A system and method for construction progress control based on WEB

Through the WEB-side construction progress control system, real-time collection and analysis of data and generation of progress reports and charts, the problems of low manual management efficiency and difficulty in sharing information are solved, accurate prediction and adjustment of construction progress are achieved, and the accuracy of project management is improved. and efficiency.

CN117474238BActive Publication Date: 2024-11-15ZHAOQING HIGHWAY DEVELOPMENT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202311381137.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-10-24
Publication Date
2024-11-15
Estimated Expiration
2043-10-24

AI Technical Summary

Technical Problem

In the prior art, there is low efficiency of manual management and difficult to ensure data accuracy in the construction progress control of engineering projects, resulting in delays in construction periods and waste of resources, and it is difficult for different departments to share and exchange information, resulting in low collaborative work capabilities.

Method used

Provide a construction progress control system based on WEB, including user management, data acquisition, progress control and information sharing units. Data is collected in real time through sensors and monitoring equipment, data preprocessing and analysis are carried out, construction progress reports and charts are generated, and real-time Monitor and early warning, and realize data sharing and collaborative work through the WEB platform.

Benefits of technology

It improves the efficiency and accuracy of construction progress, enhances the ability of collaborative work among all participants, ensures the smooth implementation of the project, promptly discovers and deals with problems, and reduces project risks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117474238B_ABST
    Figure CN117474238B_ABST
Patent Text Reader

Abstract

The present invention discloses a system and method for WEB-based construction progress control, and relates to the technical field of data processing for construction supervision and prediction. In order to solve the problem that due to the large number of project participants, it is difficult for different departments to share and exchange information, resulting in low collaborative work ability; a system for WEB-based construction progress control, including a user management unit, a progress control unit and an information sharing unit; through real-time monitoring of the construction site, the transparency of data and the timeliness of feedback are improved, the accurate analysis and prediction of the construction progress are achieved, the accurate prediction and adjustment of the construction progress are achieved, the accuracy of project management is improved, the relevant personnel can remotely understand and control the situation of the construction site, the work efficiency is improved, and it is convenient for users to query and compare, which greatly improves the control level of the construction progress, so that problems can be discovered and handled in time, reduce project risks, and improve the efficiency and accuracy of project management.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of data processing for construction supervision and prediction, and in particular to a system and method for WEB-based construction progress control. Background Art

[0002] Engineering construction projects are in the entire life cycle of engineering project construction. There are a large number of project participants, and the project information content is diverse and huge. In the collaborative management of engineering projects, there are often phenomena such as fuzzy project information data and serious information loss. There are relevant patents for the control of construction progress of engineering projects. For example, the Chinese patent with publication number CN116644878A discloses a BIM collaborative platform for engineering monitoring based on the Internet of Things, including: a progress management module for progress control, including feasibility comparison of the actual construction progress on site with the planned progress based on drone aerial pictures and the instant generation of BIM three-dimensional models to ensure The progress of the project is controllable; and the progress plan and simulation based on BIM, using the intuitive and transparent BIM model and the actual progress on site to continuously refine and adjust the project progress plan, to ensure the possibility of a reasonable, feasible and shorter construction period under the basic progress target; the on-site visual monitoring management module is used for on-site visual monitoring, combined with BIM, through mobile intelligent video monitoring, to control the safety specifications of personnel and equipment, to ensure the progress and quality of the project; the quality management module, as well as the cost control module and the labor management module are used for personnel management, based on the intuitiveness of the BIM model and Internet data, to conduct real-time background management and deployment of on-site construction personnel.

[0003] Although the above patent performs real-time background management and deployment of on-site construction personnel based on the BIM model, the following problems still exist:

[0004] In the existing technology, manual management requires a lot of human resources, and the amount of information processed is also very large, which leads to low efficiency. In addition, manual management methods are difficult to ensure the accuracy of data, which may cause delays in construction or waste of resources. At the same time, due to the large number of project participants, it is difficult for different departments to share and exchange information, resulting in low collaborative work capabilities. Summary of the invention

[0005] The purpose of the present invention is to provide a system and method for construction progress control based on the WEB side, which can effectively improve the efficiency and accuracy of construction progress control, and at the same time improve the collaborative working ability among various participants, which is conducive to the smooth implementation of the project, so as to solve the problems raised in the above background technology.

