Intelligent monitoring method, device, equipment and medium for power transmission and transformation engineering
Through intelligent monitoring methods, wire status and video data are used to identify abnormalities, and the monitoring strategy is adjusted based on abnormal correlation and fault path sequence, which solves the problem of low wire monitoring efficiency in power transmission and transformation projects and achieves efficient and reliable monitoring of wires.
Patent Information
- Application Number
- CN202410725609.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-06
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2044-06-06
AI Technical Summary
In power transmission and transformation projects, the wide distribution, long length and complex laying environment of wires make monitoring difficult. The existing fixed monitoring strategy cannot fully consider the differences of wires, and is prone to over-monitoring or insufficient monitoring, resulting in low efficiency.
Intelligent monitoring methods are adopted to determine abnormal conditions by obtaining status data and video data of wires, and adjust monitoring strategies based on abnormal correlation and fault path sequences to achieve comprehensive real-time monitoring of wires, detect abnormalities in time and predict faults, improving monitoring efficiency.
By dynamically adjusting the monitoring strategy, the efficiency and accuracy of wire monitoring are improved, ensuring the safe and stable operation of the wires, and enhancing the reliability of the power system.
Smart Images

Figure CN118316201B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of power monitoring, and in particular to an intelligent monitoring method, device, equipment and medium for power transmission and transformation projects. Background Art
[0002] In power transmission and transformation projects, wires are the main channels for power transmission. Their safe and stable operation has a decisive impact on ensuring the reliability of the entire power system. Therefore, it is very important to monitor the wires. However, due to the wide distribution, long length and complex laying environment of wires, monitoring of wires is relatively difficult.
[0003] Currently, fixed monitoring strategies (such as fixed monitoring cycles) are usually used for monitoring. However, this method does not fully consider the actual conditions and differences of wires, and is prone to over-monitoring or under-monitoring, resulting in low monitoring efficiency. Summary of the invention
[0004] In order to improve the efficiency of power line monitoring, the present application provides an intelligent monitoring method, device, equipment and medium for power transmission and transformation projects.
[0005] In a first aspect, the present application provides an intelligent monitoring method for power transmission and transformation projects, which adopts the following technical solutions:
[0006] An intelligent monitoring method for power transmission and transformation engineering, comprising:
[0007] Acquiring monitoring data of the electric wire, wherein the monitoring data includes status data and video data;
[0008] Determining a first abnormal situation based on the monitoring data and corresponding standard data;
[0009] Determine a second abnormal situation and a fault path sequence based on the first abnormal situation and the abnormal association, the abnormal association includes an association between abnormalities and / or an association between abnormalities and faults, the second abnormal situation includes at least one abnormality and / or at least one fault, and the fault path sequence includes a path sequence between the first abnormal situation and the fault;
[0010] A monitoring strategy is determined based on the first abnormal situation, the second abnormal situation, and the fault path sequence, and the monitoring strategy includes early warning information and a monitoring period.
[0011] By adopting the above technical solution, the first abnormal situation is determined through the status data of the wire and the video data, so that the wire can be fully and real-time monitored, and the abnormal situation of the wire can be discovered in time. The second abnormal situation that may occur and the fault path sequence of subsequent failures can be predicted through the first abnormal situation that has occurred and the abnormal association. The monitoring strategy is jointly determined based on the first abnormal situation, the second abnormal situation and the fault path sequence, making the monitoring strategy more reliable. The staff monitors according to the monitoring strategy, which improves the efficiency of wire monitoring.
[0012] Optionally, determining the first abnormal situation based on the monitoring data and corresponding standard data includes:
[0013] determining location information based on the monitoring data;
[0014] Acquire first standard data based on the location information, where the first standard data is standard data corresponding to the location where the monitoring data is sourced;
[0015] Determine first abnormal information based on the first standard data and the state data, wherein the first abnormal information includes an abnormal state of the electric wire;
[0016] Acquire first power data and second power data, wherein the first power data is power data transmitted by the electric wire, and the second power data is actual available power data;
[0017] Determine second abnormal information based on the first power data and the second power data, wherein the second abnormal information includes abnormal power transmission of the wire;
[0018] Identify the video data to determine third abnormal information, where the third abnormal information includes abnormal shape of the wire;
[0019] A first abnormal situation is determined based on the first abnormal information, the second abnormal information, and the third abnormal information.
[0020] By adopting the above technical scheme, different first standard data are used at different positions of the wire to determine the first abnormal information, and the actual conditions of the wires at different positions are fully considered, thereby improving the accuracy of the first abnormal information. When determining the abnormal conditions of the wires, the power transmission conditions of the wires and the abnormal conditions of their appearance are also considered, thereby making the abnormal information of the wires more comprehensive and improving the reliability of the first abnormal conditions.
[0021] Optionally, before acquiring the first standard data based on the location information, the method further includes:
[0022] Acquire historical abnormal data, wherein the historical abnormal data includes historical monitoring data and historical abnormal situations;
[0023] Dividing the historical abnormal data based on the location information to obtain multiple abnormal information combinations;
[0024] Each of the abnormal information combinations is analyzed to obtain the first standard data.
[0025] By adopting the above technical solution, the first standard data of the corresponding location is determined by the historical abnormal data of different locations, rather than using a unified and fixed first standard data, thereby improving the accuracy of the first standard data, and determining the first abnormal information based on the first standard data, thereby improving the accuracy of the first abnormal information, thereby improving the accuracy of the first abnormal situation.
