Method, device, terminal and storage medium for tracing water accumulation simulation calculation in nuclear power plant area
Through the combination of tropical cyclone inversion model, offshore wave calculation model and underground drainage system model, the problem of water accumulation distribution and coastal wave climbing in nuclear power plant areas is solved, the simulation and traceability of water accumulation in nuclear power plant areas is realized, and nuclear power design is improved accuracy and safety.
Patent Information
- Application Number
- CN202410727136.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-06
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2044-06-06
AI Technical Summary
It is difficult to accurately calculate the water accumulation distribution in the nuclear power plant area and the wave climbing along the coast in existing nuclear power designs, and the lack of general simulation calculation methods makes it difficult to determine the bottom elevation of the nuclear island design and the height of the wave retaining wall.
The tropical cyclone inversion model, offshore wave calculation model and current model are used, combined with the digital elevation model and underground drainage system model, and simulated calculation of rainfall distribution, wind field distribution, runoff and overflow volume of nuclear power plant area, thereby realizing water accumulation in the plant area traceability.
The simulation and traceability of water accumulation in nuclear power plant areas is realized, providing a basis for interception design in nuclear power design, and improving the operation safety of nuclear power plants.
Smart Images

Figure CN118296715B_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of simulation calculation, and in particular relates to a method, device, terminal and storage medium for tracing water accumulation simulation calculation in a nuclear power plant area. Background Art
[0002] Binhai Nuclear Power Plant adopts different design standards for rainwater pipe network systems in different areas according to the importance of structures in the plant area. The main plant area where the nuclear island is located adopts a once-in-a-millennium rainstorm intensity design, and the maximum possible rainstorm intensity is checked. In the design of the nuclear island, the bottom elevation of the nuclear island is an important design parameter, which is related to the operation safety of the nuclear power plant.
[0003] Severe weather systems, such as storms or typhoons, not only bring a lot of rainfall, but also may cause the increase of offshore tides. Under the influence of typhoons, the offshore waves will be huge. Typhoons will cause some seawater to cross the plant's protective dikes and enter the plant area. This part of the seawater will flow on the ground of the plant area. At present, the calculation method of the return period is used in nuclear power design. Various design parameters are too large, and the investment in engineering projects is huge. At this stage, there is no universal simulation calculation method to determine the design bottom elevation of the nuclear island and the height of the coastal wave wall. Summary of the invention
[0004] In view of this, the present invention aims to propose a method, device, terminal and storage medium for tracing the source of water accumulation simulation calculation in a nuclear power plant area, so as to solve the problem of difficulty in performing numerical simulation calculations of water accumulation distribution in a nuclear power plant area and wave height along the coast in existing nuclear power designs.
[0005] To achieve the above object, the technical solution of the present invention is achieved as follows:
[0006] In a first aspect, an embodiment of the present invention provides a method for tracing the source of water accumulation in a nuclear power plant area through simulation calculation, comprising:
[0007] Establishing a tropical cyclone inversion model, and simulating and calculating the rainfall distribution and wind field distribution in the study area according to the tropical cyclone inversion model; wherein the study area includes the factory area;
[0008] Establishing an offshore wave calculation model and an ocean current model, and performing nearshore overtopping amount simulation calculation using the offshore wave calculation model and the ocean current model according to the wind field distribution to obtain the overtopping amount;
[0009] A one-dimensional rainfall-runoff model is established based on the digital elevation model of the study area, and according to the rainfall distribution, the one-dimensional rainfall-runoff model is used to perform runoff simulation calculation to obtain the runoff of the small watershed;
[0010] Based on the underground drainage system of the plant, a two-dimensional model of the plant and a one-dimensional pipe network model are established;
[0011] Obtaining a rainfall time series of a rainfall process in a plant area output by the tropical cyclone inversion model, using the rainfall time series as a model parameter of the two-dimensional model of the plant area, and using the overtopping amount and the small watershed runoff as boundary conditions of the two-dimensional model of the plant area;
[0012] The flow of the pipeline in the one-dimensional pipe network model is accessed by using the two-dimensional plant model, and the flow difference between adjacent pipelines in the one-dimensional pipe network model is used as the flow process of the point source in the two-dimensional plant model to realize the drainage calculation of the two-dimensional plant model; and the water head information at the point source is transmitted to the one-dimensional pipe network model by using the two-dimensional plant model to realize the drainage calculation of the one-dimensional pipe network model;
[0013] After calibrating each water source in the two-dimensional model of the plant area using different tracers, the proportion of each tracer in the waterlogged area in the two-dimensional model of the plant area is calculated to trace the source of the waterlogged area.
[0014] Furthermore, the one-dimensional rainfall-runoff model is established based on the digital elevation model at the study area, and the runoff simulation calculation is performed using the one-dimensional rainfall-runoff model according to the rainfall distribution to obtain the small watershed runoff, including:
[0015] Acquire a digital elevation model of the study area, and divide the small watershed where the study area is located according to the digital elevation model;
[0016] According to the location of the plant in the study area, extract the small watershed where the flow line enters the plant, and divide the small watershed where the flow line enters the plant into a plurality of sub-catchments; wherein the flow of rainfall runoff entering the study area passes through different sub-catchments to form a flow time process for inputting the two-dimensional model of the plant;
[0017] All boundaries of the study area are used as end nodes of streamline tracing to construct a one-dimensional rainfall-runoff model; wherein the end nodes are used as point sources of the two-dimensional model of the plant area;
[0018] According to the rainfall distribution, the one-dimensional rainfall-runoff model is used to perform runoff simulation calculation to obtain the small watershed runoff.
[0019] Furthermore, the two-dimensional model of the plant area and the one-dimensional pipe network model are established based on the underground drainage system of the plant area, including:
[0020] Obtain the spatial topological relationship of the pipe network in the underground drainage system of the plant, the parameters of the pipe network, the location of the wells in the pipe network, the bottom elevation of the wells, the diameter of the wells, the outflow nodes of the pipe network, and the ocean water level of the outflow nodes;
[0021] Establish a two-dimensional model of the plant area, and use the wells in the pipe network as point sources in the two-dimensional model of the plant area;
[0022] A one-dimensional pipe network model is established according to the spatial topological relationship of the pipe network, the parameters of the pipe network, the location of the wells in the pipe network, the bottom elevation of the wells, the diameter of the wells, the outflow nodes of the pipe network, and the ocean water level of the outflow nodes.
[0023] Further, the method of using the two-dimensional plant model to access the flow of the pipeline in the one-dimensional pipe network model, using the flow difference between adjacent pipelines in the one-dimensional pipe network model as the flow process of the point source in the two-dimensional plant model to realize the drainage calculation of the two-dimensional plant model; and using the two-dimensional plant model to transfer the head information at the point source to the one-dimensional pipe network model to realize the drainage calculation of the one-dimensional pipe network model, includes:
[0024] Obtain the flow difference between adjacent pipes before and after the point source in the one-dimensional pipe network model to obtain the overflow flow of the point source , the formula is as follows:
[0025] ;
[0026] in, is the flow rate input into the pipeline in the previous section, is the flow rate of the next section of the pipeline;
[0027] The overflow flow of the point source in the one-dimensional pipe network model is accessed by using the two-dimensional model of the plant area , using the overflow flow of the point source in the one-dimensional pipe network model As the flow process of the point source in the two-dimensional model of the plant area, the drainage calculation of the two-dimensional model of the plant area is realized to obtain the head information at the point source , the calculation formula is as follows:
[0028] ;
[0029] in, is the flow rate input into the pipeline in the previous section, is the flow rate of the next section of the pipeline, is the pressure head of the point source at the end of the previous section of the pipeline, is the pressure head of the point source at the end of the next section of the pipeline, is the well water depth of the point source at the end of the pipeline in the previous section, is the well water depth of the point source at the end of the next section of the pipeline, is the average length of the pipeline, is the average water-passing short-section area of the pipeline, is the time step, is the acceleration due to gravity;
[0030] The water head information at the point source is transmitted to the one-dimensional pipe network model by using the two-dimensional model of the plant area , in order to realize the drainage calculation of the one-dimensional pipe network model.
