A precast pipe positioning and installation construction equipment

By designing prefabricated pipe positioning and installation construction equipment and using mechanical lifting and docking technology, the problems of prefabricated pipe lifting and leakage in existing equipment were solved, and the quality of sewer pipe laying was improved.

CN118561147BInactive Publication Date: 2024-10-18JINING LUNAN HIGHWAY ENG CO
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202411047792.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-01
Publication Date
2024-10-18
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The multi-strand rope structure in the existing sewer pipeline construction equipment causes the prefabricated pipes to lift during hoisting, which increases the difficulty of docking and the probability of leakage, and affects the quality of laying.

Method used

A kind of prefabricated pipe positioning and installation construction equipment is designed, which uses components such as frames, lifting plates, U-shaped frames, two-way screws, splints and push-fit parts. Through mechanical hoisting and docking installation, the prefabricated pipes are realized by using motor drive and gear systems. Linear guidance and docking to reduce the risk of warping and leakage.

Benefits of technology

It effectively reduces the probability of warping and leakage during the hoisting of prefabricated pipes, simplifies the docking installation operation, and improves the quality of sewer pipe laying.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118561147B_ABST
    Figure CN118561147B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of sewer pipes, and specifically to a prefabricated pipe positioning and installation construction equipment, comprising a frame, two lifting plates symmetrically arranged at the lower end of the frame, a positioning member installed in the frame, a U-shaped frame arranged at the lower end of the positioning member, a bidirectional screw rotatably connected between two vertical parts of the U-shaped frame, a first driver arranged at the outer end of the U-shaped frame, and the first driver is connected to the bidirectional screw, the left side of the outer end of the bidirectional screw is threadedly connected to the first plate, two left clamping plates symmetrically arranged at the lower end of the first plate, the right side of the outer end of the bidirectional screw is threadedly connected to the second plate, two right clamping plates symmetrically arranged at the lower end of the second plate, and moving parts are arranged at the lower ends of the two lifting plates. This design realizes mechanical lifting construction of prefabricated pipes, effectively reduces the probability of defects such as warping of prefabricated pipes during lifting construction, effectively reduces the probability of leakage at the docking installation position, and effectively ensures the laying quality of sewer pipes.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a prefabricated pipe positioning and installation construction device, belonging to the technical field of sewer pipes. Background Art

[0002] Sewer pipes refer to pipes for draining sewage and rainwater, and sewers are also one of the main structures in highways. Prefabricated pipes are widely used in sewer construction due to their standardized production and quick on-site installation. In the process of sewer construction, trenches are usually dug out with excavators in advance, and then prefabricated pipes are hoisted into the trenches. Then, the two prefabricated pipes in the trenches are butt-jointed and installed, and then hoisting and butt-jointing are performed continuously to realize the construction of sewers.

[0003] Generally, positioning and installation construction equipment is used to hoist the prefabricated pipes. However, the positioning and installation construction equipment generally uses a multi-strand rope structure to hoist the prefabricated pipes. The rope structure itself is flexible, which makes it easy for the multi-strand rope structure to warp during the hoisting of the prefabricated pipes, thereby increasing the difficulty of docking, resulting in poor sealing at the interface, and increasing the probability of defects such as leakage at the interface, which will affect the quality of sewer pipe laying. Summary of the invention

[0004] In view of the problems in the prior art, the present invention provides a prefabricated pipe positioning and installation construction equipment.

[0005] The technical solution adopted by the present invention to solve the technical problem is: a prefabricated pipe positioning and installation construction equipment, comprising a frame, two lifting plates are symmetrically arranged at the lower end of the frame, and the lifting plates are arranged vertically, a positioning member is installed in the frame, a U-shaped frame is arranged at the lower end of the positioning member, and the U-shaped frame is located between the two lifting plates, the U-shaped frame is located at the lower side of the frame, a bidirectional screw is rotatably connected between the two vertical parts of the U-shaped frame, a first driver is arranged at the outer end of the U-shaped frame, and the first driver is connected to the bidirectional screw;

[0006] The left side of the outer end of the bidirectional screw is threadedly connected to the first plate, and the first plate extends out of the lower side of the U-shaped frame, and two left clamping plates are symmetrically arranged at the lower end of the first plate, and the cross section of the left clamping plate is V-shaped with a narrow left and a wide right arrangement, and the right side of the outer end of the bidirectional screw is threadedly connected to the second plate, and the second plate extends out of the lower side of the U-shaped frame, and the second plate is located on the right side of the first plate, and two right clamping plates are symmetrically installed at the lower end of the second plate, and the cross section of the right clamping plate is V-shaped with a wide left and a narrow right arrangement;

[0007] A push piece is arranged on the lower side of the first plate, and is connected to the two left clamping plates; a guide piece is installed in the middle of the front end of the U-shaped frame, and is located between the left clamping plate and the right clamping plate; and a moving piece is arranged at the lower ends of the two lifting plates.

[0008] Furthermore, the moving part includes a base plate, which is installed on the lower end of the lifting plate. A plurality of moving components are equidistantly arranged on the lower end of the base plate, and the moving components are provided with a brake structure.

[0009] Further, the guide member includes a T-shaped plate, the T-shaped plate is arranged in front of the U-shaped frame, an upper cylinder is installed at the lower part of the rear end of the T-shaped plate, and the upper cylinder is located at the lower side of the U-shaped frame, the upper cylinder is located between the left clamping plate and the right clamping plate, and a plurality of first rolling members are equidistantly arranged at the upper end of the upper cylinder;

[0010] A first elevator is arranged at the middle of the lower end of the upper cylinder, a lower cylinder is installed at the lower end of the movable part of the first elevator, and the lower cylinder is located between the left clamping plate and the right clamping plate, a plurality of second rolling members are arranged at equal distances at the lower end of the lower cylinder, two third telescopic rods are symmetrically installed between the lower cylinder and the upper cylinder, and the two third telescopic rods are located at the front and rear sides of the first elevator;

[0011] A telescopic machine is arranged at the rear end of the T-shaped plate, the fixed part of the telescopic machine is installed at the upper end of the U-shaped frame, and the telescopic machine is located at the lower side of the frame, a second telescopic rod is installed at the rear end of the T-shaped plate, and the second telescopic rod is located on the right side of the telescopic machine, the fixed part of the second telescopic rod is arranged on the upper end of the U-shaped frame, and the second telescopic rod is located at the lower side of the frame.

