A tunnel joint anti-drainage structure and construction method thereof
By combining the back-attached waterstop and the cross-section waterproof structure, water pressure is used to achieve self-locking, which solves the problems of waterstop deflection and waterproof function failure, and achieves stronger tunnel waterproofing effect and construction efficiency.
Patent Information
- Application Number
- CN202410873525.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-02
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2044-07-02
AI Technical Summary
In tunnel projects, the waterstop is deflected due to the flow and vibration process of concrete, which makes it impossible to ensure anchorage and causes the waterproof function to fail. Moreover, it is difficult to control the deflection of the buried waterstop and the installation position is inaccurate, which affects driving. Safety.
The back-mounted waterstop is combined with the cross-section waterproof structure. The second waterproof and drainage structure uses internal water pressure to achieve self-locking. The setting of the buried waterstop is cancelled, and a double drainage channel design is added and set at the joints. Cross-section waterproof structure to enhance waterproofing effect.
It effectively avoids the problems of waterstop deflection and deformation, improves the waterproofing effect of the tunnel, reduces construction steps and costs, and ensures driving safety at the same time.
Smart Images

Figure CN118407789B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a tunnel joint waterproofing and drainage structure and a construction method thereof. Background Art
[0002] In tunnel construction, construction joints are formed due to the segmented pouring of concrete; deformation joints are set to adapt to the different settlements of the structure. In order to prevent water seepage in construction joints and deformation joints, waterstops are arranged at the concrete joints to prevent water leakage. Waterstops are usually used in combination with back-attached waterstops and embedded waterstops to further enhance the waterproof effect of the tunnel.
[0003] During the pouring of concrete, the waterstop will also shift due to the flow and vibration of the concrete, so it is impossible to ensure that the anchor end of the waterstop is completely anchored in the concrete, causing the waterstop to fail to perform its waterproof function. After the waterstop shifts, the concrete at the joint becomes thinner, which is easy to cause the "block drop" phenomenon, seriously affecting driving safety; among them, the embedded rubber waterstop is the most difficult to control the offset and deformation during the construction process, and it is impossible to accurately determine whether the installation position of the waterstop is accurate after the pouring is completed. In the installation process of the waterstop, the waterstop is mainly fixed by a fixed bracket. The fixed bracket needs to be bent and processed, which consumes materials, increases labor hours, and affects the progress of the project. Summary of the invention
[0004] The purpose of the present invention is to provide a tunnel joint drainage structure and a construction method thereof, so as to solve the problems existing in the above-mentioned prior art, so that the back-sticked waterstop belt will not be offset, the cross-sectional waterproof structure is adopted to further enhance the waterproof effect, the setting of the buried waterstop belt is cancelled, and the deformation and offset of the buried waterstop belt caused by construction are avoided.
[0005] To achieve the above object, the present invention provides the following solutions:
[0006] The present invention provides a tunnel joint anti-drainage structure, comprising: a back-sticked waterstop and a cross-sectional waterproof structure, the back-sticked waterstop comprises a waterstop body, a first anti-drainage structure and a second anti-drainage structure, the first anti-drainage structure and the second anti-drainage structure are both arranged on the waterstop body, the first anti-drainage structure and the second anti-drainage structure are respectively connected to the drainage pipeline, the second anti-drainage structure can utilize the internal water pressure to achieve self-locking with the concrete, and the cross-sectional waterproof structure is located at the joint.
[0007] Preferably, there are two second anti-drainage structures, and the two second anti-drainage structures are respectively located on both sides of the first anti-drainage structure.
[0008] Preferably, the first anti-drainage structure is a first U-shaped groove.
[0009] Preferably, two protrusions are provided at the opening of the first U-shaped groove, and the maximum gap between the two protrusions is 5 mm.
[0010] Preferably, the second anti-drainage structure is a second U-shaped groove, a first water-permeable structure is provided at the opening of the second U-shaped groove, and the first water-permeable structure and the second anti-drainage structure form a first cavity structure.
[0011] Preferably, the second anti-drainage structure includes a first connecting part and a second connecting part, the first connecting part is semicircular, one end of the second connecting part is connected to one end of the first connecting part, there is a gap between the other end of the second connecting part and the other end of the first connecting part, a second water-permeable structure is arranged in the gap, and the second water-permeable structure and the second anti-drainage structure form a second cavity structure.
