Method and system for collecting drainage outside the water diversion branch pipe of underground powerhouse
By dividing the external drainage area of the water diversion branch pipe of the underground factory into two independent areas, collecting and discharging external drainage in sections, and setting up pressure gauge and gate valves in each section, the safety hazards and unintuitive monitoring data in traditional systems are solved. The problem of this has achieved higher reliability and safety of external drainage systems.
Patent Information
- Application Number
- CN202311135604.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-09-05
- Publication Date
- 2024-11-29
- Estimated Expiration
- 2043-09-05
AI Technical Summary
The external drainage system of traditional underground factory water diversion branch pipes has safety hazards and unintuitive monitoring data, which causes the upper side walls of the factory to bear high pressure water, which poses safety risks, and local blockage of the external drainage pipe may cause the entire longitudinal drainage pipe to fail.
By dividing the external drainage area of the water diversion branch pipe into two independent areas, independent water collection pipes and external drainage pipes are set up separately, and external drainage pipes are collected and discharged in sections to ensure effective control of water pressure and drain water in each section. Pressure gauge and gate valve are installed at the pipe openings of the pipeline to realize real-time monitoring and control of external drainage pressure.
Effectively avoid the risk of failure of the entire longitudinal drainage pipe caused by local blockage of external drainage pipes, ensure the safety of the upper side walls of the factory, reduce the humidity or seepage of the side walls, improve the operating environment of the factory, and improve the external water. Intuitiveness of stress monitoring and targeted treatment measures.
Smart Images

Figure CN117090168B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a method and system for collecting drainage outside a water diversion branch pipe area of an underground powerhouse of a pumped-storage power station. Background Art
[0002] In order to ensure the safety, dryness and suitable operating environment of the upstream side wall and even the entire plant area of the underground powerhouse of the pumped-storage power station, as well as the external compressive stability of the water diversion branch pipe of the pumped-storage power station, a drainage system is usually set up in the water diversion branch pipe area of the underground powerhouse, that is, a longitudinal water collecting pipe and longitudinal angle steel are set on the outer wall of the water diversion branch pipe to collect seepage water from the surrounding rock walls in the water diversion branch pipe area and its upstream and downstream, and mountain groundwater, and discharge it to the water collection well near the construction branch hole through the water diversion branch pipe construction branch hole.
[0003] The conventionally designed underground powerhouse water diversion branch pipe external drainage system has the following problems in actual operation:
[0004] 1. There are certain safety hazards.
[0005] Due to the traditional drainage system, the longitudinal water collecting pipes and longitudinal angle steels installed on the outer wall of the water diversion branch pipe connect the upstream and downstream waterways of the entire water diversion branch pipe area, causing a large amount of internal water in the upstream waterway of the water diversion branch pipe to seep out, water infiltration from the surrounding rock walls and groundwater in the mountain, together with the water from the downstream waterway, enter the underground plant area along the longitudinal water collecting pipes and longitudinal angle steels on the outer wall of the water diversion branch pipe, and reach the upstream side wall of the plant, causing an impact on the upstream side wall of the underground plant, causing the upstream side wall of the plant to directly bear high-pressure water, which poses a safety hazard to the upstream side wall of the plant.
[0006] In addition, once the external drainage pipe is partially blocked, the entire longitudinal drainage pipe will fail, resulting in the inability to effectively control the external water pressure of the water diversion branch pipe. The water diversion branch pipe will lose its resistance to external pressure during draining and maintenance, and there will be a risk of rising groundwater levels in the factory area.
[0007] 2. The monitoring data is not intuitive and the treatment measures are not targeted enough.
