Multi-storey frame structure using vertical member attached support assembly construction method
By using vertical member-attached support components and inter-column temporary support components in a multi-layer frame structure, temporary support for composite beams is achieved, which solves the problems of long construction period, high cost and high safety risks in the existing technology. The support system has been optimized to improve construction efficiency and safety.
Patent Information
- Application Number
- CN202311692576.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-11
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2043-12-11
AI Technical Summary
Existing Technology In the construction of multi-layer frame structures, the temporary support system has problems such as long construction period, high cost, high safety risks, and low production efficiency and high production cost of prefabricated columns.
Adopt a multi-layer frame structure and use the assembled construction method of vertical member attached supports. By installing vertical member attached support components and inter-column temporary support components on prefabricated columns, the temporary support of superimposed beams can be achieved and the support frame body can be reduced. erection, and dismantle the supporting components after the joint strength reaches the design strength.
It realizes the construction of multi-layer frame structures with little or even no support, optimizes the support system, reduces the construction period and cost, and improves construction safety.
Smart Images

Figure CN117661859B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to an assembled construction method of a multi-story frame structure utilizing attached supports of vertical components. Background Art
[0002] The cross-section of the frame beam is generally rectangular or T-shaped. When the floor structure is a prefabricated floor, in order to reduce the height occupied by the structure and increase the building clearance, the cross-section of the frame beam is often cross-shaped or basket-shaped. In the assembled integral frame structure, the prefabricated beam is often made into a T-shaped cross-section. After the prefabricated panel is installed in place, some concrete is poured to form the so-called composite beam.
[0003] A composite beam is a beam that is poured with concrete twice. The first time is at the prefabrication site to make it a prefabricated beam; the second time is at the construction site. After the prefabricated beam is hoisted onto the prefabricated column and placed, the upper concrete is poured to connect it to the prefabricated column as a whole. In the existing method, when pouring and connecting the composite beam and the prefabricated column, a steel pipe scaffolding is usually used as a temporary support system for the composite beam. After the pouring between the composite beam and the prefabricated column is completed, the support system built with steel pipes is dismantled, or a permanent concrete bracket is set on the side of the prefabricated column to serve as the composite beam support system. However, the use of the scaffolding support system has problems such as long construction period, high cost, and high safety risk. When using the concrete bracket support system, there are not only problems such as low production efficiency and high production cost of prefabricated columns, but also the column bracket will have a certain adverse effect on the use function and aesthetic manufacturing of the building. Summary of the invention
[0004] The technical problem to be solved by the present invention is to overcome the deficiencies in the prior art, and the purpose is to provide an assembled construction method for a multi-story frame structure using attached supports of vertical components. By building different support systems on prefabricated columns, temporary support during the construction of prefabricated composite beams is achieved, and the multi-story frame structure can be constructed with less support or even without support, thereby optimizing the support system of the existing multi-story prefabricated frame structure and greatly reducing the erection of the support frame.
[0005] The present invention is achieved through the following technical solutions:
[0006] The multi-story frame structure uses an assembled construction method with vertical member attached supports, comprising the following steps:
[0007] 1) Install the vertical member attached support assembly on the side wall of the prefabricated column;
[0008] 2) Build temporary support components between prefabricated columns;
[0009] 3) Use the lifting equipment to lift the composite beam to the construction height, and use the vertical member attached support assembly to support the composite beam;
[0010] 4) Cast the ends of the composite beams and the tops of the prefabricated columns to form a frame structure. When the node strength reaches the design strength, remove the vertical member attached support assembly installed on the prefabricated column;
[0011] 5) Cast the lugs on the side walls of the composite beams and install the floor slabs on the lugs of the composite beams;
[0012] 6) Carry out the pouring process of the superimposed layer on the superimposed plate of the floor slab;
[0013] 7) Repeat steps 1) to 6) to continue constructing the next layer of frame structure.
[0014] Furthermore, the vertical member attached support assembly includes a steel corbel and a fourth threaded rod, and the fourth threaded rod penetrates the prefabricated column and is connected to the steel corbel.
[0015] Further, the vertical member attached support assembly comprises an independent support frame, the independent support frame comprises an I-beam, a support plate and two limiters, the support plate is welded to the top of the I-beam, the two limiters are symmetrically arranged on the top of the support plate, and the composite beam is located between the two limiters;
[0016] The limiting member includes an L-shaped fixing plate, a third threaded rod, and a gasket;
[0017] The support plate is provided with a strip hole, and the third threaded rod vertically passes through the gasket, the fixing plate and the strip hole in sequence, and both ends of the third threaded rod are also connected to the fifth nut to fix the fixing plate on the support plate.
[0018] Furthermore, the I-beam is also provided with a first rib plate, and the first rib plate is welded to the bottom of the support plate;
[0019] The fixing plate is also provided with a second rib plate, and the second rib plate is welded to both ends of the fixing plate;
[0020] A wooden wedge is also provided between the fixing plate and the composite beam.
[0021] Furthermore, the vertical member attachment support assembly includes a lower hoop, an upper hoop and a plurality of angle steel pieces, the lower hoop and the upper hoop each include two first channel steels and two tension bolts, the tension bolts are used to fix the two first channel steels on two opposite side walls of the prefabricated column, and fix the angle steel piece on the edge of the prefabricated column;
[0022] A second channel steel is also placed on the first channel steel of the upper hoop member, and the second channel steel and the first channel steel are both connected to the angle steel member;
[0023] It also includes a plurality of support members for supporting the composite beam, wherein the support members are placed on the first channel steel and the second channel steel of the upper hoop member.
[0024] Furthermore, the angle steel piece includes two vertical plates connected perpendicularly to each other, and the right angle formed by the connection of the two vertical plates is located at the edge of the prefabricated column;
[0025] Two first connecting rods are arranged on one of the vertical plates, and first connecting holes are arranged on the first channel steels. The first connecting rods pass through the first connecting holes and are connected with the first nuts.
[0026] Furthermore, a second connecting rod is provided on the other vertical plate, and a second connecting hole is provided on the second channel steel. The second connecting rod passes through the second connecting hole and is connected to the second nut;
[0027] Also included are a plurality of rubber pads, which are located between the vertical plates and the side walls of the prefabricated columns.
