A design method for deep foundation pit of super high-rise building

By integrating the survey data of deep and large foundation pits of super high-rise buildings and analyzing construction accidents, a monitoring implementation design table is generated, which solves the problem of lack of automated monitoring and verification in the existing technology and improves the standardization and reliability of foundation pit design. , which improves the effectiveness of regulatory analysis and processing.

CN118194406BActive Publication Date: 2024-10-18NUCLEAR IND JINHUA ENG EXPLORATION INSTITUTIONS
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410356437.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-03-27
Publication Date
2024-10-18
Estimated Expiration
2044-03-27

AI Technical Summary

Technical Problem

Existing design plans for deep and large foundation pits for super high-rise buildings lack automated data normative monitoring and verification and dynamic risk warnings, resulting in poor proactive supervision analysis and processing.

Method used

By acquiring and integrating all survey data, a survey item sorting table is generated and input into the foundation pit design requirements database for multi-dimensional data screening and verification. It is combined with construction accident data to conduct evaluation and analysis of the monitoring and implementation design table, and adaptively generates alarm prompts and design requirements. management and control to improve the standardization and reliability of monitoring implementation design.

Benefits of technology

It has realized automated supervision, analysis and processing of the design of deep and large foundation pits for super high-rise buildings, improved the standardization and reliability of construction design, enhanced multi-dimensional data support for monitoring and implementation design, timely discovered and dealt with design defects, and improved Active supervision effects.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118194406B_ABST
    Figure CN118194406B_ABST
Patent Text Reader

Abstract

The invention discloses a design method for a deep and large foundation pit of a super high-rise building, and belongs to the technical field of engineering design. The method is used to solve the technical problem that active supervision analysis and processing effects of the design of the deep and large foundation pit of a super high-rise building in the existing scheme are not good. The method obtains a survey item ranking table by processing and integrating all survey data of the deep and large foundation pit of the super high-rise building actually surveyed, and determines whether all the existing construction accident data that have occurred have value for updating the data required by the standard design monitoring by processing and analyzing all the construction accident data that have occurred in the deep and large foundation pit of the same super high-rise building. The method traverses and matches all the monitoring implementation items with the selected items in the standard monitoring requirement design table to monitor implementation major categories, and performs design analysis of monitoring implementation subcategories on the monitoring implementation items corresponding to all the monitoring implementation items in the monitoring implementation design table through a parameter recognition model, and outputs the subcategory analysis results.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of engineering design, and in particular to a design method for a deep and large foundation pit of a super high-rise building. Background Art

[0002] The design of deep and large foundation pits for super high-rise buildings is a complex and important engineering link, which requires comprehensive consideration of geological conditions, structural safety, construction technology and other factors.

[0003] When implementing the existing design scheme for deep and large foundation pits of super high-rise buildings, there is no automatic implementation of diversified data normative monitoring and verification for the formulated monitoring implementation design data, and no implementation of risk warnings and control of corresponding monitoring defect levels for the formulated monitoring implementation design data based on the monitoring and verification results in different dimensions, resulting in poor active supervision, analysis and treatment effects on the design of deep and large foundation pits of super high-rise buildings. Summary of the invention

[0004] The purpose of the present invention is to provide a design method for deep and large foundation pits of super high-rise buildings, which is used to solve the technical problems of poor active supervision and analysis and treatment effects in the existing schemes for the design of deep and large foundation pits of super high-rise buildings.