[0006] To achieve the above object, the present invention provides the following technical solutions:

[0007] A system for WEB-based construction progress control, including:

[0008] The user management unit is used to manage the users of the construction progress control system, including user registration, login and authority allocation, obtain the user data logged in by the WEB end, obtain the key information and authority level of the user data, and store and manage the user operation data after login;

[0009] The data acquisition unit is used to collect various data on the construction site and pre-process the collected data. The pre-processed data will be displayed on the WEB end respectively, indicating the construction task, daily progress, monthly progress and estimated completion time corresponding to the current user data;

[0010] The progress control unit is used to extract the real-time monitoring data from the collected data, process and analyze the real-time monitoring, generate construction progress reports and charts, and issue early warnings on the construction progress according to the construction tasks. When the construction progress is found to be at risk of delay, an early warning signal is issued;

[0011] The information sharing unit is used to share the data of the data acquisition unit and the progress control unit with various participants of the project. Each of the participants logs in to the WEB terminal based on the smart terminal to retrieve and query relevant data.

[0012] Furthermore, the user management unit includes:

[0013] User registration module, used to create and add multiple users based on the system administrator, establish an association relationship between each user and the system administrator, and establish an independent password based on user data;

[0014] User login module, used to obtain user data and its corresponding password, verify whether the identity information is correct, and obtain corresponding permissions after logging in;

[0015] The authority management module is used to assign different authority levels to each user according to job requirements, and to divide the assigned users into groups based on the authority levels;

[0016] The operation monitoring module is used to establish a log management system, record key operations and abnormal times, and use real-time monitoring technology to supervise user operations.

[0017] Furthermore, the data acquisition unit includes:

[0018] The data acquisition module is used to arrange sensors and monitoring equipment at the construction site to collect data on the construction quantity and construction progress in real time, and transmit the collected data to the server via the Internet for processing and storage;

[0019] The data processing module is used to classify the data uploaded by sensors and monitoring devices based on their categories, clean the data, and store the processed data in the database;

[0020] The project management module is used to obtain data actively uploaded by the system administrator, create corresponding construction projects based on the data actively uploaded by the system administrator, and adjust and formulate new construction plans.

[0021] Furthermore, the data acquisition module includes:

[0022] A data collection execution module is used to collect engineering quantity and construction progress data in real time during a collection cycle; wherein the collection cycle includes multiple unit times, and the value range of the unit time is 1s-3s; the value range of the unit time included in the collection unit is 30 unit times to 50 unit times;

[0023] A data volume extraction module, used to extract the data volume of the data information collected within each unit collection time in the collection cycle;

[0024] The factor acquisition module is used to set the first thread adjustment factor and the second thread adjustment factor by using the data amount of the data information collected in each unit collection time in the collection cycle, wherein the first thread adjustment factor and the second thread adjustment factor are obtained by the following formula:

[0025]

[0026]

[0027] Among them, E 01 and E 02 They represent the first thread adjustment factor and the second thread adjustment factor respectively; n represents the number of unit time contained in the acquisition cycle; C i represents the amount of data acquired per unit time; Cz represents the total amount of data acquired during the acquisition period; exp represents the exponential function operation with e as the base;

[0028] A thread parameter acquisition module, used to set thread parameters using the first thread adjustment factor and the second thread adjustment factor, and to construct a data transmission thread between a data acquisition module and the server according to the thread parameters;

[0029] The data transmission execution module is used to transmit the data information acquired during the collection period to the server through the data transmission thread.

[0030] Furthermore, the thread parameter acquisition module includes:

[0031] Extracting the first thread adjustment factor and the second thread adjustment factor;

[0032] The maximum permissible amount of data transmitted per unit time of the data transmission thread is set by using the first thread adjustment factor and the second thread adjustment factor; wherein the maximum permissible amount of data transmitted per unit time of the data transmission thread is obtained by the following formula:

[0033]

[0034] Among them, C max represents the maximum permissible amount of data transmitted per unit time of the data transmission thread; C0 represents the preset benchmark permissible amount of data transmitted; E 01 and E 02 Respectively represent the first thread adjustment factor and the second thread adjustment factor; λ 01 and λ 02 denote the first thread adjustment coefficient and the second thread adjustment coefficient respectively, and λ 01 The value range of λ is 0.36-0.47, 02 The value range of is 0.12-0.24;

[0035] According to the maximum amount of data allowed to be transmitted per unit time of the data transmission thread, a data transmission thread between the data collection module and the server is constructed, wherein the data transmission thread between the data collection module and the server corresponds to a collection period one by one;

[0036] After the data transmission thread completes the data information acquired in the current collection cycle, the thread cancellation operation is performed.