[0008] Since the traditional drainage system's longitudinal water collection pipe connects the upstream and downstream of the entire water diversion branch pipe area, the data monitored by the pressure gauge installed at the water diversion branch pipe construction branch hole plug cannot accurately reflect the pressure of the respective areas upstream and downstream of the construction branch hole plug, and the treatment measures (i.e., opening the gate to release water) are not very targeted. Summary of the invention
[0009] In view of the above reasons, the purpose of the present invention is to provide a safe and reliable method for collecting drainage outside the water diversion branch pipe of an underground powerhouse, which has obvious drainage effect and strong controllability. According to the different water volumes in the upstream and downstream areas of the water diversion branch pipe, the method collects and discharges rock seepage around the water diversion branch pipe, water outside the surface of the water diversion branch pipe and groundwater in sections and sections, thus ensuring the safety of the upstream side wall of the underground powerhouse.
[0010] Another object of the present invention is to provide an underground powerhouse water diversion branch pipe external drainage collection system. The water diversion branch pipe external drainage collection system collects and discharges water in sections and sections according to the different water volumes upstream and downstream of the water diversion branch pipe area, ensuring the safety of the upstream side wall and water diversion branch pipe of the underground powerhouse.
[0011] To achieve the above-mentioned purpose, the present invention adopts the following technical scheme: a method for collecting drainage outside the water diversion branch pipe of an underground powerhouse, which divides the drainage area outside the water diversion branch pipe into an upstream drainage area and a downstream drainage area by taking the construction branch hole of the water diversion branch pipe as the boundary;
[0012] Independent water collection pipes and external drainage pipes are respectively set in the upstream drainage area and the downstream drainage area to collect rock seepage around the water diversion branch pipe, water outside the surface of the water diversion branch pipe and groundwater in sections and sections, and discharge them to the water collection well through the construction branch hole of the water diversion branch pipe.
[0013] Preferably, in the upstream drainage area, an upstream water diversion branch pipe collecting pipe and an external drainage pipe on the upstream side wall of the construction branch tunnel are arranged next to the water diversion branch pipe, and the upstream water diversion branch pipe collecting pipe is communicated with the external drainage pipe on the upstream side wall of the construction branch tunnel; in the downstream drainage area, a downstream water diversion branch pipe collecting pipe and an external drainage pipe on the downstream side wall of the construction branch tunnel are arranged next to the water diversion branch pipe, and the downstream water diversion branch pipe collecting pipe is communicated with the external drainage pipe on the downstream side wall of the construction branch tunnel.
[0014] Preferably, a pressure gauge and a gate valve are respectively provided at the pipe openings of the external drainage pipe on the upstream side wall of the construction branch hole and the external drainage pipe on the downstream side wall of the construction branch hole.
[0015] The present invention provides an underground powerhouse water diversion branch pipe external drainage collection system, which comprises a longitudinal water collecting pipe of a water diversion branch pipe upstream of a plug, an external drainage pipe of an upstream side wall of a construction branch hole, a longitudinal water collecting pipe of a water diversion branch pipe downstream, and an external drainage pipe of a downstream side wall of a construction branch hole;
[0016] The plug upstream water diversion branch pipe longitudinal water collecting pipe includes an upstream rock external drainage longitudinal water collecting pipe buried beside the upstream water diversion branch pipe and an upstream branch pipe surface external water longitudinal water collecting pipe fixed on the outer wall of the upstream water diversion branch pipe, which is used to collect external drainage in the upstream area of the water diversion branch pipe; the upstream rock external drainage longitudinal water collecting pipe and the upstream branch pipe surface external water longitudinal water collecting pipe are in communication with the external drainage pipe on the upstream side wall of the construction branch hole;
[0017] The downstream water diversion branch pipe longitudinal water collecting pipe is buried beside the downstream water diversion branch pipe and is used to collect external drainage in the downstream area of the water diversion branch pipe; the downstream water diversion branch pipe longitudinal water collecting pipe is connected to the external drainage pipe of the downstream side wall of the construction branch tunnel.
[0018] Preferably, the longitudinal water collecting pipe of the upstream water diversion branch pipe of the plug is located in the upstream water diversion branch pipe area of the water diversion branch pipe construction branch tunnel, and is parallel to the axis of the upstream water diversion branch pipe; the longitudinal water collecting pipe of the downstream water diversion branch pipe is located in the downstream water diversion branch pipe area of the construction branch tunnel, and is parallel to the axis of the downstream water diversion branch pipe.