[0026] Optionally, before determining the second abnormal situation and the fault path sequence based on the first abnormal situation and the abnormal association, the method further includes:
[0027] Acquire historical fault data, wherein the historical fault data includes fault type, abnormality type and abnormality monitoring data;
[0028] Dividing the historical fault data based on the fault type to obtain multiple fault data sets, wherein the historical fault data in each fault data set corresponds to the same fault type;
[0029] Counting the number of the historical fault data in each of the fault data sets to obtain a plurality of first numbers;
[0030] Dividing the fault data set based on the environmental data to obtain a plurality of environmental fault combinations, wherein the historical fault data in each of the environmental fault combinations corresponds to the same environmental data;
[0031] Counting the number of the historical fault data in each of the environmental fault combinations to obtain a plurality of second numbers;
[0032] Determine an environmental fault association based on the first number and the second number, where the environmental fault association includes an association relationship between a fault and an environment;
[0033] Determine an abnormal fault association based on the fault type and the corresponding abnormal type, wherein the abnormal fault association includes an association relationship between the fault and the abnormality;
[0034] Determine a multi-anomaly association based on an association rule mining algorithm and the historical fault data, wherein the multi-anomaly association includes an association relationship between at least two anomalies;
[0035] An abnormality correlation is determined based on the environmental fault correlation, the abnormality fault correlation, and the multiple abnormality correlations.
[0036] By adopting the above technical solution, the correlation between environmental data, anomalies and faults is obtained by analyzing historical fault data, rather than using conventional thinking to manually determine the correlation, thereby improving the reliability of the correlation. The second abnormal situation and the fault path sequence are determined based on the correlation, thereby determining the monitoring strategy, improving the reliability of the monitoring strategy, and further improving the efficiency of power line monitoring.
[0037] Optionally, the determining the second abnormal situation and the fault path sequence based on the first abnormal situation and the abnormal association includes:
[0038] Determining the abnormal situation directly caused by the first abnormal situation in the abnormal association as the second abnormal situation;
[0039] Determine a path sequence corresponding to the first abnormal situation in the abnormal association as a fault path sequence;
[0040] Obtain environmental data;
[0041] correcting the second abnormal condition based on the environmental data and the abnormal association;
[0042] The determining of the monitoring strategy based on the first abnormal situation, the second abnormal situation and the fault path sequence includes:
[0043] A monitoring strategy is determined based on the first abnormal condition, the corrected second abnormal condition, and the fault path sequence.
[0044] Optionally, determining a monitoring strategy based on the first abnormal condition, the corrected second abnormal condition, and the fault path sequence includes:
[0045] determining abnormality information and first fault information based on the corrected second abnormal condition;
[0046] Determine the number of the first fault information as the number of faults;
[0047] Determine the number of the abnormal information as the abnormal number;
[0048] Calculating the total length of the fault path sequence corresponding to the first abnormal situation;
[0049] Calculate an abnormality impact value based on the number of faults, the number of abnormalities, and the total length;
[0050] determining an abnormality level based on the abnormality impact value;
[0051] A monitoring strategy is determined based on the abnormality level.
[0052] By adopting the above technical solution, the abnormal impact value of the current abnormality on the power line is determined by the number of faults, the number of abnormalities and the total length of the fault path sequence, and the abnormality level is determined according to the abnormality impact value. The monitoring strategy is determined according to the abnormality level. Different abnormality levels correspond to different monitoring strategies, which improves the reliability of the monitoring strategy. Monitoring is performed according to the monitoring strategy, which improves the efficiency of power line monitoring.
[0053] Optionally, determining a monitoring strategy based on the abnormality level includes:
[0054] Obtaining a monitoring cycle, a first number, a second number, and a third number, wherein the monitoring cycle is a cycle for monitoring the electric wire, the first number is the number of abnormalities in the current monitoring cycle, the second number is the number of monitoring cycles with continuous abnormalities or faults, and the third number is the number of faults in the current monitoring cycle;
[0055] If the abnormality level is the second abnormality level or the third abnormality level, determining whether the first number is greater than a first preset number and / or whether the second number is greater than a second preset number;
[0056] If the first number is greater than the first preset number and / or the second number is greater than the second preset number, adjusting the monitoring period based on the first number and the second number;
[0057] If the abnormality level is the first abnormality level and / or the third number is greater than a third preset number, the monitoring period is adjusted based on a preset weight.
[0058] By adopting the above technical solution, when adjusting the monitoring cycle, not only the abnormality level of the current abnormality is taken into account, but also the number of abnormalities in the current monitoring cycle, the number of consecutive monitoring cycles with abnormalities and the number of faults in the current monitoring cycle are taken into account, thereby improving the reliability of the monitoring cycle adjustment, monitoring according to the monitoring cycle, and improving the efficiency of power line monitoring.
[0059] In a second aspect, the present application provides an intelligent monitoring device for power transmission and transformation projects, which adopts the following technical solution:
[0060] An intelligent monitoring device for power transmission and transformation engineering, comprising:
[0061] A data acquisition module, used to acquire monitoring data of the electric wire, wherein the monitoring data includes status data and video data;
[0062] an abnormality determination module, configured to determine a first abnormality based on the monitoring data and corresponding standard data;
[0063] an abnormality association module, configured to determine a second abnormality and a fault path sequence based on the first abnormality and the abnormality association, wherein the abnormality association includes an association between abnormalities and / or an association between abnormalities and faults, the second abnormality includes at least one abnormality and / or at least one fault, and the fault path sequence includes a path sequence between the first abnormality and the fault;
[0064] A strategy determination module is used to determine a monitoring strategy based on the first abnormal situation, the second abnormal situation and the fault path sequence, wherein the monitoring strategy includes early warning information and a monitoring period.
[0065] By adopting the above technical solution, the first abnormal situation is determined through the status data of the wire and the video data, so that the wire can be fully and real-time monitored, and the abnormal situation of the wire can be discovered in time. The second abnormal situation that may occur and the fault path sequence of subsequent failures can be predicted through the first abnormal situation that has occurred and the abnormal association. The monitoring strategy is jointly determined based on the first abnormal situation, the second abnormal situation and the fault path sequence, making the monitoring strategy more reliable. The staff monitors according to the monitoring strategy, which improves the efficiency of wire monitoring.
[0066] In a third aspect, the present application provides an electronic device, which adopts the following technical solution:
[0067] An electronic device comprises a processor, wherein the processor is coupled to a memory;
[0068] The memory stores a computer program that can be loaded by the processor and executes the intelligent monitoring method for power transmission and transformation projects described in any one of the first aspects.
