficiency is greatly improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of artificial turf, in particular to an artificial turf for a waterlogging-proof gateball court and a construction method thereof. Background Art

[0002] Artificial turf is a simulated lawn made of non-living plastic chemical fiber products through artificial methods. After searching, Chinese patent publication number CN108914746A discloses a new method for constructing artificial turf sports fields. Although the technical solution adopts a turtleback drainage structure with a high center and low surroundings, it has the disadvantage of poor drainage. It can cope with light rain, but in heavy rain, rainwater cannot be discharged in time and water accumulation still occurs.

[0003] A search revealed that Chinese patent publication number CN217174253U discloses an artificial turf. Although the adhesive layer used in this artificial turf is primarily made of styrene-butadiene latex or polyurethane adhesive with or without colorant, and contains no additives such as calcium powder, the artificial turf does not generate dust pollution during installation. However, the performance of the artificial grass tufts in this artificial turf is poor. Over time, the tufts are prone to fading, shedding, and breaking, shortening the service life of the artificial turf and increasing its cost. Furthermore, due to material limitations, the artificial turf generates static electricity after extensive friction, which can easily cause static burns to participants and affect their safety. Summary of the Invention

[0004] In response to the deficiencies of the prior art, the present invention provides an artificial turf for a waterlogging-proof gateball court and a construction method, which solves the problem raised in the background art that the existing turf cannot drain rainwater in time during heavy rain, and water still accumulates, and is prone to fading, shedding, and breaking. In addition, due to material limitations, it will generate static electricity after a large amount of friction, which can easily cause static burns to participants and affect the safety of the activities.

[0005] To achieve the above objectives, the present invention is implemented through the following technical solutions: an artificial turf for a waterlogging-proof gateball court and a construction method, comprising a plain soil layer, a drainage layer, a concrete layer, a buffer layer and a quartz sand layer, the upper surface of the plain soil layer is paved with a drainage layer, the upper surface of the drainage layer is paved with a first geotextile, the upper surface of the first geotextile is paved with a gravel layer, the upper surface of the gravel layer is provided with a concrete layer, the upper surface of the concrete layer is paved with a buffer layer, the surface of the buffer layer is paved with a second geotextile, the upper surface of the second geotextile is paved with a quartz sand layer, the upper surface of the quartz sand layer is sprinkled with filling particles, and the surface of the quartz sand is provided with an artificial turf.

[0006] Preferably, the buffer layer is made of modified rubber material, and a plurality of strip-shaped grooves are provided on the top surface of the buffer layer, and the cross-section of the grooves is U-shaped. The grooves on the surface of the buffer layer are arranged in a straight line with equal intervals, and through holes are provided at equal intervals at the bottom of the grooves on the surface of the buffer layer. By providing grooves on the surface of the buffer layer, it is beneficial to improve the fluidity of accumulated water inside the buffer layer, and accelerate the speed at which accumulated water on the ground penetrates downward, so that the accumulated water can quickly pass through the buffer layer and then enter the concrete layer.

[0007] Preferably, through holes are opened on the surface of the concrete layer, and the surface of the concrete layer has a honeycomb structure, and the interior of the concrete honeycomb structure is filled with ceramsite, the bottom of the concrete layer is fixedly connected to the top of the gravel layer by an adhesive, and the gravel layer is made of river sand and gravel laid evenly, and the ceramsite filled inside the concrete layer is conducive to rapid absorption of water flow, and when the ceramsite is saturated with water, the excess water can be quickly discharged into the sewer through the grooves of the drainage layer, and the ceramsite is conducive to filtering impurities in the accumulated water.

[0008] Preferably, drainage ditches are provided on the top surface of the drainage layer in a straight line and at equal intervals, and both sides of the drainage ditch on the top of the drainage layer are sloped, and both ends of the drainage ditch are connected to the sewer channel, and a positioning rod is provided on the top surface of the drainage layer, and one end of the top of the positioning rod passes through the first geotextile, and the connection between the two ends of the drainage ditch and the sewer channel is conducive to the rapid discharge of accumulated water.

