Intelligent production scheduling system for ready-mixed concrete based on data regulation

By optimizing the production scheduling and mix proportions of ready-mixed concrete through an intelligent production scheduling system, the problem of incomplete consideration of factors in existing technologies has been solved, achieving efficient and precise concrete production and resource utilization, and improving production efficiency and information response speed.

CN118504842BActive Publication Date: 2024-11-22GUIYANG ZHONGJIAN WEST CONSTR CO LTD
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202410956122.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-17
Publication Date
2024-11-22
Estimated Expiration
2044-07-17

AI Technical Summary

Technical Problem

Existing technologies fail to fully consider factors such as transportation, environmental factors, and equipment capacity in the intelligent control of ready-mixed concrete, resulting in incomplete processing and production scheduling, resource waste when the mix proportions are not up to standard, untimely synchronization of supply chain information, difficulty in cooperation, and insufficient response speed.

Method used

The system employs a data-driven intelligent production scheduling system for ready-mixed concrete, which includes a supply chain management system, an intelligent production scheduling optimization system, a raw material ratio optimization system, and a production monitoring, display, and early warning system. It integrates information and performs real-time monitoring through the Internet of Things and intelligent algorithms, optimizing production scheduling and ratio schemes and dynamically adjusting them to meet production needs.

Benefits of technology

It improves the processing efficiency and precision of ready-mixed concrete, reduces resource waste, achieves transparent information management, shortens the production scheduling cycle, improves information response speed and flexibility, has strong adaptability, and high proportioning accuracy.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118504842B_ABST
    Figure CN118504842B_ABST
Patent Text Reader

Abstract

The present invention provides a ready-mixed concrete intelligent production scheduling system based on data adjustment, which relates to the field of intelligent manufacturing technology. The system includes a supply chain management system, an intelligent production scheduling optimization system, a raw material ratio optimization system and a production monitoring display and early warning system. The supply chain management system is connected with external regional links to collect information, and the production scheduling optimization plan is intelligently adjusted in combination with changes in environmental factors and implementation factors to improve flexibility and adaptability, quickly give results, and shorten the production scheduling cycle. At the same time, the raw material ratio optimization system optimizes the concrete ratio according to the production scheduling plan to achieve intelligent proportioning of concrete as required, avoid waste of resources, have strong adaptability, high proportioning accuracy, and better meet actual use needs. Monitoring, early warning, data storage and UI interactive display are performed in the entire system, so that the entire system integrates the system operation structure of intelligent scheduling optimization and intelligent proportioning of ready-mixed concrete, thereby improving the processing efficiency and accuracy of ready-mixed concrete.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of intelligent manufacturing technology, and in particular to a ready-mixed concrete intelligent production scheduling system based on data adjustment. Background Art

[0002] With the development of the concrete industry, traditional manual management methods can no longer meet the needs of production. Therefore, the concrete industry production management system came into being. The concrete industry production management system mainly includes production planning management, raw material management, production process monitoring, quality control and data analysis and other functions.

[0003] According to a kind of intelligent management system for ready-mixed concrete pouring construction site disclosed by Chinese patent number "CN117910781B", including pouring data detection module, pouring quantity analysis module, pouring time detection module, pouring time analysis module, pouring quality detection module, pouring quality analysis module, construction operation evaluation module, production adjustment module and management database, this system obtains pouring quantity evaluation coefficient through pouring quantity data analysis of each pouring vehicle in each sub-area, obtains pouring time evaluation coefficient through pouring one-way time and pouring time analysis of each pouring vehicle in each sub-area, obtains pouring quality evaluation coefficient through pouring quality data analysis of each sub-area, and then obtains construction operation evaluation index through comprehensive analysis, understands the construction operation situation, and adjusts production according to the production adjustment demand coefficient of each sub-area, optimizes the construction operation process, improves production efficiency and quality, and saves time and cost.

[0004] According to Chinese patent number "CN107203829A", a big data quality supervision method for ready-mixed concrete is disclosed, which involves a field of Internet big data analysis technology, establishing relationships between enterprises, enterprises and testing institutions, and projects and quality supervision stations; collecting data from concrete production, transportation, and quality inspection links, and establishing data relationships; analyzing the data generated in each link, discovering problems, and implementing supervision. The present invention provides data services for supervision units, construction companies, and commercial concrete mixing stations to solve existing problems in concrete quality supervision.

[0005] The above patent documents and prior art have the following technical problems when used:

[0006] Problem 1: The above patent document, with respect to the intelligent control process of ready-mixed concrete, generally uses the time sequence or the order of urgency to sort the tasks after the concrete tasks are issued, and then processes them. Other factors other than processing and production cannot be considered when scheduling concrete production, such as transportation factors, environmental factors, equipment capacity, transportation arrangements, etc., resulting in an incomplete consideration of the entire processing and scheduling process of ready-mixed concrete;

[0007] Problem 2: Concrete is usually mixed as needed during the concrete processing process, but concrete with unqualified ratios is usually discarded, resulting in a waste of resources. At the same time, the entire production line process, such as transportation environment and transportation time, cannot be taken into account during the concrete mixing process. As a result, products with qualified manufacturing parameters and performance may not meet the performance standards during use due to transportation, weather, etc.;

[0008] Problem three: The problem of information synchronization between supply chains in various regions during the concrete processing process cannot be solved, resulting in untimely information synchronization between supply chains, difficulty in cooperation, and insufficient response speed, which affects the processing and production efficiency of concrete. Summary of the invention

[0009] Technical issues solved:

[0010] In view of the shortcomings of the prior art, the present invention provides a ready-mixed concrete intelligent production scheduling system based on data adjustment, which solves the following problems:

[0011] 1. Insufficient factors are considered when scheduling and controlling the production of ready-mixed concrete, and it is impossible to adjust and sort the factors in the entire production process;

[0012] 2. When mixing premixed concrete, the ratio requirements are not considered enough, resulting in poor adjustable performance, waste of resources, and the use of products is affected by the transportation process, resulting in inaccurate parameters;

[0013] 3. In the concrete processing process, information synchronization between various supply chain areas is not timely, cooperation is difficult, and the corresponding response speed is insufficient.

