A front-end control system for dehydration of sludge treatment tank

By introducing temperature control, feeding and detection modules into the sludge treatment tank, combined with orthogonal parameter calibration and machine vision technology, precise feeding and real-time monitoring of the sludge treatment tank are achieved, solving the problem of low integration and feeding volume of the existing system. The problem of inaccuracy is eliminated, and the dehydration efficiency and system intelligence are improved.

CN118459033BActive Publication Date: 2024-10-11ENERGY RESOURCES INST HEBEI ACADEMY OF SCI +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410904969.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-08
Publication Date
2024-10-11
Estimated Expiration
2044-07-08

AI Technical Summary

Technical Problem

The existing sludge treatment tank dehydration system has low integration, inaccurate feeding amounts, cannot meet the requirements of factory intelligence, and cannot monitor the working conditions of the treatment tank and sludge status in real time.

Method used

A front-end control system for sludge treatment tank dehydration is designed, including a temperature control module, a feeding module, a detection module and a control module. The chemical addition amount, stirring time and stirring rate are determined through an orthogonal parameter calibration table to achieve accurate feeding and real-time Control and use machine vision technology to collect sludge information for monitoring.

Benefits of technology

It improves the dehydration efficiency, avoids the waste of chemicals, realizes automatic monitoring and feedback control of the sludge treatment tank, and meets the intelligent needs of the factory.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118459033B_ABST
    Figure CN118459033B_ABST
Patent Text Reader

Abstract

The present invention belongs to the technical field of sewage treatment, and proposes a sludge treatment tank dehydration front-end control system, including: a sludge treatment tank; a temperature control module; a feeding module; a dehydration module; a detection module for collecting information on sewage water level, sewage temperature, sludge viscosity, sewage pH and solid content of output mud cake in the sludge treatment tank; and a control module for controlling the feeding module to adjust the amount of chemical agent added, stirring time and stirring rate according to the sewage temperature, sewage pH and sludge viscosity collected by the detection module. The control system of the present invention has a high degree of integration, and realizes accurate feeding, real-time control of the treatment tank working conditions and sludge state monitoring.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of sewage treatment and relates to a dehydration front-end control system for a sludge treatment tank. Background Art

[0002] In recent years, as my country has paid more and more attention to water pollution, the pace of sewage treatment project construction has accelerated. In order to reduce the cost of sludge disposal in the later stage, the moisture content of the treated sludge is required to be controlled below 60%. Before sludge dehydration, concentrating and conditioning the sludge can effectively change the properties of sludge particles, enhance dehydration performance, reduce the moisture content of mud cakes, and thus significantly reduce the subsequent disposal costs.

[0003] The current sludge treatment tank dewatering system mainly adds flocculants, coagulants, dehydrating agents and other chemical agents manually, changes the three-dimensional structure of the colloid surface in the suspension solution, and uses external forces such as stirring to make the sludge particles flocculate and precipitate. However, the current factory sludge treatment tank dewatering system has a low degree of integration, the amount of feed is not accurate, and it is difficult to monitor the treatment tank working conditions and sludge status, which cannot meet the requirements of factory intelligence. Summary of the invention

[0004] The present invention provides a sludge treatment tank dehydration front-end control system with high integration, which realizes accurate feeding, real-time regulation of treatment tank working conditions and sludge state monitoring.

[0005] The technical solution of the present invention is achieved in this way:

[0006] A sludge treatment tank dehydration front-end control system, comprising:

[0007] Sludge treatment tanks, used to store sewage to be treated;

[0008] Temperature control module, used to adjust the water temperature of sewage in the sludge treatment tank;

[0009] Feeding module, used to add chemical agents to sewage;

[0010] A dehydration module is used to dehydrate the sewage to separate the sludge and water; the dehydration module includes a dehydration unit and a stirring unit, the stirring unit is used to stir the sewage in the sludge treatment tank and the chemical agent applied by the feeding module to make the chemical agent and the sewage react, and the dehydration unit dehydrates the stirred sewage to produce a mud cake;