[0031] Further, the method of using the two-dimensional plant model to access the flow of the pipeline in the one-dimensional pipe network model, using the flow difference between adjacent pipelines in the one-dimensional pipe network model as the flow process of the point source in the two-dimensional plant model to realize the drainage calculation of the two-dimensional plant model; and using the two-dimensional plant model to transfer the head information at the point source to the one-dimensional pipe network model to realize the drainage calculation of the one-dimensional pipe network model, further includes:
[0032] Using shared memory to store the overflow flow of point sources in the one-dimensional pipe network model , and the water head information at the point source in the two-dimensional model of the plant area ;
[0033] When the two-dimensional plant model reads the overflow flow of the point source in the one-dimensional pipe network model stored in the shared memory After that, clear the shared memory and write the water head information at the next point source ;
[0034] When the one-dimensional pipe network model reads the water head information at the point source in the two-dimensional plant model stored in the shared memory After that, clear the shared content and write the overflow flow of the next point source .
[0035] Furthermore, after calibrating each water source in the two-dimensional model of the plant area using different tracers, the proportion of each tracer in the waterlogged area in the two-dimensional model of the plant area is calculated to trace the source of the waterlogged area, including:
[0036] Different tracers are used to calibrate the water sources in the two-dimensional model of the plant area. The water sources of the two-dimensional model of the plant area include rainfall water, runoff water, over-wave water, and pipe network drainage. The runoff water and over-wave water are given by the boundary conditions, and the open boundary is divided into The number of wells in the network from which the network drains water Given, different tracers are set for runoff water, overtopping water, and pipe network drainage. ;
[0037] When a waterlogging area appears in the two-dimensional model of the plant area, the concentration of each tracer is , then the proportion of each water source in the waterlogged area is , , the proportion of rainfall water is , the formula is as follows:
[0038] ,
[0039] .
[0040] In a second aspect, an embodiment of the present invention further provides a nuclear power plant water accumulation simulation calculation source tracing device, comprising:
[0041] An inversion module is used to establish a tropical cyclone inversion model and simulate and calculate the rainfall distribution and wind field distribution in the study area according to the tropical cyclone inversion model; wherein the study area includes the factory area;
[0042] A calculation module is used to establish an offshore wave calculation model and an ocean current model, and to perform nearshore overtopping amount simulation calculation using the offshore wave calculation model and the ocean current model according to the wind field distribution to obtain the overtopping amount;
[0043] A rainfall module is used to establish a one-dimensional rainfall runoff model based on the digital elevation model of the study area, and to perform runoff simulation calculation using the one-dimensional rainfall runoff model according to the rainfall distribution to obtain the runoff of the small watershed;
[0044] Establish a module for establishing a two-dimensional model of the plant area and a one-dimensional pipe network model based on the underground drainage system of the plant area;
[0045] An acquisition module, used for acquiring a rainfall time series of a rainfall process in a plant area output by the tropical cyclone inversion model, using the rainfall time series as a model parameter of the two-dimensional model of the plant area, and using the overtopping amount and the small watershed runoff as boundary conditions of the two-dimensional model of the plant area;
[0046] A calculation module, used to access the flow of the pipes in the one-dimensional pipe network model using the two-dimensional plant model, use the flow difference between adjacent pipes in the one-dimensional pipe network model as the flow process of the point source in the two-dimensional plant model, so as to realize the drainage calculation of the two-dimensional plant model; and use the two-dimensional plant model to transfer the head information at the point source to the one-dimensional pipe network model, so as to realize the drainage calculation of the one-dimensional pipe network model;
[0047] The source tracing module is used to calibrate each water source in the two-dimensional model of the plant area using different tracers, and then calculate the proportion of each tracer in the waterlogged area in the two-dimensional model of the plant area to achieve source tracing of the waterlogged area.
[0048] In a third aspect, an embodiment of the present invention further provides a terminal, including:
[0049] one or more processors;
[0050] A storage device for storing one or more programs;
[0051] When the one or more programs are executed by the one or more processors, the one or more processors implement the above-mentioned nuclear power plant area water accumulation simulation calculation and tracing method.
[0052] In a fourth aspect, an embodiment of the present invention further provides a storage medium comprising computer executable instructions, which, when executed by a computer processor, are used to perform the above-mentioned nuclear power plant area water accumulation simulation calculation and tracing method.
[0053] Compared with the prior art, the method, device, terminal and storage medium for tracing the source of water accumulation in a nuclear power plant area according to the present invention have the following advantages:
[0054] The method, device, terminal and storage medium for simulating and calculating the source of water accumulation in a nuclear power plant area described in the present invention solve the problem that it is difficult to perform numerical simulation calculations on the distribution of water accumulation in a nuclear power plant area and the height of waves along the coast in existing nuclear power designs. It can realize the simulation of water accumulation in a nuclear power plant area during the nuclear power design process, and can also trace the source of the water accumulation, so as to facilitate timely interception design in nuclear power design. BRIEF DESCRIPTION OF THE DRAWINGS
[0055] The accompanying drawings constituting a part of the present invention are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the accompanying drawings:
[0056] Figure 1 A schematic diagram of a technical route of a method for tracing the source of water accumulation in a nuclear power plant area according to the first embodiment of the present invention;
[0057] Figure 2 A schematic diagram of the process of tracing the source of water accumulation in a nuclear power plant area according to the first embodiment of the present invention;
[0058] Figure 3 It is a schematic diagram of the process of tropical cyclone inversion in the method for tracing the source of water accumulation simulation calculation in a nuclear power plant area according to the first embodiment of the present invention;
[0059] Figure 4 It is a schematic diagram of the simulation process of the two-dimensional model of the plant area in the method for tracing the source of water accumulation simulation calculation in the nuclear power plant area according to the first embodiment of the present invention;
[0060] Figure 5 It is a structural schematic diagram of the interaction between the one-dimensional pipe network model and the two-dimensional plant model in the nuclear power plant area water accumulation simulation calculation and source tracing method according to the first embodiment of the present invention;
[0061] Figure 6 It is a schematic diagram of a process of using shared memory to interact between a one-dimensional pipe network model and a two-dimensional plant model in the nuclear power plant area water accumulation simulation calculation and source tracing method according to the first embodiment of the present invention;
[0062] Figure 7 It is a structural schematic diagram of the study area in the method for tracing the source of water accumulation in a nuclear power plant area according to the first embodiment of the present invention;
[0063] Figure 8 It is a structural schematic diagram of a case where there is a waterlogging area in the study area in the method for tracing the source of waterlogging in a nuclear power plant area according to the first embodiment of the present invention;
[0064] Fig. 9 A schematic diagram of the structure of a nuclear power plant water accumulation simulation calculation and source tracing device provided in the second embodiment of the present invention;
[0065] Fig.10 A schematic diagram of the structure of a nuclear power plant water accumulation simulation calculation and tracing terminal provided in Embodiment 3 of the present invention. DETAILED DESCRIPTION
[0066] The present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the present invention, rather than to limit the present invention. It should also be noted that, for ease of description, only parts related to the present invention, rather than all structures, are shown in the accompanying drawings.
[0067] Embodiment 1
[0068] Figure 1 This is a technical route diagram of the method for tracing the source of water accumulation in a nuclear power plant area according to the first embodiment of the present invention, see Figure 1 , the process of calculating water accumulation in the nuclear power plant area is as follows:
[0069] In the design of nuclear island, the bottom elevation of nuclear island is an important design parameter, which is related to the safe operation of nuclear power plant. At present, the calculation method of return period is adopted in nuclear power design, and various design parameters are too large, and the investment in engineering projects is huge. At present, there is no universal calculation method to determine the design bottom elevation of nuclear island and the height of coastal wave barrier. This embodiment intends to use different numerical models to perform numerical simulation to calculate the distribution of water accumulation in nuclear power plant area and the height of wave climbing along the coast.
[0070] Therefore, after the working conditions are determined, the nuclear island design unit currently has no method to invert the water accumulation in various places in the plant area. This embodiment can invert a tropical cyclone process through numerical simulation calculation, and can calculate the distribution of water accumulation in the entire plant area, providing guidance for engineering design.