[0028] Furthermore, a first threaded rod is provided between the first channel steel and the second channel steel of the upper hoop member, and two ends of the first threaded rod respectively penetrate the first channel steel and the second channel steel and are connected to the third nut;
[0029] The support member includes a second threaded rod and two steel wedges with right-angled triangle cross-sections. The two ends of the second threaded rod respectively pass through the two steel wedges and are connected to the fourth nut, thereby forming the two steel wedges into a rectangular structure.
[0030] Furthermore, the temporary support assembly between columns includes two tie rods and several sleeves. Telescopic rods are provided at both ends of the tie rods. One end of the telescopic rod is connected to the tie rod by a thread, and the other end is provided with a connecting plate. The sleeve is pre-buried in the prefabricated column, and the connecting plate is connected to the sleeve by a connecting bolt.
[0031] Compared with the prior art, the present invention has the following advantages and beneficial effects:
[0032] The present invention adopts three selective applications, namely, temporary steel corbels on the sides of prefabricated columns or independent support frames or hoops at the ends of beams, as temporary supports during the construction of composite beams; composite beams are used as supports for prefabricated floor components, and prefabricated floor components are matched with support-free floor components; through the above series of technical measures, the construction of multi-story frame structures with less support or even without support is achieved, the support system of existing multi-story prefabricated frame structures is optimized, and the erection of support frames is greatly reduced; at the same time, an inter-column support is arranged in the longitudinal and transverse directions of the prefabricated columns to meet the requirements of resisting horizontal forces before the strength of the single-layer beam-column nodes is reached and the structure has not formed the frame force-bearing performance during construction, thereby ensuring the safety of the multi-story prefabricated frame construction process. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] The drawings described herein are used to provide a further understanding of the embodiments of the present invention, constitute a part of this application, and do not constitute a limitation of the embodiments of the present invention. In the drawings:
[0034] Figure 1 It is a schematic diagram of the framework structure of the present invention;
[0035] Figure 2 This is a schematic diagram of the structure when no secondary beam is provided between the frame nodes of the present invention;
[0036] Figure 3 This is a schematic diagram of the structure when a secondary beam is arranged between the frame nodes of the present invention;
[0037] Figure 4 It is a structural schematic diagram of a vertical member attachment support assembly in Embodiment 2 of the present invention;
[0038] Figure 5 For the present invention Figure 4 The structural diagram of the enlarged part B in the middle;
[0039] Figure 6 This is a schematic structural diagram of a vertical member attachment support assembly in Embodiment 3 of the present invention;
[0040] Figure 7 It is a structural schematic diagram of the independent support frame of the present invention;
[0041] Figure 8 It is a structural schematic diagram of a vertical member attachment support assembly in Embodiment 4 of the present invention;
[0042] Fig. 9 For this utility model Figure 8 The structural diagram of the enlarged part A in the middle;
[0043] Fig.10 It is a structural schematic diagram of the upper hoop member and the lower hoop member of the utility model when they are connected to the prefabricated column;
[0044] Fig.11 This is a schematic diagram of the structure of the support member of the utility model;
[0045] Fig.12 This is a schematic diagram of the structure of the steel wedge of the utility model;
[0046] Fig.13 This is a schematic diagram of the structure of the angle steel member of the utility model;
[0047] Fig.14 It is a structural schematic diagram of the connection between the temporary support assembly between columns and the prefabricated columns of the present invention;
[0048] Fig.15 It is a schematic diagram of the structure when the temporary support assembly between columns of the present invention is connected to the independent support frame;
[0049] Fig.16 It is a schematic diagram of the structure when the temporary support assembly between columns of the present invention is connected with the angle steel piece;
[0050] Fig.17 It is a schematic diagram of the structure of the independent support rod of the present invention;
[0051] Fig.18 It is a structural schematic diagram of the rectangular tube of the present invention;
[0052] Fig.19 For the present invention Fig.18 The structural diagram of the enlarged part C in the middle;
[0053] Fig. 20 It is a structural schematic diagram of the movable rod of the present invention.
[0054] Marks and corresponding parts names in the attached drawings:
[0055] 1. Composite beam; 2. Independent support frame; 3. Prefabricated column; 4. First channel steel; 5. Tension bolts; 6. Angle steel; 7. Support member; 8. First threaded rod; 9. Second channel steel; 10. Steel wedge; 11. Second threaded rod; 12. Rubber pad; 15. First connecting rod; 16. Vertical plate; 17. Wooden wedge; 18. Fixed plate; 19. Second rib plate; 20. Support plate; 21. I-beam; 22. First rib plate; 24. Third threaded rod; 25. Strip hole; 26. Gasket ; 27. Second connecting rod; 28. Floor; 31. Fourth threaded rod; 32. Steel corbel; 33. Steel pipe; 34. Temporary support assembly between columns; 39. Vertical rod; 40. Push rod; 41. Third tube body; 42. Strip mouth; 43. Movable rod; 44. Plug; 45. Third airbag; 46. Connecting tube; 47. Partition; 48. First airbag; 49. Horizontal tube; 50. Bellows; 51. Second spring; 52. First air hole; 53. First tube body; 54. Second air hole; 56. Blocking plate; 57. First spring; 58. Retaining ring; 59. Second tube body; 60. Third spring; 61. Passage; 62. Blocking rod; 63. Entrance; 64. Independent support rod; 65. Rectangular tube; 66. Top plate; 67. Limit bolt; 69. Limiting plate; 70. Second airbag. DETAILED DESCRIPTION
[0056] In order to make the objectives, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with embodiments and drawings. The exemplary embodiments of the present invention and their description are only used to explain the present invention and are not intended to limit the present invention.
[0057] Example 1
[0058] like Figures 1 to 3 As shown, the present invention comprises the following steps:
[0059] 1) Install the vertical member attachment support assembly on the side wall of the prefabricated column 3;
[0060] 2) constructing temporary inter-column support components 34 between prefabricated columns 3;
[0061] 3) Using a lifting device to lift the composite beam 1 to a construction height, and using a vertical member attached support assembly to support the composite beam 1;
[0062] 4) Cast the end of the composite beam 1 and the top of the prefabricated column 3 to form a frame structure. When the node strength reaches the design strength, remove the vertical member attached support assembly installed on the prefabricated column 3;
[0063] 5) Casting the lugs on the side wall of the composite beam 1, and installing the floor slab 28 on the lugs of the composite beam 1;
[0064] 6) Performing a pouring process of the superimposed layer on the superimposed plate of the floor slab 28;
[0065] 7) Repeat steps 1) to 6) to continue constructing the next layer of frame structure.