[0009] Preferably, the steps are as follows:

[0010] S1: Observe the artificial turf paving surface for protrusions, holes and foreign objects, repair and level the protrusions and holes in time, clean up foreign objects on the paved surface, keep the surface clean, excavate 20 cm of natural base soil, sieve out gravel larger than 1 cm, then backfill and tamp to a density of 80-95%. Spray alcohol continuously during the tamping process. The humidity is 8-10%. Use a flat-bottomed electric vibrating tamper to tamp;

[0011] S2: Laying prefabricated water channel cement parts: Lay multiple prefabricated water channel cement parts of the drainage layer on the foundation, with no gaps between adjacent prefabricated water channel cement parts. After laying, assemble the multiple prefabricated water channel cement parts into a base, distribute multiple water channels on the base, and lay the first geotextile, making the first geotextile taut, and pass the positioning rod through the first geotextile to prevent the first geotextile from slipping;

[0012] S3: Spreading gravel: Spread gravel with a particle size of 10-30 mm on the surface of the rammed soil layer, and then continue to spread medium-fine sand with a particle size of 0.1-1 mm on the surface of the gravel;

[0013] S4: pouring anti-seepage concrete, mixing the concrete evenly, spreading it manually, inserting it into a hexagonal mold, and vibrating it with a vibrating rod, a flat vibrator or a fresh vibration beam. After rolling it with a steel roller and then smoothing it with a stainless steel ruler, a honeycomb surface is formed. After the initial setting of the concrete, it is watered and cured for 7 to 10 days, and the natural curing time is 20 to 28 days. After the concrete layer 5 is formed, ceramsite is filled into the honeycomb pores;

[0014] S5: Lay the buffer layer, fix the bottom of the buffer layer to the upper surface of the concrete by bonding, and apply glue on the surface of the buffer layer to fix the second geotextile, so that the surface of the second geotextile is laid flat;

[0015] S6: Laying artificial turf, unpack the turf rolls and spread them out along the long side of the field according to the construction drawing. Place them under sunlight. According to the layout drawing, align the joints of each two pieces of artificial turf. The joint gap should be controlled within 3mm. There should be no wrinkles, overlaps or convex platforms.

[0016] S7: Lay quartz sand until the sand reaches the designed elevation on a large scale, check whether there is any leakage in the local area and replenish sand in time;

[0017] S8: Lay the filling particles, first lay them in one direction at a uniform speed, and repeatedly repair them twice in this direction, then lay the filling particles in the vertical direction and comb them, repeat this 2 to 3 times until the filling particles 9 can be evenly laid to the designed elevation.

[0018] Preferably, the artificial turf is composed of the following ingredients in parts by weight: 100 parts of resin, 10 parts of masterbatch, 16 parts of bamboo fiber, 3 parts of silane coupling agent, 6 parts of dispersant, 3 parts of fixing agent, 2 parts of surfactant, 5 parts of flame retardant, 2 parts of hydrophilic modifier, 1 part of antioxidant, and 1 part of ultraviolet absorber.

[0019] Preferably, the quartz sand laying method in S7 is as follows:

[0020] a. Fill the hand-pushed sand covering machine with medium and fine sand and shake it. Pull a straight line from east to west on the lawn layer. When the sand covering machine moves, use the pull line as the center line and fill the medium and fine sand in a single pass to a thickness of 3 to 5 mm.

[0021] b. The second pass is to adjust the direction of the lawn to a straight line in the north-south direction and fill it with medium-fine sand to a thickness of 3-5mm. Then use the triangular plastic grass combing board to repeatedly comb the grass until the grass in the lawn layer is completely upright.

