A method for positioning weld seams in steel pipe sections of wind turbines

By using the clock scale method and the overall structural diagram in the weld positioning method of wind power steel structure pipe sections, the problems of intersection and proximity caused by the complexity of weld positions were solved, ensuring that the weld positions meet the specifications and simplifying the operation process.

CN117961416BActive Publication Date: 2026-11-17GUANGZHOU WENCHUAN HEAVY IND
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202410314272.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-03-19
Publication Date
2026-11-17
Estimated Expiration
2044-03-19

AI Technical Summary

Technical Problem

The weld locations of wind turbine steel structures are complex and tend to overlap or be close together during design and fabrication, leading to non-compliance with weld location specifications.

Method used

A method for locating weld seams in wind power steel structure pipe sections is adopted. The position of the longitudinal weld seam is specified in the right view of the pipe section by using the clock scale method, and a weld seam positioning system is established on the jacket in combination with the overall structural drawing to ensure the accurate position of the weld seam in the overall structure.

Benefits of technology

It achieves the avoidance of weld no-weld zones during the design and manufacturing process, has a complete weld positioning system, and is simple to operate, easy to understand and implement.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117961416B_ABST
    Figure CN117961416B_ABST
Patent Text Reader

Abstract

This invention discloses a method for locating weld seams in wind turbine steel structure pipe sections. The method involves laying the pipe section flat and viewing it from right to left. The longitudinal weld seams of each pipe section are positioned according to clock scale markings. Specifically, the longitudinal weld seam located at the top of the pipe section in the right view is designated as the 12 o'clock position; the longitudinal weld seam located at the bottom is designated as the 6 o'clock position; the longitudinal weld seam located to the right is designated as the 3 o'clock position; the longitudinal weld seam located to the left is designated as the 9 o'clock position, and so on. The position of each longitudinal weld seam in the right view corresponds to a clock scale marking. This invention, combined with the positioning method within the overall structure, allows for the specification of the position of each longitudinal weld seam within the overall wind turbine steel structure, thereby preventing longitudinal weld seams from appearing in no-weld zones during design, manufacturing, and construction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of offshore wind power steel structure processing and fabrication technology, and in particular to a method for positioning weld seams in wind power steel structure pipe sections. Background Technology

[0002] Wind power steel structures include onshore and offshore wind power steel structures. Onshore wind power steel structures generally refer to the tower structure supporting the wind turbine. Offshore wind power steel structures include offshore wind turbine towers, wind turbine monopiles, wind turbine jackets, and wind turbine substation jackets. To ensure good stress distribution, wind power steel structures generally adopt large-diameter steel cylinders or steel pipe trusses. Due to the large diameter of the steel pipes and the large structural dimensions, most wind power steel structures are constructed by splicing straight-seam pipe sections made from steel plates. Wind power steel structures have high structural requirements due to their complex stress distribution. During the design phase, to ensure structural lifespan and avoid weld fatigue failure, special regulations are set for the location of structural welds. Generally, it is required that the splicing seams and corner seams of pipe sections do not intersect and must maintain a certain distance and angle (i.e., to ensure weld distance, certain locations on the structural steel pipes are designated as weld-prohibited zones). Wind power steel structures are generally constructed by welding together various straight-seam pipe sections of different sizes. Their relative positions are diverse and complex. If the design and specifications are not clear and specific during construction, it is easy for the welds to intersect or be too close together. To ensure that the design and fabrication positions of the structural welds meet the specified misalignment requirements, a reasonable and highly operable method for positioning structural welds needs to be developed. Summary of the Invention

[0003] To address the shortcomings of existing technologies in wind turbine steel structures, such as numerous straight-seam pipe sections, complex weld locations, and the tendency for welds to intersect and become too close together during design and fabrication, thus failing to meet technical requirements for staggered welds and maintaining a certain distance, a new weld positioning method for wind turbine steel structures is designed and developed. This method ensures that the position of welds on each pipe section during all stages of the design and manufacturing process of wind turbine steel structures meets specifications and technical requirements.

[0004] This invention is achieved through the following technical solution:

[0005] A method for locating weld seams in wind turbine steel structure pipe sections, comprising the following steps:

[0006] Step S1: Formation of pipe section welds. The pipe sections of the main structure of the wind turbine jacket are made by welding flat steel plates after rolling. After a pipe section is made, 1 to 2 longitudinal straight welds will be formed. The longitudinal straight welds of the pipe sections need to be positioned during the design and construction of the main structure of the jacket.