[0005] The purpose of the present invention can be achieved through the following technical solutions:

[0006] A design method for a deep foundation pit of a super high-rise building, comprising:

[0007] Obtain all survey items and corresponding survey data of deep and large foundation pits of super high-rise buildings that are actually surveyed, set all survey items as first verification marks, set all survey data as second verification marks and arrange and combine them in the order of survey to obtain a survey item ranking table;

[0008] Input different verification marks in the survey item sorting table into the foundation pit design requirement database corresponding to the real-time standard design monitoring requirement data update of the super-high-rise building to perform multi-dimensional data screening and verification to obtain the selected items;

[0009] Obtain the monitoring requirement items associated with the same sample survey item in the foundation pit design requirement database for the selected item and mark them as selected monitoring requirement items, sort and combine all the selected items and their associated selected monitoring requirement items to obtain a standard monitoring requirement design table;

[0010] The formulated monitoring implementation design table and the standard monitoring requirement design table are matched in a multi-dimensional manner. Based on the matching results, the monitoring defects of the monitoring implementation design table are evaluated and analyzed, and dynamic alarm prompts and design requirement management are adaptively performed.

[0011] Preferably, all survey items corresponding to the deep and large foundation pit of super high-rise buildings include but are not limited to stratum survey items, geotechnical survey items and groundwater survey items;

[0012] The survey data is obtained through statistics based on the existing survey requirements of the corresponding survey project.

[0013] Preferably, the foundation pit design requires that a number of sample survey items and their corresponding sample survey data ranges are pre-stored in the database.

[0014] Preferably, the step of updating the real-time standard design monitoring requirement data of the super-high-rise foundation pit design requirement database includes:

[0015] Obtain all the construction accident data that have occurred in the deep and large foundation pit of the same super high-rise building, count all the accident locations and the accident investigation items corresponding to all the construction accident data, and use the accident investigation items to conduct normative verification of the existing standard monitoring conditions, and input the accident investigation items into the accident monitoring implementation design table and the foundation pit design requirements database for traversal retrieval;

[0016] If the accident investigation item exists in both the accident monitoring implementation design table and the foundation pit design requirements database, a monitoring implementation completion tag will be generated.

[0017] Preferably, if the accident investigation item does not exist in the accident monitoring implementation design table and the accident investigation item exists in the foundation pit design requirement database, a monitoring implementation incomplete label is generated;

[0018] If the accident investigation item does not exist in the accident monitoring implementation design table and the foundation pit design requirements database, a monitoring implementation defect label is generated and the corresponding accident investigation item is recorded as the selected accident investigation item. At the same time, the selected accident investigation item and the corresponding reviewed and formulated sample investigation data range are added and stored in the foundation pit design requirements database to update the real-time standard design monitoring requirements data.

[0019] Preferably, if the foundation pit design requires that there exists a sample survey item identical to the first verification identifier in the database, and the second verification identifier associated with the first verification identifier belongs to the sample survey data range associated with the same sample survey item, then the first verification identifier is marked as the selected item.

[0020] Preferably, all monitoring implementation items in the monitoring implementation design table and the monitoring implementation items corresponding to different monitoring implementation items are obtained, and all monitoring implementation items are traversed and matched with the selected items in the standard monitoring requirement design table according to the monitoring implementation categories;

[0021] The selected names in the monitoring implementation design table are recorded as normal major categories, and the selected names that do not exist in the monitoring implementation design table are recorded as risk major categories;

[0022] Count the total number of risk categories and analyze them.

[0023] Preferably, if the total number of risk category items is 0, a reliable label for the monitoring implementation category is generated, and the monitoring implementation items corresponding to all monitoring implementation items in the monitoring implementation design table are sequentially combined with the selected monitoring requirement items associated with the corresponding selected items in the standard monitoring requirement design table through a parameter identification model to perform design analysis of the monitoring implementation subcategory and output a subcategory analysis identifier; wherein the expression of the parameter identification model is: In the formula: c is the monitoring implementation item corresponding to the monitoring implementation project, c' is the selected monitoring requirement item associated with the selected project;

[0024] According to the sub-category analysis identifier with a value of 0, the corresponding monitoring implementation item is marked as a normal sub-category implementation item; and according to the sub-category analysis identifier with a value of 1, the monitoring implementation name to which the corresponding monitoring implementation item belongs is marked as a risk sub-category implementation item.