[0069] In a fourth aspect, the present application provides a computer-readable storage medium, which adopts the following technical solution:
[0070] A computer-readable storage medium stores a computer program that can be loaded by a processor and executes the intelligent monitoring method for power transmission and transformation engineering described in any one of the first aspects. BRIEF DESCRIPTION OF THE DRAWINGS
[0071] Figure 1 It is a flow chart of an intelligent monitoring method for power transmission and transformation projects provided in an embodiment of the present application.
[0072] Figure 2 It is a structural block diagram of an intelligent monitoring device for power transmission and transformation projects provided in an embodiment of the present application.
[0073] Figure 3 It is a structural block diagram of an electronic device provided in an embodiment of the present application. DETAILED DESCRIPTION
[0074] The present application is further described in detail below in conjunction with the accompanying drawings.
[0075] The embodiment of the present application provides an intelligent monitoring method for power transmission and transformation projects, which can be executed by an electronic device, which can be a server or a terminal device, wherein the server can be an independent physical server, a server cluster or a distributed system composed of multiple physical servers, or a cloud server providing cloud computing services. The terminal device can be a smart phone, a tablet computer, a desktop computer, etc., but is not limited thereto.
[0076] In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.
[0077] In addition, the term "and / or" in this article is only a description of the association relationship of associated objects, indicating that there can be three relationships. For example, A and / or B can represent: A exists alone, A and B exist at the same time, and B exists alone. In addition, the character " / " in this article, unless otherwise specified, generally means that the associated objects before and after are in an "or" relationship.
[0078] like Figure 1 As shown, an intelligent monitoring method for power transmission and transformation engineering, the main process of the method is described as follows (steps S101 to S104):
[0079] Step S101, obtaining monitoring data of electric wires.
[0080] Among them, the monitoring data includes status data and video data. The status data, such as current, voltage, and temperature, can be obtained in real time from various sensors. The video data is the monitoring video data of the wires, which can be obtained in real time from the camera.
[0081] Step S102: determining a first abnormal situation based on the monitoring data and corresponding standard data.
[0082] It is determined whether there is an abnormality based on the monitoring data and the standard data corresponding to each monitoring data. If an abnormality exists, a first abnormal situation is determined.
[0083] Specifically, determining a first abnormal situation based on monitoring data and corresponding standard data includes: determining location information based on the monitoring data; acquiring first standard data based on the location information, the first standard data being standard data corresponding to the location of a source of the monitoring data; determining first abnormal information based on the first standard data and status data, the first abnormal information including a status abnormality of the wire; acquiring first power data and second power data, the first power data being power data transmitted by the wire, and the second power data being actual available power data; determining second abnormal information based on the first power data and the second power data, the second abnormal information including a power transmission abnormality of the wire; identifying video data to determine third abnormal information, the third abnormal information including a morphological abnormality of the wire; determining the first abnormal situation based on the first abnormal information, the second abnormal information, and the third abnormal information.
[0084] In this embodiment, since the types, qualities, and service lives of wires used in different locations are different, the standard data used are also different. The location information of the wire is determined based on the source of the monitoring data. For example, if the monitoring data is obtained from a sensor at position A, the location information is position A. The first standard data corresponding to the position is obtained from the database based on the location information, and the status data is compared with the corresponding first standard data. If there is status data that does not satisfy the data interval corresponding to the first standard data, there is an abnormality. For example, if the current value exceeds the interval corresponding to the first standard data, the abnormal status of the wire is a current abnormality. The first abnormal information includes the current abnormality and the corresponding abnormal status data.
[0085] The first power data and the second power data are obtained from a database or a sensor. If the difference between the first power data and the second power data exceeds a preset difference or the ratio of the second power data to the first power data is less than a preset ratio, that is, the line loss rate of the wire is too high, indicating that there is an abnormality in the wire, and the abnormal power transmission of the wire is the line loss rate being too high. The second abnormal information includes the line loss rate being too high and the corresponding first power data and the second power data, wherein the preset difference and the preset ratio are both pre-set and are not specifically limited here.
[0086] The image is recognized by a preset image recognition model to obtain abnormal conditions in appearance and morphology of the wires, that is, morphological abnormalities, such as broken wires, excessive sag, and icing, etc., wherein the preset image recognition model is a pre-trained model that can recognize various abnormal conditions of the wires, and jointly determine the first abnormal information, the second abnormal information, and the third abnormal information as the first abnormal condition, that is, the first abnormal condition may include multiple abnormalities.
[0087] Furthermore, the video data is identified to determine the third abnormal information, including: identifying the video data to obtain the sag of the wire; obtaining the sag threshold based on the position information; comparing the sag with the sag threshold to obtain sag abnormal information; performing image recognition on the wire based on a preset image recognition model to obtain damage abnormal information of the wire; and determining the third abnormal information based on the sag abnormal information and the damage abnormal information.
[0088] In this embodiment, the sag of the electric wire is identified by a preset image recognition model. Since the building heights under the electric wires at different positions are different, the allowable sag thresholds will also vary to a certain extent. The sag threshold is obtained from the database according to the position information. If the sag is greater than the sag threshold, there is a sag abnormality, and the sag abnormality and the corresponding sag are determined as sag abnormality information; the preset image recognition model is used to identify whether the electric wire has a damage abnormality, that is, whether the electric wire is damaged, the wire breakage abnormality, and the icing abnormality, etc., and the abnormality type (such as damage abnormality and wire breakage abnormality) and the corresponding position are determined as damage abnormality information, and the sag abnormality information and the damage abnormality information are jointly determined as the third abnormality information.
[0089] Specifically, before obtaining the first standard data based on the location information, the method also includes: obtaining historical abnormal data, the historical abnormal data including historical monitoring data and historical abnormal situations; dividing the historical abnormal data based on the location information to obtain multiple abnormal information combinations; analyzing each abnormal information combination to obtain the first standard data.
