A cover conversion structure considering time and space effects

Through the design of the stacked plate structure, combined with the initial one-layer curved cover plate and the later cast-in-place overlap layer, the reserved anti-shear and anchor connections are used to solve the uncertainty of the time and position changes of the cover plate conversion structure, and realizes the Flexible structural adaptability and stress reliability avoid structural reinforcement and initial damage.

CN117988390BActive Publication Date: 2024-11-08WENZHOU DESIGN ASSEMBLY CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410251693.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-03-05
Publication Date
2024-11-08
Estimated Expiration
2044-03-05

AI Technical Summary

Technical Problem

There is uncertainty in the existing cover conversion structure when considering time and position changes, which is difficult to meet the needs of future building planning changes, and it is easy to cause structural reinforcement and initial structural damage when building additional buildings.

Method used

The structure design of the laminated plate is adopted. The initial first-layer curved cover is combined with the later cast-in-place superposition layer. By retaining anti-shear and anchor connections, a flexible bottom frame support structure is formed to avoid large-area reinforcement and initial structural damage.

Benefits of technology

A structural design that adapts to future urban development and changes has been realized, providing flexible space utilization methods, ensuring that the conversion layer still meets the planning changes in the future, and avoids damage to the initial structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117988390B_ABST
    Figure CN117988390B_ABST
Patent Text Reader

Abstract

The present invention discloses a cover plate conversion structure that takes time and space effects into consideration. The cover plate conversion structure is designed as a composite plate structure combined with a main beam, wherein the upper surface of the initial layer of curved cover plates is corrugated, and the elevation is lower than the elevation of the main beam surface; according to the use requirements of different time periods, the cover plate structure is divided into two situations, the initial layer of curved cover plates and the temporary pavement are combined to form an initial upper complete large space; when the upper building is constructed in the later stage, the cast-in-place composite layer is used to replace the temporary pavement to form a conversion structure including the additional upper structure in the later stage. When the later addition is made, the cast-in-place composite layer and the initial layer of curved cover plates are engaged through the corrugated surface, and the same shear-resistant parts are used in the later stage to weld and connect with the shear-resistant parts reserved in the early stage, so as to ensure the reliability of the composite conversion plate. The present invention solves the uncertainty of the construction time and position of the upper building of the conversion layer, improves the flexibility of the space utilization of the conversion layer, and improves the secondary force problem of the conversion of the composite thick plate.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a cover plate conversion structure, in particular to a cover plate conversion structure taking time and space effects into consideration. Background Art

[0002] The construction time of buildings above the transfer layer is uncertain. They may be built several years or even more than ten years later. The influence of time effect needs to be considered when designing such transfer layers. The transfer layer is constructed in two stages. It is necessary to consider the use demand of the floor after the initial construction of the cover plate and the feasibility of adding the upper building later. There is uncertainty in the location of the building above the transfer layer, that is, the location of the upper building may change due to planning or demand changes after several years. In this case, the transfer layer needs to consider the structural structure of the change in the location of the upper building to avoid connecting the additional building through embedded reinforcement. At the same time, the bearing capacity of the transfer layer should be considered to avoid large-scale structural reinforcement in the later stage. Summary of the invention

[0003] The purpose of the present invention is to overcome the shortcomings of the prior art and provide a cover plate conversion structure that takes into account the time and space effects. The conversion layer is designed as a composite plate structure, which is divided into an initial layer of curved cover plate and a later two layers of composite plates. One layer of plate considers the initial applicability, and the composite plate is a conversion layer plate added later.

[0004] The present invention adopts the following technical scheme: a cover conversion structure that takes time and space effects into consideration, comprising frame pillars, cover main beams, an initial layer of curved cover, a temporary pavement, a cast-in-place composite layer and an upper structure; the initial layer of curved cover, the cover main beams and the frame pillars together form a bottom frame support structure, the cover main beams are fixed to the frame pillars, and the upper part of the cover main beams is turned up so that its top elevation is higher than the initial layer of curved cover, and its elevation is determined according to the design elevation of the later floor surface; the initial layer of curved cover is covered with a temporary pavement on its upper part during initial use, and the top of the temporary pavement is flush with the top of the cover main beam to form a complete floor layer; the cast-in-place composite layer is used to replace the temporary pavement in the later stage, and the top of the later cast-in-place composite layer is flush with the top of the cover main beam to form a complete composite floor, and the upper structure is built on the cast-in-place composite layer.

