Method, device and equipment for optimizing maintenance plan of integrated power generation and transmission
Through the integrated maintenance optimization method of power transmission and transmission, the virtual maintenance costs and inertia levels of various types of equipment are calculated, and the optimization model is constructed, which solves the problem of inertia differences in equipment under different installation structures in the existing technology, and improves the system safety and stability guarantee. .
Patent Information
- Application Number
- CN202410977259.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-22
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2044-07-22
AI Technical Summary
When the prior art is optimizing the maintenance plan of power generation and transmission equipment, it is unable to adapt to the impact of differences in inertia parameters of multiple types of equipment under different power generation installation structures on the safety and reliability of the system, resulting in the lack of sufficient available equipment in the system during certain periods, affecting the safety of the system. Stablize.
A comprehensive maintenance plan optimization method for power generation and transmission is adopted. By obtaining basic data, the virtual maintenance cost and inertia level of various types of equipment are calculated, and an integrated maintenance optimization model for power generation and transmission is constructed, including objective functions and constraints, and N-1 safety calibration is carried out. The system inertia verification is performed in the core and fault state, and the maintenance plan is adjusted to meet the system inertia needs.
The system safety guarantee has been improved, the maintenance plan guarantees the safe and stable operation of the system has been improved, and the system inertia needs and inertia parameters of multiple types of equipment have been evaluated to ensure the stability of the system under different operating conditions.
Smart Images

Figure CN118521296B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of power grid maintenance, and in particular to a method, device and equipment for optimizing a maintenance plan for integrated power generation and transmission. Background Art
[0002] The preparation of maintenance plans for power generation and transmission equipment is an important part of power grid dispatching. During the maintenance plan window, power generation and transmission equipment will be shut down for maintenance, which will inevitably affect the dispatching decision-making process such as unit combination and economic dispatch, and thus affect the safety, reliability and economy of the entire power system. The maintenance plan is mainly divided into unit maintenance plan and line maintenance plan. Due to the electrical topology connection relationship, the maintenance plans of units and lines affect each other.
[0003] After receiving the maintenance time of the power generation and transmission equipment, the grid dispatching center will jointly optimize the maintenance plan of the generator set and the line based on the load forecast and other related boundary information, with the goal of meeting the system safety requirements and minimizing the adjustment willingness maintenance time, taking into account constraints such as power balance, section flow, system backup, and expert library (simultaneous, sequential, mutually exclusive). However, with the large-scale grid connection of fluctuating new energy, the safe and stable operation of the high-proportion new energy power system faces more severe challenges. At present, the power system regulation resources are mainly thermal power. Compared with new energy units, thermal power units of the same capacity level can provide more system inertia. With the continuous increase in the proportion of new energy installed capacity, the system inertia level and anti-interference ability continue to decline. Ensuring sufficient system inertia level is crucial for the safe and reliable operation of the system.
[0004] Therefore, when optimizing maintenance plans, the existing technology cannot adapt to the impact of differences in inertia parameters of various types of power generation and transmission equipment under different power generation installed structures in the power system on system operation. There may not be enough available equipment to meet the system inertia requirements in certain periods of time, which in turn affects the safety and stability level of the system. Summary of the invention
[0005] In view of this, the purpose of the present invention is to provide a method, device and equipment for optimizing the integrated power generation and transmission maintenance plan, so as to overcome the problem that when optimizing the maintenance plan, it is currently impossible to adapt to the impact of the inertia parameter differences of multiple types of power generation and transmission equipment under different power generation installed structures on the safety and reliability of the system.
[0006] To achieve the above objectives, the present invention adopts the following technical solutions:
[0007] On the one hand, a method for optimizing a power generation and transmission integrated maintenance plan includes:
[0008] Obtaining basic data of a target power grid maintenance plan, wherein the target power grid maintenance plan includes: a power generation and transmission equipment maintenance plan and a line maintenance plan;
[0009] Determine the virtual maintenance cost of each type of power generation and transmission equipment based on the basic data;
[0010] Calculate the inertia level that can be provided by various types of power generation and transmission equipment; and calculate the minimum inertia requirement of the target power grid system at different times;
[0011] According to the virtual maintenance cost, inertia level and minimum inertia requirement of the power generation and transmission equipment, an optimization model for the integrated maintenance plan of power generation and transmission is constructed, and the target maintenance plan is obtained by solving the model; wherein the optimization model for the integrated maintenance plan of power generation and transmission includes: an objective function and constraint conditions;
[0012] Perform N-1 safety verification and fault state system inertia verification on the target maintenance plan, and adjust the target maintenance plan according to the verification results.
