A flexible sling hoisting device and method for bridge construction

By using a flexible sling hoisting device that combines rigid and flexible components, the problems of wear and instability during the hoisting of box girders with wire ropes were solved, thus improving the safety and efficiency of bridge construction.

CN117142317BActive Publication Date: 2026-11-17中铁大桥局上海工程有限公司 +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202310859978.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-07-13
Publication Date
2026-11-17
Estimated Expiration
2043-07-13

AI Technical Summary

Technical Problem

During bridge construction, steel wire ropes can easily wear down box girders when hoisting them, and the hoisting process is unstable, posing safety risks.

Method used

A flexible sling hoisting device is adopted, including a sling assembly, a clamping assembly, a telescopic assembly, an adjusting assembly, and a retraction assembly. By combining rigid and flexible elements, the contact area with the box girder is increased, the sling length is automatically adjusted, swaying is prevented, and safety is improved.

Benefits of technology

This enhances the safety and efficiency of box girder hoisting, reduces the operational difficulty for construction personnel, lowers safety hazards, and ensures a smooth and reliable hoisting process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117142317B_ABST
    Figure CN117142317B_ABST
Patent Text Reader

Abstract

This invention relates to the field of bridge construction technology, specifically to a flexible sling hoisting device for bridge construction. The device includes a base assembly, a clamping assembly, a telescopic assembly, an adjusting assembly, and a retracting assembly. Two sets of base assemblies and clamping assemblies are arranged in parallel, with each clamping assembly corresponding to one base assembly. The lower ends of the two base assemblies are connected to the outwardly extending flanges at both ends of the box girder. The upper surface of the base assembly is fixedly connected to the lower part of the clamping assembly. The middle part of the sling passes through the upper part of the base assembly and the middle part of the clamping assembly, and is movably connected to the clamping assembly via a pulley structure. The telescopic assembly is fixedly positioned between the two base assemblies. The lower end of the adjusting assembly is fixedly connected to the upper surface of the telescopic assembly. The upper end of the adjusting assembly is connected to the retracting assembly via a spring. The retracting assembly is connected to the upper end of the sling via Velcro. This device facilitates on-site construction and can improve the safety and efficiency of box girder hoisting.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of bridge construction technology, specifically to a flexible sling hoisting device and method for bridge construction. Background Technology

[0002] In bridge construction, beam structure hoisting is often used for positioning and installation, such as... Figure 1 As shown, taking box girder 7 as an example, box girder 7 can generally be prefabricated in the factory according to the needs of bridge construction and then transported to the site for installation. The girder transport vehicle transports box girder 7 to the working position. After the bridge erecting machine 8, together with the wire rope, supports the two ends of box girder 7 at the lifting points at both ends, it is then hoisted onto the cap beam by the bridge erecting machine 8. The span of the box girder is generally about 20-40m, and its self-weight is relatively large. After the wire rope passes through the bottom of box girder 7 from top to bottom, it is not convenient for construction personnel to operate. During the hoisting process, the wire rope is in direct contact with box girder 7, which can easily cause damage to box girder 7 itself. The wire rope and box girder 7 are prone to wear during the hoisting process, and the suspension of box girder 7 is unstable during the hoisting process, resulting in a high safety risk.

[0003] Therefore, the present invention provides a flexible sling hoisting device and method for bridge construction to solve the above problems. Summary of the Invention

[0004] To address the aforementioned problems, this invention provides a flexible sling hoisting device and method for bridge construction, which facilitates on-site construction and improves the safety and efficiency of box girder hoisting.

[0005] A flexible sling hoisting device for bridge construction uses a sling to hoist box girders. It includes a sling assembly, a clamping assembly, a telescopic assembly, an adjusting assembly, and a retracting assembly. Two sets of sling assemblies and clamping assemblies are arranged in parallel, with each clamping assembly corresponding to one sling assembly. The lower ends of the two sling assemblies are connected to the outwardly extending flanges at both ends of the box girder. The upper surface of the sling assembly is fixedly connected to the lower part of the clamping assembly. The middle part of the sling passes through the upper part of the sling assembly and the middle part of the clamping assembly, and is movably connected to the clamping assembly via a pulley structure. The telescopic assembly is fixedly positioned between the two sling assemblies, with both ends fixedly connected to adjacent sides of the two sling assemblies. The lower end of the adjusting assembly is fixedly connected to the upper surface of the telescopic assembly, and the upper end of the adjusting assembly is connected to the retracting assembly via a spring. The retracting assembly is connected to the upper end of the sling via Velcro.

[0006] Preferably, the lifting bracket assembly includes a lifting member, a sliding member, and a hook. One end of the lifting member has a groove, and a strip-shaped groove extends outward from one side of the groove. One end of the sliding member has a slider that extends through the strip-shaped groove to the outside of the lifting member. The lifting member and the sliding member are slidably connected via the slider and the strip-shaped groove. Two hooks are provided, one vertically fixed to the upper part of the lifting member, and the other vertically fixed to the upper part of the sliding member. The clamping assembly includes three vertically arranged clamping units: clamping unit one, clamping unit two, and clamping unit three. Clamping unit one is fixedly located on the side of the hook on the lifting member near the sliding member. Clamping units two and three are respectively fixedly located on both sides of the hook on the sliding member. Clamping unit two cooperates with clamping unit three and rotates synchronously with clamping unit three.