[0012] Preferably, the cross-sectional waterproof structure includes a waterproof layer made of a cement-based permeable crystalline waterproof material.
[0013] Preferably, the cross-sectional waterproof structure further comprises a butyl waterproof tape, and the butyl waterproof tape is located on the waterproof layer.
[0014] Preferably, the material of the back-stick waterstop includes the following components: 38%~42% of styrene-ethylene-butylene-styrene block copolymer, 13%~17% of styrene-butadiene-styrene block copolymer, 9%~11% of polypropylene, 28%~32% of cyclohexane oil, 8%~10% of calcium carbonate, 0.8%~1.2% of antioxidant and 4.5%~5.5% of other additives.
[0015] The present invention also provides a construction method for the tunnel joint drainage structure, comprising the following steps: determining the installation position of the back-sticking waterstop before construction, and cleaning the installation position to ensure that the surface of the back-sticking waterstop and the installation position are flat, and cutting the required size of the back-sticking waterstop according to the actual required size; laying a circle of the back-sticking waterstop along the outer edge of the tunnel cross section, and fixing the position of the back-sticking waterstop with a second lining mold to prevent the back-sticking waterstop from moving during the concrete pouring process, and pouring the concrete after it is firmly fixed; removing the second lining mold after the concrete is solidified, applying a cement-based penetrating crystalline waterproof material on the concrete surface below the back-sticking waterstop, applying a layer of butyl waterproof tape after the cement-based penetrating crystalline waterproof material is dry, and tearing off the isolation film of the butyl waterproof tape before the next stage of pouring to complete the installation.
[0016] Compared with the prior art, the present invention has achieved the following technical effects:
[0017] The present invention optimizes the design of the structure of the back-sticking waterstop, increases the drainage function, realizes the double drainage channel design, and uses the internal water pressure to enhance the compression between the back-sticking waterstop and the concrete while draining water in the second drainage structure to realize the self-locking function; a cross-sectional waterproof structure is set at the joint to further enhance the waterproof effect of the tunnel. Through the above structure, the setting of the buried waterstop is eliminated, and the deformation and offset of the buried waterstop caused by the construction are avoided, the construction steps of the waterstop are reduced, and the construction cost is reduced, while the driving safety of the tunnel is also effectively guaranteed. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0019] Figure 1 This is a schematic diagram of the tunnel joint drainage structure of the present invention;
[0020] Figure 2 This is a schematic diagram of the back-sticking waterstop of the present invention (Example 1);
[0021] Figure 3 A schematic diagram of the water seepage direction of the second anti-drainage structure of the back-sticking waterstop of the present invention (Example 1);
[0022] Figure 4 A schematic diagram of the water pressure direction in the second water-proof and drainage structure of the back-sticking waterstop of the present invention (Example 1);
[0023] Figure 5 This is a schematic diagram of the back-sticking waterstop of the present invention (Example 2);
[0024] Figure 6 A schematic diagram of the water seepage direction of the second anti-drainage structure of the back-sticking waterstop of the present invention (Example 2);
[0025] Figure 7 A schematic diagram of the water pressure direction in the second water-proof and drainage structure of the back-sticking waterstop of the present invention (Example 2);
[0026] In the figure: 1-back-sticked waterstop, 2-cross-section waterproof structure, 3-waterstop body, 4-first waterproof and drainage structure, 5-second waterproof and drainage structure, 6-protrusion, 7-first permeable structure, 8-first cavity structure, 9-second permeable structure, 10-second cavity structure, 11-secondary lining, 12-waterproof board, 13-non-woven fabric, 14-initial support, 15-joint. DETAILED DESCRIPTION
[0027] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0028] The purpose of the present invention is to provide a tunnel joint drainage structure and a construction method thereof, so as to solve the problems existing in the above-mentioned prior art, so that the back-sticked waterstop belt will not be offset, the cross-sectional waterproof structure is adopted to further enhance the waterproof effect, the setting of the buried waterstop belt is cancelled, and the deformation and offset of the buried waterstop belt caused by construction are avoided.
[0029] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.
