LNG-CNG integrated gas recovery supply method and system
By obtaining and calculating the air intake parameters and characteristic parameters of the gas system, judging the meter status and performing calibration, the problem of inaccurate loss calculation caused by meter errors in the LNG-CNG integrated gas system is solved, and real-time monitoring of the gas recovery pipeline is realized. Accurate delivery.
Patent Information
- Application Number
- CN202410939554.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-15
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2044-07-15
AI Technical Summary
In the existing LNG-CNG integrated gas system, during the LNG-CNG conversion process, meter errors lead to inaccurate loss calculations, and existing calibration methods cannot maintain accurate measurement in real time.
By obtaining the air inlet parameters of the meter, the characteristic parameters of the gas recovery pipeline and temperature influencing factors, the actual gas flow rate is calculated and compared with the preset flow rate to determine the status of the meter. If it is abnormal, a calibration instruction is issued to reset it. calibration.
The real-time accuracy of the meter is achieved, ensuring that the gas recovery pipeline maintains standard metering and delivery during work.
Smart Images

Figure CN118482341B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of gas recovery, and in particular to an LNG-CNG integrated gas recovery supply method and system. Background Art
[0002] LNG-CNG integrated refers to a system that combines two natural gas storage and transportation technologies, liquefied natural gas (LNG) and compressed natural gas (CNG). This integrated system usually includes receiving, storage, gasification, compression, distribution and possible reliquefaction. It aims to make full use of the advantages of LNG and CNG to provide flexible and efficient natural gas supply solutions. For example, LNG can be used as the first choice for long-distance supply due to its high compressibility and easy long-distance transportation; CNG is suitable for localization and motor vehicle fuel needs due to its high energy density and easy use in cities.
[0003] When the existing LNG-CNG integrated gas is converting LNG-CNG, its conversion recovery supply rate reflects the loss during the LNG-CNG conversion. The existing loss calculation is usually calculated by comparing the actual capacity measured by the meter with the preset input capacity. The meter will have errors during long-term use, resulting in inaccurate loss calculation. The existing meter calibration is usually calibrated regularly within the preset working time, which makes it impossible to maintain accurate measurement during the working process. Therefore, an LNG-CNG integrated gas recovery supply method and system are needed to solve the above problems. Summary of the invention
[0004] The object of the present invention is to provide an LNG-CNG integrated gas recovery supply system to solve the technical problems raised in the above background technology.
[0005] To achieve the above object, the present invention provides the following technical solutions:
[0006] An LNG-CNG integrated gas recovery supply method is applied to a gas recovery pipeline, wherein a meter is installed at the gas inlet of the gas recovery pipeline, comprising:
[0007] Acquire multiple air intake parameters of the meter within a preset time, wherein the air intake parameters include gas pressure, gas flow rate and gas temperature;
[0008] Acquiring characteristic parameters of the gas recovery pipeline, and calculating a plurality of gas recovery flow rates according to the characteristic parameters, a plurality of the gas pressures and a plurality of the gas flow rates;
[0009] Acquire the temperature-affecting temperature difference coefficient within a preset time according to the plurality of gas temperatures, and calculate the plurality of actual gas flow rates according to the plurality of gas recovery flow rates and the temperature-affecting temperature difference coefficients;
[0010] Inputting a plurality of the actual gas flow rates and the preset gas flow rates into a comparison model for training, and outputting a comparison value;
[0011] Determining whether the comparison value is equal to a preset comparison value;
[0012] If it is equal, it is determined that the meter is in normal working condition;
[0013] If not equal, the meter is determined to be in an abnormal working state, and a calibration instruction is issued based on the gas recovery supply system, wherein the gas recovery supply system is a system for controlling the meter and the gas recovery pipeline, and the gas recovery supply system is connected to the meter and the gas recovery pipeline based on wireless communication, and the meter is reset and calibrated according to the calibration instruction.
[0014] Preferably, the step of obtaining a plurality of intake parameters of the meter within a preset time includes:
[0015] Obtain the pipeline outlet pressure when the gas recovery pipeline discharges gas;
[0016] Obtain gas density and preset flow rate;
[0017] Obtain the length and diameter of the gas recovery pipeline, and obtain the Darcy friction coefficient of the pipeline based on the Reynolds number;
[0018] The total pressure loss value is calculated according to the density of the gas, the preset flow rate, the length and diameter of the gas recovery pipeline and the Darcy friction coefficient, wherein the calculation formula is:
[0019] ;
[0020] in, Indicates the total pressure loss value, is the Darcy friction coefficient, Indicates the length of the gas recovery pipeline, Indicates the diameter of the gas recovery pipe. represents the density of the gas, Indicates the preset flow rate of gas;
[0021] The gas pressure is calculated according to the pipeline outlet pressure and the total pressure loss value, wherein the calculation formula is:
[0022] ;
[0023] in, Indicates the gas pressure. Indicates the total pressure loss value, Indicates the pipe outlet pressure.
