Balanced lifting technology of assembled steel-concrete components

By combining a multi-ring beam lifting device and a right-angle leveling frame, the problem of maintaining balance during the hoisting of precast components was solved, achieving efficient and safe installation of precast components and improving construction efficiency and accuracy.

CN117262979BActive Publication Date: 2024-11-05CHINA NAT CHEM ENG NO 14 CONSTR
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202311238164.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-09-25
Publication Date
2024-11-05
Estimated Expiration
2043-09-25

AI Technical Summary

Technical Problem

The existing precast components are difficult to keep balanced during hoisting, which makes installation and positioning difficult, increases workload, and can easily damage the precast components and wall structure, reducing installation efficiency and accuracy.

Method used

A combination of multi-ring beam lifting equipment, manual hoist, and right-angle leveling frame is used. By adjusting the length of the slings and the lifting angle, the precast steel-concrete components are kept horizontal and stable during the lifting process. Multiple lifting points and calibration planes are used to eliminate swaying and achieve balanced lifting.

Benefits of technology

It improved the safety and efficiency of hoisting, reduced construction costs, accelerated the construction progress, and reduced damage and safety risks caused by uneven installation surfaces of prefabricated components.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117262979B_ABST
    Figure CN117262979B_ABST
Patent Text Reader

Abstract

The invention discloses a balanced lifting process for assembled steel-concrete components. A beam hanger with a plurality of lifting rings is used, and a 2+1+2 hook arrangement is adopted. The balance can be adjusted and the components are not easy to shake or shift by themselves. Five manual hoists are used to adjust the height, so that the installation surface of the assembled steel-concrete components can be in a horizontal state, so that the force on the steel-concrete components is more uniform during lifting. The side vertical surface of the assembled steel-concrete components is fitted to a calibration plane, so that the shaking caused by lifting inertia or wind force can be eliminated, and whether the installation surface is shifted can be checked, so that the assembled steel-concrete components are always kept at the best installation angle during lifting. In this way, the assembled steel-concrete components can be quickly installed and positioned after being lowered, so that the workload is reduced, the construction efficiency is improved, and the installation damage and safety problems caused by the uneven installation surface of the prefabricated components can be avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of prefabricated component hoisting, and in particular relates to a balanced hoisting process for assembled steel-concrete components. Background Art

[0002] With the rapid development of the construction industry, the traditional extensive construction method has restricted the development of the construction industry due to problems such as large resource consumption, long construction period, concentrated labor, serious environmental pollution, and low degree of industrialization. The traditional construction method is in urgent need of transformation and upgrading. As a new building form in the construction industry in recent years, prefabricated housing has shown significant advantages in construction and use. It not only has the advantages of energy saving and environmental protection, but also can meet the differentiated requirements of the industrial development of residential projects. Accelerating the rapid development of prefabricated residential buildings is an important development trend of the future construction industry.

[0003] The use of assembled composite floor slabs, beams, columns, shear walls, stairs and other steel-concrete components fully integrates the advantages of prefabrication and cast-in-place, and has the advantages of good integrity, high rigidity, cost savings, less pollution, convenient construction and high efficiency. It is just a bit troublesome when hoisting. When hoisting existing prefabricated parts, it is necessary to first slowly lift one end of the prefabricated part placed horizontally on the ground through two steel wire ropes, one long and one short, and then lift the other end of the prefabricated part off the ground, so that the prefabricated part is in an inclined state and transported to the installation position. However, it is difficult to keep the prefabricated part in a balanced state. The hoisting angle of the prefabricated part is not consistent with the actual installation angle, so that the installation positioning of the prefabricated part often requires manual continuous adjustment, which requires a relatively high level of workers' operating skills and increases the workload. In addition, the uneven installation surface is easy to damage the contact point between the prefabricated part and the wall structure, reducing the efficiency and accuracy of the installation. Summary of the invention

[0004] In order to solve the above problems, the present invention discloses a balanced lifting process for assembled steel-concrete components, which increases lifting points and adjusts the length of lifting slings, and can complete the balanced lifting of different prefabricated steel-concrete components, thereby improving the safety lifting level, reducing construction costs, and accelerating construction progress.

