An automatic multi-layer steel pipe arranging device and method
By designing an automatic multi-layer steel pipe arranging device, which utilizes components such as a arranging trolley and a pipe-pulling trolley to achieve automated multi-layer arranging of steel pipes, the safety hazards and high workload of existing technologies are solved, and efficiency is improved.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- 东营市凯睿自动化有限公司
- Filing Date
- 2024-03-20
- Publication Date
- 2026-06-30
Smart Images

Figure CN118083597B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of steel pipe transfer technology, specifically to an automatic multi-layer steel pipe arranging device and method. Background Technology
[0002] From the moment steel pipes arrive at the workshop for processing, they undergo a series of processes including unloading, storage and unpacking, pipe laying, and loading onto the conveyor line. In the pipe laying process, there are currently two methods for multi-layer pipe laying, such as... Figure 3 As shown, one type of multi-layer pipe bank has a spacer between two layers of steel pipes, while the other type has two layers of steel pipes in direct contact. The specific operation process is as follows:
[0003] The process of arranging multi-layer pipes involves placing the steel pipes to be arranged into a pipe rack. Workers stand on the rack and manually move each pipe one by one to the designated position. If the pipe is not in place the first time, it needs to be moved multiple times. After the first layer of pipes is placed, workers lift the support bars from their storage positions and place them one by one onto the first layer of pipes. This process is repeated until the first layer of pipes is completed. Then, the second layer of pipes is placed. After the second layer of pipes is placed, support bars are placed on the second layer of pipes. This process is repeated until the multi-layer pipe arrangement is complete. During this process, the rolling of the pipes can easily cause safety accidents. Moreover, the manual arrangement of pipes is labor-intensive, especially in winter and summer.
[0004] The process of laying out multi-layer pipe racks involves placing the steel pipes to be arranged into a rack on a material stand. Workers stand on the rack and manually move each pipe one by one to the designated position. If the pipe is not in place the first time, it needs to be moved multiple times. After the first layer of steel pipes is laid out, the second layer is laid out, and so on, until the entire arrangement is completed. During this process, the rolling of the steel pipes can easily cause safety accidents. Moreover, manual pipe laying is labor-intensive, especially in winter and summer.
[0005] Secondly, during the process of arranging steel pipes, it is also necessary to perform pipe feeding and random pipe picking. Although the pipe feeding and conveying has been mechanized, there are still situations where the steel pipes are far from the work position and cannot be fed continuously. Manual assistance is still required for secondary pipe feeding. When picking pipes, workers need to find the picked steel pipes and lift them to the end of the material rack. Then, they need to use a pipe grabbing machine or a transport line to transport them to the appropriate position. The work intensity is high and there are safety hazards.
[0006] To reduce the safety hazards in the above-mentioned operation process, we propose an automatic multi-layer steel pipe arranging device and method. Summary of the Invention
[0007] The purpose of this invention is to provide an automatic multi-layer steel pipe arranging device and method to automate the multi-layer steel pipe arranging and improve the efficiency of multi-layer steel pipe arranging.
[0008] To achieve the above-mentioned technical objectives and effects, the present invention provides the following technical solution:
[0009] An automatic multi-layer steel pipe arranging device includes a pipe arranging trolley, characterized in that: a pipe-pulling trolley and a pipe-laying trolley are installed on the top of the pipe arranging trolley, a pipe-pulling device is installed on the pipe-pulling trolley, a gripping device I is installed at the front and rear of the pipe-laying trolley, a gripping device II is installed in the middle of the pipe-laying trolley, and a pipe-inserting device is installed on the right side of the pipe-laying trolley.
[0010] Preferably, in an automatic multi-layer steel pipe arranging device, a pipe arranging rack is provided below the pipe trolley, a discharge rack is installed at the tail end of the pipe arranging rack, a conveyor line is provided on the right side of the discharge rack, and a turning mechanism is installed between the conveyor line and the discharge rack.
[0011] Preferably, in an automatic multi-layer steel pipe arranging device, the top of the pipe rack abuts against a steel pipe, and pad bar I and pad bar II are detachably installed on the steel pipe.
[0012] Preferably, in an automatic multi-layer steel pipe arranging device, the arranging trolley adopts a mobile four-column gantry structure, and a slide rail is installed on the upper end of the arranging trolley.
[0013] Preferably, in an automatic multi-layer steel pipe arranging device, both the pipe-pulling trolley and the pipe-laying trolley are mobile, and the lower ends of the pipe-pulling trolley and the pipe-laying trolley are equipped with guide wheels that cooperate with the slide rail.
[0014] Preferably, in an automatic multi-layer steel pipe arranging device, the gripping device I is used to place and remove pad bar I and pad bar II.
[0015] Preferably, in an automatic multi-layer steel pipe arrangement device, the gripping device II is used to place and grip the steel pipes in the pipe arrangement.