[0090] Since the types, qualities, and years of use of wires at different locations are different, if unified standard data is used, the abnormal conclusions drawn will have certain errors, so different standard data should be used. In this embodiment, historical abnormal data is obtained from the database, and the historical abnormal data is divided according to the location information to obtain multiple abnormal information combinations. The historical abnormal data in each abnormal information combination corresponds to the same location information. The abnormal information combination is analyzed by a data analysis tool to obtain the first standard data corresponding to each location information. The data analysis tool can be Excel, Python, or SQL, which is not specifically limited here.
[0091] Step S103: determining a second abnormal situation and a fault path sequence based on the first abnormal situation and the abnormal association.
[0092] Among them, the abnormal association includes the association between abnormalities and / or the association between abnormalities and faults, the second abnormal situation includes at least one abnormality and / or at least one fault, and the fault path sequence includes the path sequence between the first abnormal situation and the fault.
[0093] An abnormality means that there are some problems with the wires, such as: the insulation layer is damaged, but it does not necessarily affect the use. A fault means that the wire cannot be used normally. One abnormality may directly or indirectly lead to multiple abnormalities or faults. The causal relationship between abnormalities and between abnormalities and faults is determined as an abnormal association. The second abnormal situation and the fault path sequence can be found from the abnormal association through the first abnormal situation.
[0094] Specifically, before determining the second abnormal situation and the fault path sequence based on the first abnormal situation and the abnormal association, the method also includes: obtaining historical fault data, the historical fault data including fault type, abnormal type and abnormal monitoring data; dividing the historical fault data based on the fault type to obtain multiple fault data sets, the historical fault data in each fault data set corresponding to the same fault type; counting the number of historical fault data in each fault data set to obtain multiple first numbers; dividing the fault data set based on the environmental data to obtain multiple environmental fault combinations, the historical fault data in each environmental fault combination corresponding to the same environmental data; counting the number of historical fault data in each environmental fault combination to obtain multiple second numbers; determining the environmental fault association based on the first number and the second number, the environmental fault association including the association relationship between the fault and the environment; determining the abnormal fault association based on the fault type and the corresponding abnormal type, the abnormal fault association including the association relationship between the fault and the abnormality; determining multiple abnormal associations based on the association rule mining algorithm and the historical fault data, the multiple abnormal associations including the association relationship between at least two abnormalities; determining the abnormal association based on the environmental fault association, the abnormal fault association and the multiple abnormal associations.
[0095] In this embodiment, historical fault data is obtained from a database, and the historical fault data is divided according to the fault type to obtain multiple fault data sets. The number of historical fault data in each fault data set is counted to obtain multiple first numbers, and the number of the first numbers is the same as the number of the fault data sets. Since the occurrence of the fault is also associated with the environment, the historical fault data also includes environmental data. Each fault data set is divided again according to the environmental data to obtain multiple environmental fault combinations. The historical fault data in each environmental fault combination corresponds to the same environmental data. The number of historical fault data in each environmental fault combination is counted to obtain multiple second numbers, and the number of the second numbers is the same as the number of environmental fault combinations. Each second number is ratioed with the first number corresponding to the fault data set where the environmental fault combination is located to obtain multiple environmental fault probabilities. If the environmental fault probability is greater than the preset environmental fault probability, then the environmental data has a causal relationship with the fault type, wherein the preset environmental fault probability is pre-set according to the actual situation and is not specifically limited here. All environmental data with a causal relationship are determined to be associated with the fault type and stored.
[0096] Furthermore, each fault data set is divided again according to the abnormal type to obtain multiple abnormal fault combinations, and the historical fault data in each abnormal fault combination includes the same abnormal type. Since each historical fault data may include multiple abnormal types, each historical fault data may exist in multiple abnormal fault combinations. The number of abnormal fault combinations is equal to the number of abnormal types. The number of historical fault data in each abnormal fault combination is counted to obtain multiple third quantities, and the number of third quantities is the same as the number of abnormal fault combinations. Each third quantity is ratioed with the first quantity corresponding to the fault data set where the abnormal fault combination is located to obtain multiple abnormal fault probabilities. If the abnormal fault probability is greater than the preset abnormal fault probability, then the abnormal type has a causal relationship with the fault type, wherein the preset abnormal fault probability is pre-set according to actual conditions and is not specifically limited here. All abnormal types and fault types that have a causal relationship are determined to be abnormal fault associations and stored.
[0097] Historical abnormal data is obtained from the database, and the historical fault data and historical abnormal data are analyzed through the association rule mining algorithm to obtain the association relationship between various abnormalities, that is, the causal relationship between the abnormalities. Among them, the association rule mining algorithm includes but is not limited to Apriori, FP-Growth and ECLAT. All association relationships are collectively determined as multiple abnormality associations and stored. For example, the occurrence of abnormality a often leads to the occurrence of abnormality b, and the occurrence of abnormality b often leads to the occurrence of abnormality c, then there is a multiple abnormality association abnormality a-abnormality b-abnormality c.
[0098] Environmental fault association, abnormal fault association and multiple abnormality association are associated through a database according to the same abnormality or fault to obtain abnormality association.
[0099] Specifically, determining the second abnormal situation and the fault path sequence based on the first abnormal situation and the abnormal association includes: determining the abnormal situation directly caused by the first abnormal situation in the abnormal association as the second abnormal situation; determining the path sequence corresponding to the first abnormal situation in the abnormal association as the fault path sequence; acquiring environmental data; correcting the second abnormal situation based on the environmental data and the abnormal association; determining a monitoring strategy based on the first abnormal situation, the second abnormal situation and the fault path sequence, including: determining a monitoring strategy based on the first abnormal situation, the corrected second abnormal situation and the fault path sequence.