[0025] Preferably, by the formula Calculate and obtain the monitoring implementation completeness Jw corresponding to the monitoring implementation design table;

[0026] Where: α is the impact weight of major defects, β is the impact weight of minor defects, α>β>0, Nd is the total number of major risk items, Nx is the total number of minor risk implementation items, and N is the total number of all monitoring implementation items in the monitoring implementation design table;

[0027] When evaluating and analyzing the monitoring implementation completeness to confirm the degree of monitoring defects in the monitoring implementation design table, the monitoring implementation completeness is compared and classified with the preset monitoring implementation standard value to obtain an evaluation and analysis result consisting of a normal monitoring defect label, a mild monitoring defect label, or a severe monitoring defect label.

[0028] Preferably, according to the monitoring defect mild label or monitoring defect severe label in the evaluation and analysis results, the formulated monitoring implementation design table is adaptively given a design mild defect alarm prompt or a design severe defect alarm prompt, and targeted design optimization control is performed.

[0029] Compared with the existing solutions, the present invention achieves the following beneficial effects:

[0030] The present invention obtains a survey item ranking table by processing and integrating all survey data of deep and large foundation pits of super high-rise buildings that are actually surveyed, and determines whether all existing construction accident data have value for updating standard design monitoring requirements data by processing and analyzing all construction accident data that have occurred in the same deep and large foundation pits of super high-rise buildings, so that the standard sample data in the foundation pit design requirements database can be updated and improved in a timely and efficient manner, thereby providing timely and comprehensive standard data support for the automated supervision of the monitoring and implementation design data formulated subsequently.

[0031] The present invention can not only obtain different risk categories by traversing and matching all monitoring implementation items with the selected items in the standard monitoring requirement design table, but also provide reliable data support for the design and analysis of monitoring implementation items corresponding to all monitoring implementation items in the subsequent monitoring implementation design table. By utilizing reliable labels of monitoring implementation categories, the monitoring implementation items corresponding to all monitoring implementation items in the monitoring implementation design table are further analyzed through parameter recognition models for monitoring implementation subcategories and the subcategory analysis results are output, thereby improving the multi-dimensional data normative analysis effect of the formulated monitoring implementation design table.

[0032] The present invention analyzes the numerical values ​​obtained by integrating and calculating all the abnormal major category data and abnormal minor category data obtained from the monitoring and analysis of the monitoring implementation design table, and obtains the overall monitoring implementation design defects of the formulated monitoring implementation design table, so as to adaptively implement targeted design defect prompts and controls, thereby improving the standardization and reliability of construction design, and further improving the active supervision, analysis and processing effects of deep and large foundation pit design of super-high-rise buildings. BRIEF DESCRIPTION OF THE DRAWINGS

[0033] The present invention will be further described below in conjunction with the accompanying drawings.

[0034] Figure 1 The present invention is a flowchart of a design method for a deep and large foundation pit of a super high-rise building.

[0035] Figure 2 It is a flowchart of updating the real-time standard design monitoring requirement data of the super-high-rise foundation pit design requirement database in the present invention.

[0036] Figure 3 It is a flowchart of implementing multi-dimensional monitoring and analysis on all monitoring implementation items in the monitoring implementation design table in the present invention. DETAILED DESCRIPTION

[0037] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary operation and maintenance personnel in this field without creative work are within the scope of protection of the present invention.

[0038] like Figure 1 As shown, the present invention is a design method for a deep and large foundation pit of a super high-rise building, comprising:

[0039] Obtain all survey items and corresponding survey data of deep and large foundation pits of super high-rise buildings that are actually surveyed, set all survey items as the first verification mark, and set all survey data as the second verification mark and arrange and combine them in the order of survey to obtain a survey item ranking table; including:

[0040] All survey items corresponding to the deep and large foundation pit of super high-rise buildings include but are not limited to stratum survey items, geotechnical survey items and groundwater survey items;

[0041] The survey data is obtained through survey and statistics based on the existing survey requirements of the corresponding survey items;

[0042] In the embodiment of the present invention, by processing and integrating all the survey data of the deep and large foundation pits of super high-rise buildings in actual survey to obtain a survey item ranking table, reliable survey data support can be provided for the automatic implementation of diversified supervision analysis for the subsequent monitoring implementation design data.