[0016] A pipe arrangement method for an automatic multi-layer steel pipe arranging device, applied to the aforementioned automatic multi-layer steel pipe arranging device, includes the following method:
[0017] A. Multi-layer pipe bank I
[0018] a1. The steel pipe rolls down from the lowering device onto the pipe stack. The pipe swinging trolley moves to the appropriate position of the pipe stack that needs to be swinged, and the pipe pulling trolley moves to the appropriate position of the steel pipe that needs to be pulled. The pipe pulling device moves the steel pipe to the designated position. If it lands at the designated position, the pipe pulling device does not need to be activated.
[0019] a2. After the first layer of steel pipes is placed, the gripping device I moves the pad bar I from the position where the pad bar I is placed to the appropriate position of the first layer of steel pipes, and repeats the placement until the placement is completed;
[0020] B. Multi-layer pipe bank II
[0021] b1. The steel pipe rolls from the lowering device onto the pipe stack. The pipe swinging trolley moves to the appropriate position of the pipe stack that needs to be swinged, and the pipe pulling trolley moves to the appropriate position of the steel pipe that needs to be pulled. The pipe pulling device moves the steel pipe to the designated position. If it lands at the designated position, the pipe pulling device does not need to be activated.
[0022] b2. After the first layer of steel pipes is placed, the gripping device I moves the pad bar II from the position where the pad bar II was placed to the appropriate position of the first layer of steel pipes, and repeats the placement until the placement is completed;
[0023] b3. Repeat step b. After the second layer of steel pipes is placed, gripping device II moves all the steel pipes on the first pad bar II near the discharge rack to a suitable position near the discharge rack. Gripping device I moves pad bar II to the storage position. Repeat this action until all pad bars II on the first layer of steel pipes are removed.
[0024] Compared with the prior art, the beneficial effects of the present invention are:
[0025] The present invention has a reasonable structural design. It utilizes a trolley for swaying pipes, a trolley for pushing pipes, a trolley for arranging pipes, a pipe pushing device, a pipe inserting device, a gripping device I, and a gripping device II to sway and transport steel pipes that require multi-layer swaying to the conveyor line. This realizes the automation of multi-layer swaying of steel pipes, adapts to different steel pipe racks, and improves the efficiency of multi-layer swaying of steel pipes.
[0026] The device of this invention has a compact structure and a high degree of automation. It does not require manual operation, which reduces the labor intensity of workers, avoids workers working in harsh environments, and reduces the safety hazards that exist in manual operation. Attached Figure Description
[0027] To more clearly illustrate the technical solution of the present invention, the accompanying drawings used in the description of the specific embodiments will be briefly introduced below. Obviously, the accompanying drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0028] Figure 1 This is a schematic diagram of the overall structure of the present invention;
[0029] Figure 2 This is a schematic diagram of the front structure of the present invention;
[0030] Figure 3 This is a top view of the structure of the present invention.
[0031] In the diagram: 1. Pipe swing trolley; 2. Pipe pusher trolley; 3. Pipe pusher device; 4. Pipe arrangement trolley; 5. Gripping device I; 6. Pipe insertion device; 7. Turning mechanism; 8. Discharge rack; 9. Conveyor line; 10. Pipe arrangement steel pipe; 11. Pad bar I; 12. Pipe arrangement rack; 13. Gripping device II; 14. Pad bar II. Detailed Implementation
[0032] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0033] Please see Figure 1-3 As shown, this embodiment is an automatic multi-layer steel pipe arranging device, including a pipe arranging trolley 1. A pipe-pulling trolley 2 and a pipe-laying trolley 4 are installed on the top of the pipe arranging trolley 1. A pipe-pulling device 3 is installed on the pipe-pulling trolley 2, which can move the steel pipe forward. A gripping device I 5 is installed at the front and rear of the pipe-laying trolley 4. A gripping device II 13 is installed in the middle of the pipe-laying trolley 4. A pipe-inserting device 6 is installed on the right side of the pipe-laying trolley 4.
[0034] The pipe trolley 4 is provided with a pipe feeding rack 12 below it. A discharge rack 8 is installed at the tail end of the pipe feeding rack 12. A conveyor line 9 is provided on the right side of the discharge rack 8. A turning mechanism 7 is installed between the conveyor line 9 and the discharge rack 8.
[0035] The top of the pipe rack 12 abuts against the pipe rack steel pipe 10, and the pipe rack steel pipe 10 is detachably equipped with pad bar I 11 and pad bar II 14.
[0036] The trolley 1 adopts a mobile four-column gantry structure, which can move between different pipe stacking racks. The upper end of the trolley 1 is equipped with a slide rail.