[0007] Step S2, the positioning specifications for the pipe section weld include:

[0008] Step S21: Formation of pipe segment welds. Based on the design length of the circular pipe structure, combined with the factory's equipment resources and manufacturing process, each circular pipe structure is divided into one or more pipe segments; each pipe segment is spliced ​​together from multiple pipe sections, and each pipe segment has multiple longitudinal welds of pipe sections and circumferential welds between pipe sections.

[0009] Step S22: Positioning of pipe section welds. Lay the pipe section flat and observe from right to left, i.e., the right view of the pipe section, which is a circular steel pipe cross-section. Position the longitudinal welds of each pipe section according to the clock scale. That is, the longitudinal weld of the pipe section located at the top in the right view of the pipe section is designated as the 12 o'clock position, the longitudinal weld of the pipe section located at the bottom in the right view of the pipe section is designated as the 6 o'clock position, the longitudinal weld of the pipe section located to the right in the right view of the pipe section is designated as the 3 o'clock position, the longitudinal weld of the pipe section located to the left in the right view of the pipe section is designated as the 9 o'clock position, and so on. The position of the longitudinal weld of the pipe section corresponding to the time scale of the clock in the right view of the pipe section is designated as the position of the weld.

[0010] Step S3: Positioning specifications for the main chord pipe section welds on the overall jacket structure.

[0011] To ensure the smooth integration of the weld positioning system for each structural pipe section into the overall structure of the jacket, a longitudinal weld positioning system for each pipe section is established using the top view of the jacket as the reference. In the top view of the jacket, with the center point of the jacket as the origin, the center point is connected to the lower center of each main chord pipe. This connection line is defined as the corresponding position lines of the 12 o'clock and 6 o'clock longitudinal pipe seams of each main chord pipe section. The position closer to the outside of the jacket is the 12 o'clock pipe seam position, and the position closer to the inside of the jacket is the 6 o'clock pipe seam position.

[0012] Step S4: Positioning specifications for the weld seam of the side bracing pipe section on the guide frame.

[0013] To ensure the smooth integration of the weld positioning system for each side of the inclined support pipe section into the overall structure of the jacket, when viewing each inclined support plate of the jacket from top to bottom (i.e., the top view of the jacket), along the axis where the plate is located, place the side of the inclined support plate closest to the inside of the jacket on the left and the side of the inclined support plate closest to the outside of the jacket on the right. Then, the top is 12 o'clock, the bottom is 6 o'clock, the right is 3 o'clock, and the left is 9 o'clock.

[0014] As a further improvement to the technical solution of the invention, in step S22, laying the pipe segment flat specifically means: placing the lower end of the pipe segment in the overall structure of the guide frame on the left side, placing the upper end of the pipe segment in the overall structure on the right side, placing the outer side of the pipe segment in the overall structure on the upper side, and placing the inner side of the pipe segment in the overall structure on the lower side.

[0015] The present invention has the following beneficial effects:

[0016] 1) By using the positioning method of the pipe section welds in the pipe segment, combined with the positioning method in the overall structure, the position of the longitudinal welds of each pipe segment in the overall wind power steel structure can be specified, thereby avoiding the occurrence of the longitudinal welds of the pipe segments in the no-welding zone during design, manufacturing and construction.

[0017] 2) The pipe section weld positioning method includes all construction procedures such as pipe section splicing, pipe segment splicing, panel assembly, and structural assembly, covering all procedures in the entire product manufacturing process, and the pipe section weld positioning system is complete.

[0018] 3) The method of locating the longitudinal joints of pipe sections using a clock scale is very simple, easy to understand and express. It is also easier for technicians and construction workers to operate. Attached Figure Description

[0019] Figure 1 This is a side view of the longitudinal joint positioning of the pipe section according to an embodiment of the present invention;

[0020] Figure 2 This is a diagram showing the positioning of the longitudinal joint of the pipe section in the right view according to an embodiment of the present invention (right view of the pipe section);

[0021] Figure 3 This is a top view diagram of the longitudinal joint positioning of a pipe section according to an embodiment of the present invention (top view of the pipe section);

[0022] Figure 4 This is a top view of the weld positioning of the inclined support pipe section according to an embodiment of the present invention.

[0023] In the attached diagram: 1-Main chord pipe; 2-Diagonal bracing pipe. Detailed Implementation

[0024] The present invention will now be described in detail with reference to the accompanying drawings and specific embodiments. The illustrative embodiments and descriptions of the present invention are used to explain the present invention, but are not intended to limit the present invention.

[0025] It should be noted that all directional indicators (such as up, down, left, right, front, back, upper end, lower end, top, bottom, etc.) in the embodiments of the present invention are only used to explain the relative positional relationship and movement of each component in a certain specific posture (as shown in the figure). If the specific posture changes, the directional indicator will also change accordingly.