[0014] Technical solution:

[0015] To achieve the above objectives, the present invention is implemented through the following technical solutions: a data-adjusted intelligent production scheduling system for ready-mixed concrete, the system comprising a supply chain management system, an intelligent production scheduling optimization system, a raw material ratio optimization system, and a production monitoring display and early warning system, wherein:

[0016] The supply chain management system is connected with raw material suppliers, logistics service providers and construction sites to collect and manage information on raw material inventory, logistics status and construction progress, and transmit the collected information to the intelligent production scheduling optimization system;

[0017] The intelligent production scheduling optimization system is internally provided with an intelligent production scheduling optimization algorithm, receives data provided by the supply chain management system, performs integrated weighted analysis on environmental factors and implementation factors affecting ready-mixed concrete, and provides an optimal production scheduling plan for ready-mixed concrete under the weighted constraints of maintaining minimum production cost, maximizing production efficiency and optimal delivery date;

[0018] The raw material ratio optimization system is internally provided with a ratio optimization algorithm, receives the optimal production scheduling plan given by the intelligent production scheduling optimization system, gives the initial optimized ratio of the ready-mixed concrete according to the target data of the production demand for ready-mixed concrete in each task, and puts it into processing and production. During the processing, machine vision detection is performed, and various parameters of the ready-mixed concrete processing process are monitored by using a camera in combination with an image processing algorithm. If the parameters meet the requirements, the finished product is output. If not, the monitored data is transmitted back to the ratio optimization algorithm, and the current data is combined with the target data and the target data to increase the concrete ingredients, obtain the repeatedly optimized ratio, and continue processing, production, monitoring, and transmission until the parameters of the concrete meet the requirements and the finished product is output;

[0019] The production monitoring display and early warning system integrates Internet of Things technology to monitor and intelligently control production equipment, collects equipment operation data and energy consumption data through sensors for monitoring, conducts production monitoring and early warning of abnormal conditions, stores data and interactively displays the production status through the UI, and connects with various systems. After processing, the work adjustment data of the entire system is classified and integrated, and transmitted back to each system accordingly for algorithm optimization.

[0020] Preferably, the supply chain management system uses the Internet of Things and Technology is used for logistics tracking and automated inventory management. In the supply chain management system, transactions are carried out between raw material suppliers, logistics service providers and construction sites through smart contracts.

[0021] Preferably, the data of environmental factors and implementation factors in the intelligent production scheduling optimization system are provided by the supply chain management system, and the environmental factors include at least project progress, weather conditions and traffic conditions, and the implementation factors include at least raw material inventory, production equipment status and delivery deadline.

[0022] Preferably, the content of the intelligent production scheduling optimization algorithm in the intelligent production scheduling optimization system is as follows:

[0023] The intelligent production scheduling optimization algorithm is expanded based on the genetic algorithm, and the book structure of the production scheduling plan is defined, including the task list, task start time and end time, and the parameters of the algorithm are set, including the population size, number of iterations and crossover probability. The formula is as follows:

[0024]

[0025] in:

[0026] To plan production;

[0027] The total production cost of the current production schedule;

[0028] It is production efficiency;

[0029] Actual delivery date;

[0030] Optimal delivery date;

[0031] , , is the weight coefficient, and ;

[0032] is the maximum delivery delay allowed;

[0033] According to the above formula, the project progress based on environmental factors , Weather conditions , Traffic status , raw material inventory of implementation factors , Production equipment status , Delivery deadline , the minimum production cost of the target parameter , maximize production efficiency , optimal delivery time As input parameters, the elite selection method is used to select Select individuals from the population, perform crossover operations, and generate new production scheduling plans Then, fitness evaluation, selection and genetic operation are repeated, and the multiple production scheduling schemes obtained form a population , and there is , each It contains all , the difference is that each in of The production order is different until the predetermined number of iterations is reached or the termination condition is met, and the individual with the highest fitness is selected from the population , as the optimal production scheduling plan, the optimal production scheduling plan is decoded into the actual production task arrangement and output.

[0034] Preferably, the concrete production requirements in the raw material ratio optimization system include at least parameter requirements of physical properties, workability, durability, mechanical properties, chemical properties and other properties, and the physical properties include at least density, water absorption rate, and porosity; the workability includes at least cohesion, water retention, and fluidity; the durability includes at least impermeability, frost resistance, and hydrochloric acid corrosion resistance; the mechanical properties include at least tensile strength, flexural strength, and compressive strength; the chemical properties include at least alkali content and sulfur trioxide content, and the corrosion resistance coefficient of cementitious materials; and other properties include at least water bleeding rate, air content, carbonization performance, and bubble spacing coefficient.

[0035] Preferably, in the raw material ratio optimization system, the content of the ratio optimization algorithm is as follows:

[0036] Sp1: Input data processing: Obtain the production scheduling plan including production tasks, time, quantity and performance requirements from the intelligent production scheduling optimization system, and analyze the specific performance requirements of ready-mixed concrete in each production task;

[0037] Sp2: Initial mix ratio calculation: Establish or reference a database containing various basic mix ratios of concrete. These basic mix ratios are based on past experimental data or industry standards. According to the specific requirements of the current task, select the closest mix ratio from the basic mix ratio database as the initial mix ratio, or calculate the initial mix ratio according to the empirical formula;

[0038] Sp3: Feedback mechanism adjustment: The real-time parameters of concrete during processing are obtained through the machine vision detection system, and the monitored parameters are compared with the target parameters to evaluate the effect of the current mix ratio. If the parameters do not meet the requirements, the linear programming optimization method is used to fine-tune the mix ratio according to the deviation size and direction to generate a new optimized mix ratio;

[0039] Sp4: Iterative optimization and output: Put the new ratio into production, continue to monitor it through the machine vision inspection system, repeat the above comparison, evaluation and adjustment process until all monitoring parameters meet or exceed the target requirements. When all parameters meet the standards, determine the final optimized ratio and output it to the production system, and record the optimization process and results in the database.

[0040] Preferably, in the raw material ratio optimization system, the content of the image processing algorithm is as follows:

[0041] Sp1: Image preprocessing: Use median filtering and Gaussian filtering to remove noise from the image, and enhance the visibility of key features in the image by contrast adjustment and sharpening;

[0042] Sp2: Feature Extraction: Using color space conversion and texture analysis techniques, we can identify the color and texture changes of concrete to assess its uniformity and condition. Edge detection and Hough transform methods are used to identify boundary and shape features in concrete samples;

[0043] Sp3: Parameter calculation: Based on the results of edge detection, the slump is estimated by calculating the height and diameter parameters of the slump body. The moisture content and density of the concrete are indirectly inferred through color distribution and texture characteristics. The camera is equipped with infrared function, which can directly read the temperature distribution on the concrete surface:

[0044] Sp4: Data integration and output: Integrate the extracted parameters into a unified data format to facilitate subsequent analysis and processing, and transmit the monitored parameters to the ratio optimization algorithm in real time as a basis for feedback adjustment:

[0045] Preferably, the intelligent production scheduling optimization system dynamically adjusts parameters according to the dynamic changes of environmental factors and implementation factors, and outputs the adjusted optimal production scheduling plan. The raw material ratio optimization system dynamically adjusts the start sequence of ready-mixed concrete tasks according to the dynamically adjusted optimal production scheduling plan. The raw material ratio optimization system uses the basic parameter information of ready-mixed concrete provided by the database in the production monitoring display and early warning system, and the data combined with the actual concrete production demand as the input data of the ratio optimization algorithm.

