New energy and energy storage joint operation control method and system for improving new energy consumption
Through the joint operation control method of new energy and energy storage, the output power of energy storage power stations is adjusted, and the grid dispatch difficulties caused by the intermittent and volatility of new energy generation is solved, and the prediction of the joint power of new energy and energy storage and new energy power is realized. Consistency improves the ability to absorb new energy.
Patent Information
- Application Number
- CN202311338538.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-10-16
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2043-10-16
AI Technical Summary
The intermittent and volatility of new energy power generation lead to difficulties in grid scheduling and operation, and the existing technology is difficult to keep the actual power of new energy consistent with the predicted results, affecting the stability of the power grid and the ability to absorb new energy.
A joint operation control method for new energy and energy storage is adopted. By determining the power prediction range for different periods of time, the output power of energy storage power stations is adjusted to ensure that the combined power of new energy and energy storage is consistent with the new energy power forecast, and the priority order is Ultra-short-term, short-term and medium-term power forecast.
Without losing new energy power and not exceeding the power and power of energy storage power stations, maintain the consistent forecast of new energy and energy storage with new energy power to the greatest extent, improve the consumption capacity of new energy, and improve the power grid's new energy Access and Scheduling.
Smart Images

Figure CN117394400B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to new energy and energy storage control technology for power systems, and specifically to a new energy and energy storage joint operation control method and system for improving new energy consumption. Background Art
[0002] Improving the utilization of renewable resources is the development trend of the power industry. New energy represented by wind power and photovoltaic power has become the fastest growing renewable resource. With the continuous increase in the proportion of new energy power generation, in order to improve the stability of the power grid and assist in the consumption of new energy, most provinces and cities in China currently require a certain proportion of energy storage power stations to be built in conjunction with new energy power generation such as wind power and photovoltaic power. The most important factor affecting the consumption of new energy is the intermittent and volatile nature of new energy. This will lead to inaccurate prediction of new energy power and bring difficulties to the dispatching and operation of the power grid. According to relevant regulations, the power dispatching agency shall conduct statistics and assessment on the power forecast results of wind power and photovoltaic new energy on a daily basis, and the assessment content includes medium-term forecast, day-ahead forecast and ultra-short-term forecast. Medium-term forecast refers to the prediction of the power generation of new energy power plants from 0:00 the next day to the next 240 hours, day-ahead forecast refers to the prediction of the power generation of new energy power plants from 0:00 the next day to 24:00, and ultra-short-term forecast refers to the prediction of the power generation of new energy power plants from 15 minutes to 4 hours in the future, with a time resolution of 15 minutes. The power forecast results during the power generation restricted period and the power forecast related system maintenance period approved by the power dispatching agency are not included in the assessment. How to make the actual power of renewable energy consistent with the forecast of renewable energy power, which is conducive to the dispatching and operation of the power grid and further improves the consumption of renewable energy, is still a technical problem that needs to be solved urgently. Summary of the invention
[0003] Technical problem to be solved by the present invention: In view of the above-mentioned problems of the prior art, a new energy and energy storage joint operation control method and system for improving the new energy consumption are provided. The present invention can make the combined power of new energy + energy storage consistent with the new energy power forecast to the greatest extent without losing the new energy power and not exceeding the power and electricity of the energy storage power station, thereby effectively improving the new energy consumption capacity.