[0011] The detection module is used to collect information on sewage level, interface, sewage temperature, sludge viscosity, sewage pH, sludge particles and solid content of output mud cake in the sludge treatment tank;

[0012] The control module is respectively connected to the sludge treatment tank, the temperature control module, the feeding module, the dehydration module and the detection module; the control module controls the temperature control module to adjust the water temperature of the sludge treatment tank according to the sewage temperature; the feeding module controls the amount of chemical agent added, the stirring time and the stirring rate according to the sewage temperature, the sewage pH and the sludge viscosity collected by the detection module;

[0013] The method for determining the amount of chemical agent added, the stirring time and the stirring rate includes: subtracting the sewage temperature, sewage pH and sludge viscosity collected by the detection module from the corresponding data in the orthogonal parameter calibration table, and taking the amount of chemical agent added, the stirring time and the stirring rate corresponding to the combination with the smallest sum of the differences in the table;

[0014] The formation of the orthogonal parameter calibration table includes: designing an orthogonal test according to sewage temperature, sewage pH, sludge viscosity, chemical agent addition amount, stirring time and stirring rate, selecting a combination with a solid content of the output mud cake greater than 35%, and forming an orthogonal parameter calibration table;

[0015] In the orthogonal test, the amount of chemical agents added ranged from 5-20% of the solid content of the sewage;

[0016] The sewage temperature range is 10-50℃;

[0017] The pH value of sewage ranges from 6 to 10;

[0018] The value range of sludge viscosity is 50-400;

[0019] The stirring time ranges from 0.5 to 2 hours;

[0020] The stirring rate ranges from 200 to 800 rpm.

[0021] The method for determining the solid content of sewage is: taking a sewage sample, measuring the solid content of the sewage, and thus inferring the overall solid content of the sewage.

[0022] Preferably, the detection module is also used to collect sewage interface information, sludge particle length and area data parameter information in the sludge treatment tank;

[0023] The control module calculates the sludge settling speed in the sewage based on the interface information collected by the detection module;

[0024] The control module controls the feeding module to adjust the amount of chemical agent added, stirring time and stirring rate according to the sewage temperature, sewage pH, sludge viscosity, sludge settling speed, solid content of the output mud cake, sludge particle length and area data parameter information collected by the detection module;

[0025] The method for determining the amount of chemical agent added, stirring time and stirring rate includes: subtracting the sewage temperature, sewage pH, sludge viscosity, sludge settling velocity, sludge particle length and area data collected by the detection module from the corresponding data in the orthogonal parameter calibration table, and taking the amount of chemical agent added, stirring time and stirring rate corresponding to the combination with the smallest sum of the differences in the table;

[0026] The formation of the orthogonal parameter calibration table includes: designing an orthogonal test according to sewage temperature, sewage pH, sludge viscosity, chemical agent addition amount, stirring time and stirring rate, selecting a combination with a solid content of the output mud cake greater than 35%, and recording the sludge settling velocity, sludge particle length and area data at this time to form an orthogonal parameter calibration table;

[0027] In the orthogonal test, the amount of chemical agents added ranged from 5-20% of the sludge solid content;

[0028] The sewage temperature range is 10-50℃;

[0029] The pH value of sewage ranges from 6 to 10;

[0030] The value range of sludge viscosity is 50-400;

[0031] The stirring time ranges from 0.5 to 2 hours;

[0032] The stirring rate ranges from 200 to 800 rpm.

[0033] Preferably, the temperature control module adjusts the water temperature of the sewage in the sludge treatment tank to ≥25°C.

[0034] Preferably, before the feeding module adds chemical agents to the sewage, after the temperature control module adjusts the water temperature of the sewage in the sludge treatment tank, the sludge treatment tank is also used to statically settle the sewage to be treated and remove the upper clear liquid after static settling.

