A method and system for balancing pressure loss of each branch of an energy storage liquid cooling pipeline
By adjusting the bending angle and average flow rate of the liquid-cooling pipeline in the energy storage system, the pressure loss balance of each branch pipeline is achieved, the problem of battery cluster temperature difference is solved, and the service life of the system is extended.
Patent Information
- Application Number
- CN202410697553.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-31
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2044-05-31
AI Technical Summary
In the energy storage system, the uneven arrangement of liquid cooling pipelines results in large temperature differences between battery clusters, which affects the service life of the system.
By setting a unified bending angle and preset flow average, the ideal total pressure loss coefficient of each branch pipeline is calculated, and the actual coefficient is adjusted to achieve pressure loss balance, and the liquid cooling pipeline is rearranged to eliminate differences and ensure uniform flow.
Effectively prevents temperature differences between battery clusters, extending the service life of the system and improving the overall performance of the liquid cooling system.
Smart Images

Figure CN118260980B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of liquid cooling technology, and in particular to a method and system for balancing the pressure losses of branches of an energy storage liquid cooling pipeline. Background Art
[0002] In the field of new energy storage, people have higher and higher requirements for the battery energy density and charge and discharge rate of energy storage systems, and the heat dissipation problem of batteries is becoming more and more serious. Energy storage batteries not only have specific operating temperature range requirements, but also the temperature difference between a large number of battery packs needs to be controlled.
[0003] Existing energy storage systems use a liquid-cooled cold plate thermal management system. In the system, due to the length of the transmission path between the system and the water-cooled unit (power source), there is a temperature difference between battery packs at different positions, which seriously affects the service life of the battery system. For example, the battery pack close to the water-cooled unit has a small resistance along the way and a large battery pack flow; the battery pack far away from the water-cooled unit has a small flow. Summary of the invention
[0004] The technical problem to be solved by the present invention is: to propose a method and system for balancing the pressure losses of various branches of an energy storage liquid cooling pipeline, so as to effectively prevent a large temperature difference between battery clusters and extend the service life of the system.
[0005] In order to solve the above technical problems, the technical solution adopted by the present invention is:
[0006] A method for balancing the pressure loss of each branch of an energy storage liquid cooling pipeline is applied to the liquid cooling pipeline, wherein the liquid cooling pipeline comprises a water cooling unit, a water supply pipe, a return pipe, a branch pipe and a connecting valve; the water cooling unit is connected to the water supply pipe and the return pipe respectively, the branch pipe is used to be arranged on a battery pack in a one-to-one correspondence, and the two ends of the branch pipe are connected to the water supply pipe and the return pipe respectively through one of the connecting valves, comprising the following steps:
[0007] S1. Assisting in the preliminary arrangement of the liquid cooling pipeline and maintaining the same bending degree of all the branch pipelines;
[0008] S2. Setting and calculating an ideal flow splitting ratio of each branch pipeline according to a first preset aperture of the connecting valve and a preset flow average of the branch pipeline;
[0009] S3. According to the ideal flow splitting ratio and the specification parameters of the liquid cooling pipeline, an ideal total pressure loss coefficient of the branch pipeline is obtained, wherein the ideal total pressure loss coefficient is equal to the sum of the pressure loss coefficient along the branch pipeline, the bending pressure loss coefficient, the variable diameter pressure loss coefficient and the branch pipe pressure loss coefficient;
[0010] S4, obtaining the actual aperture values of the connecting valves at both ends of the branch pipeline, calculating the along-the-line pressure loss coefficient, bending pressure loss coefficient and variable diameter pressure loss coefficient of the branch pipeline, and adjusting the flow path length or bending angle of the branch pipeline in combination with the ideal total pressure loss coefficient;
[0011] S5. Execute step S4 on all the branch pipelines to achieve pressure loss balance in all the branch pipelines.
[0012] In order to solve the above technical problems, another technical solution adopted by the present invention is:
[0013] A pressure loss balancing system for each branch of an energy storage liquid cooling pipeline, comprising a controller and a liquid cooling pipeline, wherein the liquid cooling pipeline comprises a water cooling unit, a water supply main, a water return main, a branch pipeline and a connecting valve;
[0014] The water cooling unit is connected to the water supply pipe and the water return pipe respectively, the branch pipes are used to be arranged on the battery pack in a one-to-one correspondence, and the two ends of the branch pipes are connected to the water supply pipe and the water return pipe respectively through one of the connecting valves;
[0015] The controller is in communication with the water cooling unit, and the controller is used to perform the following steps:
[0016] S1. Assisting in the preliminary arrangement of the liquid cooling pipeline and maintaining the same bending degree of all the branch pipelines;
[0017] S2. Setting and calculating an ideal flow splitting ratio of each branch pipeline according to a first preset aperture of the connecting valve and a preset flow average of the branch pipeline;
[0018] S3. According to the ideal flow splitting ratio and the specification parameters of the liquid cooling pipeline, an ideal total pressure loss coefficient of the branch pipeline is obtained, wherein the ideal total pressure loss coefficient is equal to the sum of the pressure loss coefficient along the branch pipeline, the bending pressure loss coefficient, the variable diameter pressure loss coefficient and the branch pipe pressure loss coefficient;
[0019] S4, obtaining the actual aperture values of the connecting valves at both ends of the branch pipeline, calculating the along-the-line pressure loss coefficient, bending pressure loss coefficient and variable diameter pressure loss coefficient of the branch pipeline, and adjusting the flow path length or bending angle of the branch pipeline in combination with the ideal total pressure loss coefficient;
[0020] S5. Execute step S4 on all the branch pipelines to achieve pressure loss balance in all the branch pipelines.