[0046] Beneficial effects:

[0047] The present invention provides a ready-mixed concrete intelligent production scheduling system based on data adjustment. It has the following beneficial effects:

[0048] 1. The present invention uses a supply chain management system, an intelligent production scheduling optimization system, a raw material ratio optimization system, and a production monitoring display and early warning system to perform intelligent production scheduling of ready-mixed concrete. The supply chain management system is connected to external regional links to collect information, and a data basis is provided for the intelligent production scheduling optimization system, making the intelligent production scheduling plan more accurate. At the same time, the raw material ratio optimization system is used to optimize the concrete ratio according to the production scheduling plan to improve the accuracy of the concrete ratio. Monitoring, early warning, data storage and UI interactive display are performed in the entire system, so that the entire system integrates the system operation structure of intelligent scheduling optimization and intelligent ratio of ready-mixed concrete, thereby improving the processing efficiency and accuracy of ready-mixed concrete.

[0049] 2. The present invention adopts a supply chain management system in the system to connect with external raw material suppliers, logistics suppliers and construction sites, conduct real-time monitoring and data feedback on raw material inventory, logistics status and construction progress, and provide basic data for production scheduling and proportioning plans, so that the production scheduling plan of ready-mixed concrete in the entire system covers all aspects, and each supply chain data is transparently managed, which changes the traditional phenomenon of untimely supply chain information and difficult cooperation. Through transparent management, the information response speed is improved, which facilitates the unified management of ready-mixed concrete and the rapid response of information.

[0050] 3. The present invention adopts an intelligent production scheduling optimization system to perform intelligent production scheduling optimization of ready-mixed concrete tasks. The information of each region is provided by the supply chain management system as the basis for analysis. The optimal production scheduling scheme is generated for use in combination with the consideration of minimum production cost, maximum production efficiency and optimal delivery time. The traditional manual production scheduling is inefficient and incomplete. The intelligent production scheduling structure is adopted to quickly give results and shorten the production scheduling cycle. The production scheduling optimization scheme can be intelligently adjusted according to changes in environmental factors and implementation factors to improve flexibility and adaptability.

[0051] 4. The present invention adopts a raw material ratio optimization system to optimize the ratio of the post-production scheduling plan, and provides an optimized ratio plan based on multiple factors of production demand and a ratio optimization algorithm. It also performs real-time parameter monitoring through machine vision monitoring, and transmits back unqualified parameters for optimization until all parameters meet the requirements and then outputs them. This method can realize intelligent ratioing of concrete as required, avoid waste of resources, have strong adaptability, high ratio accuracy, and better meet actual usage needs. BRIEF DESCRIPTION OF THE DRAWINGS

[0052] Figure 1 This is a system distribution structure diagram of the present invention. DETAILED DESCRIPTION

[0053] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention. Specific embodiment one:

[0055] like Figure 1 As shown in the figure, the intelligent production scheduling system for ready-mixed concrete based on data adjustment includes a supply chain management system, an intelligent production scheduling optimization system, a raw material ratio optimization system, and a production monitoring display and early warning system, among which:

[0056] The supply chain management system is connected with raw material suppliers, logistics service providers and construction sites to collect and manage information on raw material inventory, logistics status and construction progress, and transmit the collected information to the intelligent production scheduling optimization system. The supply chain management system uses the Internet of Things and RFID technology to track logistics and automate inventory management. In the supply chain management system, transactions are conducted between raw material suppliers, logistics service providers and construction sites through smart contracts, providing basic data for production scheduling and proportioning plans, so that the production scheduling plan of ready-mixed concrete in the entire system is comprehensive. The transparent management of each supply chain data changes the traditional phenomenon of untimely supply chain information and difficult cooperation. Through transparent management, the speed of information response is improved, which facilitates the unified management of ready-mixed concrete and the rapid response of information.

[0057] The intelligent production scheduling optimization system has an internal intelligent production scheduling optimization algorithm, receives data from the supply chain management system, integrates and weights the environmental factors and implementation factors that affect ready-mixed concrete, and gives the optimal production scheduling plan for ready-mixed concrete under the weighted constraints of maintaining the minimum production cost, maximizing production efficiency and optimal delivery time. It changes the traditional manual production scheduling, which is inefficient and incomplete, and adopts an intelligent production scheduling structure to quickly give results and shorten the production scheduling cycle. It can also intelligently adjust the production scheduling optimization plan according to changes in environmental factors and implementation factors to improve flexibility and adaptability.

[0058] The raw material ratio optimization system has an internal ratio optimization algorithm, which receives the optimal production scheduling plan given by the intelligent production scheduling optimization system. The raw material ratio optimization system dynamically adjusts the start sequence of the ready-mixed concrete tasks according to the dynamically adjusted optimal production scheduling plan. The raw material ratio optimization system provides basic parameter information of the ready-mixed concrete through the database in the production monitoring display and early warning system, and the data combined with the actual concrete production demand is used as the input data of the ratio optimization algorithm. According to the target data of the production demand for ready-mixed concrete in each task, the initial optimized ratio of the ready-mixed concrete is given and put into processing and production. During the processing, machine vision detection is performed, and the camera is used in conjunction with the image processing algorithm. The method monitors various parameters in the process of ready-mixed concrete processing. If the parameters meet the requirements, the finished product is output. If not, the monitored data is fed back to the ratio optimization algorithm. The current data is combined with the target data and the target data to increase the concrete ingredients, and the ratio is repeatedly optimized. The processing, production, monitoring, and feedback are continued until the parameters of the concrete meet the requirements and the finished product is output. The intelligent production scheduling optimization system dynamically adjusts the parameters according to the dynamic changes of environmental factors and implementation factors, and outputs the adjusted optimal production scheduling plan. This method can realize the intelligent ratio of concrete as required, avoid waste of resources, have strong adaptability, high ratio accuracy, and better meet actual use needs.