[0013] Optionally, the virtual maintenance cost is recorded as , indicating the device First The virtual cost of the maintenance start time is one operating day;
[0014] The calculation of the inertia level that can be provided by various types of power generation and transmission equipment includes:
[0015] Calculate the inertia that can be provided by the thermal power unit: ;
[0016] Calculate the inertia that the wind turbine can provide: ;
[0017] Calculate the inertia that the photovoltaic system can provide: ;
[0018] Calculate the inertia that the energy storage device can provide: E ES,i ;
[0019] Among them, E TH,i is the moment of inertia of the ith thermal power unit, P TH,i is the rated power of the i-th thermal power unit, H TH,i is the inertia time constant of the ith thermal power unit, E WI,i is the virtual inertia of the i-th wind turbine, P WI,i is the rated power of the i-th wind turbine, H WI,i is the inertia time constant of the i-th wind turbine, E SO,i is the virtual inertia of the ith PV unit, P SO,i is the rated power of the ith photovoltaic unit, H SO,i is the inertia time constant of the ith photovoltaic unit, E ES,iis the virtual inertia of the i-th energy storage device, P ES,i is the rated power of the i-th energy storage device, H ES,i is the inertia time constant of the i-th energy storage device.
[0020] Optionally, the minimum inertia requirement of the target power grid system is:
[0021]
[0022]
[0023] in, The minimum system inertia required for the system base state to cope with the power loss caused by system fluctuations, The minimum system inertia required to cope with power loss when a single machine fails. is the rated frequency, is the maximum power shortage of the system caused by the fault, is the maximum frequency change rate that the system can follow, The system inertia loss caused by the fault.
[0024] Optionally, it also includes: Setting maintenance priority parameters , indicating the device The maintenance priority and actual unit maintenance willingness cost are ;
[0025] The objective function is: ; Among them, NG is the total number of all overhauled equipment, ND is the total number of operating days, For equipment First The virtual cost of the maintenance start time is one operating day;
[0026] The constraints include:
[0027] The maintenance days are constrained as follows:
[0028] in, For power transmission equipment No. Maintenance status variables for each operating day; is the total number of operating days; For power transmission equipment The number of days the maintenance plan needs to last;
[0029] Maintenance status constraints:
[0030]
[0031] in, For power transmission equipment In the The maintenance start state variable of the operation day, when the value is 1, it means The maintenance starts on the first operation day, and the value of the remaining operation days is 0; For power transmission equipment In the Maintenance termination status variables for each operation day; , the number of days from the start of maintenance to the end of maintenance is .
[0032] Optionally, the constraint condition further includes an expert database constraint; the expert database constraint includes:
[0033] Mutually exclusive constraints:
[0034] i.e. Device and equipment At most, only one device can be under maintenance on the same day;
[0035] Order constraints:
[0036]
[0037] That is, equipment j needs to be repaired after equipment i is repaired, where: Any day within the total number of operating days;
[0038] At the same time constraints: , that is, equipment i and equipment j need to be repaired at the same time.
[0039] Optionally, the constraint conditions further include unit and power grid operation constraints; the unit and power grid operation constraints include:
[0040] Unit output upper and lower limit constraints:
[0041] Among them, the period Operation day Within the period of time, For equipment In the Within operating days The output level of the time period, and Equipment The lower and upper limits of output;
[0042] System spare capacity constraints:
[0043] in, is the number of all devices, No. The maximum load of the operating day, For the System reserve rate requirements for each operating day;
[0044] Base state power flow constraints:
[0045] in, , For Line The lower and upper limits of the transmission power, For power generation equipment To line The node-line power transfer distribution factor, For load To line The node-line power transfer distribution factor, For Node In the period The node load prediction value is is the total number of power generation equipment in the system, is the total number of load nodes in the system, is the total number of lines in the network topology.
[0046] Optionally, the constraint condition further includes a system inertia constraint; the system inertia constraint includes:
[0047]
[0048] in, , , , They are the total number of thermal power, wind power, photovoltaic and energy storage equipment respectively.
[0049] Optionally, the constraint condition of the N-1 safety check is:
[0050]
[0051] in, For the line that is assumed to have a fault, is the N-1 fault set; For Line Fault on line The breaking transfer distribution factor; , Equipment and load To line The node-line power transfer factor of
[0052] The constraint conditions for the fault state system inertia verification are:
[0053]
[0054] in, The equipment that has failed is the unit with the largest single-unit capacity among the units that have not been repaired. is the maximum power shortage of the system caused by the failure of device c, is the system inertia corresponding to the faulty unit.
[0055] In another aspect, a device for optimizing a power generation and transmission integrated maintenance plan comprises:
[0056] An acquisition module is used to acquire basic data of a target power grid maintenance plan, wherein the target power grid maintenance plan includes: a power generation and transmission equipment maintenance plan and a line maintenance plan;
[0057] A parameter initialization module, used to determine the virtual maintenance cost of each type of power generation and transmission equipment according to the basic data;
[0058] An inertia parameter calculation module is used to calculate the inertia level that can be provided by various types of power generation and transmission equipment; and calculate the minimum inertia requirement of the target power grid system in a time-sharing manner;
[0059] Constructing a solution module, for constructing an optimization model for the integrated maintenance plan of power generation and transmission according to the virtual maintenance cost, inertia level, and minimum inertia requirement of the power generation and transmission equipment, and solving the model to obtain a target maintenance plan; wherein the optimization model for the integrated maintenance plan of power generation and transmission includes: an objective function and constraint conditions;
[0060] The verification module is used to perform N-1 safety verification and fault state system inertia verification on the target maintenance plan, and adjust the target maintenance plan according to the verification results.