[0066] Example 2
[0067] like Figure 4 , Figure 5 As shown, on the basis of Example 1, the vertical member attached support assembly includes a steel corbel 32 and a fourth threaded rod 31 , and the fourth threaded rod 31 penetrates the prefabricated column 3 and is connected to the steel corbel 32 .
[0068] The vertical member attached support assembly in this embodiment adopts a steel corbel 32 structure to temporarily support the composite beam 1. The fourth threaded rod 31 is embedded in the prefabricated column 3. Both ends of the fourth threaded rod 31 are connected with sixth nuts. Under the action of the sixth nut, a quick connection between the steel corbel 32 and the fourth threaded rod 31 is achieved, thereby stably fixing the steel corbel 32 on the side wall of the prefabricated column 3.
[0069] During implementation, the top surface of the steel corbel 32 installed on the side wall of the precast column 3 should be located 100mm below the beam-column node area to prevent the top of the precast column 3 from being damaged by storage splitting after being stressed. Since the top of the steel corbel 32 is at an end distance from the top of the precast column 3, in order to ensure that the end of the composite beam 1 placed on the steel corbel 32 can be flush with the precast column 3, the support member 7 is also provided on the steel corbel 32. The support member 7 includes a second threaded rod 11 and two steel wedges with a right triangle cross section. 10, the two ends of the second threaded rod 11 respectively pass through the two steel wedge blocks 10 and are connected with the fourth nut, and the two steel wedge blocks 10 form a rectangular structure, and the composite beam 1 is supported by the set support member 7. When in use, the size of the steel wedge block 10 is selected according to the distance between the top of the steel corbel 32 and the top of the precast column 3, ensuring that the rectangular support member 7 formed by the splicing of the steel wedge blocks 10 can support the composite beam 1 to be flush with the top of the precast column 3, so that the beam-column node formed by the composite beam 1 and the precast column 3 can be cast.
[0070] At the same time, the support member 7 is formed by splicing two steel wedges 10, which is convenient for quick disassembly at a later time.
[0071] Example 3
[0072] like Figure 6 , Figure 7 As shown, on the basis of Example 1, the vertical member attached support assembly includes an independent support frame 2, and the independent support frame 2 includes an I-beam 21, a support plate 20 and two limit members, the support plate 20 is welded to the top of the I-beam 21, and the two limit members are symmetrically arranged on the top of the support plate 20, and the composite beam 1 is located between the two limit members; the limit members include an L-shaped fixing plate 18, a third threaded rod 24, and a gasket 26; a strip hole 25 is provided on the support plate 20, and the third threaded rod 24 vertically penetrates the gasket 26, the fixing plate 18 and the strip hole 25 in sequence, and the two ends of the third threaded rod 24 are also connected to the fifth nut to fix the fixing plate 18 on the support plate 20.
[0073] The difference between this embodiment and embodiment 2 is that in this embodiment, an independent support frame 2 is used to support the heavier composite beam 1, that is, when the beam-column node of the heavier composite beam 1 is cast, the steel corbel 32 in embodiment 2 cannot stably support it, so an independent support frame 2 is provided in this embodiment to support it, and the I-beam 21 of the independent support frame 2 is used as a support seat. During construction, the I-beam 21 should be close to the side wall of the prefabricated column 3, and then a steel pipe 33 is built on the side wall of the prefabricated column 3 to hold and tighten the I-beam 21 and the prefabricated column 3, so as to realize the use of the prefabricated column 3 as a stable lateral support of the independent support frame 2, avoid the risk of collapse of the independent support frame 2, and ensure the stability of the support system.
[0074] When supporting the composite beam 1, the end of the composite beam 1 is placed on the support plate 20 on the top of the I-beam 21, the distance between the two fixed plates 18 is adjusted, and the fixed plates 18 are used to restrict the two sides of the composite beam 1 to prevent the composite beam 1 from sliding off the support plate 20, thereby achieving stable support of the composite beam 1 by the independent support frame 2.
[0075] In order to meet the needs of composite beams 1 of different widths in this embodiment, the distance between the two limit members arranged on the support plate 20 is adjustable, so a third threaded rod 24 and a strip hole 25 are provided. By adjusting the position of the third threaded rod 24 in the strip hole 25, the distance between the two fixed plates 18 is changed, thereby achieving support for composite beams 1 of different widths.
[0076] The I-beam 21 is further provided with a first rib plate 22 , and the first rib plate 22 is welded to the bottom of the support plate 20 .
[0077] In order to improve the connection strength of the support plate 20 on the I-beam 21 in this embodiment, first ribs 22 are provided on both sides of the I-beam 21 , and the first ribs 22 are used as reinforcing ribs between the support plate 20 and the I-beam 21 .
[0078] The fixing plate 18 is further provided with a second rib 19 , and the second rib 19 is welded to two ends of the fixing plate 18 .
[0079] Similarly, in order to improve the overall strength of the L-shaped fixing plate 18 in this embodiment, a second rib plate 19 is provided. The second rib plate 19 can improve the overall strength of the fixing plate 18 .
[0080] A wooden wedge 17 is also provided between the fixing plate 18 and the composite beam 1 .
[0081] In this embodiment, in order to improve the stability of the composite beam 1 between the fixed plates 18, a wooden wedge 17 is provided. When the composite beam 1 is lifted and placed between the fixed plates 18, the wooden wedge 17 is installed in the gap between the fixed plates 18 and the composite beam 1 by knocking. The squeezing force of the wooden wedge 17 on the composite beam is utilized to improve the stability of the composite beam 1 between the fixed plates 18.
[0082] Example 4
[0083] like Figures 8 to 13As shown, on the basis of Example 1, the vertical member attached support assembly includes a lower hoop, an upper hoop and a plurality of angle steel members 6, and the lower hoop and the upper hoop each include two first channel steels 4 and two tension bolts 5, and the tension bolts 5 are used to fix the two first channel steels 4 on the two opposite side walls of the prefabricated column 3, and to fix the angle steel member 6 on the edge of the prefabricated column 3; a second channel steel 9 is also placed on the first channel steel 4 of the upper hoop, and the second channel steel 9 and the first channel steel 4 are both connected to the angle steel member 6; and also include a plurality of support members 7 for supporting the composite beam 1, and the support members 7 are placed on the first channel steel 4 and the second channel steel 9 of the upper hoop.