[0100] In this embodiment, the first abnormal situation may correspond to multiple abnormalities. The abnormality in the first abnormal situation is determined as the first abnormality, that is, the currently existing abnormality. The abnormality or fault directly caused by the first abnormality is found from the abnormal association and determined as the second abnormal situation. The path sequence where the first abnormality is located in the abnormal association is determined as the first abnormality sequence. The first abnormality sequence is segmented with the first abnormality as the dividing position, and the segmented path sequence with the first abnormality as the starting point is determined as the fault path sequence. For example: if the first abnormality is abnormality a, there are two first abnormality sequences, namely, sequence: abnormality c-abnormality a-abnormality b-fault 1 and sequence: abnormality a-abnormality f-fault 2, then the fault path sequence is sequence: abnormality a-abnormality b-fault 1 and sequence: abnormality a-abnormality f-fault 2.
[0101] Obtain the current environmental data from the meteorological department. Since some faults only occur under specific environments, the causal relationship between the abnormality and the fault should be considered in combination with the environment. The second abnormal situation should be screened through the current environmental data, and the second abnormal situation that occurs under the current environmental data should be determined as the corrected second abnormal situation. The monitoring strategy should be determined based on the first abnormal situation, the corrected second abnormal situation and the fault path sequence.
[0102] Step S104: determining a monitoring strategy based on the first abnormal situation, the second abnormal situation, and the fault path sequence.
[0103] Among them, the monitoring strategy includes warning information and monitoring cycle. The monitoring strategy is the response strategy that needs to be taken after the first abnormality occurs.
[0104] Specifically, a monitoring strategy is determined based on a first abnormal situation, a corrected second abnormal situation, and a fault path sequence, including: determining abnormal information and first fault information based on the corrected second abnormal situation; determining the number of first fault information as the number of faults; determining the number of abnormal information as the number of abnormalities; calculating the total length of the fault path sequence corresponding to the first abnormal situation; calculating an abnormal impact value based on the number of faults, the number of abnormalities, and the total length; determining an abnormality level based on the abnormal impact value; and determining a monitoring strategy based on the abnormality level.
[0105] In this embodiment, the information corresponding to the abnormality in the corrected second abnormal situation is determined as abnormal information, and the information corresponding to the fault in the corrected second abnormal situation is determined as the first fault information. The number of first fault information is counted and the number is determined as the fault number. The number of abnormal information is determined as the abnormal number. The length of each fault path sequence corresponding to the first abnormal situation is calculated. For example, if the fault path sequence is: abnormality c-abnormality a-abnormality b-fault 1, then the length of the fault path sequence is 3, and the calculated lengths are summed to obtain the total length. The abnormal impact value = the number of faults × the first number weight + the number of abnormalities × the second number weight + the total length × the third number weight, wherein the first number weight, the second number weight and the third number weight decrease in sequence, and all three are greater than zero, but the specific values are pre-set and are not specifically limited here. The corresponding relationship between the abnormal impact value and the abnormal level is stored in the database. The abnormal level is searched from the database according to the abnormal impact value, and different monitoring strategies are determined according to the abnormal level.
[0106] In this embodiment, the second abnormal situation before correction, the first abnormal situation, and the fault path sequence may also be used to determine the monitoring strategy, the method is the same as above, and will not be repeated here.
[0107] Furthermore, a monitoring strategy is determined based on the abnormality level, including: obtaining a monitoring cycle, a first number, a second number, and a third number, wherein the monitoring cycle is a cycle for monitoring the electric wires, the first number is the number of times the abnormality exists in the current monitoring cycle, the second number is the number of monitoring cycles in which the abnormality or fault exists continuously, and the third number is the number of times the fault exists in the current monitoring cycle; if the abnormality level is the second abnormality level or the third abnormality level, then determining whether the first number is greater than the first preset number and / or whether the second number is greater than the second preset number; if the first number is greater than the first preset number and / or the second number is greater than the second preset number, then adjusting the monitoring cycle based on the first number and the second number; if the abnormality level is the first abnormality level and / or the third number is greater than the third preset number, then adjusting the monitoring cycle based on the preset weight.
[0108] Among them, the first preset number of times, the second preset number of times and the third preset number of times are pre-set and are not specifically limited here.
[0109] In this embodiment, the abnormality level includes a first abnormality level, a second abnormality level and a third abnormality level. The severity of the first abnormality level, the second abnormality level and the third abnormality level gradually decreases. When the abnormality level is the first abnormality level, the warning message is "the staff shall immediately perform inspection and maintenance". When the abnormality level is the second abnormality level, the warning message is "continue to obtain the monitoring data of the wires. When the abnormality occurs again, the staff shall immediately perform inspection and maintenance". When the abnormality level is the third abnormality level, the warning message is "continue to obtain the monitoring data of the wires. No inspection and maintenance is required by the staff".
[0110] The monitoring period (i.e., how often a manual inspection is required), the first number, the second number, and the third number are obtained from the database. If the abnormality level is the second abnormality level or the third abnormality level, and the first number is greater than the first preset number and / or the second number is greater than the second preset number, then the first number and the second number are summed. The database stores the correspondence between the number and the first cycle weight value. According to the number and, the corresponding first cycle weight value is found from the database. The new monitoring period = the first cycle weight value × the original monitoring period.
[0111] If the abnormality level is the second abnormality level or the third abnormality level, and the first number is less than or equal to the first preset number, and the second number is less than or equal to the second preset number, there is no need to adjust the monitoring period.
[0112] The database stores the correspondence between the abnormality level, the third number and the preset weight. If the abnormality level is the first abnormality level and / or the third number is greater than the third preset number, the preset weight is searched from the database according to the abnormality level and the third number. The new monitoring period = preset weight × original monitoring period.
[0113] After adjusting the monitoring cycle, perform manual monitoring according to the new monitoring cycle.