[0071] Figure 2 This is a flow chart of the method for tracing the source of water accumulation in a nuclear power plant area according to the first embodiment of the present invention. Figure 2 This embodiment is applicable to the simulation calculation of water accumulation in nuclear power plants. The method can be executed by a nuclear power plant water accumulation simulation calculation source tracing device and can be integrated into a terminal. Specifically, the method includes the following steps:
[0072] Step 101: Establish a tropical cyclone inversion model, and simulate and calculate the rainfall distribution and wind field distribution in the study area according to the tropical cyclone inversion model; wherein the study area includes the factory area.
[0073] Tropical cyclone inversion: Currently, numerical models are commonly used for tropical cyclone inversion, among which WRF is a popular atmospheric numerical model used to simulate atmospheric dynamics and the evolution of weather systems. The WRF model can simulate the generation, development and movement of tropical cyclones, and provides rich simulation output data, such as precipitation, air pressure, temperature, humidity, wind field, etc., which can be used to study and predict the behavior and impact of tropical cyclones.
[0074] Figure 3 This is a schematic diagram of the process of tropical cyclone inversion in the method for tracing the source of water accumulation in a nuclear power plant area according to the first embodiment of the present invention. Figure 3 , the process of WRF simulating tropical cyclones is as follows:
[0075] The mesoscale WRF simulation of tropical cyclone inversion first needs to obtain:
[0076] Meteorological data, obtain the initial atmospheric field data during the occurrence of tropical cyclones, including information such as air pressure, temperature, humidity, wind field, etc. These data usually come from meteorological observation stations, satellite remote sensing data, global or regional meteorological model outputs, etc.
[0077] Topographic data, obtain the terrain elevation data of the simulation area, as well as the surface type data of the ocean and land, which usually come from terrain databases, remote sensing data or other topographic measurement data.
[0078] Boundary conditions: obtain boundary condition data around the simulation area, including sea surface temperature, sea surface pressure, sea surface wind field and other information, which are usually output from global or regional meteorological models. Set simulation parameters: technicians in this field can set the simulation domain range, grid resolution, time step, physical parameters, etc. according to simulation requirements and research purposes.
[0079] The above necessary input data can be used to configure the WRF model and simulate tropical cyclones. In addition, during the simulation process, attention should be paid to the selection of the simulation area, the optimization of the model settings, and the post-processing of the simulation results to ensure the accuracy and reliability of the simulation. Through the mesoscale model WRF, the rainfall distribution and wind field distribution in the study area are finally calculated.
[0080] Step 102: establish an offshore wave calculation model and an ocean current model, and perform nearshore overtopping amount simulation calculation using the offshore wave calculation model and the ocean current model according to the wind field distribution to obtain the overtopping amount.
[0081] Offshore wave prediction: Offshore wave prediction involves the generation, propagation and deformation of ocean waves, and is usually calculated using quasi-static spectrum distribution equations. In engineering calculations, numerical simulation software is usually used for calculations, and commonly used models include MIKE21, SWAN, WAVEWATCH III, etc. They are all third-generation ocean wave numerical prediction models. They can calculate the wave height, wavelength, period, direction and wave energy spectrum of waves, are suitable for complex ocean environments, and are widely used in coastal and nearshore ocean wave simulations around the world.
[0082] Specifically, the offshore wave estimation model in this embodiment uses SWAN, which is based on the third-generation ocean wave numerical model. It can capture the refraction caused by strong currents and water depth, the shallowing and reflection caused by underwater terrain changes, and the propagation process of waves in geometric space. The third-generation ocean wave numerical model uses a two-dimensional action spectral density N to describe the random wave field, and its control equation is:
[0083] ;
[0084] The first term represents the time-varying N The second and third terms represent the rate of N In space x and y The fourth term represents the propagation caused by the flow field and water depth. N The change in space, that is, the change in the frequency of fluctuation; the fifth term represents N The propagation in space is the wave refraction caused by water depth and flow field. S tot Represents the sum of source and sink terms describing various physical processes.
[0085] In actual application, simulation of offshore wind-generated waves requires: Topographic data: describes the terrain elevation data of the simulation area, including information such as the ocean bottom and land topography, which affects the propagation and deformation of waves. Wind field data: includes wind speed and direction data, usually provided in the form of a time series of ASSCILL files, which can be output by the WRF model. Others: Seafloor roughness, water temperature, seawater salinity, etc.
[0086] Therefore, those skilled in the art can also provide boundary conditions for the nearshore overtopping model by extrapolating offshore wave elements according to actual needs.
[0087] Ocean current model, two-dimensional plant model: two-dimensional flow field model, widely used at home and abroad, open source and commercial software have a certain scale of application. Open source software includes FVCOM, TELEMAC2D, etc., commercial software includes MIKE, INFOWORKS, etc. These software use average depth in the vertical direction to solve the two-dimensional form of Navier-Stokes equations, combined with shallow water equations and momentum conservation equations to simulate the flow of water.
[0088] In actual application, a two-dimensional flow model can be used to simulate the phenomenon of rising nearshore water levels under extreme weather conditions. First, a large sea area (including tropical cyclone range) is used as the calculation domain, and then the global scale tidal harmonization parameters are used to generate tidal boundary conditions, and the wind field and rainfall distribution output by WRF are coupled to calculate the coastal water level increase process under extreme conditions. The data required by the ocean current model is basically the same as the offshore wave calculation model.
[0089] Nearshore overtopping: Overtopping is not only closely related to wave elements, but also related to coastal engineering structures. There are empirical formulas and overtopping calculation formulas for calculating the overtopping amount. In terms of numerical models, although CFD models can be used for calculation, the amount of calculation is large and it is difficult to use in practice. SWASH is an open source numerical model from Delft University, which is used to simulate the wave dynamics process in coastal and nearshore areas. It is a time-domain wave numerical model based on the finite element method, which accurately describes the strong dispersion and strong nonlinearity of waves and has a fast calculation speed. The SWASH model can simulate the dynamic evolution of waves during propagation, including wave climbing, overtopping and other phenomena.
[0090] In actual application, the calculation of nearshore overtopping can refer to the following steps: After the SWAN model is calculated, the nearshore boundary conditions can be extracted as the SWASH boundary conditions, and the water depth calculated by the wind field and ocean current model can be coupled to estimate the overtopping of the breakwater. The control equations of SWASH include the shallow water equation, the vertical momentum equation, and the horizontal momentum equation, to which additional non-hydrostatic terms are added. It mainly describes the interaction between the acceleration, inertia, pressure, friction and other external forces of the water body. The control equations of SWASH are all existing technologies, so they will not be repeated here.
[0091] Step 103: establishing a one-dimensional rainfall-runoff model based on the digital elevation model of the study area, and performing runoff simulation calculation using the one-dimensional rainfall-runoff model according to the rainfall distribution to obtain the small watershed runoff.
[0092] Specifically, the one-dimensional rainfall-runoff model is established based on the digital elevation model at the study area, and the runoff simulation calculation is performed using the one-dimensional rainfall-runoff model according to the rainfall distribution to obtain the small watershed runoff, including:
[0093] Step 1031: obtain a digital elevation model of the study area, and divide the small watershed where the study area is located according to the digital elevation model.
[0094] In the actual application process, the following steps can be referred to: Based on the digital elevation model DEM, through hydrological analysis, divide the small watershed where the project is located:
[0095] Fill the depressions of the digital elevation model DEM to ensure that the water in each pixel has a flow direction.
[0096] Flow direction analysis calculates the direction of water flow in each pixel.
[0097] Traffic statistics: count the total amount of traffic flowing through each pixel.
[0098] Determine the minimum runoff volume and extract pixels with a value greater than the threshold as part of the river network.
[0099] The river network is graded and connected.
[0100] Watershed extraction: extract watersheds according to the classified river network.
[0101] Step 1032: based on the location of the plant in the study area, extract the small watershed where the streamline enters the plant, and divide the small watershed where the streamline enters the plant into a plurality of sub-catchments; wherein the flow of rainfall runoff entering the study area passes through different sub-catchments to form a flow time process for inputting a two-dimensional model of the plant.
[0102] In actual application, it is necessary to extract the watershed that needs to be considered according to the location of the nuclear power plant project. Then divide the sub-catchment area. The following is the method of dividing the sub-catchment area:
[0103] Optional, traditional method:
[0104] Based on the results of river network classification, each node of the river network is regarded as the node where the sub-catchment converges. Through smaller runoff, more refined small watersheds are determined as sub-catchments. The characteristic width of each sub-catchment is calculated using a regular quadrilateral, and the slope is calculated using the average slope of the study area.