[0061] In another aspect, a device for optimizing a power generation and transmission integrated maintenance plan includes a processor and a memory, wherein the processor is connected to the memory:
[0062] Wherein, the processor is used to call and execute the program stored in the memory;
[0063] The memory is used to store the program, and the program is used to execute at least any one of the above-mentioned methods for optimizing the integrated power generation and transmission maintenance plan.
[0064] The technical solution provided by the present invention has at least the following beneficial effects:
[0065] By adopting the technical solution of this embodiment, after obtaining the basic data of the target power grid maintenance plan, the virtual maintenance cost, inertia level, minimum inertia requirement, etc. of the power generation and transmission equipment are calculated respectively, so as to construct an integrated power generation and transmission maintenance optimization model, solve the model to obtain the target for planning, and adjust the target maintenance plan in real time. Among them, the inertia demand of the system and the inertia parameters corresponding to various types of power generation equipment are evaluated in detail, which improves the guarantee of system safety; the inertia verification of the fault state system is adopted to improve the guarantee level of system safety and stability corresponding to the maintenance plan. BRIEF DESCRIPTION OF THE DRAWINGS
[0066] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0067] Figure 1 A schematic flow chart of a method for optimizing a power generation and transmission integrated maintenance plan provided in one embodiment of the present invention;
[0068] Figure 2 A schematic diagram of a virtual maintenance cost curve provided by an embodiment of the present invention;
[0069] Figure 3 A schematic diagram of the structure of a device for optimizing the maintenance plan for integrated power generation and transmission provided by one embodiment of the present invention;
[0070] Figure 4 A schematic diagram of the structure of a power generation and transmission integrated maintenance plan optimization device provided in one embodiment of the present invention. DETAILED DESCRIPTION
[0071] To make the purpose, technical solution and advantages of the present invention clearer, the technical solution of the present invention will be described in detail below. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other implementation methods obtained by ordinary technicians in this field without creative work belong to the scope of protection of the present invention.
[0072] Based on the background technology records, the current power generation and transmission equipment maintenance plan formulation process does not take into account the system inertia level in the future period. The units that are not under maintenance and are in a shutdown state can be started a few days ago according to the system operation needs, while the units within the maintenance time window will be in a state of continuous inability to provide system inertia, and the lines in the maintenance state will also limit the delivery of system inertia of some units. If the system inertia is insufficient, there will be direct system operation risks, or the power generation and transmission equipment maintenance plan will need to be temporarily changed, which will not only disrupt the original maintenance plan, but also increase the probability of equipment failure due to failure to maintain in time.
[0073] Therefore, when formulating the maintenance plan for power generation and transmission equipment, this application considers the coupling relationship between the power generation and transmission equipment and the system inertia, considers the impact of equipment maintenance on the system inertia level, and constructs a power generation and transmission equipment maintenance plan optimization method that meets the safe and stable operation of a high-proportion new energy system.
[0074] Figure 1 This is a flow chart of a method for optimizing a power generation and transmission integrated maintenance plan provided by an embodiment of the present invention. The method provided by this application can be applied to power grids. Figure 1 , this embodiment may include the following steps:
[0075] Step S101, obtaining basic data of a target power grid maintenance plan, wherein the target power grid maintenance plan includes: a power generation and transmission equipment maintenance plan and a line maintenance plan.
[0076] Step S102: Determine the virtual maintenance cost of each type of power generation and transmission equipment according to the basic data.
[0077] Step S103, calculating the inertia level that can be provided by various types of power generation and transmission equipment; and calculating the time-sharing minimum inertia requirement of the target power grid system.
[0078] Step S104: construct an integrated power generation and transmission maintenance optimization model based on the maintenance virtual cost, inertia level, and minimum inertia requirement of the power generation and transmission equipment, and solve the model to obtain a target maintenance plan; wherein the integrated power generation and transmission maintenance model includes: an objective function and constraints.
[0079] Step S105: Perform N-1 safety verification and fault state system inertia verification on the target maintenance plan, and adjust the target maintenance plan according to the verification results.
[0080] It is understandable that, by adopting the technical solution of this embodiment, after obtaining the basic data of the target power grid maintenance plan, the virtual maintenance cost, inertia level, minimum inertia requirement, etc. of the power generation and transmission equipment are calculated respectively, so as to construct an integrated power generation and transmission maintenance optimization model, solve the model to obtain the target for planning, and adjust the target maintenance plan in real time. Among them, the inertia demand of the system and the inertia parameters corresponding to various types of power generation equipment are evaluated in detail, which improves the guarantee of system safety; the inertia verification of the fault state system is adopted to improve the guarantee level of system safety and stability corresponding to the maintenance plan.