[0084] The difference between this embodiment and embodiments 2 and 3 is that the vertical member attached support assembly in this embodiment adopts an upper hoop member and a lower hoop member to be connected to the upper end of the prefabricated column 3 in a detachable manner. The specific connection method is that the tension applied to the two first channel steels 4 by the tension bolts 5 is used to stably fix the first channel steel 4 on the side wall of the prefabricated column 3, thereby realizing a stable connection between the upper hoop member and the lower hoop member and the prefabricated column 3. At the same time, in order to improve the stability between the upper hoop member and the lower hoop member and the prefabricated column 3, the technical solution is further provided with an angle steel member 6 at the contact point between the first channel steel 4 and the prefabricated column 3, and the angle steel member 6 is located at the four edges of the prefabricated column 3. The force generated by the tension bolts 5 on the first channel steel 4 is used to stably fix the angle steel member 6 at the four edges of the prefabricated column 3. The angle steel member 6 can be used to realize the coordinated force and deformation between the upper hoop member and the lower hoop member, and the effect of getting tighter and tighter is achieved after the force is applied, thereby ensuring the stability of the upper and lower layers of hoops.
[0085] When the prefabricated column 3 is connected to the composite beam 1, according to the actual construction requirements, the two adjacent side walls of the top of the prefabricated column 3 will be connected to the composite beam 1, so that the two composite beams 1 on the prefabricated column 3 are in a vertical state. Therefore, in actual construction, in order to ensure that the upper hoop can support the composite beams 1 in two directions, a second channel steel 9 is still provided on the upper hoop, and the second channel steel 9 is also connected to the angle steel 6, so that the second channel steel 9 and the upper hoop and the lower hoop can also cooperate with the force and deformation, thereby improving the stability of the support system. When connecting with the composite beam 1, firstly, one of the composite beams 1 is hoisted on the top of the first channel steel 4 of the upper hoop, and the composite beam 1 is supported by the first channel steel 4; then, the composite beam 1 in the other direction is hoisted to the top of the second channel steel 9, and the composite beam 1 is supported by the second channel steel 9, thereby realizing the simultaneous support of two mutually perpendicular composite beams 1 on the prefabricated column 3.
[0086] In the actual support process, in order to ensure that the composite beam 1 and the top of the prefabricated column 3 are maintained at the same height, support members 7 are provided on the top of the first channel steel 4 and the second channel steel 9 of the upper clamp. The height of the support member 7 is optional. In actual construction, support members 7 of different heights are selected according to the distance between the top of the first channel steel 4 and the second channel steel 9 and the top of the prefabricated column 3. Finally, the support member 7 is used to support the composite beam 1, thereby ensuring that the composite beam 1 and the top of the prefabricated column 3 are maintained at the same height, which is convenient for subsequent casting and connection.
[0087] There are four angle steel pieces 6, which are respectively arranged at the four corners of the prefabricated column 3. The angle steel piece 6 includes two vertical plates 16 vertically connected to each other, and the right angle formed by the two vertical plates 16 is located at the edge of the prefabricated column 3; two first connecting rods 15 are arranged on one of the vertical plates 16, and the first channel steel 4 is provided with a first connecting hole, and the first connecting rod 15 is connected to the first nut after passing through the first connecting hole.
[0088] In this embodiment, in order to ensure that the upper hoop member and the lower hoop member can cooperate in force and deformation, and also to facilitate positioning and fastening during installation, two first connecting rods 15 are provided on the vertical plate 16 of the angle steel member 6. The two first connecting rods 15 are respectively connected to the first connecting holes on the first channel steels of the upper hoop member and the lower hoop member, so that the upper hoop member and the lower hoop member are formed to cooperate in force by utilizing the angle steel member 6, thereby improving the stability of the connection between the upper hoop member, the lower hoop member and the prefabricated column 3.
[0089] A second connecting rod 27 is further provided on the other vertical plate 16, and a second connecting hole is further provided on the second channel steel 9. The second connecting rod 27 passes through the second connecting hole and is connected to the second nut.
[0090] In order to achieve coordinated force and deformation between the second channel steel 9 and the upper hoop member in this embodiment, a second connecting rod 27 is further provided on the vertical plate 16. The second connecting rod 27 is connected to the second connecting hole to achieve connection between the second channel steel 9 and the angle steel member 6, thereby achieving coordinated force and deformation between the second channel steel 9 and the upper hoop member and the lower hoop member, thereby improving the supporting stability of the composite beam 1.
[0091] It also includes a plurality of rubber pads 12 , which are located between the vertical plate 16 and the side wall of the prefabricated column 3 .
[0092] In order to improve the stability of the angle steel piece 6 at the edge of the prefabricated column 3 in this embodiment, a rubber pad 12 is further provided. The rubber pad 12 can increase the friction between the angle steel piece 6 and the prefabricated column 3, thereby improving the stability of the angle steel piece 6 on the prefabricated column 3.
[0093] The thickness of the rubber pad 12 should not be less than 10 mm.
[0094] A first threaded rod 8 is further provided between the first channel steel 4 and the second channel steel 9 of the upper hoop member, and two ends of the first threaded rod 8 respectively penetrate the first channel steel 4 and the second channel steel 9 and are connected to the third nut.
[0095] In order to improve the stability between the upper clamping member and the second channel steel 9 in this embodiment, a first threaded rod 8 is also provided on the second channel steel 9. The first threaded rod 8 vertically penetrates the second channel steel 9 and the first channel steel 4 of the upper clamping member in sequence, and third nuts are installed at both ends of the first threaded rod 8, so that the second channel steel 9 can be stably fixed on the first channel steel 4.
[0096] The support member 7 includes a second threaded rod 11 and two steel wedges 10 with right-angled triangle cross-sections. The two ends of the second threaded rod 11 pass through the two steel wedges 10 respectively and are connected to a fourth nut, thereby forming the two steel wedges 10 into a rectangular structure.