[0004] In order to solve the above technical problems, the technical solution adopted by the present invention is:
[0005] A new energy and energy storage combined operation control method for improving new energy consumption, comprising:
[0006] S101. Determine the non - assessment range [Pcdmin, Pcdmax] for ultra - short - term power prediction, the non - assessment range [Pdmin, Pdmax] for short - term power prediction, and the non - assessment range [Pzmin, Pzmax] for medium - term power prediction at the current moment; determine the output range [Pwemin, Pwemax] of the combined operation of new energy and energy storage at the current moment according to the output Pw of the new - energy power plant and the power - storage capacity SOC of the energy - storage power station;
[0007] S102. Compare the non - assessment range [Pcdmin, Pcdmax] for ultra - short - term power prediction with the output range [Pwemin, Pwemax] of the combined operation of new energy and energy storage. If Pwemax < Pcdmin or Pwemin > Pcdmax, determine the current output power Pe of the energy - storage power station according to the output range [Pwemin, Pwemax] of the combined operation of new energy and energy storage, and end and exit; otherwise, calculate and correct the output range [P'wemin, P'wemax] of the combined operation of new energy and energy storage based on the non - assessment range [Pcdmin, Pcdmax] for ultra - short - term power prediction and the output range [Pwemin, Pwemax] of the combined operation of new energy and energy storage;
[0008] S103. Compare the non - assessment range [Pdmin, Pdmax] for short - term power prediction with the corrected output range [P'wemin, P'wemax] of the combined operation of new energy and energy storage. If P'wemax < Pdmin or P'wemin > Pdmax, determine the current output power Pe of the energy - storage power station according to the corrected output range [P'wemin, P'wemax] of the combined operation of new energy and energy storage, and end and exit; otherwise, correct the output range [P"wemin, P"wemax] of the combined operation of new energy and energy storage based on the non - assessment range [Pdmin, Pdmax] for short - term power prediction and the corrected output range [P'wemin, P'wemax] of the combined operation of new energy and energy storage;
[0009] S104. Compare the non - assessment range [Pzmin, Pzmax] for medium - term power prediction with the corrected output range [P"wemin, P"wemax] of the combined operation of new energy and energy storage. If P"wemax < Pzmin or P"wemin > Pzmax, determine the current output power Pe of the energy - storage power station according to the corrected output range [P"wemin, P"wemax] of the combined operation of new energy and energy storage, and end and exit; otherwise, determine the corrected output range [P'"wemin, P'"wemax] of the combined operation of new energy and energy storage based on the non - assessment range [Pzmin, Pzmax] for medium - term power prediction and the corrected output range [P"wemin, P"wemax] of the combined operation of new energy and energy storage;
[0010] S105, if the SOC of the energy storage power station is greater than the preset upper limit or less than the preset lower limit, the current output power Pe of the energy storage power station is determined in combination with the output range of the joint operation of the revised new energy and energy storage [P'"wemin, P'"wemax]; otherwise, the current output power Pe of the energy storage power station is determined according to the output range of the joint operation of the revised new energy and energy storage [P'"wemin, P'"wemax] and the output Pw of the new energy power plant at the current moment.
[0011] Optionally, in step S101, the calculation function expressions of the assessment-free range [Pcdmin, Pcdmax] of the ultra-short-term power forecast, the assessment-free range [Pdmin, Pdmax] of the short-term power forecast, and the assessment-free range [Pzmin, Pzmax] of the medium-term power forecast are:
[0012] Pcdmin=Pcd - (1-δcd)×Pwn,
[0013] Pcdmax=Pcd + (1-δcd)×Pwn,
[0014] In the above formula, Pcdmin and Pcdmax are the lower and upper limits of the assessment-free range of ultra-short-term power forecast, respectively; Pcd is the ultra-short-term power forecast value at the current moment; δcd is the accuracy assessment requirement for ultra-short-term power forecast of new energy power plants; and Pwn is the available capacity of new energy power plants.
[0015] Pdmin=Pd - (1-δd)×Pwn
[0016] Pdmax=Pd + (1-δd)×Pwn
[0017] In the above formula, Pdmin and Pdmax are the lower and upper limits of the assessment-free range of short-term power forecast, Pd is the short-term power forecast value at the current moment, and δd is the assessment requirement for the accuracy of short-term power forecast of new energy power plants;
[0018] Pzmin=Pz - (1-δz)×Pwn
[0019] Pzmax=Pz + (1-δz)×Pwn
[0020] In the above formula, Pzmin and Pzmax are the lower and upper limits of the assessment-free range of the medium-term power forecast, Pz is the medium-term power forecast value at the current moment, and δz is the assessment requirement for the accuracy of the medium-term power forecast of the new energy power plant.
[0021] Optionally, determining the output range [Pwemin, Pwemax] of the combined operation of new energy and energy storage at the current moment according to the output Pw of the new energy power plant and the power storage SOC of the energy storage power station in step S101 includes: judging the size of the power storage SOC of the energy storage power station. If the power storage SOC of the energy storage power station is 100%, then determine the output range [Pwemin, Pwemax] of the combined operation of new energy and energy storage at the current moment according to the following formula:
[0022] Pwemin = Pw,
[0023] Pwemax = Pw + PeN,
[0024] If the power storage SOC of the energy storage power station is between 0% and 100%, then determine the output range [Pwemin, Pwemax] of the combined operation of new energy and energy storage at the current moment according to the following formula:
[0025] Pwemin = Pw - PeN,
[0026] Pwemax = Pw + PeN,
[0027] If the power storage SOC of the energy storage power station is 0%, then determine the output range [Pwemin, Pwemax] of the combined operation of new energy and energy storage at the current moment according to the following formula:
[0028] Pwemin = Pw - PeN,
[0029] Pwemax = Pw,
[0030] Among them, Pw is the output of the new energy power plant at the current moment, and PeN is the rated power of the energy storage power station.