[0030] Embodiment 1
[0031] like Figures 1 to 4 As shown, this embodiment provides a tunnel joint drainage structure, including: a back-attached waterstop 1 and a cross-sectional waterproof structure 2, the back-attached waterstop 1 is arranged close to the water-facing surface of the structure, the back-attached waterstop 1 is located on the secondary lining 11, and a waterproof board 12, a non-woven fabric 13 and an initial support 14 are arranged in sequence above the back-attached waterstop 1, the back-attached waterstop 1 includes a waterstop body 3, a first drainage structure 4 and a second drainage structure 5, the first drainage structure 4 and the second drainage structure 5 are both arranged on the waterstop body 3, the first drainage structure 4 and the second drainage structure 5 are respectively connected to the drainage pipeline, the second drainage structure 5 can use the internal water pressure to achieve self-locking with the concrete, and the cross-sectional waterproof structure 2 is located at the joint 15. This embodiment optimizes the design of the structure of the back-sticking waterstop 1, adds drainage function, realizes the double drainage channel design, and uses the internal water pressure to enhance the compression between the back-sticking waterstop 1 and the concrete to realize the self-locking function while draining water in the second drainage structure 5; a cross-sectional waterproof structure 2 is set at the joint 15 to further enhance the waterproof effect of the tunnel. Through the above structure, the setting of the buried waterstop is cancelled, and the deformation and offset of the buried waterstop caused by the construction are avoided, the construction steps of the waterstop are reduced, and the construction cost is reduced, while the driving safety of the tunnel is effectively guaranteed.
[0032] Specifically, in this embodiment, there are two second anti-drainage structures 5, and the two second anti-drainage structures 5 are respectively located on both sides of the first anti-drainage structure 4 and are symmetrically arranged; the first anti-drainage structure 4 is a first U-shaped groove; two protrusions 6 are arranged at the opening of the first U-shaped groove, and the maximum gap between the two protrusions 6 is 5 mm to prevent concrete from entering during the pouring process.
[0033] In this embodiment, the second drainage structure 5 is a second U-shaped groove, and a first permeable structure 7 is arranged at the opening of the second U-shaped groove. The first permeable structure 7 is preferably geotextile or filter cotton. The first permeable structure 7 has the function of blocking concrete and has good permeability. The first permeable structure 7 prevents the concrete from flowing into and blocking the second drainage structure 5 during the pouring process. The first permeable structure 7 and the second drainage structure 5 form a first cavity structure 8.
[0034] When there is a small amount of water and the water pressure is low, most of the water will be discharged along the first drainage structure 4 in the middle of the back-sticking waterstop 1, and a small amount of water will seep out along the contact surface between the back-sticking waterstop 1 and the concrete (the direction of water seepage is as follows: Figure 3 As shown), when water passes through the second anti-drainage structure 5 on both sides, the first permeable structure 7 will absorb part of the water first. When the first permeable structure 7 is full of water, due to the partial adhesion between the back-attached waterstop 1 and the concrete, the water will not penetrate along the direction of the back-attached waterstop 1 and the concrete. The seeping water will flow along the first permeable structure 7 first, and finally gather in the second anti-drainage structure 5 on both sides, and then be discharged through the drainage pipe connected to the second anti-drainage structure 5; so that the back-attached waterstop 1 has a double drainage effect. When the water pressure is high, the second anti-drainage structure 5 at both ends cannot quickly drain the water, and the water pressure in the second cavity structure 10 at both ends will exert pressure on the second anti-drainage structure 5 (such as Figure 4 As shown), the pressing force between the outer surface of the second drainage structure 5 at both ends and the concrete is increased, thereby enhancing the waterproof performance of the back-sticked waterstop 1.
[0035] In this embodiment, the material of the back-sticking waterstop 1 includes the following components: 38%~42% of styrene-ethylene-butylene-styrene block copolymer (SEBS), 13%~17% of styrene-butadiene-styrene block copolymer (SBS), 9%~11% of polypropylene (PP), 28%~32% of cyclohexane oil, 8%~10% of calcium carbonate, 0.8%~1.2% of antioxidant and 4.5%~5.5% of other additives; preferably 41% of styrene-ethylene-butylene-styrene block copolymer, 14% of styrene-butadiene-styrene block copolymer, 11% of polypropylene, 29% of cyclohexane oil, 9% of calcium carbonate, 1% of antioxidant and 5% of other additives.