[0021] The beneficial effects of the present invention are: providing a method and system for balancing the pressure losses of each branch of an energy storage liquid cooling pipeline, preliminarily arranging the liquid cooling pipeline by setting a uniform bending angle, and combining a preset flow average, etc., to calculate the ideal total pressure loss coefficient that each branch pipeline should have when tending to equal flow, and then compare some actual coefficients of each branch pipeline with the ideal total pressure loss coefficient to highlight the difference between the flow path length or bending angle of each branch pipeline and the ideal state of achieving equal flow, and then adjust the flow path length or bending angle of the branch pipeline, that is, rearrange and eliminate the difference, so that the pressure loss of each branch pipeline is balanced, equal flow is achieved, and a large temperature difference between battery clusters is effectively prevented, thereby extending the service life of the system. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 It is a schematic diagram of the steps of a method for balancing the pressure loss of each branch of an energy storage liquid cooling pipeline of the present invention;
[0023] Figure 2 It is a schematic diagram of the connection of the pressure loss balance system of each branch of the energy storage liquid cooling pipeline during liquid injection of the present invention;
[0024] Figure 3 The figure is a schematic diagram of the composition structure of a liquid cooling pipeline of a method for balancing the pressure losses of branches of an energy storage liquid cooling pipeline according to the present invention.
[0025] Description of labels:
[0026] 1. Water supply main; 2. Return water main; 3. Branch pipeline; 4. Connecting valve; 5. Liquid cooling unit; 6. Exhaust valve; 7. Drain valve; 8. Liquid injection equipment; 9. Battery pack. DETAILED DESCRIPTION
[0027] In order to explain the technical content, achieved objectives and effects of the present invention in detail, the following is an explanation in combination with the implementation modes and the accompanying drawings.
[0028] Please refer to Figure 1 and Figure 2 A method for balancing the pressure loss of each branch of an energy storage liquid cooling pipeline is applied to a liquid cooling pipeline, wherein the liquid cooling pipeline includes a water cooling unit 5, a water supply pipe 1, a return pipe 2, a branch pipe 3 and a connecting valve 4; the water cooling unit 5 is connected to the water supply pipe 1 and the return pipe 2 respectively, and the branch pipe 3 is used to be arranged on a battery pack 9 in a one-to-one correspondence, and the two ends of the branch pipe 3 are connected to the water supply pipe 1 and the return pipe 2 respectively through one of the connecting valves 4, including the following steps:
[0029] S1, assisting in the preliminary arrangement of the liquid cooling pipeline, and maintaining the same bending degree of all the branch pipelines 3;
[0030] S2, setting and calculating the ideal flow splitting ratio of each branch pipeline 3 according to the first preset aperture of the connecting valve 4 and the preset flow mean of the branch pipeline 3;
[0031] S3. According to the ideal flow splitting ratio and the specification parameters of the liquid cooling pipeline, the ideal total pressure loss coefficient of the branch pipeline 3 is obtained, and the ideal total pressure loss coefficient is equal to the sum of the pressure loss coefficient along the branch pipeline 3, the bending pressure loss coefficient, the variable diameter pressure loss coefficient and the branch pipe pressure loss coefficient;
[0032] S4, obtaining the actual aperture values of the connecting valves 4 at both ends of the branch pipeline 3, calculating the along-the-line pressure loss coefficient, the bending pressure loss coefficient, and the variable-diameter pressure loss coefficient of the branch pipeline 3, and adjusting the flow path length or bending angle of the branch pipeline 3 in combination with the ideal total pressure loss coefficient;
[0033] S5. Execute step S4 on all the branch pipelines 3 to achieve pressure loss balance in all the branch pipelines 3.
[0034] From the above description, it can be seen that the beneficial effect of the present invention is that: by setting a uniform bending angle to preliminarily arrange the liquid cooling pipeline, and combining the preset flow mean, etc., the ideal total pressure loss coefficient that each branch pipeline 3 should have when tending to equal flow is calculated, and then some actual coefficients of each branch pipeline 3 are compared with the ideal total pressure loss coefficient to highlight the difference between the flow path length or bending angle of each branch pipeline 3 and the ideal state of achieving equal flow, and then adjust the flow path length or bending angle of the branch pipeline 3, that is, rearrange and eliminate the difference, so that the pressure loss of each branch pipeline 3 is balanced, and equal flow is achieved, which effectively prevents large temperature differences between battery clusters and extends the service life of the system.
[0035] Furthermore, the step S4 comprises:
[0036] S41, obtaining the actual aperture values of the connecting valves 4 at both ends of the branch pipeline 3, calculating the along-the-way pressure loss coefficient, bending pressure loss coefficient and variable diameter pressure loss coefficient of the branch pipeline 3, and combining the ideal total pressure loss coefficient to obtain the ideal branch pressure loss coefficient of the branch pipeline 3;
[0037] S42, obtaining the ideal aperture values of the connecting valves 4 at both ends of the branch pipeline 3 according to the ideal branch pipe pressure loss coefficient;
[0038] S43, recalculating the actual total pressure loss coefficient of the branch pipeline 3 based on the ideal aperture value;
[0039] S44. Adjust the flow path length or bending angle of the branch pipeline 3 according to the comparison result between the actual total pressure loss coefficient and the ideal total pressure loss coefficient.