[0037] Both the pipe-pulling trolley 2 and the pipe-laying trolley 4 are mobile. The lower ends of the pipe-pulling trolley 2 and the pipe-laying trolley 4 are equipped with guide wheels that cooperate with the slide rails, which facilitates installation on the swing pipe trolley 1 and movement.
[0038] The gripping device I5 is used to place and remove pad bar I11 and pad bar II14.
[0039] The gripping device II13 is used to place and grip the steel pipe 10.
[0040] A pipe arrangement method for an automatic multi-layer steel pipe arranging device, applicable to the automatic multi-layer steel pipe arranging device, includes the following method:
[0041] A. Multi-layer pipe bank I
[0042] a1. The steel pipe rolls down from the lowering device onto the pipe stack. The pipe swaying trolley 1 moves to the appropriate position of the pipe stack that needs to be swayed, and the pipe-pulling trolley 2 moves to the appropriate position of the steel pipe that needs to be pulled. The pipe-pulling device 3 moves the steel pipe to the designated position. If it lands at the designated position, the pipe-pulling device 3 does not need to be activated.
[0043] a2. After the first layer of steel pipes is placed, the gripping device I5 moves the pad I11 from the position where the pad I11 is placed to the appropriate position of the first layer of steel pipes, and repeats the placement until the placement is completed;
[0044] B. Multi-layer pipe bank II
[0045] b1. The steel pipe rolls down from the lowering device onto the pipe stack. The pipe swinging trolley 1 moves to the appropriate position of the pipe stack that needs to be swinged, and the pipe lifting trolley 2 moves to the appropriate position of the steel pipe that needs to be lifted. The pipe lifting device 3 moves the steel pipe to the designated position. If it lands at the designated position, the pipe lifting device 3 does not need to be activated.
[0046] b2. After the first layer of steel pipes is placed, the gripping device I5 moves the pad II14 from the position where the pad II14 is placed to the appropriate position of the first layer of steel pipes, and repeats the placement until the placement is completed.
[0047] b3. Repeat action b1. After the second layer of steel pipes is placed, gripping device II13 moves all the steel pipes on the first pad bar II14 near the discharge rack 8 to a suitable position near the discharge rack 8. Gripping device I5 moves pad bar II14 to the storage position. Repeat this action until all pad bars II14 on the first layer of steel pipes are removed.
[0048] The specific implementation method of this embodiment is as follows:
[0049] When performing the multi-layer pipe stack arrangement method, the steel pipes are rolled from the dropping device onto the pipe stack. If the drop does not reach the designated position, the pipe trolley 1 moves to the appropriate position of the pipe stack that needs to be piped, the pipe-pulling trolley 2 moves to the appropriate position of the steel pipe that needs to be pulled, and the pipe-pulling device 3 moves the steel pipe to the designated position. If the drop reaches the designated position, the pipe-pulling device does not need to be activated. After the first layer of steel pipes is placed, the gripping device I5 moves the pad bar I11 from the position of the pad bar I11 to the appropriate position of the first layer of steel pipes. The placement is repeated until the placement is completed. This device realizes the pipe stack arrangement of the multi-layer pipe stack through the above actions.
[0050] When performing the multi-layer pipe stack II arrangement, the steel pipes are rolled from the dropping device onto the pipe stack. If they do not land in the designated position, the pipe trolley 1 moves to the appropriate position of the pipe stack that needs to be arranged, the pipe-pulling trolley 2 moves to the appropriate position of the steel pipe that needs to be pulled, and the pipe-pulling device 3 moves the steel pipe to the designated position. If the steel pipes land in the designated position, the pipe-pulling device does not need to be activated. After the first layer of steel pipes is arranged, the gripping device I5 moves the pad bar II14 from the position of the pad bar II16 to the appropriate position of the first layer of steel pipes. This arrangement is repeated until the arrangement is completed. After the second layer of steel pipes is arranged, the gripping device II13 moves all the steel pipes on the first pad bar II14 near the discharge rack 8 to the appropriate position near the discharge rack 8. The gripping device I5 moves the pad bar II14 to the position of the storage pad bar. This action is repeated until all the pad bars II14 on the first layer of steel pipes are removed. The above actions of the device realize the arrangement of the multi-layer pipe stack II.
[0051] When it is necessary to transport steel pipes to the required location, the pipe trolley 1 moves to the pipe stack on which the steel pipes need to be transported, the pipe trolley 4 moves to the appropriate position, the pipe insertion device 3 first inserts and pulls the steel pipes from the multi-layer pipe stack to a single-layer pipe stack, and then the pipe insertion device 6 inserts and pulls the steel pipes to roll onto the discharge rack 8. The turning mechanism 7 moves the steel pipes to the rollers of the conveyor line 9, and the steel pipes are transferred to the required location along with the conveyor line 9. This action is repeated until the steel pipes that need to be transferred are transferred.