[0024] Preferably, the step of obtaining characteristic parameters of the gas recovery pipeline and calculating a plurality of gas recovery flow rates according to the characteristic parameters, a plurality of the gas pressures and a plurality of the gas flow rates comprises:
[0025] Obtaining the pipeline cross-sectional area and the pipeline material obstruction medium coefficient according to the characteristic parameters of the gas recovery pipeline;
[0026] Acquire multiple pressure differences according to the multiple gas pressures and the preset pipeline outlet pressures;
[0027] Obtaining an average gas pressure according to the plurality of gas pressures;
[0028] The pressure influence index is calculated according to the plurality of pressure differences and the average gas pressure, wherein the calculation formula is:
[0029] ;
[0030] in, represents the pressure impact index, Indicates the pressure difference, Represents the average gas pressure, where i=1, 2, 3...n;
[0031] A plurality of gas recovery flow rates are calculated in sequence according to the plurality of gas flow rates, pipeline cross-sectional areas, pipeline material resistance medium coefficients and pressure influence indexes, wherein the calculation formula is:
[0032] ;
[0033] in, represents the gas recovery flow from the oth to the kth, represents the cross-sectional area of the pipe, represents the oth gas flow rate, Indicates the medium resistance coefficient of the pipeline material, Represents the pressure influence index, where o represents the sequence number, o=1, 2, 3...k.
[0034] Preferably, the step of obtaining the temperature difference coefficient of temperature influence within a preset time according to the multiple gas temperatures comprises:
[0035] Get the start time and end time according to the preset time;
[0036] The average gas temperature is calculated according to the multiple gas temperatures, the start time and the end time, wherein the calculation formula is:
[0037] ;
[0038] in, represents the average gas temperature, Indicates the starting time, Indicates the end time, Indicates the gas temperature, n indicates the number of gas temperatures, where n=1, 2, 3...n;
[0039] The standard temperature difference value is calculated according to the plurality of gas temperatures and the average gas temperature, wherein the calculation formula is:
[0040] ;
[0041] in, Indicates the standard temperature difference, represents the lth gas temperature, Indicates the number of gas temperatures, l indicates the serial number of the zone gas temperature, Indicates the average gas temperature;
[0042] The temperature difference coefficient of temperature influence is calculated according to the standard temperature difference value and the average gas temperature, wherein the calculation formula is:
[0043] ;
[0044] in, Indicates the temperature difference coefficient of temperature influence, represents the average gas temperature, Indicates the standard temperature difference.
[0045] Preferably, the step of calculating a plurality of actual gas flow rates according to the plurality of gas recovery flow rates and temperature-affecting temperature difference coefficients comprises:
[0046] A plurality of actual gas flows are calculated according to the plurality of gas recovery flows and the temperature difference coefficients of temperature influence, wherein the calculation formula is:
[0047] ;
[0048] in, represents the actual gas flow from the jth to the hth, represents the jth gas recovery flow rate, represents the temperature difference coefficient of temperature influence, j represents the sequence number of the gas recovery flow rate, where j represents the sequence number, j=1, 2, 3...h.
[0049] Preferably, the step of inputting a plurality of the actual gas flow rates and the preset gas flow rates into a comparison model for training and outputting a comparison value comprises:
[0050] A plurality of the actual gas flow rates and the preset gas flow rates are input into the comparison model for training, and a comparison value is output, wherein the function formula of the comparison model is:
[0051] ;
[0052] in, Indicates the comparison value, Indicates the actual gas flow rate. represents the preset gas flow rate, and b represents the number of actual gas flow rates, where b=1, 2, 3...e.
[0053] The present application also provides an LNG-CNG integrated gas recovery supply system, comprising:
[0054] A first acquisition module is used to acquire a plurality of intake parameters of the meter within a preset time, wherein the intake parameters include gas pressure, gas flow rate and gas temperature;
[0055] A second acquisition module is used to acquire characteristic parameters of the gas recovery pipeline, and calculate multiple gas recovery flow rates according to the characteristic parameters, multiple gas pressures and multiple gas flow rates;
[0056] A third acquisition module is used to acquire the temperature-affected temperature difference coefficient within a preset time according to the multiple gas temperatures, and calculate multiple actual gas flow rates according to the multiple gas recovery flow rates and the temperature-affected temperature difference coefficients;
[0057] A first training module, used for inputting a plurality of the actual gas flow rates and the preset gas flow rates into a comparison model for training, and outputting a comparison value;
[0058] A first judging module, used to judge whether the comparison value is equal to a preset comparison value;
[0059] If it is equal, it is determined that the meter is in normal working condition;
[0060] If not equal, the meter is determined to be in an abnormal working state, and a calibration instruction is issued based on the gas recovery supply system, wherein the gas recovery supply system is a system for controlling the meter and the gas recovery pipeline, and the gas recovery supply system is connected to the meter and the gas recovery pipeline based on wireless communication, and the meter is reset and calibrated according to the calibration instruction.