[0031] Optionally, determining the current output power Pe of the energy storage power station according to the output range [Pwemin, Pwemax] of the combined operation of new energy and energy storage in step S102 includes: if Pwemax < Pcdmin, determine the current output power Pe of the energy storage power station according to Pe = Pwemax - Pw; if Pwemin > Pcdmax, determine the current output power Pe of the energy storage power station according to Pe = Pwemin - Pw; the function expression for calculating and correcting the output range [P'wemin, P'wemax] of the combined operation of new energy and energy storage according to the non-assessment range [Pcdmin, Pcdmax] of the ultra-short-term power prediction and the output range [Pwemin, Pwemax] of the combined operation of new energy and energy storage in step S102 is:
[0032] P'wemin = max(Pcdmin, Pwemin),
[0033] P'wemax = min(Pcdmax, Pwemax),
[0034] In the above formula, max represents taking the maximum value, and min represents taking the minimum value.
[0035] Optionally, determining the current output power Pe of the energy storage power station according to the corrected output power range [P'wemin, P'wemax] of the combined operation of new energy and energy storage in step S103 includes: if P'wemax < Pdmin, then the current output power Pe of the energy storage power station is determined according to Pe = P'wemax - Pw; if P'wemin > Pdmax, then the current output power Pe of the energy storage power station is determined according to Pe = P'wemin - Pw; the function expression for correcting the output power range [P'wemin, P'wemax] of the combined operation of new energy and energy storage according to the non-assessment range [Pdmin, Pdmax] of short-term power prediction and the corrected output power range [P'wemin, P'wemax] of the combined operation of new energy and energy storage in step S103 is:
[0036] P"wemin = max(Pdmin, P'wemin),
[0037] P"wemax = min(Pdmax, P'wemax),
[0038] In the above formula, max represents taking the maximum value, and min represents taking the minimum value.
[0039] Optionally, determining the current output power Pe of the energy storage power station according to the corrected output power range [P"wemin, P"wemax] of the combined operation of new energy and energy storage in step S104 includes: if P"wemax < Pzmin, then the current output power Pe of the energy storage power station is determined according to Pe = P"wemax - Pw; if P"wemin > Pzmax, then the current output power Pe of the energy storage power station is determined according to Pe = P"wemin - Pw; the function expression for determining the corrected output power range [P'"wemin, P'"wemax] of the combined operation of new energy and energy storage according to the non-assessment range [Pzmin, Pzmax] of medium-term power prediction and the corrected output power range [P"wemin, P"wemax] of the combined operation of new energy and energy storage in step S104 is:
[0040] P'"wemin = max(Pzmin, P"wemin),
[0041] P'"wemax = min(Pzmax, P"wemax),
[0042] In the above formula, max represents taking the maximum value, and min represents taking the minimum value.
[0043] Optionally, determining the current output power Pe of the energy storage power station in combination with the output power range [P'"wemin, P'"wemax] of the combined operation of the corrected new energy and energy storage in step S105 includes: if the state of charge (SOC) of the energy storage power station is greater than the preset upper limit value, then determine the current output power Pe of the energy storage power station according to Pe = P'"wemax - Pw; if the state of charge (SOC) of the energy storage power station is less than the preset lower limit value, then determine the current output power Pe of the energy storage power station according to Pe = P'"wemin - Pw.
[0044] Optionally, determining the current output power Pe of the energy storage power station according to the output power range [P'"wemin, P'"wemax] of the combined operation of the corrected new energy and energy storage and the output power Pw of the new energy power generation field at the current moment in step S105 includes: if Pw > P'"wemax, then determine the current output power Pe of the energy storage power station according to Pe = P'"wemax - Pw; if Pw < P'"wemin, then determine the current output power Pe of the energy storage power station according to Pe = P'"wemin - Pw.
[0045] In addition, the present invention also provides a new energy and energy storage combined operation control system for improving new energy consumption, including a microprocessor and a memory connected to each other, and the microprocessor is programmed or configured to execute the new energy and energy storage combined operation control method for improving new energy consumption.
[0046] In addition, the present invention also provides a computer-readable storage medium, in which a computer program is stored, and the computer program is used to be programmed or configured by a microprocessor to execute the new energy and energy storage combined operation control method for improving new energy consumption.