[0043] Input different verification marks in the survey item sorting table into the foundation pit design requirement database corresponding to the real-time standard design monitoring requirement data update of the super-high-rise building for multi-dimensional data screening and verification;

[0044] If the foundation pit design requires that there is a sample survey item identical to the first verification identifier in the database, and the second verification identifier associated with the first verification identifier belongs to the sample survey data range associated with the same sample survey item, then the first verification identifier is marked as the selected item;

[0045] Otherwise, the second verification mark is marked as a regular item;

[0046] Among them, a number of sample survey items and their corresponding sample survey data ranges are pre-stored in the foundation pit design requirements database. The specific sample survey items and their corresponding sample survey data ranges are determined based on the existing industry survey requirements big data corresponding to the deep and large foundation pits of super high-rise buildings;

[0047] In addition, the real-time standard design monitoring requirement data update steps for the super-high-rise foundation pit design requirement database include:

[0048] like Figure 2 As shown, all construction accident data that have occurred in the deep and large foundation pit of the same super high-rise building are obtained, and all accident locations and accident investigation items corresponding to all construction accident data are counted. The accident investigation item to which the accident location belongs is determined based on professional and technical personnel in this field. When the accident investigation item is used to perform normative verification on the existing standard monitoring conditions, the accident investigation item is respectively input into the accident monitoring implementation design table and the foundation pit design requirement database for traversal retrieval;

[0049] If the accident survey item exists in both the accident monitoring implementation design table and the foundation pit design requirements database, a monitoring implementation complete label is generated;

[0050] If the accident investigation item does not exist in the accident monitoring implementation design table and the accident investigation item exists in the foundation pit design requirement database, an incomplete monitoring implementation label is generated;

[0051] If the accident investigation item does not exist in the accident monitoring implementation design table and the foundation pit design requirement database, a monitoring implementation defect label is generated and the corresponding accident investigation item is recorded as the selected accident investigation item. At the same time, the selected accident investigation item and the corresponding reviewed and formulated sample investigation data range are supplemented and stored in the foundation pit design requirement database to update the real-time standard design monitoring requirement data; wherein, the sample investigation data range corresponding to the selected accident investigation item is formulated by professional and technical personnel in this field through review in combination with the actual accident impact;

[0052] In an embodiment of the present invention, by processing and analyzing the data of all construction accidents that have occurred in the deep and large foundation pit of the same super-high-rise building, it is determined whether there is value in updating the standard design monitoring requirements data for all the existing construction accident data, so that the standard sample data in the foundation pit design requirements database can be updated and improved in a timely and efficient manner, thereby providing timely and comprehensive standard data support for the automated supervision of the monitoring and implementation design data formulated subsequently.

[0053] Obtain the monitoring requirement items associated with the same sample survey item in the foundation pit design requirement database for the selected item and mark them as selected monitoring requirement items, sort and combine all the selected items and their associated selected monitoring requirement items to obtain a standard monitoring requirement design table;

[0054] In the embodiment of the present invention, by autonomously sorting and combining all the selected items obtained through processing and identification and the selected monitoring requirements items matched thereto to obtain a standard monitoring requirement design table, reliable data support can be provided for the regulatory analysis of different dimensions actively implemented by the formulated monitoring implementation design table;

[0055] The developed monitoring implementation design table is matched with the standard monitoring requirement design table in multiple dimensions, and the monitoring defects of the monitoring implementation design table are evaluated and analyzed based on the matching results, and dynamic alarm prompts and design requirement management are adaptively performed. Including:

[0056] like Figure 3 As shown, all monitoring implementation items in the monitoring implementation design table and the monitoring implementation items corresponding to different monitoring implementation items are obtained, and all monitoring implementation items are traversed and matched with the selected items in the standard monitoring requirement design table according to the monitoring implementation categories;

[0057] The selected names in the monitoring implementation design table are recorded as normal major categories, and the selected names that do not exist in the monitoring implementation design table are recorded as risk major categories;

[0058] Count the total number of risk categories and conduct analysis;

[0059] If the total number of risk category items is not 0, a label indicating that the monitoring implementation category is unreliable is generated;

[0060] If the total number of risk category items is 0, a reliable label for the monitoring implementation category is generated, and based on the reliable label for the monitoring implementation category, the monitoring implementation items corresponding to all monitoring implementation items in the monitoring implementation design table are sequentially combined with the selected monitoring requirement items associated with the corresponding selected items in the standard monitoring requirement design table through the parameter identification model to perform design analysis on the monitoring implementation subcategory and output the subcategory analysis identification;

[0061] Among them, the expression of the parameter identification model is In the formula: c is the monitoring implementation item corresponding to the monitoring implementation project, c' is the selected monitoring requirement item associated with the selected project;

[0062] Among them, the output sub-category analysis identifier is a numerical value of 0 or 1;

[0063] According to the sub-category analysis identifier with a value of 0, the corresponding monitoring implementation item is marked as a normal sub-category implementation item;

[0064] And, according to the sub-category analysis identifier with a value of 1, the monitoring implementation name target to which the corresponding monitoring implementation item belongs is recorded as a risk sub-category implementation item;

[0065] In the embodiment of the present invention, by traversing and matching all monitoring implementation items with the selected items in the standard monitoring requirement design table, different risk categories can be obtained, and reliable data support can be provided for the design analysis of monitoring implementation items corresponding to all monitoring implementation items in the subsequent monitoring implementation design table. By using the reliable labels of the monitoring implementation categories, the monitoring implementation items corresponding to all monitoring implementation items in the monitoring implementation design table are further analyzed for the design of monitoring implementation subcategories through the parameter recognition model and the subcategory analysis results are output, thereby improving the standardized analysis effect of the multi-dimensional data formulation of the formulated monitoring implementation design table;

[0066] By formula Calculate and obtain the monitoring implementation completeness Jw corresponding to the monitoring implementation design table;

[0067] Where: α is the impact weight of major defects, β is the impact weight of minor defects, α>β>0, Nd is the total number of major risk items, Nx is the total number of minor risk implementation items, and N is the total number of all monitoring implementation items in the monitoring implementation design table;

[0068] Among them, the monitoring implementation completeness is a value used to analyze the overall situation of the overall monitoring implementation design defects by integrating and calculating all the abnormal major category data and abnormal minor category data obtained from the monitoring and analysis of the monitoring implementation design table;

[0069] When evaluating and analyzing the completeness of monitoring implementation to confirm the degree of monitoring defects in the monitoring implementation design table, the completeness of monitoring implementation is compared and classified with the preset monitoring implementation standard value to obtain an evaluation and analysis result consisting of a normal monitoring defect label, a mild monitoring defect label, or a severe monitoring defect label;

[0070] Specifically, if the monitoring implementation completeness is not greater than the monitoring implementation standard value, a normal monitoring defect label is generated; the monitoring implementation standard value is determined according to the corresponding super-high-rise existing foundation pit design requirement parameter data;

[0071] If the monitoring implementation completeness is greater than the monitoring implementation standard value and not greater than Y% of the monitoring implementation standard value, where Y is a real number greater than 100, a monitoring defect minor label is generated;

[0072] If the monitoring implementation completeness is greater than Y% of the monitoring implementation standard value, a monitoring defect severity label is generated;

[0073] According to the monitoring defect light label or monitoring defect heavy label in the evaluation and analysis results, the monitoring implementation design table is adaptively issued with a design light defect warning prompt or a design heavy defect warning prompt, and targeted design optimization control is performed;

[0074] Among them, targeted design optimization and control include: supplementing and updating the names of non-existent major risk categories, and correcting the monitoring data of all existing minor risk implementation items.

