A mooring structure and method for installing a berthing member

By setting auxiliary piles and support components on both sides of the wharf and connecting them with threaded steel bars and anchoring holes, the problem of the support beam tilting caused by large lateral spacing of the pile foundation or heavy weight of the berthing components was solved, and the stable installation and high-precision positioning of the berthing components were achieved.

CN116837786BActive Publication Date: 2025-11-07CRCC HARBOR & CHANNEL ENG BUREAU GRP
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202310869005.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-07-17
Publication Date
2025-11-07
Estimated Expiration
2043-07-17

Smart Images

  • Figure CN116837786B_ABST
    Figure CN116837786B_ABST
Patent Text Reader

Abstract

The application provides a fixed structure and method for installing a berthing component, comprising two second auxiliary piles, a support assembly, a berthing component and a fixing device, the second auxiliary piles are arranged in front of a wharf and on the left and right sides of the wharf, the upper end surfaces of the two second auxiliary piles and the upper end surfaces of the first auxiliary piles arranged on the two sides of the wharf in the width direction form a support platform, the support assembly is arranged on the support platform, a plurality of anchoring holes are arranged on the support assembly, a plurality of threaded steel bars are arranged on the berthing component, and the portions of the threaded steel bars that pass through the anchoring holes are connected with the support assembly through the fixing device. The application has the beneficial effects that the anchoring beams on the berthing component and the support assembly are connected through the fixing device, the pressure of the pile cap bottom die support system is reduced, the stability and safety of the construction temporary structure are ensured, the problem of installing the berthing component under the condition of no counter pressure is solved, the positioning position is more accurate, the influence on the construction process caused by the pile cap pouring is small, and the construction precision is improved.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present application relates to the technical field of anal canal auxiliary device, and in particular to a fixing structure and method for installing a berthing member. BACKGROUND

[0002] According to the high-pile wharf structure, the berthing member is arranged at the front of the wharf. Most of the existing berthing member installation methods adopt the resting method, the resting support beam is designed simultaneously with the wharf pile cap support system, and the eccentric moment is balanced by using the counter-pressure method before the installation of the berthing member: the berthing member is rested on the overhanging end of the support beam, the support beam must be placed on the adjacent two pile foundations, and the upper and lower positions of the contact part between the support beam and the pile foundation are limited to form a fixed counter-pressure to prevent the end of the support beam from being raised after the berthing member is rested and fixed.

[0003] During the construction of the pile foundation, a construction platform in the range of the pile cap and the berthing member needs to be installed, and a first auxiliary pile also needs to be arranged. After the construction of the pile foundation is completed, the pile cap, the construction platform in the range of the berthing member, and the first auxiliary pile are removed together.

[0004] The installation of the berthing member by using the resting method is mostly suitable for the installation of the berthing member with a small lateral spacing of the pile foundation and a light weight of the berthing member itself. Because the wharf is arranged at sea, for the berthing member with a large lateral spacing of the pile foundation, the counter-pressure cannot be arranged; for the berthing member with a heavy weight of the berthing member itself, the end of the support beam cannot be raised, so that the stability of the support system during the installation of the berthing member and the cast-in-place construction of the pile cap cannot be ensured. SUMMARY

[0005] The present application aims to solve the problems that for the berthing member with a large lateral spacing of the pile foundation, the counter-pressure cannot be arranged; for the berthing member with a heavy weight of the berthing member itself, the end of the support beam cannot be raised, so that the stability of the support system during the installation of the berthing member and the cast-in-place construction of the pile cap cannot be ensured.

[0006] To solve the above problems, the present application provides a fixing structure for installing a berthing member, comprising:

[0007] two second auxiliary piles arranged in front of the wharf and located on the left and right sides of the wharf, the upper end surfaces of the two second auxiliary piles and the upper end surfaces of the first auxiliary piles arranged on the left and right sides of the wharf form a support platform;

[0008] a support assembly arranged on the support platform, and a plurality of anchor holes are formed in the support assembly;

[0009] a berthing member, a plurality of threaded steel bars are arranged on the berthing member, and the upper ends of the plurality of threaded steel bars are respectively arranged in the plurality of anchor holes.