[0012] Further, the push-fitting member includes a second driver, the fixed portion of the second driver is mounted on the front end of the left clamping plate located at the front side, the rear end of the movable portion of the second driver is provided with a first shaft, the first shaft passes through the two left clamping plates, and the two left clamping plates are both rotatably connected to the first shaft;

[0013] The left end surfaces of the lower sides of the two left clamping plates are both recessed to the right to form a second through slot, and the second through slot runs through the left clamping plate, the first shaft runs through the two second through slots, and two first rollers are symmetrically arranged at the outer end of the first shaft, the two first rollers are respectively located in the two second through slots, and the first rollers extend out of the right side of the second through slot;

[0014] The left end surfaces of the upper sides of the two left clamping plates are both recessed to the right to form a first through slot, and the first through slot runs through the left clamping plate, the first through slot is located above the second through slot, the insides of the two first through slots are both rotatably connected to the first rotating shaft, the outer ends of the two first rotating shafts are both provided with second rollers, and the second rollers extend out of the right side of the first through slot;

[0015] A linkage assembly is arranged between the two left clamping plates, and the linkage assembly is connected to the first shaft, and a rear end of the linkage assembly is connected to the first rotating shaft located at the rear side.

[0016] Further, the linkage assembly includes a first rod, the first rod is rotatably connected between the two left clamping plates, and the first rod is located above the first shaft, a second bevel gear is arranged at the outer end of the first rotating shaft located at the rear side, and the second bevel gear is located on the upper side of the second roller, the second bevel gear is arranged to be narrow at the top and wide at the bottom, the front upper end of the second bevel gear is meshed with the first bevel gear, and the first bevel gear is arranged to be wide at the front and narrow at the back, the first bevel gear is located in the first through groove at the rear side, and the rear end of the first rod passes through the left clamping plate at the rear side and is connected to the first bevel gear;

[0017] A synchronous belt is movably installed between the two left clamps, the bottom end of the synchronous belt is meshed with the first gear, the first gear is installed at the outer end of the first shaft, the top end of the synchronous belt is meshed with the second gear, the second gear is set at the outer end of the first rod, the second rod is rotatably connected between the two left clamps, and the second rod is located between the first shaft and the first rod, a guide wheel is installed at the outer end of the second rod, and the guide wheel is movably connected to the right end of the synchronous belt, the third rod is rotatably connected between the two left clamps, and the third rod is located to the left of the second rod, an auxiliary gear is set at the outer end of the third rod, and the third rod passes through the synchronous belt, and the auxiliary gear is meshed with the left wall inside the synchronous belt.

[0018] Further, the two right clamping plates are rotatably connected to a second shaft, and the second shaft penetrates the two right clamping plates, the right end surfaces of the lower sides of the two right clamping plates are both recessed to the left to form a fourth through slot, and the fourth through slot penetrates the right clamping plates, the second shaft penetrates the two fourth through slots, and two third rollers are symmetrically arranged at the outer end of the second shaft, the two third rollers are respectively located in the two fourth through slots, and the third roller extends out of the left side of the fourth through slot;

[0019] The right end surfaces on the upper sides of the two right splints are both recessed to the left to form a third through slot, and the third through slot runs through the right splint. The third through slot is located above the fourth through slot. The insides of the two third through slots are both rotatably connected to the second rotating shaft. Fourth rollers are provided at the outer ends of the two second rotating shafts, and the fourth rollers extend out of the left side of the third through slot.

[0020] Further, the positioning member includes a sliding block, the sliding block is located in the frame, a second lift is arranged in the middle of the upper end of the sliding block, a movable part of the second lift passes through the sliding block and is connected to the upper end of the U-shaped frame, and the second lift is located between the telescopic machine and the second telescopic rod;

[0021] The frame is internally rotatably connected to an adjusting screw, and the adjusting screw is located at the rear side of the second elevator. The adjusting screw passes through the sliding block, and the adjusting screw is threadedly connected to the sliding block. A third driver is arranged at the right end of the frame, and the movable part of the third driver is connected to the adjusting screw.

[0022] Furthermore, a polished rod is arranged inside the frame, and the polished rod is located at the front side of the second lifter, the polished rod passes through the sliding block, and the sliding block is slidably connected to the polished rod;

[0023] Two round rods are symmetrically arranged at the upper end of the U-shaped frame, and the two round rods are located on the left and right sides of the T-shaped plate. The two round rods both penetrate the sliding block, and the sliding block is slidably connected to the round rods, and the two round rods are located between the two bare rods;

[0024] A plurality of guide rods are equidistantly arranged between the two vertical parts of the U-shaped frame, and the guide rods are located above the bidirectional screw rods, the plurality of guide rods all penetrate the first plate, and the plurality of guide rods are all slidably connected to the first plate, and the plurality of guide rods all penetrate the second plate, and the plurality of guide rods are all slidably connected to the second plate.

[0025] Beneficial effects of the present invention:

[0026] 1. Use the second motor and the bidirectional screw to move the first plate and the second plate inward, and then move the left clamping plate and the right clamping plate inward, so as to realize the mechanical lifting construction of the prefabricated pipe, effectively reduce the probability of defects such as warping of the prefabricated pipe during the lifting construction, effectively reduce the probability of leakage at the docking installation position, and effectively ensure the quality of sewer pipe laying.

[0027] 2. Through the third motor, the first shaft, the first gear, the synchronous belt, the second gear, the first rod, the first bevel gear, the second bevel gear and the first rotating shaft, and with the assistance of another second roller and two fourth rollers, the clamped prefabricated pipe is rotated and moved outward synchronously, so as to realize the linear mechanical convenient docking installation operation of the prefabricated pipe, effectively reduce the difficulty of installation operation, effectively reduce the probability of damage caused by docking installation, effectively reduce the probability of leakage at the docking installation position, and effectively ensure the quality of sewer pipe laying.