[0019] Preferably, a pressure gauge and a gate valve are respectively provided at the pipe openings of the external drainage pipe on the upstream side wall of the construction branch hole and the external drainage pipe on the downstream side wall of the construction branch hole.
[0020] Preferably, the diameters of the longitudinal water collecting pipe of the water diversion branch pipe upstream of the plug and the external drainage pipe of the upstream side wall of the construction branch tunnel are greater than or equal to the diameters of the longitudinal water collecting pipe of the water diversion branch pipe downstream and the external drainage pipe of the downstream side wall of the construction branch tunnel.
[0021] Preferably, each of the water collecting pipes and external drainage pipes is a seamless pipe.
[0022] Compared with the traditional drainage system, the drainage collection method and system outside the water diversion branch pipe of the present invention has the following advantages:
[0023] 1. The structural layout is reasonable and the upstream side wall of the underground plant operates safely.
[0024] Since the present invention uses the construction branch hole of the water diversion branch pipe as the boundary, the external drainage area of the water diversion branch pipe is divided into an upstream drainage area and a downstream drainage area. The two drainage areas are independent of each other and do not communicate with each other. The external drainage is collected in separate areas and discharged through the construction branch holes to the collection wells outside the plugs of the construction branch holes. This effectively avoids the risk of failure of the entire longitudinal drainage pipe due to local blockage of the external drainage pipeline, thereby greatly improving the reliability and safety of the external drainage.
[0025] The external drainage collection method of the present invention effectively cuts off the high-pressure water and groundwater in the upstream waterway of the water diversion branch pipe area from entering the underground plant area along the longitudinal water collecting pipe, and impacts the upstream side wall of the underground plant, thereby preventing the upstream side wall of the plant from directly bearing the high-pressure water, ensuring the safety of the upstream side wall of the plant, reducing moisture or water seepage on the side wall of the plant, and improving the operating environment of the plant.
[0026] In addition, the present invention eliminates the drainage angle steel and annular connecting pipe on the surface of the downstream water diversion branch pipe and replaces them with longitudinal water collecting pipes, thereby preventing the groundwater in the area from entering the factory area along the drainage system on the surface of the water diversion branch pipe.
[0027] 2. External water pressure monitoring is intuitive.
[0028] The present invention designs external drainage pipes on the upstream side wall and the downstream side wall of the construction branch hole, which are respectively connected to the upstream and downstream longitudinal water collecting pipes of the water diversion branch pipes, and a pressure gauge and a gate valve are arranged at the pipe mouth, which can respectively monitor the pressure of the external drainage upstream and downstream of the water diversion branch pipe, and the safety risks of the water diversion branch pipe and the upstream side wall of the factory building can be evaluated at any time.
[0029] 3. The response to emergencies is fast and the handling measures are simple, safe and convenient.
[0030] Since the present invention collects and discharges external drainage in sections and respectively sets pressure gauges and gate valves on the upstream and downstream external drainage pipes, the gate valves corresponding to the drainage pipes in different sections can be opened at any time to relieve pressure according to the pressure conditions of the drainage pipes in each section, thereby effectively controlling the water pressure outside the water diversion branch pipes in each section and avoiding complex and technically risky engineering measures such as grouting upstream of the side wall of the factory building to seal the groundwater after it seeps into the factory building and opening holes in the side wall for drainage.
[0031] 4. The invention has simple construction and strong operability. BRIEF DESCRIPTION OF THE DRAWINGS
[0032] Figure 1 It is a schematic diagram of the layout of the external drainage system of the underground powerhouse of a pumped storage power station;
[0033] Figure 2 It is a schematic diagram of the drainage collection system outside the water diversion branch pipe of the underground powerhouse of the present invention;
[0034] Figure 3 yes Figure 2 A partial enlarged view of part A in the middle;.