[0059] The production monitoring display and early warning system integrates Internet of Things technology to monitor and intelligently control production equipment. It collects equipment operation data and energy consumption data through sensors for monitoring, conducts production monitoring and early warning of abnormal conditions, stores data and interactively displays production status through the UI, and connects to various systems. After processing, it classifies and integrates the work adjustment data of the entire system and transmits it back to each system accordingly for algorithm optimization, so that the entire system integrates the system operation structure of intelligent optimization of production scheduling and intelligent proportioning of ready-mixed concrete, thereby improving the processing efficiency and accuracy of ready-mixed concrete. Specific embodiment 2:

[0061] like Figure 1 As shown, according to the content of the specific embodiment 1, the following technical solutions are further disclosed:

[0062] In the case of avoiding waste of resources, it is mainly achieved through intelligent production scheduling optimization system and raw material ratio optimization system. The intelligent production scheduling optimization system can avoid waste of production equipment resources, and the raw material ratio optimization system can avoid waste of concrete materials. The specific contents are as follows:

[0063] For production equipment resources, through the intelligent production scheduling optimization system, combined with the influence of environmental factors and implementation factors, the goal of minimizing production costs, maximizing production efficiency and optimizing delivery time is achieved. According to the processing tasks of ready-mixed concrete, the optimal production scheduling plan is given. Compared with the traditional direct processing and production method, this application can understand the status of the environment and equipment before production, and can adjust the production scheduling plan in time according to the actual environment and equipment loading, so as to avoid the problem of equipment being unable to operate halfway through, transporting halfway, and encountering bad weather, which affects the quality of concrete. The overall situation can be controlled and adjusted in time, so as to make full use of production equipment resources and avoid waste.

[0064] In order to solve the problem of waste of concrete materials, the raw material ratio optimization system is used to increase the amount of raw materials for each batch of concrete according to the task requirements and the content of concrete in the database, and feedback is given through parameter monitoring and optimization of the processing process to optimize the ratio. Compared with the traditional method of directly processing and proportioning, this application can make timely adjustments during the processing process if the parameters do not meet the requirements, so as to avoid the entire concrete in the processing process being discarded due to unqualified parameters, thereby avoiding waste of resources. At the same time, in order to avoid waste of resources, this application, in combination with the intelligent production scheduling optimization system, also takes into account factors such as transportation, weather and project progress. For example, in bad weather, the entire environment The environment is humid, and the water vapor on the surface of concrete during transportation will increase compared to normal weather transportation. Therefore, the requirements for water content or water vapor can be appropriately reduced during the production process, so that the water vapor added during transportation can meet the concrete parameter requirements, thereby achieving precise control of concrete production parameters. For example, in high temperature weather and water evaporation, the concrete production process needs to have a surplus of water vapor evaporated during transportation to ensure that the parameters of the concrete can meet the water requirements after transportation to the destination. This content cannot be achieved by existing proportioning based on demand, thereby avoiding waste of resources from all angles and maximizing the functionality of each raw material of concrete. Specific embodiment three:

[0066] like Figure 1 As shown, according to the contents of specific embodiments 1 and 2, the following technical solutions are further disclosed:

[0067] The data of environmental factors and implementation factors in the intelligent production scheduling optimization system are provided by the supply chain management system, and the environmental factors at least include project progress, weather conditions and traffic conditions, and the implementation factors at least include raw material inventory, production equipment status and delivery deadline.

[0068] The contents of the intelligent production scheduling optimization algorithm in the intelligent production scheduling optimization system are as follows:

[0069] The intelligent production scheduling optimization algorithm is based on the genetic algorithm and defines the book structure of the production scheduling plan, including the task list, task start time and end time, and sets the algorithm parameters, including population size, number of iterations and crossover probability. The formula is as follows:

[0070] ;

[0071] in:

[0072] To plan production;

[0073] The total production cost of the current production schedule;

[0074] It is production efficiency;

[0075] Actual delivery date;

[0076] Optimal delivery date;

[0077] , , is the weight coefficient, and ;

[0078] is the maximum delivery delay allowed;

[0079] According to the above formula, the project progress based on environmental factors , Weather conditions , Traffic status , raw material inventory of implementation factors , Production equipment status , Delivery deadline , the minimum production cost of the target parameter , maximize production efficiency , optimal delivery time are input parameters, where:

[0080] Project Progress :The project progress will affect the production plan. If the progress of a project is ahead of schedule, it will require the progress of related production tasks to be accelerated. If the progress lags behind, the production plan needs to be adjusted to adapt to the new time requirements. The formula is expressed as follows according to the progress percentage:

[0081] ;

[0082] in:

[0083] For the minimum percentage, assign a value of -10;

[0084] The maximum percentage, i.e. the progress closest to completion, is assigned a value of 10;

[0085] The corresponding project progress is gradually approaching completion, and the corresponding values ​​are arranged in an arithmetic progression;

[0086] Weather conditions :Weather conditions directly affect production efficiency. For example, bad weather can lead to reduced production efficiency and delivery time, such as transportation delays. Weather conditions can also indirectly affect the stability of raw material supply. To ensure the accuracy of the weather, the weather conditions can correspond to the meteorological warnings of external equipment. Weather conditions The formula is as follows:

[0087] ;

[0088] in:

[0089] For the best weather condition, the value is 10;

[0090] For the worst weather condition, the value is -10;

[0091] The corresponding weather conditions gradually become worse, and the corresponding values ​​are arranged in an arithmetic progression;

[0092] Traffic status Traffic conditions directly affect transportation efficiency and delivery time. Traffic congestion or accidents can cause transportation delays, which in turn affects the execution of production plans and the satisfaction of delivery dates. The formula is expressed as follows according to the road congestion status:

[0093] ;

[0094] in:

[0095] For the most congested state, the value is -10;

[0096] The most unobstructed state is assigned a value of 10;

[0097] The corresponding road traffic gradually becomes smoother, and the corresponding values ​​are arranged in an arithmetic progression;

[0098] Raw material inventory :The inventory level of raw materials directly affects whether the production can proceed smoothly. Insufficient inventory can lead to production interruption, while excessive inventory can increase storage costs. The formula is expressed as follows based on the current inventory:

[0099] ;

[0100] in:

[0101] The most shortage state, that is, the current inventory is lower than the minimum inventory, is assigned a value of -10;

[0102] The most sufficient state, that is, the current inventory is higher than the safety stock, is assigned a value of 10;

[0103] The corresponding inventory gradually increases, and the corresponding values ​​are arranged in an arithmetic progression;

[0104] Production equipment status :The status of production equipment directly affects production efficiency. Equipment failure or maintenance requirements may lead to production suspension or reduced efficiency. The formula is expressed as follows according to the current state of the device:

[0105] ;

[0106] in:

[0107] The most faulty state of the equipment, that is, the state of being unable to work, is assigned a value of -10;

[0108] The maximum efficiency state is the stable and efficient operation state, and the value is 10;

[0109] The corresponding equipment operating efficiency gradually increases, and the corresponding values ​​are arranged in an arithmetic progression;