[0022] c. However, the third time, the grass is filled with fine sand in a single east-west direction with a thickness of 3 to 5 mm, and the total thickness of the sand is guaranteed to be 9 to 15 mm. The grass fibers of the vertical lawn layer are brushed again;

[0023] d. Repeat steps b and c. When filling for the seventh time, the filling of medium and fine sand is completed.

[0024] Preferably, the filling particles in S7 are any one or more of polyethylene, polypropylene, polyvinyl chloride and polyamide.

[0025] Preferably, the step S6 further comprises laying a seam cloth under the joint and applying bonding glue on the seam cloth. At the same time, the two adjacent artificial turfs are sewn together and the seam is bonded to the seam cloth with the bonding glue.

[0026] The present invention provides an artificial turf for a waterlogging-proof gateball court and a construction method thereof. It has the following beneficial effects:

[0027] (1) The artificial turf and construction method for the gateball court for preventing water accumulation are as follows: when it rains heavily, the water on the ground will penetrate through the surface of the turf into the grooves on the top surface of the buffer layer. The grooves on the surface of the buffer layer are provided to improve the fluidity of the water inside the buffer layer and accelerate the speed of the water on the ground penetrating downward, so that the water can quickly pass through the buffer layer and then enter the concrete layer. The honeycomb structure of the concrete is conducive to improving the speed of water penetration, which has a faster water permeability than traditional permeable concrete. The expanded clay filled in the concrete layer is conducive to rapid absorption of water. When the expanded clay is saturated with water, the excess water can be quickly discharged into the sewer through the grooves of the drainage layer. The expanded clay is conducive to filtering impurities in the water, thereby avoiding clogging the drainage channel of the drainage layer. Compared with traditional artificial turf, the drainage efficiency is greatly improved.

[0028] (2) The artificial turf and construction method for the gateball court for preventing water accumulation have a porous structure of a clay layer in the expanded clay, which is conducive to storing the water accumulated on the ground inside the clay layer and storing water on rainy days. After the temperature of the artificial turf rises, the water stored in the clay layer absorbs heat and evaporates, thereby reducing the temperature of the artificial turf. At the same time, the evaporated water vapor can moisten the artificial turf and reduce the generation of static electricity. At the same time, the artificial turf is prepared by rationally using raw materials, so that the color fixing performance, anti-stripping performance and anti-fracture performance of the artificial turf are significantly improved, thereby greatly improving the quality of the artificial turf, thereby extending the service life of the artificial turf and reducing the cost of use.

[0029] This solves the problem that the existing lawn cannot drain rainwater in time during heavy rain, and water still accumulates. It is also prone to fading, shedding, and breaking. In addition, due to material limitations, it will generate static electricity after a lot of friction, which can easily cause static burns to participants and affect the safety of the activities. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] Figure 1 It is a schematic diagram of the overall structure of the present invention;

[0031] Figure 2Schematic diagram of the buffer layer structure of the present invention;

[0032] Figure 3 Schematic diagram of the concrete structure of the present invention;

[0033] Figure 4 This is a schematic diagram of the drainage layer structure of the present invention;

[0034] Figure 5 It is a schematic diagram of the process of the present invention.

[0035] In the figure, 1. Soil layer; 2. Drainage layer; 3. First geotextile; 4. Gravel layer; 5. Concrete layer; 6. Buffer layer; 7. Second geotextile; 8. Quartz sand layer; 9. Filling particles; 10. Artificial turf; 11. Positioning rod. DETAILED DESCRIPTION

[0036] The following will provide a clear and complete description of the technical solutions in the embodiments of the present invention in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. All other embodiments obtained by ordinary technicians in this field based on the embodiments of the present invention without making any creative efforts shall fall within the scope of protection of the present invention.