[0037] Furthermore, the project management module is specifically:

[0038] Acquire the project to be created based on the data actively uploaded by the system administrator, read the project to be created, and determine the construction plan of the project to be created;

[0039] There is at least one project to be created, and the construction plan includes the project name, construction type and construction task of the project to be created;

[0040] Analyzing the construction plan, determining the priorities of the construction tasks based on the estimated completion time of the construction tasks, and executing the construction plan based on the priorities;

[0041] The worker requirements corresponding to the construction plan are determined based on the attribute information of the project to be created, and worker positions and the number of workers are created based on the worker requirements.

[0042] Furthermore, the progress control unit includes:

[0043] The progress monitoring module is used to extract construction progress data from the collected data and monitor the construction progress of the construction site in real time;

[0044] The progress data statistics module is used to compare the actual construction progress with the planned construction progress, and to make construction plan forecasts based on the comparison results and historical construction progress data to obtain forecast results;

[0045] A progress report generation module, used to generate corresponding construction reports and construction progress charts of the construction project based on the prediction results;

[0046] The early warning module is used to make early warning judgments on the construction progress. When it is judged that there is a risk of delay in the construction progress, an early warning signal will be issued and the early warning information will be sent to the management personnel via the Internet.

[0047] Furthermore, the progress report generation module generates a construction progress chart of the construction project, specifically:

[0048] Determine the actual progress of the construction plan based on real-time monitoring of the construction progress data, and retrieve relevant information of the construction plan according to the actual progress of the construction plan;

[0049] The associated information includes: actual daily progress data, actual monthly progress data and the estimated completion time of the project under the current progress;

[0050] Combining the associated information of the construction plan with the progress of the construction plan to form a corresponding relationship under the current construction progress state;

[0051] Determine the data fluctuation relationship according to the corresponding relationship under the current construction progress status and the corresponding relationship under the historical construction progress status;

[0052] The data fluctuation relationship is filled into a chart template to obtain a construction progress chart of the construction plan, and abnormal data is highlighted in the construction progress chart of the construction plan.

[0053] Furthermore, the information sharing unit includes:

[0054] The data interaction module is used to establish a data sharing mechanism. Based on the data sharing mechanism, the construction progress data and the real-time monitoring data of the project are shared with all the participants of the project. All the participants can realize multi-party online collaborative work based on the WEB page.

[0055] Data visualization module is used to generate construction progress charts based on processed data, so that users can intuitively view the construction progress through the WEB page, and provide users with query and comparison functions;

[0056] The feedback module is used to obtain feedback information from users to evaluate or put forward opinions on the current construction progress, and to process and store the user's feedback information.

[0057] The present invention provides another technical solution, a method for WEB-based construction progress control, comprising the following steps:

[0058] Step 1: Log in to the user data on the WEB terminal, obtain the basic information and permission level of the user data, and log the user operation data;

[0059] Step 2: Set up sensors and cameras at the construction site to collect construction data in real time, analyze the collected construction data, and generate reports and charts reflecting the construction progress;

[0060] Step 3: When the analysis results show that there are abnormalities or potential problems in the construction progress, an early warning will be automatically issued. After receiving the early warning, relevant personnel will adjust and control the construction according to the actual situation.

[0061] Compared with the prior art, the present invention has the following beneficial effects:

[0062] Through real-time monitoring of the construction site, the transparency of data and the timeliness of feedback are improved, the accurate analysis and prediction of the construction progress are achieved, the accurate prediction and adjustment of the construction progress are realized, and the accuracy of project management is improved. By using the WEB platform, relevant personnel can remotely understand and control the situation of the construction site, which improves work efficiency and facilitates users to query and compare, greatly improving the level of construction progress control, so that problems can be discovered and dealt with in a timely manner, reducing project risks and improving the efficiency and accuracy of project management. BRIEF DESCRIPTION OF THE DRAWINGS

[0063] Figure 1 It is a system module diagram of the WEB-based construction progress control of the present invention. DETAILED DESCRIPTION