[0026] In this invention, unless otherwise explicitly specified and limited, the term "connection" should be interpreted broadly. For example, "connection" can be a fixed connection, a detachable connection, or an integral part; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium; it can be the internal communication of two components or the interaction between two components, unless otherwise explicitly limited. Those skilled in the art can understand the specific meaning of the above terms in this invention according to the specific circumstances.

[0027] Furthermore, in this invention, descriptions involving "first," "second," etc., are for descriptive purposes only and should not be construed as indicating or implying their relative importance or implicitly specifying the number of technical features indicated. Thus, a feature defined with "first" or "second" may explicitly or implicitly include at least one of that feature. Additionally, the technical solutions of various embodiments can be combined with each other, but only on the basis of being achievable by those skilled in the art. If the combination of technical solutions is contradictory or impossible to implement, such a combination should be considered non-existent and not within the scope of protection claimed by this invention.

[0028] The following is in conjunction with the appendix Figure 1-4 The present invention will be described in further detail below.

[0029] This invention relates to a method for locating weld seams in wind turbine steel structure pipe sections. By combining the method for locating weld seams within pipe sections with a method for locating weld seams within the overall structure, the location of longitudinal weld seams in each pipe section within the overall wind turbine steel structure can be specified. This prevents longitudinal weld seams from appearing in no-weld zones during design, manufacturing, and construction. The method includes the following steps:

[0030] Step S1: Formation of pipe section welds. The pipe sections of the main structure of the wind turbine jacket are made by welding flat steel plates after rolling. After a pipe section is made, 1 to 2 longitudinal straight welds will be formed. The longitudinal straight welds of the pipe sections need to be positioned during the design and construction of the main structure of the jacket.

[0031] Step S2, the positioning specifications for the pipe section weld include:

[0032] Step S21: Formation of pipe segment welds. Based on the design length of the circular pipe structure, combined with the factory's equipment resources and manufacturing process, each circular pipe structure is divided into one or more pipe segments; each pipe segment is spliced ​​together from multiple pipe sections, and each pipe segment has multiple longitudinal welds of pipe sections and circumferential welds between pipe sections.

[0033] Step S22: Positioning of pipe section welds. Lay the pipe section flat (place the lower end of the pipe section in the overall structure of the jacket framework on the left, the upper end on the right, the outer side on the top, and the inner side on the bottom). Observe from right to left, i.e., the right view of the pipe section, which is a circular steel pipe cross-section. Position the longitudinal welds of each pipe section according to the clock scale. Specifically, the longitudinal weld of the pipe section directly above in the right view is designated as the 12 o'clock position; the longitudinal weld of the pipe section directly below is designated as the 6 o'clock position; the longitudinal weld of the pipe section directly to the right is designated as the 3 o'clock position; the longitudinal weld of the pipe section directly to the left is designated as the 9 o'clock position, and so on. The position of the longitudinal weld of the pipe section corresponding to the clock scale in the right view is defined as the position of that weld. For example... Figure 1 and Figure 2 As shown.

[0034] Step S3: The positioning specifications of the weld seam of the main chord pipe section 1 on the overall structure of the jacket support.

[0035] To ensure the smooth integration of the weld positioning system for each structural pipe segment into the overall structure of the jacket support, a longitudinal weld positioning system for each pipe segment is established using the top view of the jacket support as the reference drawing. In the top view of the jacket support, with the center point of the jacket support as the origin, a line is drawn connecting the center point to the lower center of each main chord pipe 1. This line is defined as the corresponding position lines for the longitudinal welds at the 12 o'clock and 6 o'clock points of each main chord pipe segment. The line closer to the outside of the jacket support is the position of the 12 o'clock weld, and the line closer to the inside of the jacket support is the position of the 6 o'clock weld. Figure 3 As shown.

[0036] Step S4: Positioning specifications for the weld seam of the side bracing pipe section 2 on the guide frame.

[0037] To ensure the smooth integration of the weld positioning system for the two pipe sections of the diagonal bracing on each side into the overall structure of the jacket support, the diagonal bracing plates of the jacket support are positioned as follows: looking down at each diagonal bracing plate (top view of the jacket support), along the axis of the plate, the inner side of the diagonal bracing plate is placed on the left, and the outer side is placed on the right. Therefore, the position is: 12 o'clock directly above, 6 o'clock directly below, 3 o'clock directly to the right, and 9 o'clock directly to the left. Figure 4 As shown.