[0105] Optionally, based on the pixel-by-pixel tracking of the d8 flow direction, object-oriented programming is used: streamline tracing, starting from any corner position around the pixel matrix, and performing streamline statistics pixel by pixel according to the flow direction grid, ending when encountering the river node mentioned in method 1 or other divided streamlines, this section of streamline is placed in the map container, and the flow direction value at the streamline position in the d8 flow direction pixel is modified to 0 (as the end mark). At the initial starting position, find the secondary starting position according to the combination of directions from left to right and from top to bottom, and find the river node or the allocated streamline again until the end position is found to complete the streamline allocation. Merge streamlines, using the river nodes as breakpoints to merge scattered streamlines. Construct a streamline object, construct a streamline object, and use the inflow and outflow nodes, the length of the line segment, and the collection of all inflow streamlines as its attributes, and recursively obtain the length and slope of the streamline as its method. Construct a multi-branch tree, based on the streamline object, with the inflow and outflow nodes as the confluence relationship, to construct a multi-branch tree.
[0106] Among them, the flow of rainfall runoff entering the study area passes through different inflow paths, forming a flow time process, which is used to input into the two-dimensional model of the plant area.
[0107] Step 1033: taking all boundaries of the study area as end nodes of streamline tracing to construct a one-dimensional rainfall-runoff model; wherein the end nodes serve as point sources of the two-dimensional model of the plant area.
[0108] Since the surface water in the plant area can be considered using the plant area two-dimensional model, the plant area water supply is set in the plant area two-dimensional model as follows:
[0109] The runoff (watershed) can be calculated by constructing a one-dimensional rainfall-runoff model by taking all boundaries of the study area as the end nodes of the streamline tracing. All end nodes can be used as point sources of the two-dimensional model of the plant area. The runoff from the one-dimensional rainfall-runoff model can be input into the two-dimensional model of the plant area in the form of a time curve.
[0110] After SWASH calculates the overtopping, it counts the overtopping amounts on different coasts to form a time series file, sets different coasts as different boundaries in the plant area two-dimensional model, and uses this as the boundary condition to input the overtopping amount into the plant area two-dimensional model.
[0111] Precipitation: Precipitation can be directly considered by using the rainfall module of the plant 2D model. The rainfall process uses the time series of the site rainfall process output by WRF. Since the consideration is the water accumulation in the nuclear power plant under extreme weather conditions, infiltration and evaporation in the plant are not considered.
[0112] Step 1034: According to the rainfall distribution, use the one-dimensional rainfall-runoff model to perform runoff simulation calculation to obtain the small watershed runoff.
[0113] Specifically, rainfall runoff calculation: The rainfall runoff process in a large area around the plant is usually calculated using a one-dimensional rainfall runoff model. The rainfall type can be calculated using the Chicago rainfall type method, and the study area is divided into several sub-catchments. The runoff coefficient, infiltration process, characteristic width, characteristic slope, and filling volume of each sub-catchment are considered as a coefficient, and each sub-catchment calculates rainfall runoff, infiltration, and other processes separately. The one-dimensional rainfall runoff model can quickly consider the rainfall runoff process and the calculation speed is fast.
[0114] In addition, each grid in the two-dimensional model of the plant is a single unit, and the runoff process is calculated one by one in each unit; when calculating runoff at the basin level, the spatial difference interval is generally large to reduce the amount of calculation, especially in areas with large terrain changes. The sub-catchment area division of the one-dimensional rainfall-runoff model is usually based on the digital elevation model DEM. By calibrating the model, more accurate rainfall-runoff results can usually be obtained. For areas with large human influence factors, DEM cannot reflect the elevation characteristics well. The manually corrected DTM can generalize the project area well, and based on the corrected elevation data, the parameters required by the model can be accurately calculated.
[0115] Step 104: Based on the underground drainage system of the factory area, a two-dimensional model of the factory area and a one-dimensional pipe network model are established.
[0116] The plant area 2D model can be constructed based on the nuclear power plant area to simulate the nuclear power plant area. Since the water supply to the nuclear power plant area mainly comes from: direct rainfall in the plant area, runoff generated by rainfall in nearby areas, and seawater overtopping; the drainage of the engineering area is mainly through the surface runoff of the plant area (which will be considered in the plant area 2D model itself) and pipe network drainage. In addition, other measures such as pumping and drainage devices can be directly considered by setting point sources in the plant area 2D model.
[0117] For example, after the seawater overflows the waves, a seawater collection tank is set at the rear side, and a pumping device is provided. A point source can be set in the two-dimensional model of the plant area to consider, and the water depth at the collection tank is queried through a subroutine, and the water volume is calculated, and the pumping and drainage volume of the two-dimensional model of the plant area is dynamically controlled through the pumping and drainage capacity.
[0118] One-dimensional pipe network model of the plant: There are many pipe network models at present, such as SWMM, EPANET, MIKE URBAN, etc. Most of them are energy equations and momentum equations that consider the head loss along the water and the local head loss. In the calculation of the pipe network model, it is mainly necessary to consider the spatial topological relationship, roughness and depth of the pipe network. Both the rainfall runoff model and the overtopping model can be calculated in advance and then input into the two-dimensional model of the plant as a time series process. The pipe network model needs to interact with the two-dimensional model of the plant to determine the process of accumulated water flowing into the pipe network and the process of water gushing out of the pipe network, so as to consider the drainage of the accumulated water area and the backflow process of the local manhole.
[0119] In actual application, rainfall can be directly considered by using the rainfall module of the plant 2D model. The rainfall process uses the time series of the site rainfall process output by WRF. Since the consideration is the water accumulation in the nuclear power plant under extreme weather conditions, infiltration and evaporation in the plant are not considered.
[0120] Specifically, due to the complex underground drainage system in the factory area, the water flow in the pipe network is relatively simple compared to the flow in the ocean and rivers, and can be generalized as along-the-way and local energy losses. In practical applications, it is therefore considered through a one-dimensional pipe network model.
[0121] The establishment of a one-dimensional pipe network model requires: the spatial topological relationship of the pipe network. The diameter, roughness and other parameters of the pipe network. The location of the manhole and rainwater outlet, the elevation of the bottom of the well and the well diameter. The outflow node of the pipe network and the ocean water level of the water flow node. The one-dimensional pipe network model can use the finite difference method to solve the equation of a section of the pipe in the form of a differential formula. The pipe flow rate, pipe area and pipe roughness are all averaged along the way.
[0122] Specifically, the two-dimensional model of the plant area and the one-dimensional pipe network model are established based on the underground drainage system of the plant area, and the steps include:
[0123] Step 1041, obtaining the spatial topological relationship of the pipe network in the underground drainage system of the factory area, the parameters of the pipe network, the location of the wells in the pipe network, the bottom elevation of the wells, the diameter of the wells, the outflow nodes of the pipe network, and the ocean water level of the outflow nodes.
[0124] Step 1042: Establish a two-dimensional model of the plant area, and use the wells in the pipe network as point sources in the two-dimensional model of the plant area.
[0125] Step 1043: Establish a one-dimensional pipe network model according to the spatial topological relationship of the pipe network, the parameters of the pipe network, the location of the wells in the pipe network, the bottom elevation of the wells, the diameter of the wells, the outflow nodes of the pipe network, and the ocean water level of the outflow nodes.
[0126] Step 105, obtaining the rainfall time series of the rainfall process in the plant area output by the tropical cyclone inversion model, using the rainfall time series as the model parameters of the two-dimensional model of the plant area, and using the overtopping amount and the small watershed runoff as the boundary conditions of the two-dimensional model of the plant area.
[0127] Figure 4 This is a schematic diagram of the simulation process of the two-dimensional model of the plant area in the method for tracing the source of water accumulation simulation calculation in the nuclear power plant area according to the first embodiment of the present invention, see Figure 4 .
