A coordinated control system for low-voltage power in power distribution network

By designing a collaborative control system for power demand estimation, power supply plan formulation, reactive power compensation processing and power supply quality assessment modules in the medium and low-voltage distribution network, the problems of power supply load regulation and insufficient reactive power compensation are solved, and the power efficiency is improved. The efficiency and reliability of the system promote energy transition and sustainable development.

CN118367563BActive Publication Date: 2024-10-01CHANGCHUN POWER SUPPLY OF JILIN POWER
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202410791003.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-06-19
Publication Date
2024-10-01
Estimated Expiration
2044-06-19

AI Technical Summary

Technical Problem

It is difficult for the existing medium and low-voltage distribution network to accurately grasp and regulate the power supply load in short-term power supply dispatch, resulting in insufficient reliability and economy of power supply. It also lacks efficient reactive power compensation management, which increases the problems of energy loss and reduced operating efficiency. .

Method used

A collaborative control system for medium and low voltage power in the power distribution network is designed, including a power demand estimation module, a power supply plan formulation module, a reactive power compensation processing module and a power supply quality assessment module. Through real-time monitoring and processing of the reactive power compensation of the power supply path demand, optimize power supply solutions to match power supply and demand, reduce energy loss, and evaluate power supply quality.

Benefits of technology

It achieves refined matching of electric energy supply and demand, improves the operating efficiency and economy of the power system, promotes the utilization of renewable energy, reduces the cost of non-renewable energy use, and promotes the development of the power grid in a more efficient, intelligent and environmentally friendly direction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118367563B_ABST
    Figure CN118367563B_ABST
Patent Text Reader

Abstract

The present invention relates to the field of electric power engineering technology, and in particular to a low-voltage power collaborative control system for an electric power distribution network. The present invention compares the demand electric load in a target area during a set time period on the day with the supply electric load of various energy power supply terminals covering the target area in the power supply range, and develops a power supply plan for the target area during the set time period on the day. During the process of supplying power to the target area during the set time period on the day, the reactive power compensation demand of the current power supply path of each target power supply terminal is understood in real time and corresponding reactive power compensation processing is performed, so as to reduce energy loss caused by reactive power flow during the power supply process. After the target area is supplied with power during the set time period on the day, the power supply quality of the target area during the set time period on the day is evaluated based on the reactive power compensation benefit coefficient and the active power matching benefit coefficient, so as to realize a closed loop of power supply dispatching management optimization, thereby promoting the development of power grids in a more efficient, smarter and more environmentally friendly direction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of electric power engineering technology, and in particular to a low voltage power coordinated control system in an electric power distribution network. Background Art

[0002] As the global energy system accelerates its transformation toward renewable and low-carbon energy, the rapid development of smart grid technology has brought unprecedented opportunities for change to the power system, but it is also accompanied by a series of complex challenges. In particular, with the acceleration of urbanization, the power distribution network, as a key link in the power supply chain, has a direct impact on the overall safety, reliability and economy of the power grid. In this process, the medium and low voltage power distribution field is facing the dynamic diversity of large-scale integration of distributed energy and growing energy demand on the user side. How to efficiently integrate distributed energy resources while ensuring grid stability and power quality has become a core issue that the power industry urgently needs to solve.

[0003] In the prior art, there are also some solutions related to monitoring, regulation and management of medium and low voltage distribution networks. For example, the invention patent application of a control method and system for a medium / low voltage AC / DC hybrid distribution network with Chinese patent number CN2022109065542 determines the grid data of the medium / low voltage AC / DC hybrid distribution network, substitutes the grid data into a pre-established centralized optimization model suitable for medium voltage AC / DC hybrid distribution network and a distributed optimization model suitable for low voltage AC / DC hybrid distribution network, obtains the optimal solution for the network loss of the medium voltage AC / DC hybrid distribution network and the power fluctuation of the PCC node of the low voltage substation of the low voltage AC / DC hybrid distribution network, determines the centralized distributed collaborative control strategy of the medium / low voltage AC / DC hybrid distribution network according to the optimal solution, controls the medium / low voltage AC / DC hybrid distribution network with the centralized distributed collaborative control strategy, and realizes the collaborative control of the medium / low voltage AC / DC hybrid distribution network.