[0028] 3. Through the second electric push rod and T-plate, the structure formed by the upper cylinder and the lower cylinder and other components is inserted into the hoisted prefabricated pipe, and the third electric push rod is used to drive the lower cylinder and the multiple second bull's eyes to move downward, so that the multiple third bull's eyes and the multiple second bull's eyes are respectively fitted on the upper and lower ends of the hoisted prefabricated pipe, so as to realize linear guidance of the prefabricated pipe for linear mechanical docking installation, effectively reduce the probability of swinging of the prefabricated pipe during the docking installation process, effectively reduce the probability of defects such as expansion of the docking position due to shaking and other phenomena, effectively reduce the probability of leakage at the docking installation position, and effectively ensure the quality of sewer pipe laying.

[0029] 4. The two first telescopic rods, two guide frames and the first bull's eyeball are used to restrict the U-shaped frame, effectively preventing the prefabricated pipe from swinging left and right during the rotation process, effectively reducing the probability of defects such as damage caused by docking installation, effectively reducing the probability of leakage at the docking installation position, and effectively ensuring the quality of sewer pipe laying. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] Other features, objects and advantages of the present invention will become more apparent from the detailed description of non-limiting embodiments made with reference to the following drawings:

[0031] Figure 1 This is a structural schematic diagram of a prefabricated pipe positioning and installation construction equipment of the present invention;

[0032] Figure 2 It is a front view of a prefabricated pipe positioning and installation construction equipment of the present invention;

[0033] Figure 3 It is a cross-sectional view of a prefabricated pipe positioning and installation construction equipment of the present invention;

[0034] Figure 4 A three-dimensional diagram of a frame in a prefabricated pipe positioning and installation construction device of the present invention;

[0035] Figure 5 It is an assembly diagram of a first telescopic rod and a guide frame in a prefabricated pipe positioning and installation construction device of the present invention;

[0036] Figure 6 A three-dimensional diagram of a U-shaped frame in a prefabricated pipe positioning and installation construction device of the present invention;

[0037] Figure 7 It is an assembly diagram of a first plate and two left clamping plates in a prefabricated pipe positioning and installation construction device of the present invention;

[0038] Figure 8 A three-dimensional diagram of a T-shaped plate in a prefabricated pipe positioning and installation construction device of the present invention;

[0039] Fig. 9 The present invention provides an assembly diagram of a second plate and two right clamping plates in a prefabricated pipe positioning and installation construction device.

[0040] In the figure: 1, frame, 2, lifting plate, 3, U-shaped frame, 4, left splint, 5, first plate, 6, T-shaped plate, 7, right splint, 8, second plate, 11, adjusting screw, 12, round rod, 13, first electric push rod, 14, sliding block, 15, first motor, 16, light rod, 21, first telescopic rod, 22, guide groove, 23, guide frame, 24, bottom plate, 25, moving wheel, 26, first bull eyeball, 31, second motor, 32, guide rod, 33, bidirectional screw, 41, first shaft, 42, first roller, 43, third motor, 44, first rod, 45, first rotating shaft, 46, second roller, 47, third motor, 48, first rod, 49, first rotating shaft, 50, first rotating shaft, 51, first rotating shaft, 52, first rotating shaft, 53, first rotating shaft, 54, first rotating shaft, 55, first rotating shaft, 56, first rotating shaft, 57, first rotating shaft, 58, first rotating shaft, 59, first rotating shaft, 60, first rotating shaft, 61, first rotating shaft, 62, first rotating shaft, 63, first rotating shaft, 64, first rotating shaft, 65, first rotating shaft, 66, first rotating shaft, 67, first rotating shaft, 68, first rotating shaft, 69, first rotating shaft, 70, first rotating shaft, 71, first rotating shaft, 72, first rotating shaft, 73, first rotating shaft, 74, first rotating shaft, 75, first rotating shaft, 76, first rotating shaft, 77, first rotating shaft, 78, first rotating shaft, 79, first rotating shaft, 80, first rotating shaft, 81, first rotating shaft, 82, first rotating shaft, 83, first rotating shaft, 84 7. Second rod, 48. Third rod, 49. Synchronous belt, 61. Lower cylinder, 62. Upper cylinder, 63. Second electric push rod, 64. Second telescopic rod, 71. Second shaft, 72. Third roller, 73. Fourth roller, 401. First through slot, 402. Second through slot, 411. First gear, 441. First bevel gear, 442. Second gear, 451. Second bevel gear, 471. Guide wheel, 481. Auxiliary gear, 611. Second bull's eyeball, 621. Third bull's eyeball, 622. Third telescopic rod, 623. Third electric push rod, 701. Third through slot, 702. Fourth through slot. DETAILED DESCRIPTION

[0041] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further explained below in conjunction with specific implementation methods.

[0042] Embodiment 1: Figure 1 , Figure 2 , Figure 3 , Figure 4 , Figure 6 , Figure 7 and Fig. 9 As shown, a prefabricated pipe positioning and installation construction equipment is provided, including a frame 1, two vertically arranged lifting plates 2 are symmetrically arranged on the lower end of the frame 1, the two lifting plates 2 are used in combination to lift and install the frame 1, and two bottom plates 24 are respectively installed on the lower ends of the two lifting plates 2, through the bottom plates 24, a mounting carrier is provided for the mobile component, and then a plurality of fans of the fixed parts of the mobile components with brake structures are arranged on the lower ends of the bottom plates 24, and a plurality of mobile components are used in combination to realize the mobile operation, and the mobile components can use mobile wheels 25;

[0043] The adjusting screw 11, which is located at the rear side of the second lifter and passes through the sliding block 14 located in the frame 1 and is threadedly connected to the sliding block 14, is rotatably connected to the inside of the frame 1. The sliding block 14 is moved left and right by the adjusting screw 11. The movable part of the third driver whose fixed part is set at the right end of the frame 1 is connected to the adjusting screw 11. The adjusting screw 11 is driven to rotate by the third driver. The third driver can use the first motor 15. Then, the light rod 16, which is located at the front side of the second lifter and passes through the sliding block 14 and is slidably connected to the sliding block 14, is set inside the frame 1. The movement of the sliding block 14 is guided by the light rod 16.