[0081] In some embodiments, the basic data include: system parameters of the power grid to be repaired, line data, interconnection line data, node data, power plant data, regional data, section data, unit data, unit inertia parameters, maintenance information data (maintenance equipment, maintenance priority, intended maintenance time interval), system new energy forecast information, load forecast information, etc.
[0082] In this embodiment, after obtaining the basic data, the virtual maintenance cost of each type of power generation and transmission equipment can be obtained according to the basic data of each type of power generation and transmission equipment. For example, the virtual maintenance cost can be a virtual maintenance cost curve C i,d , represents the virtual cost of equipment i taking the dth operating day as the start time of maintenance, expressed as:
[0083]
[0084] in, The start time of maintenance as declared by the equipment operator. is the maintenance start time after optimization. is the maintenance willingness cost constant.
[0085] If the equipment operator declares the start time of the maintenance he / she intends to start, the intended cost will be the lowest. If the optimized start time deviates, the more days of deviation, the higher the intended cost. Figure 2 A schematic diagram of a virtual maintenance cost curve provided by an embodiment of the present invention is shown in FIG. Figure 2 , you can check the virtual maintenance cost, which is the maintenance willingness cost. Among them, the power generation equipment can be various types of units.
[0086] In this application, considering the differences among units, the maintenance priority parameter w is set. i , represents the maintenance priority of equipment i. The higher the priority, the larger the parameter value. For example, important and high-priority equipment can set its priority parameter to 2, 3, etc., and general equipment can set the parameter to 1. The actual unit maintenance willingness cost is w i ·C i,d, that is, adjusting high-priority units will lead to a greater increase in willingness cost, so the adjustment of important high-priority units is reduced in this way.
[0087] In the traditional mode, only the existing information such as installed capacity and output level of the units that need to be repaired is obtained, and the inertia level of each device is not evaluated, so its contribution to the system inertia demand cannot be measured. In this embodiment, the characteristics of various units are quite different, and their inertia constants are also different. The inertia of thermal power units, wind power units, photovoltaic units, and energy storage equipment are evaluated separately:
[0088]
[0089]
[0090]
[0091] E ES,i ;
[0092] Among them, E TH,i is the moment of inertia of the ith thermal power unit, P TH,i is the rated power of the i-th thermal power unit, H TH,i is the inertia time constant of the ith thermal power unit, E WI,i is the virtual inertia of the i-th wind turbine, P WI,i is the rated power of the i-th wind turbine, H WI,i is the inertia time constant of the i-th wind turbine, E SO,i is the virtual inertia of the ith PV unit, P SO,i is the rated power of the ith photovoltaic unit, H SO,i is the inertia time constant of the ith photovoltaic unit, E ES,i is the virtual inertia of the i-th energy storage device, P ES,i is the rated power of the i-th energy storage device, H ES,i is the inertia time constant of the i-th energy storage device.
[0093] It is worth noting that if a wind turbine, photovoltaic unit, or energy storage device cannot provide virtual inertia due to its own technical type or due to maintenance shutdown, its corresponding inertia time constant and virtual inertia will both be 0.
[0094] In the traditional maintenance optimization process, the main consideration is whether the power supply capacity of the power supply can meet the load demand, but whether the system inertia is sufficient. The inertia level required by the system is not clear during the analysis. The inertia requirement of the system is mainly to meet stable operation, including coping with daily load and frequency fluctuations, as well as fluctuations under fault conditions. From the perspective of safety and stability, this application should consider the base state requirements and fault state requirements of conventional operation. At the moment of system failure, since the generator regulator has not yet acted, the power imbalance phenomenon is most serious and the demand for system inertia is the strongest. The minimum inertia requirement of the target power grid system is calculated based on this:
[0095]
[0096]
[0097] in, The minimum system inertia required for the system base state to cope with the power loss caused by system fluctuations, The minimum system inertia required to cope with power loss when a single machine fails. is the rated frequency, is the maximum power shortage of the system caused by the fault, is the maximum frequency change rate that the system can follow, The system inertia loss caused by the fault.
[0098] It is worth noting that the system base state of the present application is the daily working state of the system.
[0099] When constructing the integrated transmission maintenance model, it is completed by constructing: objective function and constraint conditions. In this application, the objective function can be:
[0100]
[0101] Among them, NG is the total number of all overhauled equipment, ND is the total number of operating days, is the virtual maintenance cost of the equipment.
[0102] The constraints include:
[0103] The maintenance days are constrained as follows:
[0104] in, For power transmission equipment No. The maintenance status variable of each operating day, when the value is 1, it means there is a maintenance plan, and when it is 0, it means there is no maintenance plan; is the total number of operating days; For power transmission equipment The number of days required for the maintenance plan.