[0047] Compared with the prior art, the present invention mainly has the following advantages: The new energy and energy storage combined operation control method for improving new energy consumption of the present invention includes adjusting the output of the energy storage power station according to the priority order of ultra-short-term power prediction, short-term power prediction, and medium-term power prediction, so that the combined power of new energy + energy storage at the current moment is maximally kept consistent with the new energy power prediction. Thus, without losing the new energy power and not exceeding the power and electricity of the energy storage power station, the combined power of new energy and energy storage can be maximally made consistent with the new energy power prediction, which helps the operation and scheduling of new energy access to the power grid, and thus effectively improves the power grid's ability to consume new energy. BRIEF DESCRIPTION OF THE DRAWINGS
[0048] Figure 1 It is a basic process schematic diagram of the method of the embodiment of the present invention. DETAILED DESCRIPTION OF THE EMBODIMENTS
[0049] As Figure 1 shown, the new energy and energy storage combined operation control method for improving new energy consumption in this embodiment includes:
[0050] S101. Determine the non - assessment range of ultra - short - term power prediction [Pcdmin, Pcdmax], the non - assessment range of short - term power prediction [Pdmin, Pdmax], and the non - assessment range of medium - term power prediction [Pzmin, Pzmax] at the current moment; determine the output power range [Pwemin, Pwemax] of the combined operation of new energy and energy storage at the current moment according to the output Pw of the new - energy power plant and the power - storage capacity SOC of the energy - storage power station;
[0051] S102. Compare the non - assessment range of ultra - short - term power prediction [Pcdmin, Pcdmax] with the output power range [Pwemin, Pwemax] of the combined operation of new energy and energy storage. If Pwemax < Pcdmin or Pwemin > Pcdmax, determine the current output power Pe of the energy - storage power station according to the output power range [Pwemin, Pwemax] of the combined operation of new energy and energy storage, and end and exit; otherwise, calculate and correct the output power range [P'wemin, P'wemax] of the combined operation of new energy and energy storage according to the non - assessment range of ultra - short - term power prediction [Pcdmin, Pcdmax] and the output power range [Pwemin, Pwemax] of the combined operation of new energy and energy storage;
[0052] S103. Compare the non - assessment range of short - term power prediction [Pdmin, Pdmax] with the corrected output power range [P'wemin, P'wemax] of the combined operation of new energy and energy storage. If P'wemax < Pdmin or P'wemin > Pdmax, determine the current output power Pe of the energy - storage power station according to the corrected output power range [P'wemin, P'wemax] of the combined operation of new energy and energy storage, and end and exit; otherwise, correct the output power range [P"wemin, P"wemax] of the combined operation of new energy and energy storage according to the non - assessment range of short - term power prediction [Pdmin, Pdmax] and the corrected output power range [P'wemin, P'wemax] of the combined operation of new energy and energy storage;
[0053] S104. Compare the non - assessment range [Pzmin, Pzmax] of the medium - term power prediction with the output range [P"wemin, P"wemax] of the corrected combined operation of new energy and energy storage. If P"wemax < Pzmin or P"wemin > Pzmax, then determine the current output power Pe of the energy storage power station according to the output range [P"wemin, P"wemax] of the corrected combined operation of new energy and energy storage, and end and exit; otherwise, determine the output range [P'"wemin, P'"wemax] of the corrected combined operation of new energy and energy storage according to the non - assessment range [Pzmin, Pzmax] of the medium - term power prediction and the output range [P"wemin, P"wemax] of the corrected combined operation of new energy and energy storage;
[0054] S105. If the state of charge (SOC) of the energy storage power station is greater than the preset upper limit value or less than the preset lower limit value, then determine the current output power Pe of the energy storage power station in combination with the output range [P'"wemin, P'"wemax] of the corrected combined operation of new energy and energy storage; otherwise, determine the current output power Pe of the energy storage power station according to the output range [P'"wemin, P'"wemax] of the corrected combined operation of new energy and energy storage and the output Pw of the new - energy power generation field at the current moment.