[0035] Preferably, it also includes updating the orthogonal parameter calibration table: recording the newly added sewage temperature, sewage pH, sludge viscosity, chemical agent addition amount and stirring time, selecting the combined data sample with the solid content of the output mud cake greater than 35%, and optimizing and iterating the orthogonal parameter calibration table.

[0036] Preferably, the method for the detection module to collect sewage pH information includes: sampling the sewage through a sampling device, adding a pH reagent, and then passing it to a black box to take a picture through an industrial camera, and then pre-processing the obtained image, the pre-processing adopts a bilateral filtering method, and the obtained RGB values ​​are subtracted from the calibration values ​​in the calibration database respectively. The calibration database stores RGB values ​​corresponding to different pH values, and the pH value corresponding to the combination with the smallest sum of the differences in the table is taken and output.

[0037] Preferably, the formation of the calibration database includes: sampling the sewage through a sampling device and adding a pH reagent, detecting the pH of the sewage to be tested through a high-precision pH meter and recording the pH value, then taking a picture of the sewage to be tested through an industrial camera in a black box, and then pre-processing the obtained image using a bilateral filtering method, recording the RGB value corresponding to the pH value, and forming a database in which different pH values ​​correspond to different RGB values.

[0038] Preferably, the method for the detection module to collect sewage water level includes: taking a picture of the sludge treatment tank through an industrial camera to obtain an image, then pre-processing the image, using a bilateral filtering method, using a contour extraction algorithm to identify boundary points and scale lines, connecting the identified boundary points to obtain the boundary contour, and using the total range minus the number of upper scales to obtain water level information, which is output.

[0039] Preferably, the method for the detection module to collect sewage interface data includes: taking samples with a sampling cup, taking photos of the samples to obtain an image, and then pre-processing the image using a bilateral filtering method, using a contour extraction algorithm to identify boundary points and scale lines, and connecting the identified boundary points to obtain the boundary contour; the sludge settling velocity can be obtained by differentiating the interface position.

[0040] Preferably, the method for the detection module to collect sludge particle length and area data information includes: taking pictures of the sludge particles by an industrial camera, then binarizing and segmenting the image, extracting area information, and outputting the sludge particle length and area data.

[0041] Preferably, the chemical agent is selected from one or a mixture of porous carbon, polyacrylamide, polyaluminum chloride, and polyferric chloride.

[0042] Preferably, the dehydration unit is a plate and frame filter press.

[0043] The working principle and beneficial effects of the present invention are:

[0044] 1. The sludge treatment tank dehydration front-end control system of the present invention overcomes the shortcomings of the existing sludge dehydration system, such as low integration, inability to accurately control the amount of feed, and inability to monitor the temperature and sludge state, by quantitative feeding, water temperature control, and visual monitoring of sludge. At the same time, it avoids the waste of reagents and improves the dehydration efficiency.

[0045] 2. The sludge treatment tank dehydration front-end control system of the present invention regulates the real-time status of the treatment tank through automated monitoring equipment, can provide real-time feedback on sludge morphology information, and perform feedback control on automated material preparation equipment. BRIEF DESCRIPTION OF THE DRAWINGS

[0046] The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.

[0047] Figure 1 This is the overall control diagram of the dehydration front-end control system of the sludge treatment tank of the present invention.

[0048] Figure 2 This is the process of determining pH value using machine vision in the present invention.

[0049] Figure 3 This is the process of determining the water level and sedimentation velocity using machine vision in the present invention.