[0037] Example 1:

[0038] An artificial turf for a waterlogging-proof gateball court and a construction method thereof, comprising a plain soil layer 1, a drainage layer 2, a concrete layer 5, a buffer layer 6, and a quartz sand layer 8. The plain soil layer 1 is paved with a drainage layer 2, the drainage layer 2 is paved with a first geotextile 3, the first geotextile 3 is paved with a crushed stone layer 4, the crushed stone layer 4 is paved with a concrete layer 5, the concrete layer 5 is paved with a buffer layer 6, the buffer layer 6 is paved with a second geotextile 7, the second geotextile 7 is paved with a quartz sand layer 8, the quartz sand layer 8 is sprinkled with filling particles 9, an artificial turf 10 is provided on the quartz sand surface, the buffer layer 6 is made of modified rubber, and the top surface of the buffer layer 6 is provided with a modified rubber layer. There are multiple strip-shaped grooves, and the cross-section of the grooves is U-shaped. The grooves on the surface of the buffer layer 6 are arranged in a straight line with equal intervals, and through holes are opened at equal intervals on the bottom of the grooves on the surface of the buffer layer 6. When it rains heavily, the accumulated water on the ground will penetrate through the lawn surface into the grooves on the top surface of the buffer layer 6. By opening grooves on the surface of the buffer layer 6, it is beneficial to improve the fluidity of the accumulated water inside the buffer layer 6 and accelerate the speed of the ground water infiltration downward, so that the accumulated water can quickly pass through the buffer layer 6 and then enter the concrete layer 5. The honeycomb structure of the concrete is beneficial to improve the penetration speed of the water flow, and has a faster water permeability than traditional permeable concrete.

[0039] Example 2:

[0040] The surface of the concrete layer 5 is provided with through holes, and the surface of the concrete layer 5 is a honeycomb structure, and the interior of the concrete honeycomb structure is filled with ceramsite. The bottom of the concrete layer 5 is fixedly connected to the top of the gravel layer 4 by an adhesive. The gravel layer 4 is made of river sand and gravel laid evenly. The top surface of the drainage layer 2 is provided with drainage ditches in a straight line and at equal intervals, and the two sides of the drainage ditch on the top of the drainage layer 2 are sloped structures, and the two ends of the drainage ditch are connected to the sewer channel, and a positioning rod 11 is provided on the top surface of the drainage layer 2. One end of the top of the positioning rod 11 passes through the first geotextile 3. The ceramsite filled inside the concrete layer 5 is conducive to rapid absorption of water flow. When the ceramsite is saturated with water, the excess water can be quickly discharged into the sewer through the grooves of the drainage layer 2. The ceramsite is conducive to filtering impurities in the accumulated water, thereby avoiding clogging the drainage channel of the drainage layer 2, which greatly improves the drainage efficiency compared with the traditional artificial turf 10.

[0041] Example 3:

[0042] An artificial turf for a waterlogging-proof gateball court and a construction method thereof, the steps of which are as follows:

[0043] S1: Observe whether there are protrusions, holes and foreign objects on the artificial turf 10 paving ground, repair and level the protrusions and holes on the ground in time, clean up the foreign objects on the paving ground, keep the ground clean, excavate 20 cm of natural base soil, sieve out gravel larger than 1 cm, then backfill and tamp, the tamping density is 80-95%, spray alcohol continuously during the tamping process, the humidity is 10%, and use a flat-bottom electric vibration tamping machine to tamp; S2: Lay the prefabricated cement parts of the water channel: put more than 2 layers of drainage layer The prefabricated cement water channel components are laid on the foundation, leaving no gaps between adjacent prefabricated water channel components. After completion, multiple prefabricated water channel components are assembled into a base, on which multiple water channels are distributed. The first geotextile 3 is then laid, tightened, and positioning rods 11 are passed through the first geotextile 3 to prevent it from slipping. S3: Spreading gravel: Gravel with a particle size of 10 to 30 mm is spread on the surface of the rammed soil layer. Gravel with a particle size of 0.1-1mm medium-fine sand; S4: pouring anti-seepage concrete, mixing the concrete evenly, spreading it manually, and inserting it into a hexagonal mold. Vibrating it with a vibrating rod, flat vibrator or fresh vibration beam, rolling it with a steel roller and then scraping it with a stainless steel ruler to form a honeycomb surface. After the concrete is initially set, it is watered and cured for 7 to 10 days, and the natural curing time is 20 to 28 days. After the concrete layer 5 is formed, ceramsite is filled into the honeycomb pores; S5: laying the buffer layer 6, and bonding the bottom of the buffer layer 6 to the upper surface of the concrete by bonding. Fix, and apply glue on the surface of the buffer layer 6 to fix the second geotextile 7, so that the surface of the second geotextile 7 is laid flat; S6: Lay artificial turf, unpack the grass roll and spread it out along the long side of the site according to the construction drawing, and under the sunlight; according to the layout drawing, align the joints of each two artificial turfs, and control the joint gap to be less than 3mm, without wrinkles, overlaps, and convex platforms; S7: Lay quartz sand until the sand is spread over a large area to the design elevation, check whether there is any leakage in the local area and replenish the sand in time; S8: Lay filling particles 9, first at a uniform speed in one direction Lay, and repair it repeatedly twice in this direction, then lay rubber filling particles 9 in the vertical direction and comb, repeat this 2 to 3 times, until the filling particles 9 can be evenly laid to the designed elevation; the artificial turf 10 is composed of the following components by weight: 100 parts of resin, 10 parts of masterbatch, 16 parts of bamboo fiber, 3 parts of silane coupling agent, 6 parts of dispersant, 3 parts of color fixing agent, 2 parts of surfactant, 5 parts of flame retardant, 2 parts of hydrophilic modifier, 1 part of antioxidant, 1 part of ultraviolet absorber, the porous structure of the clay layer in the ceramsite is conducive to making the water on the ground Water can be stored within the clay layer, allowing it to accumulate during rainy days. Later, when the temperature of the artificial turf rises, the water stored within the clay layer absorbs heat and evaporates, thereby reducing the temperature of the artificial turf. The evaporated water vapor also moistens the artificial turf, reducing the generation of static electricity. Furthermore, by rationally using raw materials to produce the artificial turf 10, the color retention, anti-threading, and anti-fracture properties of the artificial turf 10 are significantly improved, greatly enhancing the quality of the artificial turf 10, thereby extending its service life and reducing its operating costs.

[0044] Example 3:

[0045] The quartz sand laying method is as follows:

[0046] a. Fill the lawn with medium-fine sand and shake it with a hand-pushed sand covering machine. First, draw a straight line from east to west on the lawn layer. When the sand covering machine moves, use the pulling line as the center line and fill the lawn with 5mm thick medium-fine sand in a single pass; b. For the second pass, adjust the direction to draw a straight line from north to south and fill the lawn with 5mm thick medium-fine sand in a single pass. Then use the triangular plastic grass combing board to repeatedly comb the grass fibers until the grass fibers of the lawn layer are completely upright; c. However, for the third pass, change the direction to east to west and fill the lawn with 5mm thick medium-fine sand in a single pass. The total thickness of the sand covering is guaranteed to be 15mm, and the grass fibers of the lawn layer are brushed upright again; d. Repeat steps b and c. When the seventh pass is completed, the filling of medium-fine sand is completed.

[0047] The components of the present invention, including 1. a plain soil layer; 2. a drainage layer; 3. a first geotextile; 4. a crushed stone layer; 5. a concrete layer; 6. a buffer layer; 7. a second geotextile; 8. a quartz sand layer; 9. filling particles; 10. an artificial turf; and 11. a positioning rod, are all universal standard parts or parts known to those skilled in the art, and their structures and principles can be known to those skilled in the art through technical manuals or conventional experimental methods.