[0007] Preferably, each clamping unit includes a connecting seat, a second motor, a first gear, a second gear, a first pulley, a second pulley, and a pressure sensor; a groove is provided at one end of the connecting seat, the pressure sensor is located on the upper part of the groove, and the signal of the pressure sensor is fed back to the second motor; the output shaft of the second motor is fixedly connected to the first gear and the first pulley respectively, and a rotating shaft is rotatably provided at the upper end of the connecting seat, with the second gear and the second pulley fixedly connected to the rotating shaft respectively; the first gear meshes with the second gear, and the first pulley engages with the second pulley.

[0008] Preferably, the telescopic assembly includes telescopic plates, movable plates, and telescopic rods; four telescopic plates are provided, two sets of two telescopic plates are provided, and the two sets of telescopic plates are respectively provided on the upper and lower sides of the movable plate. Two fixing holes are provided through each telescopic plate, and the four fixing holes on the two sets of telescopic plates are respectively aligned vertically; two movable plates are provided, and two movable slots are provided through each movable plate, with the fixing holes corresponding vertically to the movable slots; six telescopic rods are provided, with two telescopic rods fixedly provided between adjacent sides of two sets of two telescopic plates, and two telescopic rods fixedly provided between adjacent sides of two movable plates.

[0009] Preferably, the telescopic assembly further includes a traction electromagnet, and four traction electromagnets are provided, each traction electromagnet corresponding to each fixing hole. The lower end of the traction electromagnet is provided with an outwardly extending flange edge that is fixedly connected to the lower surface of the telescopic plate located on the lower side. The upper end of the traction electromagnet can extend to the top of the telescopic plate located on the upper side, and a traction spring is provided at the upper end of the traction electromagnet.

[0010] Preferably, the positioning assembly includes a housing, a fourth motor, a transmission wheel set, a rotating shaft, a third gear, and a sliding plate; the rotating shaft is rotatably connected to the housing, and the third gear is fixedly installed at both ends of the rotating shaft, and the rotating shaft is fixedly connected to the upper part of the transmission wheel set; the sliding plate is slidably connected to the housing, and two racks are installed on the side of the sliding plate near the transmission wheel set, and the two racks mesh with the third gear respectively.

[0011] Preferably, the fastening assembly includes a connecting ring, Velcro, and connecting blocks; two connecting blocks are fixedly sleeved on the connecting ring, and the two connecting blocks are symmetrically arranged on the connecting ring; four Velcro are provided, two of which are set as a group, and a total of two groups are provided, with each group of Velcro positioned between two connecting blocks.

[0012] Preferably, the suspension bracket assembly further includes a clamping structure, wherein two clamping structures are provided and arranged symmetrically. One of the clamping structures is fixedly connected to the bottom of the suspension member away from the sliding member, and the other is fixedly connected to the bottom of the sliding member away from the suspension member. The clamping structures abut against the flanges on both sides of the box girder.

[0013] Preferably, a first hook and a second hook are respectively provided at both ends of the sling, the middle part of the sling passes between the first pulley and the second pulley, and multiple hanging rings are fixedly provided on the sling, with the multiple hanging rings located between the gathering assembly and the second hook.

[0014] The present invention also provides a method for lifting flexible slings for bridge construction using the above-mentioned flexible sling lifting device, comprising the following steps:

[0015] S1: Hook the first and second hooks onto the lifting hooks of the bridge erecting machine, adjust the positioning components to raise the gathering components to the lowest point, and use the bridge erecting machine to move the flexible sling hoisting device for bridge construction to a suitable position above the box girder.

[0016] S2: Activate the telescopic assembly to move one set of hanging brackets, causing the two sets of hanging brackets to move in opposite directions until both sets of hanging brackets are close to both ends of the box girder; turn on the switch of the traction electromagnet to clamp the telescopic plate and the moving plate.

[0017] S3: Start the lifting bracket assembly to move the sliding part away from the lifting part. At the same time, adjust the lifting hook height of the bridge erecting machine to a suitable position. Clamping unit one, two and three are linked to adjust the lifting straps until the width of the box girder is adapted between the two clamping structures. The lifting straps of the first lifting buckle and the clamping assembly are in the pulled-in state. Adjust the elongation of the clamping structure to adapt to the height of the two flanges of the box girder.

[0018] S4: Check the length of the sling between the gathering assembly and the second hook at this time. If the length is too long, select a suitable lifting ring and attach the lifting ring to the lifting hook of the bridge erecting machine.

[0019] S5: Activate the adjustment component to raise the slide plate until the gathering component adapts to the height of the two slings, and connect the gathering component to the slings;

[0020] S6: Start the bridge erecting machine and, according to the hoisting construction requirements, use the flexible sling hoisting device for bridge construction to hoist the box girder to the appropriate position.

[0021] Compared with the prior art, the beneficial effects of the present invention are:

[0022] This invention provides a flexible sling hoisting device for bridge construction. Taking a box girder as an example, the device uses rigid components for the lifting base assembly, clamping assembly, and telescopic assembly. During hoisting, this flexible sling hoisting device not only increases the contact area with the box girder, making the box girder less susceptible to damage, but also facilitates on-site construction by construction personnel. The device is also reusable. Flexible components are used in the positioning assembly, sling, and retraction assembly. The sling can automatically adjust to a suitable length according to the dimensions of the box girder under the action of the clamping assembly, reducing the need for personnel intervention. The retraction assembly can change shape according to actual needs during hoisting to prevent the sling from swaying and reduce safety hazards. The positioning assembly and retraction assembly are connected by springs, which improves the applicability of the retraction assembly's function in retracting the sling during hoisting.