[0040] From the above description, it can be seen that by using the mathematical relationship between the ideal total pressure loss coefficient and the pressure loss coefficient along the way, the bending pressure loss coefficient, the variable diameter pressure loss coefficient and the branch pressure loss coefficient, the original idea of seeking the difference by comparing the ideal total pressure loss coefficient with the actual total pressure loss coefficient is transformed into the difference of the detailed data of the branch pressure loss coefficient, that is, seeking the specific adjustment that can be made on the branch pipeline 3 to achieve equal flow, and finally the adjustment is directed to the aperture size of the connecting valve 4 and the flow path length or bending angle of the branch pipeline 3, so as to reduce the complexity of the adjustment to achieve equal flow. And corresponding adjustments can be made for each branch for the same content.
[0041] Furthermore, the step S2 comprises:
[0042] Selecting the first preset aperture from the preset aperture specification group as the aperture size of the connecting valve 4;
[0043] The step S43 specifically includes:
[0044] S431, selecting a second preset aperture value closest to the ideal aperture value from the preset aperture specification group;
[0045] S432. Recalculate the actual total pressure loss coefficient of the branch pipeline 3 according to the second preset aperture.
[0046] From the above description, it can be seen that when adjusting the aperture of the connecting valve 4, the closest specification is selected from the preset existing specifications based on the ideal aperture value obtained by achieving equal flow, so as to complete the adjustment in terms of aperture to the greatest extent, avoiding the need to customize the aperture of the connecting valve 4. The difference that still exists after the aperture adjustment is completed is eliminated by adjusting the flow path length or bending angle of the branch pipeline 3. Adjustments in different aspects are coordinated in sequence to achieve the optimal adjustment.
[0047] Furthermore, the step S44 specifically includes:
[0048] S441, setting a coefficient size interval according to the ideal total pressure loss coefficient;
[0049] S442, determining whether the actual total pressure loss coefficient falls within the coefficient size interval; if not, adjusting the flow path length or bending angle of the branch pipeline 3.
[0050] From the above description, it can be seen that setting the coefficient size range can flexibly meet the actual current equalization target requirements, and allowing the actual total pressure loss coefficient to float within the range can also reduce the difficulty of re-adjusting the arrangement.
[0051] Furthermore, before step S1, the following steps are also included:
[0052] S00, an exhaust valve 6 is provided at the highest point of the return water main 2, and a drain valve 7 is provided at the lowest point of the return water main 2;
[0053] S01. During liquid injection, the drain valve 7 is connected to the water outlet of the liquid injection device 8, and the exhaust valve 6 is connected to the water inlet of the liquid injection device 8 through the gas-liquid separation tank.
[0054] From the above description, it can be seen that in addition to setting up a pressure loss balance mechanism, a liquid injection and exhaust optimization method is also added; when injecting liquid, rapid gas-liquid separation is performed in the liquid injection equipment 8 outside the liquid cooling pipeline, thereby improving the liquid injection and exhaust efficiency, reducing the residual proportion of gas and gas-liquid mixture in the liquid cooling system, and helping to achieve uniform flow, thereby increasing the service life of the liquid cooling system.
[0055] Please refer to Figure 2 , a pressure loss balancing system for each branch of an energy storage liquid cooling pipeline, comprising a controller and a liquid cooling pipeline, wherein the liquid cooling pipeline comprises a water cooling unit 5, a water supply main 1, a return water main 2, a branch pipeline 3 and a connecting valve 4;
[0056] The water cooling unit 5 is connected to the water supply pipe 1 and the water return pipe 2 respectively, and the branch pipe 3 is used to be arranged on the battery pack 9 in a one-to-one correspondence, and the two ends of the branch pipe 3 are connected to the water supply pipe 1 and the water return pipe 2 respectively through a connecting valve 4;
[0057] The controller is in communication with the water cooling unit 5, and the controller is used to perform the following steps:
[0058] S1, assisting in the preliminary arrangement of the liquid cooling pipeline, and maintaining the same bending degree of all the branch pipelines 3;
[0059] S2, setting and calculating the ideal flow splitting ratio of each branch pipeline 3 according to the first preset aperture of the connecting valve 4 and the preset flow mean of the branch pipeline 3;
[0060] S3. According to the ideal flow splitting ratio and the specification parameters of the liquid cooling pipeline, the ideal total pressure loss coefficient of the branch pipeline 3 is obtained, and the ideal total pressure loss coefficient is equal to the sum of the pressure loss coefficient along the branch pipeline 3, the bending pressure loss coefficient, the variable diameter pressure loss coefficient and the branch pipe pressure loss coefficient;
[0061] S4, obtaining the actual aperture values of the connecting valves 4 at both ends of the branch pipeline 3, calculating the along-the-line pressure loss coefficient, the bending pressure loss coefficient, and the variable-diameter pressure loss coefficient of the branch pipeline 3, and adjusting the flow path length or bending angle of the branch pipeline 3 in combination with the ideal total pressure loss coefficient;
[0062] S5. Execute step S4 on all the branch pipelines 3 to achieve pressure loss balance in all the branch pipelines 3.
[0063] From the above description, it can be seen that the beneficial effect of the present invention is that: by setting a uniform bending angle to preliminarily arrange the liquid cooling pipeline, and combining the preset flow mean, etc., the ideal total pressure loss coefficient that each branch pipeline 3 should have when tending to equal flow is calculated, and then some actual coefficients of each branch pipeline 3 are compared with the ideal total pressure loss coefficient to highlight the difference between the flow path length or bending angle of each branch pipeline 3 and the ideal state of achieving equal flow, and then adjust the flow path length or bending angle of the branch pipeline 3, that is, rearrange and eliminate the difference, so that the pressure loss of each branch pipeline 3 is balanced, and equal flow is achieved, which effectively prevents large temperature differences between battery clusters and extends the service life of the system.