[0114] The monitoring strategy also includes a monitoring personnel combination strategy. The staff performs monitoring inspections or wire maintenance work according to the monitoring personnel combination. When determining the monitoring personnel combination, the staff's historical inspection records and historical error records are obtained from the database. The number of historical inspections of each staff member is counted according to the historical inspection records, and the number of historical errors of each staff member is counted according to the historical error records. The grade score = historical inspection times × first preset weight - historical error times × second preset weight, wherein the first preset weight is less than the second preset weight, and both are greater than zero, but the specific values are pre-set and are not specifically limited here. The database stores the correspondence between the grade score and the work level. The work level corresponding to the staff member is searched from the database according to the grade score. The work level includes a first work level, a second work level and a third work level, and the levels of the first work level, the second work level and the third work level decrease in sequence.
[0115] The combination of monitoring personnel is determined according to the work level, and the number of people in the combination is not specifically limited. The monitoring personnel combination strategy includes: if the number of staff is one, the work level of the staff is the first work level or the second work level; if the number of staff is greater than one, and there is a staff member with the third work level, then there is at least one staff member with the first work level; if the number of staff is greater than one, and there is no staff member with the third work level, then the work level of each staff member can be the first work level or the second work level.
[0116] Figure 2 A structural block diagram of an intelligent monitoring device 200 for power transmission and transformation projects provided in an embodiment of the present application.
[0117] like Figure 2 As shown, the intelligent monitoring device 200 for power transmission and transformation engineering mainly includes:
[0118] A data acquisition module 201 is used to acquire monitoring data of the electric wire, wherein the monitoring data includes status data and video data;
[0119] An abnormality determination module 202, configured to determine a first abnormality based on the monitoring data and corresponding standard data;
[0120] The abnormal association module 203 is used to determine the second abnormal situation and the fault path sequence based on the first abnormal situation and the abnormal association, the abnormal association includes the association between the state data and / or the association between the state data and the fault, the second abnormal situation includes at least one state data and / or at least one fault, and the fault path sequence includes the path sequence between the first abnormal situation and the fault;
[0121] The strategy determination module 204 is used to determine the monitoring strategy based on the first abnormal situation, the second abnormal situation and the fault path sequence.
[0122] As an optional implementation of this embodiment, the abnormality determination module 202 is also specifically used to determine a first abnormal situation based on the monitoring data and the corresponding standard data, including: determining location information based on the monitoring data; acquiring first standard data based on the location information, the first standard data being the standard data corresponding to the location of the monitoring data source; determining first abnormal information based on the first standard data and the status data, the first abnormal information including the abnormal status of the wire; acquiring first power data and second power data, the first power data being the power data transmitted by the wire, and the second power data being the actual available power data; determining second abnormal information based on the first power data and the second power data, the second abnormal information including the abnormal power transmission of the wire; identifying the video data to determine third abnormal information, the third abnormal information including the abnormal shape of the wire; determining the first abnormal situation based on the first abnormal information, the second abnormal information and the third abnormal information.
[0123] As an optional implementation of this embodiment, the abnormality determination module 202 is also specifically used to, before obtaining the first standard data based on the location information, also include: obtaining historical abnormality data, the historical abnormality data including historical monitoring data and historical abnormal conditions; dividing the historical abnormality data based on the location information to obtain multiple abnormal information combinations; analyzing each abnormal information combination to obtain the first standard data.
[0124] As an optional implementation of this embodiment, the abnormal association module 203 is also specifically used to determine the second abnormal situation and the fault path sequence based on the first abnormal situation and the abnormal association, and also includes: obtaining historical fault data, the historical fault data including fault type, abnormal type and abnormal monitoring data; dividing the historical fault data based on the fault type to obtain multiple fault data sets, and the historical fault data in each fault data set corresponds to the same fault type; counting the number of historical fault data in each fault data set to obtain multiple first numbers; dividing the fault data set based on the environmental data to obtain multiple environmental fault combinations, and the historical fault data in each environmental fault combination corresponds to the same environmental data; counting the number of historical fault data in each environmental fault combination to obtain multiple second numbers; determining the environmental fault association based on the first number and the second number, and the environmental fault association includes the association relationship between the fault and the environment; determining the abnormal fault association based on the fault type and the corresponding abnormal monitoring data, and the abnormal fault association includes the association relationship between the fault and the abnormality; determining multiple abnormal associations based on the association rule mining algorithm and the historical fault data, and the multiple abnormal associations include the association relationship between at least two abnormalities; determining the abnormal association based on the environmental fault association, the abnormal fault association and the multiple abnormal associations.
[0125] As an optional implementation of this embodiment, the abnormal association module 203 is also specifically used to determine the second abnormal situation and the fault path sequence based on the first abnormal situation and the abnormal association, including: determining the abnormal situation directly caused by the first abnormal situation in the abnormal association as the second abnormal situation; determining the path sequence corresponding to the first abnormal situation in the abnormal association as the fault path sequence; obtaining environmental data; correcting the second abnormal situation based on the environmental data and the abnormal association; determining the monitoring strategy based on the first abnormal situation, the second abnormal situation and the fault path sequence, including: determining the monitoring strategy based on the first abnormal situation, the corrected second abnormal situation and the fault path sequence.
[0126] As an optional implementation of this embodiment, the strategy determination module 204 is also specifically used to determine the monitoring strategy based on the first abnormal situation, the corrected second abnormal situation and the fault path sequence, including: determining the abnormal information and the first fault information based on the corrected second abnormal situation; determining the number of first fault information as the number of faults; determining the number of abnormal information as the number of abnormalities; calculating the total length of the fault path sequence corresponding to the first abnormal situation; calculating the abnormal impact value based on the number of faults, the number of abnormalities and the total length; determining the abnormal level based on the abnormal impact value; and determining the monitoring strategy based on the abnormal level.
[0127] As an optional implementation of this embodiment, the strategy determination module 204 is also specifically used to determine the monitoring strategy based on the abnormality level, including: obtaining a monitoring period, a first number, a second number and a third number, wherein the monitoring period is a period for monitoring the electric wires, the first number is the number of times the abnormality exists in the current monitoring period, the second number is the number of monitoring periods with continuous abnormality, and the third number is the number of times the fault exists in the current monitoring period; if the abnormality level is the second abnormality level or the third abnormality level, then determine whether the first number is greater than the first preset number and / or whether the second number is greater than the second preset number; if the first number is greater than the first preset number and / or the second number is greater than the second preset number, then adjust the monitoring period based on the first number and the second number; if the abnormality level is the first abnormality level and / or the third number is greater than the third preset number, then adjust the monitoring period based on the preset weight.