[0105] Maintenance status constraints:
[0106]
[0107] in, For power transmission equipment In the The maintenance start state variable of the operation day, when the value is 1, it means The maintenance starts on the first operation day, and the value of the remaining operation days is 0; For power transmission equipment In the The maintenance termination status variable of the operation day, when the value is 1, it means that The maintenance starts on the first operation day, and the value of the remaining operation days is 0. , the number of days from the start of maintenance to the end of maintenance is ;
[0108] Expert database constraints, unit and grid operation constraints, and system inertia constraints.
[0109] In this application, in the process of optimizing the maintenance plan, it is also necessary to combine the actual operation of the power grid and consider the expert library constraints of the impact between the maintenance tasks of multiple equipment. This type of constraint is formulated based on the power grid topology and actual operation to meet the power grid operation requirements and improve the operation efficiency. Specifically, it includes the following constraints:
[0110] Considering the topological connection relationship of power generation and transmission equipment, the simultaneous maintenance of some equipment will have a significant impact on the topological structure or system operation. This application sets that the equipment cannot be maintained simultaneously in the same time period:
[0111] Mutually exclusive constraints:
[0112] i.e. Device and equipment At most, only one device can be under maintenance on the same day;
[0113] Some equipment needs to have maintenance sequence requirements. In this application, in the actual modeling process, it is necessary to further add constraints on the sequence based on the mutually exclusive constraints:
[0114] Order constraints:
[0115]
[0116] in, is any day within the total number of operating days; the above constraints can be used to realize the equipment On the device Complete the inspection before starting the repair.
[0117] In the power system, some equipment has a close connection relationship, and maintenance should be carried out simultaneously to improve the utilization efficiency of the equipment:
[0118] At the same time constraints: .
[0119] Through the above formula, you can arrange the equipment and equipment Perform maintenance in the same time period.
[0120] In this embodiment, when making maintenance plan arrangements, it is necessary to meet the system output and operation requirements, and it is necessary to establish corresponding unit and grid operation constraints. At the same time, the present invention also includes the system inertia requirements, specifically including the following constraints:
[0121] The unit output needs to meet the upper and lower limit requirements. Assuming that the unit is in the startup state, the unit and the grid operation constraints include:
[0122] Unit output upper and lower limit constraints:
[0123] Among them, the period Operation day Within the period of time, For equipment In the Within operating days The output level of the time period, and Equipment If the unit is under maintenance, its upper output limit will be reduced to 0, that is, it has no output capacity;
[0124] The output capacity of the non-maintenance units needs to meet the system backup requirements, and the corresponding system backup capacity constraints are:
[0125] in, is the number of all devices, No. The maximum load of the operating day, For the System reserve rate requirements for each operating day;
[0126] The line power flow constraints need to consider the base state and the operation constraints after N-1 faults, which can be as follows:
[0127] Base state power flow constraints:
[0128] in, , For Line The lower and upper limits of the transmission power, For power generation equipment To line The node-line power transfer distribution factor, For load To line The node-line power transfer distribution factor, For Node In the period The node load prediction value is is the total number of power generation equipment in the system, is the total number of load nodes in the system, is the total number of lines in the network topology.
[0129] In order to ensure the system safety level and adapt to the high proportion of new energy scenarios, this application considers the constraints of the system rotation inertia margin under maintenance status in the optimization model, and considers the constraints of two scenarios: power loss caused by large power fluctuations and power loss caused by unit failures. The system inertia constraints under the maximum power loss caused by power fluctuations include:
[0130]
[0131] in, , , , are the total number of thermal power, wind power, photovoltaic, and energy storage equipment respectively. The above formula ensures that the system available inertia meets the safety requirements on each operating day. In this application, when modeling, the system inertia that can be provided by the unit is multiplied by the unit maintenance status parameter in the constraint conditions to ensure that all types of units cannot provide rotational inertia when they are in maintenance status. At the same time, since it is directly associated with the decision variables in the constraints, the dynamic adjustment of the system available inertia level during the optimization process can be achieved. During the optimization solution process, the system available inertia level also changes synchronously to achieve joint optimization with the lowest maintenance intention.
[0132] By solving the above model, we can obtain the maintenance plan for power generation and transmission equipment that meets the basic operation of the power grid and minimizes the regulation cost, which is the target maintenance plan.
[0133] In order to consider the safety and stability level of the power grid in this application, a conventional N-1 safety check is performed, and the system inertia under the fault state is also checked.
[0134] In this application, the constraints of the N-1 safety check are:
[0135]
[0136] in, For the line that is assumed to have a fault, is the N-1 fault set; For Line Fault on line The breaking transfer distribution factor; , Equipment and load To line The node-line power transfer factor of the constraint means that the line After a fault occurs, the power grid still meets the power flow constraints.
[0137] The constraint conditions for the inertia check of the system under the fault state under the power loss caused by the fault are:
[0138]
[0139] in, The equipment that has failed is the unit with the largest single-unit capacity among the units that have not been repaired. The system inertia of the faulty unit. Based on the optimization results of the base state system inertia constraint maintenance, the fault state system inertia verification can be performed. On the one hand, the positions that do not meet the verification requirements can be identified and corrected. On the other hand, the time period when the system inertia margin is relatively tight can be given for decision-making reference by system operators.