[0128] The water inflow to the nuclear power plant area mainly includes: direct rainfall in the plant area, runoff generated by rainfall in nearby areas, and seawater overtopping. Therefore, a one-dimensional rainfall-runoff model can be constructed by taking all the boundaries of the study area as the end nodes of the streamline tracing. All the end nodes can be used as point sources of the two-dimensional model of the plant area. The runoff collected by the one-dimensional rainfall-runoff model is input into the two-dimensional model of the plant area in the form of a time curve. After SWASH calculates the overtopping, the overtopping amount on different coasts is counted to form a time series file, and different coasts are set as different boundaries in the two-dimensional model of the plant area, and the overtopping amount is input into the two-dimensional model of the plant area as a boundary condition.
[0129] In addition, rainfall can be directly considered by using the rainfall module of the plant 2D model. The rainfall process uses the site rainfall process time series output by WRF. Since the consideration is the water accumulation in the nuclear power plant under extreme weather conditions, the infiltration and evaporation in the plant are not considered.
[0130] Step 106: Use the two-dimensional plant model to access the flow of the pipes in the one-dimensional pipe network model, use the flow difference between adjacent pipes in the one-dimensional pipe network model as the flow process of the point source in the two-dimensional plant model, so as to realize the drainage calculation of the two-dimensional plant model; and use the two-dimensional plant model to transfer the head information at the point source to the one-dimensional pipe network model, so as to realize the drainage calculation of the one-dimensional pipe network model.
[0131] Figure 5 This is a schematic diagram of the interaction between the one-dimensional pipe network model and the two-dimensional plant model in the nuclear power plant area water accumulation simulation calculation and source tracing method described in Example 1 of the present invention. Figure 5 .
[0132] Since the water in the plant enters the pipes through the rainwater inlets and manholes, the model area is drained through the outlets of the pipes. Therefore, in order to realize the interaction between the one-dimensional pipe network model and the two-dimensional model of the plant, the one-dimensional pipe network model needs to know the water head of each inspection well and manhole, and transmit the water head information to the one-dimensional pipe network model through the two-dimensional model of the plant to realize the drainage calculation of the one-dimensional pipe network model; while the two-dimensional model of the plant can access the flow of each section of the pipeline and use the flow difference of adjacent pipelines as the flow process of the point source of the two-dimensional model of the plant to realize the drainage calculation of the two-dimensional model of the plant.
[0133] It should be noted that since the one-dimensional pipe network model itself is a dynamic wave model, it can simulate the backflow of water and transmit it to the two-dimensional model of the plant through a point source to realize the overflow calculation within the two-dimensional model of the plant.
[0134] In addition, unlike rainfall runoff and overtopping calculations, the one-dimensional pipe network model needs to interact with the two-dimensional plant model and the ocean water level. In the open source numerical calculation software, it is necessary to obtain the water level process of the specified node in real time, which can be obtained by accessing the water level matrix of the node.
[0135] Specifically, the method uses the two-dimensional plant model to access the flow of the pipeline in the one-dimensional pipe network model, uses the flow difference between adjacent pipelines in the one-dimensional pipe network model as the flow process of the point source in the two-dimensional plant model, so as to realize the drainage calculation of the two-dimensional plant model; and uses the two-dimensional plant model to transfer the head information at the point source to the one-dimensional pipe network model, so as to realize the drainage calculation of the one-dimensional pipe network model, which specifically includes the following steps:
[0136] Step 1061: Obtain the flow difference between adjacent pipes before and after the point source in the one-dimensional pipe network model to obtain the overflow flow of the point source. , the formula is as follows:
[0137] ;
[0138] in, is the flow rate input into the pipeline in the previous section, is the flow rate of the next pipe section.
[0139] Step 1062: Use the two-dimensional plant model to access the overflow flow of the point source in the one-dimensional pipe network model. , using the overflow flow of the point source in the one-dimensional pipe network model As the flow process of the point source in the two-dimensional model of the plant area, the drainage calculation of the two-dimensional model of the plant area is realized to obtain the head information at the point source , the calculation formula is as follows:
[0140] ;
[0141] in, is the flow rate input into the pipeline in the previous section, is the flow rate of the next section of the pipeline, is the pressure head of the point source at the end of the previous section of the pipeline, is the pressure head of the point source at the end of the next section of the pipeline, is the well water depth of the point source at the end of the pipeline in the previous section, is the well water depth of the point source at the end of the next section of the pipeline, is the average length of the pipeline, is the average water-passing short-section area of the pipeline, is the time step, is the acceleration due to gravity.
[0142] In actual application, is the well water depth at the point source at the end of the left pipeline, is the well water depth of the point source at the end of the pipeline on the right, and the flow rate input from the well point source on the left to the two-dimensional model of the plant area is the overflow flow rate , since the one-dimensional pipe network model is a dynamic wave equation, the overflow flow This value can be positive or negative.
[0143] Step 1063: Use the two-dimensional plant model to transfer the water head information at the point source to the one-dimensional pipe network model. , to realize the drainage calculation of the one-dimensional pipe network model, the calculation formula is as follows:
[0144] ;
[0145] in, is the pressure head of the point source at the end of the previous pipe in the one-dimensional pipe network model, is the pressure head of the point source at the end of the last pipe section in the one-dimensional pipe network model, is the average length of the pipeline, is the average water-passing short-section area of the pipeline, is the time step, is the acceleration due to gravity.
[0146] Since the one-dimensional pipe network model calculates the flow change in the pipeline, three aspects are considered: 1. inertia term, 2. pressure term, and 3. friction term. This embodiment mainly considers the pressure term, among which, is the pressure head of the point source at the end of the previous pipe in the one-dimensional pipe network model, is the pressure head of the point source at the end of the last section of the pipeline in the one-dimensional pipe network model. In the interactive process of the one-dimensional pipe network model and the two-dimensional plant model, it is necessary to convert the first t Pressure head per time step Add to the manhole pressure head On the other hand, we can add up the values without changing the source code, that is, .
[0147] Correspondingly, the pressure head of the point source at the end of the previous pipe in the one-dimensional pipe network model is , which is actually equal to the pressure head in the original one-dimensional pipe network model Plus the 2D model of the plant t The pressure head transmitted to the one-dimensional pipe network model Similarly, the pressure head of the point source at the end of the next section of the pipeline is , which is actually equal to the pressure head in the original one-dimensional pipe network model Plus the 2D model of the plant t The pressure head transmitted to the one-dimensional pipe network model .
[0148] In the actual application process, the two-dimensional model of the plant area is used to access the flow of the pipeline in the one-dimensional pipe network model, and the flow difference between adjacent pipelines in the one-dimensional pipe network model is used as the flow process of the point source in the two-dimensional model of the plant area to realize the drainage calculation of the two-dimensional model of the plant area; and the two-dimensional model of the plant area is used to transfer the head information at the point source to the one-dimensional pipe network model to realize the drainage calculation of the one-dimensional pipe network model, and the following steps are also included:
[0149] Step 1064: Use shared memory to store the overflow flow of the point source in the one-dimensional pipe network model , and the water head information at the point source in the two-dimensional model of the plant area ; When the two-dimensional plant model reads the overflow flow of the point source in the one-dimensional pipe network model stored in the shared memory After that, clear the shared memory and write the water head information at the next point source ; When the one-dimensional pipe network model reads the water head information at the point source in the two-dimensional model of the plant area stored in the shared memory After that, clear the shared content and write the overflow flow of the next point source .
[0150] Figure 6 This is a flow chart of the interaction between the one-dimensional pipe network model and the two-dimensional plant model using shared memory in the method for tracing the source of water accumulation in a nuclear power plant area according to the first embodiment of the present invention. Figure 6 , the specific interaction methods are as follows:
[0151] The one-dimensional pipe network model and the two-dimensional plant model can interact through shared memory. The essence of shared memory is to read and write information in the same memory through different programs, and the time steps of the two models need to be consistent. Point sources need to be set in the two-dimensional plant model to provide an interface for the flow inflow and outflow of the one-dimensional pipe network model.
[0152] For details, see Figure 5 and Figure 6 , the flow rate from the left manhole into the two-dimensional model of the plant area is calculated as follows:
[0153] Step 1: Clear the shared memory of the plant 2D model and write the water depth at the point source ;
[0154] Step 2: The one-dimensional pipe network model reads water depth information from shared memory ;
[0155] Step 3: Clear the shared one-dimensional pipe network model and write the manhole overflow flow ;
[0156] Step 4: The plant 2D model reads the manhole overflow flow from the shared memory ;
[0157] Repeat steps 1 to 4 above to realize the interaction between the one-dimensional pipe network model and the two-dimensional plant model.