[0044] The movable part of the second lifter, which is located between the telescopic machine and the second telescopic rod 64 and whose fixed part is arranged in the middle of the upper end of the sliding block 14, penetrates the sliding block 14 and is connected to the upper end of the U-shaped frame 3 located between the two lifting plates 2 and on the lower side of the frame 1. The U-shaped frame 3 is driven to move up and down by the second lifter. The second lifter can adopt the first electric push rod 13, and two round rods 12, which are located on the left and right sides of the T-shaped plate 6 and between the two bare rods 16 and penetrate the sliding block 14 and are slidably connected to the sliding block 14, are symmetrically arranged on the upper end of the U-shaped frame 3. The two round rods 12 are used together to guide the movement of the U-shaped frame 3.

[0045] The bidirectional screw 33 is rotatably connected between the two vertical parts of the U-shaped frame 3, and the first plate 5 and the second plate 8 are relatively moved by the bidirectional screw 33, and the movable part of the first driver whose fixed part is arranged at the outer end of the U-shaped frame 3 is connected to the bidirectional screw 33, and the bidirectional screw 33 is driven by the first driver, and the first driver can adopt the second motor 31;

[0046] The first plate 5 extending from the lower side of the U-shaped frame 3 is threadedly connected to the left side of the outer end of the bidirectional screw 33, and the first plate 5 is used to provide a mounting carrier for the left clamping plate 4, and the second plate 8 extending from the lower side of the U-shaped frame 3 and located on the right side of the first plate 5 is threadedly connected to the right side of the outer end of the bidirectional screw 33, and the second plate 8 is used to provide a mounting carrier for the right clamping plate 7;

[0047] A plurality of guide rods 32 which are located above the bidirectional screw rod 33, penetrate the first plate 5 and the second plate 8 and are slidably connected to the first plate 5 and the second plate 8 are equidistantly arranged between the two vertical parts of the U-shaped frame 3. The plurality of guide rods 32 are used in combination to guide the movement of the first plate 5 and the second plate 8. Two V-shaped left clamping plates 4 with narrow left and wide right cross sections are symmetrically arranged on the lower end of the first plate 5. Then, two V-shaped right clamping plates 7 with wide left and narrow right cross sections are symmetrically installed on the lower end of the second plate 8. The left clamping plate 4 and the right clamping plate 7 are used in combination to clamp the prefabricated pipe.

[0048] When in use, first, with the assistance of the moving wheel 25, the device formed by the two lifting plates 2 and the frame 1 and other components is moved to the position where the prefabricated pipe is placed, and the left clamping plate 4 and the right clamping plate 7 are located on both sides of the prefabricated pipe, and then the second motor 31 is started to drive the bidirectional screw 33 to rotate. Since the bidirectional screw 33 is threadedly connected to the first plate 5 and the second plate 8 respectively, the rotation of the bidirectional screw 33 will cause the first plate 5 and the second plate 8 to move inward, and then the left clamping plate 4 and the right clamping plate 7 to move inward, so that the prefabricated pipe is mechanically clamped by the mutual movement of the left clamping plate 4 and the right clamping plate 7;

[0049] Then, the first electric push rod 13 is started to drive the U-shaped frame 3 to move upward, thereby lifting the clamped prefabricated pipe, and then the equipment is pushed to transport the lifted prefabricated pipe to the installation position, and the lifted prefabricated pipe is placed above the groove for laying the sewer pipe, and then the first electric push rod 13 is used to move the U-shaped frame 3 downward, thereby lowering the lifted prefabricated pipe into the groove, so that the lifted prefabricated pipe and the laid prefabricated pipe are on the same plane;

[0050] When the docking position between the suspended prefabricated pipe and the laid prefabricated pipe is not aligned, the first motor 15 is started to drive the adjusting screw 11 to rotate, thereby causing the sliding block 14 to move left and right along the frame 1, thereby causing the first electric push rod 13 to move left and right, thereby causing the U-shaped frame 3 to move left and right, thereby causing the suspended prefabricated pipe to move to a suitable position, thereby aligning the suspended prefabricated pipe with the laid prefabricated pipe, and then performing docking installation operation on the suspended prefabricated pipe and the laid prefabricated pipe. After docking installation, soil is filled between the suspended prefabricated pipe and the bottom end of the groove to stably place the prefabricated pipe;

[0051] Then, the second motor 31 and the bidirectional screw 33 are used to move the first plate 5 and the second plate 8 outward, thereby moving the left clamping plate 4 and the right clamping plate 7 outward, thereby releasing the clamping of the prefabricated pipe, and completing the laying of the prefabricated pipe, realizing mechanical lifting construction of the prefabricated pipe, effectively reducing the probability of defects such as warping of the prefabricated pipe during lifting construction, effectively reducing the probability of leakage at the docking installation position, and effectively ensuring the quality of sewer pipe laying.

[0052] Embodiment 2: The left clamping plate 4 and the right clamping plate 7 are used to mechanically hoist the prefabricated pipe, and the hoisted prefabricated pipe is aligned and positioned with the laid prefabricated pipe, and then the whole equipment is pushed to perform a straight-line docking installation operation between the hoisted prefabricated pipe and the laid prefabricated pipe. However, such docking installation operation makes it easy for the hoisted prefabricated pipe and the laid prefabricated pipe to be unable to complete the docking installation operation at one time, which increases the difficulty of the installation operation, and the docking position is prone to a large impact during the straight-line docking installation operation, resulting in a high probability of damage to the docking position, resulting in a high probability of leakage at the docking installation position.

