A quay crane assembly method and a quay crane assembly transport device

Through the design of the shore and bridge assembly transportation device, indoor transportation and assembly of shore and bridge assembly is realized, the problems of low assembly efficiency and safety hazards are solved, and the assembly efficiency and safety are improved.

CN116969322BActive Publication Date: 2025-08-26SHANGHAI ZHENHUA HEAVY IND
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202310975451.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-08-03
Publication Date
2025-08-26
Estimated Expiration
2043-08-03

AI Technical Summary

Technical Problem

During the assembly process of the existing technology, the assembly efficiency is low and there are safety hazards. Especially the assembly of trolleys with large trucks, balance beams and lower beams at all levels requires multiple equipment and personnel, and requires water operation, which takes up a long time to complete the assembly station and poses safety risks.

Method used

A shore bridge assembly transport device is provided, including a transport unit, a first fixing device and a second fixing device, for stabilizing a plurality of shore bridge assembly, realizing indoor transportation through rollers, reducing water-to-water operations, and improving assembly efficiency.

Benefits of technology

The indoor centralized operation of the shore and bridge assembly is realized, the impact of outdoor operations on production is reduced, assembly efficiency and safety is improved, and the occupation time of the final assembly station is shortened.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116969322B_ABST
    Figure CN116969322B_ABST
Patent Text Reader

Abstract

The object of the present invention is to provide a quay crane assembly method and a quay crane assembly transport device thereof, the quay crane assembly transport device comprising a transport unit, a first fixing device and a second fixing device. The transport unit has a load-bearing surface on the upper part and rollers on the lower part. The first fixing device is arranged on the load-bearing surface, and extends along the width direction of the transport unit in the assembled state, and has a first fixing portion. Two or more quay crane assemblies to be transported are fixed to the first fixing device through the first fixing portion, and the two or more quay crane assemblies after being fixed are arranged at intervals along the extension direction of the first fixing device. The second fixing device is arranged on the upper surface of the adjacent two-bank gantry assemblies, and has a second fixing portion at both ends. The adjacent two-bank gantry assemblies are fixedly connected to the second fixing device through the second fixing portion. The present quay crane assembly transport device can improve the assembly efficiency of the quay crane.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of quay crane assembly, and in particular to a quay crane assembly method and a quay crane assembly transport device. Background Art

[0002] The trolley travel of the shore container crane (abbreviated as quay crane in this article) is the most important component for the movement of the quay crane. During normal operation of the container terminal, since the position of the freighter is relatively fixed, the containers at different positions along the length of the freighter are moved between the quay crane and the freighter by the trolley travel, thereby loading and unloading containers at different positions on the freighter.

[0003] Currently, during the final assembly of quay cranes, the trolleys for the gantry crane travel mechanism, the balance beams at each stage, and the connected lower crossbeams are transported separately to the final assembly station, where they are assembled into components one by one. This method allows only one gantry crane travel mechanism and lower crossbeam to be assembled at a single station, requiring the same number of equipment and personnel for multiple gantry cranes. The assembly of the lower crossbeams and gantry crane travel mechanism also requires the use of large outdoor lifting equipment (floating cranes, truck cranes). This not only occupies a long assembly time, but also involves working near water, posing safety risks.

[0004] How to provide a new assembly method to achieve fast and effective assembly of quay cranes is an urgent problem that needs to be solved. Summary of the Invention

[0005] The object of the present invention is to provide a quay crane assembly transport device, which can improve the assembly efficiency of the quay crane.

[0006] In order to achieve the above-mentioned purpose, a quay crane assembly transport device includes:

[0007] A transport unit having a load-bearing surface at the upper portion and rollers at the lower portion;

[0008] a first fixing device, disposed on the carrying surface, extending along the width direction of the transport unit in the assembled state, and having a first fixing portion, wherein two or more quay crane assemblies to be transported are fixed to the first fixing device via the first fixing portion, and the two or more quay crane assemblies after being fixed are arranged at intervals along the extension direction of the first fixing device; and

[0009] The second fixing device is arranged on the upper surface of the adjacent two-bank bridge assemblies and has second fixing parts at both ends. The adjacent two-bank bridge assemblies are fixedly connected to the second fixing device through the second fixing parts.