[0110] Delivery deadline :Delivery deadline is an external constraint of production plan, which requires that production must be completed within a specified time. The urgency of delivery deadline can prompt enterprises to take various measures to improve production efficiency and shorten production cycle. The formula is expressed as follows based on the current completed time:

[0111] ;

[0112] in:

[0113] The state with the longest delivery deadline delay is assigned a value of -10;

[0114] The state with the longest lead time for delivery deadline is assigned a value of 10;

[0115] The corresponding lead time for delivery gradually increases, and the corresponding values ​​are arranged in an arithmetic progression;

[0116] According to the above content, each factor is weighted to obtain the weighted parameters:

[0117] ;

[0118] According to the formula content, The parameter score is obtained according to the assignment. The higher the score, the higher the priority. The lower the score, the lower the priority. The specific value of the corresponding assignment can be set according to the actual assignment range. For example, if the assignment range is set in The interval between values ​​is 1, etc., and is set in combination with actual numerical requirements. At the same time, the longest state and the most unobstructed state in the above content are based on the relative amount of the values. These factors will be used as input parameters and encoded into chromosomes, that is, the production order of task volume A. In order to facilitate the sorting of task volume A, the elite selection method is used to select the task volume A from the production order. Select individuals from the population, perform crossover operations, and generate new production scheduling plans Then, fitness evaluation, selection and genetic operation are repeated, and the multiple production scheduling schemes obtained form a population , and there is , each It contains all , the difference is that each in of The production order is different until the predetermined number of iterations is reached or the termination condition is met, and the individual with the highest fitness is selected from the population , as the optimal production scheduling plan, the optimal production scheduling plan is decoded into the actual production task arrangement and output.

[0119] In actual use, the number of iterations is set according to the number of ready-mixed concrete tasks. Generally, the number of iterations is set to 3-5 times. However, there is no direct linear relationship between the number of ready-mixed concrete tasks and the number of iterations. The number of iterations increases according to the amount of tasks. If the amount of tasks is large, the amount of production scheduling parameter processing required increases. In order to ensure that the accuracy meets the requirements, more iterations are required. On the contrary, if the amount of tasks is small, only the conventional setting of 3-5 iterations can meet the requirements of optimal production scheduling, so the number of iterations is set to be small. Specific embodiment four:

[0121] like Figure 1 As shown, according to the content of the specific embodiment 4, the following contents are further disclosed:

[0122] When using the weighted values ​​for each factor, the following are provided:

[0123] The project progress is graded according to percentage. , the corresponding assignment is ;

[0124] Weather conditions , the corresponding assignment is ;

[0125] Traffic status , the corresponding assignment is ;

[0126] Raw material inventory sets one or more thresholds to define the status, set , Among them are , the corresponding assignment is ;

[0127] The status of production equipment is classified according to the operating status. , the corresponding assignment is ;

[0128] The delivery deadline is a specific time point or time period, expressed as a percentage. , the corresponding assignment is, ;

[0129] The above parameters are graded and integrated, and the numerical scores are matched with the above sets, and the specific content of the scoring is put into the formula Perform weighted summation in .

[0130] Suppose there are two tasks, Task 1 and Task 2, and their scores are as follows:

[0131] Task 1: Progress score 3, weather score +2, traffic score +2, inventory score +2, equipment score +2, delivery deadline score -1;

[0132] Task 2: Progress score 2, Weather score -2, Traffic score 0, Inventory score 0, Equipment score -2, Delivery deadline score -3,

[0133] Their combined scores are:

[0134] Task 1: 3+2+2+2+2-1=10

[0135] Task 2: 2-2+0+0-2-3=-5

[0136] Therefore, Task 1 has a higher priority than Task 2. Specific embodiment five:

[0138] like Figure 1 As shown, according to the contents of specific embodiments 1, 2, 3 and 4, the following technical solutions are further disclosed:

[0139] The concrete production requirements in the raw material ratio optimization system include at least parameter requirements for physical properties, workability, durability, mechanical properties, chemical properties and other properties, and the physical properties include at least density, water absorption rate, and porosity; the workability includes at least cohesion, water retention, and fluidity; the durability includes at least impermeability, frost resistance, and hydrochloric acid corrosion resistance; the mechanical properties include at least tensile strength, flexural strength, and compressive strength; the chemical properties include at least alkali content and sulfur trioxide content, and the corrosion resistance coefficient of cementitious materials; other properties include at least water bleeding rate, air content, carbonization performance, and bubble spacing coefficient.

[0140] In the raw material ratio optimization system, the content of the ratio optimization algorithm is as follows:

[0141] Sp1: Input data processing: Obtain the production scheduling plan including production tasks, time, quantity and performance requirements from the intelligent production scheduling optimization system, and analyze the specific performance requirements of ready-mixed concrete in each production task;

[0142] Sp2: Initial mix ratio calculation: Establish or reference a database containing various basic mix ratios of concrete. These basic mix ratios are based on past experimental data or industry standards. According to the specific requirements of the current task, select the closest mix ratio from the basic mix ratio database as the initial mix ratio, or calculate the initial mix ratio according to the empirical formula;

[0143] Sp3: Feedback mechanism adjustment: The real-time parameters of concrete during processing are obtained through the machine vision detection system, and the monitored parameters are compared with the target parameters to evaluate the effect of the current mix ratio. If the parameters do not meet the requirements, the linear programming optimization method is used to fine-tune the mix ratio according to the deviation size and direction to generate a new optimized mix ratio;

[0144] Sp4: Iterative optimization and output: Put the new ratio into production, continue to monitor it through the machine vision inspection system, repeat the above comparison, evaluation and adjustment process until all monitoring parameters meet or exceed the target requirements. When all parameters meet the standards, determine the final optimized ratio and output it to the production system, and record the optimization process and results in the database.

[0145] In the process of raw material proportioning, the performance proportions of ready-mixed concrete mainly exist in the following forms:

[0146] The first type is that the task accurately specifies the specific range of each performance of concrete. The raw material ratio optimization system mixes multiple raw materials, such as cement, sand, and gravel, to make the formed concrete reach its specified parameter range;

[0147] The second type is that the task part specifies the range of various properties of concrete. After ensuring that various parameters of ready-mixed concrete meet the target requirements, the raw material ratio optimization system sets other parameters according to the conventional parameters of concrete;

[0148] The third type is that the task does not specify the parameters of the concrete, but limits the usage scenarios and functions. The raw material ratio optimization system combines the conventional basic ratios in the database with experimental data or industry standards to use the corresponding concrete ratio.

[0149] During the entire proportioning process, on the basis of considering the characteristics of concrete itself, the environmental factors and equipment factors given by the intelligent production scheduling optimization system are simultaneously taken into account within the scope, so as to adapt to the concrete status requirements in each process of production and transportation.