[0023] The flexible sling hoisting method for bridge construction described in this invention uses a bridge erecting machine to hoist box girders using the aforementioned flexible sling hoisting device. Compared with traditional hoisting methods, this flexible sling hoisting method for bridge construction is simple to operate, safe to construct, and can hoist box girders stably, thereby improving the safety and efficiency of box girder hoisting. Attached Figure Description

[0024] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, for those skilled in the art, other drawings can be obtained based on these drawings without creative effort.

[0025] Figure 1 This is a schematic diagram of a bridge erecting machine hoisting a box girder structure in the existing technology;

[0026] Figure 2 This is a schematic diagram of the structure used in the connection of the present invention with a box girder;

[0027] Figure 3 This is a partial exploded view of the hanging bracket assembly and clamping assembly according to an embodiment of the present invention;

[0028] Figure 4 This is a front view cross-sectional structural diagram of the connection between the hanging bracket assembly and the clamping assembly in an embodiment of the present invention;

[0029] Figure 5 This is an exploded structural diagram of the telescopic component according to an embodiment of the present invention;

[0030] Figure 6This is a schematic cross-sectional view of the telescopic component in an embodiment of the present invention;

[0031] Figure 7 This is a cross-sectional schematic diagram of the positioning component according to an embodiment of the present invention;

[0032] Figure 8 This is a schematic diagram of the convergence component structure according to an embodiment of the present invention.

[0033] Explanation of reference numerals in the attached figures:

[0034] 1. Lifting bracket assembly; 11. Lifting component; 12. Sliding component; 121. Sliding block; 13. Clamping structure; 131. Fixed box; 132. Moving block; 133. Adjusting gear; 134. Adjusting motor; 14. Machine base; 141. First motor; 15. First lead screw; 16. Lifting hook; 2. Clamping assembly; 21. Connecting seat; 211. Slide groove; 22. Second motor; 23. First gear; 24. Second gear; 25. First pulley; 26. Second pulley; 27. Pressure sensor; 3. Telescopic assembly; 31. Telescopic plate; 311. Fixing hole; 32. Moving plate; 321. Moving groove; 3 3. Third motor; 34. Traction block; 35. Second lead screw; 36. Traction electromagnet; 37. Telescopic rod; 4. Adjustment assembly; 41. Housing; 42. Fourth motor; 43. Transmission wheel set; 431. Driving gear; 432. Transmission belt; 433. Driven gear; 44. Rotating shaft; 45. Third gear; 46. Slide plate; 461. Rack; 47. Spring; 5. Converging assembly; 51. Connecting ring; 52. Fixing component; 53. Velcro; 54. Connecting block; 541. Slide rod; 6. Sling; 61. First lifting buckle; 62. Second lifting buckle; 63. Lifting ring; 7. Box girder; 8. Bridge erecting machine. Detailed Implementation

[0035] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0036] In the following description of the invention, it should be noted that the terms "upper," "lower," "left," "right," "inner," and "outer," etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings, and are only for the convenience of describing the invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation or be constructed and operated in a specific orientation. The term "connection" simply indicates a connection between devices and has no special meaning.

[0037] For specific embodiments, please refer to Figures 2-8 A flexible sling hoisting device for bridge construction is disclosed, used for hoisting box girder 7. The hoisting is achieved using a sling 6. The device includes a lifting base assembly 1, a clamping assembly 2, a telescopic assembly 3, an adjusting assembly 4, and a retracting assembly 5. Two sets of lifting base assemblies 1 are arranged in parallel, with their lower ends connected to the outwardly extending flanges at both ends of the box girder 7. The clamping assembly 2 is positioned above the lifting base assembly 1, with its lower part fixedly connected to the upper surface of the lifting base assembly 1. The middle portion of the sling 6 passes through the upper part of the lifting base assembly 1 and the middle of the clamping assembly 2, and then connects to the clamping assembly 2. The belt is connected by a pulley structure; two sets of clamping components 2 are provided, each set of clamping components 2 corresponds to each set of hanging base components, and are used to adjust the sling 6; the telescopic component 3 is fixedly set in the middle of the two sets of hanging base components 1, and both ends of the telescopic component 3 are fixedly connected to the adjacent side of the two sets of hanging base components 1 respectively; the adjustment component 4 is set on the telescopic component 3, the lower end of the adjustment component 4 is fixedly connected to the upper surface of the telescopic component 3, and the upper end of the adjustment component 4 is connected to the tightening component 5 through a spring 47. The tightening component 5 is connected to the upper end of the sling 6 through Velcro 53.

[0038] Two slings 6 are provided, each corresponding to one of the two sets of lifting base assemblies 1 and one of the two sets of clamping assemblies 2. The slings 6 can be flexible. The two ends of the slings 6 are respectively provided with a first buckle 61 and a second buckle 62. The two ends of the slings 6 extend in the left and right directions, passing through the middle of the clamping assembly 2 and the upper part of the lifting base assembly 1, and then passing through the gathering assembly 5 from bottom to top. The first buckle 61 and the second buckle 62 are both above the gathering assembly 5. Multiple lifting rings 63 are fixedly provided on the slings 6. The multiple lifting rings 63 are located between the second buckle 62 and the gathering assembly 5. The lifting rings 63 at different positions can be selected according to the unused length of the slings 6 above the gathering assembly 5 to prevent the box girder 7 from swaying during hoisting due to the excessive length of the slings 6, thereby improving construction efficiency and reducing safety hazards.