[0050] Figure 4 This is the process of machine vision identification of sludge particles in the present invention. DETAILED DESCRIPTION

[0051] The following will be combined with the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0052] like Figure 1 As shown, it is the overall control diagram of the sludge treatment tank dehydration front-end control system of the present invention, including:

[0053] The sludge treatment tank is used to store the sewage to be treated; the concentration tank discharges the sewage from the concentration tank into the sludge treatment tank through a pipe, and there is a solenoid valve in the middle for control. If the water volume of the sewage system exceeds the processing capacity of the plate and frame filter press, the valve port is closed. That is, during the operation of the plate and frame filter press, the water level of the sludge tank is photographed from above, and the water level information of the treatment tank is obtained through machine vision. A flow sensor is added to the water inlet of the plate and frame filter press, and the working efficiency of the plate and frame filter press is obtained by integrating the flow information. The water inlet of the treatment tank is controlled according to the working efficiency of the plate and frame filter press and the water level information of the treatment tank;

[0054] The temperature control module adjusts the water temperature of the sewage in the sludge treatment tank according to the threshold control method; monitors the temperature of the sewage treatment tank in real time. If the temperature is less than 25°C, the treatment tank is heated to make the temperature of the sludge treatment tank not lower than 25°C. The sewage completes the sedimentation and discharges the supernatant in this environment; the temperature detection adopts the Capeson CXCWX-TK high-precision temperature sensor;

[0055] The detection module is used to collect information about the sewage level, interface, sewage temperature, sewage pH, sludge particle length, area and solid content of the output mud cake in the sludge treatment tank; the detection module transmits the collected parameters to the control module, and the control module controls the feeding module to add chemical agents according to the preset logic;

[0056] The dehydration module is used to dehydrate the sewage to separate the sludge and water; the dehydration module includes a dehydration unit and a stirring unit. After the feeding module feeds, the stirring unit, i.e., an automatic stirrer, is used to stir the sewage in the sludge treatment tank and the chemical agent applied by the feeding module, so that the chemical agent and the sewage react. The dehydration unit, i.e., a plate and frame filter press, dehydrates the stirred sewage to produce a mud cake; the solid content information of the produced mud cake is collected by the detection module; after the stirring is completed, the detection module collects the interface information of the output sludge, and the control module derives the interface position to obtain the deposition speed of the sludge; at the same time, the detection module collects the length and area information of the sludge particles, and calculates the length and area data of the sludge particles;

[0057] The control module is respectively connected to the sludge treatment tank, the temperature control module, the feeding module, the dehydration module and the detection module; the control module controls the temperature control module to adjust the water temperature of the sludge treatment tank according to the sewage temperature; the feeding module controls the amount of chemical agent added, the stirring time and the stirring rate according to the sewage temperature, the sewage pH and the sludge viscosity collected by the detection module;

[0058] The method for determining the amount of chemical agent added, the stirring time and the stirring rate includes: subtracting the sewage temperature, sewage pH and sludge viscosity collected by the detection module from the corresponding data in the orthogonal parameter calibration table, and taking the amount of chemical agent added, the stirring time and the stirring rate corresponding to the combination with the smallest sum of the differences in the table;

[0059] Subtract the sewage temperature, sewage pH and sludge viscosity collected by the detection module from the corresponding data in the orthogonal parameter calibration table, and take the chemical agent addition amount, stirring time and stirring rate corresponding to the combination with the smallest difference in the table, that is, take the formula The corresponding amount of chemical reagents added, stirring time and stirring rate; a is the acquisition value, k is the influencing factor, and the value range of k is 0.5-1.5; A is the calibration value, and n is the type of factors affecting the amount of feed;

[0060] The formation of the orthogonal parameter calibration table includes: designing an orthogonal test according to sewage temperature, sewage pH, sludge viscosity, chemical agent addition amount, stirring time and stirring rate, selecting a combination with a solid content of the output mud cake greater than 35%, and forming an orthogonal parameter calibration table;

[0061] In the orthogonal test, the amount of chemical agents added ranged from 5-20% of the sludge solid content;

[0062] The sewage temperature range is 10-50℃;

[0063] The pH value of sewage ranges from 6 to 10;

[0064] The value range of sludge viscosity is 50-400;

[0065] The stirring time ranges from 0.5 to 2 hours;

[0066] The stirring rate ranges from 200 to 800 rpm.