[0004] Another invention patent application for a method and system for coordinated control of medium and low voltage distribution networks with Chinese patent number CN2023103877419 constructs a coordinated dispatching framework for medium and low voltage distribution networks containing emerging loads, constructs an optimal dispatching model for medium voltage distribution networks containing EV charging stations, calculates the dispatching results of medium voltage distribution networks, constructs an optimal dispatching model for low voltage distribution networks containing 5G base stations, calculates the dispatching results of low voltage distribution networks, constructs a task allocation model for emerging load operators, calculates the task allocation results of emerging load operators, constructs a benefit allocation model for emerging load operators, calculates the benefit allocation results of emerging load operators, and uses an actual radial grid to verify the effectiveness of the dispatching strategy of medium and low voltage distribution networks containing multiple emerging loads, thereby solving the current problems of insufficient flexible adjustment resources and unclear benefits of emerging loads participating in demand response.

[0005] Although the above schemes propose some solutions for the management of medium and low voltage distribution networks, the existing technologies still have the following limitations, specifically: 1. The existing medium and low voltage distribution networks focus on the evaluation of power supply rather than power supply load in the short-term power supply dispatch analysis of distributed energy. The power supply load, as the total amount of electric power that the power system needs to carry instantly, directly reflects the real-time power consumption rate of users and is an instant indicator for measuring the quality of power services and the efficiency of system operation. In contrast, the power supply involves the total amount of energy transmitted over a period of time. Although it is equally important, for short-term dispatch control, the accurate grasp and regulation of the power supply load is more critical. However, the existing technology is still insufficient for accurate prediction and rapid response mechanism of active power demand, and it is difficult to ensure the reliability and economy of power supply.

[0006] 2. When integrating distributed energy resources to perform short-term power supply scheduling tasks, the existing medium and low voltage distribution networks lack an efficient and timely reactive power compensation management mechanism, resulting in non-optimal distribution of reactive power flow, which in turn increases energy losses during power transmission and reduces the operating efficiency of the entire medium and low voltage distribution network. Summary of the invention

[0007] In order to overcome the shortcomings of the background technology, an embodiment of the present invention provides a low-voltage power cooperative control system in an electric power distribution network, which can effectively solve the problems involved in the above-mentioned background technology.

[0008] The purpose of the present invention can be achieved through the following technical solutions: a low voltage power collaborative control system in an electric power distribution network, comprising: a power demand estimation module, a power supply plan formulation module, a reactive power compensation processing module, a power supply quality assessment module and a cloud database.

[0009] The electricity demand estimation module is connected to the power supply plan formulation module, the power plan formulation module is connected to the reactive power compensation processing module, the reactive power compensation processing module is connected to the power supply quality assessment module, and the cloud database is connected to the power supply plan formulation module and the reactive power compensation processing module respectively.

[0010] The electricity demand estimation module is used to collect the electricity load of each unit time period of each day in the target area in the current season, and estimate the demand electricity load of the target area in the set time period of the day.

[0011] The power supply plan formulation module is used to estimate the power supply load of various energy power supply terminals in the target area covered by the power supply range during the set time period of the day, formulate the power supply plan for the target area during the set time period of the day, and record the various energy power supply terminals participating in the power supply plan as target power supply terminals.

[0012] The reactive power compensation processing module is used to monitor the power parameters of the power supply paths of each target power supply end in real time during the power supply to the target area during the set time period of the day, determine the reactive power compensation requirements of the current power supply paths of each target power supply end, and perform corresponding reactive power compensation processing.

[0013] The power supply quality assessment module is used to evaluate the power supply quality coefficient of the target area during the set time period of the day and provide feedback after the power supply to the target area is completed during the set time period of the day.

[0014] The cloud database is used to store the preset target area backup power load and the preset reasonable threshold value of the power factor of the power supply path of the distribution network.