[0039] The lifting bracket assembly 1 includes a lifting member 11, a sliding member 12, a clamping structure 13, a base 14, a first lead screw 15, and a hook 16. One end of the lifting member 11 has a groove, and a strip-shaped groove extends outward from one side of the groove. The base 14 is fixedly mounted on the side of the lifting member 11 with the strip-shaped groove. A first motor 141 is mounted at one end of the base 14. Both ends of the first lead screw 15 are rotatably connected to the base 14, and the end of the first lead screw 15 near the first motor 141 is fixedly connected to the output shaft of the first motor 141. The sliding member 12 is inserted into the lifting member 11. A slider 121 is provided at one end of the lifting member 11. The slider 121 extends through the strip groove to the outside of the lifting member 11. The first lead screw 15 passes through the slider 121 and is threadedly connected to the slider 121. The lifting member 11 and the sliding member 12 are slidably connected to the strip groove through the slider 121. Two hooks 16 are provided. One hook 16 is vertically set on the upper part of the lifting member 11 and is fixedly connected to the upper surface of the lifting member 11. The other hook 16 is vertically set on the upper part of the sliding member 12 and is fixedly connected to the upper surface of the sliding member 12. The two ends of the sling 6 extend through the two hooks 16 in the left and right directions, respectively.

[0040] The clamping structure 13 can be height adjusted via a gear and rack structure to accommodate box girders 7 of different sizes. Two clamping structures 13 are provided, symmetrically arranged. One is fixedly connected to the bottom end of the lifting member 11 away from the sliding member 12, and the other is fixedly connected to the bottom end of the sliding member 12 away from the lifting member 11. The clamping structure 13 abuts against the flanges on both sides of the box girder 7. The clamping structure 13 includes a fixed housing 131, a moving block 132, an adjusting gear 133, and an adjusting motor 134. The upper end of the fixed housing 131 is fixedly connected to the bottom of the lifting member 11 or the sliding member 12. The lower end of 31 is inserted into the movable block 132. An adjustment motor 134 is fixedly installed on one side of the lower part of the fixed box 131. The lower part of the fixed box 131 is rotatably connected to the adjustment gear 133. The output shaft of the adjustment motor 134 is fixedly connected to the adjustment gear 133. A mounting groove is opened at the upper end of the movable block 132. A fixed rack is fixedly installed in the mounting groove. The fixed rack meshes with the adjustment gear 133 to realize the telescopic function of the clamping structure 13. The lower end of the movable block 132 extends into a boss in the left or right direction. The top of the boss abuts against the bottom of the flanges on both sides of the box beam 7. The two clamping structures 13 cooperate to realize the clamping function of the box beam 7.

[0041] The clamping assembly 2 is provided in two sets, each set of clamping assembly 2 includes three clamping units: clamping unit one, clamping unit two, and clamping unit three; each clamping unit includes a connecting seat 21, a second motor 22, a first gear 23, a second gear 24, a first pulley 25, a second pulley 26, and a pressure sensor 27; clamping unit one is located on the upper part of the lifting member 11, and is located on the side of the hook 16 on the lifting member 11 near the sliding member 12. Clamping units two and three are both located on the upper part of the sliding member 12, and are respectively located on both sides of the hook 16 on the sliding member 12. Clamping unit two is used in conjunction with clamping unit three and rotates synchronously with clamping unit three. This can improve the adjustment efficiency of the sling 6. Clamping units one, two and three detect the state of the sling 6 through pressure sensor 27. When the device is in use, the two ends of the sling 6 are respectively hooked on the lifting hook of the bridge erecting machine 8, the sling 6 is tightened, and the upper end of the sling 6 is in contact with the pressure sensor 27. The pressure sensor 27 can detect the pressure generated by the sling 6. When the adjustment seat assembly 1 is adapted to the width of the box girder 7, the lifting hook of the bridge erecting machine 8 is lowered, the sling 6 is loosened, the pressure sensor 27 detects the pressure change, and clamping units one, two and three adjust the sling 6 in linkage until the pressure sensor 27 detects that the pressure generated by the sling 6 is maintained within the specified value range.

[0042] The connecting seat 21 is fixedly connected to the upper surface of the lifting member 11 or the sliding member 12. The connection method can be screw connection. One end of the connecting seat 21 is provided with a sliding groove 211, which corresponds to the height of the hook 16, so that the sling 6 can pass through the hook 16 and then through the clamping assembly 2. The second motor 22 is fixedly connected to the lower end of one side of the connecting seat 21. The output shaft of the second motor 22 passes through the connecting seat 21 and is fixedly connected to the first gear 23 and the first pulley 25 respectively. The upper end of the connecting seat 21 is provided with a rotating shaft, which is rotatably connected to the connecting seat 21. The second gear 24 and the second pulley 26 are fixedly connected to the rotating shaft. The first gear 23 and the second gear 24 mesh, and the first pulley 25 and the second pulley 26 cooperate. The middle part of the sling 6 passes through the gap between the first pulley 25 and the second pulley 26 through the sliding groove 211. The middle part of the sling 6 is connected to the first pulley 25 and the second pulley 26 through friction transmission, which is used to adjust the tension or relaxation of the sling 6.