[0005] As an improvement, the upper surface of the initial layer of curved cover plate is corrugated, and the bottom of the temporary pavement and the cast-in-place superimposed layer is wavy and interlocked with the initial layer of curved cover plate.

[0006] As an improvement, an initial layer of curved cover plate is embedded with a shear member inside near the upper surface, and a shear member is arranged on the lower surface of the cast-in-place composite layer and is welded to the shear member of the initial layer of curved cover plate.

[0007] As an improvement, the superstructure includes superstructure vertical members and superstructure structural beams, wherein the superstructure vertical members are anchored into the cast-in-place composite layer, and the superstructure structural beams are fixed to the superstructure vertical members.

[0008] As an improvement, it also includes horizontal steel bars and vertical dowel bars of the superimposed layer. The support force-bearing steel bars placed on the top surface of the cast-in-place superimposed layer form the superimposed layer. Vertical dowel bars are arranged at the vertical components of the upper structure and are anchored to the cast-in-place superimposed layer by the vertical dowel bars.

[0009] As an improvement, the upper surface of the initial layer of curved cover plate is roughened at a later stage to be matched with the lower surface of the cast-in-place composite layer.

[0010] As an improvement, the construction steps of the cover conversion structure considering the time and space effect are as follows:

[0011] Step 1: Initial construction of the bottom frame support structure, including frame pillars, cover plate main beams and the initial first layer of curved cover plate;

[0012] Step 2: Use temporary paving to cover the initial layer of curved cover to complete the initial floor layer;

[0013] Step 3: When adding upper buildings as needed later, remove the temporary pavement;

[0014] Step 4: Construct the cast-in-place superimposed layer, embed the shear members, weld and connect them with the shear members reserved in the initial curved cover plate, and fix the horizontal steel bars and vertical dowels of the superimposed layer;

[0015] Step 5: Construct the superstructure, including superstructure vertical components, superstructure structural beams, and floor slabs.

[0016] As an improvement, between step 3 and step 4, there is also a step 3.1: roughening the initial layer of the curved cover plate.

[0017] As an improvement, step 3.2 is included between step 3 and step 4: the concrete protective layer of the steel bars is chiseled off from the upper surface of the cover plate main beam to support the horizontal steel bars of the laminated layer on the cover plate main beam.

[0018] As an improvement, step 5 also includes: vertical dowel bars corresponding to the vertical components of the upper structure are anchored in the cast-in-place composite layer.

[0019] Beneficial effects of the present invention:

[0020] 1. The transfer structure can adapt to future changes in urban development and demand; the transfer layer takes into account factors such as the future construction time and location changes of the upper building to ensure that the transfer structure can still meet the needs of planning changes in the future.

[0021] 2. The conversion structure is flexible and can adapt to different superstructure location requirements and time period changes; this design approach can provide a more flexible way of utilizing space, such as for urban rail transit systems, to adapt to changes in urban development.

[0022] 3. The initial layer of the composite slab conversion layer is flush with the slab surface through reserved shear parts, meeting the use requirements after the initial conversion layer is constructed. When the composite slab is added later, the same shear parts are built into the composite slab and welded to the shear steel plate reserved in the early stage. It is easy to operate and will not cause damage to the initial layer of the built slab.

[0023] 4. The transfer layer is designed as a composite slab. The surface elevation of the initial layer of the composite slab is lower than the surface elevation of the main beam of the cover slab, so that the surface elevation of the composite slab added later is the same as the beam surface elevation, and the force is reasonable and reliable. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 This is a schematic diagram of the construction and use process of the present invention taking into account the time and space effects.

[0025] Figure 2 It is a schematic diagram of the elevation structure of the bottom frame support structure in the present invention.

[0026] Figure 3 It is a schematic diagram of the elevation structure of the initial use structure in the present invention.

[0027] Figure 4 It is a schematic diagram of the elevation structure of the late-stage composite plate conversion structure of the present invention.

[0028] Figure 5 It is a schematic diagram of the three-dimensional structure of the bottom frame support structure in the present invention.