[0067] The method for determining the solid content of sewage is: taking a sewage sample, measuring the solid content of the sewage, and thus inferring the overall solid content of the sewage.

[0068] In order to more accurately control sludge dewatering, the present invention also includes updating the orthogonal parameter calibration table: recording the newly added sewage temperature, sewage pH, sludge viscosity, chemical agent addition amount, stirring time and stirring rate, selecting the combined data sample with the solid content of the output mud cake greater than 35%, and optimizing and iterating the orthogonal parameter calibration table.

[0069] Some orthogonal parameter calibration tables are shown in Table 1.

[0070] The chemical agent is selected from one or a mixture of porous carbon, polyacrylamide, polyaluminum chloride, and polyferric chloride. The chemical agent mentioned in Table 1 is porous carbon. The preparation method of the porous carbon is: after physically mixing iron mud and sawdust in a mass ratio of 1:5, calcining in air at 500°C for 2 hours to obtain porous carbon, the iron mud used is solid waste generated in the process of reducing nitro compounds using iron powder as a catalyst, with an iron content of 65%-68%, and the sawdust has a length of 3-8mm and a diameter of 1-2mm.

[0071] Table 1

[0072]

[0073] In order to more accurately control sludge dehydration, the control module controls the feeding module to adjust the amount of chemical agent added, stirring time and stirring rate according to the sewage temperature, sewage pH, sludge viscosity, sludge settling speed, sludge particle length and area data parameter information collected by the detection module;

[0074] The method for determining the amount of chemical agent added, stirring time and stirring rate includes: subtracting the sewage temperature, sewage pH, sludge viscosity, sludge settling velocity, sludge particle length and area data collected by the detection module from the corresponding data in the orthogonal parameter calibration table, and taking the amount of chemical agent added, stirring time and stirring rate corresponding to the combination with the smallest sum of the differences in the table;

[0075] The formation of the orthogonal parameter calibration table includes: designing an orthogonal test according to sewage temperature, sewage pH, sludge viscosity, chemical agent addition amount, stirring time and stirring rate, selecting a combination with a solid content of the output mud cake greater than 35%, and recording the sludge settling velocity, sludge particle length and area data at this time to form an orthogonal parameter calibration table;

[0076] In the orthogonal test, the amount of chemical agents added ranged from 5-20% of the sludge solid content;

[0077] The sewage temperature range is 10-50℃;

[0078] The pH value of sewage ranges from 6 to 10;

[0079] The value range of sludge viscosity is 50-400;

[0080] The stirring time ranges from 0.5 to 2 hours;

[0081] The stirring rate ranges from 200 to 800 rpm.

[0082] Furthermore, in order to more accurately control sludge dewatering, the orthogonal parameter calibration table can also be updated to record newly added sewage temperature, sewage pH, sludge viscosity, chemical agent addition amount, stirring time, stirring rate, sludge settling rate, sludge particle length and area data, and select combined data samples with a solid content of the output mud cake greater than 35%, and optimize and iterate the orthogonal parameter calibration table.

[0083] like Figure 2 , the method for the detection module to collect sewage pH information includes: sampling sewage through a sampling device, adding pH reagent, and then passing it to a black box to take a picture through an industrial camera, and then pre-processing the obtained image, the pre-processing is to use bilateral filtering to eliminate unnecessary interference of the image so as to improve the accuracy of color data, and the obtained RGB value is subtracted from the calibration value in the calibration database, and the calibration database stores RGB values ​​corresponding to different pH values, and the pH value corresponding to the combination with the smallest difference sum in the table is taken and output;

[0084] The obtained RGB value is subtracted from the calibration value in the calibration database, and the pH value corresponding to the combination with the smallest difference in the table is taken, that is, the formula is taken The corresponding pH value, where Rn, Gn, and Bn represent the R, G, and B values ​​corresponding to different pH values ​​in the calibration database, respectively, and n is the calibration number; r, g, and b represent the R, G, and B values ​​obtained by taking pictures with an industrial camera, respectively.