[0005] To achieve the above object, the technical solution of the present invention is as follows:

[0006] The balanced lifting process of assembled steel-concrete components includes the following steps:

[0007] (1) The prefabricated steel-concrete components are placed horizontally on the ground;

[0008] (2) Making a crossbeam hanger, with multiple upper hanging rings on both ends of the crossbeam hanger and multiple lower hanging rings on the bottom of the crossbeam hanger;

[0009] (3) The tower crane hooks the upper lifting ring of the beam hoist through two steel wire ropes, and the lower lifting ring hooks the prefabricated steel-concrete member through five manual hoists, one of which hooks the middle of the prefabricated steel-concrete member, and the other four manual hoists hook the auxiliary lifting devices reserved at the four corners of the prefabricated steel-concrete member;

[0010] (4) After the prefabricated steel-concrete component is lifted 200 to 300 mm off the ground, stop lifting, adjust the manual hoist, and adjust the installation surface of the prefabricated steel-concrete component to a horizontal position;

[0011] (5) After the inspection is complete, the formal lifting process can be carried out. After the lifting is stable, the boom is rotated at a constant speed. After approaching the building, the lifting worker uses a hook to catch the cable wind rope, pulls the prefabricated steel-concrete component above the installation position and slowly lowers it to stop above the initial installation position;

[0012] (6) A right-angle leveling frame is installed on the outside of the wall installation surface. The calibration plane of the right-angle leveling frame is perpendicular to the installation surface and is located on the vertical plane of the installation surface.

[0013] (7) Lower the side of the prefabricated steel-concrete component along the calibration plane and finally place it flat on the installation surface. Check the elevation and plane position deviation of the prefabricated steel-concrete component and start installation after checking that everything is correct;

[0014] (8) Prefabricated steel-concrete components are welded and fixed to beam stirrups.

[0015] As an improvement of the present invention, the beam hanger in step (2) includes a middle beam, 2-4 upper hanging rings are provided above both ends of the beam, a lower hanging ring is provided in the middle below the beam, and 3-6 lower hanging rings are provided at both ends.

[0016] As an improvement of the present invention, the lifting hook used for lifting in step (3) is provided with a one-way anti-slip device.

[0017] As an improvement of the present invention, the auxiliary hanger in step (3) includes an embedded sleeve, a mounting bolt, a mounting block, and a lifting ring, two of the embedded sleeves are embedded in the assembled steel-concrete member, the mounting bolt passes through the mounting block to connect the embedded sleeves, and the lifting ring is arranged directly above the mounting block.

[0018] As an improvement of the present invention, after the installation surface of the prefabricated steel-concrete member is adjusted to a horizontal position in step (4), a level meter is used to check the horizontal and vertical levels of the installation surface, and the parts that do not meet the standards need to be readjusted.

[0019] As an improvement of the present invention, a safety strap is added before the formal lifting in step (5).

[0020] As an improvement of the present invention, the right-angle leveling frame in step (6) is a triangular structure consisting of a calibration plane, a mounting plane and an oblique support frame, the mounting plane is fixed to the outside of the wall by bolts, and the calibration plane is perpendicular to the mounting surface and is located on a vertical plane of the mounting surface.

[0021] As an improvement of the present invention, the inspection in step (7) includes: checking the plane position of the prefabricated steel-concrete component with a positioning control line, and then confirming it with a hanging hammer and a lower part; and re-measuring the elevation of the prefabricated steel-concrete component with a level.

[0022] The beneficial effects of the present invention are:

[0023] (1) By using a beam hoist with multiple lifting rings + five manual hoists + the installation surface of the prefabricated steel-concrete component being perpendicular to the side, the prefabricated steel-concrete component can always be kept at the optimal installation angle. In this way, it can be quickly installed and positioned after being lowered, reducing the workload and improving construction efficiency. At the same time, it can also avoid installation damage and safety problems caused by uneven installation surfaces of prefabricated components.

[0024] (2) The lower lifting ring adopts a 2+1+2 hook arrangement, which can make the steel-concrete component more evenly stressed during lifting and is less likely to shake or shift after adjusting the balance.

[0025] (3) There are multiple lower lifting rings at both ends, which can be changed with the span of the steel-concrete member and have a wide range of applications.