[0158] Step 107: After calibrating each water source in the two-dimensional model of the plant area using different tracers, calculate the proportion of each tracer in the waterlogged area in the two-dimensional model of the plant area to achieve source tracing of the waterlogging.
[0159] Figure 7 This is a schematic diagram of the structure of the study area in the method for tracing the source of water accumulation in a nuclear power plant area according to the first embodiment of the present invention. Figure 7 . The left side of the project area is mainly small basin runoff. After dividing the one-dimensional sub-catchment area, the small basin runoff flows to the next catchment area until it flows into the catchment area near the nuclear power plant area, and then flows into the plant area two-dimensional model through boundaries 1-7. The right side is the sea side. In order to finely illustrate the direction of the water inflow, the sea side boundary can be refined and divided into multiple boundary conditions such as S1, S2, E1, E2, N1, and N2. The overtopping amount solved by the non-static pressure model is merged into the plant area two-dimensional model through the boundary. The nuclear power plant area has inspection wells and pipe networks (simplified in the figure). Part of the plant area drainage is discharged from the project area through the pipe network. When the pipe network is full, some inspection wells may overflow and flow into the plant area two-dimensional model. In addition, rainfall is directly input through the plant area two-dimensional model parameter file.
[0160] Figure 8 This is a schematic diagram of the structure when there is a waterlogging area in the study area in the method for tracing the source of waterlogging in a nuclear power plant area according to the first embodiment of the present invention. Figure 8 .
[0161] Specifically, after calibrating each water source in the two-dimensional model of the plant area using different tracers, the proportion of each tracer in the waterlogged area in the two-dimensional model of the plant area is calculated to achieve tracing the source of the waterlogged area, which specifically includes the following steps:
[0162] Step 1071, using different tracers to calibrate the water sources in the two-dimensional model of the plant area; wherein the water sources of the two-dimensional model of the plant area include rainfall water, runoff water, over-wave water, and pipe network drainage, runoff water and over-wave water are given by boundary conditions, and the open boundary is divided into The number of wells in the network from which the network drains water Given, different tracers are set for runoff water, overtopping water, and pipe network drainage. ;
[0163] Step 1072: When a waterlogging area appears in the two-dimensional model of the plant area, the concentration of each tracer is , then the proportion of each water source in the waterlogged area is , , the proportion of rainfall water is , the formula is as follows:
[0164] ,
[0165] .
[0166] Since the total is 1, the proportion of each water source in the flooded area is subtracted from 1. , we can get the proportion of rainfall water as .
[0167] In actual application, different tracers are set, and the distribution of water sources in each area is calculated by calculating the proportion of tracers in each direction. If the water source of the project to be protected (nuclear island) mainly comes from a certain boundary, the main water flow direction can be intercepted in a targeted manner.
[0168] The present embodiment describes a method for tracing the source of water accumulation simulation calculation in a nuclear power plant area, which is implemented by establishing a tropical cyclone inversion model, and simulating and calculating the rainfall distribution and wind field distribution in the study area based on the tropical cyclone inversion model; wherein the study area includes the plant area; establishing an offshore wave calculation model and an ocean current model, and according to the wind field distribution, using the offshore wave calculation model and the ocean current model to simulate and calculate the nearshore overtopping amount to obtain the overtopping amount; establishing a one-dimensional rainfall-runoff model based on the digital elevation model at the study area, and according to the rainfall distribution, using the one-dimensional rainfall-runoff model to simulate and calculate the runoff to obtain the small watershed runoff; establishing a two-dimensional plant area model and a one-dimensional pipe network model based on the underground drainage system of the plant area; and obtaining the rainfall process of the plant area output by the tropical cyclone inversion model. The rainfall time series is used as the model parameter of the two-dimensional model of the plant area, and the overtopping amount and the small watershed runoff are used as the boundary conditions of the two-dimensional model of the plant area; the flow of the pipeline in the one-dimensional pipe network model is accessed by the two-dimensional model of the plant area, and the flow difference between adjacent pipelines in the one-dimensional pipe network model is used as the flow process of the point source in the two-dimensional model of the plant area to realize the drainage calculation of the two-dimensional model of the plant area; and the head information at the point source is transmitted to the one-dimensional pipe network model by the two-dimensional model of the plant area to realize the drainage calculation of the one-dimensional pipe network model; after calibrating each water source in the two-dimensional model of the plant area by different tracers, the proportion of each tracer in the waterlogged area in the two-dimensional model of the plant area is calculated to realize the tracing of the waterlogging.
[0169] Compared with the existing technology, the method solves the problems of difficulty in numerical simulation calculation of water accumulation distribution in nuclear power plant areas and wave height along the coast in existing nuclear power design. It can realize the simulation of water accumulation in nuclear power plant areas during nuclear power design, and can also trace the source of water accumulation, so as to facilitate timely interception design in nuclear power design.
[0170] Embodiment 2
[0171] Fig. 9 A schematic diagram of the structure of a nuclear power plant area water accumulation simulation calculation and tracing device provided in Example 2 of the present invention. Fig. 9 A block diagram of an exemplary apparatus suitable for implementing embodiments of the present invention is shown. Fig. 9 The device shown is only an example and should not limit the functions and scope of use of the embodiments of the present invention. Fig. 9 As shown, including:
[0172] The inversion module 201 is used to establish a tropical cyclone inversion model, and simulate and calculate the rainfall distribution and wind field distribution in the study area according to the tropical cyclone inversion model; wherein the study area includes the factory area.
[0173] The calculation module 202 is used to establish an offshore wave calculation model and an ocean current model, and perform nearshore overtopping amount simulation calculation using the offshore wave calculation model and the ocean current model according to the wind field distribution to obtain the overtopping amount.
[0174] The rainfall module 203 is used to establish a one-dimensional rainfall-runoff model based on the digital elevation model at the study area, and to perform runoff simulation calculation using the one-dimensional rainfall-runoff model according to the rainfall distribution to obtain the runoff of the small watershed.
[0175] The building module 204 is used to build a two-dimensional model of the plant area and a one-dimensional pipe network model based on the underground drainage system of the plant area.
[0176] The acquisition module 205 is used to obtain the rainfall time series of the factory area rainfall process output by the tropical cyclone inversion model, use the rainfall time series as the model parameter of the factory area two-dimensional model, and use the overtopping amount and the small watershed runoff as the boundary conditions of the factory area two-dimensional model.
[0177] The calculation module 206 is used to use the two-dimensional plant model to access the flow of the pipes in the one-dimensional pipe network model, use the flow difference between adjacent pipes in the one-dimensional pipe network model as the flow process of the point source in the two-dimensional plant model, so as to realize the drainage calculation of the two-dimensional plant model; and use the two-dimensional plant model to transmit the head information at the point source to the one-dimensional pipe network model to realize the drainage calculation of the one-dimensional pipe network model.
[0178] The source tracing module 207 is used to calibrate each water source in the two-dimensional model of the plant area using different tracers, and then calculate the proportion of each tracer in the waterlogged area in the two-dimensional model of the plant area to achieve source tracing of the waterlogged area.
[0179] The nuclear power plant area water accumulation simulation calculation and tracing device provided in the embodiment of the present invention can execute the nuclear power plant area water accumulation simulation calculation and tracing method provided in any embodiment of the present invention, and has the corresponding functional modules and beneficial effects of the execution method.
[0180] Embodiment 3
[0181] Fig.10 A schematic diagram of the structure of a nuclear power plant water accumulation simulation calculation and tracing terminal provided in the third embodiment of the present invention; Fig.10 A block diagram of an exemplary terminal suitable for implementing embodiments of the present invention is shown. Fig.10 The terminal shown is only an example and should not bring any limitation to the functions and scope of use of the embodiments of the present invention.
[0182] like Fig.10 As shown, the terminal 12 is in the form of a general-purpose computing device. The components of the terminal 12 may include, but are not limited to: one or more processors or processing units 16, a system memory 28, and a bus 18 connecting different system components (including the system memory 28 and the processing unit 16).