[0015] Compared with the prior art, the embodiments of the present invention have at least the following advantages or beneficial effects: 1. The present invention develops a power supply plan for a set time period of the day in the target area from the perspective of the supply power load. By conducting a detailed analysis of the demand power load for the set time period of the day in the target area and comprehensively comparing the supply power load of various energy power supply terminals covering the target area, the present invention achieves refined matching of power supply and demand and high-quality allocation of resources, thereby improving the overall operational efficiency and economy of the power system.

[0016] 2. In the process of formulating the power supply plan for the set time period of the target area on the same day, the present invention adheres to the scheduling order of renewable energy power supply end first and non-renewable energy power supply end later, which not only promotes the effective use of renewable energy, but also reduces the cost of using non-renewable energy, provides a reliable power supply for the target area, and realizes energy transformation and sustainable development.

[0017] 3. The present invention understands the reactive power compensation requirements of the power supply paths of each target power supply end in real time and performs corresponding reactive power compensation processing during the power supply process to the target area during the set time period of the day, thereby reducing the energy loss caused by the flow of reactive power during the power supply process, thereby improving the efficiency and quality of power supply to user terminals in the target area.

[0018] 4. After the present invention completes power supply to the target area during the set time period of the day, the power supply quality of the target area during the set time period of the day is evaluated based on the reactive power compensation benefit coefficient and the active power matching benefit coefficient, thereby realizing a closed loop of power supply dispatching management optimization, thereby helping to promote the development of the power grid towards a more efficient, smarter and more environmentally friendly direction. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] The present invention is further described using the accompanying drawings, but the embodiments in the accompanying drawings do not constitute any limitation to the present invention. A person skilled in the art can obtain other drawings based on the following drawings without creative work.

[0020] Figure 1 It is a schematic diagram of module connection of the present invention. DETAILED DESCRIPTION

[0021] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0022] Reference Figure 1 As shown, the present invention provides a low-voltage power collaborative control system in an electric power distribution network, comprising: a power demand estimation module, a power supply plan formulation module, a reactive power compensation processing module, a power supply quality assessment module and a cloud database.

[0023] The electricity demand estimation module is connected to the power supply plan formulation module, the power plan formulation module is connected to the reactive power compensation processing module, the reactive power compensation processing module is connected to the power supply quality assessment module, and the cloud database is connected to the power supply plan formulation module and the reactive power compensation processing module respectively.

[0024] The electricity demand estimation module is used to collect the electricity load of each unit time period of each day in the target area in the current season, and estimate the electricity load demand of the target area in the set time period of the current day.

[0025] It should be noted that the electricity load of each unit time period on each day of the above-mentioned target area in the current season is collected from the power grid server corresponding to the target area.

[0026] Specifically, the estimated power load demand for the set time period of the target area on the day includes: extracting the power load of each unit time period of the set time period of each day in the target area in the current season, and accumulating the power load of each day in the target area in the current season corresponding to the set time period. , is the number of each historical day in the season, , according to the formula Get the power demand load of the target area during the set time period of the day, The historical number of days in the season.

[0027] The power supply plan formulation module is used to estimate the power supply load of various energy power supply terminals in the target area covered by the power supply range during the set time period of the day, formulate a power supply plan for the target area during the set time period of the day, and record the various energy power supply terminals participating in the power supply plan as target power supply terminals.

[0028] Specifically, the estimated power load supplied by various energy power supply terminals in the target area covered by the power supply range during the set time period of the day includes: screening the various energy power supply terminals in the target area covered by the power supply range into renewable energy power supply terminals and non-renewable energy power supply terminals according to energy type.

[0029] It should be noted that the above-mentioned energy power supply terminals include but are not limited to solar power supply terminals, wind power supply terminals, hydropower power supply terminals, biomass power supply terminals, fuel power supply terminals, etc.

[0030] Collect the energy output of each non-renewable energy supply terminal for each day of the season corresponding to the set time period and electricity production, of which is the number of each non-renewable energy supply terminal, , taking the ratio of power generation to energy generation as the power generation conversion rate, constructing a coordinate system with date sorting as the horizontal axis and power generation conversion rate as the vertical axis, marking the power generation conversion rate of each non-renewable energy power supply end in the corresponding set time period in the current season in the form of coordinates in the coordinate system, drawing the power generation conversion curve of each non-renewable energy power supply end in the current season and importing it into Matlab software to generate its corresponding fitting function, substituting the date sorting of the day into the fitting function to obtain the estimated power generation conversion rate of each non-renewable energy power supply end in the set time period of the day , and then by the formula Get the power supply load of each non-renewable energy supply terminal during the set time period of the day, where The span length of the set time period.