[0026] (4) Adjust the five manual hoists so that the installation surface of the prefabricated steel-concrete components (composite floor slabs, beams and columns, shear walls, and stairs) is in a horizontal state. When it reaches the installation position, it falls down along the calibration plane of the right-angle leveling frame to eliminate the shaking caused by the lifting inertia or wind force. Also check whether the installation surface has shifted (if there is an oblique gap between the side of the prefabricated steel-concrete component and the calibration plane, it means that the installation surface is no longer horizontal) to ensure that the concrete component always maintains the optimal installation angle. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a schematic diagram of the structure of the present invention.

[0028] Figure 2 This is a detailed installation diagram of the present invention.

[0029] Figure 3 It is a schematic diagram of the auxiliary lifting device described in the present invention.

[0030] List of Figure Symbols:

[0031] 1. Prefabricated steel-concrete member, 2. Beam hanger, 3. Upper lifting ring, 4. Lower lifting ring, 5. Tower crane, 6. Steel wire rope, 7. Manual hoist, 8. Auxiliary hanger, 9. Installation surface of prefabricated steel-concrete member, 10. Right-angle leveling frame, 11. Calibration plane, 12. Installation plane, 13. Oblique support frame, 14. Vertical surface of installation surface, 15. Beam, 16. Embedded sleeve, 17. Installation bolt, 18. Installation block, 19. Lifting ring. Implementation

[0032] The present invention will be further explained below in conjunction with the accompanying drawings and specific embodiments. It should be understood that the following specific embodiments are only used to illustrate the present invention and are not used to limit the scope of the present invention.

[0033] As shown in the figure, a balanced lifting process for assembled steel-concrete components according to the present invention comprises the following steps:

[0034] (1) The assembled steel-concrete member 1 is placed horizontally on the ground;

[0035] (2) Making a beam hanger 2, including a middle beam 15, with a plurality of upper hanging rings 3 above both ends of the beam 15, a lower hanging ring 4 in the middle below the beam 15, and 3-6 lower hanging rings 4 at both ends;

[0036] (3) The tower crane 5 hooks the upper lifting ring 3 of the beam hanger through two steel wire ropes 6, and the lower lifting ring 4 hooks the assembled steel-concrete component 1 through five manual hoists 7, one of which hooks the middle of the assembled steel-concrete component 1, and the other four manual hoists hook the auxiliary lifting devices 8 reserved at the four corners of the assembled steel-concrete component 1;

[0037] (4) After the prefabricated steel-concrete component 1 is lifted 200 to 300 mm off the ground, the lifting is stopped, and the manual hoist 7 is adjusted to adjust the installation surface 9 of the prefabricated steel-concrete component to a horizontal position;

[0038] (5) After the inspection is complete, the formal lifting process can be carried out. After the lifting is stable, the boom is rotated at a constant speed. After approaching the building, the lifting worker uses a hook to catch the cable wind rope, pulls the prefabricated steel-concrete component 1 above the installation position and slowly lowers it to stop above the preliminary installation position;

[0039] (6) A right-angle leveling frame 10 is arranged outside the wall mounting surface, and a calibration plane 11 of the right-angle leveling frame is perpendicular to the mounting surface and is located on a vertical plane 14 of the mounting surface.

[0040] (7) Lower the side of the prefabricated steel-concrete component along the calibration plane 11, and finally let it fall flat on the installation surface 9, and check the elevation and plane position deviation of the prefabricated steel-concrete component 1. After checking that they are correct, start installation;

[0041] (8) The prefabricated steel-concrete member 1 is welded and fixed to the beam stirrups.

[0042] The most critical part of the balanced hoisting process of the assembled steel-concrete component described in the present invention is to adjust the installation surface 9 of the assembled steel-concrete component to a horizontal position, that is, to balance the hoisting without shaking or shifting. Therefore, the present invention adopts three technical points to achieve this purpose:

[0043] 1. A beam sling 2 is used instead of the previous square sling. The force is directly borne by a beam, and the structure is simple and strong with less shaking. There are multiple lower lifting rings 4 under the beam 15. When in use, five-point hooks are used, one of which is in the middle and the other four are on both sides. A 2+1+2 hook arrangement is used, which can make the force on the steel-concrete component more uniform during hoisting, and it is not easy to shake or shift after adjusting the balance.