[0052] In special circumstances where it is necessary to pick out the pipe, the gripping device II13 can pick out the steel pipe and then transport it to the required location using a pipe gripping machine or a transport line.
[0053] In the description of this specification, references to terms such as "an embodiment," "example," "specific example," etc., indicate that a specific feature, structure, material, or characteristic described in connection with that embodiment or example is included in at least one embodiment or example of the invention. In this specification, illustrative expressions of the above terms do not necessarily refer to the same embodiment or example. Furthermore, the specific features, structures, materials, or characteristics described may be combined in any suitable manner in one or more embodiments or examples.
[0054] The preferred embodiments of the present invention disclosed above are merely illustrative of the invention. These preferred embodiments do not exhaustively describe all details, nor do they limit the invention to the specific implementations described. Clearly, many modifications and variations can be made based on the content of this specification. This specification selects and specifically describes these embodiments to better explain the principles and practical applications of the invention, thereby enabling those skilled in the art to better understand and utilize the invention. The invention is limited only by the claims and their full scope and equivalents.
Claims
1. An automatic multi-layer steel pipe arranging device, comprising a trolley (1), characterized in that: The top of the swing tube trolley (1) is equipped with a tube-pulling trolley (2) and a tube-laying trolley (4). The tube-pulling trolley (2) is equipped with a tube-pulling device (3). The tube-pulling device (3) moves the steel pipe to a designated position. The bottom of the tube-laying trolley (4) is provided with a tube-laying rack (12). The top of the tube-laying rack (12) abuts against a tube-laying steel pipe (10). The tube-laying steel pipe (10) is detachably equipped with pad bar I (11) and pad bar II (14). The pipe-laying trolley (4) is equipped with gripping device I (5) at the front and rear. The gripping device I (5) is used to place and remove pad bar I (11) and pad bar II (14). The pipe-laying trolley (4) is equipped with gripping device II (13) in the middle. The gripping device II (13) is used to place and grip the pipe-laying steel pipe (10). The pipe-laying trolley (4) is equipped with a pipe-inserting device (6) on the right side. The pipe-inserting device (6) is used to insert and pull steel pipes from the multi-layer pipe-laying structure to make it into a single-layer pipe-laying structure.
2. The automatic multi-layer steel pipe arranging device according to claim 1, characterized in that: The tail end of the tube feed rack (12) is equipped with a discharge rack (8), and a conveyor line (9) is provided on the right side of the discharge rack (8). A turning mechanism (7) is installed between the conveyor line (9) and the discharge rack (8).
3. The automatic multi-layer steel pipe arranging device according to claim 1, characterized in that: The trolley (1) adopts a mobile four-column gantry structure, and the upper end of the trolley (1) is equipped with a slide rail.
4. The automatic multi-layer steel pipe arranging device according to claim 1, characterized in that: Both the pipe-pulling trolley (2) and the pipe-laying trolley (4) are mobile, and the lower ends of the pipe-pulling trolley (2) and the pipe-laying trolley (4) are equipped with guide wheels that cooperate with the slide rail.
5. A pipe-laying method for an automatic multi-layer steel pipe arranging device, applied to the automatic multi-layer steel pipe arranging device according to any one of claims 1-4, characterized in that, Including the following methods: A. Multi-layer pipe bank I a1. The steel pipe rolls down from the dropping device onto the pipe stack. The pipe trolley (1) moves to the appropriate position of the pipe stack that needs to be trolled. The pipe-pulling trolley (2) moves to the appropriate position of the steel pipe that needs to be pulled. The pipe-pulling device (3) moves the steel pipe to the designated position. If it lands at the designated position, the pipe-pulling device (3) does not need to be activated. a2. After the first layer of steel pipes is placed, the gripping device I (5) moves the pad I (11) from the position of the pad I (11) to the appropriate position of the first layer of steel pipes, and repeats the placement until the placement is completed. B. Multi-layer pipe bank II b1. The steel pipe rolls down from the lowering device onto the pipe stack. The pipe trolley (1) moves to the appropriate position of the pipe stack that needs to be trolled, the pipe-pulling trolley (2) moves to the appropriate position of the steel pipe that needs to be pulled, and the pipe-pulling device (3) moves the steel pipe to the designated position. If it lands at the designated position, the pipe-pulling device (3) does not need to be activated. b2. After the first layer of steel pipes is placed, the gripping device I (5) moves the pad II (14) from the position of the pad II (14) to the appropriate position of the first layer of steel pipes, and repeats the placement until the placement is completed. b3. Repeat action b1. After the second layer of steel pipes is placed, the gripping device II (13) moves all the steel pipes on the first pad bar II (14) near the discharge rack (8) to a suitable position in the direction of the discharge rack (8). The gripping device I (5) moves the pad bar II (14) to the position of storing the pad bar. Repeat this action until all the pad bars II (14) on the first layer of steel pipes are removed.