[0031] It should be noted that the energy production and power generation output of each non-renewable energy power supply terminal corresponding to the set time period on each historical day of the season are collected from the internal data recording terminal of each non-renewable energy power supply terminal.

[0032] Collect the energy output, power generation output and monitoring values ​​of each capacity quantitative impact indicator of each renewable energy power supply end for the set time period on each historical day of the season, and obtain the power generation conversion rate of each renewable energy power supply end for the set time period on each historical day of the season , is the number of each renewable energy power supply terminal, , analyze the estimated energy production of each renewable energy power supply terminal during the set time period of the day , according to the formula The power supply load of each renewable energy power supply terminal during the set time period of the day is obtained.

[0033] It should be noted that the energy output, power generation output and monitoring values ​​of various production capacity quantitative impact indicators of each renewable energy power supply terminal corresponding to the set time period on each historical day of the season are collected from the internal data recording terminal of each renewable energy power supply terminal.

[0034] It should also be noted that the above-mentioned quantitative impact indicators of the production capacity of each renewable energy power supply end refer to parameters expressed in numerical form that can specifically quantify and evaluate the impact of various factors on the power generation of renewable energy.

[0035] Exemplarily, the quantitative influencing indicators of production capacity at the solar power supply end include sunshine hours, irradiance, temperature coefficient, photovoltaic module efficiency and irradiation area; the quantitative influencing indicators of production capacity at the wind power supply end include wind speed, wind turbine efficiency, capacity factor and turbulence intensity; the quantitative influencing indicators of production capacity at the hydropower supply end include water head height, flow rate and utilization hours; the quantitative influencing indicators of production capacity at the biomass energy power supply end include biomass raw material supply and biomass fuel density; the quantitative influencing indicators of production capacity at the geothermal energy power supply end include geothermal fluid temperature and geothermal well output.

[0036] Specifically, the estimated energy production of each renewable energy power supply terminal in the set time period of the day is analyzed, including: obtaining the energy change production of each renewable energy power supply terminal in the set time period corresponding to each historical day of the season and its adjacent days And the monitoring change value of each capacity quantitative impact indicator , is the number of each capacity quantitative impact indicator, , according to the formula Get the energy production sensitivity corresponding to each capacity quantitative impact index of each renewable energy power supply end in the current season, and set the basic energy production impact weight corresponding to each capacity quantitative impact index of each renewable energy power supply end , calculate the average energy output of each renewable energy power supply end for the set time period on a single day in the season and the average monitoring value of each capacity quantitative impact indicator, which are recorded as .

[0037] It should be noted that the setting of the basic energy production impact weights corresponding to the quantitative impact indicators of each capacity of the above-mentioned renewable energy power supply end is based on a comprehensive consideration of energy characteristics, environmental benefits, economic factors, resource renewability and sustainability. For details, please refer to the IEA's renewable energy integration assessment and renewable energy indicators, and the above requirements .

[0038] Collect the monitoring values ​​of each capacity quantitative impact indicator of each renewable energy power supply terminal during the set time period of the day , according to the formula u ′ r = u ¯ r + ∑ g = 1 d [ ( h ′ rg − h ¯ rg ) * φ rg * δ rg ] Get the estimated energy production of each renewable energy power supply terminal during the set time period of the day.

[0039] The embodiment of the present invention develops a power supply plan for a set time period of the day in the target area from the perspective of supplied power load. By conducting a detailed analysis of the demand power load for the set time period of the day in the target area and comprehensively comparing the supply power loads of various energy power supply terminals whose power supply ranges cover the target area, refined matching of power supply and demand and high-quality allocation of resources are achieved, thereby improving the overall operational efficiency and economy of the power system.

[0040] Specifically, the power supply plan for the target area during the set time period on the day includes: extracting a preset target area backup power load from a cloud database, and using the cumulative value of the backup power load and the demand power load for the target area during the set time period on the day as a reference power load.