[0140] If the inertia constraint is not satisfied, the unsatisfied fault state system inertia constraint is added to the constructed model and solved again until it is satisfied.
[0141] The technical solution provided in this application has at least the following beneficial effects:
[0142] 1. In the maintenance plan, on the basis of the traditional supply and demand balance, consider the contribution of multiple types of rotational inertia or virtual inertia to the system, and comprehensively evaluate the contribution of various types of power generation equipment to the system inertia in addition to the power capacity;
[0143] 2. Consider the system inertia requirements under the system base state and fault state, optimize and verify the maintenance plan, and improve the maintenance plan's ability to ensure safe and stable operation of the system;
[0144] 3. Couple the unit maintenance status and inertia level in the system inertia constraint to improve the precision and accuracy of inertia assessment.
[0145] Based on a general inventive concept, the present invention also provides a device for optimizing the maintenance plan of integrated power generation and transmission, which is used to implement the above method embodiment. Figure 3 The schematic diagram of the structure of a device for optimizing the maintenance plan of integrated power generation and transmission provided by one embodiment of the present invention. Figure 3 As shown, the device provided by the embodiment of the present invention may include:
[0146] An acquisition module 31 is used to acquire basic data of a target power grid maintenance plan, wherein the target power grid maintenance plan includes: a power generation and transmission equipment maintenance plan and a line maintenance plan;
[0147] A parameter initialization module 32, for determining the virtual maintenance cost of each type of power generation and transmission equipment according to the basic data;
[0148] The inertia parameter calculation module 33 is used to calculate the inertia level that can be provided by various types of power generation and transmission equipment; and calculate the time-sharing minimum inertia requirement of the target power grid system;
[0149] A solution module 34 is constructed, which is used to construct an optimization model for the integrated maintenance plan of power generation and transmission according to the virtual maintenance cost, inertia level, and minimum inertia requirement of the power generation and transmission equipment, and solve the model to obtain a target maintenance plan; wherein the optimization model for the integrated maintenance plan of power generation and transmission includes: an objective function and constraint conditions;
[0150] The verification module 35 is used to perform N-1 safety verification and fault state system inertia verification on the target maintenance plan, and adjust the target maintenance plan according to the verification results.
[0151] Regarding the device in the above embodiment, the specific manner in which each module performs operations has been described in detail in the embodiment of the method, and will not be elaborated here.
[0152] The present invention also provides a device for optimizing the maintenance plan of integrated power generation and transmission, which is used to implement the above method embodiment. Figure 4 A schematic diagram of a structure of a power generation and transmission integrated maintenance plan optimization device provided by an embodiment of the present invention. Figure 4 As shown, the power generation and transmission integrated maintenance plan optimization device of this embodiment includes a processor 31 and a memory 42, and the processor 41 is connected to the memory 42. The processor 41 is used to call and execute the program stored in the memory 42; the memory 42 is used to store the program, and the program is at least used to execute the power generation and transmission integrated maintenance plan optimization method in the above embodiment.
[0153] The specific implementation scheme of the power generation and transmission integrated maintenance plan optimization device provided in the embodiment of the present application can refer to the implementation scheme of the power generation and transmission integrated maintenance plan optimization method in any of the above embodiments, and will not be repeated here.
[0154] It can be understood that the same or similar parts of the above embodiments can be referenced to each other, and the contents not described in detail in some embodiments can refer to the same or similar contents in other embodiments.
[0155] It should be noted that, in the description of the present invention, the terms "first", "second", etc. are only used for descriptive purposes and cannot be understood as indicating or implying relative importance. In addition, in the description of the present invention, unless otherwise specified, the meaning of "plurality" refers to at least two.
[0156] Any process or method description in a flowchart or otherwise described herein may be understood to represent a module, segment or portion of code that includes one or more executable instructions for implementing the steps of a specific logical function or process, and the scope of the preferred embodiments of the present invention includes alternative implementations in which functions may not be performed in the order shown or discussed, including performing functions in a substantially simultaneous manner or in the reverse order depending on the functions involved, which should be understood by those skilled in the art to which the embodiments of the present invention belong.
[0157] It should be understood that the various parts of the present invention can be implemented by hardware, software, firmware or a combination thereof. In the above-mentioned embodiments, multiple steps or methods can be implemented by software or firmware stored in a memory and executed by a suitable instruction execution system. For example, if implemented by hardware, as in another embodiment, it can be implemented by any one of the following technologies known in the art or their combination: a discrete logic circuit having a logic gate circuit for implementing a logic function for a data signal, a dedicated integrated circuit having a suitable combination of logic gate circuits, a programmable gate array (PGA), a field programmable gate array (FPGA), etc.
[0158] A person skilled in the art may understand that all or part of the steps in the method for implementing the above-mentioned embodiment may be completed by instructing related hardware through a program, and the program may be stored in a computer-readable storage medium, which, when executed, includes one or a combination of the steps of the method embodiment.
