A train screening method, system, device and storage medium of a TACS system

By adopting automatic and manual train screening methods in the TACS system, combined with the railside resource manager and train controller, the problem of difficulty in detecting train occupation in the TACS system is solved, reducing the dependence of secondary detection equipment, and improving screening efficiency and system flexibility.

CN116039734BActive Publication Date: 2024-12-10CASCO SIGNAL LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202211603707.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-12-13
Publication Date
2024-12-10
Estimated Expiration
2042-12-13

AI Technical Summary

Technical Problem

The TACS system lacks an effective way to safely and reliably understand the occupancy of trains on line sections, which leads to difficulty in train screening, and reliance on traditional secondary testing equipment leads to high installation and maintenance costs and low efficiency.

Method used

Using automatic train screening and manual train screening, train occupation status is initialized and monitored through the railside resource manager (WRC), combined with train controller (xTC) and automatic monitoring system (ATS), and automatically screened, and when needed, it is Local operators confirm that the dependence on secondary inspection equipment is reduced.

Benefits of technology

Realize train screening without relying on traditional secondary detection equipment, reduces the number of system equipment and maintenance costs, improves screening efficiency and flexibility, ensures the diversity and ease of operation of train screening, and enhances the rapid system failure recovery ability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116039734B_ABST
    Figure CN116039734B_ABST
Patent Text Reader

Abstract

The present invention relates to a train screening method, system, device and storage medium of a TACS system. The method realizes the confirmation of the train occupancy status of a line section by automatic train screening and manual train screening. For the main line section, automatic train screening is performed by a communication train, and for the non-main line section, manual train screening is performed by a local operator button confirmation plus central dispatch authorization. Compared with the prior art, the present invention has the advantages of greatly reducing the number of trackside equipment, construction cost and maintenance workload of the system, shortening the cycle of old line reconstruction and new line construction, and improving the competitiveness and flexibility of the system.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to a train signal control system, and in particular to a train screening method, system, equipment and storage medium of a TACS system. Background Art

[0002] Compared with the traditional CBTC system, the Train Autonomous Operation System (TACS system) based on vehicle-to-vehicle communication is "train-centric" and the train autonomously calculates mobile authorization. The essence of the TACS system is to transplant the trackside core control functions of the traditional CBTC system to the train, optimize the system architecture, and at the same time reduce the number of trackside equipment, significantly reducing the workload of equipment maintenance.

[0003] However, since the TACS system does not use traditional secondary detection equipment for train occupancy detection, the TACS system lacks an effective way to safely and reliably obtain the occupancy status of trains on the line section. Therefore, in the TACS system, how to screen trains on the line is a huge challenge.

[0004] In the traditional CBTC system, the screening of downgraded trains or non-communication trains depends largely on the detection of track occupancy. The main means of track occupancy detection include track circuits and axle counting based on electromagnetic induction technology. However, the installation process of such secondary detection equipment is complicated, requiring the layout of a large number of cables, and the construction and maintenance costs are high. In addition, the secondary detection equipment may fail to complete the correct screening due to its own failure.

[0005] After searching, Chinese patent publication number CN114454923A discloses a train screening method and system based on autonomous operation control mode, the method includes the following steps: the on-board equipment of the current train obtains the axle counter status information from the turnout controller; the on-board equipment of the current train obtains the location information of other trains from the on-board equipment of other trains and the turnout controller; the on-board equipment of the current train completes the screening of the current train in combination with the axle counter status information and the location information of other trains. Aiming at the problem that the current urban rail transit train screening and judgment function involves many equipment links and the information transmission and judgment speed is slow, resulting in the problem that the efficiency of mobile block tracking after the train is screened is reduced, by redistributing the functions, realizing the combination of multiple mechanisms, reducing communication transmission, improving the autonomous judgment and control capabilities of the on-board equipment, and can also be used for the train autonomous operation control mode. However, the existing patents still rely on axle counter equipment for train screening. Therefore, in the TACS system, how to design a train screening technology that does not rely on traditional secondary detection equipment has become a technical problem that needs to be solved. Summary of the invention

[0006] The purpose of the present invention is to overcome the defects of the above-mentioned prior art and to provide a train screening method, system, device and storage medium for a TACS system.