[0035] Figure 4 yes Figure 2 A partial enlarged view of part B. DETAILED DESCRIPTION
[0036] The structure and features of the present invention are described in detail below in conjunction with the accompanying drawings and embodiments. It should be noted that various modifications can be made to the embodiments disclosed herein, and therefore, the embodiments disclosed in the specification should not be regarded as limiting the present invention, but are only examples of embodiments, the purpose of which is to make the features of the present invention obvious.
[0037] Figure 1 It is a diagram of the external drainage system of the underground powerhouse of a pumped storage power station. In the figure, the figure number 1 is the upstream side wall of the underground powerhouse, the figure number 2 is the drainage gallery of the lower layer of the underground powerhouse, and the figure number 3 is a water collection well. Several water diversion branches 4 and a water diversion branch construction branch hole 5 are arranged outside the upstream side wall of the underground powerhouse. A longitudinal water collection pipe is arranged on the outer wall of the water diversion branch 4 to collect water from the water diversion branch area, the surrounding rock wall and the underground of the mountain, and the water is discharged to the water collection well 3 through the water diversion branch construction branch hole 5, the drainage maintenance channel 6, and the drainage gallery 2 of the lower layer of the underground powerhouse.
[0038] Since the upstream reinforced concrete waterway of the water diversion branch pipe 4 is long, has a large water collection volume and a rapid water flow, there is a risk that the high-pressure water from the upstream waterway and the groundwater from the mountain will be led to the upstream side wall of the factory building along the longitudinal water collection pipe and longitudinal angle steel of the water diversion steel branch pipe after the internal water seeps out. The traditional water diversion branch pipe external drainage system connects the upstream and downstream waterways of the water diversion branch pipe, so that the large amount of upstream water collected by the water diversion branch pipe will impact the upstream side wall 1 of the factory building. The upstream side wall 1 of the factory building is subjected to high-pressure water, which poses a safety risk to the upstream side wall of the factory building. Therefore, if Figure 2 As shown, the present invention adopts a strategy of collecting drainage outside the water diversion branch pipe area in sections and segments to ensure the safe operation of the upstream side wall of the underground powerhouse of the pumped storage power station and even the entire powerhouse area.
[0039] like Figure 2-Figure 4 As shown, the present invention divides the drainage area outside the water diversion branch pipe into an upstream drainage area and a downstream drainage area with the water diversion branch pipe construction branch tunnel 5 as the boundary. Accordingly, an upstream water collection device and a downstream water collection device are separately arranged outside the upstream water diversion branch pipe and the downstream water diversion branch pipe, and the upstream and downstream water collection devices are respectively connected to the drainage pipe outside the water diversion branch pipe construction branch tunnel, and the collected water is led to the water collection well outside the construction branch tunnel plug through the water diversion branch pipe construction branch tunnel.
[0040] The present invention constructs an external drainage pipe on the upstream side wall of the construction branch tunnel and an external drainage pipe on the downstream side wall of the construction branch tunnel, which are connected with an upstream water diversion branch pipe water collecting device and a downstream water diversion branch pipe water collecting device, respectively, upstream and downstream of the water diversion branch pipe construction branch tunnel to discharge water collected by the upstream water collecting device and the downstream water collecting device of the water diversion branch pipe, respectively.
[0041] Pressure gauges and gate valves are respectively installed at the pipe openings of the external drainage pipes on the upstream side wall of the construction branch tunnel and the external drainage pipes on the downstream side wall of the construction branch tunnel to evaluate the safety risks of the water diversion branch pipe and the upstream side wall of the plant at any time. Combined with the pressure conditions of the external drainage pipes in each section, the gate valves corresponding to the external drainage pipes in different sections are opened to relieve pressure during the project emptying and maintenance, and the water pressure outside the water diversion branch pipes in each section is controlled to prevent groundwater from seeping into the plant and posing a threat to the upstream side wall of the plant, thereby ensuring the safe operation of the upstream side wall of the plant and even the entire plant area.