[0041] The supply load being greater than or equal to the reference load is used as a condition for formulating the power supply plan.

[0042] Create an energy power supply terminal sequence, arrange each renewable energy power supply terminal as the first tier before the energy power supply terminal sequence, arrange each non-renewable energy power supply terminal as the second tier after the first tier, and sort each energy power supply terminal in the first and second tiers according to the supply load value from large to small, and compare whether the supply load of the first-ranked energy power supply terminal in the energy power supply terminal sequence meets the power supply plan formulation conditions. If it meets, the first-ranked energy power supply terminal is required to supply power to the user terminal in the target area with the reference load. If not, compare whether the cumulative value of the supply load of the first and second-ranked energy power supply terminals in the energy power supply terminal sequence meets the power supply plan formulation conditions. If it meets, the first and second-ranked energy power supply terminals are required to successively add the supply load to the reference load to supply power to the user terminal in the target area, and so on, so as to formulate a power supply plan for the target area for the set time period on the day.

[0043] In the process of formulating the power supply plan for the set time period of the target area on the same day, the embodiment of the present invention adheres to the scheduling order of renewable energy power supply end first and non-renewable energy power supply end later, which not only promotes the effective utilization of renewable energy, but also reduces the cost of using non-renewable energy, provides a reliable power supply for the target area, and realizes energy transformation and sustainable development.

[0044] The reactive power compensation processing module is used to monitor the power parameters of the power supply paths of each target power supply end in real time during the power supply to the target area during the set time period of the day, determine the reactive power compensation requirements of the current power supply paths of each target power supply end, and perform corresponding reactive power compensation processing.

[0045] Specifically, the power parameters include the power factor, active power and reactive power of the transformer area and each load area.

[0046] It should be noted that the power parameters of the power supply paths of the above-mentioned target power supply ends are obtained in real time through power monitors deployed on the corresponding monitoring nodes in the transformer area and each load area of ​​the power supply path of each target power supply end.

[0047] Specifically, the determination of the reactive power compensation demand of the current power supply path of each target power supply end includes: extracting the power factors of the transformer area and each load area in the power parameters of the current power supply path of each target power supply end, respectively recorded as ,in is the number of each target power supply terminal, , is the number of each load zone, , and the preset reasonable threshold value of the power factor of the distribution network power supply path stored in the cloud database To compare, , The judgment conditions 1 and 2 are respectively used as the target power supply end power supply path whether there is a reactive power compensation demand. If the power supply path of a target power supply end meets any one of the judgment conditions 1 or 2, it is judged that there is a reactive power compensation demand in the power supply path of the target power supply end, and the target power supply end is recorded as the compensation power supply end, and then the reactive power compensation demand of each current target power supply end power supply path is judged, and each current compensation power supply end is obtained.

[0048] Specifically, the reactive power compensation processing for the power supply path of each compensation power supply end includes: arbitrarily selecting a compensation power supply end, if the power supply path of the compensation power supply end meets the judgment condition 1, obtaining the voltage value of each monitoring time point in the current monitoring time period of the transformer area of ​​the power supply path of the compensation power supply end, drawing the current voltage change curve of the transformer area of ​​the power supply path of the compensation power supply end and calculating its slope value , extract the active power of the transformer area in the power parameters of the current power supply path of the compensation power supply end and reactive power , calculate the reactive compensation power of the transformer area of ​​the current compensation power supply path , .

[0049] If the power supply path of the compensation power supply end meets judgment condition 2, the compensation load areas of the power supply path of the compensation power supply end are screened out, and the reactive supplementary power of each compensation load area of ​​the power supply path of the compensation power supply end is obtained in accordance with the reactive supplementary power analysis method of the transformer area of ​​the current power supply path of the compensation power supply end.

[0050] If the power supply path of the compensation power supply end satisfies judgment conditions 1 and 2 at the same time, the reactive supplementary power of the transformer area of ​​the current power supply path of the compensation power supply end is calculated. And the reactive power of each compensation load area , is the number of each compensation load zone, , requiring the current power supply path transformer area of ​​the compensation power supply end to be Reactive power compensation is performed, and each compensation load area is Reactive power compensation is performed, where is the number of load zones.