[0055] In this embodiment, the calculation function expressions for the non - assessment ranges [Pcdmin, Pcdmax] of the ultra - short - term power prediction, [Pdmin, Pdmax] of the short - term power prediction, and [Pzmin, Pzmax] of the medium - term power prediction in step S101 are as follows:
[0056] Pcdmin = Pcd - (1 - δcd)×Pwn,
[0057] Pcdmax = Pcd + (1 - δcd)×Pwn,
[0058] In the above formula, Pcdmin and Pcdmax are respectively the lower limit value and the upper limit value of the non - assessment range of the ultra - short - term power prediction, Pcd is the ultra - short - term power prediction value at the current moment, δcd is the assessment requirement for the accuracy of the ultra - short - term power prediction of the new - energy power generation field, and Pwn is the available capacity of the new - energy power generation field;
[0059] Pdmin = Pd - (1 - δd)×Pwn
[0060] Pdmax = Pd + (1 - δd)×Pwn
[0061] In the above formula, Pdmin and Pdmax are respectively the lower limit value and the upper limit value of the non - assessment range of the short - term power prediction, Pd is the short - term power prediction value at the current moment, and δd is the assessment requirement for the accuracy of the short - term power prediction of the new - energy power generation field;
[0062] Pzmin=Pz - (1-δz)×Pwn
[0063] Pzmax=Pz + (1-δz)×Pwn
[0064] In the above formula, Pzmin and Pzmax are the lower and upper limits of the assessment-free range of the medium-term power forecast, respectively, Pz is the medium-term power forecast value at the current moment, and δz is the assessment requirement for the accuracy of the medium-term power forecast of the new energy power plant. As an optional implementation, in this embodiment, the accuracy assessment requirements for the ultra-short-term, short-term, and medium-term power forecasts of the wind farm are 87%, 83%, and 70%, respectively, that is:
[0065] Pcdmin=Pcd-0.13×Pwn,
[0066] Pcdmax=Pcd+0.13×Pwn,
[0067] Pcmin=Pd-0.17×Pwn,
[0068] Pcmax=Pd+0.17×Pwn,
[0069] Pzmin=Pz-0.3×Pwn,
[0070] Pzmax=Pz+0.3×Pwn.
[0071] In step S101 of this embodiment, determining the output range [Pwemin, Pwemax] of the joint operation of new energy and energy storage at the current moment according to the output Pw of the new energy power plant and the power SOC of the energy storage station includes: judging the size of the power SOC of the energy storage station; if the power SOC of the energy storage station is 100%, determining the output range [Pwemin, Pwemax] of the joint operation of new energy and energy storage at the current moment according to the following formula:
[0072] Pwemin=Pw,
[0073] Pwemax=Pw+PeN,
[0074] If the SOC of the energy storage power station is between 0% and 100%, the output range [Pwemin, Pwemax] of the combined operation of new energy and energy storage at the current moment is determined according to the following formula:
[0075] Pwemin=Pw-PeN,
[0076] Pwemax=Pw+PeN,
[0077] If the SOC of the energy storage power station is 0%, the output power range [Pwemin, Pwemax] of the new energy and energy storage combined operation at the current moment is determined according to the following formula:
[0078] Pwemin = Pw - PeN,
[0079] Pwemax = Pw,
[0080] where Pw is the output power of the new energy power generation field at the current moment, and PeN is the rated power of the energy storage power station.
[0081] In step S102 of this embodiment, determining the current output power Pe of the energy storage power station according to the output power range [Pwemin, Pwemax] of the new energy and energy storage combined operation includes: if Pwemax < Pcdmin, determining the current output power Pe of the energy storage power station according to Pe = Pwemax - Pw; if Pwemin > Pcdmax, determining the current output power Pe of the energy storage power station according to Pe = Pwemin - Pw; the function expression for calculating and correcting the output power range [P'wemin, P'wemax] of the new energy and energy storage combined operation according to the non - assessment range [Pcdmin, Pcdmax] of the ultra - short - term power prediction and the output power range [Pwemin, Pwemax] of the new energy and energy storage combined operation in step S102 is:
[0082] P'wemin = max(Pcdmin, Pwemin),
[0083] P'wemax = min(Pcdmax, Pwemax),
[0084] In the above formula, max represents taking the maximum value, and min represents taking the minimum value.
[0085] In step S103 of this embodiment, determining the current output power Pe of the energy storage power station according to the corrected output power range [P'wemin, P'wemax] of the new energy and energy storage combined operation includes: if P'wemax < Pdmin, determining the current output power Pe of the energy storage power station according to Pe = P'wemax - Pw; if P'wemin > Pdmax, determining the current output power Pe of the energy storage power station according to Pe = P'wemin - Pw; the function expression for correcting the output power range [P'wemin, P'wemax] of the new energy and energy storage combined operation according to the non - assessment range [Pdmin, Pdmax] of the short - term power prediction and the corrected output power range [P'wemin, P'wemax] of the new energy and energy storage combined operation in step S103 is:
[0086] P"wemin = max(Pdmin, P'wemin),
[0087] P"wemax = min(Pdmax, P'wemax),
[0088] In the above formula, max represents taking the maximum value, and min represents taking the minimum value.