[0042] The underground powerhouse water diversion branch pipe external drainage collection system of the present invention comprises a longitudinal water collecting pipe 8 of the water diversion branch pipe upstream of the plug, an external drainage pipe 9 on the upstream side wall of the construction branch hole, a longitudinal water collecting pipe 10 of the water diversion branch pipe downstream and an external drainage pipe 11 on the downstream side wall of the construction branch hole.
[0043] The plug upstream water diversion branch pipe longitudinal water collecting pipe 8 includes an upstream rock external drainage longitudinal water collecting pipe 81 buried beside the upstream water diversion branch pipe and an upstream branch pipe surface external water longitudinal water collecting pipe 82 fixed on the outer wall of the upstream water diversion branch pipe. The upstream rock external drainage longitudinal water collecting pipe 81 and the upstream branch pipe surface external water longitudinal water collecting pipe 82 are connected with the external drainage pipe 9 of the upstream side wall of the construction branch hole, and the external drainage collected in the upstream water diversion branch pipe area is discharged into the water collecting well through the external drainage pipe 9 of the upstream side wall of the construction branch hole.
[0044] The plug upstream water diversion branch pipe longitudinal water collecting pipe 8 is located in the upstream water diversion branch pipe area of the water diversion branch pipe construction branch tunnel, and is parallel to the axis of the upstream water diversion branch pipe 4.
[0045] Since the amount of water downstream of the water diversion branch pipe 4 is small, the downstream water diversion branch pipe longitudinal water collecting pipe 10 of the present invention is only provided with a rock external drainage longitudinal water collecting pipe buried beside the downstream water diversion branch pipe, which is used to collect rock seepage water around the downstream area of the water diversion branch pipe, water on the surface of the water diversion branch pipe and groundwater. The downstream water diversion branch pipe longitudinal water collecting pipe 10 is connected with the external drainage pipe 11 of the downstream side wall of the construction branch hole, and the collected external drainage of the downstream area is discharged into the water collecting well through the external drainage pipe 11 of the downstream side wall of the construction branch hole.
[0046] The downstream water diversion branch pipe longitudinal water collecting pipe 10 is located in the downstream water diversion branch pipe area of the construction branch tunnel and is parallel to the axis of the downstream water diversion branch pipe 4.
[0047] The pipe diameters of the water collecting pipes and external drainage pipes of the present invention must meet the drainage requirements. Usually, the pipe diameters of the longitudinal water collecting pipe 8 of the upstream water diversion branch pipe of the plug and the external drainage pipe 9 of the upstream side wall of the construction branch hole must be greater than or equal to the pipe diameters of the longitudinal water collecting pipe 10 of the downstream water diversion branch pipe and the external drainage pipe 11 of the downstream side wall of the construction branch hole. Each water collecting pipe and external drainage pipe is a seamless pipe.
[0048] In order to accurately grasp the drainage volume of the upstream and downstream areas of the water diversion branch pipe, the present invention is provided with a pressure gauge 12 and a gate valve 13 at the pipe openings of the external drainage pipes 9 and 11 of the upstream and downstream side walls of the construction branch hole, respectively, to monitor the pressure of the external drainage upstream and downstream of the water diversion branch pipe, respectively, and to assess the safety risks of the water diversion branch pipe and the upstream side wall of the factory building at any time. When the pressure of the drainage pipelines in each zone is relatively high, the gate valve on the external drainage pipe can be opened at any time to relieve the pressure, effectively controlling the water pressure outside the water diversion branch pipes in each section.
[0049] Finally, it should be noted that the above-described embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some or all of the technical features thereof may be replaced by equivalents. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the scope of the technical solutions of the embodiments of the present invention.