[0007] The purpose of the present invention can be achieved by the following technical solutions:

[0008] According to the first aspect of the present invention, a train screening method for a TACS system is provided, which realizes the confirmation of the train occupancy status of a line section by automatic train screening and manual train screening. For the mainline section, automatic train screening is performed by a communication train, and for the non-mainline section, manual train screening is performed by a local operator button confirmation plus central dispatch authorization.

[0009] As a preferred technical solution, the non-mainline section includes a crossover line, a storage line or a vehicle depot area.

[0010] As a preferred technical solution, the method specifically comprises the following steps:

[0011] Step S101, after the trackside resource manager WRC is powered on or restarted, the WRC is powered on and unlocked through a WRC initialization command;

[0012] Step S102, WRC determines the train occupancy status of the entire line section. If there is no unknown train occupancy status in the line section, it is considered that the line screening is successful, otherwise, step S103 is executed;

[0013] Step S103, perform automatic train screening, and execute step S104;

[0014] Step S104, after the automatic train screening of the line is completed, it is determined whether there is still an unknown train occupying the section, if yes, step S105 is executed; otherwise, it is considered that the line screening is successful;

[0015] Step S105, performing manual train screening.

[0016] As a preferred technical solution, the power-on unlocking of the WRC in step S101 is used to ensure the normal operation of the WRC, to perform normal intrusion detection, and to monitor the situation of trains illegally entering the signal area during line section screening.

[0017] As a preferred technical solution, the WRC in step S102 sends the train occupancy status of the entire line section to the ATS for display.

[0018] As a preferred technical solution, the specific process of automatic train screening in step S103 is as follows:

[0019] Step S1031, WRC calculates whether there is unknown train occupation on the line and provides unknown train occupation information to ATS;

[0020] Step S1032, ATS displays the line section information occupied by unknown trains to the dispatch terminal;

[0021] Step S1033, the dispatching terminal decides to send the train screening operation task to the train controller xTC according to the displayed occupancy information;

[0022] Step S1034, ATS sends the screened running task to xTC;

[0023] Step S1035, xTC applies for line resources according to the received task;

[0024] Step S1036, WRC allocates line resources to xTC;

[0025] Step S1037, xTC calculates the mobile authorization operation path and sends it to ATS;

[0026] Step S1038, the ATS displays the running path resource information to the dispatch terminal;

[0027] Step S1039, the dispatching terminal authorizes the driver to manually drive the train according to the resources applied for by the train and performs line section screening;

[0028] Step S10310, the driver manually drives the train according to the dispatching instruction;

[0029] Step S10311, the xTC provides location information to the WRC in real time according to its own location;

[0030] Step S10312, WRC screens the line section according to the location information provided by xTC;

[0031] Step S10313, ATS confirms whether the line section has completed the screening process based on the screening results.

[0032] As a preferred technical solution, in the step S10312, when the automatic screening conditions of the section or automatic screening area through which the train physically passes are met, it is considered that there is no unknown train occupying the corresponding section.

[0033] As a preferred technical solution, the specific process of manual train screening in step S105 is as follows:

[0034] Step S1051, WRC calculates whether there is unknown train occupation on the line and provides unknown train occupation information to ATS;

[0035] Step S1052, ATS displays the line section information occupied by unknown trains to the dispatch terminal;

[0036] Step S1053, the dispatch terminal authorizes and notifies the local operator to manually confirm whether there is an unknown train in the line section according to the displayed occupancy information;

[0037] Step S1054, when the local operator confirms that there is no unknown train occupying the manual screening area and no unknown train entering, he presses the trackside confirmation button;

[0038] Step S1055, OC collects the filter button information and sends it to WRC;

[0039] Step S1056, after the WRC collects the manual screening button, it sends confirmation information of providing the manual screening area to the ATS;

[0040] Step S1057, the ATS prompts the dispatch terminal to perform manual screening and confirmation on the interface;

[0041] Step S1058, the dispatch terminal confirms on the ATS interface;

[0042] Step S1059, ATS sends scheduling confirmation information to WRC;

[0043] Step S10510, WRC completes the screening process of the manual screening area;

[0044] Step S10511, ATS displays a successful screening message;

[0045] Step S10512, the dispatch terminal confirms that the screening is successfully completed.