[0064] Furthermore, the step S4 comprises:
[0065] S41, obtaining the actual aperture values of the connecting valves 4 at both ends of the branch pipeline 3, calculating the along-the-way pressure loss coefficient, bending pressure loss coefficient and variable diameter pressure loss coefficient of the branch pipeline 3, and combining the ideal total pressure loss coefficient to obtain the ideal branch pressure loss coefficient of the branch pipeline 3;
[0066] S42, obtaining the ideal aperture values of the connecting valves 4 at both ends of the branch pipeline 3 according to the ideal branch pipe pressure loss coefficient;
[0067] S43, recalculating the actual total pressure loss coefficient of the branch pipeline 3 based on the ideal aperture value;
[0068] S44. Adjust the flow path length or bending angle of the branch pipeline 3 according to the comparison result between the actual total pressure loss coefficient and the ideal total pressure loss coefficient.
[0069] From the above description, it can be seen that by using the mathematical relationship between the ideal total pressure loss coefficient and the pressure loss coefficient along the way, the bending pressure loss coefficient, the variable diameter pressure loss coefficient and the branch pressure loss coefficient, the original idea of seeking the difference by comparing the ideal total pressure loss coefficient with the actual total pressure loss coefficient is transformed into the difference of the detailed data of the branch pressure loss coefficient, that is, seeking the specific adjustment that can be made on the branch pipeline 3 to achieve equal flow, and finally the adjustment is directed to the aperture size of the connecting valve 4 and the flow path length or bending angle of the branch pipeline 3, so as to reduce the complexity of the adjustment to achieve equal flow. And corresponding adjustments can be made for each branch for the same content.
[0070] Furthermore, the step S2 comprises:
[0071] Selecting the first preset aperture from the preset aperture specification group as the aperture size of the connecting valve 4;
[0072] The step S43 specifically includes:
[0073] S431, selecting a second preset aperture value closest to the ideal aperture value from the preset aperture specification group;
[0074] S432. Recalculate the actual total pressure loss coefficient of the branch pipeline 3 according to the second preset aperture.
[0075] From the above description, it can be seen that when adjusting the aperture of the connecting valve 4, the closest specification is selected from the preset existing specifications based on the ideal aperture value obtained by achieving equal flow, so as to complete the adjustment from the aperture to the greatest extent, avoiding the need to customize the aperture of the connecting valve 4. The difference that still exists after the aperture adjustment is completed is eliminated by adjusting the flow path length or bending angle of the branch pipeline 3. Adjustments in different aspects are linked and coordinated in sequence to achieve the optimal adjustment.
[0076] Furthermore, the step S44 specifically includes:
[0077] S441, setting a coefficient size interval according to the ideal total pressure loss coefficient;
[0078] S442, determining whether the actual total pressure loss coefficient falls within the coefficient size interval; if not, adjusting the flow path length or bending angle of the branch pipeline 3.
[0079] From the above description, it can be seen that setting the coefficient size range can flexibly meet the actual current equalization target requirements, and allowing the actual total pressure loss coefficient to float within the range can also reduce the difficulty of re-adjusting the arrangement.
[0080] Furthermore, before step S1, the following steps are also included:
[0081] S00, an exhaust valve 6 is provided at the highest point of the return water main 2, and a drain valve 7 is provided at the lowest point of the return water main 2;
[0082] S01. During liquid injection, the drain valve 7 is connected to the water outlet of the liquid injection device 8, and the exhaust valve 6 is connected to the water inlet of the liquid injection device 8 through the gas-liquid separation tank.
[0083] From the above description, it can be seen that in addition to setting up a pressure loss balance mechanism, a liquid injection and exhaust optimization method is also added; when injecting liquid, rapid gas-liquid separation is performed in the liquid injection equipment 8 outside the liquid cooling pipeline, thereby improving the liquid injection and exhaust efficiency, reducing the residual proportion of gas and gas-liquid mixture in the liquid cooling system, and helping to achieve uniform flow, thereby increasing the service life of the liquid cooling system.
[0084] Please refer to Figure 1 , Embodiment 1 of the present invention is:
[0085] A method for balancing the pressure loss of each branch of an energy storage liquid cooling pipeline is applied to the liquid cooling pipeline, wherein the liquid cooling pipeline includes a water cooling unit 5, a water supply pipe 1, a return pipe 2, a branch pipe 3, and a connecting valve 4; the water cooling unit 5 is connected to the water supply pipe 1 and the return pipe 2 respectively, and the branch pipe 3 is used to be arranged on the battery pack 9 in a one-to-one correspondence, and the two ends of the branch pipe 3 are respectively connected to the water supply pipe 1 and the return pipe 2 through a connecting valve 4, including the following steps:
[0086] S1, assisting in the preliminary arrangement of the liquid cooling pipeline, and maintaining the same degree of bending of all branch pipelines 3;
[0087] S2, setting and calculating the ideal flow splitting ratio of each branch pipeline 3 according to the first preset aperture of the connecting valve 4 and the preset flow mean of the branch pipeline 3;
[0088] In this embodiment, a first preset aperture is selected from the preset aperture specification group as the aperture size of the connecting valve 4. As shown in the figure, for the connecting valve 4, the connecting valve 4 located in the middle of the water supply pipe 1 or the return pipe 2 is a three-way valve, and the connecting valve 4 located at the end of the water supply pipe 1 or the return pipe 2 is a two-way valve. The aperture specifications of the optional three-way joint or two-way joint are a, b, c, etc.;
[0089] In the n branch pipelines 3, the preset flow mean is set to Q, and the distance from the middle position of the liquid cooling unit is m=ROUND(n / 2,0). Assuming that the apertures of the three-way joint m-1 (water supply side) and the three-way joint m-2 (water return side) of this loop are Dm-1=Dm-2=b, the flow splits in the mth branch are (nm)*Q and Q respectively, and the ideal split ratio = (nm):1.