[0053] In order to solve the above problems, Figure 1 , Figure 2 , Figure 7 and Fig. 9 As shown, the first shaft 41 that penetrates the two left clamping plates 4 and is rotatably connected with the two left clamping plates 4 and penetrates the two second through slots 402 is connected to the rear end of the movable part of the second driver whose fixed part is installed at the front end of the left clamping plate 4 located at the front side, and the first shaft 41 is driven to rotate by the second driver. The second driver can adopt a third motor 43, and the left end surfaces of the lower sides of the two left clamping plates 4 are both recessed to the right to form the second through slots 402 that penetrate the left clamping plates 4, and the second through slots 402 provide installation space for the first roller 42;

[0054] Two first rollers 42 respectively located in the two second through slots 402 and extending to the right side of the second through slots 402 are symmetrically arranged on the outer end of the first shaft 41, and the two first rollers 42 are rotated synchronously through the first shaft 41. The left end surfaces of the upper sides of the two left clamping plates 4 are both recessed to the right to form a first through slot 401 that penetrates the left clamping plate 4 and is located above the second through slot 402. Through the first through slot 401, an installation space is provided for components such as the first rotating shaft 45, and the two first rotating shafts 45 are respectively rotatably connected inside the two first through slots 401, and a mounting carrier is provided for the second roller 46 through the first rotating shaft 45;

[0055] Two second rollers 46 extending out of the right side of the first through slot 401 are respectively arranged on the outer ends of the two first rotating shafts 45, and the second rollers 46 are used to assist in clamping the prefabricated pipe, and the first rod 44 located above the first shaft 41 is rotatably connected between the two left clamping plates 4, and a mounting carrier is provided for the second gear 442 through the first rod 44, and then a second bevel gear 451 arranged in an upper narrow and lower wide manner and located on the upper side of the second rollers 46 is arranged on the outer end of the first rotating shaft 45 located at the rear side, and the first rotating shaft 45 at the rear side is rotated through the second bevel gear 451;

[0056] The first bevel gear 441, which is arranged to be wide at the front and narrow at the rear and is located in the first through slot 401 at the rear side and connected to the rear end of the first rod 44 passing through the rear left clamping plate 4, is meshed with the front upper end of the second bevel gear 451. The second bevel gear 451 is rotated through the first bevel gear 441. The synchronous belt 49 is movably installed between the two left clamping plates 4. The first gear 411 and the second gear 442 are rotated synchronously through the synchronous belt 49.

[0057] The first gear 411 installed at the outer end of the first shaft 41 is meshed with the inner bottom end of the synchronous belt 49, and the synchronous belt 49 is moved through the first gear 411, and the second gear 442 installed at the outer end of the first rod 44 is meshed with the inner top end of the synchronous belt 49, and the first rod 44 is rotated by the second gear 442, and then the second rod 47 located between the first shaft 41 and the first rod 44 is rotatably connected between the two left clamping plates 4, and a mounting carrier is provided for the guide wheel 471 through the second rod 47;

[0058] The guide wheel 471 movably connected to the right end of the synchronous belt 49 is installed on the outer end of the second rod 47. The moving synchronous belt 49 is limited by the guide wheel 471 to effectively avoid contact between the synchronous belt 49 and the clamped prefabricated pipe. The third rod 48 located on the left side of the second rod 47 and passing through the synchronous belt 49 is rotatably connected between the two left clamping plates 4. The third rod 48 is used to provide a mounting carrier for the auxiliary gear 481. The auxiliary gear 481 meshed with the inner left wall of the synchronous belt 49 is then set on the outer end of the third rod 48. The movement of the synchronous belt 49 is assisted by the auxiliary gear 481.

[0059] The second shaft 71 that passes through the two right clamping plates 7 and the two fourth through slots 702 is rotatably connected between the two right clamping plates 7, and a mounting carrier is provided for the third roller 72 through the second shaft 71. The right end surfaces of the lower sides of the two right clamping plates 7 are both recessed to the left to form a fourth through slot 702 that passes through the right clamping plates 7. The fourth through slot 702 provides a mounting space for the third roller 72, and two third rollers 72 that are respectively located in the two fourth through slots 702 and extend out of the left side of the fourth through slot 702 are symmetrically arranged on the outer end of the second shaft 71, and the third roller 72 is used to assist the movement of the clamped prefabricated pipe;

[0060] The right end surfaces on the upper sides of the two right clamping plates 7 are both recessed to the left to form a third through slot 701 that penetrates the right clamping plate 7 and is located above the fourth through slot 702. The third through slot 701 provides installation space for the second rotating shaft and other components, and the two second rotating shafts are rotatably connected to the inside of the two third through slots 701 respectively. The second rotating shaft provides an installation carrier for the fourth roller 73, and the two fourth rollers 73 extending out of the left side of the third through slot 701 are respectively arranged on the outer ends of the two second rotating shafts.

[0061] When in use, the second motor 31 and the bidirectional screw 33 are first used to move the first plate 5 and the second plate 8 inward, and then the left clamping plate 4 and the right clamping plate 7 are moved inward, so that the two first rollers 42, the two second rollers 46, the two third rollers 72 and the two fourth rollers 73 are in contact with the outer ends of the prefabricated pipes, thereby completing the clamping of the prefabricated pipes, and then with the assistance of the moving wheel 25, the clamped prefabricated pipes are transported to the installation position, and the clamped prefabricated pipes are aligned and positioned with the laid prefabricated pipes;

[0062] Then the third motor 43 is started to drive the first shaft 41 to rotate, so that the two first rollers 42 rotate synchronously, and then the clamped prefabricated pipe rotates with the assistance of the two third rollers 72. At the same time, the rotation of the first shaft 41 rotates the first gear 411, and with the assistance of the synchronous belt 49, the second gear 442 rotates, so that the first rod 44 rotates, and then the first bevel gear 441 rotates, and the second bevel gear 451 rotates, so that the corresponding first rotating shaft 45 rotates, so that the corresponding second roller 46 rotates;

[0063] And with the assistance of another second roller 46 and two fourth rollers 73, the clamped prefabricated pipe is moved outward, and then the clamped prefabricated pipe is rotated and moved outward synchronously, realizing a linear mechanical and convenient docking installation operation on the prefabricated pipe, effectively reducing the difficulty of installation operation, effectively reducing the probability of damage caused by docking installation, effectively reducing the probability of leakage at the docking installation position, and effectively ensuring the quality of sewer pipe laying.