[0038] Compared with existing technologies, the present invention has the following advantages:

[0039] 1) By using the positioning method of the pipe section welds in the pipe segment, combined with the positioning method in the overall structure, the position of the longitudinal welds of each pipe segment in the overall wind power steel structure can be specified, thereby avoiding the occurrence of the longitudinal welds of the pipe segments in the no-welding zone during design, manufacturing and construction.

[0040] 2) The pipe section weld positioning method includes all construction procedures such as pipe section splicing, pipe segment splicing, panel assembly, and structural assembly, covering all procedures in the entire product manufacturing process, and the pipe section weld positioning system is complete.

[0041] 3) The method of locating the longitudinal joints of pipe sections using a clock scale is very simple, easy to understand and express. It is also easier for technicians and construction workers to operate.

[0042] The technical solutions provided by the embodiments of the present invention have been described in detail above. Specific examples have been used to illustrate the principles and implementation methods of the embodiments of the present invention. The descriptions of the embodiments above are only for helping to understand the principles of the embodiments of the present invention. At the same time, for those skilled in the art, there will be changes in the specific implementation methods and application scope based on the embodiments of the present invention. Therefore, the content of this specification should not be construed as a limitation of the present invention.

Claims

1. A method for locating weld seams in wind turbine steel structure pipe sections, characterized in that, Includes the following steps: Step S1: Formation of pipe section welds. The pipe sections of the main structure of the wind turbine jacket are made by welding flat steel plates after rolling. After a pipe section is made, 1 to 2 longitudinal straight welds will be formed. The longitudinal straight welds of the pipe sections need to be positioned during the design and construction of the main structure of the jacket. Step S2, the positioning specifications for the pipe section weld include: Step S21: Formation of pipe segment welds. Based on the design length of the circular pipe structure, combined with the factory's equipment resources and manufacturing process, each circular pipe structure is divided into one or more pipe segments; each pipe segment is spliced ​​together from multiple pipe sections, and each pipe segment has multiple longitudinal welds of pipe sections and circumferential welds between pipe sections. Step S22: Positioning of pipe section welds. Lay the pipe section flat and observe from right to left, i.e., the right view of the pipe section, which is a circular steel pipe cross-section. Position the longitudinal welds of each pipe section according to the clock scale. That is, the longitudinal weld of the pipe section located at the top in the right view of the pipe section is designated as the 12 o'clock position, the longitudinal weld of the pipe section located at the bottom in the right view of the pipe section is designated as the 6 o'clock position, the longitudinal weld of the pipe section located to the right in the right view of the pipe section is designated as the 3 o'clock position, the longitudinal weld of the pipe section located to the left in the right view of the pipe section is designated as the 9 o'clock position, and so on. The position of the longitudinal weld of the pipe section corresponding to the time scale of the clock in the right view of the pipe section is designated as the position of the weld. Step S3: Positioning specifications for the main chord pipe section welds on the overall jacket structure. To ensure the smooth integration of the weld positioning system for each structural pipe section into the overall structure of the jacket, a longitudinal weld positioning system for each pipe section is established using the top view of the jacket as the reference. In the top view of the jacket, with the center point of the jacket as the origin, the center point is connected to the lower center of each main chord pipe. This connection line is defined as the corresponding position lines of the 12 o'clock and 6 o'clock longitudinal pipe seams of each main chord pipe section. The position closer to the outside of the jacket is the 12 o'clock pipe seam position, and the position closer to the inside of the jacket is the 6 o'clock pipe seam position. Step S4: Positioning specifications for the weld seam of the side bracing pipe section on the guide frame. To ensure the smooth integration of the weld positioning system for each side of the inclined support pipe section into the overall structure of the jacket, when viewing each inclined support plate of the jacket from top to bottom (i.e., the top view of the jacket), along the axis where the plate is located, place the side of the inclined support plate closest to the inside of the jacket on the left and the side of the inclined support plate closest to the outside of the jacket on the right. Then, the top is 12 o'clock, the bottom is 6 o'clock, the right is 3 o'clock, and the left is 9 o'clock.

2. The method for positioning weld seams in wind power steel structure pipe sections according to claim 1, characterized in that: In step S22, laying the pipe segment flat specifically involves placing the lower end of the pipe segment in the overall structure of the guide frame on the left side, placing the upper end of the pipe segment in the overall structure on the right side, placing the outer side of the pipe segment in the overall structure on the upper side, and placing the inner side of the pipe segment in the overall structure on the lower side.

Citation Information

Patent Citations

  • Construction process of 1600T mast crane upper mast

    CN107717346A

  • Manufacturing method of eccentric jacket

    CN113146109A

  • Combined outer protective pipe for heat supply pipeline field joint heat preservation

    CN209671843U