[0090] S3. According to the ideal flow splitting ratio and the specification parameters of the liquid cooling pipeline, the ideal total pressure loss coefficient of the branch pipeline 3 is obtained. The ideal total pressure loss coefficient is equal to the sum of the pressure loss coefficient along the branch pipeline 3, the bending pressure loss coefficient, the variable diameter pressure loss coefficient and the branch pipe pressure loss coefficient;
[0091] In order to fully understand the relationship between the pressure loss coefficient and the flow distribution, the following explanation is given:
[0092] The flow resistance formula of the liquid cooling pipeline is as follows:
[0093] = ;
[0094] Among them, ζ is the total pressure loss coefficient, which is the sum of the pressure loss coefficients of various types of resistance; ρ is the density of the cooling medium; Q is the volume flow rate; S is the cross-sectional area of the pipeline, and v represents the flow velocity of the fluid; the flow resistance of each parallel flow path is consistent. In order to achieve consistent volume flow rates of each parallel flow path, the total pressure loss coefficient ζ must be consistent.
[0095] For liquid cooling pipelines, the resistance pressure loss mainly includes the following aspects:
[0096] 1. Resistance along the way, its value is proportional to the path length, pressure loss coefficient ζa, each branch pipeline 3 has a different pressure loss coefficient along the way due to different flow path lengths;
[0097] 2. Variable diameter resistance, which can be divided into reduction loss and expansion loss. The value is related to the diameter reduction ratio. Each diameter reduction is calculated independently, and the coefficients are accumulated. The pressure loss coefficient ζb. In each branch pipeline, the difference in the variable diameter pressure loss coefficient is related to the aperture of the valve 4 connected to the above-mentioned component;
[0098] 3. Bending resistance, its value is related to the bending angle of the branch pipe 3. Each bend is calculated independently, and the coefficients are accumulated, and the pressure loss coefficient ζc; in each branch pipe 3, the difference in bending resistance is related to the difference in shape of the water supply main pipe 1 and the return water main pipe 2;
[0099] 4. The branch pipe resistance is related to the pipe diameter ratio and flow ratio of the branch pipeline 3. Each branch pipe is calculated independently, and the coefficients are accumulated. The pressure loss coefficient ζd is related to the position of the branch pipeline 3 in each branch pipeline 3.
[0100] It can be concluded that step S3 can be further expressed as: calculate the along-the-line pressure loss coefficient ζam, variable-diameter pressure loss coefficient ζbm, bending pressure loss coefficient ζcm, and branch pressure loss coefficient ζdm of the m-th branch, and obtain the ideal total pressure loss coefficient ζm of the m-th branch.
[0101] The total pressure loss coefficient of each branch pipeline is listed. Since the purpose of this method is to make the total pressure loss coefficient of each branch pipeline connected in parallel consistent so as to achieve close flow of each branch pipeline, this is used as input, and the formulas of each pressure loss coefficient are combined, that is, ζ1=ζ2=ζ3=…=ζn=ζ. Then, the aperture size of each connecting valve 4 or the bending angle difference of each branch pipeline 3 is obtained by solving. For details, see the subsequent steps.
[0102] S4, obtaining the actual aperture values of the connecting valves 4 at both ends of the branch pipeline 3, calculating the pressure loss coefficient along the branch pipeline 3, the bending pressure loss coefficient, and the variable diameter pressure loss coefficient, and adjusting the flow path length or bending angle of the branch pipeline 3 in combination with the ideal total pressure loss coefficient, specifically including:
[0103] S41, obtaining the actual aperture values of the connecting valves 4 at both ends of the branch pipeline 3, calculating the pressure loss coefficient along the branch pipeline 3, the bending pressure loss coefficient and the variable diameter pressure loss coefficient, and combining the ideal total pressure loss coefficient to obtain the ideal branch pressure loss coefficient of the branch pipeline 3;
[0104] S42, according to the ideal branch pipe pressure loss coefficient, obtain the ideal aperture value of the connecting valve 4 at both ends of the branch pipe 3;
[0105] S431, selecting a second preset aperture value closest to the ideal aperture value from the preset aperture specification group;
[0106] S432. Recalculate the actual total pressure loss coefficient of the branch pipeline 3 according to the second preset aperture.
[0107] S44. According to the comparison result between the actual total pressure loss coefficient and the ideal total pressure loss coefficient, the flow path length or bending angle of the branch pipeline 3 is adjusted, as follows:
[0108] S441, setting a coefficient size interval according to an ideal total pressure loss coefficient;
[0109] S442, determining whether the actual total pressure loss coefficient falls within the coefficient size interval; if not, adjusting the flow path length or bending angle of the branch pipeline 3.
[0110] In this embodiment, the branch pipeline 3 closest to the liquid cooling unit is taken as the first branch, and the above steps are illustrated as follows:
[0111] Solve the first branch, and calculate the along-the-way pressure loss coefficient ζa1, bending pressure loss coefficient ζc1, and variable diameter pressure loss coefficient ζb1 of the first branch through the mean flow rate, length, bending angle of the first branch and the actual aperture values of the connecting valves 4 at both ends. The total pressure loss coefficient ζ1 of the first branch = ζm, thus ζc1 = ζm-ζa1-ζb1-ζc1 can be achieved, and then the apertures D1-1 and D1-2 of the connecting valves 4 at both ends of the first branch are obtained.