[0064] Embodiment three: firstly, the left clamping plate 4 and the right clamping plate 7 are used to mechanically hoist the prefabricated pipe, and the hoisted prefabricated pipe is aligned and positioned with the laid prefabricated pipe, and then the third motor 43, the first shaft 41, the first roller 42, the second roller 46, the third roller 72 and the fourth roller 73 are used to rotate and move the hoisted prefabricated pipe synchronously, and then a linear mechanical convenient docking installation operation is performed. However, during the rotation process, the docking part of the hoisted prefabricated pipe is prone to swinging due to centrifugal force, resulting in a high probability of defects such as expansion of the docking position between the hoisted prefabricated pipe and the laid prefabricated pipe, resulting in a high probability of leakage at the docking installation position.

[0065] In order to solve the above problems, Figure 1 , Figure 2 , Figure 3 and Figure 8 As shown, the upper cylinder 62 located at the lower side of the U-shaped frame 3 and between the left clamping plate 4 and the right clamping plate 7 is connected to the lower rear end of the T-shaped plate 6 located in front of the U-shaped frame 3, and the T-shaped plate 6 is used to provide a mounting carrier for the upper cylinder 62, and the fixing parts of multiple first rolling members are equidistantly arranged on the upper end of the upper cylinder 62. The multiple first rolling members are used in combination to guide the movement of the hoisted prefabricated pipe, and the first rolling member can adopt a third bull's eyeball 621;

[0066] The fixed part of the first elevator is arranged on the middle part of the lower end of the upper cylinder 62, and the upper cylinder 62 is used to provide a mounting carrier for the first elevator and other components, and the lower cylinder 61 located between the left clamping plate 4 and the right clamping plate 7 is installed on the lower end of the movable part of the first elevator, and the lower cylinder 61 is driven to move up and down by the first elevator. The first elevator can use a third electric push rod 623, and then two third telescopic rods 622 located on the front and rear sides of the first elevator are symmetrically installed between the lower cylinder 61 and the upper cylinder 62. The two third telescopic rods 622 are used together to guide the movement of the lower cylinder 61;

[0067] The fixed parts of multiple second rolling members are equidistantly arranged on the lower end of the lower cylinder 61. The multiple second rolling members are used in combination to guide the movement of the hoisted prefabricated pipe. The second rolling member can adopt a second bull's eye 611, and the movable part of the telescopic machine whose fixed part is installed on the upper end of the U-shaped frame 3 and located on the lower side of the frame 1 is connected to the rear end of the T-shaped plate 6. The T-shaped plate 6 is driven to move forward and backward through the telescopic machine. The telescopic machine can adopt a second electric push rod 63, and then the movable part of the second telescopic rod 64 located on the right side of the telescopic machine and on the lower side of the frame 1 and whose fixed part is arranged on the upper end of the U-shaped frame 3 is connected to the rear end of the T-shaped plate 6. The movement of the T-shaped plate 6 is guided by the second telescopic rod 64.

[0068] After the prefabricated pipe is hoisted by using the left clamping plate 4 and the right clamping plate 7, the second electric push rod 63 is started, so that the T-shaped plate 6 moves inward, so that the structure formed by the upper cylinder 62 and the lower cylinder 61 and other components moves inward, and then the structure is inserted into the hoisted prefabricated pipe. At this time, the rolling parts of the plurality of third bull's eyeballs 621 are attached to the top of the inner part of the hoisted prefabricated pipe;

[0069] Then, the third electric push rod 623 is started to drive the lower cylinder 61 to move downward, so that the plurality of second bull's eyeballs 611 move downward, and the rolling parts of the plurality of second bull's eyeballs 611 are attached to the bottom end of the hoisted prefabricated pipe, so as to orient the hoisted prefabricated pipe, and then the third motor 43, the first shaft 41, the first roller 42, the second roller 46, the third roller 72 and the fourth roller 73 are used to make the hoisted prefabricated pipe rotate and move outward synchronously, so as to perform a linear mechanical convenient docking installation operation;

[0070] It can realize linear guidance of prefabricated pipes that are installed by linear mechanical docking, effectively reduce the probability of prefabricated pipes swinging during the docking installation process, effectively reduce the probability of defects such as expansion at the docking position due to shaking, effectively reduce the probability of leakage at the docking installation position, and effectively ensure the quality of sewer pipe laying.

[0071] Embodiment 4: First, the left clamp 4 and the right clamp 7 are used to mechanically lift the prefabricated pipe, and the lifted prefabricated pipe is aligned and positioned with the laid prefabricated pipe, and then the third motor 43, the first shaft 41, the first roller 42, the second roller 46, the third roller 72 and the fourth roller 73 are used to rotate and move the lifted prefabricated pipe synchronously, so as to perform a linear mechanical convenient docking installation operation, and at the same time, the upper cylinder 62, the lower cylinder 61, the second bull's eye 611 and the third bull's eye 621 are used to linearly guide the prefabricated pipe for linear mechanical docking installation. However, during the rotation process, the U-shaped frame 3 is prone to swing left and right around the center line of the lifted prefabricated pipe, resulting in a high probability of defects such as damage at the docking position between the lifted prefabricated pipe and the laid prefabricated pipe due to collision, resulting in a high probability of leakage at the docking installation position.