[0010] In one or more embodiments, the first fixing portion is an elongated hole formed on the first fixing device.

[0011] In one or more embodiments, the second fixing portion is an elongated hole formed on the second fixing device.

[0012] In one or more embodiments, partitions are provided in the second fixing device, and the second fixing portion is provided between the partitions.

[0013] In one or more embodiments, the first fixing device includes wing portions protruding toward both sides of the transport unit, and the first fixing portions are respectively arranged on the wing portions. The quay crane assembly transport device is used to transport a pair of quay crane assemblies, and the quay crane assemblies on both sides are respectively fixed on the two wing portions.

[0014] In one or more embodiments, the quay crane assembly transport device includes a pair of the transport units, a pair of the first fixing devices, and a pair of the second fixing devices, the pair of the first fixing devices are respectively fixed at the lower ends of the length direction of the quay crane assembly, and the pair of the second fixing devices are respectively fixed at the upper ends of the length direction of the quay crane assembly.

[0015] In one or more embodiments, a stop portion is further provided on the wing portion, and the stop portion is provided close to the first fixing portion.

[0016] In one or more embodiments, a pad is further provided on the wing portion, and the pad is provided close to the stop portion.

[0017] In one or more embodiments, the quay crane assembly includes a traveling mechanism and a lower beam assembly, the bottom of the traveling mechanism is fixedly connected to the first fixing device, and the top of the lower beam assembly is fixedly connected to the second fixing device.

[0018] On the other hand, according to some embodiments of the present application, a method for assembling a quay crane is further provided, comprising the following steps:

[0019] Configure assembly stations and final assembly stations;

[0020] Assembling the quay crane trolley traveling assembly and the quay crane lower crossbeam assembly into a quay crane assembly at the assembly station;

[0021] Transporting the quay crane assembly from the assembly station to the final assembly station using the aforementioned quay crane assembly transport device;

[0022] At the final assembly station, the quay crane assembly is hoisted onto the pre-laid track to complete the assembly of the quay crane.

[0023] In one or more embodiments, assembling the quay crane assembly at the assembly station further comprises the following steps:

[0024] Arrange the trolley according to design requirements;

[0025] Hoist the first crossbeam onto two adjacent vehicles;

[0026] Hoist the second beam onto the two first beams;

[0027] Arranging supports on the second crossbeam to assemble and form a walking mechanism unit body;

[0028] Arrange the relative distance between the two traveling mechanism units according to the designed trolley base distance;

[0029] The lower crossbeam assembly is hoisted onto the two traveling mechanism units to complete the assembly of the quay crane assembly.

[0030] The beneficial effects of the present invention are:

[0031] This assembly method allows the entire quay crane assembly process to be unaffected by the final assembly station, such as the dock environment. This allows for centralized indoor operations, reducing the impact of various weather factors on production during outdoor operations and reducing waterborne operations, thus facilitating safe production. Furthermore, it shortens the time spent at the dock assembly station and improves assembly efficiency.

[0032] The above description is only an overview of the technical solution of the present application. In order to more clearly understand the technical means of the present application, it can be implemented in accordance with the contents of the specification. In order to make the above and other purposes, features and advantages of the present application more obvious and easy to understand, the specific implementation methods of the present application are listed below. BRIEF DESCRIPTION OF THE DRAWINGS

[0033] Various other advantages and benefits will become apparent to those skilled in the art upon reading the detailed description of the preferred embodiment below. The accompanying drawings are for illustration purposes only and are not to be considered as limiting the present application. The same reference numerals are used throughout the drawings to represent the same components. In the drawings:

[0034] Figure 1 A three-dimensional schematic diagram showing a state of transporting a quay crane assembly according to some embodiments of the quay crane assembly transporting device is shown;

[0035] Figure 2 A side schematic diagram showing a state of transporting a quay crane assembly according to some embodiments of the quay crane assembly transporting device is shown;