[0112] After obtaining the above D1-1 and D1-2, compare them with the actual optional aperture D specifications a, b, and c of the connecting valve 4, select the closest specification, that is, the second preset aperture, substitute it into the calculation to obtain the actual total pressure loss coefficient ζ1' of the first branch, and according to the flow resistance formula, the pressure loss coefficient is inversely proportional to the square of the flow rate. According to the flow equalization target, the following judgment is made:
[0113] If ζ1' is within the interval (0.81*ζ1, 1.21*ζ1), then the current equalization target is considered to be achieved;
[0114] If ζ1' is not within the interval of (0.81*ζ1, 1.21*ζ1), it is necessary to change the flow path length or bending angle of the first branch, that is, change ζa1 and ζb1 to correct ζ1' and achieve the flow equalization target.
[0115] S5. Execute step S4 for all branch pipelines 3 to achieve pressure loss balance for all branch pipelines 3.
[0116] In order to intuitively reflect the benefits of the above method, the following examples are given:
[0117] Reference Figure 2As shown, the liquid cooling pipeline includes: a water supply main pipe 1, which is connected to the water outlet of the water cooling unit 5 through a quick plug; a return water main pipe 2, which is connected to the water inlet of the water cooling unit 5 through a quick plug; 7 water supply branches (the same number as the battery pack 9) are connected to the water inlet of the battery pack 9 through a quick plug; 7 return water branches (the same number as the battery pack 9) are connected to the water outlet of the battery pack 9 through a quick plug;
[0118] Among them, the T-type three-way joint is used to connect the main pipe and the branch pipe with different inner diameters; the L-type two-way joint is used to connect the water supply main pipe at the end and the water supply branch pipe; the exhaust valve 6 is located at the highest point of the return water main line and is used for exhausting the system; the drain valve 7 is located at the lowest point of the return water main line and is used for draining the system.
[0119] In this application example, the rated flow of the water cooling unit 5 is 50L / min, the inner diameter of the connector is 21mm, the inner diameter of the connector of the battery pack 9 is 12mm, the maximum pressure resistance of the system is 3.5Bar, and the flow of each battery pack 9 is required to be within ±20%.
[0120] The inner diameters of the water supply pipe 1 and the return pipe 2 are 21 mm, which are consistent with the inner diameter of the joint of the water cooling unit 5; the inner diameters of the water supply branch pipe and the return branch pipe are 12 mm, which are consistent with the inner diameter of the joint of the battery pack 9.
[0121] In this application example, the inner diameters of the branch pipes of the T-type three-way connector and the L-type two-way connector are calculated and designed by the above method, and the flow equalization target can be achieved without adjusting the length and bending angle differences of each branch, as shown in Table 1:
[0122] Table 1 Inner diameter of the branch pipes of T-type three-way connectors and L-type two-way connectors
[0123]
[0124] The flow distribution of each battery pack meets the ±10% flow requirement, as shown in Table 2:
[0125] Table 2 Battery pack flow distribution
[0126]
[0127] Please refer to Figure 2 , Embodiment 2 of the present invention is:
[0128] A method for balancing the pressure loss of each branch of an energy storage liquid cooling pipeline, based on the above-mentioned embodiment 1, further comprising before step S1:
[0129] S00, an exhaust valve 6 is set at the highest point of the return water main 2, and a drain valve 7 is set at the lowest point of the return water main 2;
[0130] S01. During liquid injection, the drain valve 7 is connected to the water outlet of the liquid injection device 8, and the exhaust valve 7 is connected to the water inlet of the liquid injection device 8 through the gas-liquid separation tank.
[0131] like Figure 2 As shown, during liquid injection, the gas in the system is squeezed by the liquid and discharged from the top exhaust valve, and then enters the gas-liquid separation tank after the liquid injection device; the liquid part re-enters the liquid injection chamber of the liquid injection device 8 and is refilled into the liquid cooling system, while the gas is collected and does not participate in the subsequent circulation. Therefore, with the help of rapid gas-liquid separation in the liquid injection device 8 outside the liquid cooling system, the liquid injection exhaust efficiency is improved, and the residual proportion of gas and gas-liquid mixture in the liquid cooling system is reduced.
[0132] When the coolant needs to be discharged for system maintenance, in this embodiment, a drain valve 7 is set at the lowest point of the return water main 2, which can be externally connected to a standard pipeline to quickly discharge the system liquid, and gas can be injected into the exhaust valve 7 at the highest point to speed up the discharge of residual liquid in the system.
[0133] Please refer to Figure 2 and Figure 3 , Embodiment 3 of the present invention is:
[0134] A pressure loss balancing system for each branch of an energy storage liquid cooling pipeline comprises a controller and a liquid cooling pipeline, wherein the liquid cooling pipeline comprises a water cooling unit 5, a water supply pipe 1, a return pipe 2, a branch pipe 3 and a connecting valve 4; the water cooling unit 5 is respectively connected to the water supply pipe 1 and the return pipe 2, the branch pipe 3 is used to be arranged on a battery pack in a one-to-one correspondence, and the two ends of the branch pipe 3 are respectively connected to the water supply pipe 1 and the return pipe 2 through a connecting valve 4; the highest point of the return pipe 2 is provided with an exhaust valve 6, and the lowest point of the return pipe 2 is provided with a drain valve 7; the controller is communicatively connected to the water cooling unit 5, and the controller is used to execute a pressure loss balancing method for each branch of an energy storage liquid cooling pipeline in embodiment one or two.