[0072] In order to solve the above problems, Figure 1 , Figure 2 , Figure 3 and Figure 5 As shown, the four end surfaces of the lifting plate 2 are all recessed inward to form guide grooves 22 extending to the upper and lower ends of the lifting plate 2. The movement of the first bull's eye 26 is guided by the guide grooves 22, and the fixing parts of the two first telescopic rods 21 located on the upper side of the second motor 31 and on the inner side of the lifting plate 2 are respectively installed on the left and right ends of the U-shaped frame 3;

[0073] The two guide frames 23 respectively mounted on the outer sides of the two lifting plates 2 are connected to the movable parts of the two first telescopic rods 21 toward the outer ends respectively, and the guide frame 23 is connected to the U-shaped frame 3 through the first telescopic rods 21, and the fixed parts of the four first bull's eye balls 26 are respectively arranged on the four inner walls of the guide frame 23 in front, back, left and right directions, and the rolling parts of the first bull's eye balls 26 are rollingly connected to the guide grooves 22, and the first bull's eye balls 26 are used to assist the guide frame 23 and the lifting plates 2 to move relative to each other.

[0074] When in use, the second motor 31 and the bidirectional screw 33 are first used to move the first plate 5 and the second plate 8 inward, thereby moving the left clamping plate 4 and the right clamping plate 7 inward, so that the two first rollers 42, the two second rollers 46, the two third rollers 72 and the two fourth rollers 73 are in contact with the outer ends of the prefabricated pipes, thereby completing the clamping of the prefabricated pipes, and then the first electric push rod 13 is used to drive the U-shaped frame 3 and the clamped prefabricated pipes to move upward;

[0075] Then, the second electric push rod 63 is used to move the T-shaped plate 6 inward, and the structure formed by the upper cylinder 62 and the lower cylinder 61 and other components is inserted into the hoisted prefabricated pipe. At this time, the rolling parts of the plurality of third bull's eye balls 621 are attached to the top of the inner part of the hoisted prefabricated pipe. Then, the third electric push rod 623 is used to drive the lower cylinder 61 and the plurality of second bull's eye balls 611 to move downward, so that the rolling parts of the plurality of second bull's eye balls 611 are attached to the bottom of the inner part of the hoisted prefabricated pipe, thereby orienting the hoisted prefabricated pipe. Then, with the assistance of the moving wheel 25, the clamped prefabricated pipe is transported to the installation position.

[0076] Then, the first electric push rod 13 is used to lower the U-shaped frame 3 and the hoisted prefabricated pipe into the groove. During the lowering process, the two first telescopic rods 21 are synchronously moved downward, and the two guide frames 23 are respectively moved downward along the two lifting plates 2, so that the first bull's eye 26 is moved downward along the guide groove 22, thereby guiding the lowering movement of the hoisted prefabricated pipe and making the hoisted prefabricated pipe and the laid prefabricated pipe on the same plane;

[0077] When the docking position between the suspended prefabricated pipe and the laid prefabricated pipe is not aligned, the first motor 15 is started to drive the adjusting screw 11 to rotate, thereby causing the sliding block 14 to move left and right along the frame 1, thereby causing the first electric push rod 13 to move left and right, thereby causing the U-shaped frame 3 to move left and right, and the two first telescopic rods 21 are used to guide the movement of the U-shaped frame 3, thereby causing the suspended prefabricated pipe to move to a suitable position, so that the docking position between the suspended prefabricated pipe and the laid prefabricated pipe is aligned;

[0078] Then, the third motor 43, the first shaft 41, the first roller 42, the second roller 46, the third roller 72 and the fourth roller 73 are used to rotate and move the hoisted prefabricated pipe synchronously, and then a linear mechanical convenient docking installation operation is performed, and the two first telescopic rods 21, the two guide frames 23 and the first bull's eye 26 are used to restrict the U-shaped frame 3, effectively preventing the U-shaped frame 3 from swinging left and right during the rotation of the prefabricated pipe, effectively reducing the probability of defects such as damage caused by docking installation, effectively reducing the probability of leakage at the docking installation position, and effectively ensuring the quality of sewer pipe laying.

[0079] Although this specification is described according to implementation modes, not every implementation mode includes only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