[0046] As a preferred technical solution, when the length of the crossover does not meet the requirements for configuration as an automatic screening area, the corresponding turnout section is configured as a manual screening area, and manual confirmation is performed to determine whether there is an unknown train in the section.

[0047] According to a second aspect of the present invention, a system for the train screening method of the TACS system is provided, the system comprising a trackside resource manager WRC, a train controller xTC, a target controller OC, an automatic train monitoring system ATS, an intelligent operation and maintenance system IOM, a train intrusion detection system TID and a screening button CZB;

[0048] The trackside resource manager WRC is respectively communicated with the train controller xTC, the target controller OC, the train automatic monitoring system ATS, and the intelligent operation and maintenance system IOM; the target controller OC is respectively communicated with the train intrusion detection system TID and the screening button CZB; and the train automatic monitoring system ATS is communicated with the train controller xTC.

[0049] As a preferred technical solution, the ATS sends the line screening operation task to the train controller xTC according to the needs of train screening, and the train controller xTC applies for resources from the trackside resource manager WRC; the WRC transmits the line section occupancy display to the ATS, and the ATS sends the scheduling manual screening command to the WRC.

[0050] As a preferred technical solution, the local operator confirms whether the section exists in the unknown train by pressing the screening button CZB and sends it to the target controller OC; the OC sends the button information to the WRC.

[0051] As a preferred technical solution, the train intrusion detection system TID detects whether there is a train illegally intruding into the signal area.

[0052] As a preferred technical solution, the intelligent operation and maintenance system IOM displays the working status of the TACS equipment.

[0053] According to a third aspect of the present invention, there is provided an electronic device, comprising a memory and a processor, wherein a computer program is stored in the memory, and the method described above is implemented when the processor executes the program.

[0054] According to a fourth aspect of the present invention, there is provided a computer-readable storage medium having a computer program stored thereon, wherein the program implements the method described when executed by a processor.

[0055] Compared with the prior art, the present invention has the following advantages:

[0056] 1) The present invention completes the screening of the entire line section through automatic screening by communication trains and manual confirmation without the need to arrange secondary detection equipment such as axle counters or track circuits, thus getting rid of the dependence on traditional secondary detection equipment, greatly reducing the number of trackside equipment in the system, construction costs and maintenance workload, shortening the cycle of old line reconstruction and new line construction, and improving the competitiveness and flexibility of the system.

[0057] 2) The present invention includes two methods: automatic train screening and manual screening. For the main line, the communication train is used to perform rapid automatic screening. For special sections such as complex crossing lines, storage lines or vehicle depots, the local operator button confirmation + central dispatch authorization method can be used to perform rapid train screening. Through the complementarity of the two methods, the train screening function of all sections of the line can be conveniently completed, ensuring the diversity of train screening methods and ease of operation of the TACS system;

[0058] 3) The present invention designs a set of train illegal intrusion detection system to ensure that when WRC is working normally, if a train illegally intrudes into the signal area, it can be detected by the system, so as to know whether there is an unknown train intruding on the line; when it is confirmed that there is no illegal train intruding on the line, when the train is restarted or the line section blockade is cancelled, when the train resumes its position, the system can automatically complete the train screening according to the position information of the trains on all lines, without the need for manual screening operations, thereby ensuring the train screening efficiency of the TACS system and enabling the TACS system to have a fast fault recovery capability. BRIEF DESCRIPTION OF THE DRAWINGS

[0059] Figure 1 This is a structural diagram of the TACS system used for train screening;

[0060] Figure 2 Schematic diagram of the workflow of the TACS system train screening method;

[0061] Figure 3-1 This is a schematic diagram of the layout of the automatic screening area of ​​the TACS system;

[0062] Figure 3-2 This is a schematic diagram of the layout of the automatic screening area of ​​the TACS system;

[0063] Figure 3-3 This is a schematic diagram of the layout of the automatic screening area of ​​the TACS system;

[0064] Figure 4 This is the layout of the manual screening area of ​​the TACS system;

[0065] Figure 5 Schematic diagram of the train screening interface information of the TACS system;

[0066] Figure 6-1 This is a schematic diagram of the automatic train screening workflow of the TACS system;

[0067] Figure 6-2 Schematic diagram of the manual screening workflow for TACS system trains. DETAILED DESCRIPTION

[0068] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.