[0135] In summary, the present invention provides a method and system for balancing the pressure losses of branches of energy storage liquid cooling pipelines. The liquid cooling pipelines are preliminarily arranged by setting a unified bending angle, and combined with a preset flow average, etc., to calculate the ideal total pressure loss coefficient that each branch pipeline should have when tending to equal flow, and then some actual coefficients of each branch pipeline are compared with the ideal total pressure loss coefficient to highlight the difference between the flow path length or bending angle of each branch pipeline compared to the ideal state of achieving equal flow, and then adjust the flow path length or bending angle of the branch pipeline, that is, rearrange and eliminate the difference, so that the pressure loss of each branch pipeline is balanced, equal flow is achieved, and a large temperature difference between battery clusters is effectively prevented, thereby extending the service life of the system.
[0136] The above descriptions are merely embodiments of the present invention and are not intended to limit the patent scope of the present invention. Any equivalent transformations made using the contents of the present invention's specification and drawings, or directly or indirectly applied in related technical fields, are also included in the patent protection scope of the present invention.
Claims
1. A method for balancing the pressure loss of each branch of an energy storage liquid cooling pipeline, applied to a liquid cooling pipeline, wherein the liquid cooling pipeline comprises a water cooling unit, a water supply pipe, a return pipe, a branch pipe and a connecting valve; the water cooling unit is connected to the water supply pipe and the return pipe respectively, the branch pipe is used to be arranged on the battery pack in a one-to-one correspondence, and the two ends of the branch pipe are connected to the water supply pipe and the return pipe respectively through one of the connecting valves, characterized in that: The steps include: S1. Assisting in the preliminary arrangement of the liquid cooling pipeline and maintaining the same bending degree of all the branch pipelines; S2. Setting and calculating an ideal flow splitting ratio of each branch pipeline according to a first preset aperture of the connecting valve and a preset flow average of the branch pipeline; Step S2 is specifically as follows: The first preset aperture is selected from the preset aperture specification group as the aperture size of the connecting valve. The connecting valve located in the middle of the water supply main or the return water main is a three-way valve, and the connecting valve located at the end of the water supply main or the return water main is a two-way valve. The aperture specifications of the three-way valve or the two-way valve that can be selected include a, b, and c. In the n branch pipelines, the preset flow mean is set to Q. The distance from the middle position of the liquid cooling unit is m=ROUND(n / 2,0). Assume that the aperture D of the three-way valve m-1 and the three-way valve m-2 of the mth branch pipeline m-1 =D m-2 =b, m-1 is the valve on the water supply side of the m-th branch pipeline, m-2 is the valve on the return side of the m-th branch pipeline, the flow splits in the m-th branch pipeline are (nm)×Q and Q respectively, and the ideal split ratio of each branch pipeline = (nm): 1; S3. According to the ideal flow splitting ratio and the specification parameters of the liquid cooling pipeline, the pressure loss coefficient along the m-th branch pipeline, the pressure loss coefficient of the variable diameter, the pressure loss coefficient of the bending, and the pressure loss coefficient of the branch pipe are calculated to obtain the ideal total pressure loss coefficient of the m-th branch pipeline, which is equal to the sum of the pressure loss coefficient along the m-th branch pipeline, the pressure loss coefficient of the bending, the pressure loss coefficient of the variable diameter, and the pressure loss coefficient of the branch pipe; S4, obtaining the actual aperture values of the connecting valves at both ends of the branch pipeline, calculating the along-the-line pressure loss coefficient, bending pressure loss coefficient and variable diameter pressure loss coefficient of the branch pipeline, and adjusting the flow path length or bending angle of the branch pipeline in combination with the ideal total pressure loss coefficient of the mth branch pipeline; The step S4 comprises: S41, obtaining the actual aperture values of the connecting valves at both ends of the first branch pipeline, calculating the along-line pressure loss coefficient, bending pressure loss coefficient and variable diameter pressure loss coefficient of the first branch pipeline, and combining the ideal total pressure loss coefficient of the m-th branch pipeline to obtain the ideal branch pipe pressure loss coefficient of the first branch pipeline, the ideal branch pipe coefficient of the first branch pipeline is the ideal total pressure loss coefficient of the m-th branch pipeline minus the along-line pressure loss coefficient, bending pressure loss coefficient and variable diameter pressure loss coefficient of the first branch pipeline, the ideal branch pipe pressure loss coefficient of the first branch pipeline is the ideal total pressure loss coefficient of the m-th branch pipeline minus the along-line pressure loss coefficient, bending pressure loss coefficient and variable diameter pressure loss coefficient of the first branch pipeline; S42, obtaining ideal aperture values of the connecting valves at both ends of the first branch pipeline according to the ideal branch pipe pressure loss coefficient of the first branch pipeline; S43, recalculating the actual total pressure loss coefficient of the first branch pipeline based on the ideal aperture values of the connecting valves at both ends of the first branch pipeline; S44, adjusting the flow path length or bending angle of the first branch pipeline according to a comparison result of an actual total pressure loss coefficient of the first branch pipeline and an ideal total pressure loss coefficient of the mth branch pipeline; The step S43 specifically includes: S431, selecting a second preset aperture that is closest to the ideal aperture value of the connecting valve at both ends of the first branch pipeline from the preset aperture specification group; S432, recalculating the actual total pressure loss coefficient of the first branch pipeline according to the second preset aperture; S5. Execute step S4 on all the branch pipelines to achieve pressure loss balance in all the branch pipelines.
2. A method for balancing the pressure loss of each branch of an energy storage liquid cooling pipeline according to claim 1, characterized in that: The step S44 specifically includes: S441, setting a coefficient size interval according to the ideal total pressure loss coefficient of the mth branch pipeline; S442: Determine whether the actual total pressure loss coefficient falls within the coefficient size range; if not, adjust the flow path length or bending angle of the first branch pipeline.