[0183] Bus 18 represents one or more of several types of bus structures, including a memory bus or memory controller, a peripheral bus, an accelerated graphics port, a processor or a local bus using any of a variety of bus architectures. By way of example, these architectures include, but are not limited to, an Industry Standard Architecture (ISA) bus, a Micro Channel Architecture (MAC) bus, an Enhanced ISA bus, a Video Electronics Standards Association (VESA) local bus, and a Peripheral Component Interconnect (PCI) bus.
[0184] Terminal 12 typically includes a variety of computer system readable media. These media can be any available media that can be accessed by terminal 12, including volatile and non-volatile media, removable and non-removable media.
[0185] System memory 28 may include computer system readable media in the form of volatile memory, such as random access memory (RAM) 30 and / or cache memory 32. Terminal 12 may further include other removable / non-removable, volatile / non-volatile computer system storage media. By way of example only, storage system 34 may be used to read and write non-removable, non-volatile magnetic media ( Fig.10 not shown, usually called a "hard drive"). Although Fig.10Not shown in the figure, a disk drive for reading and writing to a removable non-volatile disk (e.g., a "floppy disk"), and an optical disk drive for reading and writing to a removable non-volatile optical disk (e.g., a CD-ROM, a DVD-ROM, or other optical media) may be provided. In these cases, each drive may be connected to the bus 18 via one or more data medium interfaces. The memory 28 may include at least one program product having a set (e.g., at least one) of program modules that are configured to perform the functions of the various embodiments of the present invention.
[0186] A program / utility 40 having a set (at least one) of program modules 42 may be stored, for example, in the memory 28, such program modules 42 including but not limited to an operating system, one or more application programs, other program modules, and program data, each of which or some combination may include an implementation of a network environment. The program modules 42 generally perform the functions and / or methods of the embodiments described herein.
[0187] The terminal 12 may also communicate with one or more external devices 14 (e.g., keyboards, pointing devices, displays 24, etc.), may communicate with one or more devices that enable a user to interact with the terminal 12, and / or may communicate with any device that enables the terminal 12 to communicate with one or more other computing devices (e.g., network cards, modems, etc.). Such communication may be performed via an input / output (I / O) interface 22. Furthermore, the terminal 12 may also communicate with one or more networks (e.g., local area networks (LANs), wide area networks (WANs), and / or public networks, such as the Internet) via a network adapter 20. As shown, the network adapter 20 communicates with other modules of the terminal 12 via a bus 18. It should be understood that, although not shown in the figure, other hardware and / or software modules may be used in conjunction with the terminal 12, including but not limited to: microcode, device drivers, redundant processing units, external disk drive arrays, RAID systems, tape drives, and data backup storage systems.
[0188] The processing unit 16 executes various functional applications and data processing by running programs stored in the system memory 28, such as implementing the nuclear power plant area water accumulation simulation calculation and tracing method provided in an embodiment of the present invention.
[0189] Embodiment 4
[0190] Embodiment 4 of the present invention further provides a storage medium comprising computer executable instructions, which, when executed by a computer processor, are used to execute any of the nuclear power plant water accumulation simulation calculation and tracing methods provided in the above embodiments.
[0191] The computer storage medium of the embodiment of the present invention may adopt any combination of one or more computer-readable media. The computer-readable medium may be a computer-readable signal medium or a computer-readable storage medium. The computer-readable storage medium may be, for example, but not limited to, an electrical, magnetic, optical, electromagnetic, infrared, or semiconductor system, device or device, or any combination thereof. More specific examples (non-exhaustive list) of computer-readable storage media include: an electrical connection with one or more wires, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination thereof. In this document, a computer-readable storage medium may be any tangible medium containing or storing a program, which may be used by or in combination with an instruction execution system, device or device.
[0192] Computer-readable signal media may include data signals propagated in baseband or as part of a carrier wave, which carry computer-readable program code. Such propagated data signals may take a variety of forms, including but not limited to electromagnetic signals, optical signals, or any suitable combination of the above. Computer-readable signal media may also be any computer-readable medium other than a computer-readable storage medium, which may send, propagate, or transmit a program for use by or in conjunction with an instruction execution system, apparatus, or device.
[0193] Program code embodied on a computer readable medium may be transmitted using any appropriate medium, including but not limited to wireless, wireline, optical fiber cable, RF, etc., or any suitable combination of the foregoing.
[0194] Computer program code for performing the operations of the present invention may be written in one or more programming languages or a combination thereof, including object-oriented programming languages such as Java, Smalltalk, C++, and conventional procedural programming languages such as "C" or similar programming languages. The program code may be executed entirely on the user's computer, partially on the user's computer, as a separate software package, partially on the user's computer and partially on a remote computer, or entirely on a remote computer or server. In the case of a remote computer, the remote computer may be connected to the user's computer through any type of network, including a local area network (LAN) or a wide area network (WAN), or may be connected to an external computer (e.g., through the Internet using an Internet service provider).
[0195] Note that the above are only preferred embodiments of the present invention and the technical principles used. Those skilled in the art will understand that the present invention is not limited to the specific embodiments described herein, and that various obvious changes, readjustments and substitutions can be made by those skilled in the art without departing from the scope of protection of the present invention. Therefore, although the present invention has been described in more detail through the above embodiments, the present invention is not limited to the above embodiments, and may include more other equivalent embodiments without departing from the concept of the present invention, and the scope of the present invention is determined by the scope of the appended claims.
Claims
1. A method for tracing the source of water accumulation in a nuclear power plant area through simulation calculation, characterized in that: include: Establishing a tropical cyclone inversion model, and simulating and calculating the rainfall distribution and wind field distribution in the study area according to the tropical cyclone inversion model; wherein the study area includes the factory area; An offshore wave calculation model and an ocean current model are established, and according to the wind field distribution, the offshore wave calculation model, the ocean current model, and the SWASH model are used to simulate and calculate the nearshore overtopping amount to obtain the overtopping amount; wherein the ocean current model is a two-dimensional flow field model, which simulates the flow of water and calculates the water depth by combining the shallow water equation and the momentum conservation equation; the offshore wave calculation model is used to simulate and calculate nearshore waves, and after calculation using the offshore wave calculation model, the overtopping amount is calculated by extracting the nearshore boundary conditions as the boundary conditions of the SWASH model, coupling the wind field distribution and the water depth calculated by the ocean current model; A one-dimensional rainfall-runoff model is established based on the digital elevation model of the study area, and according to the rainfall distribution, the one-dimensional rainfall-runoff model is used to simulate and calculate the runoff volume to obtain the runoff volume of the small watershed; the one-dimensional rainfall-runoff model is established based on the digital elevation model of the study area, and according to the rainfall distribution, the one-dimensional rainfall-runoff model is used to simulate and calculate the runoff volume to obtain the runoff volume of the small watershed, including: obtaining the digital elevation model of the study area, and dividing the small watershed of the study area according to the digital elevation model; according to the location of the plant in the study area The location in the study area is extracted, and the small watershed where the streamline enters the plant area is extracted, and the small watershed where the streamline enters the plant area is divided into multiple sub-catchments; wherein the flow of rainfall runoff entering the study area passes through different sub-catchments to form a flow time process for inputting the two-dimensional model of the plant area; all boundaries of the study area are used as the end nodes of the streamline tracing to construct a one-dimensional rainfall runoff model; wherein the end node is used as the point source of the two-dimensional model of the plant area; according to the rainfall distribution, the one-dimensional rainfall runoff model is used to perform runoff simulation calculation to obtain the runoff of the small watershed; Based on the underground drainage system of the plant, a two-dimensional model of the plant and a one-dimensional pipe network model are established; Obtaining a rainfall time series of a rainfall process in a plant area output by the tropical cyclone inversion model, using the rainfall time series as a model parameter of the two-dimensional model of the plant area, and using the overtopping amount and the small watershed runoff as boundary conditions of the two-dimensional model of the plant area; The flow of the pipeline in the one-dimensional pipe network model is accessed by using the two-dimensional plant model, and the flow difference between adjacent pipelines in the one-dimensional pipe network model is used as the flow process of the point source in the two-dimensional plant model to realize the drainage calculation of the two-dimensional plant model; and the water head information at the point source is transmitted to the one-dimensional pipe network model by using the two-dimensional plant model to realize the drainage calculation of the one-dimensional pipe network model; After calibrating each water source in the two-dimensional model of the plant area using different tracers, the proportion of each tracer in the waterlogged area in the two-dimensional model of the plant area is calculated to trace the source of the waterlogged area.