[0061] Preferably, the first acquisition module includes:
[0062] A first acquisition unit is used to acquire the pipeline outlet pressure when the gas recovery pipeline discharges the gas;
[0063] A second acquisition unit, used to acquire the density and preset flow rate of the gas;
[0064] A third acquisition unit is used to acquire the length and diameter of the gas recovery pipeline, and acquire the Darcy friction coefficient of the pipeline based on the Reynolds number;
[0065] The first calculation unit is used to calculate the total pressure loss value according to the density of the gas, the preset flow rate, the length and diameter of the gas recovery pipeline and the Darcy friction coefficient, wherein the calculation formula is:
[0066] ;
[0067] in, Indicates the total pressure loss value, is the Darcy friction coefficient, Indicates the length of the gas recovery pipeline, Indicates the diameter of the gas recovery pipe. represents the density of the gas, Indicates the preset flow rate of gas;
[0068] The gas pressure is calculated according to the pipeline outlet pressure and the total pressure loss value, wherein the calculation formula is:
[0069] ;
[0070] in, Indicates the gas pressure. Indicates the total pressure loss value, Indicates the pipe outlet pressure.
[0071] The present application also provides a computer device, including a memory and a processor, wherein the memory stores a computer program, and the processor implements the steps of the above method when executing the computer program.
[0072] The present application also provides a computer-readable storage medium on which a computer program is stored. When the computer program is executed by a processor, the steps of the above method are implemented.
[0073] The beneficial effects of the present application are as follows: the present invention first obtains a plurality of air intake parameters of the meter within a preset time, wherein the air intake parameters include gas pressure, gas flow rate and gas temperature, and then obtains characteristic parameters of the gas recovery pipeline, and then calculates a plurality of gas recovery flow rates according to the characteristic parameters, a plurality of the gas pressures and a plurality of the gas flow rates, and then obtains the temperature effect temperature difference coefficient within the preset time according to the plurality of the gas temperatures, and calculates a plurality of actual gas flow rates under the influence of the temperature effect temperature difference coefficient, and then inputs the plurality of actual gas flow rates and the preset gas flow rates into a comparison model for training, outputs a comparison value, and determines whether the comparison value is equal to the preset comparison value, if it is equal, it is determined that the meter is in a normal working state, if it is not equal, it is determined that the meter is in an abnormal working state, and issues a calibration instruction based on the gas recovery supply system, and resets and calibrates the meter according to the calibration instruction, so that when an error occurs in the meter installed at the gas inlet of the gas recovery pipeline, the meter can be calibrated in time, and then the meter can be kept accurate in real time, so that the gas recovery pipeline can maintain standard metering for transportation in real time during operation. BRIEF DESCRIPTION OF THE DRAWINGS
[0074] Figure 1 The figure is a schematic diagram of a method flow of an embodiment of the present application.
[0075] Figure 2 A schematic diagram of the system structure of an embodiment of the present application.
[0076] Figure 3 A schematic diagram of the internal structure of a computer device according to an embodiment of the present application.
[0077] The realization of the purpose, functional features and advantages of this application will be further explained in conjunction with embodiments and with reference to the accompanying drawings. DETAILED DESCRIPTION
[0078] It should be understood that the specific embodiments described herein are only used to explain the present invention, and are not used to limit the present invention.
[0079] like Figure 1-Figure 3 As shown, the present application provides an LNG-CNG integrated gas recovery supply method, which is applied to a gas recovery pipeline, wherein a meter is installed at the gas inlet of the gas recovery pipeline, including:
[0080] S1. Acquire multiple air intake parameters of the meter within a preset time, wherein the air intake parameters include gas pressure, gas flow rate and gas temperature;
[0081] S2. Acquire characteristic parameters of the gas recovery pipeline, and calculate multiple gas recovery flow rates according to the characteristic parameters, multiple gas pressures and multiple gas flow rates;
[0082] S3, obtaining the temperature difference coefficient of temperature influence within a preset time according to the multiple gas temperatures, and calculating multiple actual gas flow rates according to the multiple gas recovery flow rates and the temperature difference coefficient of temperature influence;
[0083] S4, inputting a plurality of the actual gas flow rates and the preset gas flow rates into a comparison model for training, and outputting a comparison value;
[0084] S5, determining whether the comparison value is equal to a preset comparison value;
[0085] If it is equal, it is determined that the meter is in normal working condition;
[0086] If not equal, the meter is determined to be in an abnormal working state, and a calibration instruction is issued based on the gas recovery supply system, wherein the gas recovery supply system is a system for controlling the meter and the gas recovery pipeline, and the gas recovery supply system is connected to the meter and the gas recovery pipeline based on wireless communication, and the meter is reset and calibrated according to the calibration instruction.