[0069] The TACS system confirms the train occupancy status of line sections through automatic train screening and manual train screening. When the WRC is powered on successfully, the WRC is powered on and unlocked through the WRC initialization command to ensure that the WRC can work normally and perform normal intrusion detection. During the line section screening, the trains that illegally enter the signal area are monitored; then, according to the line section occupancy status provided by the WRC, it is decided whether to perform automatic train screening operations. After the automatic screening operation is completed, if there are still unknown train occupation sections in some special sections, manual screening operations need to be performed to realize the processing of train screening for all line sections.

[0070] like Figure 2 As shown, the present invention specifically comprises the following steps:

[0071] Step S101, after the trackside resource manager WRC is powered on or restarted, the WRC is powered on and unlocked through a WRC initialization command;

[0072] Step S102, WRC determines the train occupancy status of the entire line section. If there is no unknown train occupancy status in the line section, it is considered that the line screening is successful, otherwise, step S103 is executed;

[0073] Step S103, perform automatic train screening, and execute step S104;

[0074] Step S104, after the automatic train screening of the line is completed, it is determined whether there is still an unknown train occupying the section, if yes, step S105 is executed; otherwise, it is considered that the line screening is successful;

[0075] Step S105, performing manual train screening.

[0076] like Figure 3-1 As shown, for the track section connected to the car block, it can be configured as an automatic screening area. When the distance L between the minimum head of the communication train T1 and the car block is less than the minimum train length of the line, the track section can be automatically screened out; Figure 3-2 As shown, for the signal boundary, if the train illegal intrusion detection equipment is arranged, when the turnout reverse track section is less than the minimum train length of the line, the section can be configured as an automatic screening area. When the communication train T1 passes through the turnout P1, the turnout P1 reverse track section can be automatically screened out; Figure 3-3 As shown, when the length of a single crossover is less than the minimum vehicle length of the line + the length of the side rush zone, the crossover track section can be configured as an automatic screening area. When the communication train T1 passes through the switch P3 and the train T2 passes through the switch P5, the crossover track section can be automatically screened out.

[0077] like Figure 4As shown, when the length of the crossover does not meet the requirements for configuration as an automatic screening area, in order to quickly screen trains in the line section, the turnout section can be configured as a manual screening area, and manual confirmation is performed to determine whether there are unknown trains in the section.

[0078] The schematic diagram of the TACS system train manual screening interface information is as follows Figure 5 As shown, it mainly involves the interfaces among the subsystems such as the trackside resource manager WRC, the train controller xTC, the target controller OC, the automatic train monitoring system ATS, the intelligent operation and maintenance system IOM, the train intrusion detection system TID, and the screening button CZB; when the system is powered on successfully, ATS sends the line screening operation task to the train controller xTC according to the needs of train screening; the train controller xTC applies for resources from the trackside resource manager WRC; WRC transmits the line section occupancy display to ATS, and ATS sends the dispatching manual screening command to WRC; the local operator confirms whether the unknown train exists in the section through the screening button CZB, and sends it to the target controller OC; OC sends the button information to WRC; the train intrusion detection system detects whether there is a train illegally intruding into the signal area; the intelligent operation and maintenance system IOM can display the working status of the TACS equipment; through the information interaction between the subsystems, the TACS system can realize the screening and processing of trains;

[0079] The train screening interface information of the TACS system is shown in Table 1:

[0080] Table 1

[0081] interface Transmitting information ① ATS sends screening operation tasks to the train controller xTC ② xTC applies to WRC for line resources for screening ③ Line section occupancy status sent by WRC to ATS ④ Manual screening authorization command sent by ATS to WRC ⑤ Local operator presses the filter button status information ⑥ Filter button status information ⑦ Train Illegal Intrusion Detection Information ⑧ TACS system equipment operation status information

[0082] The automatic train screening workflow of the TACS system is as follows: Figure 6-1 As shown, the automatic screening workflow is as follows:

[0083] Step S1031, WRC calculates whether there is unknown train occupation on the line and provides unknown train occupation information to ATS;