2. The method according to claim 1, characterized in that The two-dimensional model of the plant area and the one-dimensional pipe network model are established based on the underground drainage system of the plant area, including: Obtain the spatial topological relationship of the pipe network in the underground drainage system of the plant, the parameters of the pipe network, the location of the wells in the pipe network, the bottom elevation of the wells, the diameter of the wells, the outflow nodes of the pipe network, and the ocean water level of the outflow nodes; Establish a two-dimensional model of the plant area, and use the wells in the pipe network as point sources in the two-dimensional model of the plant area; A one-dimensional pipe network model is established according to the spatial topological relationship of the pipe network, the parameters of the pipe network, the location of the wells in the pipe network, the bottom elevation of the wells, the diameter of the wells, the outflow nodes of the pipe network, and the ocean water level of the outflow nodes.
3. The method according to claim 1, characterized in that: The method of using the two-dimensional plant model to access the flow of the pipeline in the one-dimensional pipe network model, using the flow difference between adjacent pipelines in the one-dimensional pipe network model as the flow process of the point source in the two-dimensional plant model to realize the drainage calculation of the two-dimensional plant model; and using the two-dimensional plant model to transfer the head information at the point source to the one-dimensional pipe network model to realize the drainage calculation of the one-dimensional pipe network model, includes: Obtain the flow difference between adjacent pipes before and after the point source in the one-dimensional pipe network model to obtain the overflow flow of the point source , the formula is as follows: ; in, is the flow rate input into the pipeline in the previous section, is the flow rate of the next section of the pipeline; The overflow flow of the point source in the one-dimensional pipe network model is accessed by using the two-dimensional model of the plant area , using the overflow flow of the point source in the one-dimensional pipe network model As the flow process of the point source in the two-dimensional model of the plant area, the drainage calculation of the two-dimensional model of the plant area is realized to obtain the head information at the point source , the calculation formula is as follows: ; in, is the flow rate input into the pipeline in the previous section, is the flow rate of the next section of the pipeline, is the pressure head of the point source at the end of the previous section of the pipeline, is the pressure head of the point source at the end of the next section of the pipeline, is the well water depth of the point source at the end of the pipeline in the previous section, is the well water depth of the point source at the end of the next section of the pipeline, is the average length of the pipeline, is the average water-passing short-section area of the pipeline, is the time step, is the acceleration due to gravity; The water head information at the point source is transmitted to the one-dimensional pipe network model by using the two-dimensional model of the plant area , in order to realize the drainage calculation of the one-dimensional pipe network model.
4. The method according to claim 3, characterized in that The method of using the two-dimensional plant model to access the flow of the pipeline in the one-dimensional pipe network model, using the flow difference between adjacent pipelines in the one-dimensional pipe network model as the flow process of the point source in the two-dimensional plant model to realize the drainage calculation of the two-dimensional plant model; and using the two-dimensional plant model to transfer the head information at the point source to the one-dimensional pipe network model to realize the drainage calculation of the one-dimensional pipe network model, further includes: Using shared memory to store the overflow flow of point sources in the one-dimensional pipe network model , and the water head information at the point source in the two-dimensional model of the plant area ; When the two-dimensional plant model reads the overflow flow of the point source in the one-dimensional pipe network model stored in the shared memory After that, clear the shared memory and write the water head information at the next point source ; When the one-dimensional pipe network model reads the water head information at the point source in the two-dimensional plant model stored in the shared memory After that, clear the shared content and write the overflow flow of the next point source .
5. The method according to claim 1, characterized in that After calibrating each water source in the two-dimensional model of the plant area by using different tracers, the proportion of each tracer in the waterlogged area in the two-dimensional model of the plant area is calculated to achieve the tracing of the waterlogged area, including: Different tracers are used to calibrate the water sources in the two-dimensional model of the plant area. The water sources of the two-dimensional model of the plant area include rainfall water, runoff water, over-wave water, and pipe network drainage. The runoff water and over-wave water are given by the boundary conditions, and the open boundary is divided into The number of wells in the network from which the network drains water Given, different tracers are set for runoff water, overtopping water, and pipe network drainage. ; When a waterlogging area appears in the two-dimensional model of the plant area, the concentration of each tracer is , then the proportion of each water source in the waterlogged area is , , the proportion of rainfall water is , the formula is as follows: , 。 6. A nuclear power plant water accumulation simulation calculation and source tracing device, characterized in that: include: An inversion module is used to establish a tropical cyclone inversion model and simulate and calculate the rainfall distribution and wind field distribution in the study area according to the tropical cyclone inversion model; wherein the study area includes the factory area; A calculation module is used to establish an offshore wave calculation model and an ocean current model, and according to the wind field distribution, use the offshore wave calculation model, the ocean current model, and the SWASH model to simulate and calculate the nearshore overtopping amount to obtain the overtopping amount; wherein the ocean current model is a two-dimensional flow field model, which simulates the flow of water and calculates the water depth by combining the shallow water equation and the momentum conservation equation; the offshore wave calculation model is used to simulate and calculate nearshore waves, and after calculation using the offshore wave calculation model, the overtopping amount is calculated by extracting the nearshore boundary conditions as the boundary conditions of the SWASH model, coupling the wind field distribution and the water depth calculated by the ocean current model; A rainfall module is used to establish a one-dimensional rainfall runoff model based on the digital elevation model of the study area, and use the one-dimensional rainfall runoff model to simulate and calculate the runoff according to the rainfall distribution to obtain the runoff of the small watershed; the one-dimensional rainfall runoff model is established based on the digital elevation model of the study area, and the one-dimensional rainfall runoff model is used to simulate and calculate the runoff according to the rainfall distribution to obtain the runoff of the small watershed, including: obtaining the digital elevation model of the study area, and dividing the small watershed of the study area according to the digital elevation model; according to the plant area At the location within the study area, extract the small watershed where the streamline enters the plant area, and divide the small watershed where the streamline enters the plant area into multiple sub-catchment areas; wherein the flow of rainfall runoff entering the study area passes through different sub-catchment areas to form a flow time process for inputting the two-dimensional model of the plant area; use all boundaries of the study area as the end nodes of streamline tracing to construct a one-dimensional rainfall runoff model; wherein the end node serves as a point source of the two-dimensional model of the plant area; according to the rainfall distribution, use the one-dimensional rainfall runoff model to perform runoff simulation calculation to obtain the runoff of the small watershed; Establish a module for establishing a two-dimensional model of the plant area and a one-dimensional pipe network model based on the underground drainage system of the plant area; An acquisition module, used for acquiring a rainfall time series of a rainfall process in a plant area output by the tropical cyclone inversion model, using the rainfall time series as a model parameter of the two-dimensional model of the plant area, and using the overtopping amount and the small watershed runoff as boundary conditions of the two-dimensional model of the plant area; A calculation module, used to access the flow of the pipes in the one-dimensional pipe network model using the two-dimensional plant model, use the flow difference between adjacent pipes in the one-dimensional pipe network model as the flow process of the point source in the two-dimensional plant model, so as to realize the drainage calculation of the two-dimensional plant model; and use the two-dimensional plant model to transfer the head information at the point source to the one-dimensional pipe network model, so as to realize the drainage calculation of the one-dimensional pipe network model; The source tracing module is used to calibrate each water source in the two-dimensional model of the plant area using different tracers, and then calculate the proportion of each tracer in the waterlogged area in the two-dimensional model of the plant area to achieve source tracing of the waterlogged area.
7. A terminal, characterized in that: include: one or more processors; A storage device for storing one or more programs; When the one or more programs are executed by the one or more processors, the one or more processors implement the nuclear power plant area water accumulation simulation calculation and tracing method as described in any one of claims 1-5.
8. A storage medium comprising a computer executable instruction program, wherein the computer executable instruction program, when executed by a computer processor, is used to execute the nuclear power plant area water accumulation simulation calculation and tracing method as described in any one of claims 1 to 5.