[0036] Table 1 Physical and mechanical properties of materials of back-stick waterstop
[0037]
[0038] In this embodiment, the material used for the back-sticking waterstop 1 has the characteristics of high elasticity and high strength of rubber and can be extruded. The back-sticking waterstop 1 made of this material can ensure that the back-sticking waterstop 1 remains horizontal without relying on external support during the construction process, especially during the pouring and vibration of concrete. While ensuring that the waterproof performance is not affected, it reduces the difficulty of installing the waterstop and reduces the cost required for the fixing bracket.
[0039] In this embodiment, the cross-sectional waterproof structure 2 includes a waterproof layer made of cement-based permeable crystallization waterproof material and a butyl waterproof tape, and the butyl waterproof tape is located on the waterproof layer. After the waterproof layer made of cement-based permeable crystallization waterproof material reacts with water, the active chemical substances have strong permeability, and can use water as a carrier to penetrate deeply into the internal pores of cement concrete, prompting the unhydrated cement particles to undergo chemical reactions, generating a large number of needle-shaped crystals, filling and closing the capillary pores, and having excellent waterproof and anti-seepage properties. The butyl waterproof tape is laid on the waterproof layer and the concrete base surface and quickly and tightly combined with them, truly achieving an "integrated" effect of firm bonding and no water leakage, and can effectively combine the joints 15 formed by pouring into one, so that it itself has a good waterproof effect, thereby enhancing the waterproof effect of the entire waterproof system.
[0040] By optimizing the structure of the back-stick waterstop 1, it has dual drainage and water pressure self-locking functions, so that the waterproof effect of the back-stick waterstop 1 is effectively improved; by optimizing the material of the back-stick waterstop 1, the problem of deformation and offset of the waterstop during installation and construction is solved, so that the waterproof performance of the waterstop can be more effectively exerted; by waterproofing the cross section of the joint 15, the waterproof performance of the joint 15 is further enhanced. The above three improvements on the waterproof performance of the waterstop structure, waterstop material and cross section of the joint 15 are combined to strengthen the drainage effect of the entire drainage system. Since the drainage system is effectively strengthened, the setting of the buried waterstop can be cancelled, avoiding the deformation and offset of the buried waterstop caused by construction, reducing the construction steps of the waterstop, reducing the construction cost, and effectively ensuring the driving safety of the tunnel.
[0041] Embodiment 2
[0042] like Figures 5 to 7As shown, the difference between this embodiment and the first embodiment is that: in this embodiment, the second drainage structure 5 includes a first connection part and a second connection part, the first connection part is semicircular, the second connection part is horizontally arranged, one end of the second connection part is connected to one end of the first connection part, and there is a gap between the other end of the second connection part and the other end of the first connection part, and a second permeable structure 9 is arranged in the gap. The second permeable structure 9 is preferably a geotextile or filter cotton, and the second permeable structure 9 and the second drainage structure 5 form a second cavity structure 10. When there is a small amount of water, under the condition of low water pressure, most of the water will be discharged along with the first drainage structure 4 in the middle of the back-attached waterstop 1, and a small part will seep out along the contact surface between the back-attached waterstop 1 and the concrete (the direction of water seepage is as shown in FIG. 1 ). Figure 6 As shown), when water passes through the second anti-drainage structure 5 on both sides, the second permeable structure 9 will first absorb part of the water. When the second permeable structure 9 is filled with water, due to the partial adhesion between the back-attached waterstop 1 and the concrete, the water will not penetrate along the direction of the back-attached waterstop 1 and the concrete. The seeping water will preferentially flow along the second permeable structure 9, and finally gather in the second anti-drainage structure 5 on both sides, and then be discharged through the drainage pipe connected to the second anti-drainage structure 5; so that the back-attached waterstop 1 has a double drainage effect. When the water pressure is high, the second anti-drainage structure 5 at both ends cannot quickly drain the water, and the water pressure in the second cavity structure 10 at both ends will exert pressure on the second anti-drainage structure 5 (such as Figure 7 As shown), the pressing force between the outer surface of the second drainage structure 5 at both ends and the concrete is increased, thereby enhancing the waterproof performance of the back-sticked waterstop 1.