[0089] In step S104 of this embodiment, determining the current output power Pe of the energy storage power station according to the adjusted output power range [P"wemin, P"wemax] of the combined operation of new energy and energy storage includes: if P"wemax < Pzmin, then the current output power Pe of the energy storage power station is determined according to Pe = P"wemax - Pw; if P"wemin > Pzmax, then the current output power Pe of the energy storage power station is determined according to Pe = P"wemin - Pw; the function expression for determining the adjusted output power range [P'"wemin, P'"wemax] of the combined operation of new energy and energy storage according to the non-assessment range [Pzmin, Pzmax] of medium-term power prediction and the adjusted output power range [P"wemin, P"wemax] in step S104 is:
[0090] P'"wemin = max(Pzmin, P"wemin),
[0091] P'"wemax = min(Pzmax, P"wemax),
[0092] In the above formula, max represents taking the maximum value, and min represents taking the minimum value.
[0093] In step S105 of this embodiment, determining the current output power Pe of the energy storage power station in combination with the adjusted output power range [P'"wemin, P'"wemax] of the combined operation of new energy and energy storage includes: if the SOC of the energy storage power station is greater than the preset upper limit value, then the current output power Pe of the energy storage power station is determined according to Pe = P'"wemax - Pw; if the SOC of the energy storage power station is less than the preset lower limit value, then the current output power Pe of the energy storage power station is determined according to Pe = P'"wemin - Pw. As an optional implementation manner, in this embodiment, the preset upper limit value is 80%, and the preset lower limit value is 20%, that is:
[0094] If the SOC of the energy storage power station > 80%, Pe = P'"wemax - Pw;
[0095] If the SOC of the energy storage power station < 20%, Pe = P'"wemin - Pw.
[0096] In step S105 of this embodiment, determining the current output power Pe of the energy storage power station according to the corrected output power range [P'"wemin, P'"wemax] of the combined operation of new energy and energy storage and the output power Pw of the new energy power station at the current moment includes: if Pw > P'"wemax, then determine the current output power Pe of the energy storage power station according to Pe = P'"wemax - Pw; if Pw < P'"wemin, then determine the current output power Pe of the energy storage power station according to Pe = P'"wemin - Pw. Finally, the value of the current output power Pe of the energy storage power station can be positive or negative, indicating charging or discharging, or can be 0, indicating that the energy storage power station does not discharge or charge.
[0097] In summary, the steps of the control method for the combined operation of new energy and energy storage to improve new energy consumption in this embodiment include adjusting the output of the energy storage power station in the priority order of ultra-short-term power prediction, short-term power prediction, and medium-term power prediction, so that the combined power of new energy + energy storage at the current moment is maximally consistent with the new energy power prediction. The method of this embodiment can, on the premise of not losing new energy power and not exceeding the power and electricity of the energy storage power station, maximally make the combined power of new energy and energy storage consistent with the new energy power prediction, and effectively improve the new energy consumption capacity.
[0098] In addition, this embodiment also provides a control system for the combined operation of new energy and energy storage to improve new energy consumption, including a microprocessor and a memory connected to each other, and the microprocessor is programmed or configured to execute the control method for the combined operation of new energy and energy storage to improve new energy consumption.
[0099] In addition, this embodiment also provides a computer-readable storage medium, in which a computer program is stored, and the computer program is used to be programmed or configured by a microprocessor to execute the control method for the combined operation of new energy and energy storage to improve new energy consumption.
[0100] Those skilled in the art should understand that the embodiments of the present application can be provided as methods, systems, or computer program products. Therefore, the present application can take the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware. Moreover, the present application can take the form of a computer program product implemented on one or more computer-readable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code. The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the process Figure 1 A process or multiple processes and / or boxes Figure 1 These computer program instructions can also be stored in a computer-readable memory that can guide a computer or other programmable data processing device to work in a specific way, so that the instructions stored in the computer-readable memory produce a product including an instruction device, which implements the functions specified in the process. Figure 1 A process or multiple processes and / or boxes Figure 1 These computer program instructions can also be loaded onto a computer or other programmable data processing device, so that a series of operation steps are executed on the computer or other programmable device to produce a computer-implemented process, so that the instructions executed on the computer or other programmable device provide for implementing the process in the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.
[0101] The above is only a preferred embodiment of the present invention, and the protection scope of the present invention is not limited to the above embodiments. All technical solutions under the concept of the present invention belong to the protection scope of the present invention. It should be pointed out that for ordinary technicians in this technical field, some improvements and modifications without departing from the principle of the present invention should also be regarded as the protection scope of the present invention.