[0087] As described in the above steps S1-S5, when the existing LNG-CNG integrated gas is converting LNG-CNG, its conversion recovery supply rate reflects the loss during the LNG-CNG conversion, and the existing calculation of loss is usually calculated by dividing the actual capacity measured by the meter with the preset input capacity, and the meter will have errors during long-term use, resulting in inaccurate loss calculations, and the existing meter calibration is usually calibrated regularly within a preset working time, which makes it impossible to maintain accurate measurement during the working process. Based on this, a plurality of intake parameters of the meter within a preset time are first obtained, wherein the intake parameters include gas pressure, gas flow rate and gas temperature, so that the intake parameters including gas pressure, gas flow rate and gas temperature can provide a basis for obtaining the actual gas flow, and then the characteristic parameters of the gas recovery pipeline are obtained, and then a plurality of gas recovery flow rates can be calculated based on the characteristic parameters, a plurality of the gas pressures and a plurality of the gas flow rates, and the plurality of gas recovery flow rates obtained in this way are gas The recovery pipeline presets a transmission flow rate, and then obtains the temperature-affected temperature difference coefficient within a preset time according to the multiple gas temperatures, and calculates multiple actual gas flows under the influence of the temperature-affected temperature difference coefficient, and then inputs the multiple actual gas flows and the preset gas flows into a comparison model for training, outputs a comparison value, and determines whether the comparison value is equal to the preset comparison value. If it is equal, it is determined that the meter is in a normal working state. If it is not equal, it is determined that the meter is in an abnormal working state, and a calibration instruction is issued based on the gas recovery supply system, wherein the gas recovery supply system is a system for controlling the meter and the gas recovery pipeline, and the gas recovery supply system is connected to the meter and the gas recovery pipeline based on wireless communication, and resets and calibrates the meter according to the calibration instruction, so that when an error occurs in the meter installed at the gas inlet of the gas recovery pipeline, the meter can be calibrated in time, so that the meter can be kept accurate in real time, so that the gas recovery pipeline can maintain standard metering for transportation in real time during operation.
[0088] In one embodiment, the step S1 of obtaining a plurality of intake parameters of the meter within a preset time includes:
[0089] S101, obtaining the outlet pressure of the gas recovery pipeline when the gas is discharged;
[0090] S102, obtaining the density and preset flow rate of the gas;
[0091] S103, obtaining the length and diameter of the gas recovery pipeline, and obtaining the Darcy friction coefficient of the pipeline based on the Reynolds number;
[0092] S104. Calculate the total pressure loss value according to the density of the gas, the preset flow rate, the length and diameter of the gas recovery pipeline, and the Darcy friction coefficient, wherein the calculation formula is:
[0093] ;
[0094] in, Indicates the total pressure loss value, is the Darcy friction coefficient, Indicates the length of the gas recovery pipeline, Indicates the diameter of the gas recovery pipe. represents the density of the gas, Indicates the preset flow rate of gas;
[0095] S105, calculating the gas pressure according to the pipeline outlet pressure and the total pressure loss value, wherein the calculation formula is:
[0096] ;
[0097] in, Indicates the gas pressure. Indicates the total pressure loss value, Indicates the pipe outlet pressure.
[0098] As described in the above steps S101-S105, since the gas pressure at the gas inlet of the gas recovery pipeline will affect the flow transmission metering, it is necessary to obtain the gas pressure at the gas inlet of the gas recovery pipeline to accurately calculate the actual capacity of the current gas recovery pipeline inlet. After obtaining the actual capacity, it is convenient to compare with the preset flow. On this basis, the pipeline outlet pressure when the gas is discharged from the gas recovery pipeline is first obtained, wherein the pipeline outlet pressure is the pressure of the pipeline after the last complete output, and then the density of the gas and the preset flow rate are obtained, and then the length and diameter of the gas recovery pipeline are obtained, and the Darcy friction coefficient of the pipeline is obtained based on the Reynolds number, wherein the Darcy friction coefficient is an important concept in fluid mechanics, which is used to describe the friction resistance encountered by the fluid when it flows in the pipeline. It represents the energy loss caused by the roughness of the pipe wall and the viscosity of the fluid when the fluid flows inside the pipeline. Under laminar flow conditions, the Darcy friction coefficient can be directly calculated by the Reynolds number, and the formula is as follows: , wherein Re represents the Reynolds number. Then, the total pressure loss value is calculated according to the density of the gas, the preset flow rate, the length and diameter of the gas recovery pipeline and the Darcy friction coefficient. Then, the gas pressure is calculated according to the pipeline outlet pressure and the total pressure loss value. After the gas pressure is calculated, it can provide an important basis for accurately calculating the actual capacity of the current gas recovery pipeline inlet.