[0043] Embodiment 3
[0044] The present embodiment also provides a construction method of a tunnel joint waterproofing and drainage system of embodiment 1, comprising the following steps: before construction, determine the installation position of the back-sticking waterstop 1, clean the installation position, ensure that the surface of the back-sticking waterstop 1 and the installation position are flat, and cut the required size of the back-sticking waterstop 1 according to the actual required size; lay the back-sticking waterstop 1 in a circle along the outer edge of the tunnel cross section, and fix the position of the back-sticking waterstop 1 with a second lining mold to prevent the back-sticking waterstop 1 from moving during the concrete pouring process, and pour the concrete after it is firmly fixed; after the concrete is solidified, remove the second lining mold, apply a cement-based penetrating crystalline waterproof material on the concrete surface below the back-sticking waterstop 1, and apply a layer of butyl waterproof tape after the cement-based penetrating crystalline waterproof material is dry, and tear off the isolation film of the butyl waterproof tape before pouring the next stage to complete the installation.
[0045] The present invention uses specific examples to illustrate the principles and implementation methods of the present invention. The above examples are only used to help understand the method and core ideas of the present invention. At the same time, for those skilled in the art, according to the ideas of the present invention, there will be changes in the specific implementation methods and application scope. In summary, the content of this specification should not be understood as limiting the present invention.
Claims
1. A tunnel joint drainage structure, characterized in that: include: A back-sticking waterstop and a cross-sectional waterproof structure, wherein the back-sticking waterstop comprises a waterstop body, a first anti-drainage structure and a second anti-drainage structure, wherein the first anti-drainage structure and the second anti-drainage structure are both arranged on the waterstop body, the first anti-drainage structure and the second anti-drainage structure are respectively connected to a drainage pipeline, the second anti-drainage structure can realize self-locking with concrete by utilizing internal water pressure, and the cross-sectional waterproof structure is located at the joint; There are two second anti-drainage structures, and the two second anti-drainage structures are respectively located on both sides of the first anti-drainage structure; The first anti-drainage structure is a first U-shaped groove; The second anti-drainage structure is a second U-shaped groove, a first water-permeable structure is arranged at the opening of the second U-shaped groove, and the first water-permeable structure and the second anti-drainage structure form a first cavity structure; The second anti-drainage structure includes a first connection part and a second connection part, the first connection part is semicircular, one end of the second connection part is connected to one end of the first connection part, and there is a gap between the other end of the second connection part and the other end of the first connection part, and a second water-permeable structure is arranged in the gap, and the second water-permeable structure and the second anti-drainage structure form a second cavity structure; The cross-section waterproof structure comprises a waterproof layer made of cement-based permeable crystallization waterproof material.
2. The tunnel joint waterproofing and drainage structure according to claim 1 is characterized in that: Two protrusions are arranged at the opening of the first U-shaped groove, and the maximum gap between the two protrusions is 5 mm.
3. The tunnel joint waterproofing and drainage structure according to claim 1 is characterized in that: The cross-sectional waterproof structure also includes a butyl waterproof tape, and the butyl waterproof tape is located on the waterproof layer.
4. A construction method for a tunnel joint waterproofing and drainage structure according to any one of claims 1 to 3, characterized in that: The following steps are involved: Before construction, determine the installation position of the back-sticking waterstop and clean the installation position to ensure that the surface of the back-sticking waterstop and the installation position is flat, and cut the required size of the back-sticking waterstop according to the actual required size; lay the back-sticking waterstop along the outer edge of the tunnel cross-section in a circle, and fix the position of the back-sticking waterstop with a secondary lining mold to prevent the back-sticking waterstop from moving during the concrete pouring process, and pour the concrete after it is firmly fixed; after the concrete solidifies, remove the secondary lining mold, apply cement-based penetrating crystalline waterproof material on the concrete surface below the back-sticking waterstop, and apply a layer of butyl waterproof tape after the cement-based penetrating crystalline waterproof material is dry. Before the next stage of pouring, tear off the isolation film of the butyl waterproof tape to complete the installation.