[0043] The pressure sensor 27 is located on the upper part of the slide groove 211. When the sling 6 is taut, the pressure remains within a certain range; when the sling 6 is slack, the pressure decreases. The state of the sling 6 can be sensed by the pressure change. In other embodiments, the pressure sensor 27 can be located on the lower part of the slide groove 211. When the sling 6 is taut, the sling 6 can be designed not to contact the pressure sensor 27. When the sling 6 is slack, the sling 6 presses on the pressure sensor 27 under the action of gravity, and the pressure increases. The signal from the pressure sensor 27 is fed back to the second motor 22 for starting or stopping the second motor 22. The pressure sensor 27 can detect the pressure generated on the sling 6 passing through the slide groove 211. The pressure value generated can be displayed as either relaxed or tense before the sling 6 passes through the clamping unit. When the device is in use, the pressure sensor 27 can detect the pressure generated by the sling 6 passing through the slide 211. If the pressure is less than the specified range, the second motor 22 can be started. The second motor 22 drives the first gear 23 and the first pulley 25 to rotate. The first gear 23 drives the second gear 24 to rotate. The second gear 24 drives the second pulley 26 to rotate through the shaft. The first pulley 25 and the second pulley 26 cooperate with the sling 6 to adjust the sling 6 until the pressure generated by the sling 6 is within the specified range.

[0044] The telescopic assembly 3 is used to adjust the distance between the two sets of hanging seat assemblies 1, and includes a telescopic plate 31, a movable plate 32, a third motor 33, a traction block 34, a second lead screw 35, a traction electromagnet 36, and a telescopic rod 37. Four telescopic plates 31 are provided, with two sets arranged in a left-right direction. The two sets of telescopic plates 31 are respectively arranged parallel to each other on the upper and lower sides of the movable plate 32. One end of each set of telescopic plates 31 is fixedly connected to the side of one of the hanging seat assemblies 1 without the base 14, and the other end is slidably connected to one end of the movable plate 32. The other end of the movable plate 32 is fixedly connected to the side of the other hanging seat assembly 1 with the base 14. Two plates 32 are provided. Both of the two telescopic plates 31 and the two movable plates 32 can be made of strip plates. One end of one telescopic plate 31 or movable plate 32 is fixedly connected to the hanging member 11, and the other end of the other telescopic plate 31 or movable plate 32 is fixedly connected to the sliding member 12. Six telescopic rods 37 are provided. Two telescopic rods 37 are fixedly provided between adjacent sides of two telescopic plates 31 in each group. The two telescopic rods 37 are located at both ends of the telescopic plate 31. Two telescopic rods 37 are fixedly provided between adjacent sides of two movable plates 32. The two telescopic rods 37 are located at both ends of the movable plate 32. This is used to realize the synchronous contraction or extension of the telescopic plates 31 and movable plates 32 with the hanging base assembly 1.

[0045] The two telescopic rods 37 located between the two movable plates 32 are fixedly connected to the two ends of the second lead screw 35 on their adjacent sides. Two fixing holes 311 are provided through each telescopic plate 31 from top to bottom, and the four fixing holes 311 on the two sets of telescopic plates 31 correspond one-to-one. A moving groove 321 is provided through each movable plate 32 from top to bottom for traction electromagnet 36. The moving groove 321 corresponds vertically to the fixing holes 311. The third motor 33 is mounted on the telescopic rod 37 on the movable plate 32 at the end away from the telescopic plate 31 and is fixedly connected to the third motor 33. One end of the second lead screw 35 is fixedly connected to the output shaft of the third motor 33, and the other end passes through the traction block 34 and is rotatably connected to the telescopic rod 37 at the other end of the movable plate 32. The traction block 34 is located between each set of two telescopic plates 31, and its upper and lower ends are fixedly connected to the ends of the two sets of telescopic plates 31 closest to the movable plate 32, respectively. The guide block 34 cooperates with the second lead screw 35 to enable the moving plate 32 to slide along the telescopic plate 31. Four traction electromagnets 36 are provided, each corresponding to a fixed hole 311. The lower end of the traction electromagnet 36 is provided with an outwardly extending flange edge, which is fixedly connected to the lower surface of the telescopic plate 31 located on the lower side. The upper end of the traction electromagnet 36 can extend to the upper surface of the telescopic plate 31 located on the upper side. A traction spring is provided at the upper end of the traction electromagnet 36. When the traction electromagnet 36 is energized, the upper end of the traction electromagnet 36 abuts against the upper surface of the telescopic plate 31 located on the upper side, clamping the telescopic plate 31 and the moving plate 32, which can enhance the support force between the two sets of hanging seat assemblies 1. When the traction electromagnet 36 is de-energized, under the action of the traction spring above the traction electromagnet 36, the traction electromagnet 36 returns to its initial state, allowing the moving plate 32 to slide along the direction of the second lead screw 35 under the drive of the third motor 33.