[0051] It should be noted that the reactive power compensation processing of the compensation power supply end power supply path that meets judgment condition 1 is a centralized compensation mode, and the reactive power compensation processing of the compensation power supply end power supply path that meets judgment condition 2 is a partitioned compensation mode. When the compensation power supply end power supply path meets judgment conditions 1 and 2 at the same time, it indicates that this compensation power supply end power supply path needs to consider centralized compensation to cope with a large range of reactive power demands, and also needs to use partitioned compensation to finely manage the reactive power in the local area. At this time, the reactive power compensation measures in the transformer area have a direct impact on the reactive power demands of the load areas behind. Therefore, the reactive power compensation scheme in the load area must take into account the reactive compensation effect of the upstream transformer area to avoid over-compensation or under-compensation and achieve the optimal allocation of reactive power.

[0052] The embodiment of the present invention understands the reactive power compensation requirements of the power supply paths of each target power supply end in real time and performs corresponding reactive power compensation processing during the power supply process to the target area during the set time period of the day, thereby reducing the energy loss caused by the flow of reactive power during the power supply process, thereby improving the efficiency and quality of power supply to user terminals in the target area.

[0053] The power supply quality evaluation module is used to evaluate the power supply quality coefficient of the target area in the set time period of the day and provide feedback after the power supply to the target area is completed in the set time period of the day.

[0054] Specifically, the power supply quality coefficient of the target area during the set time period on the day of evaluation includes: obtaining the actual power load at each set time point during the set time period on the day of the target area; and supply electrical loads , It is the number of each set time point within the set time period of the day. , analyze the active power matching benefit coefficient of the target area during the set time period of the day , and its calculation formula is: , Set the number of time points within the set time period for the day, is the preset reasonable electric load deviation threshold, is a natural constant.

[0055] Get the reference power factor of each target power supply end power supply path at each set time point within the set time period of the day , analyze the reactive power compensation benefit coefficient of the target area during the set time period of the day , and its calculation formula is: .

[0056] The product of the reactive power compensation benefit coefficient and the active power matching benefit coefficient is used as the power supply quality coefficient of the target area during the set time period of the day.

[0057] Specifically, the The acquisition process is as follows: obtain the power factors of the transformer area and each load area of ​​the power supply path of each target power supply end at each set time point within the set time period of the day, and select the minimum value of the power factors of the transformer area and each load area as the reference power factor.

[0058] After the embodiment of the present invention completes power supply to the target area during the set time period of the day, the power supply quality of the target area during the set time period of the day is evaluated based on the reactive power compensation benefit coefficient and the active power matching benefit coefficient, thereby realizing a closed loop of power supply dispatching management optimization, thereby helping to promote the development of the power grid towards a more efficient, smarter and more environmentally friendly direction.

[0059] The cloud database is used to store the preset target area backup power load and the preset reasonable threshold value of the power factor of the power supply path of the distribution network.

[0060] The data sources in the cloud database of this embodiment are shown in Table 1 below.

[0061] Table 1

[0062]

[0063] The above contents are merely examples and explanations of the structure of the present invention. The technicians in this technical field may make various modifications or additions to the specific embodiments described or replace them in a similar manner. As long as they do not deviate from the structure of the invention or exceed the scope defined by the present invention, they should all fall within the protection scope of the present invention.