[0085] RGB color space is a commonly used method for color representation in computer vision. It uses three color channels, red (R), green (G), and blue (B), to represent the colors of all visible light. The value range of each channel is 0 to 255, representing the intensity of the corresponding color. By combining three channels of different intensities, a variety of colors can be represented. In the RGB color space, the color of each pixel can be represented as a three-dimensional vector (R, G, B), where R, G, and B represent the intensity of red, green, and blue, respectively.

[0086] The formation of the calibration database includes: sampling the sewage through a sampling device and adding a pH reagent, detecting the pH of the sewage to be tested through a high-precision pH meter and recording the pH value, then taking a picture of the sewage to be tested through an industrial camera in a black box, and then pre-processing the obtained image, using a bilateral filtering method for pre-processing, recording the RGB value corresponding to the pH value, and forming a database of different RGB values ​​corresponding to different pH values.

[0087] As shown in Table 2, two adjacent groups of calibrated pH values ​​are shown. The pH values ​​obtained by taking photos are R (99.22) G (89.11) B (103.57). According to the above method, the sampling pH is 3.9.

[0088] Table 2 pH calibration values ​​of machine vision parts

[0089]

[0090] like Figure 3 ,The method of detecting module to collect sewage water level includes: taking pictures of the sludge treatment pool by an industrial camera, or taking samples by a sampling cup, taking pictures of the samples to obtain an image, and then pre-processing the image, the pre-processing still uses the bilateral filtering method, mainly completing the filtering and enhancement of the image information, using the contour extraction algorithm to identify the boundary points and scale lines, the identified boundary points are connected to obtain the boundary contour, and the total range minus the number of scales is used to obtain the water level information, and output.

[0091] The method for detecting the interface of sewage by the detection module includes: taking samples with a sampling cup, taking pictures of the samples to obtain an image, and then pre-processing the image, using a bilateral filtering method for the pre-processing, using a contour extraction algorithm to identify boundary points and scale lines, and connecting the identified boundary points to obtain the boundary contour; the sludge settling velocity can be obtained by differentiating the interface position.

[0092] like Figure 4 The method for the detection module to collect sludge particle length and area data information includes: taking pictures of the sludge particles through an industrial camera, then binarizing and segmenting the image, extracting regional information, and outputting the sludge particle length and area data.

[0093] Finally, sludge samples and mud cake samples can be collected before and after the plate and frame filter press works to judge the sludge treatment effect.