[0029] Figure 6 It is a three-dimensional structural schematic diagram of the structure used in the initial stage of the present invention.

[0030] Figure 7 It is a three-dimensional structural schematic diagram of the late-stage composite plate conversion structure of the present invention.

[0031] Among them: 1. Frame support; 2. Initial first layer of curved cover plate; 3. Cover plate main beam; 4. Shear members; 5. Temporary pavement; 6. Cast-in-place composite layer; 601. Horizontal reinforcement of composite layer; 602. Vertical inserted reinforcement; 7. Vertical components of upper structure; 8. Roughening of joint surface; 9. Structural beam of upper structure. DETAILED DESCRIPTION

[0032] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0033] like Figure 1-7 As shown, it is a specific embodiment of the cover plate conversion structure considering the time and space effect of the present invention. This embodiment includes frame pillars 1, cover plate main beams 3, an initial layer of curved cover plate 2, temporary pavement 5, cast-in-place composite layer 6 and superstructure; the initial layer of curved cover plate 2, cover plate main beams 3 and frame pillars 1 together form the bottom frame support structure, the cover plate main beams 3 are fixed to the frame pillars 1, and the upper part of the cover plate main beams 3 is turned up so that its top elevation is higher than the initial layer of curved cover plate 2, and its elevation is determined according to the design elevation of the later floor surface; the initial layer of curved cover plate 2 is covered with a temporary pavement 5 on its upper part during initial use, and the top of the temporary pavement 5 is flush with the top of the cover plate main beam 3 to form a complete floor layer; the cast-in-place composite layer 6 is used to replace the temporary pavement 5 in the later stage, and the top of the later cast-in-place composite layer 6 is flush with the top of the cover plate main beam 3 to form a complete composite floor, and the superstructure is built on the cast-in-place composite layer 6.

[0034] The present invention aims to adapt to future needs, that is, the conversion structure can adapt to changes in future urban development and needs. The conversion layer takes into account factors such as the construction time and position changes of the future upper building to ensure that the conversion structure can still meet the needs of planning changes in the future. By designing the conversion layer as a composite plate form, the conversion structure is flexible and can adapt to different upper building location requirements and time period changes. The technical points are: considering different building structures, especially when applied to the TOD cover structure of urban rail transit, its cover conversion structure has particularity. The upper structure of the conversion layer is generally built at a different time from the conversion layer and the lower part, that is, it must be constructed in batches; the first construction needs to meet the use requirements of the conversion layer floor; the later construction of the upper structure is the second construction, which needs to meet the force and construction requirements of the conversion layer. Therefore, this type of conversion layer takes into account the effects of various force conditions and the reliability of the conversion structure. The conversion layer is designed as a main beam + composite plate structure, which is divided into an initial one-layer plate and a later two-layer composite plate. The initial one-layer plate considers the applicability of the early stage, and the later two-layer composite plate is the conversion layer plate added later. The elevation of the initial layer of slab, i.e. the initial layer of curved cover slab 2, is lower than the elevation of the top surface of the cover slab main beam 3, so that the elevation of the later added composite slab, i.e. the cast-in-place composite layer 6, is the same as the elevation of the top surface of the cover slab main beam 3, and the force is reasonable and reliable.

[0035] As an improved specific implementation method, the upper surface of the initial curved cover plate 2 is corrugated, and the bottoms of the temporary pavement 5 and the cast-in-place composite layer 6 are wavy and interlocked with the initial curved cover plate 2.

[0036] like Figure 2 , 3 As shown in 4, the initial layer of curved cover plate 2 itself can select any form of curved structure. In the preferred embodiment, it is set to be corrugated, which on the one hand reduces the cost of construction and building, and on the other hand provides a stable and good bonding surface, and forms a bite structure with the cast-in-place composite layer 6, so that the composite plate can withstand shear force reliably.

[0037] As an improved specific implementation method, the initial curved cover plate 2 has a shear member 4 embedded inside near the upper surface, and the lower surface of the cast-in-place composite layer 6 is provided with a shear member 4 which is welded to the shear member 4 of the initial curved cover plate 2 .