[0150] In view of the above content, the detailed description of the ratio optimization algorithm using nonlinear programming in this application is as follows:

[0151] In concrete mix optimization, the objective function is generally the sum of minimizing cost and maximizing performance parameters. Minimizing cost includes factors such as the market price of raw materials, transportation costs, and energy consumption in the production process. Maximizing the sum of performance parameters includes weighted factors such as strength, durability, and workability. Therefore, the objective function is set as:

[0152] ;

[0153] in:

[0154] Indicates Amount of raw materials used;

[0155] is the unit cost of raw materials;

[0156] is the number of types of raw materials.

[0157] The constraint adjustment is implemented by adopting various performance factors of concrete, including:

[0158] Physical property constraints: Concrete density, water absorption, etc. need to meet specific standards or design requirements;

[0159] Working performance constraints: including cohesion, water retention, etc., which directly affect the construction performance and final quality of concrete;

[0160] Durability constraints: such as impermeability and freeze-thaw resistance, are important indicators for evaluating the long-term performance of concrete;

[0161] Mechanical property constraints: such as compressive strength and tensile strength, which are directly related to the bearing capacity and safety of concrete structures;

[0162] Chemical property constraints: such as alkali-aggregate reaction and chloride ion content, need to be controlled within a certain range to avoid potential chemical damage.

[0163] In actual use, special optimization software or libraries can be used, such as of , of Through the above content, the precise proportion and adaptability of the parameters of ready-mixed concrete can be achieved, and the proportion can be integrated with environmental factors, equipment factors and performance requirements to control the proportion, with high accuracy and strong adaptability, avoiding waste of resources and improving the utilization rate of various raw materials.

[0164] In the raw material ratio optimization system, the content of the image processing algorithm is as follows:

[0165] Sp1: Image preprocessing: Use median filtering and Gaussian filtering to remove noise from the image, and enhance the visibility of key features in the image by contrast adjustment and sharpening;

[0166] Sp2: Feature Extraction: Using color space conversion and texture analysis techniques, we can identify the color and texture changes of concrete to assess its uniformity and condition. Edge detection and Hough transform methods are used to identify boundary and shape features in concrete samples;

[0167] Sp3: Parameter calculation: Based on the results of edge detection, the slump is estimated by calculating the height and diameter parameters of the slump body. The moisture content and density of the concrete are indirectly inferred through color distribution and texture characteristics. The camera is equipped with infrared function, which can directly read the temperature distribution on the concrete surface:

[0168] Sp4: Data integration and output: Integrate the extracted parameters into a unified data format to facilitate subsequent analysis and processing, and transmit the monitored parameters to the ratio optimization algorithm in real time as a basis for feedback adjustment.

[0169] Since the image processing algorithm is a mature and public technical content in actual use, the existing image processing algorithm is directly used in this application. The entire detection process is described based on the above content. The specific technical content and how to perform the detection are described. For edge detection and feature extraction, etc., you can refer to the corresponding image processing algorithm content for use. This method can achieve intelligent proportioning of concrete as required, avoid waste of resources, have strong adaptability, high proportioning accuracy, and better meet actual usage needs. Specific embodiment six:

[0171] like Figure 1 As shown, according to the contents in the above specific embodiments, the following technical solutions are further disclosed:

[0172] For the supply chain management system, each blockchain adopts the following content when controlling information transmission:

[0173] RFID technology: used for automated management of raw material inventory. RFID tags are attached to each raw material package or storage container, and scanned by RFID readers at the warehouse entrance, exit and key storage areas to update inventory information in real time.

[0174] IoT sensors: deployed at key nodes such as logistics vehicles and construction site equipment to collect logistics status such as vehicle location, speed, temperature and humidity, and construction progress information such as concrete pouring progress and equipment operating status;

[0175] Smart contracts are implemented using blockchain platforms such as Ethereum. The regional chain platform is used to implement smart contracts to ensure that transactions between raw material suppliers, logistics service providers and construction sites are transparent, tamper-proof and automatically executed. Smart contracts automatically trigger payment or the next step according to preset conditions such as arrival of goods and acceptance.

[0176] Data Transfer and Integration:

[0177] The supply chain management system communicates with the raw material suppliers, logistics service providers, and construction sites of all parties involved. or etc. interfaces for data exchange;

[0178] Message queues such as , : Used to handle asynchronous data transmission in high-concurrency situations, ensuring reliable data transmission and system decoupling;

[0179] Cloud storage and data processing , : Use cloud service providers’ storage services to store massive amounts of data and use their big data processing tools such as , Conduct data analysis to provide data support for the intelligent production scheduling optimization system.

[0180] The transmission connection between adjacent areas adopts a cloud-edge collaborative architecture, that is, after the data is initially processed by edge devices such as RFID readers and IoT sensors, it is transmitted through wired or wireless networks such as 4G / 5G, Transmitted to cloud data center for further processing and analysis, using The protocol encrypts data transmission to ensure the security of information during transmission. API Interface and message queue mechanism realize data synchronization and integration between modules within the supply chain management system and with external systems, ensuring the real-time and consistency of data.

[0181] The entire supply chain management system can be divided into the following levels:

[0182] Perception layer: including RFID tags, IoT sensors, etc., responsible for collecting raw data;

[0183] Network layer: responsible for transmitting the data of the perception layer to the data center through wired or wireless networks;

[0184] Platform layer: including cloud storage, big data processing platform, blockchain platform, etc., to store, process and analyze data, and run smart contracts;

[0185] Application layer: including intelligent production scheduling optimization system, visualization tools, etc., providing an intuitive interface to display information such as production scheduling, inventory status, logistics tracking, etc., to facilitate managers to monitor and adjust in real time, and provide users with decision support and information display.

[0186] Through such a technical architecture and implementation method, we can effectively solve the problems of untimely information and difficult cooperation in traditional supply chain management, improve the speed of information response, and achieve unified management of ready-mixed concrete and rapid response of information. Specific embodiment seven:

[0188] like Figure 1 As shown, according to the contents in the above specific embodiments, the following technical solutions are further disclosed:

[0189] The production monitoring display and early warning system further includes the following contents:

[0190] Sensor deployment and data collection: According to the characteristics of production equipment and monitoring requirements, select appropriate sensors, such as temperature sensors, pressure sensors, vibration sensors, flow sensors, and electric energy meters, to collect equipment operating parameters and energy consumption data. Sensors are connected through wired or wireless methods such as , , The collected data is transmitted to the data collection node or directly uploaded to the cloud server, and the received raw data is cleaned, filtered and preliminarily analyzed to remove noise data and improve data quality. Stream processing technology such as , Process real-time data streams to ensure that the system can quickly respond to changes in device status. According to preset thresholds and algorithms, the device operating status is evaluated to determine whether it is within the normal range.