[0036] Figure 3 A partial schematic diagram of a first fixing device according to some embodiments of the present quay crane assembly transport device is shown;

[0037] Figure 4 A partial schematic diagram of a second fixing device according to some embodiments of the present quay crane assembly transport device is shown;

[0038] Figures 5 to 16 Schematic diagrams of the quay crane assembly process in some embodiments are shown. DETAILED DESCRIPTION

[0039] The following embodiments of the technical solution of the present application will be described in detail with reference to the accompanying drawings. The following embodiments are only used to more clearly illustrate the technical solution of the present application and are therefore only examples and are not intended to limit the scope of protection of the present application.

[0040] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by those skilled in the art to which this application belongs; the terms used herein are only for the purpose of describing specific embodiments and are not intended to limit this application; the terms "including" and "having" and any variations thereof in the specification and claims of this application and the above-mentioned figure descriptions are intended to cover non-exclusive inclusions.

[0041] In order to improve the assembly efficiency and safety of a quay crane, on the one hand, according to some embodiments of the present application, a quay crane assembly method is provided, which includes the following steps:

[0042] First, assembly stations and final assembly stations are configured. In a specific embodiment, the final assembly station is located at the dock, and the assembly stations are located in an assembly plant near the dock.

[0043] Then, at the assembly station, the quay crane trolley travel assembly and the quay crane lower crossbeam assembly are assembled into the quay crane assembly;

[0044] Subsequently, the quay crane assembly is transported from the assembly station to the final assembly station using the quay crane assembly transport device;

[0045] Finally, the quay crane assembly is hoisted onto the pre-laid track at the final assembly station to complete the assembly of the quay crane.

[0046] The aforementioned assembly method allows the entire quay crane assembly process to be unaffected by the final assembly station, such as the dock environment. This allows for centralized indoor operations, minimizing the impact of various weather factors on production during outdoor operations and reducing waterborne operations, thus facilitating safe production. Furthermore, it reduces the time spent at the dock assembly station, improving assembly efficiency.

[0047] In the process of assembling the quay crane using the aforementioned quay crane assembly method, one of the difficulties is how to transport the quay crane assembly from the assembly station to the final assembly station. In order to solve the aforementioned problem, on the other hand, according to some embodiments of the present application, a quay crane assembly transportation device is also provided.

[0048] like Figure 1 A three-dimensional schematic diagram showing the state of transporting a quay crane assembly according to some embodiments of the quay crane assembly transport device is shown. Figure 2 A side schematic diagram of the state of transporting a quay crane assembly according to some embodiments of the quay crane assembly transporting device is shown.

[0049] Combine Figure 1 as well as Figure 2 As shown in the figure, the present quay crane assembly transport device comprises a first fixing device 1, a second fixing device 2 and a transport unit 3. The transport unit 3 has a bearing surface 30 on the upper part and rollers 31 on the lower part. The first fixing device 1 is arranged on the bearing surface 30 and extends along the width direction of the transport unit 3 in the assembled state. Two or more quay crane assemblies 9 to be transported are arranged on the first fixing device 1, as shown in FIG. Figure 3 As can be seen from the partial details shown, the first fixing device 1 has a first fixing portion 10, and the quayside bridge assembly 9 is fixed to the first fixing device 1 through the first fixing portion 10. Two or more quayside bridge assemblies 9 are arranged at intervals along the extension direction of the first fixing device 1. The second fixing device 2 is provided on the upper surface of the adjacent two-bank bridge assemblies 9 and is fixedly connected to the upper surface of the adjacent two-bank bridge assemblies 9, as shown in FIG. Figure 4 It can be seen from the local details shown that the second fixing device 2 has a second fixing portion 20 at each end, and the bridge assemblies 9 on the adjacent two banks are fixedly connected to the second fixing device 2 via the second fixing portion 20 .