[0084] Step S1032, ATS displays the line section information occupied by unknown trains to the dispatch terminal;

[0085] Step S1033, the dispatching terminal decides to send the train screening operation task to the train controller xTC according to the displayed occupancy information;

[0086] Step S1034, ATS sends the screened running task to xTC;

[0087] Step S1035, xTC applies for line resources according to the received task;

[0088] Step S1036, WRC allocates line resources to xTC;

[0089] Step S1037, xTC calculates the mobile authorization operation path and sends it to ATS;

[0090] Step S1038, the ATS displays the running path resource information to the dispatch terminal;

[0091] Step S1039, the dispatching terminal authorizes the driver to manually drive the train according to the resources applied for by the train and performs line section screening;

[0092] Step S10310, the driver manually drives the train according to the dispatching instruction;

[0093] Step S10311, the xTC provides location information to the WRC in real time according to its own location;

[0094] Step S10312, WRC screens the line sections according to the location information provided by xTC. When the section through which the train physically passes or the automatic screening area meets the automatic screening conditions, it is considered that there is no unknown train occupying the corresponding section;

[0095] Step S10313, ATS confirms whether the line section has completed the screening process based on the screening results.

[0096] The automatic train screening workflow of the TACS system is as follows: Figure 6-2 As shown, the manual screening workflow is as follows:

[0097] Step S1051, WRC calculates whether there is unknown train occupation on the line and provides unknown train occupation information to ATS;

[0098] Step S1052, ATS displays the line section information occupied by unknown trains to the dispatch terminal;

[0099] Step S1053, the dispatch terminal authorizes and notifies the local operator to manually confirm whether there is an unknown train in the line section according to the displayed occupancy information;

[0100] Step S1054, when the local operator confirms that there is no unknown train occupying the manual screening area and no unknown train entering, he presses the trackside confirmation button;

[0101] Step S1055, OC collects the filter button information and sends it to WRC;

[0102] Step S1056, after the WRC collects the manual screening button, it sends confirmation information of providing the manual screening area to the ATS;

[0103] Step S1057, the ATS prompts the dispatch terminal to perform manual screening and confirmation on the interface;

[0104] Step S1058, the dispatch terminal confirms on the ATS interface;

[0105] Step S1059, ATS sends scheduling confirmation information to WRC;

[0106] Step S10510, WRC completes the screening process of the manual screening area;

[0107] Step S10511, ATS displays a successful screening message;

[0108] Step S10512, the dispatch terminal confirms that the screening is successfully completed.

[0109] The above is an introduction to the method embodiment. The following is a further explanation of the solution of the present invention through a system embodiment.

[0110] like Figure 1 As shown in the figure, the train autonomous operation system (TACS system) based on vehicle-to-vehicle communication mainly includes the trackside resource manager WRC, the trackside train controller WTC, the target controller OC, the train automatic monitoring system ATS, the onboard controller CC, the intelligent operation and maintenance system IOM, and the train intrusion detection system TID. Among them, the train automatic monitoring system ATS subsystem is responsible for supervising and controlling the operation of the train, and has the functions of train tracking operation, alarm and event reporting, operation adjustment, and operation control; the trackside resource manager WRC is responsible for line resource allocation and recovery, train line section occupancy management and other functions; the trackside train controller WTC is mainly responsible for managing and tracking faulty trains, taking over faulty trains to apply for and release resources, and interacting with adjacent trains; the target controller OC mainly realizes the state collection and drive of trackside equipment, including collecting the state of manual screening buttons on the trackside; the onboard controller CC requests and releases line resources according to the plan, actively controls the train, and realizes the train safety protection function and the train automatic driving function; the train intrusion detection system TID is mainly used to detect whether there is a train illegally invading the signal area at the entrance of the TACS signal area; the intelligent operation and maintenance system IOM is mainly responsible for monitoring the working status of the equipment and providing alarms to maintenance personnel;

[0111] Those skilled in the art can clearly understand that, for the convenience and brevity of description, the specific working process of the described module can refer to the corresponding process in the aforementioned method embodiment, and will not be repeated here.