[0064] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0065] In order to solve the technical problem of low collaborative work ability caused by the large number of project participants, it is difficult for different departments to share and exchange information, please refer to Figure 1 , this embodiment provides the following technical solutions:

[0066] A system for WEB-based construction progress control, including:

[0067] The user management unit is used to manage the users of the construction progress control system, including user registration, login and authority allocation, obtain the user data logged in by the WEB end, obtain the key information and authority level of the user data, and store and manage the user operation data after login;

[0068] User management unit, including:

[0069] User registration module, used to create and add multiple users based on the system administrator, establish an association relationship between each user and the system administrator, and establish an independent password based on user data;

[0070] User login module, used to obtain user data and its corresponding password, verify whether the identity information is correct, and obtain corresponding permissions after logging in;

[0071] The authority management module is used to assign different authority levels to each user according to job requirements, such as ordinary users, administrators, super administrators, etc., and to divide the assigned users into groups based on the authority levels;

[0072] Operation monitoring module, used to establish a log management system, record key operations and abnormal times, and use real-time monitoring technology to supervise user operations;

[0073] Specifically, the authority levels are divided in detail according to positions and work needs, so as to better control the location and scope of operation. At the same time, the approval links and approval personnel are clarified to ensure the rationality and scientificity of authority allocation, the fairness and accuracy of authority allocation, improve work efficiency, establish a log management system to facilitate tracing and source tracing, ensure the compliance and safety of operations, discover abnormal operations in time, hold relevant personnel accountable and deal with them, increase employees' attention to safe operations, and continuously improve management levels;

[0074] The data acquisition unit is used to collect various data on the construction site, including but not limited to the engineering quantity, construction progress, human resources, material usage, etc., and pre-process the collected data. The pre-processed data will be displayed on the WEB end respectively, indicating the construction task, daily progress, monthly progress and estimated completion time corresponding to the current user data;

[0075] The progress control unit is used to extract real-time monitoring data from the collected data, including but not limited to data on engineering quantity, manpower, material resources, etc., process and analyze the real-time monitoring, generate construction progress reports and charts, and issue early warnings on the construction progress according to the construction tasks. When the construction progress is found to be at risk of delay, an early warning signal is issued;

[0076] The information sharing unit is used to share the data of the data acquisition unit and the progress control unit with all participants of the project, including but not limited to the construction unit, the supervision unit, the design unit and the owner, etc. Each participant logs in to the WEB terminal based on the smart terminal to retrieve and query relevant data;

[0077] Information sharing unit, including:

[0078] The data interaction module is used to establish a data sharing mechanism. Based on the data sharing mechanism, the construction progress data and the real-time monitoring data of the project are shared with all the participants of the project. All the participants can realize multi-party online collaborative work based on the WEB page.

[0079] Data visualization module is used to generate construction progress charts based on processed data, so that users can intuitively view the construction progress through the WEB page, and provide users with query and comparison functions;

[0080] The feedback module is used to obtain feedback information from users to evaluate or put forward opinions on the current construction progress, and to process and store the user's feedback information.

[0081] Specifically, the construction progress is warned according to the construction tasks. When the construction progress is found to be at risk of delay, a warning signal is issued so that the management personnel can take appropriate measures in time. The users can intuitively view the construction progress through the WEB page so that the management personnel can intuitively understand the construction progress and existing problems. The users evaluate the current construction progress or provide feedback on their opinions. All parties can make corresponding decisions based on the latest data to facilitate subsequent data processing and analysis, effectively improve the efficiency and accuracy of construction progress control, and at the same time improve the collaborative working ability among all participants, which is conducive to the smooth implementation of the project.