[0075] In the embodiment of the present invention, by integrating and calculating the numerical values ​​obtained from the monitoring and analysis of the monitoring implementation design table for all abnormal major category data and abnormal minor category data, the overall monitoring implementation design defects of the formulated monitoring implementation design table are obtained, so that targeted design defect prompts and controls can be implemented adaptively, thereby improving the standardization and reliability of the construction design, and further improving the active supervision, analysis and processing effects of the deep and large foundation pit design of super-high-rise buildings.

[0076] In the several embodiments provided by the present invention, it should be understood that the disclosed method can be implemented in other ways. For example, the above-described embodiments of the invention are only illustrative, for example, the division of modules is only a logical function division, and there may be other division methods in actual implementation.

[0077] The modules described as separate components may or may not be physically separated, and the components shown as modules may or may not be physical modules, and may be located in one place or distributed on multiple network modules. Some or all of the modules may be selected according to actual needs to achieve the purpose of the solution of this embodiment.

[0078] In addition, each functional module in each embodiment of the present invention may be integrated into one processing module, or each module may exist physically separately, or two or more modules may be integrated into one module. The above-mentioned integrated module may be implemented in the form of hardware or in the form of hardware plus software functional modules.

[0079] It is obvious to those skilled in the art that the present invention is not limited to the details of the above exemplary embodiments, and that the present invention can be implemented in other specific forms without departing from the basic features of the present invention.

[0080] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, ordinary operation and maintenance personnel in the field should understand that the technical solution of the present invention can be modified or replaced by equivalents without departing from the spirit and scope of the technical solution of the present invention.

Claims

1. A design method for a deep foundation pit of a super high-rise building, characterized in that: include: Obtain all survey items and corresponding survey data of deep and large foundation pits of super high-rise buildings that are actually surveyed, set all survey items as first verification marks, set all survey data as second verification marks and arrange and combine them in the order of survey to obtain a survey item ranking table; Input different verification marks in the survey item sorting table into the foundation pit design requirement database corresponding to the real-time standard design monitoring requirement data update of the super-high-rise building to perform multi-dimensional data screening and verification to obtain the selected items; Obtain the monitoring requirement items associated with the same sample survey item in the foundation pit design requirement database for the selected item and mark them as selected monitoring requirement items, sort and combine all the selected items and their associated selected monitoring requirement items to obtain a standard monitoring requirement design table; The formulated monitoring implementation design table is matched with the standard monitoring requirement design table in multiple dimensions to standardize the formulated data. Based on the matching results, the monitoring defects of the monitoring implementation design table are evaluated and analyzed, and dynamic alarm prompts and design requirement management are adaptively performed; among them, all monitoring implementation names in the monitoring implementation design table and the monitoring implementation items corresponding to different monitoring implementation names are obtained, and all monitoring implementation names are matched with the selected names in the standard monitoring requirement design table for the major categories of monitoring implementation; The selected names in the monitoring implementation design table are recorded as normal major categories, and the selected names that do not exist in the monitoring implementation design table are recorded as risk major categories; Count the total number of risk categories and analyze them.

2. The design method of a deep foundation pit for a super high-rise building according to claim 1, characterized in that: All survey items corresponding to the deep and large foundation pit of super high-rise buildings include but are not limited to stratum survey items, geotechnical survey items and groundwater survey items; The survey data is obtained through statistics based on the existing survey requirements of the corresponding survey project.

3. The design method of a deep foundation pit for a super high-rise building according to claim 2 is characterized in that: The foundation pit design requires that a number of sample survey items and their corresponding sample survey data ranges be pre-stored in the database.