[0128] In one example, the module in any of the above devices can be one or more integrated circuits configured to implement the above methods, such as: one or more application specific integrated circuits (ASICs), or, one or more digital signal processors (DSPs), or, one or more field programmable gate arrays (FPGAs), or a combination of at least two of these integrated circuit forms.
[0129] For another example, when the modules in the device can be implemented in the form of a processing element scheduling program, the processing element can be a general-purpose processor, such as a central processing unit (CPU) or other processor that can call a program. For another example, these modules can be integrated together and implemented in the form of a system-on-a-chip (SOC).
[0130] Those skilled in the art can clearly understand that, for the convenience and brevity of description, the specific working processes of the above-described devices and modules can refer to the corresponding processes in the aforementioned method embodiments and will not be repeated here.
[0131] Figure 3 A structural block diagram of an electronic device 300 provided in an embodiment of the present application.
[0132] like Figure 3 As shown, the electronic device 300 includes a processor 301 and a memory 302 , and may further include an information input / information output (I / O) interface 303 , one or more of a communication component 304 , and a communication bus 305 .
[0133] The processor 301 is used to control the overall operation of the electronic device 300 to complete all or part of the steps of the above-mentioned intelligent monitoring method for power transmission and transformation engineering; the memory 302 is used to store various types of data to support the operation of the electronic device 300, and these data may include, for example, instructions for any application or method used to operate on the electronic device 300, and data related to the application. The memory 302 can be implemented by any type of volatile or non-volatile storage device or a combination thereof, such as static random access memory (SRAM), electrically erasable programmable read-only memory (EEPROM), erasable programmable read-only memory (EPROM), programmable read-only memory (PROM), read-only memory (ROM), magnetic memory, flash memory, magnetic disk or optical disk.
[0134] The I / O interface 303 provides an interface between the processor 301 and other interface modules, and the above-mentioned other interface modules can be keyboards, mice, buttons, etc. These buttons can be virtual buttons or physical buttons. The communication component 304 is used for wired or wireless communication between the electronic device 300 and other devices. Wireless communication, such as Wi-Fi, Bluetooth, Near Field Communication (NFC), 2G, 3G or 4G, or a combination of one or more of them, so the corresponding communication component 304 can include: Wi-Fi components, Bluetooth components, NFC components.
[0135] The electronic device 300 can be implemented by one or more application specific integrated circuits (ASIC), digital signal processors (DSP), digital signal processing devices (DSPD), programmable logic devices (PLD), field programmable gate arrays (FPGA), controllers, microcontrollers, microprocessors or other electronic components to execute the intelligent monitoring method for power transmission and transformation projects given in the above embodiments.
[0136] The communication bus 305 may include a path to transmit information between the above components. The communication bus 305 may be a PCI (Peripheral Component Interconnect) bus or an EISA (Extended Industry Standard Architecture) bus, etc. The communication bus 305 may be divided into an address bus, a data bus, a control bus, etc.
[0137] The electronic device 300 may include, but is not limited to, mobile terminals such as mobile phones, laptop computers, digital broadcast receivers, PDAs (personal digital assistants), PADs (tablet computers), PMPs (portable multimedia players), vehicle-mounted terminals (such as vehicle-mounted navigation terminals), etc., and fixed terminals such as digital TVs, desktop computers, etc., and may also be servers, etc.
[0138] The present application also provides a computer-readable storage medium, on which a computer program is stored. When the computer program is executed by a processor, the steps of the above-mentioned intelligent monitoring method for power transmission and transformation projects are implemented.
[0139] The computer-readable storage medium may include: a USB flash drive, a mobile hard disk, a read-only memory (ROM), a random access memory (RAM), a magnetic disk or an optical disk, and other media that can store program codes.
[0140] The terms "comprises," "comprising," or any other variations thereof are intended to cover non-exclusive inclusion such that a process, method, article, or apparatus that includes a list of elements includes not only those elements but also other elements not expressly listed, or also includes elements inherent to such process, method, article, or apparatus.
[0141] The above description is only a preferred embodiment of the present application and an explanation of the technical principles used. Those skilled in the art should understand that the scope of application involved in the present application is not limited to the technical solution formed by a specific combination of the above technical features, but should also cover other technical solutions formed by any combination of the above technical features or their equivalent features without departing from the aforementioned application concept. For example, the above features are replaced with (but not limited to) technical features with similar functions applied in the present application.
Claims
1. An intelligent monitoring method for power transmission and transformation engineering, characterized in that: include: Acquiring monitoring data of the electric wire, wherein the monitoring data includes status data and video data; Determining a first abnormal situation based on the monitoring data and corresponding standard data; Determine a second abnormal situation and a fault path sequence based on the first abnormal situation and the abnormal association, the abnormal association includes an association between abnormalities and / or an association between abnormalities and faults, the second abnormal situation includes at least one abnormality and / or at least one fault, and the fault path sequence includes a path sequence between the first abnormal situation and the fault; Determine a monitoring strategy based on the first abnormal situation, the second abnormal situation and the fault path sequence, wherein the monitoring strategy includes warning information and a monitoring period; The determining the first abnormal situation based on the monitoring data and the corresponding standard data includes: determining location information based on the monitoring data; Acquire first standard data based on the location information, where the first standard data is standard data corresponding to the location where the monitoring data is sourced; Determine first abnormal information based on the first standard data and the state data, wherein the first abnormal information includes an abnormal state of the electric wire; Acquire first power data and second power data, wherein the first power data is power data transmitted by the electric wire, and the second power data is actual available power data; Determine second abnormal information based on the first power data and the second power data, wherein the second abnormal information includes abnormal power transmission of the wire; Identify the video data to determine third abnormal information, where the third abnormal information includes abnormal shape of the wire; A first abnormal situation is determined based on the first abnormal information, the second abnormal information, and the third abnormal information.