Claims
1. A new energy and energy storage joint operation control method for improving new energy consumption, characterized in that: include: S101, determine the following formula to calculate the assessment-free range [Pcdmin, Pcdmax] of the ultra-short-term power forecast at the current moment, the assessment-free range [Pdmin, Pdmax] of the short-term power forecast, and the assessment-free range [Pzmin, Pzmax] of the medium-term power forecast: Pcdmin=Pcd - (1-δcd)×Pwn, Pcdmax=Pcd + (1-δcd)×Pwn, In the above formula, Pcdmin and Pcdmax are the lower and upper limits of the assessment-free range of ultra-short-term power forecast, respectively; Pcd is the ultra-short-term power forecast value at the current moment; δcd is the accuracy assessment requirement for ultra-short-term power forecast of new energy power plants; and Pwn is the available capacity of new energy power plants. Pdmin=Pd - (1-δd)×Pwn Pdmax=Pd + (1-δd)×Pwn In the above formula, Pdmin and Pdmax are the lower and upper limits of the assessment-free range of short-term power forecast, Pd is the short-term power forecast value at the current moment, and δd is the assessment requirement for the accuracy of short-term power forecast of new energy power plants; Pzmin=Pz - (1-δz)×Pwn Pzmax=Pz + (1-δz)×Pwn In the above formula, Pzmin and Pzmax are the lower limit and upper limit of the assessment-free range of the medium-term power forecast, respectively; Pz is the medium-term power forecast value at the current moment; δz is the assessment requirement for the accuracy of the medium-term power forecast of the new energy power plant; the output range [Pwemin, Pwemax] of the joint operation of new energy and energy storage at the current moment is determined according to the output Pw of the new energy power plant and the SOC of the energy storage power station, including: judging the size of the SOC of the energy storage power station; if the SOC of the energy storage power station is 100%, the output range [Pwemin, Pwemax] of the joint operation of new energy and energy storage at the current moment is determined according to the following formula: Pwemin=Pw, Pwemax=Pw+PeN, If the SOC of the energy storage power station is between 0% and 100%, the output range [Pwemin, Pwemax] of the combined operation of new energy and energy storage at the current moment is determined according to the following formula: Pwemin=Pw-PeN, Pwemax=Pw+PeN, If the SOC of the energy storage power station is 0%, the output range [Pwemin, Pwemax] of the combined operation of new energy and energy storage at the current moment is determined according to the following formula: Pwemin=Pw-PeN, Pwemax=Pw, Among them, Pw is the output of the new energy power plant at the current moment, and PeN is the rated power of the energy storage power station; S102. Compare the non - assessment range [Pcdmin, Pcdmax] of the ultra - short - term power prediction with the output range [Pwemin, Pwemax] of the combined operation of new energy and energy storage. If Pwemax < Pcdmin or Pwemin > Pcdmax, determine the current output power Pe of the energy storage power station according to the output range [Pwemin, Pwemax] of the combined operation of new energy and energy storage, and end and exit; otherwise, calculate and correct the output range [P'wemin, P'wemax] of the combined operation of new energy and energy storage based on the non - assessment range [Pcdmin, Pcdmax] of the ultra - short - term power prediction and the output range [Pwemin, Pwemax] of the combined operation of new energy and energy storage. S103. Compare the non - assessment range [Pdmin, Pdmax] of the short - term power prediction with the corrected output range [P'wemin, P'wemax] of the combined operation of new energy and energy storage. If P'wemax < Pdmin or P'wemin > Pdmax, determine the current output power Pe of the energy storage power station according to the corrected output range [P'wemin, P'wemax] of the combined operation of new energy and energy storage, and end and exit; otherwise, correct the output range [P"wemin, P"wemax] of the combined operation of new energy and energy storage based on the non - assessment range [Pdmin, Pdmax] of the short - term power prediction and the corrected output range [P'wemin, P'wemax] of the combined operation of new energy and energy storage. S104. Compare the non - assessment range [Pzmin, Pzmax] of the medium - term power prediction with the corrected output range [P"wemin, P"wemax] of the combined operation of new energy and energy storage. If P"wemax < Pzmin or P"wemin > Pzmax, determine the current output power Pe of the energy storage power station according to the corrected output range [P"wemin, P"wemax] of the combined operation of new energy and energy storage, and end and exit; otherwise, determine the corrected output range [P'"wemin, P'"wemax] of the combined operation of new energy and energy storage based on the non - assessment range [Pzmin, Pzmax] of the medium - term power prediction and the corrected output range [P"wemin, P"wemax] of the combined operation of new energy and energy storage. S105. If the state of charge (SOC) of the energy storage power station is greater than the preset upper limit value or less than the preset lower limit value, determine the current output power Pe of the energy storage power station in combination with the corrected output range [P'"wemin, P'"wemax] of the combined operation of new energy and energy storage; otherwise, determine the current output power Pe of the energy storage power station according to the corrected output range [P'"wemin, P'"wemax] of the combined operation of new energy and energy storage and the output Pw of the new - energy power plant at the current moment.