[0097] In actual construction, it is necessary to reserve a casting template installation space at the casting node of the precast column 3 and the composite beam 1 so as to cast the beam-column casting point normally. Therefore, when installing the second channel steel 9 and the upper hoop, a certain distance is required from the top of the precast column 3. The composite beam 1 is supported by the support member 7 on the second channel steel 9 and the first channel steel 4 of the upper hoop, so that the support member 7 occupies a small space and can effectively support the composite beam 1. After completing the connection between the composite beam 1 and the precast column 3, in order to facilitate the disassembly of the support member 7 supported at the bottom of the composite beam 1, the support member 7 in this embodiment is spliced by two steel wedges 10. The two steel wedges 10 are connected into a rectangular structure by a second threaded rod 11 to support the composite beam 1. After completing the support of the composite beam 1, the fourth nut on the second threaded rod 11 is loosened, so that the two steel wedges 10 are easy to separate quickly, thereby facilitating the removal of the support member 7 from the bottom of the composite beam 1, so as to facilitate the subsequent removal of the second channel steel 9. , removal of the upper and lower clamping parts.
[0098] Example 5
[0099] On the basis of Example 1, it also includes independent support rods 64 for supporting the composite beam 1. In actual construction, the composite beam 1 is subjected to bearing capacity verification according to the load conditions during construction. If the supports at both ends cannot meet the requirements of the beam cross-section bearing capacity, deformation, or cracks, one or two independent support rods 64 may be added in the middle of the composite beam 1.
[0100] The independent support rod 64 includes a rectangular tube 65, a top plate 66 and two L-shaped limit plates 69. The top plate 66 is welded to the top of the rectangular tube 65. The limit plates 69 are fixed to the top plate 66 by limit bolts 67. During construction, one or two rectangular tubes 65 are set between two prefabricated columns 3, and the top plates 66 on the rectangular tubes 65 are used to support the composite beam 1 at different positions, thereby improving the overall support capacity of the composite beam 1; at the same time, a wooden wedge block 17 is also provided between the limit plate 69 and the composite beam 1, and the wooden wedge block 17 can be used to stably fix the composite beam 1 between the two limit plates 69.
[0101] Example 6
[0102] like Fig.14 As shown, on the basis of Example 1, the temporary support assembly 34 between columns includes two tie rods and a plurality of sleeves. Telescopic rods are provided at both ends of the tie rods. One end of the telescopic rod is connected to the tie rod by a thread, and the other end is provided with a connecting plate. The sleeve is pre-buried in the prefabricated column 3, and the connecting plate is connected to the sleeve by connecting bolts.
[0103] In order to improve the stability of each layer of the frame structure during construction, in this embodiment, a temporary support assembly 34 between columns needs to be added during the construction stage of each layer of the frame structure. One is set along the longitudinal and transverse directions of the structural plane. The temporary support assembly 34 between columns is composed of two cross-connected tie rods and sleeves. The sleeve is pre-buried in the prefabricated column 3. During construction, one end of a tie rod is first connected to the sleeve on a prefabricated column 3 through a connecting plate, and then the other end of the tie rod is connected to the sleeve on another prefabricated column 3. Finally, the other tie rod is connected to the sleeves on the two prefabricated columns 3 respectively to form a cross internal support structure. At the same time, in order to facilitate installation, telescopic rods are set at both ends of the tie rods. The telescopic rods are connected to the tie rods through threads. By rotating the telescopic rods, the protruding length of the telescopic rods on the tie rods can be adjusted. On the one hand, the supporting capacity of the temporary support assembly 34 between the columns to the prefabricated columns 3 can be adjusted to improve the stability of the composite beam 1. On the other hand, it can meet the use of prefabricated columns 3 with different spacings.
[0104] Example 7
[0105] like Fig.15 As shown, on the basis of Example 3, the temporary support assembly 34 between columns includes a pull rod, a connecting plate and a telescopic rod, wherein the telescopic rod is respectively located at both ends of the pull rod, and one end of the telescopic rod is connected to the pull rod by a thread, and the other end is connected to the connecting plate, which is welded to the side wall of the I-beam 21. The pull rod is used to support the I-beam 21 installed on the side wall of the prefabricated column 3, thereby improving the stability between the prefabricated columns 3, thereby improving the stability of the composite beam 1 on the prefabricated column 3.
[0106] Example 8
[0107] like Fig.16 As shown, on the basis of Example 4, the temporary support assembly 34 between columns includes a pull rod, a connecting plate, a telescopic rod and a sleeve. The sleeve is pre-buried in the lower section of the prefabricated column 3. The two ends of the pull rod are respectively threadedly connected to the telescopic rod, and the telescopic rod is connected to the connecting plate. The connecting plate on the telescopic rod at the lower end of the pull rod is connected to the sleeve at the lower section of the prefabricated column 3 through bolts. The connecting plate on the telescopic rod at the upper end of the pull rod is welded to the angle steel piece 6 on the prefabricated column 3, thereby fixing the temporary support assembly 34 between the prefabricated columns 3 to improve the stability of the composite beam 1.
[0108] Example 9
[0109] Based on Example 3, a connecting sleeve is pre-buried at the bottom of the composite beam 1, and a positioning bolt for connecting to the connecting sleeve is also provided at the bottom of the support plate 20 of the independent support frame 2, and the positioning bolt is threadedly connected to the connecting sleeve at the bottom of the composite beam 1.
[0110] When the independent support frame 2 in this embodiment temporarily supports the composite beam 1, in order to ensure that the horizontal stress of the composite beam 1 placed on the independent support frame 2 is effectively transmitted to the independent support frame 2 during the construction process, thereby improving the stable support of the composite beam 1 under the action of the independent support frame 2, a connecting sleeve for connecting with the bottom of the composite beam 1 is provided on the support plate 20 of the independent support frame 2, thereby realizing the temporary connection between the composite beam 1 and the independent support frame 2, ensuring that the horizontal stress generated by the composite beam 1 during the casting process with the prefabricated column 3 can be transmitted to the independent support frame 2, and the independent support frame 2 can be used to stably support the composite beam 1 in the horizontal direction.
[0111] Example 10
[0112] On the basis of Example 4, a connecting sleeve is pre-buried at the bottom of the composite beam 1 , and positioning bolts are provided on the second channel steel 9 and the first channel steel 4 , and the positioning bolts are threadedly connected to the connecting sleeve at the bottom of the composite beam 1 .