2. The method according to claim 1, characterized in that Before acquiring the first standard data based on the position information, the method further includes: Acquire historical abnormal data, wherein the historical abnormal data includes historical monitoring data and historical abnormal situations; Dividing the historical abnormal data based on the location information to obtain multiple abnormal information combinations; Each of the abnormal information combinations is analyzed to obtain the first standard data.
3. The method according to claim 1, characterized in that: Before determining the second abnormal situation and the fault path sequence based on the first abnormal situation and the abnormal association, the method further includes: Acquire historical fault data, wherein the historical fault data includes fault type, abnormality type and abnormality monitoring data; Dividing the historical fault data based on the fault type to obtain multiple fault data sets, wherein the historical fault data in each fault data set corresponds to the same fault type; Counting the number of the historical fault data in each of the fault data sets to obtain a plurality of first numbers; Dividing the fault data set based on the environmental data to obtain a plurality of environmental fault combinations, wherein the historical fault data in each of the environmental fault combinations corresponds to the same environmental data; Counting the number of the historical fault data in each of the environmental fault combinations to obtain a plurality of second numbers; Determine an environmental fault association based on the first number and the second number, where the environmental fault association includes an association relationship between a fault and an environment; Determine an abnormal fault association based on the fault type and the corresponding abnormal type, wherein the abnormal fault association includes an association relationship between the fault and the abnormality; Determine a multi-anomaly association based on an association rule mining algorithm and the historical fault data, wherein the multi-anomaly association includes an association relationship between at least two anomalies; An abnormality correlation is determined based on the environmental fault correlation, the abnormality fault correlation, and the multiple abnormality correlations.
4. The method according to claim 1, characterized in that: The determining the second abnormal situation and the fault path sequence based on the first abnormal situation and the abnormal association includes: Determining the abnormal situation directly caused by the first abnormal situation in the abnormal association as the second abnormal situation; Determine a path sequence corresponding to the first abnormal situation in the abnormal association as a fault path sequence; Obtain environmental data; correcting the second abnormal condition based on the environmental data and the abnormal association; The determining of the monitoring strategy based on the first abnormal situation, the second abnormal situation and the fault path sequence includes: A monitoring strategy is determined based on the first abnormal condition, the corrected second abnormal condition, and the fault path sequence.
5. The method according to claim 4, characterized in that The determining of a monitoring strategy based on the first abnormal condition, the corrected second abnormal condition, and the fault path sequence includes: determining abnormality information and first fault information based on the corrected second abnormal condition; Determine the number of the first fault information as the number of faults; Determine the number of the abnormal information as the abnormal number; Calculating the total length of the fault path sequence corresponding to the first abnormal situation; Calculate an abnormality impact value based on the number of faults, the number of abnormalities, and the total length; determining an abnormality level based on the abnormality impact value; A monitoring strategy is determined based on the abnormality level.
6. The method according to claim 5, characterized in that The determining of a monitoring strategy based on the abnormality level includes: Obtaining a monitoring cycle, a first number, a second number, and a third number, wherein the monitoring cycle is a cycle for monitoring the electric wire, the first number is the number of abnormalities in the current monitoring cycle, the second number is the number of monitoring cycles with continuous abnormalities or faults, and the third number is the number of faults in the current monitoring cycle; If the abnormality level is the second abnormality level or the third abnormality level, determining whether the first number is greater than a first preset number and / or whether the second number is greater than a second preset number; If the first number is greater than the first preset number and / or the second number is greater than the second preset number, adjusting the monitoring period based on the first number and the second number; If the abnormality level is the first abnormality level and / or the third number is greater than a third preset number, the monitoring period is adjusted based on a preset weight.
7. An intelligent monitoring device for power transmission and transformation engineering, characterized in that: include: A data acquisition module, used to acquire monitoring data of the electric wire, wherein the monitoring data includes status data and video data; an abnormality determination module, configured to determine a first abnormality based on the monitoring data and corresponding standard data; an abnormality association module, configured to determine a second abnormality and a fault path sequence based on the first abnormality and the abnormality association, wherein the abnormality association includes an association between abnormalities and / or an association between abnormalities and faults, the second abnormality includes at least one abnormality and / or at least one fault, and the fault path sequence includes a path sequence between the first abnormality and the fault; A strategy determination module, configured to determine a monitoring strategy based on the first abnormal situation, the second abnormal situation, and the fault path sequence, wherein the monitoring strategy includes warning information and a monitoring period; The abnormality determination module is further specifically used to determine the first abnormal situation based on the monitoring data and the corresponding standard data, including: determining location information based on the monitoring data; Acquire first standard data based on the location information, where the first standard data is standard data corresponding to the location where the monitoring data is sourced; Determine first abnormal information based on the first standard data and the state data, wherein the first abnormal information includes an abnormal state of the electric wire; Acquire first power data and second power data, wherein the first power data is power data transmitted by the electric wire, and the second power data is actual available power data; Determine second abnormal information based on the first power data and the second power data, wherein the second abnormal information includes abnormal power transmission of the wire; Identify the video data to determine third abnormal information, where the third abnormal information includes abnormal shape of the wire; A first abnormal situation is determined based on the first abnormal information, the second abnormal information, and the third abnormal information.
8. An electronic device, characterized in that: comprising a processor coupled to a memory; The processor is configured to execute a computer program stored in the memory, so that the electronic device executes the method according to any one of claims 1 to 6.
9. A computer-readable storage medium, characterized in that: The method comprises a computer program or an instruction, which, when executed on a computer, causes the computer to execute the method according to any one of claims 1 to 6.
Citation Information
Patent Citations
Network fault diagnosis method and device, network device and storage medium
CN110380907A
Data center intelligent fire-fighting management method, device, equipment and medium
CN117689105A