[0048] The above shows and describes the basic principles and main features of the present invention and the advantages of the present invention. It is obvious to those skilled in the art that the present invention is not limited to the details of the above exemplary embodiments, and that the present invention can be implemented in other specific forms without departing from the spirit or essential characteristics of the present invention. Therefore, from all points of view, the embodiments should be regarded as illustrative and non-restrictive. The scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes that fall within the meaning and range of equivalents of the claims are included in the present invention. Any reference signs in the claims should not be construed as limiting the claim to which they relate.

[0049] In addition, it should be understood that although this specification is described in terms of implementation methods, not every implementation method contains only one independent technical solution. This narrative method of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment can also be appropriately combined to form other implementation methods that can be understood by those skilled in the art.

Claims

1. An artificial turf for a waterlogging-proof gateball court, characterized in that: The invention comprises a plain soil layer (1), a drainage layer (2), a concrete layer (5), a buffer layer (6) and a quartz sand layer (8); the plain soil layer (1) is provided with a drainage layer (2); the drainage layer (2) is provided with a first geotextile (3) on the upper surface; the first geotextile (3) is provided with a crushed stone layer (4) on the upper surface; the crushed stone layer (4) is provided with a concrete layer (5); the concrete layer (5) is provided with a buffer layer (6) on the upper surface; the buffer layer (6) is provided with a second geotextile (7); the second geotextile (7) is provided with a quartz sand layer (8) on the upper surface; the quartz sand layer (8) is provided with filling particles (9) on the upper surface; and an artificial lawn (10) is provided on the surface of the quartz sand.

2. The artificial turf for anti-waterlogging gateball court according to claim 1, characterized in that: The buffer layer (6) is made of modified rubber material, and a plurality of strip-shaped grooves are provided on the top surface of the buffer layer (6), and the cross-section of the grooves is arranged in a U shape. The grooves on the surface of the buffer layer (6) are arranged in a straight line at equal intervals, and through holes are provided at equal intervals at the bottom of the grooves on the surface of the buffer layer (6).

3. The artificial turf for anti-waterlogging gateball court according to claim 1, characterized in that: The surface of the concrete layer (5) is provided with through holes, and the surface of the concrete layer (5) presents a honeycomb structure, and the interior of the concrete honeycomb structure is filled with ceramsite, the bottom of the concrete layer (5) is fixedly connected to the top of the gravel layer (4) by an adhesive, and the gravel layer (4) is formed by evenly paving river sand and gravel.

4. The artificial turf for anti-waterlogging gateball court according to claim 1, characterized in that: The top surface of the drainage layer (2) is provided with drainage ditches at equal intervals in a straight line, and both sides of the drainage ditches on the top of the drainage layer (2) are sloped structures, and both ends of the drainage ditches are connected to the sewer channel. A positioning rod (11) is provided on the top surface of the drainage layer (2), and one end of the top of the positioning rod (11) penetrates the first geotextile (3).