2. The new energy and energy storage combined operation control method for improving new energy consumption according to claim 1 is characterized in that: In step S102, determining the current output power Pe of the energy storage power station according to the output power range [Pwemin, Pwemax] of the combined operation of new energy and energy storage includes: if Pwemax < Pcdmin, then determine the current output power Pe of the energy storage power station according to Pe = Pwemax - Pw; if Pwemin > Pcdmax, then determine the current output power Pe of the energy storage power station according to Pe = Pwemin - Pw; the function expression for calculating the corrected output power range [P'wemin, P'wemax] of the combined operation of new energy and energy storage according to the non-assessment range [Pcdmin, Pcdmax] of the ultra-short-term power prediction and the output power range [Pwemin, Pwemax] of the combined operation of new energy and energy storage in step S102 is: P'wemin = max(Pcdmin, Pwemin), P'wemax = min(Pcdmax, Pwemax), In the above formula, max represents taking the maximum value, and min represents taking the minimum value.
3. The new energy and energy storage combined operation control method for improving new energy consumption according to claim 1 is characterized in that: In step S103, determining the current output power Pe of the energy storage power station according to the corrected output power range [P'wemin, P'wemax] of the combined operation of new energy and energy storage includes: if P'wemax < Pdmin, then determine the current output power Pe of the energy storage power station according to Pe = P'wemax - Pw; if P'wemin > Pdmax, then determine the current output power Pe of the energy storage power station according to Pe = P'wemin - Pw; the function expression for correcting the output power range [P"wemin, P"wemax] of the combined operation of new energy and energy storage according to the non-assessment range [Pdmin, Pdmax] of the short-term power prediction and the corrected output power range [P'wemin, P'wemax] of the combined operation of new energy and energy storage in step S103 is: P"wemin = max(Pdmin, P'wemin), P"wemax = min(Pdmax, P'wemax), In the above formula, max represents taking the maximum value, and min represents taking the minimum value.
4. The new energy and energy storage combined operation control method for improving new energy consumption according to claim 1 is characterized in that: In step S104, determining the current output power Pe of the energy storage power station according to the corrected output power range [P"wemin, P"wemax] of the combined operation of new energy and energy storage includes: if P"wemax < Pzmin, then determine the current output power Pe of the energy storage power station according to Pe = P"wemax - Pw; if P"wemin > Pzmax, then determine the current output power Pe of the energy storage power station according to Pe = P"wemin - Pw; the function expression for determining the corrected output power range [P'"wemin, P'"wemax] of the combined operation of new energy and energy storage according to the non-assessment range [Pzmin, Pzmax] of the medium-term power prediction and the corrected output power range [P"wemin, P"wemax] of the combined operation of new energy and energy storage in step S104 is: P'"wemin = max(Pzmin, P"wemin), P'"wemax = min(Pzmax, P"wemax), In the above formula, max represents taking the maximum value, and min represents taking the minimum value.
5. The new energy and energy storage combined operation control method for improving new energy consumption according to claim 1 is characterized in that: In step S105, determining the current output power Pe of the energy storage power station by combining the corrected output power range [P'"wemin, P'"wemax] of the combined operation of new energy and energy storage includes: if the state of charge (SOC) of the energy storage power station is greater than the preset upper limit value, then determine the current output power Pe of the energy storage power station according to Pe = P'"wemax - Pw; if the SOC of the energy storage power station is less than the preset lower limit value, then determine the current output power Pe of the energy storage power station according to Pe = P'"wemin - Pw.
6. The new energy and energy storage combined operation control method for improving new energy consumption according to claim 1 is characterized in that: In step S105, determining the current output power Pe of the energy storage power station according to the corrected output power range [P'"wemin, P'"wemax] of the combined operation of new energy and energy storage and the output power Pw of the new energy power generation field at the current moment includes: if Pw > P'"wemax, then determine the current output power Pe of the energy storage power station according to Pe = P'"wemax - Pw; if Pw < P'"wemin, then determine the current output power Pe of the energy storage power station according to Pe = P'"wemin - Pw.
7. A new energy and energy storage combined operation control system for improving new energy consumption, comprising a microprocessor and a memory connected to each other, characterized in that: The microprocessor is programmed or configured to execute the control method for the combined operation of new energy and energy storage for improving new energy consumption described in any one of claims 1 to 6.
8. A computer-readable storage medium having a computer program stored therein, characterized in that: The computer program is used to be programmed or configured by the microprocessor to execute the control method for the combined operation of new energy and energy storage for improving new energy consumption described in any one of claims 1 to 6.