[0113] When the hoop support structure in this embodiment supports the composite beam 1, in order to ensure that the horizontal stress of the composite beam 1 placed on the second channel steel 9 and the first channel steel 4 is effectively transferred to the hoop structure support system during the construction process, the prefabricated column 3 is cooperated to improve the support stability of the composite beam 1. Therefore, positioning bolts are provided on the second channel steel 9 and the first channel steel 4. The positioning bolts are connected to the connecting sleeve at the bottom of the composite beam 1 to achieve a temporary connection between the composite beam 1 and the hoop support system, so that the horizontal stress generated by the composite beam 1 during the construction process can be transferred to the second channel steel 9 and the first channel steel 4, and the hoop support system on the prefabricated column 3 is used to improve the stability of the composite beam 1 in the horizontal direction.
[0114] Embodiment 11
[0115] like Figures 17 to 20 As shown, on the basis of Example 5, a partition 47 is further provided in the rectangular tube 65, a first airbag 48 is provided at the bottom of the partition 47, a second airbag 70 is provided at the top of the partition 47, a vertical rod 39 is provided on the second airbag 70, the vertical rod 39 passes through the top of the top plate 66, and a first tube body 53 is further provided at the bottom of the second airbag 70, and the first tube body 53 extends into the first airbag 48.
[0116] In order to increase the overall weight of the independent support rod 64 and facilitate on-site construction and installation, a rectangular tube 65 is used as the support rod. The interior of the rectangular tube 65 is a hollow structure. Although the weight of the independent support rod 64 is greatly reduced, the contact area between the bottom of the independent support rod 64 and the supporting plane is small, resulting in the rectangular tube 65 being prone to sliding during actual use. Therefore, in order to further improve the stability of the independent support rod 64 during use and avoid deflection and collapse during the support process, the first airbag 48 and the second airbag 70 are arranged in the rectangular tube 65. During construction, the rectangular tube 65 is vertically placed at the supporting position to place the composite beam 1 When lifted to the top of the top plate 66 and placed on the top plate 66, the composite beam 1 presses down on the vertical rod 39, forcing the bottom of the vertical rod 39 to compress the second airbag 70, and finally causing the gas inside the second airbag 70 to enter the first airbag 48 through the first tube body 53, forcing the first airbag 48 to expand in the bottom end of the rectangular tube 65, and finally filling the bottom of the rectangular tube 65 with the first airbag 48, so that the expanded first airbag 48 can effectively contact the supporting surface, thereby increasing the contact area between the rectangular tube 65 and the supporting plane, thereby increasing the friction resistance between the bottom of the rectangular tube 65 and the supporting plane, and improving the stability of the independent support rod 64 during use.
[0117] At the same time, in actual application, the vertical rod 39 is extended to a longer position on the top of the top plate 66 to ensure that the vertical rod 39 has a sufficient distance to compress the second airbag 70, so that the gas transferred from the second airbag 70 to the first airbag 48 can force the first airbag 48 to expand to protrude to the bottom of the rectangular tube 65, that is, the first airbag 48 expands and becomes larger at the bottom end of the rectangular tube 65, and the expanded first airbag 48 is used to contact the supporting plane, and the rectangular tube 65 is located on the expanded first airbag 48, and the first airbag 48 is used to support the rectangular tube 65, and the rectangular tube 65 supports the composite beam 1. This design further increases the first airbag 48. The contact area between the bag 48 and the supporting plane improves the stability of the independent support rod 64. On the other hand, since the independent support rod 64 is set as a temporary support, it is necessary to remove the independent support rod 64 after the casting of the node between the composite beam 1 and the prefabricated column 3 is completed. Since the bottom of the rectangular tube 65 is supported by the inflated first air bag 48, when the gas introduced into the first air bag 48 is discharged and the inflated first air bag 48 is deflated and restored to shape, the height of the rectangular tube 65 will gradually decrease, thereby removing the close contact of the top plate 66 to the composite beam 1, so that the independent support rod 64 can be quickly removed from the bottom of the composite beam 1, thereby improving construction efficiency.
[0118] The bottom side wall of the rectangular tube 65 is also provided with a notch, and a bellows 50 with closed structures at both ends is provided in the notch. The bellows 50 can be stretched in the horizontal direction after being inflated to change the length of the bellows 50. A transverse tube 49 is also provided in the first airbag 48, and the two ends of the transverse tube 49 respectively penetrate into the bellows 50 on both sides of the rectangular tube 65; the first tube body 53 is vertically connected to the transverse tube 49, and a first air hole 52 is provided on the side wall of the first tube body 53. A second tube body 59 is also provided in the first tube body 53, and the two ends of the second tube body 59 are both closed structures. A baffle is provided in the second tube body 59. Ring 58, first spring 57, sealing plate 56, the upper end of the second tube body 59 is provided with an air inlet hole, the air inlet hole is connected with the inside of the second tube body 59, the first spring 57 is used to push the sealing plate 56 to block the air inlet hole; the upper end side wall of the second tube body 59 is also provided with a second air hole 54, the lower end side wall of the second tube body 59 is provided with a third air hole, the second tube body 59 extends into the transverse tube 49, the transverse tube 49 is provided with a second spring 51, the second spring 51 pushes the upper end of the second tube body 59 to extend into the second airbag 70, and the third air hole is connected with the first air hole 52.
[0119] A push rod 40 located in the second air bag 70 is also provided at the bottom of the vertical rod 39, and the push rod 40 can extend into the air inlet of the second tube body 59 and push the sealing plate 56 to compress the first spring 57; a cavity is provided inside the push rod 40, and two fourth air holes connected to the cavity are provided on the side wall of the push rod 40, and the two fourth air holes are distributed along the axial direction of the push rod 40, and one of the fourth air holes is close to the bottom end of the push rod 40.