[0082] In order to solve the technical problem that manual management methods cannot guarantee data accuracy, which may cause delays in construction or waste of resources, please refer to Figure 1 , this embodiment provides the following technical solutions:

[0083] The data acquisition unit comprises:

[0084] The data acquisition module is used to arrange sensors and monitoring equipment at the construction site to collect data on the construction quantity and construction progress in real time, and transmit the collected data to the server via the Internet for processing and storage;

[0085] The data processing module is used to classify the data uploaded by sensors and monitoring devices based on their categories, clean the data, and store the processed data in the database;

[0086] The project management module is used to obtain the data actively uploaded by the system administrator, create corresponding construction projects based on the data actively uploaded by the system administrator, and adjust and formulate new construction plans;

[0087] Specifically, the data acquisition module includes:

[0088] A data collection execution module is used to collect engineering quantity and construction progress data in real time during a collection cycle; wherein the collection cycle includes multiple unit times, and the value range of the unit time is 1s-3s; the value range of the unit time included in the collection unit is 30 unit times to 50 unit times;

[0089] A data volume extraction module, used to extract the data volume of the data information collected within each unit collection time in the collection cycle;

[0090] The factor acquisition module is used to set the first thread adjustment factor and the second thread adjustment factor by using the data amount of the data information collected in each unit collection time in the collection cycle, wherein the first thread adjustment factor and the second thread adjustment factor are obtained by the following formula:

[0091]

[0092]

[0093] Among them, E 01 and E 02 They represent the first thread adjustment factor and the second thread adjustment factor respectively; n represents the number of unit time contained in the acquisition cycle; C i represents the amount of data acquired per unit time; Cz represents the total amount of data acquired during the acquisition period; exp represents the exponential function operation with e as the base;

[0094] A thread parameter acquisition module, used to set thread parameters using the first thread adjustment factor and the second thread adjustment factor, and to construct a data transmission thread between a data acquisition module and the server according to the thread parameters;

[0095] The data transmission execution module is used to transmit the data information acquired during the collection period to the server through the data transmission thread.

[0096] The technical effects of the above technical solution are: Real-time data collection: The system can collect engineering quantity and construction progress data in real time within a very short collection period (the value range of each unit time is 1 second to 3 seconds). This helps to obtain the progress of the project in a timely manner.

[0097] Dynamic adjustment of data volume: By using the amount of data acquired in each unit of acquisition time during the acquisition cycle, the system can dynamically set the first thread adjustment factor and the second thread adjustment factor to adapt to different data generation rates and data volumes. This helps the system adjust according to actual needs and data characteristics.

[0098] Thread parameter adjustment: The system uses the first thread adjustment factor and the second thread adjustment factor to set the parameters of the data acquisition thread. This allows the system to optimize the performance of the thread during data transmission to handle different data volumes and acquisition cycles.

[0099] Efficient data transmission: By building data transmission threads and using dynamically adjusted thread parameters, the system can achieve efficient data transmission. This ensures that the collected data can be transmitted to the server in a timely manner for further analysis and management.

[0100] Data reliability: Real-time collection and efficient transmission help ensure data reliability. Data will not lag, thus supporting timely monitoring and decision-making of engineering quantities and construction progress.

[0101] In general, the technical effect of this technical solution is to improve the efficiency, real-time and reliability of engineering data collection, while also adapting to the needs of different data situations and collection cycles, helping to better manage and monitor project progress.

[0102] Specifically, the thread parameter acquisition module includes:

[0103] Extracting the first thread adjustment factor and the second thread adjustment factor;

[0104] The maximum permissible amount of data transmitted per unit time of the data transmission thread is set by using the first thread adjustment factor and the second thread adjustment factor; wherein the maximum permissible amount of data transmitted per unit time of the data transmission thread is obtained by the following formula:

[0105]

[0106] Among them, C max represents the maximum permissible amount of data transmitted per unit time of the data transmission thread; C0 represents the preset benchmark permissible amount of data transmitted; E 01 and E 02 Respectively represent the first thread adjustment factor and the second thread adjustment factor; λ 01 and λ 02 denote the first thread adjustment coefficient and the second thread adjustment coefficient respectively, and λ 01 The value range of λ is 0.36-0.47, 02 The value range of is 0.12-0.24;

[0107] According to the maximum amount of data allowed to be transmitted per unit time of the data transmission thread, a data transmission thread between the data collection module and the server is constructed, wherein the data transmission thread between the data collection module and the server corresponds to a collection period one by one;

[0108] After the data transmission thread completes the data information acquired in the current collection cycle, the thread cancellation operation is performed.

[0109] The technical effects of the above technical solution are: Dynamic thread adjustment: By obtaining the first thread adjustment factor and the second thread adjustment factor, the system can dynamically adjust the parameters of the data transmission thread in each acquisition cycle. This helps to optimize the thread performance to meet the needs of different acquisition cycles.