[0159] In addition, each functional unit in each embodiment of the present invention may be integrated into a processing module, or each unit may exist physically separately, or two or more units may be integrated into one module. The above-mentioned integrated module may be implemented in the form of hardware or in the form of a software functional module. If the integrated module is implemented in the form of a software functional module and sold or used as an independent product, it may also be stored in a computer-readable storage medium.
[0160] The storage medium mentioned above can be a read-only memory, a magnetic disk or an optical disk, etc.
[0161] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "examples", "specific examples", or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner.
[0162] Although the embodiments of the present invention have been shown and described above, it is to be understood that the above embodiments are exemplary and are not to be construed as limitations of the present invention. A person skilled in the art may change, modify, replace and vary the above embodiments within the scope of the present invention.
Claims
1. A method for optimizing the integrated power generation and transmission maintenance plan, characterized in that: include: Obtaining basic data of a target power grid maintenance plan, wherein the target power grid maintenance plan includes: a power generation and transmission equipment maintenance plan and a line maintenance plan; Determine the virtual maintenance cost of each type of power generation and transmission equipment based on the basic data; Calculate the inertia level that can be provided by various types of power generation and transmission equipment; and calculate the minimum inertia requirement of the target power grid system at different times; According to the virtual maintenance cost, inertia level and minimum inertia requirement of the power generation and transmission equipment, an optimization model for the integrated maintenance plan of power generation and transmission is constructed, and the target maintenance plan is obtained by solving the model; wherein the optimization model for the integrated maintenance plan of power generation and transmission includes: an objective function and constraint conditions; Performing N-1 safety verification and fault state system inertia verification on the target maintenance plan, and adjusting the target maintenance plan according to the verification results; The constraint conditions for the fault state system inertia verification are: in, The equipment that has failed is the unit with the largest single-unit capacity among the units that have not been repaired. is the maximum power shortage of the system caused by the failure of device c, is the system inertia corresponding to the faulty unit; The constraints of the N-1 safety check are: in, For the line that is assumed to have a fault, is the N-1 fault set; For Line Fault on line The breaking transfer distribution factor; , Equipment and load To line The node-line power transfer factor; The virtual maintenance cost is recorded as , indicating the device First The virtual cost of the maintenance start time is one operating day; The calculation of the inertia level that can be provided by various types of power generation and transmission equipment includes: Calculate the inertia that the thermal power unit can provide: ; Calculate the inertia that the wind turbine can provide: ; Calculate the inertia that the photovoltaic system can provide: ; Calculate the inertia that the energy storage device can provide: E ES,i ; Among them, E TH,i is the moment of inertia of the ith thermal power unit, P TH,i is the rated power of the i-th thermal power unit, H TH,i is the inertia time constant of the ith thermal power unit, E WI,i is the virtual inertia of the i-th wind turbine, P WI,i is the rated power of the i-th wind turbine, H WI,i is the inertia time constant of the i-th wind turbine, E SO,i is the virtual inertia of the ith PV unit, P SO,i is the rated power of the ith photovoltaic unit, H SO,i is the inertia time constant of the ith photovoltaic unit, E ES,i is the virtual inertia of the i-th energy storage device, P ES,i is the rated power of the i-th energy storage device, H ES,i is the inertia time constant of the i-th energy storage device; Among them, the minimum inertia requirement of the target power grid system is: in, The minimum system inertia required for the system base state to cope with the power loss caused by system fluctuations, The minimum system inertia required to cope with power loss when a single machine fails. is the rated frequency, is the maximum power shortage of the system caused by the fault, is the maximum frequency change rate that the system can follow, The system inertia loss caused by the fault; Also includes: Setting maintenance priority parameters , indicating the device The maintenance priority and actual unit maintenance willingness cost are ; The objective function is: ; Among them, NG is the total number of all overhauled equipment, ND is the total number of operating days, For equipment First The virtual cost of the maintenance start time is one operating day; The constraints include: The maintenance days are constrained as follows: in, For power transmission equipment No. Maintenance status variables for each operating day; is the total number of operating days; For power transmission equipment The number of days the maintenance plan needs to last; Maintenance status constraints: in, For power transmission equipment In the The maintenance start state variable of the operation day, when the value is 1, it means The maintenance starts on the first operation day, and the value of the remaining operation days is 0; For power transmission equipment In the Maintenance termination status variables for each operation day; , the number of days from the start of maintenance to the end of maintenance is .
2. The method according to claim 1, characterized in that The constraint conditions also include expert database constraints; the expert database constraints include: Mutually exclusive constraints: i.e. Device and equipment At most, only one device can be under maintenance on the same day; Order constraints: That is, equipment j needs to be repaired after equipment i is repaired, where: Any day within the total number of operating days; At the same time constraints: , that is, equipment i and equipment j need to be repaired at the same time.