[0010] The fixing device is used for connecting the plurality of threaded steel bars and the support assembly.

[0011] In the present application, the mooring member and the support assembly are connected through the fixing device, which not only reduces the pressure of the pile cap bottom mold support system, but also supports and connects the mooring member through the support platform composed of the first auxiliary pile and the second auxiliary pile, so that the mooring member is stably lifted. The combination of the fixing device and the support platform can ensure the accurate and stable position of the mooring member during installation. The stability and safety of the temporary structure during construction are ensured. The problem of installing the mooring member under no back pressure condition is solved. The positioning is more accurate, and the construction process is less affected by the pile cap pouring, so that the construction precision is greatly improved.

[0012] Preferably, the support assembly comprises two girders and at least one anchoring beam. The two girders are respectively located on the left and right sides of the wharf. The first auxiliary pile and the second auxiliary pile on the same side are arranged in front of and behind each other. Each of the girders is respectively erected and fixed on the first auxiliary pile and the second auxiliary pile on the same side. The anchoring beam is erected and horizontally fixed on the two girders. The anchoring beam is located above the mooring member. The plurality of anchoring holes are arranged on the anchoring beam.

[0013] In the present application, the connection between the support assembly and the auxiliary pile is more stable through the girders and the anchoring beam, so that the mooring member is more stable after being connected.

[0014] Further preferably, the anchoring beam is provided with two parallel anchoring beams. Two anchoring holes are arranged on each of the anchoring beams.

[0015] In the present application, the four anchoring holes make the fixation of the mooring member more stable and prevent the mooring member from being deviated by the flow of seawater.

[0016] Further preferably, the anchoring steel bars and the connecting device are further included. The lower end of each anchoring steel bar is connected to the upper end of one threaded steel bar through one connecting device. The upper end of each anchoring steel bar is connected to the anchoring beam through the fixing device.

[0017] In the present application, the length of the threaded steel bar can be lengthened through the connecting device and the anchoring steel bar, and the position of the anchoring beam can be raised to prevent the mooring member from being submerged by seawater during high tide.

[0018] As a further preferred embodiment, the connecting device includes a straight threaded sleeve, with each end of the straight threaded sleeve being threadedly connected to one of the anchoring steel bars and one of the threaded steel bars, respectively.

[0019] In this solution, the straight threaded sleeve connects the anchoring steel bar and the threaded steel bar, thereby increasing the length of the threaded steel bar and making the connection more stable.

[0020] As a further preferred embodiment, the fixing device includes a fixing nut, the anchoring steel bar is provided with external threads, each fixing nut is threadedly connected to one end of the anchoring steel bar that protrudes from the anchoring hole, and the lower end face of each fixing nut abuts against the upper end face of the anchoring beam.

[0021] In this scheme, the fixing nuts securely fix the anchoring steel bars to the anchoring beam, thereby fixing the berthing components as well.

[0022] As a further preferred embodiment, each of the anchoring beams and each of the main beams is formed by splicing two 45mm I-beams together with their sides touching.

[0023] A method for securing a berthing component includes:

[0024] S1. Before the pile foundation construction, construct the first auxiliary pile at the designated location, and set up the pile cap and construction platform through the first auxiliary pile; after the pile foundation construction is completed, remove the pile cap and construction platform, but do not remove the first auxiliary pile;

[0025] S2. Two second auxiliary piles are erected in front of the dock and on the left and right sides of the dock, and the second auxiliary piles and the first auxiliary piles on the left or right side of the dock are set at an interval.

[0026] S3. Two 45 I-beams are spliced ​​together to form a main beam. A total of two main beams are set up. The two main beams are respectively connected to a second auxiliary pile and a first auxiliary pile located on the same side.