[0120] In order to further improve the stability of the rectangular tube 65 in use, bellows 50 are provided on both sides of the bottom end of the rectangular tube 65 in the present embodiment. In the initial state, when the top of the rectangular tube 65 does not support the composite beam 1, the second airbag 70 is not in a compressed state. At this time, the push rod 40 at the bottom of the vertical rod 39 does not extend into the air inlet hole of the second tube body 59. At this time, the upper end of the second tube body 59 extends into the second airbag 70 under the action of the second spring 51, so that the second air hole 54 on the second tube body 59 connects the second airbag 70 with the second tube body 59, and the second tube body 59 is The third air hole is just aligned with the first air hole 52. Therefore, when the composite beam 1 is placed on the top plate 66 of the rectangular tube 65, the composite beam 1 presses down the vertical rod 39, and the second airbag 70 is compressed at the vertical rod 39, so that the gas in the second airbag 70 enters the second tube body 59 through the second air hole 54 on the second tube body 59, and the gas entering the second tube body 59 enters the first airbag 48 through the third air hole and the first air hole 52 in turn, thereby achieving the purpose of inflating the first airbag 48, so that the first airbag 48 expands at the bottom of the rectangular tube 65 and supports the rectangular tube 65.
[0121] When the push rod 40 is inserted into the air inlet of the second tube body 59 and gradually extends into the second tube body 59, when the sealing plate 56 pushed by the push rod 40 compresses the first spring 57 to the minimum deformation, the push rod 40 will push the second tube body 59 to compress the second spring 51 while continuing to move downward, and finally push the second tube body 59 into the cross tube 49, and use the third air hole on the side wall of the second tube body 59 to connect the second tube body 59 with the cross tube 49. At this time, while the vertical rod 39 continues to compress the second airbag 70, the gas inside the second airbag 70 will enter the second tube body 59 through the fourth air hole on the side wall of the push rod 40, and then the gas will enter the bellows 50 through the cross tube 49, forcing the bellows 50 to expand and stretch in the vertical direction, further improving the stability of the rectangular tube 65.
[0122] The partition plate 47 in the rectangular tube 65 is also provided with a connecting tube 46 and a third airbag 45. The connecting tube 46 is sleeved on the second airbag 70. The third airbag 45 is sleeved on the connecting tube 46. The third airbag 45 is also provided with a third tube body 41. The third tube body 41 is provided with a one-way valve to ensure that the gas in the third airbag 45 enters the second airbag 70 through the one-way valve, while the gas in the second airbag 70 cannot flow back into the third airbag 45. The side wall of the rectangular tube 65 is also provided with a strip opening 42. A movable rod 43 is also provided in the strip-shaped opening 42, and the movable rod 43 is connected to the third airbag 45. A channel 61 connected to the third airbag 45 is provided inside the movable rod 43. An air suction hole is provided on the movable rod 43, and a blocking rod 62 is provided in the air suction hole. A T-shaped entrance 63 is provided inside the blocking rod 62. A third spring 60 is also provided in the channel 61, and the third spring 60 is connected to the blocking rod 62. When the third spring 60 is in a natural state, the entrance 63 connects the outside with the channel 61.
[0123] In order to reduce the length of the vertical rod 39 extending outside the top of the top plate 66 and ensure that after the top of the vertical rod 39 is retracted into the top plate 66, the squeezing of the second airbag 70 by the vertical rod 39 can satisfy the expansion of the first airbag 48, without passing the gas squeezed by the second airbag 70 into the bellows 50, a third airbag 45 is provided. When the composite beam 1 is placed on the top plate 66 of the rectangular tube 65, the rectangular tube 65 is supported by the inflated first airbag 48, and the construction personnel press the blocking rod 62 with their palms so that the blocking rod 62 is pressed into the suction hole. At this time, the channel 61 in the movable rod 43 and the The outside is in a disconnected state, which is used to push down the movable rod 43. The movable rod 43 drives the third airbag 45 to be compressed, and transfers the gas in the third airbag 45 to the second airbag 70 through the third tube body 41. Since the second airbag 70 is outerly provided with a connecting tube 46, the connecting tube 46 is used to constrain the expansion of the second airbag 70, so that the gas entering the second airbag 70 cannot expand the second airbag 70. The gas entering the second airbag 70 can only enter the second tube body 59 through the push rod 40, and then enter the bellows 50 through the cross tube 49, so as to achieve the purpose of expanding the bellows 50 in the horizontal direction.
[0124] Plugs 44 are provided on the bellows 50 and the first airbag 48, and the plugs 44 are connected to the bellows 50 and the first airbag 48 through threads. Therefore, after the construction is completed, when it is necessary to quickly remove the rectangular tube 65 from the bottom of the composite beam 1, the plugs 44 on the bellows 50 and the first airbag 48 are removed, so that the internal gas of the inflated first airbag 48 and the bellows 50 can be discharged, so that the first airbag 48 and the bellows 50 can quickly restore their deformation and reduce the height of the rectangular tube 65, thereby facilitating the rapid disassembly of the independent support rod 64.
[0125] A fourth spring is further disposed in the second airbag 70 , and the fourth spring is used to support the vertical rod 39 .
[0126] The specific implementation methods described above further illustrate the objectives, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above description is only a specific implementation method of the present invention and is not intended to limit the scope of protection of the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.