[0038] like Figure 2 , 3 As shown in Figure 4, the initial layer of the conversion layer composite board, i.e. the initial layer of the curved cover plate 2, is flush with the surface of the initial layer of the curved cover plate 2 by means of the reserved shear member 4, so as to meet the use requirements after the initial conversion layer is constructed. When the composite board is added later, i.e. the cast-in-place composite layer 6 is built with the same shear member 4, which is welded and connected with the reserved shear member 4 in the early stage, so as to strengthen the connection of the composite surface and make them bear the force together. This connection method is easy to operate and will not cause damage to the initial layer of the board that has been built in the early stage. The shear member 4 can preferably be an H-shaped steel.

[0039] As an improved specific implementation manner, the upper structure includes an upper structure vertical member 7 and an upper structure structural beam 9 , the upper structure vertical member 7 is anchored into the cast-in-place composite layer 6 , and the upper structure structural beam 9 is fixed to the upper structure vertical member 7 .

[0040] like Figure 4 , 7 As shown, the upper structure vertical member 7 is anchored into the cast-in-place composite layer 6 through the vertical dowel 602, so that the structure can be extended in the height direction, and the superstructure is built upward in an orderly and stable manner. The upper structure structural beam 9 is used in conjunction with the upper structure vertical member 7 to form a force-bearing structure of the building above the transfer layer.

[0041] As an improved specific implementation method, it also includes horizontal steel bars 601 and vertical dowel bars 602 of the superimposed layer, which are placed on the top surface of the cast-in-place superimposed layer 6 to form support force-bearing steel bars of the superimposed layer. The vertical dowel bars 602 are arranged at the vertical components 7 of the upper structure and are anchored to the cast-in-place superimposed layer 6 by the vertical dowel bars 602.

[0042] like Figure 4As shown, the horizontal reinforcement 601 of the composite layer provides the stress-bearing reinforcement for the initial curved cover plate 2 and the cast-in-place composite layer 6 as an integrated composite plate, and the vertical dowel bars 602 are anchored in the cast-in-place composite layer 6 for the upper structure vertical components 7 to continue to be constructed upward, so that the later added structure does not need to be embedded with reinforcement, and avoids large-scale reinforcement and damage to the initially built structure.

[0043] As an improved specific implementation method, the upper surface of the initial layer of curved cover plate 2 is roughened 8 at a later stage to be matched with the lower surface of the cast-in-place composite layer 6.

[0044] like Figure 4 As shown, the upper surface of the first layer of curved cover plate 2 is roughened to ensure a firm fit with the cast-in-place composite layer 6 to form a composite plate that bears force together.

[0045] As an improved specific implementation method, the construction steps of the cover conversion structure considering the time and space effect are as follows:

[0046] Step 1: Initial construction of the bottom frame support structure, including frame support 1, cover plate main beam 3 and the initial first layer of curved cover plate 2;

[0047] Step 2: Use a temporary paving surface 5 to cover the initial layer of curved cover plate 2 to complete the initial floor layer;

[0048] Step 3: When the upper building is added later as needed, the temporary pavement 5 is removed;

[0049] Step 4: construct a cast-in-place superimposed layer 6, with built-in shear members 4, welded to the shear members 4 reserved in the initial curved cover plate 2, and fix the horizontal steel bars 601 and vertical dowel bars 602 of the superimposed layer;

[0050] Step 5: construct the superstructure, including superstructure vertical members 7, superstructure structural beams 9, and floor slabs.

[0051] By designing the transfer layer as a composite slab, the transfer structure is flexible and can adapt to different upper building location requirements and time period changes, and then be constructed in an orderly manner according to needs to ensure initial use and later conversion construction, so that the later added structure does not need to be rebar-planted, and is free from large-area reinforcement and damage to the initially built structure.

[0052] As an improved specific implementation method, step 3.1 is also included between step 3 and step 4: roughening the initial layer of curved cover plate 2 to ensure a firm fit with the cast-in-place composite layer 6 to form a composite plate that is jointly stressed.

[0053] As an improved specific implementation method, step 3.2 is also included between step 3 and step 4: the concrete protective layer of the steel bars is chiseled off the upper surface of the cover plate main beam 3, so as to support the horizontal steel bars 601 of the overlapping layer on the cover plate main beam 3; by supporting the horizontal steel bars 601 of the overlapping layer on the cover plate main beam, reasonable structural force is provided to ensure that the structural force is consistent with that of the conventional beams and slabs cast at the same time.