Claims

1. A low voltage power coordinated control system for an electric power distribution network, characterized in that ,include: The electricity demand estimation module is used to collect the electricity load of each unit time period of each day in the target area in the current season, and estimate the demand electricity load of the target area in the set time period of the day; The power supply plan formulation module is used to estimate the supply load of various energy power supply terminals in the target area covered by the power supply range during the set time period of the day, formulate the power supply plan for the target area during the set time period of the day, and record the various energy power supply terminals participating in the power supply plan as each target power supply terminal; The reactive power compensation processing module is used to monitor the power parameters of the power supply paths of each target power supply end in real time during the power supply to the target area during the set time period of the day, determine the reactive power compensation requirements of the current power supply paths of each target power supply end, and perform corresponding reactive power compensation processing; The power supply quality assessment module is used to assess the power supply quality coefficient of the target area during the set time period of the day and provide feedback after the power supply to the target area is completed during the set time period of the day; A cloud database is used to store preset target area backup power loads and preset reasonable thresholds of power factors of power supply paths of the distribution network; The estimated power load supplied by various energy power supply terminals in the target area covered by the power supply range during the set time period on the day includes: screening various energy power supply terminals in the target area covered by the power supply range into various renewable energy power supply terminals and various non-renewable energy power supply terminals according to energy types; Collect the energy output of each non-renewable energy supply terminal for each day of the season corresponding to the set time period and electricity production, of which is the number of each non-renewable energy supply terminal, , taking the ratio of power generation to energy generation as the power generation conversion rate, constructing a coordinate system with date sorting as the horizontal axis and power generation conversion rate as the vertical axis, marking the power generation conversion rate of each non-renewable energy power supply end in the corresponding set time period in the current season in the form of coordinates in the coordinate system, drawing the power generation conversion curve of each non-renewable energy power supply end in the current season and importing it into Matlab software to generate its corresponding fitting function, substituting the date sorting of the current day into the fitting function to obtain the estimated power generation conversion rate of each non-renewable energy power supply end in the set time period of the current day , and then by the formula Get the power supply load of each non-renewable energy supply end during the set time period of the day, where To set the span of the time period; Collect the energy output, power generation output and monitoring values ​​of each capacity quantitative impact indicator of each renewable energy power supply end for the set time period on each day of the season history, and obtain the power generation conversion rate of each renewable energy power supply end for the set time period on each day of the season history , is the number of each renewable energy power supply terminal, , analyze the estimated energy production of each renewable energy power supply terminal during the set time period of the day , according to the formula Get the power supply load of each renewable energy power supply terminal during the set time period of the day, is the number of each historical day in the season, , is the historical number of days in the season; Analyze the estimated energy production of each renewable energy power supply terminal during the set time period of the day, including: obtaining the energy change production of each renewable energy power supply terminal during the set time period corresponding to each historical day of the season and its adjacent days And the monitoring change value of each capacity quantitative impact indicator , is the number of each capacity quantitative impact indicator, , according to the formula Get the energy production sensitivity corresponding to each capacity quantitative impact index of each renewable energy power supply end in the current season, and set the basic energy production impact weight corresponding to each capacity quantitative impact index of each renewable energy power supply end , calculate the average energy output of each renewable energy power supply end for the set time period on a single day in the season and the average monitoring value of each capacity quantitative impact indicator, which are recorded as ; Collect the monitoring values ​​of each capacity quantitative impact indicator of each renewable energy power supply terminal during the set time period of the day , according to the formula Obtain the estimated energy production of each renewable energy power supply terminal during a set time period of the day; The formulating of the power supply plan for the target area during the set time period on the day includes: extracting the preset target area standby power load from the cloud database, and using the cumulative value of the preset target area standby power load and the target area demand power load during the set time period on the day as the reference power load; The supply load is greater than or equal to the reference load as a condition for formulating the power supply plan; Create an energy power supply terminal sequence, arrange each renewable energy power supply terminal as the first echelon before the energy power supply terminal sequence, arrange each non-renewable energy power supply terminal as the second echelon after the first echelon, and sort each energy power supply terminal in the first and second echelons according to the supply load value from large to small, and compare whether the supply load of the first-order energy power supply terminal in the energy power supply terminal sequence meets the power supply plan formulation conditions. If it meets, the first-order energy power supply terminal is required to supply power to the target area user terminal with the reference load. If not, compare whether the cumulative value of the supply