[0050] With this arrangement, the upper and lower portions of two or more quay crane assemblies 9 are fixed together as a whole by the first fixing device 1 and the second fixing device 2, respectively, and then transported by the transport unit 3. By providing the fixing devices at the upper and lower portions of the two or more quay crane assemblies 9, respectively, the quay crane assembly transport device can simultaneously transport at least two quay crane assemblies 9, while ensuring the stable fixation of at least two quay crane assemblies 9, preventing the quay crane assemblies 9 from slipping or overturning during transportation, and ensuring the safety of the transportation process.

[0051] In the description of the embodiments of the present application, technical terms such as "first" and "second" are only used to distinguish different objects and cannot be understood as indicating or implying relative importance or implicitly indicating the number, specific order or primary and secondary relationship of the indicated technical features.

[0052] In the description of the embodiments of the present application, “multiple” means more than two, unless otherwise clearly and specifically defined.

[0053] References herein to "embodiments" mean that a particular feature, structure, or characteristic described in connection with the embodiments may be included in at least one embodiment of the present application. The appearance of this phrase in various places in the specification does not necessarily refer to the same embodiment, nor does it constitute an independent or alternative embodiment that is mutually exclusive of other embodiments. It is understood, both explicitly and implicitly, by those skilled in the art that the embodiments described herein may be combined with other embodiments.

[0054] In one embodiment of the present quay crane assembly transport device, the first fixing portion 10 is an elongated hole formed in the first fixing device 1, through which the lower portion of the quay crane assembly 9 is fixedly connected via a fastener. The provision of the elongated hole ensures that quay crane assemblies 9 of different sizes can be secured, thereby expanding the application range of the present quay crane assembly transport device.

[0055] In one embodiment of the present quay crane assembly transport device, the second fixing portion 20 is an elongated hole formed in the second fixing device 2, through which the upper portion of the quay crane assembly 9 is fixedly connected via fasteners. The provision of the elongated hole ensures that quay crane assemblies 9 of varying sizes can be secured, thereby expanding the application range of the present quay crane assembly transport device.

[0056] In one embodiment of the present quay crane assembly transporting device, a plurality of partitions 21 are provided in the second fixing device 2 , and the second fixing portion 20 is provided between the partitions 21 .

[0057] In one embodiment of the present quay crane assembly transport device, the first fixing device 1 includes a wing plate portion 11 protruding toward both sides of the transport unit 3, and the first fixing portion 10 is respectively arranged on the wing plate portion 11. The present quay crane assembly transport device is used to transport a pair of quay crane assemblies 9, and the quay crane assemblies 9 on both sides are respectively fixed on the two wing plate portions 11.

[0058] In one embodiment of the present quay crane assembly transport device, the present quay crane assembly transport device includes a pair of transport units 3, a pair of first fixing devices 1, and a pair of second fixing devices 2. The pair of first fixing devices 1 are fixed to the lower ends of the quay crane assembly 9 in the longitudinal direction, and the pair of second fixing devices 2 are fixed to the upper ends of the quay crane assembly 9 in the longitudinal direction. This configuration enables the quay crane assembly 9 to be fixed and supported at both ends in the longitudinal direction, ensuring stability during transportation.

[0059] In one embodiment of the present quay crane assembly transport device, a stop portion 12 is further provided on the wing portion 11. The stop portion 12 is arranged close to the first fixing portion 10. When the transported quay crane assembly 9 abuts against the stop portion 12, it can be fixed to the first fixing portion 10.

[0060] In one embodiment of the present quay crane assembly transport device, pads 13 are further provided on the wing plate portion 11, positioned adjacent to the stop portion 12. In a specific embodiment, the pads 13 are sleepers. The provision of the pads 13 ensures the stability of the support for the quay crane assembly 9, preventing it from slipping during transport.

[0061] In one embodiment of the present quay crane assembly transport device, the quay crane assembly 9 includes a traveling mechanism and a lower crossbeam assembly, the bottom of the traveling mechanism is fixedly connected to the first fixing device 1 , and the top of the lower crossbeam assembly is fixedly connected to the second fixing device 2 .