[0099] In one embodiment, the step S2 of obtaining characteristic parameters of the gas recovery pipeline and calculating multiple gas recovery flow rates according to the characteristic parameters, multiple gas pressures and multiple gas flow rates includes:
[0100] S201, obtaining the pipeline cross-sectional area and the pipeline material obstruction medium coefficient according to the characteristic parameters of the gas recovery pipeline;
[0101] S202, obtaining a plurality of pressure differences according to a plurality of gas pressures and a preset pipeline outlet pressure;
[0102] S203, obtaining an average gas pressure according to the multiple gas pressures;
[0103] S204, calculating a pressure influence index according to the plurality of pressure differences and the average gas pressure, wherein the calculation formula is:
[0104] ;
[0105] in, represents the pressure impact index, Indicates the pressure difference, Represents the average gas pressure, where i=1, 2, 3...n;
[0106] S205, sequentially calculating a plurality of gas recovery flow rates according to the plurality of gas flow rates, pipeline cross-sectional areas, pipeline material resistance medium coefficients and pressure influence indexes, wherein the calculation formula is:
[0107] ;
[0108] in, represents the gas recovery flow from the oth to the kth, represents the cross-sectional area of the pipe, represents the oth gas flow rate, Indicates the medium resistance coefficient of the pipeline material, Represents the pressure influence index, where o represents the sequence number, o=1, 2, 3...k.
[0109] As described in the above steps S201-S205, the present invention first obtains the pipeline cross-sectional area and the pipeline material obstruction medium coefficient according to the characteristic parameters of the gas recovery pipeline, so that after the characteristic coefficient of the gas recovery pipeline, it can provide a basis for the subsequent calculation of the actual gas flow rate based on accurate calculation, and then obtains multiple pressure differences based on the multiple gas pressures and the preset pipeline outlet pressure, and then obtains the gas average pressure based on the multiple gas pressures, so that the pressure influence index is calculated based on the multiple pressure differences and the gas average pressure, and then the gas recovery flow rate can be calculated more accurately through the pressure influence index, and then multiple gas recovery flow rates are calculated in sequence according to the multiple gas flow rates, pipeline cross-sectional areas, pipeline material obstruction medium coefficients and pressure influence indexes, and the gas recovery flow rate calculated in this way can provide an important basis for calculating the actual capacity of the current gas recovery pipeline inlet.
[0110] In one embodiment, the step S3 of obtaining the temperature difference coefficient of temperature influence within a preset time according to the multiple gas temperatures includes:
[0111] S301, obtaining a start time and an end time according to a preset time;
[0112] S302, calculating an average gas temperature according to the plurality of gas temperatures, start time and end time, wherein the calculation formula is:
[0113] ;
[0114] in, represents the average gas temperature, Indicates the starting time, Indicates the end time. Indicates the gas temperature, n indicates the number of gas temperatures, where n=1, 2, 3...n;
[0115] S303, calculating a standard temperature difference value according to the plurality of gas temperatures and the average gas temperature, wherein the calculation formula is:
[0116] ;
[0117] in, Indicates the standard temperature difference, represents the lth gas temperature, Indicates the number of gas temperatures, l indicates the serial number of the zone gas temperature, Indicates the average gas temperature;
[0118] S304, calculating the temperature difference coefficient of temperature influence according to the standard temperature difference value and the average gas temperature, wherein the calculation formula is:
[0119] ;
[0120] in, Indicates the temperature difference coefficient of temperature influence, represents the average gas temperature, Indicates the standard temperature difference.
[0121] As described in the above steps S301-S304, since the pipeline is affected by temperature during gas transmission, the start time and the end time are first obtained according to the preset time, and then the average gas temperature is calculated according to the multiple gas temperatures, the start time and the end time, and then the standard temperature difference is calculated according to the multiple gas temperatures and the average gas temperature, and finally the temperature influence temperature difference coefficient is calculated according to the standard temperature difference and the average gas temperature. After the temperature influence temperature difference coefficient is calculated, the current actual gas flow is calculated by the temperature influence temperature difference coefficient and the gas recovery flow. In this way, the calculated actual gas flow can be made more accurate to reduce the calculation error, and it can be prepared to determine whether the flow meter has an error.
[0122] In one embodiment, the step S3 of calculating a plurality of actual gas flows according to the plurality of gas recovery flows and temperature-affecting temperature difference coefficients comprises:
[0123] S305, calculating a plurality of actual gas flows according to the plurality of gas recovery flows and the temperature difference coefficients of temperature influence, wherein the calculation formula is:
[0124] ;
[0125] in, represents the actual gas flow from the jth to the hth, represents the jth gas recovery flow rate, represents the temperature difference coefficient of temperature influence, j represents the sequence number of the gas recovery flow rate, where j represents the sequence number, j=1, 2, 3...h.