load of the first and second-order energy power supply terminals in the energy power supply terminal sequence meets the power supply plan formulation conditions. If it meets, the first and second-order energy power supply terminals are required to successively superimpose the supply load to the reference load to supply power to the target area user terminal, and so on, so as to formulate a power supply plan for the target area for the set time period on the day; The determination of the reactive power compensation requirements of the current power supply paths of each target power supply end includes: extracting the power factors of the transformer area and each load area in the power parameters of the current power supply paths of each target power supply end, and recording them as ,in is the number of each target power supply terminal, , is the number of each load zone, , and the preset reasonable threshold value of the power factor of the distribution network power supply path stored in the cloud database To compare, , As the judgment conditions 1 and 2 of whether the power supply path of the target power supply end has reactive power compensation demand, respectively, if the power supply path of a target power supply end satisfies any one of the judgment conditions 1 or 2, it is judged that the power supply path of the target power supply end has reactive power compensation demand, and the target power supply end is recorded as the compensation power supply end, and then the reactive power compensation demand of the current power supply path of each target power supply end is judged, and each current compensation power supply end is obtained; The corresponding reactive power compensation processing includes: arbitrarily selecting a certain compensation power supply end, if the power supply path of the compensation power supply end meets the judgment condition 1, obtaining the voltage value of each monitoring time point in the current monitoring time period of the transformer area of ​​the power supply path of the compensation power supply end, drawing the current voltage change curve of the transformer area of ​​the power supply path of the compensation power supply end and calculating its slope value , extract the active power of the transformer area in the power parameters of the current power supply path of the compensation power supply end and reactive power , calculate the reactive compensation power of the transformer area of ​​the current compensation power supply path , ; If the power supply path of the compensation power supply end meets judgment condition 2, the compensation load areas of the power supply path of the compensation power supply end are screened out, and the reactive supplementary power of each compensation load area of ​​the power supply path of the compensation power supply end is obtained in accordance with the reactive supplementary power analysis method of the transformer area of ​​the current power supply path of the compensation power supply end; If the power supply path of the compensation power supply end satisfies judgment conditions 1 and 2 at the same time, the reactive supplementary power of the transformer area of ​​the current power supply path of the compensation power supply end is calculated. And the reactive supplementary power of each compensation load area , is the number of each compensation load zone, , requiring the current compensation power supply end power supply path transformer area to Reactive power compensation is performed, and each compensation load area is Reactive power compensation is performed, where is the number of load zones; The power supply quality coefficient of the target area during the set time period of the day is evaluated, including: obtaining the actual power load at each set time point during the set time period of the target area on the day and supply electrical loads , It is the number of each set time point within the set time period of the day. , analyze the active power matching benefit coefficient of the target area during the set time period of the day , and its calculation formula is: , Set the number of time points within the set time period for the day, is the preset reasonable electric load deviation threshold, is a natural constant; Get the reference power factor of each target power supply end power supply path at each set time point within the set time period of the day , analyze the reactive power compensation benefit coefficient of the target area during the set time period of the day , and its calculation formula is: ; The product of the reactive power compensation benefit coefficient and the active power matching benefit coefficient is used as the power supply quality coefficient of the target area during the set time period of the day; Said The acquisition process is as follows: obtain the power factors of the transformer area and each load area of ​​the power supply path of each target power supply end at each set time point within the set time period of the day, and select the minimum value of the power factors of the transformer area and each load area as the reference power factor.

2. A low voltage power coordinated control system in an electric power distribution network according to claim 1, characterized in that: The estimated target area's demand load for the set time period on the day includes: extracting the load of each unit period of the set time period of each day in the target area's history of the season, and accumulating the load of each unit period of the set time period of each day in the target area's history of the season. , is the number of each historical day in the season, , according to the formula Get the power demand load of the target area during the set time period of the day, The historical number of days in the season.

3. A low voltage power coordinated control system for an electric power distribution network according to claim 1, characterized in that: The power parameters include the power factor, active power and reactive power of the transformer area and each load area.

Citation Information

Patent Citations

  • Control method and system for medium / low-voltage AC / DC hybrid power distribution network

    CN115360776A

  • Method and system for cooperative control of medium and low voltage distribution network

    CN117039834A

  • Control method for adjusting reactive voltage of power distribution network to ensure electric energy quality of low-voltage region

    CN107565575A

  • Microgrid electric energy quality and energy cooperative control method based on power generation power and load prediction

    CN109713663A

  • Urban power grid reactive voltage dynamic optimization control method based on zone control

    CN117477541A