[0054] As an improved specific implementation method, step 5 also includes: the vertical dowel bars 602 corresponding to the upper structure vertical components 7 are anchored in the cast-in-place composite layer 6, so that the later added structure does not need to be embedded with reinforcement, and avoids large-area reinforcement and damage to the initially built structure.

[0055] The above are only preferred embodiments of the present invention. The protection scope of the present invention is not limited to the above embodiments. All technical solutions under the concept of the present invention belong to the protection scope of the present invention. It should be pointed out that for ordinary technicians in this technical field, some improvements and modifications without departing from the principle of the present invention should also be regarded as the protection scope of the present invention.

Claims

1. A construction method for cover conversion structure considering time and space effects, Features: It comprises a frame support (1), a cover plate main beam (3), an initial first layer of curved cover plate (2), a temporary paving surface (5), a cast-in-place composite layer (6) and an upper structure; the initial first layer of curved cover plate (2), the cover plate main beam (3) and the frame support (1) together form a bottom frame support structure; the cover plate main beam (3) is fixed to the frame support (1); the upper part of the cover plate main beam (3) is turned up so that its top elevation is higher than the initial first layer of curved cover plate (2), and its elevation is determined according to the design elevation of the later floor surface; the initial first layer of curved cover plate (2) is covered with a temporary paving surface (5) on its upper part during initial use, and the top of the temporary paving surface (5) is flush with the top of the cover plate main beam (3) to form a complete floor layer; the cast-in-place composite layer (6) is used to replace the temporary paving surface (5) in the later stage, and the top of the later cast-in-place composite layer (6) is flush with the top of the cover plate main beam (3) to form a complete composite floor, and the upper structure is built on the upper part of the cast-in-place composite layer (6); The upper surface of the initial curved cover plate (2) is corrugated, and the bottoms of the temporary paving (5) and the cast-in-place superimposed layer (6) are wavy and interlock with the initial curved cover plate (2); The initial layer of curved cover plate (2) has a shear-resistant member (4) embedded in the interior near the upper surface, and the lower surface of the cast-in-place superimposed layer (6) is provided with a shear-resistant member (4) which is welded to the shear-resistant member (4) of the initial layer of curved cover plate (2); The upper surface of the initial layer of curved cover plate (2) is roughened (8) at a later stage to be matched and connected with the lower surface of the cast-in-place superimposed layer (6); The superstructure comprises a superstructure vertical member (7) and a superstructure structural beam (9), wherein the superstructure vertical member (7) is anchored into the cast-in-place composite layer (6), and the superstructure structural beam (9) is fixed to the superstructure vertical member (7); It also includes horizontal reinforcement bars (601) and vertical dowel bars (602) of the laminated layer, wherein the horizontal reinforcement bars (601) are placed on the top surface of the cast-in-place laminated layer (6) to form support force reinforcement bars of the laminated layer, and the vertical dowel bars (602) are arranged at the vertical components (7) of the upper structure and are anchored to the cast-in-place laminated layer (6) by the vertical dowel bars (602); The construction steps of the cover conversion structure considering the time and space effect are as follows: Step 1: Initially construct the bottom frame support structure, including frame pillars (1), cover plate main beams (3) and an initial layer of curved cover plate (2); Step 2: Use a temporary paving surface (5) to cover the initial layer of curved cover plate (2) to complete the initial floor layer; Step 3: When the upper structure is added later as needed, the temporary pavement (5) is removed; Step 3.1: roughening the initial curved cover plate (2); Step 3.2: The concrete protective layer of the steel bars is chiseled off from the upper surface of the cover plate main beam (3) to support the horizontal steel bars (601) of the laminated layer on the cover plate main beam (3); Step 4: constructing a cast-in-place superimposed layer (6), inserting a shear member (4), welding and connecting the shear member (4) reserved in the initial curved cover plate (2), and fixing the horizontal reinforcement (601) and vertical dowel (602) of the superimposed layer; Step 5: constructing the upper structure, including the upper structure vertical components (7), the upper structure structural beams (9), and the floor slab; the vertical dowel bars (602) corresponding to the upper structure vertical components (7) are anchored in the cast-in-place superimposed layer (6).