4. The method for designing a deep foundation pit for a super high-rise building according to claim 3, characterized in that: The steps for updating the real-time standard design monitoring requirements data of the super-high-rise foundation pit design requirements database include: Obtain all the construction accident data that have occurred in the deep and large foundation pit of the same super high-rise building, count all the accident locations and the accident investigation items corresponding to all the construction accident data, and use the accident investigation items to conduct normative verification of the existing standard monitoring conditions, and input the accident investigation items into the accident monitoring implementation design table and the foundation pit design requirements database for traversal retrieval; If the accident investigation item exists in both the accident monitoring implementation design table and the foundation pit design requirements database, a monitoring implementation completion tag will be generated.

5. The method for designing a deep foundation pit for a super high-rise building according to claim 4, characterized in that: If the accident investigation item does not exist in the accident monitoring implementation design table and the accident investigation item exists in the foundation pit design requirement database, an incomplete monitoring implementation label is generated; If the accident investigation item does not exist in the accident monitoring implementation design table and the foundation pit design requirements database, a monitoring implementation defect label is generated and the corresponding accident investigation item is recorded as the selected accident investigation item. At the same time, the selected accident investigation item and the corresponding reviewed and formulated sample investigation data range are added and stored in the foundation pit design requirements database to update the real-time standard design monitoring requirements data.

6. The method for designing a deep foundation pit for a super high-rise building according to claim 1, characterized in that: If the foundation pit design requires that there exists a sample survey item identical to the first verification identifier in the database, and the second verification identifier associated with the first verification identifier belongs to the sample survey data range associated with the same sample survey item, the first verification identifier shall be marked as the selected item.

7. The method for designing a deep foundation pit for a super high-rise building according to claim 1, characterized in that: If the total number of risk categories is 0, a reliable label for the monitoring implementation category is generated, and based on the reliable label for the monitoring implementation category, the monitoring implementation items corresponding to all monitoring implementation categories in the monitoring implementation design table are sequentially combined with the selected monitoring requirement items associated with the corresponding selected categories in the standard monitoring requirement design table through the parameter identification model to perform design analysis on the monitoring implementation subcategory and output the subcategory analysis identifier; where the expression of the parameter identification model is: In the formula: c is the monitoring implementation item corresponding to the monitoring implementation project, c' is the selected monitoring requirement item associated with the selected project; According to the sub-category analysis identifier with a value of 0, the corresponding monitoring implementation item is marked as a normal sub-category implementation item; and according to the sub-category analysis identifier with a value of 1, the monitoring implementation name to which the corresponding monitoring implementation item belongs is marked as a risk sub-category implementation item.

8. The method for designing a deep foundation pit for a super high-rise building according to claim 7, characterized in that: By formula Calculate and obtain the monitoring implementation completeness Jw corresponding to the monitoring implementation design table; Where: α is the impact weight of major defects, β is the impact weight of minor defects, α>β>0, Nd is the total number of major risk items, Nx is the total number of minor risk implementation items, and N is the total number of all monitoring implementation items in the monitoring implementation design table; When evaluating and analyzing the monitoring implementation completeness to confirm the degree of monitoring defects in the monitoring implementation design table, the monitoring implementation completeness is compared and classified with the preset monitoring implementation standard value to obtain an evaluation and analysis result consisting of a normal monitoring defect label, a mild monitoring defect label, or a severe monitoring defect label.

9. A method for designing a deep foundation pit for a super high-rise building according to claim 8, characterized in that: According to the monitoring defect mild label or monitoring defect severe label in the evaluation and analysis results, the formulated monitoring implementation design table is adaptively issued with design mild defect alarm prompts or design severe defect alarm prompts, and targeted design optimization control is carried out.

Citation Information

Patent Citations

  • A deep foundation pit monitoring risk assessment system and assessment method based on big data

    CN109934474A

  • Safety evaluation method for unloading deformation of deep and large rock foundation pit

    CN115495956A