[0027] S4. Two 45 I-beams are spliced ​​together to form an anchor beam for fixing the berthing components. Two anchor beams are set up horizontally on the two main beams. The two anchor beams are set parallel and spaced apart. Four anchor holes are opened at corresponding positions on the anchor beams.

[0028] S5. After threading the straight thread sleeve according to the diameter of the threaded steel bar on the berthing component, connect the straight thread sleeve to the threaded steel bar of the berthing component.

[0029] S6. Use a crane to lift the berthing component to the design position and corresponding elevation. Use four anchoring steel bars, which are the same as the threaded steel bars of the berthing component, to pass through the anchoring holes reserved in the anchoring beam from top to bottom, and connect them to the threaded steel bars of the berthing component through straight threaded sleeves.

[0030] S7, using the corresponding type of fixed nut to fix the anchoring steel bars which are out of the anchoring holes and above the anchoring beams with the anchoring beams; checking the position, elevation and perpendicularity of the berthing component, and adjusting the connection position of the fixed nut and the anchoring steel bars to meet the design requirements of the berthing component installation;

[0031] S8, loosening the crane hook, limiting and fixing the berthing component and the pile cap supporting system, and completing the installation of the berthing component. BRIEF DESCRIPTION OF DRAWINGS

[0032] Figure 1 It is a structural schematic view of the fixing structure for installing the berthing component of the present application.

[0033] Figure 2 It is a side view structural schematic view of the fixing structure for installing the berthing component of the present application.

[0034] The reference signs are explained as follows: 1, support assembly; 11, anchoring beam; 12, girder; 2, berthing component; 3, first auxiliary pile; 4, threaded steel bar; 5, fixing device; 51, fixed nut; 6, anchoring steel bar; 7, connecting device; 71, straight thread sleeve; 8, second auxiliary pile. DETAILED DESCRIPTION

[0035] In order to make the above-mentioned objects, features and advantages of the present application more obvious and easy to understand, the specific embodiments of the present application are described in detail below with reference to the drawings.

[0036] In the preferred embodiment of the present application, based on the above-mentioned problems existing in the prior art, a fixing structure and method for installing a berthing component are provided, as shown in the drawings, which comprises two second auxiliary piles 8, a support assembly 1, a berthing component 2 and a fixing device 5. Figures 1-2 The second auxiliary piles 8 are arranged in front of the wharf and located on the left and right sides of the wharf, and the upper end surfaces of the two second auxiliary piles 8 and the upper end surfaces of the first auxiliary piles 3 arranged on the two sides of the width direction of the wharf form a support platform; the support assembly 1 is arranged on the support platform; and a plurality of anchoring holes are formed in the support assembly 1; the berthing component 2 is provided with a plurality of threaded steel bars 4; the portions of the threaded steel bars 4 which are out of the anchoring holes are connected with the support assembly 1 through the fixing device 5, so as to connect the berthing component 2 with the support assembly 1 through the anchoring steel bars 6.

[0037] The support assembly 1 includes two main beams 12 and at least one anchor beam 11. The two main beams 12 are located on the left and right sides of the wharf, respectively. The first auxiliary pile 3 and the second auxiliary pile 8 on the same side are arranged at an interval. Each main beam 12 is erected and fixed on the first auxiliary pile 3 and the second auxiliary pile 8 on the same side. The anchor beam 11 is erected and horizontally fixed on the two main beams 12 and is located above the berthing component 2. Multiple anchoring holes are provided on the anchor beam 11. There are two anchor beams 11, which are arranged in parallel, and each anchor beam 11 has two anchoring holes.

[0038] It also includes: multiple anchoring steel bars 6 and connecting devices 7. The lower end of each anchoring steel bar 6 is connected to the upper end of a threaded steel bar 4 through a connecting device 7. The upper ends of the multiple anchoring steel bars 6 pass through anchoring holes and are connected to the anchoring beam 11 through fixing devices 5.