[0110] Adaptability: The thread parameters are set according to the first thread adjustment factor and the second thread adjustment factor, and can be flexibly adjusted according to the actual data situation and the adjustment coefficient. This provides the system with adaptability to cope with different data situations.

[0111] Setting the maximum amount of data to be transferred per unit time: The system dynamically calculates the maximum amount of data to be transferred per unit time for the data transfer thread based on a formula. This helps control the speed of data transfer to avoid data loss or transmission overload.

[0112] Thread revocation operation: When the data transmission thread completes the data transmission of the current acquisition cycle, the thread revocation operation is performed. This helps to release resources in time to prepare for the data transmission of the next acquisition cycle.

[0113] Efficiency and performance optimization: By dynamically adjusting thread parameters, the system can achieve efficient data transmission in different situations to improve the efficiency of data collection and transmission.

[0114] In general, the technical effect of this technical solution is to improve the adaptability and performance of the data transmission thread, ensure the real-time and reliability of data transmission, and optimize the efficiency of data collection and transmission. This is very important for the management and monitoring of engineering quantity and construction progress data.

[0115] Project management module, specifically:

[0116] Based on the data actively uploaded by the system administrator, the project to be created is obtained, and the project to be created is read to determine the construction plan of the project to be created;

[0117] There is at least one project to be created, and the construction plan includes the project name, construction type and construction task of the project to be created;

[0118] Analyze the construction plan, determine the priority of construction tasks based on the estimated completion time of the construction tasks, and execute the construction plan based on the priority;

[0119] Determine the worker requirements corresponding to the construction plan based on the attribute information of the project to be created, and create worker positions and the number of workers based on the worker requirements;

[0120] Specifically, through data collection, processing and plan formulation, the detailed construction schedule formulated by the project manager according to project requirements and resource conditions is read to achieve accurate and effective creation of the project to be created, and the priority of the construction task is determined based on the expected completion time of the construction task, including the time arrangement, resource allocation, key personnel, etc. of the construction stage. The construction task management of the construction personnel is carried out, and the construction task data analysis is carried out. With the responsibility assigned to individuals, the construction process can be managed more meticulously, the construction efficiency and quality can be improved, and the accuracy and effectiveness of the plan can be further improved;

[0121] Progress control unit, including:

[0122] The progress monitoring module is used to extract construction progress data from the collected data and monitor the construction progress of the construction site in real time;

[0123] The progress data statistics module is used to compare the actual construction progress with the planned construction progress, and to make construction plan forecasts based on the comparison results and historical construction progress data to obtain forecast results;

[0124] A progress report generation module is used to generate corresponding construction reports and construction progress charts of construction projects based on the prediction results;

[0125] The progress report generation module generates a construction progress chart for the construction project, specifically:

[0126] Based on the real-time monitoring of construction progress data, determine the actual progress of the construction plan, and retrieve the relevant information of the construction plan according to the actual progress of the construction plan;

[0127] Related information includes: actual daily progress data, actual monthly progress data and the estimated completion time of the project under the current progress;

[0128] Combine the related information of the construction plan with the progress of the construction plan to form a corresponding relationship under the current construction progress status;

[0129] Determine the data fluctuation relationship based on the corresponding relationship under the current construction progress status and the corresponding relationship under the historical construction progress status;

[0130] Fill the data fluctuation relationship into the chart template to obtain the construction progress chart of the construction plan, and highlight the abnormal data in the construction progress chart of the construction plan;

[0131] Specifically, the chart template not only makes the chart have a unified format, but also only needs to be filled in to form a construction progress chart of the construction plan, which effectively improves the efficiency of the construction progress chart of the construction plan. In addition, by highlighting abnormal data in the construction progress chart of the construction plan, the sensitivity to abnormal data is improved. The progress data statistics module estimates the construction progress in advance, intervenes in delayed risk projects early, and ensures the stable completion of the project progress.

[0132] The early warning module is used to make early warning judgments on the construction progress. When it is judged that there is a risk of delay in the construction progress, an early warning signal will be issued and the early warning information will be sent to the management personnel via the Internet.