[0126] As described in the above step S305, the present invention calculates multiple actual gas flow rates based on the multiple gas recovery flow rates and the temperature difference coefficient of temperature influence. The multiple actual gas flow rates calculated in this way can provide accurate parameters for comparison with the preset gas flow rates, and thus the error of a single measurement can be reduced through the multiple actual gas flow rates.
[0127] In one embodiment, the step S4 of inputting the plurality of actual gas flow rates and the preset gas flow rates into the comparison model for training and outputting the comparison value comprises:
[0128] S401, inputting a plurality of the actual gas flow rates and the preset gas flow rates into a comparison model for training, and outputting a comparison value, wherein the function formula of the comparison model is:
[0129] ;
[0130] in, Indicates the comparison value, Indicates the actual gas flow rate. represents the preset gas flow rate, and b represents the number of actual gas flow rates, where b=1, 2, 3...e.
[0131] As described in the above step S401, the present application inputs multiple actual gas flow rates and preset gas flow rates into the comparison model for training, and outputs a comparison value. The output comparison value calculated in this way can provide an important basis for comparison with the preset comparison value, and judge whether the output comparison value is equal to 1. If it is equal to 1, it is determined that the meter is in a normal working state. If it is not equal to 1, it is determined that the meter is in an abnormal working state, and a calibration instruction is issued based on the gas recovery supply system, and the meter is reset and calibrated according to the calibration instruction. In this way, when an error occurs in the meter installed at the air inlet of the gas recovery pipeline, the meter can be calibrated in time, so that the meter can be kept accurate in real time, so that the gas recovery pipeline can maintain standard metering for transportation in real time during operation.
[0132] The present application also provides an LNG-CNG integrated gas recovery supply system, comprising:
[0133] The first acquisition module 1 is used to acquire multiple intake parameters of the meter within a preset time, wherein the intake parameters include gas pressure, gas flow rate and gas temperature;
[0134] A second acquisition module 2 is used to acquire characteristic parameters of the gas recovery pipeline, and calculate multiple gas recovery flow rates according to the characteristic parameters, multiple gas pressures and multiple gas flow rates;
[0135] A third acquisition module 3 is used to acquire the temperature-affected temperature difference coefficient within a preset time according to the multiple gas temperatures, and calculate multiple actual gas flow rates according to the multiple gas recovery flow rates and the temperature-affected temperature difference coefficients;
[0136] A first training module 4, used for inputting a plurality of the actual gas flow rates and the preset gas flow rates into a comparison model for training, and outputting a comparison value;
[0137] A first judging module 5, used to judge whether the contrast value is equal to a preset contrast value;
[0138] If it is equal, it is determined that the meter is in normal working condition;
[0139] If not equal, the meter is determined to be in an abnormal working state, and a calibration instruction is issued based on the gas recovery supply system, wherein the gas recovery supply system is a system for controlling the meter and the gas recovery pipeline, and the gas recovery supply system is connected to the meter and the gas recovery pipeline based on wireless communication, and the meter is reset and calibrated according to the calibration instruction.
[0140] In one embodiment, the first acquisition module includes:
[0141] A first acquisition unit is used to acquire the pipeline outlet pressure when the gas recovery pipeline discharges the gas;
[0142] A second acquisition unit, used to acquire the density and preset flow rate of the gas;
[0143] A third acquisition unit is used to acquire the length and diameter of the gas recovery pipeline, and acquire the Darcy friction coefficient of the pipeline based on the Reynolds number;
[0144] The first calculation unit is used to calculate the total pressure loss value according to the density of the gas, the preset flow rate, the length and diameter of the gas recovery pipeline and the Darcy friction coefficient, wherein the calculation formula is:
[0145] ;
[0146] in, Indicates the total pressure loss value, is the Darcy friction coefficient, Indicates the length of the gas recovery pipeline, Indicates the diameter of the gas recovery pipe. represents the density of the gas, Indicates the preset flow rate of gas;
[0147] The gas pressure is calculated according to the pipeline outlet pressure and the total pressure loss value, wherein the calculation formula is:
[0148] ;
[0149] in, Indicates the gas pressure. Indicates the total pressure loss value, Indicates the pipe outlet pressure.
[0150] like Figure 3 As shown, the present invention also provides a computer device, including a memory and a processor, wherein the memory stores a computer program, and the processor implements the steps of the above-mentioned LNG-CNG integrated gas recovery supply method when executing the computer program.
[0151] The present invention also provides a computer-readable storage medium having a computer program stored thereon, and when the computer program is executed by a processor, the steps of the above-mentioned method for integrated LNG-CNG gas recovery supply are implemented.