[0046] The adjusting component 4 can adjust the height of the retracting component 5 according to the length of the sling 6 used for hoisting, so that it can retract the sling 6. It includes a housing 41, a fourth motor 42, a transmission wheel set 43, a rotating shaft 44, a third gear 45, a sliding plate 46, and a spring 47. The housing 41 is set above the telescopic plate 31 at the upper end of the moving plate 32. The bottom of the housing 41 is fixedly connected to the upper surface of the telescopic plate 31, and the connection can be made by screws. The fourth motor 42 is set outside one end of the housing 41. The output shaft of the fourth motor 42 is fixedly connected to the lower part of the transmission wheel set 43, and the upper part of the transmission wheel set 43 is fixedly connected to the rotating shaft 44. The rotating shaft 44 passes through both ends of the housing 41 and is rotatably connected to the housing 41. The third gear 45 is fixedly set at both ends of the rotating shaft 44, and the third gear 45 is located inside the housing 41.

[0047] The transmission wheel assembly 43 includes a driving gear 431, a transmission belt 432, and a driven gear 433. The driving gear 431 is fixedly connected to the output shaft of the fourth motor 42, and the driven gear 433 is fixedly connected to the rotating shaft 44. The transmission belt 432 meshes with the driving gear 431 and the driven gear 433 through a toothed structure. The slide plate 46 is disposed inside the housing 41 and is slidably connected to the housing 41. Two racks 461 are disposed on the side of the slide plate 46 near the transmission wheel assembly 43. The two racks 461 are located at both ends of the slide plate 46 and mesh with two third gears 45 respectively. The upper end of the slide plate 46 is arranged from top to bottom. Two placement slots are provided, and two springs 47 are respectively installed outside the two placement slots. One end of the spring 47 is fixedly connected to the upper end of the slide plate 46, and the other end is fixedly connected to the gathering assembly 5. This can improve the adaptability of the gathering assembly 5 to changes in the sling 6 during the hoisting process. When the device is in use, the construction personnel start the fourth motor 42, which drives the transmission wheel set 43 to rotate. The transmission wheel set 43 drives the rotating shaft 44 and the third gear 45 to rotate. The third gear 45 meshes with the rack 461 to drive the slide plate 46 upward, which drives the spring 47 to move. After the gathering assembly 5 is raised to the appropriate position, the fourth motor 42 is turned off.

[0048] The tightening assembly 5 is used to tighten the sling 6 and prevent the sling 6 from swaying during hoisting. It includes a connecting ring 51, fasteners 52, Velcro 53, and connecting blocks 54. The connecting ring 51 can be made into a closed ring using a flexible belt. The fasteners 52 and connecting blocks 54 are fixedly fitted onto the connecting ring 51. Two connecting blocks 54 are provided, symmetrically arranged on the connecting ring 51. The lower end of the connecting block 54 is fixedly connected to the spring 47. A sliding rod 541 is provided at the lower end of the connecting block 54 and is located in the spring 47. The lower end of the sliding rod 541 is slidably connected to the placement groove on the slide plate 46 to support the spring 47. Four fasteners 52 and four Velcro 53 are provided. Two of the four fasteners 52 and four Velcro 53 are set as a group, for a total of two groups. Each group of fasteners 52 and each group of Velcro 53 has two fasteners 52 and two groups of Velcro 53. 3 are all set between two connecting blocks 54. Each set of fasteners 52 and each set of hook and loop fasteners 53 corresponds to one of the slings 6. The hook and loop fasteners 53 are set on the fasteners 52. The fasteners 52 have a through-hole. The connecting ring 51 is located on one side of the through-hole. The hook and loop fasteners 53 are placed on the other side of the through-hole. One end of the hook and loop fasteners 53 is a fixed end, which is fixedly connected to the fasteners 52. The other end is a movable end. The movable end extends outward to form an annular hole and then passes through the through-hole. One side of the hook and loop fasteners 53 is round hair and the other side is barbed hair. The two sides cooperate to tighten the slings 6. When the device is used, the operator passes one end of the sling 6 from bottom to top through the annular hole on the hook and loop fasteners 53. After adjusting the movable end of the hook and loop fasteners 53 to a suitable position, it is connected by the round hair and barbed hair. One set of hook and loop fasteners 53 corresponds to the two ends of one sling 6.

[0049] The present invention also provides a method for lifting a bridge using a flexible sling, comprising the following steps:

[0050] S1: Hook the first hook 61 and the second hook 62 onto the lifting hook of the bridge erecting machine 8 respectively, adjust the positioning component 4 so that the gathering component 5 is at the lowest end, and use the bridge erecting machine 8 to transport the flexible sling hoisting device for bridge construction to a suitable position above the box girder 7.

[0051] S2: Start the third motor 33. The output shaft of the third motor 33 drives the second lead screw 35 to rotate. The second lead screw 35 cooperates with the traction block 34. The traction block 34 drives another set of hanging seat assemblies 1 to move, so that the two sets of hanging seat assemblies 1 move in opposite directions until both sets of hanging seat assemblies 1 are close to both ends of the box girder 7; turn on the switch of the traction electromagnet 36 to clamp the telescopic plate 31 and the moving plate 32.

[0052] S3: Start the first motor 141. The output shaft of the first motor 141 drives the first lead screw 15 to rotate, causing the sliding part 12 to move away from the lifting part 11. At the same time, adjust the lifting hook height of the bridge erecting machine 8 to a suitable position. The clamping units one, two, and three adjust the lifting strap 6 in a coordinated manner until the width between the two clamping structures 13 is adapted to the width of the box girder 7, so that the first lifting buckle 61 and the lifting strap 6 between the clamping units one, two, and three are in a taut state. Adjust the position of the fixed box 131 and the moving block 132 to adapt to the height of the flanges on both sides of the box girder 7, and connect the lifting seat assembly 1 to the box girder 7.