[0191] UI interactive design, design an intuitive dashboard interface, display the operating status, production efficiency, energy consumption and other important indicators of production equipment in real time, provide historical data query function, users can filter and view historical data according to time range, equipment type and other conditions, conduct trend analysis and comparative analysis, when the equipment is in an abnormal state, it will be highlighted on the UI interface through color changes, flashing, etc. to remind the operator to pay attention, use charts such as line charts, bar charts, pie charts, etc. and equipment distribution charts to display production data, making the information more intuitive and easy to understand, and generate interactive production reports. Users can click on the charts or data points in the report to further view detailed information and related data.

[0192] Anomaly detection sets upper and lower thresholds for equipment operating parameters, triggers an early warning when the parameters exceed the threshold, uses machine learning algorithms to perform pattern recognition on equipment operating data, identifies abnormal patterns and triggers early warnings, sets different early warning levels such as warnings, alarms, and emergencies according to the degree of abnormality, and sends early warning notifications to relevant personnel through different channels such as SMS, email, and APP push, formulates emergency response procedures, clarifies response measures and responsible persons under different warning levels, and ensures that anomalies can be handled in a timely manner.

[0193] After the processing is completed, the system classifies and integrates the monitoring data of the entire production cycle, including equipment operation data, energy consumption data, production status data, etc. interface or message queue mechanism to transmit the integrated data back to various related systems such as system, Systems, intelligent production scheduling systems, etc. provide data support for algorithm optimization. Based on the returned production data and equipment status information, intelligent algorithms are used to optimize and adjust the production schedule to improve production efficiency and resource utilization. Combined with factors such as raw material quality, equipment performance, and production environment, intelligent algorithms are used to optimize and adjust the proportion of ready-mixed concrete to improve product accuracy and quality stability.

[0194] Through the above content, it can be ensured that the production monitoring display and early warning system can effectively monitor and intelligently control the production equipment, and improve the processing efficiency and accuracy of ready-mixed concrete.

[0195] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the statement "comprising a reference structure" do not exclude the existence of other identical elements in the process, method, article or device including the elements.

[0196] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. The intelligent production scheduling system for ready-mixed concrete based on data adjustment is characterized by: The system includes a supply chain management system, an intelligent production scheduling optimization system, a raw material ratio optimization system, and a production monitoring display and early warning system, among which: The supply chain management system is connected with raw material suppliers, logistics service providers and construction sites to collect and manage information on raw material inventory, logistics status and construction progress, and transmit the collected information to the intelligent production scheduling optimization system; The intelligent production scheduling optimization system is internally provided with an intelligent production scheduling optimization algorithm, receives data provided by the supply chain management system, integrates and weights the environmental factors and implementation factors affecting the ready-mixed concrete, and gives the optimal production scheduling plan for the ready-mixed concrete under the weighted constraints of maintaining the minimum production cost, maximizing the production efficiency and the optimal delivery date; the contents of the intelligent production scheduling optimization algorithm in the intelligent production scheduling optimization system are as follows: The intelligent production scheduling optimization algorithm is expanded based on the genetic algorithm, and the book structure of the production scheduling plan is defined, including the task list, task start time and end time, and the parameters of the algorithm are set, including the population size, number of iterations and crossover probability. The formula is as follows: ; in: To plan production; The total production cost of the current production schedule; It is production efficiency; Actual delivery date; Optimal delivery date; , , is the weight coefficient, and ; is the maximum delivery delay allowed; According to the above formula, the project progress based on environmental factors , Weather conditions , Traffic status , raw material inventory of implementation factors , Production equipment status , Delivery deadline , the minimum production cost of the target parameter , maximize production efficiency , optimal delivery time are input parameters, where: Project Progress :The project progress will affect the production plan. If the progress of a project is ahead of schedule, it will require the progress of related production tasks to be accelerated. If the progress lags behind, the production plan needs to be adjusted to adapt to the new time requirements. The formula is expressed as follows according to the progress percentage: ; in: For the minimum percentage, assign a value of -10; The maximum percentage, i.e. the progress closest to completion, is assigned a value of 10; The corresponding project progress is gradually approaching completion, and the corresponding values ​​are arranged in an arithmetic progression; Weather conditions :Weather conditions directly affect production efficiency. Bad weather can lead to reduced production efficiency and delayed delivery. Weather conditions can also indirectly affect the stability of raw material supply. To ensure the accuracy of the weather, the weather conditions can correspond to the meteorological warnings of external equipment. The formula is as follows: ; in: For the best weather condition, the value is 10; For the worst weather condition, the value is -10; The corresponding weather conditions gradually become worse, and the corresponding values ​​are arranged in an arithmetic progression; Traffic status Traffic conditions directly affect transportation efficiency and delivery time. Traffic congestion or accidents can cause transportation delays, which in turn affects the execution of production plans and the satisfaction of delivery dates. The formula is expressed as follows according to the road congestion status: ; in: For the most congested state, the value is -10; The most unobstructed state is assigned a value of 10; The corresponding road traffic gradually becomes smoother, and the corresponding values ​​are arranged in an arithmetic progression; Raw material inventory :The inventory level of raw materials directly affects whether the production can proceed smoothly. Insufficient inventory can lead to production interruption, while excessive inventory can increase storage costs. The formula is expressed as follows based on the current inventory: ; in: The most shortage state, that is, the current inventory is lower than the minimum inventory, is assigned a value of -10; The most sufficient state, that is, the current inventory is higher than the safety stock, is assigned a value of 10; The corresponding inventory gradually increases, and the corresponding values ​​are arranged in an arithmetic progression; Production equipment status :The status of production equipment directly affects production efficiency. Equipment failure or maintenance requirements may lead to production suspension or reduced efficiency. The formula is expressed as follows according to the current state of the device: ; in: The most faulty state of the equipment, that is, the state of being unable to work, is assigned a value of -10; The maximum efficiency state is the stable and efficient operation state, and the value is 10; The corresponding equipment operating efficiency gradually increases, and the corresponding values ​​are arranged in an arithmetic progression; Delivery deadline :Delivery deadline is an external constraint of production plan, which requires that production must be completed within a specified time. The urgency of delivery deadline can prompt enterprises to take various measures to improve production efficiency and shorten production cycle. The formula is expressed as follows based on the current completed time: ; in: The state with the longest delivery deadline delay is assigned a value of -10; The state with the longest lead time for delivery deadline is assigned a value of 10; The corresponding lead time for delivery gradually increases, and the corresponding values ​​are arranged in an arithmetic progression; According to the above content, each factor is weighted to obtain the weighted parameters: ; According to the formula content, the parameter score is obtained according to the assigned value. The higher the score, the higher the priority. The lower the score, the lower the priority. At the same time, the longest state and the most unobstructed state in the above content are based on the relative amount of the numerical value. These factors will be used as input parameters and encoded into the chromosome, that is, the production order of task volume A. In order to facilitate the sorting of task volume A, the elite selection method is used to sort the task volume A. Select individuals from the population, perform crossover operations, and generate new production scheduling plans Then, fitness evaluation, selection and genetic operation are repeated, and the multiple production scheduling schemes obtained form a population , and there is , each It contains all , the difference is that each in of The production order is different until the predetermined number of iterations is reached or the termination condition is met, and the individual with the highest fitness is selected from the population , as the optimal production scheduling plan, decode the optimal production scheduling plan into the actual production task arrangement and output it; The raw material ratio optimization system is internally provided with a ratio optimization algorithm, receives the optimal production scheduling scheme given by the intelligent production scheduling optimization system, gives the initial optimized ratio of the ready-mixed concrete according to the target data of the production demand for ready-mixed concrete in each task, and puts it into processing and production. During the processing, machine vision detection is performed, and the camera is used in conjunction with the image processing algorithm to monitor various parameters during the processing of ready-mixed concrete. If the parameters meet the requirements, the finished product is output. If not, the monitored data is fed back to the ratio optimization algorithm, and the current data is combined with the target data to increase the concrete ingredients to obtain the repeatedly optimized ratio, and the processing, production, monitoring, and feedback are continued until the parameters of the concrete meet the requirements and the finished product is output. In the raw material ratio optimization system, the content of the ratio optimization algorithm is as follows: Sp1: Input data processing: Obtain the production scheduling plan including production tasks, time, quantity and performance requirements from the intelligent production scheduling optimization system, and analyze the specific performance requirements of ready-mixed concrete in each production task; Sp2: Initial mix ratio calculation: Establish or reference a database containing various basic mix ratios of concrete. These basic mix ratios are based on past experimental data or industry standards. According to the specific requirements of the current task, select the closest mix ratio from the basic mix ratio database as the initial mix ratio, or calculate the initial mix ratio according to the empirical formula; Sp3: Feedback mechanism adjustment: The real-time parameters of concrete during processing are obtained through the machine vision detection system, and the monitored parameters are compared with the target parameters to evaluate the effect of the current mix ratio. If the parameters do not meet the requirements, the linear programming optimization method is used to fine-tune the mix ratio according to the deviation size and direction to generate a new optimized mix ratio; Sp4: Iterative optimization and output: Put the new ratio into production, continue to monitor it through the machine vision inspection system, repeat the above comparison, evaluation and adjustment process until all monitoring parameters meet or exceed the target requirements. When all parameters meet the standards, determine the final optimized ratio and output it to the production system, and record the optimization process and results in the database; The production monitoring display and early warning system integrates Internet of Things technology to monitor and intelligently control production equipment, collects equipment operation data and energy consumption data through sensors for monitoring, conducts production monitoring and early warning of abnormal conditions, stores data and interactively displays the production status through the UI, and connects with various systems. After processing, the work adjustment data of the entire system is classified and integrated, and transmitted back to each system accordingly for algorithm optimization.