Claims

1. A prefabricated pipe positioning and installation construction equipment, Features: The invention comprises a frame (1), wherein two lifting plates (2) are symmetrically arranged at the lower end of the frame (1), and the lifting plates (2) are arranged vertically; a positioning member is installed in the frame (1); a U-shaped frame (3) is arranged at the lower end of the positioning member, and the U-shaped frame (3) is located between the two lifting plates (2); the U-shaped frame (3) is located at the lower side of the frame (1); a bidirectional screw rod (33) is rotatably connected between the two vertical parts of the U-shaped frame (3); a first driver is arranged at the outer end of the U-shaped frame (3), and the first driver is connected to the bidirectional screw rod (33); The left side of the outer end of the bidirectional screw rod (33) is threadedly connected to the first plate (5), and the first plate (5) extends out of the lower side of the U-shaped frame (3). Two left clamping plates (4) are symmetrically arranged at the lower end of the first plate (5), and the cross section of the left clamping plates (4) is V-shaped with a narrow left side and a wide right side. The right side of the outer end of the bidirectional screw rod (33) is threadedly connected to the second plate (8), and the second plate (8) extends out of the lower side of the U-shaped frame (3). The second plate (8) is located on the right side of the first plate (5). Two right clamping plates (7) are symmetrically installed at the lower end of the second plate (8), and the cross section of the right clamping plates (7) is V-shaped with a wide left side and a narrow right side. A push-fitting member is arranged at the lower side of the first plate (5), and the push-fitting member is connected to the two left clamping plates (4); a guide member is installed at the middle of the front end of the U-shaped frame (3), and the guide member is located between the left clamping plate (4) and the right clamping plate (7); and a moving member is arranged at the lower ends of the two lifting plates (2); The moving part comprises a bottom plate (24), the bottom plate (24) is mounted on the lower end of the lifting plate (2), a plurality of moving components are equidistantly arranged on the lower end of the bottom plate (24), and the moving components are provided with a brake structure; The guide member comprises a T-shaped plate (6), the T-shaped plate (6) is arranged in front of the U-shaped frame (3), an upper cylinder (62) is installed at the lower part of the rear end of the T-shaped plate (6), and the upper cylinder (62) is located at the lower side of the U-shaped frame (3), the upper cylinder (62) is located between the left clamping plate (4) and the right clamping plate (7), and a plurality of first rolling members are equidistantly arranged at the upper end of the upper cylinder (62); A first elevator is arranged at the middle of the lower end of the upper cylinder (62), a lower cylinder (61) is installed at the lower end of the first elevator, a plurality of second rolling members are arranged at equal intervals at the lower end of the lower cylinder (61), a telescopic machine is arranged at the rear end of the T-shaped plate (6), the telescopic machine is installed at the upper end of the U-shaped frame (3), and the telescopic machine is located at the lower side of the frame (1), a second telescopic rod (64) is installed at the rear end of the T-shaped plate (6), and the second telescopic rod (64) is located at the right side of the telescopic rod, and the second telescopic rod (64) is arranged at the upper end of the U-shaped frame (3); The push-fitting member comprises a second driver, the second driver is mounted on the front end of the left clamping plate (4) located at the front side, a first shaft (41) is arranged at the rear end of the second driver, the first shaft (41) passes through the two left clamping plates (4), the left end surfaces of the lower sides of the two left clamping plates (4) are both recessed to the right to form a second through groove (402), and the second through groove (402) passes through the left clamping plate (4), two first rollers (42) are symmetrically arranged at the outer end of the first shaft (41), and the two first rollers (42) are respectively located in the two second through grooves (402); The left end surfaces of the upper sides of the two left clamping plates (4) are both recessed to the right to form a first through groove (401), and the first through groove (401) passes through the left clamping plate (4), the first through groove (401) is located above the second through groove (402), the insides of the two first through grooves (401) are both rotatably connected to the first rotating shaft (45), the outer ends of the two first rotating shafts (45) are both provided with second rollers (46), and a linkage component is provided between the two left clamping plates (4), and the linkage component is connected to the first shaft (41); The linkage assembly comprises a first rod (44), the first rod (44) is rotatably connected between the two left clamping plates (4), and the first rod (44) is located above the first shaft (41), a second bevel gear (451) is arranged at the outer end of the first rotating shaft (45) located at the rear side, the front upper end of the second bevel gear (451) is meshed with the first bevel gear (441), the first bevel gear (441) is located in the first through groove (401) at the rear side, and the rear end of the first rod (44) passes through the left clamping plate (4) at the rear side and is connected to the first bevel gear (441); A synchronous belt (49) is movably installed between the two left clamping plates (4), the bottom end of the interior of the synchronous belt (49) is meshed with a first gear (411), the first gear (411) is installed on the outer end of the first shaft (41), the top end of the interior of the synchronous belt (49) is meshed with a second gear (442), the second gear (442) is arranged on the outer end of the first rod (44), the second rod (47) is rotatably connected between the two left clamping plates (4), a guide wheel (471) is installed on the outer end of the second rod (47), the guide wheel (471) is movably connected to the right end of the synchronous belt (49), the third rod (48) is rotatably connected between the two left clamping plates (4), an auxiliary gear (481) is arranged on the outer end of the third rod (48), and the auxiliary gear (481) is meshed with the left wall inside the synchronous belt (49); The positioning member comprises a sliding block (14), the sliding block (14) is located in the frame (1), a second lift is arranged in the middle of the upper end of the sliding block (14), the second lift passes through the sliding block (14) and is connected to the upper end of the U-shaped frame (3), and the second lift is located between the telescopic machine and the second telescopic rod (64); The frame (1) is internally rotatably connected to an adjusting screw (11), and the adjusting screw (11) is located at the rear side of the second elevator. The adjusting screw (11) passes through a sliding block (14), and the adjusting screw (11) is threadedly connected to the sliding block (14). A third driver is arranged at the right end of the frame (1), and a movable part of the third driver is connected to the adjusting screw (11).

2. The prefabricated pipe positioning and installation construction equipment according to claim 1, Features: The two right clamping plates (7) are rotatably connected to each other by a second shaft (71), and the second shaft (71) passes through the two right clamping plates (7). The right end surfaces of the lower sides of the two right clamping plates (7) are both recessed to the left to form a fourth through groove (702), and the fourth through groove (702) passes through the right clamping plates (7). The second shaft (71) passes through the two fourth through grooves (702). Two third rollers (72) are symmetrically arranged at the outer end of the second shaft (71), and the two third rollers (72) are respectively located in the two fourth through grooves (702), and the third roller (72) extends out of the left side of the fourth through groove (702). The right end surfaces of the upper sides of the two right clamping plates (7) are both recessed to the left to form a third through slot (701), and the third through slot (701) passes through the right clamping plate (7), and the third through slot (701) is located above the fourth through slot (702). The insides of the two third through slots (701) are both rotatably connected to the second rotating shaft, and the outer ends of the two second rotating shafts are both provided with fourth rollers (73), and the fourth rollers (73) extend out of the left side of the third through slot (701).

3. The prefabricated pipe positioning and installation construction equipment according to claim 1, Features: A light rod (16) is arranged inside the frame (1), and the light rod (16) is located at the front side of the second lifter, the light rod (16) passes through the sliding block (14), and the sliding block (14) is slidably connected to the light rod (16), two round rods (12) are symmetrically arranged at the upper end of the U-shaped frame (3), and the two round rods (12) are located on the left and right sides of the T-shaped plate (6), the two round rods (12) both pass through the sliding block (14), and the sliding block (14) is slidably connected to the round rod (12), and the two round rods (12) are located between the two light rods (16); A plurality of guide rods (32) are equidistantly arranged between the two vertical parts of the U-shaped frame (3), and the guide rods (32) are located above the bidirectional screw rods (33); the plurality of guide rods (32) all penetrate the first plate (5), and the plurality of guide rods (32) are slidably connected to the first plate (5); the plurality of guide rods (32) all penetrate the second plate (8), and the plurality of guide rods (32) are slidably connected to the second plate (8).

Citation Information

Patent Citations

  • Device for fixing the hydraulic piping of construction equipment

    CN103890278A

  • Steel beam hoisting and leveling device for building steel structure assembly

    CN113636459A