[0044] There are multiple lower hanging rings under the crossbeam 15, which can be changed with the span of the steel-concrete member and have a wide range of applications.

[0045] 2. The lifting rope is replaced by a manual hoist 7, the length of which can be adjusted. The present invention can adjust five manual hoists at the same time, so that the installation surface 9 of the assembled steel-concrete member (composite floor, beam column, shear wall, staircase) can be in a horizontal state.

[0046] 3. A triangular right-angle leveling frame 10 is arranged outside the wall installation surface. The right-angle leveling frame 10 includes a calibration plane 11, a mounting plane 12 and an oblique support frame 13. The mounting plane 12 is fixed to the outside of the wall by bolts. The calibration plane 11 is perpendicular to the mounting surface 9 and is above the vertical plane 14 of the mounting surface (on the same plane). When the assembled steel-concrete component 1 is hoisted above the installation position, the side of the assembled steel-concrete component falls down along the calibration plane 11 of the right-angle leveling frame. Figure 2 As shown, it can eliminate the shaking caused by lifting inertia or wind, and check whether the installation surface has shifted (if there is an oblique gap between the side of the prefabricated steel-concrete component and the calibration plane, it means that the installation surface is no longer horizontal), ensuring that the steel-concrete component is always maintained at the best installation angle, so that it can be quickly installed and positioned after being lowered, reducing workload and improving construction efficiency. At the same time, it can also avoid installation damage and safety problems caused by uneven installation surface of prefabricated parts.

[0047] The present invention is based on the fact that the steel-concrete member is prefabricated and uniformly manufactured in the factory, and the installation surface 9 is perpendicular to the vertical surface 14 of the side at 90° (plus or minus no more than 1°), and its quality can be guaranteed. Therefore, the vertical surface 14 of the side can be used to verify the horizontal state of the installation surface 9 during installation.

[0048] Technical and economic indicators of steel-concrete components:

[0049] Flatness of adjacent components: the flatness of the plate end surface is not greater than 2mm; the exposed part of the beam and plate bottom surface is not greater than 1mm, and the non-exposed part is not greater than 2mm;

[0050] Component inclination: beam no more than 2mm;

[0051] Component elevation: The bottom or top surface of beams, columns, walls and slabs shall be controlled within ±2mm;

[0052] Component shelving length: beams and plates controlled within ±3mm;

[0053] The center line of the component shall not exceed 5mm from the axis position of the foundation, the vertical component shall not exceed 3mm, and the horizontal component shall not exceed 2mm.

[0054] The invention provides a one-way anti-dropping device on the lifting hook for lifting, thereby ensuring that the hook will not be detached, and the operation is convenient and the safety is high.

[0055] After the installation surface 9 of the assembled steel-concrete member in step (4) of the present invention is adjusted to a horizontal position, a level meter can be used to check the horizontal and vertical levels of the installation surface. Parts that do not meet the standards need to be readjusted by a manual hoist.

[0056] Add safety straps before lifting steel-concrete components to ensure safety.

[0057] The auxiliary lifting device 8 in step (3) of the present invention includes a pre-buried sleeve 16, a mounting bolt 17, a mounting block 18, and a lifting ring 19. Figure 3 As shown, each corner of the steel-concrete component has two embedded sleeves 16 embedded in the assembled steel-concrete component (the steel-concrete component is too heavy, and one embedded sleeve 16 may not be able to bear it, so two are used), and the lifting ring 19 is arranged directly above the mounting block 18. Before lifting, the bolt 17 is installed to pass through the mounting block 18 to connect the embedded sleeve 16, and wooden blocks and plastic pads are placed in the middle. The hook under the manual hoist hooks the lifting ring 19 for lifting, which can avoid damage to the component during the lifting process.

[0058] The inspection in step (7) of the present invention comprises: checking the plane position of the prefabricated steel-concrete component with a positioning control line, and then confirming it with a hanging hammer and a lower part; and re-measuring the elevation of the prefabricated steel-concrete component with a level.