[0053] S4: Check the length of the sling 6 located between the gathering assembly 5 and the second hook 62. If the length is too long, select a suitable lifting ring 63 and attach the lifting ring 63 to the lifting hook of the bridge erecting machine 8.

[0054] S5: Start the fourth motor 42. The output shaft of the fourth motor 42 drives the drive gear 431 to rotate. The drive gear 431 and the driven gear 433 mesh through the tooth structure on the transmission belt 432, so that the driven gear 433 drives the rotating shaft 44 and the third gear 45 fixed on the rotating shaft 44 to rotate. The third gear 45 meshes with the rack 461, so that the slide plate 46 rises until the gathering assembly 5 adapts to the height of the two suspenders 6. Then, the two sets of Velcro 53 are wrapped and gathered one by one with the two ends of the two suspenders 6 respectively.

[0055] S6: Start the bridge erecting machine 8, and according to the hoisting construction requirements, use the flexible sling hoisting device for bridge construction to hoist the box girder 7 to the appropriate position.

[0056] This invention provides a flexible sling hoisting device for bridge construction. Taking a box girder as an example, the device uses rigid components for the lifting base assembly, clamping assembly, and telescopic assembly. During hoisting, this flexible sling hoisting device not only increases the contact area with the box girder, making the box girder less susceptible to damage, but also facilitates on-site construction by construction personnel. The device is also reusable. Flexible components are used in the positioning assembly, sling, and retraction assembly. The sling can automatically adjust to a suitable length according to the dimensions of the box girder under the action of the clamping assembly, reducing the need for personnel intervention. The retraction assembly can change shape according to actual needs during hoisting to prevent the sling from swaying and reduce safety hazards. The positioning assembly and retraction assembly are connected by springs, which improves the applicability of the retraction assembly's function in retracting the sling during hoisting.

[0057] The flexible sling hoisting method for bridge construction described in this invention uses a bridge erecting machine to hoist box girders using the aforementioned flexible sling hoisting device. Compared with traditional hoisting methods, this flexible sling hoisting method for bridge construction is simple to operate, safe to construct, and can hoist box girders stably, thereby improving the safety and efficiency of box girder hoisting.

[0058] Although embodiments of the invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the invention, the scope of which is defined by the appended claims and their equivalents.

Claims

1. A flexible sling hoisting device for bridge construction, which realizes box girder (7) hoisting construction by using a sling (6), characterized in that, It includes a suspension seat assembly (1), a clamping assembly (2), a telescopic assembly (3), an adjustment assembly (4), and a retraction assembly (5); the suspension seat assembly (1) and the clamping assembly (2) are arranged in two parallel sets, with each set of clamping assemblies (2) corresponding to each set of suspension seat assemblies (1). The lower ends of the two sets of suspension seat assemblies (1) are respectively connected to the outwardly extending flanges at both ends of the box girder (7). The upper surface of the suspension seat assembly (1) is fixedly connected to the lower part of the clamping assembly (2). The middle part of the sling (6) passes through the upper part of the suspension seat assembly (1) and the clamping assembly (2). After the middle of the clamping component (2), it is movably connected to the clamping component (2) through a pulley structure; the telescopic component (3) is fixedly set in the middle of the two sets of hanging base components (1), and the two ends of the telescopic component (3) are respectively fixedly connected to the adjacent side of the two sets of hanging base components (1); the lower end of the adjusting component (4) is fixedly connected to the upper surface of the telescopic component (3), and the upper end of the adjusting component (4) is connected to the gathering component (5) through a spring (47), and the gathering component (5) is connected to the upper end of the sling (6) through Velcro (53); The lifting bracket assembly (1) includes a lifting member (11), a sliding member (12), and a hook (16). One end of the lifting member (11) is provided with a groove, and a strip groove extends outward from one side of the groove. One end of the sliding member (12) is provided with a slider (121), which extends through the strip groove to the outside of the lifting member (11). The lifting member (11) and the sliding member (12) are slidably connected to the strip groove through the slider (121). Two hooks (16) are provided, one of which is vertically fixed. On the upper part of the lifting component (11), another hook (16) is vertically fixed on the upper part of the sliding component (12); the clamping assembly (2) includes three vertically arranged clamping units: clamping unit one, clamping unit two and clamping unit three. Clamping unit one is fixedly arranged on the side of the hook (16) on the lifting component (11) near the sliding component (12). Clamping units two and three are respectively fixedly arranged on both sides of the hook (16) on the sliding component (12). Clamping unit two cooperates with clamping unit three and rotates synchronously with clamping unit three. Each clamping unit includes a connecting seat (21), a second motor (22), a first gear (23), a second gear (24), a first pulley (25), a second pulley (26), and a pressure sensor (27); a sliding groove (211) is provided at one end of the connecting seat (21), and the pressure sensor (27) is provided on the upper part of the sliding groove (211). The signal of the pressure sensor (27) is fed back to the second motor (22); the output shaft of the second motor (22) is fixedly connected to the first gear (23) and the first pulley (25), and a rotating shaft is rotatably provided on the upper end of the connecting seat (21). The second gear (24) and the second pulley (26) are fixedly connected to the rotating shaft respectively; the first gear (23) meshes with the second gear (24), and the first pulley (25) cooperates with the second pulley (26); The sling (6) is provided with a first buckle (61) and a second buckle (62) at both ends. The middle part of the sling (6) passes between the first pulley (25) and the second pulley (26). Multiple hanging rings (63) are fixedly provided on the sling (6). The multiple hanging rings (63) are located between the gathering assembly (5) and the second buckle (62).