[0039] Specifically, in this embodiment, as Figure 1 As shown, the left side of the pier is the left side of the pier, and the right side of the pier is the right side of the pier. The first auxiliary pile 3 and the second auxiliary pile 8 are arranged in parallel, and the two first auxiliary piles 3 and the two second auxiliary piles 8 are respectively located at the four corners of a rectangle. A large beam 12 is installed on one of the first auxiliary piles 3 and the other of the second auxiliary pile 8 on the same side. Two parallel anchoring beams 11 are laid between the two large beams 12. There are four anchoring holes, and each anchoring beam 11 has two anchoring holes. The four anchoring holes are arranged corresponding to the four corners of the upper end of the berthing component 2, which can make the fixation more secure and prevent the berthing component 2 from deflecting due to the flow of seawater. When dismantling the pile caps and the construction platform within the area of ​​the mooring component 2, the first auxiliary pile 3 is not removed, and two second auxiliary piles 8 are added to form four supports. A main beam 12 is connected to each first auxiliary pile 3 and each second auxiliary pile 8 on the same side. Two parallel anchoring beams 11 are connected between the main beams 12 on the left and right sides, with the anchoring beams 11 horizontally positioned between the two main beams 12. The four anchoring holes ensure a more secure fixation of the mooring component 2, preventing it from shifting with the flow of seawater. Each anchoring beam 11 and each main beam 12 is formed by splicing two 45mm I-beams together on their sides. The diameter of both the first auxiliary pile 3 and the second auxiliary pile 8 is 630mm, and their height is 8mm.

[0040] Specifically, in the embodiment, the berthing member 2 and the support assembly 1 are connected by the fixing device 5, the pressure of the pile cap bottom die support system is reduced, the stability and safety of the construction temporary structure are ensured, the problem of installation of the berthing member 2 under the condition of no counter-pressure is solved, the positioning position is more accurate, the construction process is less affected by the pile cap pouring, and the construction precision is greatly improved. The support assembly 1 and the auxiliary pile can be more stably connected by arranging the beam 12 and the anchoring beam 11, so that the berthing member 2 is more stably connected. The length of the threaded steel bar 4 can be lengthened and the position of the anchoring beam 11 can be raised by arranging the connecting device 7 and the anchoring steel bar 6, so that the berthing member 2 is prevented from being submerged by seawater during high tide.

[0041] The connecting device 7 comprises straight-thread sleeves 71, and each straight-thread sleeve 71 is threadedly connected with one anchoring steel bar 6 and one threaded steel bar 4 at both ends thereof. The fixing device 5 comprises fixing nuts 51, and each anchoring steel bar 6 is provided with external threads. Each fixing nut 51 is threadedly connected with one end of one anchoring steel bar 6 that penetrates through the anchoring hole, and the lower end surface of each fixing nut 51 abuts against the upper end surface of the anchoring beam 11.

[0042] Specifically, in the embodiment, the threaded steel bar 4 and the anchoring steel bar 6 are both provided with external threads, the straight-thread sleeve 71 is provided with internal threads, and the internal threads and the external threads are threadedly matched to fix the threaded steel bar 4 and the anchoring steel bar 6. The fixing device 5 comprises fixing nuts 51, and preferably, the fixing device 5 comprises double nuts of the fixing nuts 51 and locking nuts. The fixing nuts 51 and the locking nuts are both provided with internal threads, and the internal threads are threadedly matched with the external threads of the anchoring steel bar 6. The straight-thread sleeve 71 connects the anchoring steel bar 6 and the threaded steel bar 4, thereby lengthening the length of the threaded steel bar 4 and making the connection more stable. The fixing nuts 51 firmly fix the anchoring steel bar 6 and the anchoring beam 11, and the locking nuts further lock the anchoring steel bar 6 and the anchoring beam 11, thereby fixing the berthing member 2.