5. A method for constructing an artificial turf for a waterlogging-proof gateball court according to any one of claims 1 to 4, characterized in that: The steps are as follows: S1: Laying the base layer, observing whether there are protrusions, holes and foreign objects on the artificial turf (10) paving ground, promptly repairing and leveling the protrusions and holes on the ground, cleaning the foreign objects on the paved ground, keeping the ground clean, excavating 20 cm of natural base soil, screening out gravel larger than 1 cm, then backfilling and compacting, the compaction density is 80-95%, spraying water continuously during the compaction process, the humidity is 8-10%, and compacting is carried out using a flat-bottomed electric vibration compactor; S2: Laying prefabricated cement parts of water guide grooves: laying a plurality of prefabricated cement parts of water guide grooves of the drainage layer (2) on the foundation, with no gap between adjacent prefabricated cement parts of water guide grooves. After the laying is completed, the plurality of prefabricated cement parts of water guide grooves are assembled into a base, a plurality of water guide grooves are distributed on the base, and a first geotextile (3) is laid, the first geotextile (3) is tightened, and a positioning rod (11) is passed through the first geotextile (3) to prevent the first geotextile (3) from slipping; S3: Spreading gravel: Spread gravel with a particle size of 10 to 30 mm on the surface of the compacted soil layer, and continue to spread medium and fine sand with a particle size of 0.1 to 1 mm on the surface of the gravel; S4: pouring impermeable concrete, mixing the concrete evenly, spreading it manually, inserting it into a hexagonal mold, tamping it with a vibrating rod, a flat vibrator or a fresh vibration beam, rolling it with a steel roller and then scraping it with a stainless steel ruler to form a honeycomb surface. After the concrete is initially set for 8 to 12 hours, it is watered and cured for 7 to 10 days, and the natural curing time is 20 to 28 days. After the concrete layer (5) is formed, ceramsite is filled into the honeycomb holes; S5: laying a buffer layer (6), fixing the bottom of the buffer layer (6) to the upper surface of the concrete by bonding, and applying glue on the surface of the buffer layer (6) for fixing the second geotextile (7), so that the surface of the second geotextile (7) is laid flat; S6: Laying artificial turf, unpack the turf rolls and spread them out along the long side of the field according to the construction drawing, and place them under the sun; align the joints of every two pieces of artificial turf according to the layout drawing, and control the joint gap within 3mm, without wrinkles, overlaps, or convex platforms; S7: Lay quartz sand until the sand is laid over a large area to the designed elevation, check whether there are any gaps in the sand and replenish the sand in time; S8: Lay the filling particles 9, first at a uniform speed in one direction, and repeatedly repair it twice in this direction, then lay the filling particles (9) in the vertical direction and comb it, repeat this 2 to 3 times until the filling particles 9 can be evenly laid to the designed elevation.

6. The method for constructing an artificial turf for a waterlogging-proof gateball court according to claim 5, characterized in that: The artificial turf (10) is composed of the following components in parts by weight: 100 parts of resin, 10 parts of masterbatch, 16 parts of bamboo fiber, 3 parts of silane coupling agent, 6 parts of dispersant, 3 parts of color fixing agent, 2 parts of surfactant, 5 parts of flame retardant, 2 parts of hydrophilic modifier, 1 part of antioxidant, and 1 part of ultraviolet absorber.

7. The method for constructing an artificial turf for a waterlogging-proof gateball court according to claim 5, characterized in that: The quartz sand laying method in S7 is as follows: a. Fill the hand-pushed sand covering machine with medium and fine sand and shake it. Pull a straight line from east to west on the lawn layer. When the sand covering machine is moving, use the pull line as the center line and fill the medium and fine sand with a thickness of 3 to 5 mm in a single pass; b. The second time, adjust the direction of the lawn to be straight and fill it with medium-fine sand with a thickness of 3 to 5 mm. Then use the triangular plastic grass combing board to comb the grass repeatedly until the grass in the lawn layer is completely upright. c. However, the third time, the grass is filled with medium-fine sand in a single pass in the east-west direction with a thickness of 3 to 5 mm, and the total thickness of the sand is guaranteed to be 9 to 15 mm, and the grass fibers of the lawn layer are brushed again; d. Repeat steps b and c. When filling for the seventh time, the filling of medium and fine sand is completed.

8. The method for constructing an artificial turf for a waterlogging-proof gateball court according to claim 5, characterized in that: The filling particles (9) in S7 are any one or more of polyethylene, polypropylene, polyvinyl chloride and polyamide.

9. The method for constructing an artificial turf for a waterlogging-proof gateball court according to claim 5, characterized in that: The step S6 also includes laying an overlap cloth under the joint and applying bonding glue on the overlap cloth. At the same time, two adjacent pieces of artificial turf are sewn together and the joint is bonded to the overlap cloth with the bonding glue.

Citation Information

Patent Citations

  • Construction method of novel artificial turf sports field

    CN108914746A

  • Artificial turf

    CN217174253U

Cited By

  • Bio-based thermoplastic prefabricated buffer layer and preparation method and application thereof

    CN119391168A