[0152] Those of ordinary skill in the art can understand that all or part of the processes in the above-mentioned embodiment methods can be completed by instructing the relevant hardware through a computer program, and the computer program can be stored in a non-volatile computer-readable storage medium. When the computer program is executed, it can include the processes of the embodiments of the above-mentioned methods. Among them, any reference to memory, storage, database or other media provided in this application and used in the embodiments may include non-volatile and / or volatile memory. Non-volatile memory may include read-only memory (ROM), programmable ROM (PROM), electrically programmable ROM (EPROM), electrically erasable programmable ROM (EEPROM) or flash memory. Volatile memory may include random access memory (RAM) or external cache memory. By way of illustration and not limitation, RAM is available in many forms, such as static RAM (SRAM), dynamic RAM (DRAM), synchronous DRAM (SDRAM), double data rate SDRAM (SSRSDRAM), enhanced SDRAM (ESDRAM), synchronous link (Synchlink) DRAM (SLDRAM), memory bus (Rambus) direct RAM (RDRAM), direct memory bus dynamic RAM (DRDRAM), and memory bus dynamic RAM (RDRAM), etc.
[0153] It should be noted that, in this article, the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, device, article or method including a series of elements includes not only those elements, but also includes other elements not explicitly listed, or also includes elements inherent to such process, device, article or method. In the absence of further restrictions, an element defined by the sentence "includes a ..." does not exclude the presence of other identical elements in the process, device, article or method including the element.
[0154] The above description is only a preferred embodiment of the present invention, and does not limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made by using the contents of the present invention specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.
Claims
1. An LNG-CNG integrated gas recovery supply method, applied to a gas recovery pipeline, wherein: A meter is installed at the gas inlet of the gas recovery pipeline, which is characterized by including: Acquire multiple air intake parameters of the meter within a preset time, wherein the air intake parameters include gas pressure, gas flow rate and gas temperature; Acquiring characteristic parameters of the gas recovery pipeline, and calculating a plurality of gas recovery flow rates according to the characteristic parameters, a plurality of the gas pressures and a plurality of the gas flow rates; Get the start time and end time according to the preset time; The average gas temperature is calculated according to the multiple gas temperatures, the start time and the end time, wherein the calculation formula is: ; in, represents the average gas temperature, Indicates the starting time, Indicates the end time, Indicates the gas temperature, n indicates the number of gas temperatures, where n=1, 2, 3...n; The standard temperature difference value is calculated according to the plurality of gas temperatures and the average gas temperature, wherein the calculation formula is: ; in, Indicates the standard temperature difference, represents the lth gas temperature, Indicates the number of gas temperatures, l indicates the sequence number of gas temperatures, Indicates the average gas temperature; The temperature difference coefficient of temperature influence is calculated according to the standard temperature difference value and the average gas temperature, wherein the calculation formula is: ; in, Indicates the temperature difference coefficient of temperature influence, represents the average gas temperature, Indicates a standard temperature difference value, and calculates a plurality of actual gas flow rates according to a plurality of said gas recovery flow rates and temperature-affecting temperature difference coefficients; Inputting a plurality of the actual gas flow rates and the preset gas flow rates into a comparison model for training, and outputting a comparison value; Determining whether the comparison value is equal to a preset comparison value; If it is equal, it is determined that the meter is in normal working condition; If not equal, the meter is determined to be in an abnormal working state, and a calibration instruction is issued based on the gas recovery supply system, wherein the gas recovery supply system is a system for controlling the meter and the gas recovery pipeline, and the gas recovery supply system is connected to the meter and the gas recovery pipeline based on wireless communication, and the meter is reset and calibrated according to the calibration instruction.
2. The LNG-CNG integrated gas recovery supply method according to claim 1, characterized in that: The step of obtaining a plurality of intake parameters of the meter within a preset time further includes: Obtain the pipeline outlet pressure when the gas recovery pipeline discharges gas; Obtain gas density and preset flow rate; Obtain the length and diameter of the gas recovery pipeline, and obtain the Darcy friction coefficient of the pipeline based on the Reynolds number; The total pressure loss value is calculated according to the density of the gas, the preset flow rate, the length and diameter of the gas recovery pipeline and the Darcy friction coefficient, wherein the calculation formula is: ; in, Indicates the total pressure loss value, is the Darcy friction coefficient, Indicates the length of the gas recovery pipeline, Indicates the diameter of the gas recovery pipe. Indicates the density of the gas, and V indicates the preset flow rate of the gas; The gas pressure is calculated according to the pipeline outlet pressure and the total pressure loss value, wherein the calculation formula is: ; in, Indicates the gas pressure. Indicates the total pressure loss value, Indicates the pipe outlet pressure.