[0043] A fixing method for installing a berthing member, comprising:

[0044] S1, before pile foundation construction, a first auxiliary pile 3 is constructed at a set position, and a pile cap and a construction platform are arranged through the first auxiliary pile 3; after the pile foundation construction is completed, the pile cap and the construction platform are removed, and the first auxiliary pile 3 is not removed;

[0045] S2, two second auxiliary piles 8 are erected in front of the wharf and on the left and right sides of the wharf, and the second auxiliary pile 8 located on the left side or the right side of the wharf and the first auxiliary pile 3 are both arranged in a front-rear interval;

[0046] S3, two 45-shaped steel bars are spliced to form one beam 12, and two beams 12 are arranged, and the two beams 12 are respectively connected with one second auxiliary pile 8 and one first auxiliary pile 3 located on the same side;

[0047] S4, two 45-shaped steel are spliced to form an anchoring beam 11 for fixing the berthing member 2, the anchoring beam 11 is arranged on two girders 12 in a horizontal manner, and the two anchoring beams 11 are arranged in parallel and at intervals; four anchoring holes are formed in corresponding positions of the anchoring beam 11;

[0048] S5, after the size of the straight thread sleeve 71 is threaded according to the diameter of the threaded steel bar 4 on the berthing member 2, the straight thread sleeve 71 is connected with the threaded steel bar 4 of the berthing member 2;

[0049] S6, the berthing member 2 is hoisted to a designed position and a corresponding elevation by using a crane, four anchoring steel bars 6 which are the same as the threaded steel bar 4 of the berthing member 2 are passed through the anchoring holes reserved in the anchoring beam 11 from top to bottom, and are connected with the threaded steel bar 4 of the berthing member 2 through the straight thread sleeve 71;

[0050] S7, the anchoring steel bars 6 which are passed out of the anchoring holes and located above the anchoring beam 11 are fixed with the anchoring beam 11 by using a fixing nut 51 of a corresponding model; the position, elevation and perpendicularity of the berthing member 2 are checked, and the connection position of the fixing nut 51 and the anchoring steel bar 6 is adjusted so as to meet the installation design requirements of the berthing member 2;

[0051] S8, the crane hook is loosened, the berthing member 2 is fixed and limited with the pile cap supporting system, and the installation of the berthing member 2 is completed.

[0052] In S2, the vibration hammer is used to increase the erection of two φ630*8mm second auxiliary piles 8; the length of the part of the anchoring steel bar 6 which is passed out of the anchoring hole and located above the upper surface of the anchoring beam 11 is not less than 30cm; three anchoring holes can also be formed in the anchoring beam 11, two anchoring holes are formed in one anchoring beam 11, and one anchoring hole is formed in the anchoring beam 11 which is located at the middle position between the two anchoring holes, thereby solving the problem of installation of the berthing member 2 under the condition of no counter pressure; the independent supporting system is adopted for fixation, thereby reducing the pressure of the pile cap bottom die supporting system and ensuring the stability and safety of the construction temporary structure; the positioning position is more accurate, the influence on the construction process caused by the pile cap pouring is smaller, the construction precision is greatly improved, and the installation is more convenient and stable.

[0053] Although the present disclosure is disclosed as above, the protection scope of the present disclosure is not limited to this. Those skilled in the art can make various changes and modifications without departing from the spirit and scope of the present disclosure, and these changes and modifications shall fall within the protection scope of the present disclosure.