[0112] The electronic device of the present invention includes a central processing unit (CPU), which can perform various appropriate actions and processes according to computer program instructions stored in a read-only memory (ROM) or loaded from a storage unit into a random access memory (RAM). In the RAM, various programs and data required for device operation can also be stored. The CPU, ROM and RAM are connected to each other via a bus. An input / output (I / O) interface is also connected to the bus.

[0113] Multiple components in the device are connected to the I / O interface, including: input units, such as keyboards, mice, etc.; output units, such as various types of displays, speakers, etc.; storage units, such as disks, optical disks, etc.; and communication units, such as network cards, modems, wireless communication transceivers, etc. The communication unit allows the device to exchange information / data with other devices through computer networks such as the Internet and / or various telecommunication networks.

[0114] The processing unit performs the various methods and processes described above, such as methods S101 to S105. For example, in some embodiments, methods S101 to S105 may be implemented as a computer software program, which is tangibly contained in a machine-readable medium, such as a storage unit. In some embodiments, part or all of the computer program may be loaded and / or installed on the device via a ROM and / or a communication unit. When the computer program is loaded into the RAM and executed by the CPU, one or more steps of methods S101 to S105 described above may be performed. Alternatively, in other embodiments, the CPU may be configured to execute methods S101 to S105 in any other appropriate manner (e.g., by means of firmware).

[0115] The functions described above herein may be performed at least in part by one or more hardware logic components. For example, without limitation, exemplary types of hardware logic components that may be used include: field programmable gate arrays (FPGAs), application specific integrated circuits (ASICs), application specific standard products (ASSPs), systems on chips (SOCs), complex programmable logic devices (CPLDs), and the like.

[0116] The program code for implementing the method of the present invention can be written in any combination of one or more programming languages. These program codes can be provided to a processor or controller of a general-purpose computer, a special-purpose computer or other programmable data processing device, so that the program code, when executed by the processor or controller, enables the functions / operations specified in the flow chart and / or block diagram to be implemented. The program code can be executed entirely on the machine, partially on the machine, partially on the machine as a stand-alone software package and partially on a remote machine, or entirely on a remote machine or server.

[0117] In the context of the present invention, a machine-readable medium may be a tangible medium that may contain or store a program for use by or in conjunction with an instruction execution system, device, or equipment. A machine-readable medium may be a machine-readable signal medium or a machine-readable storage medium. A machine-readable medium may include, but is not limited to, electronic, magnetic, optical, electromagnetic, infrared, or semiconductor systems, devices, or equipment, or any suitable combination of the foregoing. A more specific example of a machine-readable storage medium may include an electrical connection based on one or more lines, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the foregoing.

[0118] The above is only a specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can easily think of various equivalent modifications or replacements within the technical scope disclosed by the present invention, and these modifications or replacements should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention shall be based on the protection scope of the claims.

Claims

1. A train screening method for a TACS system, characterized in that: The method realizes the confirmation of the train occupancy status of the line section by automatic train screening and manual train screening. For the main line section, automatic train screening is carried out by using a communication train, and for the non-main line section, manual train screening is carried out by using a local operator button confirmation plus central dispatch authorization. The method specifically comprises the following steps: Step S101, after the trackside resource manager WRC is powered on or restarted, the WRC is powered on and unlocked through a WRC initialization command; Step S102, WRC determines the train occupancy status of all line sections. If there is no unknown train occupancy status in the line section, it is considered that the line screening is successful, otherwise, step S103 is executed; Step S103, perform automatic train screening, and execute step S104; Step S104, after the automatic train screening of the line is completed, it is determined whether there is still an unknown train occupying the section, if yes, step S105 is executed; otherwise, it is considered that the line screening is successful; Step S105, performing manual train screening; The specific process of automatic train screening in step S103 is as follows: Step S1031, WRC calculates whether there is unknown train occupation on the line and provides unknown train occupation information to ATS; Step S1032, ATS displays the line section information occupied by unknown trains to the dispatch terminal; Step S1033, the dispatching terminal decides to send the train screening operation task to the train controller xTC according to the displayed occupancy information; Step S1034, ATS sends the screened running task to xTC; Step S1035, xTC applies for line resources according to the received task; Step S1036, WRC allocates line resources to xTC; Step S1037, xTC calculates the mobile authorization operation path and sends it to ATS; Step S1038, the ATS displays the running path resource information to the dispatch terminal; Step S1039, the dispatching terminal authorizes the driver to manually drive the train according to the resources applied for by the train and performs line section screening; Step S10310, the driver manually drives the train according to the dispatching instruction; Step S10311, the xTC provides location information to the WRC in real time according to its own location; Step S10312, WRC screens the line section according to the location information provided by xTC; Step S10313, ATS confirms whether the route section has completed the screening process according to the screening result; The specific process of manual train screening in step S105 is as follows: Step S1051, WRC calculates whether there is unknown train occupation on the line and provides unknown train occupation information to ATS; Step S1052, ATS displays the line section information occupied by unknown trains to the dispatching terminal; Step S1053, the dispatch terminal authorizes and notifies the local operator to manually confirm whether there is an unknown train in the line section according to the displayed occupancy information; Step S1054, when the local operator confirms that there is no unknown train occupying the manual screening area and no unknown train entering, he presses the trackside confirmation button; Step S1055, OC collects the filter button information and sends it to WRC; Step S1056, after the WRC collects the manual screening button, it sends confirmation information of providing the manual screening area to the ATS; Step S1057, the ATS prompts the dispatch terminal to perform manual screening and confirmation on the interface; Step S1058, the dispatch terminal confirms on the ATS interface; Step S1059, ATS sends scheduling confirmation information to WRC; Step S10510, WRC completes the screening process of the manual screening area; Step S10511, ATS displays a successful screening message; Step S10512, the dispatch terminal confirms that the screening is successfully completed.