[0133] Specifically, the progress monitoring module enables real-time monitoring of the construction site, improves data transparency and timeliness of feedback, accurately analyzes and predicts the construction progress, realizes accurate prediction and adjustment of the construction progress, improves the accuracy of project management, and has an intuitive progress display function. By using the WEB platform, relevant personnel can remotely understand and control the situation of the construction site, improve work efficiency, facilitate users to query and compare, and greatly improve the level of construction progress control, so that problems can be discovered and dealt with in a timely manner, reducing project risks and improving the efficiency and accuracy of project management.

[0134] In order to better demonstrate the implementation of the WEB-based construction progress control system, this embodiment provides a WEB-based construction progress control method, including the following steps:

[0135] Step 1: Log in the user data on the WEB side, obtain the basic information and permission level of the user data, and log the user operation data. The user can log in to the system through mobile phones, computers and other devices, and can view the construction progress and related reports at any time;

[0136] Step 2: Set up sensors and cameras at the construction site to collect construction data in real time, analyze the collected construction data, and generate reports and charts reflecting the construction progress so that managers can intuitively understand the construction progress and existing problems;

[0137] Step 3: When the analysis results show that there are abnormalities or potential problems in the construction progress, an early warning will be automatically issued. After receiving the early warning, the relevant personnel will adjust and control the construction according to the actual situation so that the management personnel can take appropriate measures in time.

[0138] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A system for WEB-based construction progress control, characterized by: include: The user management unit is used to manage the users of the construction progress control system, including user registration, login and authority allocation, obtain the user data logged in by the WEB end, obtain the key information and authority level of the user data, and store and manage the user operation data after login; The data acquisition unit is used to collect various data on the construction site and pre-process the collected data. The pre-processed data will be displayed on the WEB end respectively, indicating the construction task, daily progress, monthly progress and estimated completion time corresponding to the current user data; The progress control unit is used to extract the real-time monitoring data from the collected data, process and analyze the real-time monitoring, generate construction progress reports and charts, and issue early warnings on the construction progress according to the construction tasks. When the construction progress is found to be at risk of delay, an early warning signal is issued; An information sharing unit is used to share the data of the data acquisition unit and the progress control unit with various project participants. Each of the participants logs in to the WEB terminal based on a smart terminal to retrieve and query relevant data; The data acquisition unit comprises: The data acquisition module is used to arrange sensors and monitoring equipment at the construction site to collect data on the construction quantity and construction progress in real time, and transmit the collected data to the server via the Internet for processing and storage; The data processing module is used to classify the data uploaded by sensors and monitoring devices based on their categories, clean the data, and store the processed data in the database; A project management module, which is used to obtain data actively uploaded by the system administrator, and to create corresponding construction projects based on the data actively uploaded by the system administrator, and to adjust and formulate new construction plans; Data acquisition module, including: A data collection execution module is used to collect engineering quantity and construction progress data in real time during a collection cycle; wherein the collection cycle includes multiple unit times, and the value range of the unit time is 1s-3s; the value range of the unit time included in the collection cycle is 30 unit times to 50 unit times; A data volume extraction module, used to extract the data volume of the data information collected within each unit collection time in the collection cycle; The factor acquisition module is used to set the first thread adjustment factor and the second thread adjustment factor by using the data amount of the data information collected in each unit collection time in the collection cycle, wherein the first thread adjustment factor and the second thread adjustment factor are obtained by the following formula: Among them, E 01 and E 02 They represent the first thread adjustment factor and the second thread adjustment factor respectively; n represents the number of unit time contained in the acquisition cycle; C i represents the amount of data acquired per unit time; Cz represents the total amount of data acquired during the acquisition period; exp represents the exponential function operation with e as the base; A thread parameter acquisition module, used to set thread parameters using the first thread adjustment factor and the second thread adjustment factor, and to construct a data transmission thread between a data acquisition module and the server according to the thread parameters; A data transmission execution module, used for transmitting the data information acquired in the collection period to the server through the data transmission thread; Thread parameter acquisition module, including: Extracting the first thread adjustment factor and the second thread adjustment factor; The maximum permissible amount of data transmitted per unit time of the data transmission thread is set by using the first thread adjustment factor and the second thread adjustment factor; wherein the maximum permissible amount of data transmitted per unit time of the data transmission thread is obtained by the following formula: Among them, C max represents the maximum permissible amount of data transmitted per unit time of the data transmission thread; C0 represents the preset benchmark permissible amount of data transmitted; E 01 and E 02 Respectively represent the first thread adjustment factor and the second thread adjustment factor; λ 01 and λ 02 denote the first thread adjustment coefficient and the second thread adjustment coefficient respectively, and λ 01 The value range of λ is 0.36-0.47, 02 The value range of is 0.12-0.24; According to the maximum amount of data allowed to be transmitted per unit time of the data transmission thread, a data transmission thread between the data collection module and the server is constructed, wherein the data transmission thread between the data collection module and the server corresponds to a collection period one by one; After the data transmission thread completes the data information acquired in the current collection cycle, the thread cancellation operation is performed.