[0059] Based on the traditional lifting of assembled steel-concrete components, the present invention makes feasibility transformation on the traditional lifting device, develops and adopts streamlined balanced lifting operation, improves construction quality, efficiency and progress, reduces the risk of high-altitude operations, shortens the construction period by about 5%, and saves 10% of the cost; and the present invention can also complete the balanced lifting of different prefabricated steel-concrete components by adding lifting points and adjusting the length of the lifting slings, making it easier to achieve accurate, efficient and safe lifting of assembled structures.

[0060] It should be noted that the above content only illustrates the technical idea of ​​the present invention and cannot be used to limit the protection scope of the present invention. For ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the present invention. These improvements and modifications all fall within the protection scope of the claims of the present invention.

Claims

1. The balanced lifting process of assembled steel-concrete components is characterized by: The following steps are involved: (1) The prefabricated steel-concrete components are placed horizontally on the ground; (2) Making a crossbeam hanger, with multiple upper hanging rings on both ends of the crossbeam hanger and multiple lower hanging rings on the bottom of the crossbeam hanger; (3) The tower crane hooks the upper lifting ring of the beam hoist through two steel wire ropes, and the lower lifting ring hooks the prefabricated steel-concrete member through five manual hoists, one of which hooks the middle of the prefabricated steel-concrete member, and the other four manual hoists hook the auxiliary lifting devices reserved at the four corners of the prefabricated steel-concrete member; (4) After the prefabricated steel-concrete component is lifted 200 to 300 mm off the ground, stop lifting, adjust the manual hoist, and adjust the installation surface of the prefabricated steel-concrete component to a horizontal position; (5) After the inspection is complete, the formal lifting process can be carried out. After the lifting is stable, the boom is rotated at a constant speed. After approaching the building, the lifting worker uses a hook to catch the cable wind rope, pulls the prefabricated steel-concrete component above the installation position and slowly lowers it to stop above the initial installation position; (6) A right-angle leveling frame is installed on the outside of the wall installation surface. The calibration plane of the right-angle leveling frame is perpendicular to the installation surface and is located on the vertical plane of the installation surface. (7) Lower the side of the prefabricated steel-concrete component along the calibration plane and finally let it fall flat on the installation surface. Check the elevation and plane position deviation of the prefabricated steel-concrete component and start installation after checking that everything is correct. (8) Prefabricated steel-concrete components are welded and fixed to beam stirrups.

2. The balanced hoisting process for assembled steel-concrete components according to claim 1 is characterized in that: The beam hanger in step (2) includes a middle beam, 2-4 upper lifting rings above both ends of the beam, a lower lifting ring in the middle below the beam, and 3-6 lower lifting rings at both ends.

3. The balanced hoisting process for assembled steel-concrete components according to claim 1 is characterized in that: The lifting hook used for lifting in step (3) is provided with a one-way anti-slip device.

4. The balanced hoisting process for assembled steel-concrete components according to claim 1 is characterized in that: The auxiliary lifting device in step (3) comprises an embedded sleeve, a mounting bolt, a mounting block, and a lifting ring. Two embedded sleeves are embedded in the assembled steel-concrete member. The mounting bolt passes through the mounting block to connect the embedded sleeves. The lifting ring is arranged directly above the mounting block.

5. The balanced hoisting process for assembled steel-concrete components according to claim 1 is characterized in that: After the installation surface of the prefabricated steel-concrete member is adjusted to a horizontal position in step (4), a level meter is used to check the horizontal and vertical levels of the installation surface, and any parts that do not meet the standards need to be readjusted.

6. The balanced hoisting process for assembled steel-concrete components according to claim 1 is characterized in that: Add safety straps before formal lifting in step (5).

7. The balanced hoisting process for assembled steel-concrete components according to claim 1 is characterized in that: The right-angle leveling frame in step (6) is a triangular structure consisting of a calibration plane, a mounting plane and an oblique support frame. The mounting plane is fixed to the outside of the wall by bolts. The calibration plane is perpendicular to the mounting surface and is located on the vertical plane of the mounting surface.

8. The balanced hoisting process for assembled steel-concrete components according to claim 1 is characterized in that: The inspection in step (7) includes: checking the plane position of the prefabricated steel-concrete component with a positioning control line, and then confirming it with a hanging hammer and a lower part; and re-measuring the elevation of the prefabricated steel-concrete component with a level.