[0062] On the other hand, according to some embodiments of the present quay crane assembly method, assembling the quay crane assembly 9 at the assembly station further includes the following steps:

[0063] First, the trolley 91 is arranged according to the design requirements, such as Figure 5 As shown, the trolleys 91 are arranged at a distance from each other according to design requirements.

[0064] Then, the first crossbeam 92 is hoisted onto two adjacent vehicles 91, as shown in FIG. Figure 6 As shown, since the assembly station can be located in an indoor workshop, the first crossbeam 92 can be hoisted and fixed on two adjacent vehicles 91 using, for example, hoisting equipment in the workshop.

[0065] Then, the second beam 93 is hoisted on the two first beams 92, as shown in FIG. Figure 7 As shown, since the assembly station can be located in an indoor workshop, the second crossbeam 93 can be hoisted and fixed on the two first crossbeams 92 using, for example, hoisting equipment in the workshop.

[0066] Then, the support 94 is arranged on the second cross beam 93 to assemble the Figure 8 The walking mechanism unit body 900 is shown.

[0067] Then, if Figure 9 As shown, the relative distance between the two walking mechanism units 900 is arranged according to the designed trolley base distance a.

[0068] Then, if Figure 10 As shown, the lower crossbeam assembly 95 is hoisted onto the two traveling mechanism units 900 to realize the assembly of the quay crane assembly 9 .

[0069] Furthermore, in a specific embodiment, when the lower crossbeam assembly 95 is hoisted on the two walking mechanism units 900, first Figure 11 As shown, along the width direction of the lower cross beam assembly 95, a lifting beam 96 is pre-arranged below it to facilitate adjustment during the assembly of the quay crane. In a specific embodiment, as shown in FIG. Figure 12 In the enlarged view shown, a hanging ear 950 is provided on the lower cross beam assembly 95 , and the end of the lifting beam 96 is fixedly connected to the hanging ear 950 via a steel wire rope 961 .

[0070] Furthermore, in a specific embodiment, Figure 13 As shown, the lower cross beam assembly 95 and the support 94 are fixedly connected by a plurality of pins 951 .

[0071] Furthermore, in a specific embodiment, Figure 14 As shown, after the lower cross beam assembly 95 is hoisted on the two walking mechanism unit bodies 900, an anti-tilt unit 960 is provided to support the lower cross beam assembly 95 from the side to prevent the lower cross beam assembly 95 from tilting.

[0072] Furthermore, in a specific embodiment, after the lower crossbeam assembly 95 is hoisted on the two walking mechanism units 900, it is determined whether the installation of the accessories affects the positioning of the transfer equipment. If so, the installation is performed after the equipment is transferred to the final assembly station. If not, the installation is performed as follows. Figures 15 and 16 As shown, the accessories on the walking mechanism are installed. In some specific embodiments, the accessories include Figures 15 and 16 As shown in: driving mechanism 971, railing 972, lower beam process platform 973, process ladder 974.

[0073] Furthermore, using the quay crane assembly transport device to transport the quay crane assembly from the assembly station to the final assembly station includes:

[0074] The quay crane assembly 9 is hoisted as a whole onto the first fixing device 1 using lifting equipment and fixed, specifically, by fasteners such as bolts. In some specific embodiments, sleepers are filled between the quay crane assembly 9 and the limit blocks.

[0075] Subsequently, the second fixture 2 is hoisted onto the quay crane assembly 9 and secured, specifically, by fastening it to the second fixture 2 through the lower crossbeam manhole using fasteners such as bolts. The transport unit 3 enters the quay crane assembly 9 along its length and transports the components to a designated storage location.

[0076] Furthermore, in a specific embodiment, after the quay crane assembly is hoisted onto the pre-laid track at the final assembly station, relevant data needs to be measured, the deviation data needs to be adjusted, and after meeting the requirements, baffles need to be welded on the track to prevent the wheels from rolling.

[0077] In the description of the embodiments of the present application, unless otherwise expressly specified or limited, technical terms such as "installed," "connected," "connected," and "fixed" should be understood in a broad sense. For example, they can refer to fixed connections, detachable connections, or integration; mechanical connections or electrical connections; direct connections or indirect connections through an intermediate medium; internal connections between two components or interactions between two components. Those skilled in the art can understand the specific meanings of the above terms in the embodiments of the present application based on specific circumstances.