2. A system for WEB-based construction progress control as claimed in claim 1, characterized in that: User management unit, including: User registration module, used to create and add multiple users based on the system administrator, establish an association relationship between each user and the system administrator, and establish an independent password based on user data; User login module, used to obtain user data and its corresponding password, verify whether the identity information is correct, and obtain corresponding permissions after logging in; The authority management module is used to assign different authority levels to each user according to job requirements, and to divide the assigned users into groups based on the authority levels; The operation monitoring module is used to establish a log management system, record key operations and abnormal times, and use real-time monitoring technology to supervise user operations.

3. A system for WEB-based construction progress control as claimed in claim 2, characterized in that: The project management module is specifically: Acquire the project to be created based on the data actively uploaded by the system administrator, read the project to be created, and determine the construction plan of the project to be created; There is at least one project to be created, and the construction plan includes the project name, construction type and construction task of the project to be created; Analyzing the construction plan, determining the priorities of the construction tasks based on the estimated completion time of the construction tasks, and executing the construction plan based on the priorities; The worker requirements corresponding to the construction plan are determined based on the attribute information of the project to be created, and worker positions and the number of workers are created based on the worker requirements.

4. A system for WEB-based construction progress control as claimed in claim 3, characterized in that: Progress control unit, including: The progress monitoring module is used to extract construction progress data from the collected data and monitor the construction progress of the construction site in real time; The progress data statistics module is used to compare the actual construction progress with the planned construction progress, and to make construction plan forecasts based on the comparison results and historical construction progress data to obtain forecast results; A progress report generation module, used to generate corresponding construction reports and construction progress charts of the construction project based on the prediction results; The early warning module is used to make early warning judgments on the construction progress. When it is judged that there is a risk of delay in the construction progress, an early warning signal will be issued and the early warning information will be sent to the management personnel via the Internet.

5. A system for WEB-based construction progress control as claimed in claim 4, characterized in that: The progress report generation module generates a construction progress chart for the construction project, specifically: Determine the actual progress of the construction plan based on real-time monitoring of the construction progress data, and retrieve relevant information of the construction plan according to the actual progress of the construction plan; The associated information includes: actual daily progress data, actual monthly progress data and the estimated completion time of the project under the current progress; Combining the associated information of the construction plan with the progress of the construction plan to form a corresponding relationship under the current construction progress state; Determine the data fluctuation relationship according to the corresponding relationship under the current construction progress status and the corresponding relationship under the historical construction progress status; The data fluctuation relationship is filled into a chart template to obtain a construction progress chart of the construction plan, and abnormal data is highlighted in the construction progress chart of the construction plan.

6. A system for WEB-based construction progress control as claimed in claim 5, characterized in that: Information sharing unit, including: The data interaction module is used to establish a data sharing mechanism. Based on the data sharing mechanism, the construction progress data and the real-time monitoring data of the project are shared with all the participants of the project. All the participants can realize multi-party online collaborative work based on the WEB page. Data visualization module is used to generate construction progress charts based on processed data, so that users can intuitively view the construction progress through the WEB page, and provide users with query and comparison functions; The feedback module is used to obtain feedback information from users to evaluate or put forward opinions on the current construction progress, and to process and store the user's feedback information.

7. A method for WEB-based construction progress control, implemented based on the WEB-based construction progress control system as claimed in claim 6, characterized in that: The following steps are involved: Step 1: Log in to the user data on the WEB terminal, obtain the basic information and permission level of the user data, and log the user operation data; Step 2: Set up sensors and cameras at the construction site to collect construction data in real time, analyze the collected construction data, and generate reports and charts reflecting the construction progress; Step 3: When the analysis results show that there are abnormalities or potential problems in the construction progress, an early warning will be automatically issued. After receiving the early warning, relevant personnel will adjust and control the construction according to the actual situation.