Claims

1. A fixing method of a fixed structure of a berthing component, the fixed structure comprising two second auxiliary piles (8) arranged in front of a wharf and on the left and right sides of the wharf, upper end faces of the two second auxiliary piles (8) and upper end faces of preset first auxiliary piles (3) on the left and right sides of the wharf forming a support platform, a support assembly (1) arranged on the support platform, the support assembly (1) being provided with a plurality of anchoring holes, a berthing component (2) provided with a plurality of threaded steel bars (4), upper ends of the plurality of threaded steel bars (4) being respectively arranged in the plurality of anchoring holes, a fixing device (5) connecting the plurality of threaded steel bars (4) that pass out of the anchoring holes and the support assembly (1) to connect the berthing component (2) and the support assembly (1) through the threaded steel bars (4), the support assembly (1) comprising two girders (12) and at least one anchoring beam (11), the two girders (12) being respectively arranged on the left and right sides of the wharf, the first auxiliary piles (3) and the second auxiliary piles (8) on the same side being arranged in front of and behind each other, each of the girders (12) being respectively arranged and fixed on the first auxiliary piles (3) and the second auxiliary piles (8) on the same side, the anchoring beam (11) being arranged and fixed horizontally on the two girders (12) and above the berthing component (2), and the plurality of anchoring holes being arranged on the anchoring beam (11); and the method further comprising: A plurality of anchoring steel bars (6) and connecting devices (7), the lower end of each of the anchoring steel bars (6) is connected with the upper end of one of the threaded steel bars (4) through one of the connecting devices (7) respectively, the upper end of each of the anchoring steel bars (6) is connected with the anchoring beam (11) through the fixing device (5) through the anchoring hole; the connecting device (7) comprises a straight threaded sleeve (71), the two ends of each of the straight threaded sleeves (71) are threadedly connected with one of the anchoring steel bars (6) and one of the threaded steel bars (4) respectively; the fixing device (5) comprises a fixing nut (51), the anchoring steel bars (6) are provided with external threads, each of the fixing nuts (51) is threadedly connected with one end of one of the anchoring steel bars (6) which passes through the anchoring hole, and the lower end surface of each of the fixing nuts (51) abuts against the upper end surface of the anchoring beam (11); the fixing method of the fixing structure comprises the following steps: S1, before the pile foundation construction, a first auxiliary pile (3) is constructed at a set position, a pile cap and a construction platform are arranged through the first auxiliary pile (3); after the pile foundation construction is completed, the pile cap and the construction platform are removed, and the first auxiliary pile (3) is not removed; S2, two second auxiliary piles (8) are erected in front of the wharf and on the left and right sides of the wharf, and the second auxiliary pile (8) on the left side or the right side of the wharf and the first auxiliary pile (3) are arranged in front and back intervals; S3, two 45-shaped steels are used to splice to form a large beam (12), two large beams (12) are arranged, and the two large beams (12) are connected with one second auxiliary pile (8) and one first auxiliary pile (3) on the same side respectively; S4, two 45-shaped steels are used to splice to form an anchoring beam (11) for fixing the berthing member (2), the anchoring beam (11) is arranged in two and horizontally erected on the two large beams (12), and the two anchoring beams (11) are arranged in parallel and intervals; four anchoring holes are arranged at corresponding positions of the anchoring beam (11); S5, after the size of the straight threaded sleeve (71) is threaded according to the diameter of the threaded steel bar (4) on the berthing member (2), the straight threaded sleeve (71) is connected with the threaded steel bar (4) of the berthing member (2); S6, the berthing member (2) is hoisted to the designed position and the corresponding elevation by using a crane, four anchoring steel bars (6) which are the same as the threaded steel bar (4) of the berthing member (2) are passed through the anchoring holes reserved in the anchoring beam (11) from top to bottom, and are connected with the threaded steel bar (4) of the berthing member (2) through the straight threaded sleeve (71); S7, the anchoring steel bar (6) which passes out of the anchoring hole and is located above the anchoring beam (11) is fixed with the anchoring beam (11) by using a fixing nut (51) of a corresponding model; the position, elevation and perpendicularity of the berthing member (2) and the anchoring steel bar (6) are checked, the connection position of the fixing nut (51) and the anchoring steel bar (6) is adjusted to meet the installation design requirements of the berthing member (2); S8, the hook of the crane is loosened, the berthing member (2) is limited and fixed with the pile cap supporting system, and the installation of the berthing member (2) is completed.

Citation Information

Patent Citations

  • Tidal sea area berthing component mounting device and construction method

    CN115450173A

  • Fixing structure for mounting berthing component

    CN220202593U