[0078] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some or all of the technical features therein. These modifications or replacements do not deviate the essence of the corresponding technical solutions from the scope of the technical solutions of the embodiments of the present application, and they should all be included in the scope of the claims and specification of the present application. In particular, as long as there is no structural conflict, the various technical features mentioned in the various embodiments can be combined in any way. The present application is not limited to the specific embodiments disclosed herein, but includes all technical solutions that fall within the scope of the claims.

Claims

1. A quay crane assembly transport device, characterized in that: include: A transport unit having a load-bearing surface at the upper portion and rollers at the lower portion; a first fixing device, disposed on the carrying surface, extending in the width direction of the transport unit in the assembled state, and having a first fixing portion, wherein two or more quay crane assemblies to be transported are fixed to the first fixing device via the first fixing portion, and the two or more quay crane assemblies after being fixed are arranged at intervals along the extension direction of the first fixing device; as well as The second fixing device is arranged on the upper surface of the adjacent two-bank bridge assemblies and has second fixing parts at both ends. The adjacent two-bank bridge assemblies are fixedly connected to the second fixing device through the second fixing parts.

2. The quay crane assembly transport device according to claim 1, characterized in that: The first fixing portion is an elongated hole formed on the first fixing device.

3. The quay crane assembly transport device according to claim 1, characterized in that: The second fixing portion is an elongated hole formed on the second fixing device.

4. The quay crane assembly transport device according to claim 3, characterized in that: Partitions are provided in the second fixing device, and the second fixing portion is provided between the partitions.

5. The quay crane assembly transport device according to claim 1, characterized in that: The first fixing device includes wing portions protruding toward both sides of the transport unit, and the first fixing portions are respectively arranged on the wing portions. The quay crane assembly transport device is used to transport a pair of quay crane assemblies, and the quay crane assemblies on both sides are respectively fixed on the two wing portions.

6. The quay crane assembly transport device according to claim 1, characterized in that: The quay crane assembly transport device includes a pair of transport units, a pair of first fixing devices and a pair of second fixing devices. The pair of first fixing devices are respectively fixed at the lower parts of both ends of the quay crane assembly in the length direction, and the pair of second fixing devices are respectively fixed at the upper parts of both ends of the quay crane assembly in the length direction.

7. The quay crane assembly transport device according to claim 5, characterized in that: A stop portion is further provided on the wing portion, and the stop portion is arranged close to the first fixing portion.

8. The quay crane assembly transport device according to claim 7, characterized in that: A pad is also provided on the wing portion, and the pad is arranged close to the stop portion.

9. The quay crane assembly transport device according to claim 1, wherein: The quay crane assembly includes a traveling mechanism and a lower crossbeam assembly. The bottom of the traveling mechanism is fixedly connected to the first fixing device, and the top of the lower crossbeam assembly is fixedly connected to the second fixing device.

10. A quay crane assembly method, characterized in that: The steps include: Configure assembly stations and final assembly stations; Assembling the quay crane trolley traveling assembly and the quay crane lower crossbeam assembly into a quay crane assembly at the assembly station; Transporting the quay crane assembly from the assembly station to the final assembly station using the quay crane assembly transporting device according to any one of claims 1 to 9; At the final assembly station, the quay crane assembly is hoisted onto the pre-laid track to complete the assembly of the quay crane.

11. The quay crane assembly method according to claim 10, characterized in that: Assembling the quay crane assembly at the assembly station also includes the following steps: Arrange the trolley according to design requirements; Hoist the first crossbeam onto two adjacent vehicles; Hoist the second beam onto the two first beams; Arranging supports on the second crossbeam to assemble and form a walking mechanism unit body; Arrange the relative distance between the two traveling mechanism units according to the designed trolley base distance; The lower crossbeam assembly is hoisted onto the two traveling mechanism units to complete the assembly of the quay crane assembly.