[0094] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A sludge treatment tank dehydration front-end control system, characterized in that: include: Sludge treatment tanks, used to store sewage to be treated; Temperature control module, used to adjust the water temperature of sewage in the sludge treatment tank; Feeding module, used to add chemical agents to sewage; Dewatering module, used to dewater sewage to separate sludge and water; The dehydration module includes a dehydration unit and a stirring unit, wherein the stirring unit is used to stir the sewage in the sludge treatment tank and the chemical agent applied by the feeding module so that the chemical agent and the sewage react, and the dehydration unit dehydrates the stirred sewage to produce a mud cake; The detection module is used to collect the sewage level, sewage temperature, sludge viscosity, sewage pH, sewage interface information, sludge particle length, area data parameter information and solid content information of the output mud cake in the sludge treatment tank; The control module is respectively connected to the sludge treatment tank, the temperature control module, the feeding module, the dehydration module and the detection module; the control module controls the temperature control module to adjust the water temperature of the sludge treatment tank according to the sewage temperature; the control module calculates the sludge settling speed in the sewage according to the interface information collected by the detection module; the control module controls the feeding module to adjust the amount of chemical agent added, the stirring time and the stirring rate according to the sewage temperature, sewage pH, sludge viscosity, sludge settling speed, sludge particle length and area data parameter information collected by the detection module; The method for determining the amount of chemical agent added, stirring time and stirring rate includes: subtracting the sewage temperature, sewage pH, sludge viscosity, sludge settling velocity, sludge particle length and area data collected by the detection module from the corresponding data in the orthogonal parameter calibration table, and taking the amount of chemical agent added, stirring time and stirring rate corresponding to the combination with the smallest sum of the differences in the table; The formation of the orthogonal parameter calibration table includes: designing an orthogonal test according to sewage temperature, sewage pH, sludge viscosity, chemical agent addition amount, stirring time and stirring rate, selecting a combination with a solid content of the output mud cake greater than 35%, and recording the sludge settling velocity, sludge particle length and area data at this time to form an orthogonal parameter calibration table; In the orthogonal test, the amount of chemical agents added ranged from 5-20% of the sludge solid content; The sewage temperature range is 10-50℃; The pH value of sewage ranges from 6 to 10; The value range of sludge viscosity is 50-400; The stirring time ranges from 0.5 to 2 hours; The stirring rate range is 200-800 rpm; The method for collecting sewage pH information by the detection module includes: sampling sewage through a sampling device, adding a pH reagent, and then passing it to a black box to take a photo through an industrial camera, and then pre-processing the obtained image, the pre-processing adopts a bilateral filtering method, and the obtained RGB value is subtracted from the calibration value in the calibration database, and the RGB values ​​corresponding to different pH values ​​are stored in the calibration database, and the pH value corresponding to the combination with the smallest difference sum in the table is taken and output; The formation of the calibration database includes: sampling the sewage through a sampling device, adding a pH reagent, detecting the pH of the sewage to be tested through a high-precision pH meter and recording the pH value, then taking a picture of the sewage to be tested through an industrial camera in a black box, and then pre-processing the obtained image, using a bilateral filtering method for pre-processing, recording the RGB value corresponding to the pH value, and forming a database in which different pH values ​​correspond to different RGB values; The method for the detection module to collect sewage interface data includes: taking samples with a sampling cup, taking photos of the samples to obtain images, and then pre-processing the images, using a bilateral filtering method, using a contour extraction algorithm to identify boundary points and scale lines, and connecting the identified boundary points to obtain the boundary contour; the sludge settling velocity can be obtained by deriving the interface position.

2. A sludge treatment tank dehydration front-end control system according to claim 1, characterized in that: The temperature control module adjusts the water temperature of the sewage in the sludge treatment tank to ≥25°C.

3. A sludge treatment tank dehydration front-end control system according to claim 1, characterized in that: Before the feeding module adds chemical agents to the sewage, the temperature control module adjusts the water temperature of the sewage in the sludge treatment tank. The sludge treatment tank is also used to statically settle the sewage to be treated and remove the upper clear liquid after static settling.

4. A sludge treatment tank dehydration front-end control system according to claim 1, characterized in that: It also includes the update of the orthogonal parameter calibration table: recording the newly added sewage temperature, sewage pH, sludge viscosity, chemical agent addition amount, stirring time and stirring rate, selecting the combined data sample with the solid content of the output mud cake greater than 35%, and optimizing and iterating the orthogonal parameter calibration table.

5. A sludge treatment tank dehydration front-end control system according to claim 1, characterized in that: The method for collecting sewage water level by the detection module includes: taking a picture of the sludge treatment tank through an industrial camera to obtain an image, then pre-processing the image, using a bilateral filtering method for pre-processing, using a contour extraction algorithm to identify boundary points and scale lines, connecting the identified boundary points to obtain the boundary contour, and using the total range to subtract the number of upper scales to obtain water level information, and outputting it.

6. A sludge treatment tank dehydration front-end control system according to claim 1, characterized in that: The method for the detection module to collect sludge particle length and area data information includes: taking pictures of the sludge particles by an industrial camera, then binarizing and segmenting the image, extracting area information, and outputting the sludge particle length and area data.