2. A train screening method for a TACS system according to claim 1, characterized in that: The non-mainline section includes a crossover, a storage line or a vehicle depot area.

3. The train screening method of a TACS system according to claim 1, characterized in that: The power-on unlocking of the WRC in step S101 is used to ensure the normal operation of the WRC, to perform normal intrusion detection, and to monitor the situation where trains illegally enter the signal area during line section screening.

4. The train screening method of a TACS system according to claim 1, characterized in that: The WRC in step S102 sends the train occupancy status of the entire line section to the ATS for display.

5. The train screening method of a TACS system according to claim 1, characterized in that: In the step S10312, when the automatic screening conditions of the section or automatic screening area through which the train physically passes are met, it is considered that there is no unknown train occupying the corresponding section.

6. The train screening method of a TACS system according to claim 1, characterized in that: When the length of the crossover does not meet the requirements for configuration as an automatic screening area, the corresponding switch section will be configured as a manual screening area, and manual confirmation will be performed to determine whether there is an unknown train in the section.

7. A system for the train screening method of the TACS system according to claim 1, characterized in that: The system includes the trackside resource manager WRC, the train controller xTC, the target controller OC, the automatic train monitoring system ATS, the intelligent operation and maintenance system IOM, the train intrusion detection system TID and the screening button CZB; The trackside resource manager WRC is respectively communicated with the train controller xTC, the target controller OC, the train automatic monitoring system ATS, and the intelligent operation and maintenance system IOM; the target controller OC is respectively communicated with the train intrusion detection system TID and the screening button CZB; and the train automatic monitoring system ATS is communicated with the train controller xTC.

8. The system according to claim 7, characterized in that According to the needs of train screening, the ATS sends the line screening operation task to the train controller xTC, and the train controller xTC applies for resources from the trackside resource manager WRC; the WRC transmits the line section occupancy display to the ATS, and the ATS sends the scheduling manual screening command to the WRC.

9. The system according to claim 7, characterized in that The local operator confirms whether the unknown train exists in the section by pressing the screening button CZB and sends it to the target controller OC; OC sends the button information to WRC.

10. The system according to claim 7, characterized in that The train intrusion detection system TID detects whether there is a train illegally intruding into the signal area.

11. The system according to claim 7, characterized in that The intelligent operation and maintenance system IOM displays the working status of the TACS equipment.

12. An electronic device comprising a memory and a processor, wherein a computer program is stored in the memory, wherein: When the processor executes the program, the method according to any one of claims 1 to 6 is implemented.

13. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the program is executed by a processor, the method according to any one of claims 1 to 6 is implemented.

Citation Information

Patent Citations

  • Train screening method and system based on autonomous operation control mode

    CN114454923A