2. The data-adjusted ready-mixed concrete intelligent production scheduling system according to claim 1 is characterized in that: The supply chain management system uses the Internet of Things and RFID technology to track logistics and automate inventory management. In the supply chain management system, transactions are conducted between raw material suppliers, logistics service providers and construction sites through smart contracts.

3. The data-adjusted ready-mixed concrete intelligent production scheduling system according to claim 1 is characterized in that: The data of environmental factors and implementation factors in the intelligent production scheduling optimization system are provided by the supply chain management system, and the environmental factors include project progress, weather conditions and traffic conditions, and the implementation factors include raw material inventory, production equipment status and delivery deadline.

4. The data-adjusted ready-mixed concrete intelligent production scheduling system according to claim 1 is characterized in that: The concrete production requirements in the raw material ratio optimization system include parameter requirements of physical properties, work performance, durability, mechanical properties, chemical properties and other properties, and the physical properties include density, water absorption rate, and porosity; the work performance includes cohesion, water retention, and fluidity; the durability includes impermeability, frost resistance, and hydrochloric acid corrosion resistance; the mechanical properties include tensile strength, flexural strength, and compressive strength; the chemical properties include alkali content and sulfur trioxide content, and the corrosion resistance coefficient of cementitious materials; and other properties include water bleeding rate, air content, carbonization performance, and bubble spacing coefficient.

5. The data-adjusted ready-mixed concrete intelligent production scheduling system according to claim 1 is characterized in that: In the raw material ratio optimization system, the content of the image processing algorithm is as follows: Sp1: Image preprocessing: Use median filtering and Gaussian filtering to remove noise in the image, and enhance the visibility of key features in the image by contrast adjustment and sharpening; Sp2: Feature extraction: Using color space conversion and texture analysis techniques, identify the color and texture changes of concrete to evaluate its uniformity and condition, through Edge detection and Hough transform methods are used to identify boundary and shape features in concrete samples; Sp3: Parameter calculation: Based on the results of edge detection, the slump is estimated by calculating the height and diameter parameters of the slump body. The moisture content and density of the concrete are indirectly inferred through color distribution and texture characteristics. The camera is equipped with infrared function, which can directly read the temperature distribution on the concrete surface: Sp4: Data integration and output: Integrate the extracted parameters into a unified data format to facilitate subsequent analysis and processing, and transmit the monitored parameters to the ratio optimization algorithm in real time as a basis for feedback adjustment.

6. The data-adjusted ready-mixed concrete intelligent production scheduling system according to claim 1 is characterized in that: The intelligent production scheduling optimization system dynamically adjusts parameters according to the dynamic changes of environmental factors and implementation factors, and outputs the adjusted optimal production scheduling plan. The raw material ratio optimization system dynamically adjusts the start sequence of ready-mixed concrete tasks according to the dynamically adjusted optimal production scheduling plan. The raw material ratio optimization system uses the basic parameter information of ready-mixed concrete provided by the database in the production monitoring display and early warning system, and the data combined with the actual concrete production demand as the input data of the ratio optimization algorithm.

Citation Information

Patent Citations

  • Big data quality supervision method for premixed concrete

    CN107203829A

  • An intelligent management system for construction site of ready-mixed concrete pouring

    CN117910781B

  • Concrete detection method and device based on machine vision

    CN115683225A

  • Concrete production schedule processing method and system

    CN117371713A

  • Automatic proportioning method and system for civil construction mixed materials

    CN117610435A