2. The flexible sling hoisting device for bridge construction according to claim 1, characterized in that, The telescopic assembly (3) includes telescopic plates (31), movable plates (32), and telescopic rods (37). Four telescopic plates (31) are provided, with two telescopic plates (31) forming a group, and two groups are provided in total. The two groups of telescopic plates (31) are respectively provided on the upper and lower sides of the movable plate (32). Two fixing holes (311) are provided through each telescopic plate (31), and the four fixing holes (311) on the two groups of telescopic plates (31) correspond one-to-one vertically. Two movable plates (32) are provided, with two movable slots (321) provided through each movable plate (32), and the fixing holes (311) correspond vertically to the movable slots (321). Six telescopic rods (37) are provided, with two telescopic rods (37) fixedly provided between adjacent sides of two groups of two telescopic plates (31) and two telescopic rods (37) fixedly provided between adjacent sides of two movable plates (32).

3. The flexible sling hoisting device for bridge construction according to claim 2, characterized in that, The telescopic assembly (3) also includes a traction electromagnet (36). Four traction electromagnets (36) are provided, and each traction electromagnet (36) corresponds to each fixing hole (311). The lower end of the traction electromagnet (36) is provided with an outwardly extending flange edge that is fixedly connected to the lower surface of the telescopic plate (31) located on the lower side. The upper end of the traction electromagnet (36) can extend to the upper side of the telescopic plate (31). A traction spring is provided at the upper end of the traction electromagnet (36).

4. The flexible sling hoisting device for bridge construction according to claim 3, characterized in that, The adjustment assembly (4) includes a housing (41), a fourth motor (42), a transmission wheel set (43), a rotating shaft (44), a third gear (45), and a sliding plate (46). The rotating shaft (44) is rotatably connected to the housing (41), and the third gear (45) is fixedly installed at both ends of the rotating shaft (44). The rotating shaft (44) is fixedly connected to the upper part of the transmission wheel set (43). The sliding plate (46) is slidably connected to the housing (41). Two racks (461) are installed on the side of the sliding plate (46) near the transmission wheel set (43), and the two racks (461) mesh with the third gear (45) respectively.

5. A flexible sling hoisting device for bridge construction according to claim 4, characterized in that, The gathering component (5) includes a connecting ring (51), Velcro (53) and connecting blocks (54); the connecting ring (51) is fixedly fitted with connecting blocks (54), and two connecting blocks (54) are provided, with the two connecting blocks (54) symmetrically arranged on the connecting ring (51); four Velcro (53) are provided, with two of them set as a group, for a total of two groups, and each group of Velcro (53) is set between two connecting blocks (54).

6. A flexible sling hoisting device for bridge construction according to claim 5, characterized in that, The hanging bracket assembly (1) also includes a clamping structure. Two clamping structures are provided and arranged symmetrically. One of them is fixedly connected to the bottom of the hanging member (11) away from the sliding member (12), and the other is fixedly connected to the bottom of the sliding member (12) away from the hanging member (11). The clamping structure abuts against the flanges on both sides of the box beam (7).

7. A method for hoisting a flexible sling for bridge construction, applied to the hoisting device for the flexible sling for bridge construction according to claim 6, characterized in that, Includes the following steps: S1: Hook the first hook (61) and the second hook (62) onto the lifting hook of the bridge erecting machine (8) respectively, adjust the adjustment component (4) so ​​that the gathering component (5) rises to the lowest point, and use the bridge erecting machine (8) to move the flexible sling hoisting device for bridge construction to a suitable position above the box girder (7). S2: Start the telescopic assembly (3) so that the moving plate (32) drives a set of hanging bracket assemblies (1) to move, so that the two sets of hanging bracket assemblies (1) move in opposite directions until both sets of hanging bracket assemblies (1) are close to both ends of the box girder (7); turn on the switch of the traction electromagnet (36) so that it clamps the telescopic plate (31) and the moving plate (32). S3: Start the lifting seat assembly (1) to move the sliding part (12) away from the lifting part (11), and at the same time adjust the lifting hook height of the bridge erecting machine (8) to a suitable position. The clamping unit 1, 2 and 3 are linked to adjust the lifting strap (6) until the width of the box girder (7) is adapted between the two clamping structures, so that the first lifting buckle (61) and the lifting strap (6) of the clamping assembly (2) are in a taut state. Adjust the elongation of the clamping structure to adapt to the height of the flanges on both sides of the box girder (7). S4: Check the length of the sling (6) between the gathering assembly (5) and the second hook (62). If the length is too long, select a suitable lifting ring (63) and attach the lifting ring (63) to the lifting hook of the bridge erecting machine (8). S5: Activate the adjustment component (4) to raise the slide plate (46) until the gathering component (5) adapts to the height of the two slings (6), and then connect the gathering component (5) to the slings (6); S6: Start the bridge erecting machine (8), and according to the hoisting construction requirements, use the flexible sling hoisting device for bridge construction to hoist the box girder (7) to the appropriate position.