Claims
1. The multi-story frame structure uses an assembled construction method with vertical member attachment support, which is characterized by: The following steps are involved: 1) Installing the vertical member attachment support assembly on the side wall of the prefabricated column (3); 2) constructing temporary inter-column support components (34) between the prefabricated columns (3); 3) using a lifting device to lift the composite beam (1) to a construction height, and using a vertical member attached support assembly to support the composite beam (1); 4) Casting the ends of the composite beam (1) and the tops of the prefabricated columns (3) to form a frame structure, and when the node strength reaches the design strength, removing the vertical member attached support assembly installed on the prefabricated columns (3); 5) Casting a lug on the side wall of the composite beam (1), and installing the floor slab (28) on the lug of the composite beam (1); 6) performing a pouring process of a superimposed layer on the superimposed plate of the floor slab (28); 7) Repeat steps 1) to 6) to continue constructing the next layer of frame structure; It also includes an independent support rod (64) for supporting the composite beam (1), wherein one or two independent support rods (64) are additionally provided in the middle of the span of the composite beam (1), wherein the independent support rod (64) includes a rectangular tube (65), a top plate (66), and two L-shaped limiting plates (69), wherein the top plate (66) is welded to the top of the rectangular tube (65), and the limiting plates (69) are fixed to the top plate (66) by limiting bolts (67); A partition (47) is further provided in the rectangular tube (65), a first airbag (48) is provided at the bottom of the partition (47), a second airbag (70) is provided at the top of the partition (47), a vertical rod (39) is provided on the second airbag (70), the vertical rod (39) penetrates to the top of the top plate (66), a first tube body (53) is further provided at the bottom of the second airbag (70), and the first tube body (53) extends into the first airbag (48); The bottom side wall of the rectangular tube (65) is also provided with a notch, and a bellows (50) with closed structures at both ends is provided in the notch. After the bellows (50) is inflated, it can be stretched in the horizontal direction to change the length of the bellows (50). A transverse tube (49) is also provided in the first airbag (48), and the two ends of the transverse tube (49) respectively penetrate into the bellows (50) on both sides of the rectangular tube (65). The first tube body (53) is vertically connected to the transverse tube (49), and a first air hole (52) is provided on the side wall of the first tube body (53). A second tube body (59) is also provided in the first tube body (53), and the two ends of the second tube body (59) are closed structures. A retaining ring is provided in the second tube body (59). (58), a first spring (57), a blocking plate (56), an upper end portion of the second tube (59) being provided with an air inlet hole, the air inlet hole being communicated with the interior of the second tube (59), the first spring (57) being used to push the blocking plate (56) to block the air inlet hole; a second air hole (54) being further provided on the upper end side wall of the second tube (59), a third air hole being provided on the lower end side wall of the second tube (59), the second tube (59) extending into the transverse tube (49), a second spring (51) being provided in the transverse tube (49), the second spring (51) pushing the upper end portion of the second tube (59) to extend into the second air bag (70), and the third air hole being communicated with the first air hole (52); A push rod (40) located in the second air bag (70) is also provided at the bottom of the vertical rod (39), a cavity is provided inside the push rod (40), and two fourth air holes communicating with the cavity are provided on the side wall of the push rod (40); The temporary support assembly (34) between columns comprises two tie rods and a plurality of sleeves. Telescopic rods are provided at both ends of the tie rods. One end of the telescopic rod is connected to the tie rods via a thread, and the other end is provided with a connecting plate. The sleeves are pre-buried in the prefabricated columns (3), and the connecting plates are connected to the sleeves via connecting bolts.
2. The method for assembling a multi-story frame structure using vertical member attachment support according to claim 1 is characterized in that: The vertical member attached support assembly comprises a steel corbel (32) and a fourth threaded rod (31); the fourth threaded rod (31) penetrates the prefabricated column (3) and is connected to the steel corbel (32).
3. The method for assembling a multi-story frame structure using vertical member attachment support according to claim 1, characterized in that: The vertical member attached support assembly comprises an independent support frame (2), the independent support frame (2) comprises an I-beam (21), a support plate (20) and two stoppers, the support plate (20) is welded to the top of the I-beam (21), the two stoppers are symmetrically arranged on the top of the support plate (20), and the composite beam (1) is located between the two stoppers; The limiting member comprises an L-shaped fixing plate (18), a third threaded rod (24), and a gasket (26); The support plate (20) is provided with a strip hole (25), and the third threaded rod (24) vertically penetrates the gasket (26), the fixing plate (18) and the strip hole (25) in sequence, and both ends of the third threaded rod (24) are also connected to fifth nuts to fix the fixing plate (18) on the support plate (20).
4. The method for assembling a multi-story frame structure using vertical member attachment support according to claim 3 is characterized in that: The I-beam (21) is also provided with a first rib plate (22), and the first rib plate (22) is welded to the bottom of the support plate (20); The fixing plate (18) is also provided with a second rib plate (19), and the second rib plate (19) is welded to both ends of the fixing plate (18); A wooden wedge (17) is also provided between the fixing plate (18) and the composite beam (1).
5. The method for assembling a multi-story frame structure using vertical member attachment support according to claim 1, characterized in that: The vertical member attachment support assembly comprises a lower hoop member, an upper hoop member and a plurality of angle steel members (6), wherein the lower hoop member and the upper hoop member each comprise two first channel steels (4) and two tension bolts (5), wherein the tension bolts (5) are used to fix the two first channel steels (4) on two opposite side walls of the prefabricated column (3), and to fix the angle steel member (6) on the edge of the prefabricated column (3); A second channel steel (9) is also placed on the first channel steel (4) of the upper hoop member, and the second channel steel (9) and the first channel steel (4) are both connected to the angle steel member (6); It also includes a plurality of support members (7) for supporting the composite beam (1), wherein the support members (7) are placed on the first channel steel (4) and the second channel steel (9) of the upper hoop member.
6. The method for assembling a multi-story frame structure using vertical member attachment support according to claim 5 is characterized in that: The angle steel member (6) comprises two vertical plates (16) connected perpendicularly to each other, and the right angle formed by the two vertical plates (16) is located at the edge of the prefabricated column (3); Two first connecting rods (15) are arranged on one of the vertical plates (16), and first connecting holes are arranged on the first channel steels (4). The first connecting rods (15) pass through the first connecting holes and are connected to the first nuts.
7. The method for assembling a multi-story frame structure using vertical member attachment support according to claim 6 is characterized in that: A second connecting rod (27) is further provided on the other vertical plate (16), and a second connecting hole is further provided on the second channel steel (9), and the second connecting rod (27) passes through the second connecting hole and is connected to the second nut; It also includes a plurality of rubber pads (12), wherein the rubber pads (12) are located between the vertical plate (16) and the side wall of the prefabricated column (3).
8. The method for assembling a multi-story frame structure using vertical member attachment support according to claim 5, characterized in that: A first threaded rod (8) is further provided between the first channel steel (4) and the second channel steel (9) of the upper hoop member, and two ends of the first threaded rod (8) respectively penetrate the first channel steel (4) and the second channel steel (9) and are then connected to a third nut; The support member (7) comprises a second threaded rod (11) and two steel wedges (10) with right-angled triangle cross-sections, wherein two ends of the second threaded rod (11) respectively penetrate the two steel wedges (10) and are connected to a fourth nut, thereby forming a rectangular structure with the two steel wedges (10).
Citation Information
Patent Citations
New pre-cast concrete column to pre-cast concrete beam connection
CA2433164A1
Mechanical hydraulic supporting leg for changing stress area size of base by means of expansion and shrinkage of air bag
CN109854869A
Fabricated building construction load self-bearing system and construction method thereof
CN114232791A
Beam quick-release support frame
CN115233977A
Novel gate-type scaffold and erecting method
CN116856660A