3. The method according to claim 2, characterized in that The constraints also include unit and grid operation constraints; the unit and grid operation constraints include: Unit output upper and lower limit constraints: Among them, the period Operation day Within the period, For equipment In the Within operating days The output level of the time period, and Equipment The lower and upper limits of output; System spare capacity constraints: in, is the number of all devices, No. The maximum load of the operating day, For the System reserve rate requirements for each operating day; Base state power flow constraints: in, , For Line The lower and upper limits of the transmission power, For power generation equipment To line The node-line power transfer distribution factor, For load To line The node-line power transfer distribution factor, For Node In the period The node load prediction value is is the total number of power generation equipment in the system, is the total number of load nodes in the system, is the total number of lines in the network topology.
4. The method according to claim 2, characterized in that: The constraint conditions also include system inertia constraints; the system inertia constraints include: in, , , , They are the total number of thermal power, wind power, photovoltaic and energy storage equipment respectively.
5. A device for optimizing the maintenance plan for integrated power generation and transmission, characterized in that: include: An acquisition module is used to acquire basic data of a target power grid maintenance plan, wherein the target power grid maintenance plan includes: a power generation and transmission equipment maintenance plan and a line maintenance plan; A parameter initialization module, used to determine the virtual maintenance cost of each type of power generation and transmission equipment according to the basic data; An inertia parameter calculation module is used to calculate the inertia level that can be provided by various types of power generation and transmission equipment; and calculate the minimum inertia requirement of the target power grid system in a time-sharing manner; Constructing a solution module, for constructing an optimization model for the integrated maintenance plan of power generation and transmission according to the virtual maintenance cost, inertia level, and minimum inertia requirement of the power generation and transmission equipment, and solving the model to obtain a target maintenance plan; wherein the optimization model for the integrated maintenance plan of power generation and transmission includes: an objective function and constraint conditions; A verification module, used to perform N-1 safety verification and fault state system inertia verification on the target maintenance plan, and adjust the target maintenance plan according to the verification results; The constraint conditions for the fault state system inertia verification are: in, The equipment that has failed is the unit with the largest single-unit capacity among the units that have not been repaired. is the maximum power shortage of the system caused by the failure of device c, is the system inertia corresponding to the faulty unit; The constraints of the N-1 safety check are: in, For the line that is assumed to have a fault, is the N-1 fault set; For Line Fault on line The breaking transfer distribution factor; , Equipment and load To line The node-line power transfer factor; The virtual maintenance cost is recorded as , indicating the device First The virtual cost of the maintenance start time is one operating day; The calculation of the inertia level that can be provided by various types of power generation and transmission equipment includes: Calculate the inertia that the thermal power unit can provide: ; Calculate the inertia that the wind turbine can provide: ; Calculate the inertia that the photovoltaic system can provide: ; Calculate the inertia that the energy storage device can provide: E ES,i ; Among them, E TH,i is the moment of inertia of the ith thermal power unit, P TH,i is the rated power of the i-th thermal power unit, H TH,i is the inertia time constant of the ith thermal power unit, E WI,i is the virtual inertia of the i-th wind turbine, P WI,i is the rated power of the i-th wind turbine, H WI,i is the inertia time constant of the i-th wind turbine, E SO,i is the virtual inertia of the ith PV unit, P SO,i is the rated power of the ith photovoltaic unit, H SO,i is the inertia time constant of the ith photovoltaic unit, E ES,i is the virtual inertia of the i-th energy storage device, P ES,i is the rated power of the i-th energy storage device, H ES,i is the inertia time constant of the i-th energy storage device; Among them, the minimum inertia requirement of the target power grid system is: in, The minimum system inertia required for the system base state to cope with the power loss caused by system fluctuations, The minimum system inertia required to cope with power loss when a single machine fails. is the rated frequency, is the maximum power shortage of the system caused by the fault, is the maximum frequency change rate that the system can follow, The system inertia loss caused by the fault; Also includes: Setting maintenance priority parameters , indicating the device The maintenance priority and actual unit maintenance willingness cost are ; The objective function is: ; Among them, NG is the total number of all overhauled equipment, ND is the total number of operating days, For equipment First The virtual cost of the maintenance start time is one operating day; The constraints include: The maintenance days are constrained as follows: in, For power transmission equipment No. Maintenance status variables for each operating day; is the total number of operating days; For power transmission equipment The number of days the maintenance plan needs to last; Maintenance status constraints: in, For power transmission equipment In the The maintenance start state variable of the operation day, when the value is 1, it means The maintenance starts on the first operation day, and the value of the remaining operation days is 0; For power transmission equipment In the Maintenance termination status variables for each operation day; , the number of days from the start of maintenance to the end of maintenance is .
6. A device for optimizing the maintenance plan of integrated power generation and transmission, characterized in that: The invention comprises a processor and a memory, wherein the processor is connected to the memory: Wherein, the processor is used to call and execute the program stored in the memory; The memory is used to store the program, and the program is at least used to execute the method for optimizing the integrated power generation and transmission maintenance plan as described in any one of claims 1-4.