Claims
1. A method for collecting drainage outside the water diversion branch pipe of an underground powerhouse, characterized in that: The drainage area outside the water diversion branch pipe is divided into an upstream drainage area and a downstream drainage area with the water diversion branch pipe construction tunnel (5) as the boundary; Independent water collection pipes and external drainage pipes are respectively set in the upstream drainage area and the downstream drainage area to collect rock seepage around the water diversion branch pipe, water outside the surface of the water diversion branch pipe and groundwater in sections and sections, and drain them to the water collection well through the construction branch hole of the water diversion branch pipe; In the upstream drainage area, an upstream water diversion branch pipe water collecting pipe and an external drainage pipe on the upstream side wall of the construction branch hole are arranged beside the water diversion branch pipe, and the upstream water diversion branch pipe water collecting pipe is connected with the external drainage pipe on the upstream side wall of the construction branch hole; In the downstream drainage area, a downstream water diversion branch pipe water collecting pipe and an external drainage pipe on the downstream side wall of the construction branch tunnel are arranged beside the water diversion branch pipe, and the downstream water diversion branch pipe water collecting pipe is communicated with the external drainage pipe on the downstream side wall of the construction branch tunnel.
2. The method for collecting drainage from the water diversion branch pipe of an underground powerhouse according to claim 1, characterized in that: A pressure gauge and a gate valve are respectively arranged at the pipe openings of the external drainage pipe of the upstream side wall of the construction branch hole and the external drainage pipe of the downstream side wall of the construction branch hole.
3. An underground powerhouse water diversion branch pipe external drainage collection system, characterized by: It includes a longitudinal water collecting pipe for the water diversion branch pipe upstream of the plug, an external drainage pipe on the upstream side wall of the construction branch hole, a longitudinal water collecting pipe for the water diversion branch pipe downstream, and an external drainage pipe on the downstream side wall of the construction branch hole; The plug upstream water diversion branch pipe longitudinal water collecting pipe includes an upstream rock external drainage longitudinal water collecting pipe buried beside the upstream water diversion branch pipe and an upstream branch pipe surface external water longitudinal water collecting pipe fixed on the outer wall of the upstream water diversion branch pipe, which is used to collect external drainage in the upstream area of the water diversion branch pipe; the upstream rock external drainage longitudinal water collecting pipe and the upstream branch pipe surface external water longitudinal water collecting pipe are in communication with the external drainage pipe on the upstream side wall of the construction branch hole; The downstream water diversion branch pipe longitudinal water collecting pipe is buried beside the downstream water diversion branch pipe and is used to collect external drainage in the downstream area of the water diversion branch pipe; the downstream water diversion branch pipe longitudinal water collecting pipe is connected to the external drainage pipe of the downstream side wall of the construction branch tunnel.
4. The underground powerhouse water diversion branch pipe external drainage collection system according to claim 3 is characterized by: The longitudinal water collecting pipe of the upstream water diversion branch pipe of the plug is located in the upstream water diversion branch pipe area of the water diversion branch pipe construction branch tunnel, and is parallel to the axis of the upstream water diversion branch pipe; The downstream water diversion branch pipe longitudinal water collecting pipe is located in the downstream water diversion branch pipe area of the construction branch tunnel and is parallel to the axis of the downstream water diversion branch pipe.
5. The underground powerhouse water diversion branch pipe external drainage collection system according to claim 4 is characterized by: A pressure gauge and a gate valve are respectively arranged at the pipe openings of the external drainage pipe of the upstream side wall of the construction branch hole and the external drainage pipe of the downstream side wall of the construction branch hole.
6. The underground powerhouse water diversion branch pipe external drainage collection system according to claim 5, characterized in that: The diameters of the longitudinal water collecting pipe of the water diversion branch pipe upstream of the plug and the external drainage pipe of the upstream side wall of the construction branch tunnel must be greater than or equal to the diameters of the longitudinal water collecting pipe of the water diversion branch pipe downstream and the external drainage pipe of the downstream side wall of the construction branch tunnel.
7. The underground powerhouse water diversion branch pipe external drainage collection system according to claim 6, characterized in that: The water collecting pipes and external drainage pipes are all seamless pipes.
Citation Information
Patent Citations
Combined arrangement structure of construction adit, pressure pipeline drainage gallery and access hole
CN215669375U