3. The LNG-CNG integrated gas recovery supply method according to claim 1, characterized in that: The step of obtaining characteristic parameters of the gas recovery pipeline and calculating a plurality of gas recovery flow rates according to the characteristic parameters, a plurality of the gas pressures and a plurality of the gas flow rates comprises: Obtaining the pipeline cross-sectional area and the pipeline material obstruction medium coefficient according to the characteristic parameters of the gas recovery pipeline; Acquire multiple pressure differences according to the multiple gas pressures and the preset pipeline outlet pressures; Obtaining an average gas pressure according to the plurality of gas pressures; The pressure influence index is calculated according to the plurality of pressure differences and the average gas pressure, wherein the calculation formula is: ; in, represents the pressure impact index, Indicates the pressure difference, Represents the average gas pressure, where i=1, 2, 3...n; A plurality of gas recovery flow rates are calculated in sequence according to the plurality of gas flow rates, pipeline cross-sectional areas, pipeline material resistance medium coefficients and pressure influence indexes, wherein the calculation formula is: ; in, represents the gas recovery flow from the oth to the kth, represents the cross-sectional area of the pipe, represents the oth gas flow rate, Indicates the medium resistance coefficient of the pipeline material, Represents the pressure influence index, where o represents the sequence number, o=1, 2, 3...k.
4. The LNG-CNG integrated gas recovery supply method according to claim 1, characterized in that: The step of calculating a plurality of actual gas flow rates according to a plurality of gas recovery flow rates and temperature-affecting temperature difference coefficients comprises: A plurality of actual gas flows are calculated according to the plurality of gas recovery flows and the temperature difference coefficients of temperature influence, wherein the calculation formula is: ; in, represents the actual gas flow from the jth to the hth, represents the jth gas recovery flow rate, represents the temperature difference coefficient of temperature influence, j represents the sequence number of the gas recovery flow rate, where j represents the sequence number, j=1, 2, 3...h.
5. The LNG-CNG integrated gas recovery supply method according to claim 1, characterized in that: The step of inputting the plurality of actual gas flow rates and the preset gas flow rates into the comparison model for training and outputting the comparison value comprises: A plurality of the actual gas flow rates and the preset gas flow rates are input into the comparison model for training, and a comparison value is output, wherein the function formula of the comparison model is: ; in, Indicates the comparison value, Indicates the actual gas flow rate. represents the preset gas flow rate, and b represents the number of actual gas flow rates, where b=1, 2, 3...e.
6. A system for the LNG-CNG integrated gas recovery supply method as claimed in claim 1, characterized in that: include: A first acquisition module is used to acquire a plurality of intake parameters of the meter within a preset time, wherein the intake parameters include gas pressure, gas flow rate and gas temperature; A second acquisition module is used to acquire characteristic parameters of the gas recovery pipeline, and calculate multiple gas recovery flow rates according to the characteristic parameters, multiple gas pressures and multiple gas flow rates; A third acquisition module is used to acquire the temperature-affected temperature difference coefficient within a preset time according to the multiple gas temperatures, and calculate multiple actual gas flow rates according to the multiple gas recovery flow rates and the temperature-affected temperature difference coefficients; A first training module, used for inputting a plurality of the actual gas flow rates and the preset gas flow rates into a comparison model for training, and outputting a comparison value; A first judging module, used to judge whether the comparison value is equal to a preset comparison value; If it is equal, it is determined that the meter is in normal working condition; If not equal, the meter is determined to be in an abnormal working state, and a calibration instruction is issued based on the gas recovery supply system, wherein the gas recovery supply system is a system for controlling the meter and the gas recovery pipeline, and the gas recovery supply system is connected to the meter and the gas recovery pipeline based on wireless communication, and the meter is reset and calibrated according to the calibration instruction.
7. The system according to claim 6, characterized in that The first acquisition module includes: A first acquisition unit is used to acquire the pipeline outlet pressure when the gas recovery pipeline discharges the gas; A second acquisition unit, used to acquire the density and preset flow rate of the gas; A third acquisition unit is used to acquire the length and diameter of the gas recovery pipeline, and acquire the Darcy friction coefficient of the pipeline based on the Reynolds number; The first calculation unit is used to calculate the total pressure loss value according to the density of the gas, the preset flow rate, the length and diameter of the gas recovery pipeline and the Darcy friction coefficient, wherein the calculation formula is: ; in, Indicates the total pressure loss value, is the Darcy friction coefficient, Indicates the length of the gas recovery pipeline, Indicates the diameter of the gas recovery pipe. Indicates the density of the gas, and V indicates the preset flow rate of the gas; The gas pressure is calculated according to the pipeline outlet pressure and the total pressure loss value, wherein the calculation formula is: ; in, Indicates the gas pressure. Indicates the total pressure loss value, Indicates the pipe outlet pressure.
8. A computer device comprising a memory and a processor, wherein the memory stores a computer program, wherein: When the processor executes the computer program, the steps of the method according to any one of claims 1 to 5 are implemented.
9. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the steps of the method according to any one of claims 1 to 5 are implemented.