3. A method for balancing the pressure loss of each branch of an energy storage liquid cooling pipeline according to claim 1, characterized in that: Before step S1, the following steps are also included: S00, an exhaust valve is arranged at the highest point of the water return pipe, and a drain valve is arranged at the lowest point of the water return pipe; S01. During liquid injection, the drain valve is connected to the water outlet of the liquid injection device, and the exhaust valve is connected to the water inlet of the liquid injection device through a gas-liquid separation tank.
4. A pressure loss balancing system for each branch of an energy storage liquid cooling pipeline, characterized in that: It includes a controller and a liquid cooling pipeline, wherein the liquid cooling pipeline includes a water cooling unit, a water supply pipe, a water return pipe, a branch pipe and a connecting valve; The water cooling unit is connected to the water supply pipe and the water return pipe respectively, the branch pipes are used to be arranged on the battery pack in a one-to-one correspondence, and the two ends of the branch pipes are connected to the water supply pipe and the water return pipe respectively through one of the connecting valves; The controller is in communication with the water cooling unit, and the controller is used to perform the following steps: S1. Assisting in the preliminary arrangement of the liquid cooling pipeline and maintaining the same bending degree of all the branch pipelines; S2. Setting and calculating an ideal flow splitting ratio of each branch pipeline according to a first preset aperture of the connecting valve and a preset flow average of the branch pipeline; Step S2 is specifically as follows: The first preset aperture is selected from the preset aperture specification group as the aperture size of the connecting valve. The connecting valve located in the middle of the water supply main or the return water main is a three-way valve, and the connecting valve located at the end of the water supply main or the return water main is a two-way valve. The aperture specifications of the three-way valve or the two-way valve that can be selected include a, b, and c. In the n branch pipelines, the preset flow mean is set to Q. The distance from the middle position of the liquid cooling unit is m=ROUND(n / 2,0). Assume that the aperture D of the three-way valve m-1 and the three-way valve m-2 of the mth branch pipeline m-1 =D m-2 =b, m-1 is the valve on the water supply side of the m-th branch pipeline, m-2 is the valve on the return side of the m-th branch pipeline, the flow splits in the m-th branch pipeline are (nm)×Q and Q respectively, and the ideal split ratio of each branch pipeline = (nm): 1; S3. According to the ideal flow splitting ratio and the specification parameters of the liquid cooling pipeline, the pressure loss coefficient along the m-th branch pipeline, the pressure loss coefficient of the variable diameter, the pressure loss coefficient of the bending, and the pressure loss coefficient of the branch pipe are calculated to obtain the ideal total pressure loss coefficient of the m-th branch pipeline, which is equal to the sum of the pressure loss coefficient along the m-th branch pipeline, the pressure loss coefficient of the bending, the pressure loss coefficient of the variable diameter, and the pressure loss coefficient of the branch pipe; S4, obtaining the actual aperture values of the connecting valves at both ends of the branch pipeline, calculating the along-the-line pressure loss coefficient, bending pressure loss coefficient and variable diameter pressure loss coefficient of the branch pipeline, and adjusting the flow path length or bending angle of the branch pipeline in combination with the ideal total pressure loss coefficient of the mth branch pipeline; The step S4 comprises: S41, obtaining the actual aperture values of the connecting valves at both ends of the first branch pipeline, calculating the along-line pressure loss coefficient, bending pressure loss coefficient and variable diameter pressure loss coefficient of the first branch pipeline, and combining the ideal total pressure loss coefficient of the m-th branch pipeline to obtain the ideal branch pipe pressure loss coefficient of the first branch pipeline, which is the ideal branch pipe pressure loss coefficient of the m-th branch pipeline minus the along-line pressure loss coefficient, bending pressure loss coefficient and variable diameter pressure loss coefficient of the first branch pipeline; S42, obtaining ideal aperture values of the connecting valves at both ends of the first branch pipeline according to the ideal branch pipe pressure loss coefficient of the first branch pipeline; S43, recalculating the actual total pressure loss coefficient of the first branch pipeline based on the ideal aperture values of the connecting valves at both ends of the first branch pipeline; S44, adjusting the flow path length or bending angle of the first branch pipeline according to a comparison result of an actual total pressure loss coefficient of the first branch pipeline and an ideal total pressure loss coefficient of the mth branch pipeline; The step S43 specifically includes: S431, selecting a second preset aperture that is closest to the ideal aperture value of the connecting valve at both ends of the first branch pipeline from the preset aperture specification group; S432, recalculating the actual total pressure loss coefficient of the first branch pipeline according to the second preset aperture; S5. Execute step S4 on all the branch pipelines to achieve pressure loss balance in all the branch pipelines.
5. A pressure loss balancing system for each branch of an energy storage liquid cooling pipeline according to claim 4, characterized in that: The step S44 specifically includes: S441, setting a coefficient size interval according to the ideal total pressure loss coefficient of the mth branch pipeline; S442: Determine whether the actual total pressure loss coefficient falls within the coefficient size range; if not, adjust the flow path length or bending angle of the first branch pipeline.
6. A pressure loss balancing system for each branch of an energy storage liquid cooling pipeline according to claim 4, characterized in that: Before step S1, the following steps are also included: S00, an exhaust valve is arranged at the highest point of the water return pipe, and a drain valve is arranged at the lowest point of the water return pipe; S01. During liquid injection, the drain valve is connected to the water outlet of the liquid injection device, and the exhaust valve is connected to the water inlet of the liquid injection device through a gas-liquid separation tank.
Citation Information
Patent Citations
Thermal simulation analysis method and device for liquid cooling energy storage system and storage medium
CN115203909A
Maximum friction coefficient estimation system and maximum friction coefficient estimation method
US20230347901A1